Construction Activities for Zone B
Slide Show 1 of 3
Mark Atencio
March 17, 2010
Zone B Facilities
2009-2010 Activities
•Treatment Plant
•By -product Pipeline
•Great Salt Lake Selenium Standard
•UPDES Permit Application
Zone B Facilities
Southwest Groundwater
Treatment Plant
•Design
•Bidding
•Construction
Treatment Plant Design
•Process Design
•Civil Site Plan
•Landscaping Plan
•Architectural Plan
Landscaping
Plan
Architectural Sections
Treatment Plant Specifications
Beginning of Construction
Treatment Plant Construction
•Treatment Plant Site
•Utility Corridor
Removal of Russian Olives
Excavation of Native Soils
Pumping of Shallow
Groundwater During Excavation
Utility Corridor
Removal of Topsoil
Stockpiling Topsoil
Electric Power
Conduit Installation
24” Steel Treated Water Line (white)
16” HDPE By-product Pipeline (black)
Fuse Welding 30” HDPE
Shallow Groundwater Pipeline
Placement of Pipe Bedding
Utility Corridor
(End of slides 1 of 3)