KENNECOTT UTAH COPPER CORPORATION
JORDAN VALLEY WATER CONSERVANCY DISTRICT
Proposal to the Utah State NRD Trustee and
USEPA CERCLA Remedial Project Manager
for a
Groundwater Extraction and Treatment Remedial Project
In the Southwestern Jordan Valley
June 11, 2004
June 11, 2004 i
Table of Contents
1.0 INTRODUCTION ................................................................................................................1
1.1 Executive Summary .............................................................................................2
1.2 Adjustments to the Project ..................................................................................2
2.0 BACKGROUND ..................................................................................................................4
2.1 Natural Resource Damage Claim and Consent Decree (UDEQ).................4
2.2 Federal CERCLA Requirements Design (USEPA).........................................7
2.3 KUCC/JVWCD Study and Conceptual Design ................................................9
2.4 JVWCD System and Service Area ....................................................................9
3.0 PURPOSES OF PROPOSED PROJECT ........................................................................10
3.1 Meet the Requirements and Intent of the NRD Consent Decree ...............10
3.2 Meet the Intent and Remedial Requirements of CERCLA ..........................11
3.3 KUCC/JVWCD Purposes ..................................................................................11
4.0 AFFECTED AREA AND PUBLIC IN THE AFFECTED AREAS ......................................12
4.1 Affected Area ......................................................................................................12
5.0 PROPOSED PROJECT ....................................................................................................12
5.1 General ................................................................................................................12
5.2 Groundwater Extraction ....................................................................................12
5.3 Collection Pipelines............................................................................................14
5.4 Water Treatment Plants ....................................................................................14
5.5 Treated Water Deliveries ..................................................................................16
5.6 Concentrate Disposal ........................................................................................16
6.0 GROUNDWATER IMPACTS AND REMEDIATION ........................................................19
6.1 Groundwater Modeling ......................................................................................19
6.2 Hydrogeology ......................................................................................................20
6.3 Plume Contraction and Containment ..............................................................21
7.0 WATER RIGHTS AND MANAGEMENT WITHIN AFFECTED AREA .............................21
7.1 Consent Decree Requirements........................................................................21
7.2 Water Rights in the Affected Area ...................................................................21
7.3 Proposal to the State Engineer Concerning Water Rights ..........................23
8.0 COST ESTIMATES...........................................................................................................24
June 11, 2004 ii
8.1 Capital Costs for Water Treatment ..................................................................24
8.2 Concentrate Disposal Costs .............................................................................25
8.3 Operation, Maintenance and Replacement Costs ........................................25
8.4 Avoided Capital Costs .......................................................................................25
8.5 Avoided Operating Costs ..................................................................................30
8.6 Total Cost Estimate............................................................................................30
9.0 PROJECT FUNDING ........................................................................................................30
10.0 OPERATION, MAINTENANCE, REPLACEMENT RESPONSIBILITIES ........................35
10.1 Zone A Plant .......................................................................................................35
10.2 Zone B/Lost Use Integrated Facilities (for Deep Groundwater Extraction)35
10.3 Lost Use Facilities (for Shallow Groundwater Extraction)...........................35
11.0 ALLOCATION OF PROJECT BENEFITS ........................................................................36
12.0 SCHEDULE, DESIGN & CONSTRUCTION, FACILITIES OWNERSHIP .......................40
12.1 Proposed Project Schedule ..............................................................................40
12.2 Design ...................................................................................................................41
12.3 Construction ..........................................................................................................42
12.4 Facilities Ownership ...........................................................................................42
13.0 LIABILITY AND AGREEMENTS ......................................................................................43
13.1 Liability .................................................................................................................43
13.2 Contract Mileposts ................................................................................................43
13.3 KUCC/JVWCD Agreement (“The Project Agreement”)..............................43
13.4 KUCC/JVWCD Agreement with the State of Utah ........................................44
14.0 ZONES A AND B RATIONALE ........................................................................................45
14.1 Zone A ..................................................................................................................45
14.2 Zone B ..................................................................................................................46
15.0 MEETING INTENT OF NRD CONSENT DECREE ..................................................47
June 11, 2004 iii
Figures
Figure 2.4A Jordan Valley Water Conservancy District Customers and Boundaries
Figure 2.4B Jordan Valley Water Conservancy District Water System
Figure 4.1A S.W. Jordan Valley Highest Sulfate Concentration Data
Figure 5.2A Proposed Groundwater Extraction and Treatment System
Figure 5.4A Zone A Plume-Treatment Flow Chart
Figure 5.4B Zone B/Lost Use Integrated Design -Treatment Flow Chart
Figure 5.4C Zone B/Lost Use Minimum Integrated Design Treatment Flow Chart
Figure 5.4D Zone B and Lost Use Separate Design Treatment Flow Chart
Figure 5.4C Zone B/Lost Use Integrated Design
Figure 6.3A Sulfate contours Layer 4 at 2025
Figure 6.3B Sulfate contours Layer 4 at 2050
Figure 8.5A JVWTP Groundwater Development Project in Southwest Salt Lake
Valley, Absent Mining Contamination
Tables
Table 2.1 State NRD Trust Fund
Table 5.2A Annual Groundwater Remediation Extraction Volumes
Table 5.4A Treatment Plant Flows
Table 5.6A Effect of Zone A Reverse Osmosis Concentrate on Tailings Line Chemistry
Table 5.6B Project Concentrate Flows
Table 7.2A Approved Municipal Water Rights in December 1999
Table 7.2B Approved JVWCD Shallow Groundwater Rights
Table 7.3A Approved Water Right Change Applications
Table 8.5A Estimate for Avoided JVWCD Capital Cost of Groundwater Development, Absent
Mining Contamination
Table 9.0A Distribution and funding of Project Costs
Table 11.0A Allocation of Zone A Treated Water Among Affected Municipalities
Table 11.0B Illustration of Discounted Wholesale Water Rate Methodology for Zone A Treated
Water
Table 12.1A Proposed Project Schedule
Table 12.2A Design Responsibility
Table 12.4A Ownership of Facilities for Proposed Project
Table 14.1A JVWCD Water Purchase contacts with Affected Municipalities
Table 15.0A Intent of NRD Consent Decree
June 11, 2004 iv
Appendices
A KUCC Groundwater Model
B. Draft Explanation of Significant Differences
Record of Decision (USEPA)
C. Reserved
D. Revised Flow and Transport Model for Southwestern Jordan Valley
E. Letter to State Engineer & Groundwater Management Plan
F. Allocation of Zone A water to the Affected Municipalities
G. Letters of Support from Affected Municipalities
H. Pilot Study Final Report – Carollo Engineers
Attachment
CDM Report
June 11, 2004 1
KENNECOTT UTAH COPPER CORPORATION
JORDAN VALLEY WATER CONSERVANCY DISTRICT
Proposal to the Utah State NRD Trustee and
USEPA CERCLA Remedial Project Manager
for a
Groundwater Extraction and Treatment Remedial Project
In the Southwestern Jordan Valley
June 11, 2004
1.0 INTRODUCTION
Kennecott Utah Copper Corporation (KUCC) and the Jordan Valley Water
Conservancy District (JVWCD) make this joint proposal (Proposal) to Dr. Dianne R.
Nielson, the Utah Trustee for natural resource damages (NRD), who also acts as
Director of the Utah Department of Environmental Quality (UDEQ). In addition, the
Proposal has been made to Dr. Eva J. Hoffman, the United States Environmental
Protection Agency (USEPA) Remedial Project Manager for the KUCC
Comprehensive Environmental Response, Compensation, and Liability Act
(CERCLA) site remediation and Mr. Jerry Olds, P.E., State Engineer for the State of
Utah.
KUCC and JVWCD propose to develop and construct a groundwater extraction and
treatment project with groundwater remedial functions that will provide treated,
municipal quality water to the public in the Affected Area of the southwestern Jordan
Valley (Project) as defined in the Consent Decree dated August 21, 1995, entered in
Civil Action No. 86-C-0902G in the United States District Court for the District of
Utah (“the Consent Decree”). KUCC and JVWCD seek to utilize for the Project the
trust fund set up under the Consent Decree in a manner consistent with the terms of
the Consent Decree to restore the injured ground water resource.
The concepts of this Proposal have been presented to the governing organizations
of Herriman City, Riverton City, South Jordan City and West Jordan City and a
technical review committee comprised of representatives from various federal, state
and local governmental agencies, as well as representatives from local
municipalities and local residents.
June 11, 2004 2
1.1 Executive Summary
In summary, the Project outlined in this Proposal:
· Is designed to provide 8235 acre-feet/year (afy) of municipal quality water to the
public in the Affected Area.
· Includes the construction and operation of two reverse-osmosis water treatment
plants. One plant, the Zone A Plant, is to be built, owned and operated by
KUCC. The other, consisting of the Zone B Facilities and the Lost Use
Facilities, is to be built, owned, and operated by JVWCD.
· Includes construction and operation of pipelines and extraction wells.
· Seeks to utilize all portions of the Trust Fund, except that relating to
administration costs. The Trust Fund consists of the existing Irrevocable Letter
of Credit (ILC) and the cash portion of the Trust Fund. KUCC and JVWCD seek
full credit against the ILC in exchange for 7000 afy of municipal quality water.
JVWCD seeks the cash portion for an additional 1235 afy of municipal quality
water.
· Provides additional costs and in-kind contributions to the Project of more than
$184 million by KUCC and approximately $16 million by JVWCD.
· Anticipates providing some of the municipal quality water to the public in the
Affected Area by approximately two years following approval of the Proposal.
· Presents an allocation of water rights to the Utah State Engineer. The allocation
of water rights is necessary to meet the intent of the NRD Consent Decree.
· Integrates the CERCLA remedial response for the Bingham Creek acid and
elevated sulfate plume with the actions required to satisfy the NRD Consent
Decree.
This Proposal provides an overview of the expected development of the Project.
Because the Project is intended to be ongoing for more than forty years, not all
circumstances can be anticipated, much less addressed. Many of the
circumstances, as well as the definitive rights and obligations of KUCC, JVWCD and
the State under the Project and implementing agreements, are referred to
throughout this Proposal and summarized in Section 5.6 (Concentrate Disposal),
Section 9 (Project Funding) and in Section 13 (Liability and Agreements).
1.2 Adjustments to the Project
This Joint NRD Proposal was previously submitted to the Trustee and the USEPA
on August 7, 2003. Public hearings and a public comment period on the August 7,
June 11, 2004 3
2003 Proposal were held between August and November of 2003. Some members
of the public expressed opposition to the portion of the Proposal providing for
discharge of concentrates from the Zone B Facilities and Lost Use Facilities to the
Jordan River. The principal objections related to the presence of selenium in the
concentrates from the shallow groundwater to be treated by the Lost Use Facilities.
Due to that opposition, JVWCD withdrew its discharge permit and adjusted its plans
for the Lost Use Facilities.
The August 7, 2003 Proposal and the corresponding Project Agreement and State
Agreement have now been updated to reflect these adjustments to the proposed
Project as described in this May 25, 2004 Proposal. The adjustments include
options for providing water for the Lost Use Facilities from the Zone B deep
groundwater and the shallow aquifer, options for concentrate disposal and
corresponding easements, as follows:
OPTIONS FOR LOST USE FACILITIES
JVWCD will investigate and select one of three options for the Lost Use Facilities.
These options are briefly described below and in Section 5.4 of this Proposal.
· Integrated Design
o JVWCD may integrate the Lost Use Facilities with the Zone B Facilities,
using feed water from the Zone B Deep Wells, for a combined production
of 4195 afy of treated water, 3500 afy of which is attributable to the Zone B
Facilities and 695 afy of which is attributable to the Lost Use Facilities.
JVWCD will provide the r emainder of 540 afy f rom other sources available
to it in order to satisfy its obligation to provide 4735 afy of treated water.
o JVWCD may proceed as described above, but treat additional feed water
from the Zone B Deep Wells, for a combined production of 4735 afy of
treated water, 3500 afy of which is attributable to the Zone B Facilities and
1235 afy of which is attributable to the Lost Use Facilities. This will require
approval from the Utah State Engineer to change water rights currently
approved for other points of diversion into the Zone B Deep Wells.
· Separate Design
o JVWCD may proceed as outlined in the August 7, 2003 Proposal with a
separate design for the Lost Use Facilities, in which case the Zone B
Facilities will produce 3500 afy of treated water from the Zone B Deep
Wells and the Lost Use Facilities will produce at least 1235 afy of treated
water from the shallow aquifer. This option differs from the August 7, 2003
Proposal in that, instead of discharging concentrates to the Jordan River,
concentrates will be conveyed to the Great Salt Lake, bypassing the
June 11, 2004 4
Jordan River and its associated wetlands. Such future discharge is
subject to further studies by JVWCD concerning selenium to determine
impacts to the Great Salt Lake from JVWCD’s concentrate discharge and
permitting and regulatory approval.
· Decision Process
o In cooperation with DEQ, EPA, USFWS, USGS, KUCC, and
environmental organizations, JVWCD will initiate and commission
additional studies on the impacts of selenium in Great Salt Lake. JVWCD
will need to make a decision on which Lost Use facility option to proceed
with. The outcome of these studies will help guide JVWCD's decision.
JVWCD will make a decision on which Lost Use Facility alternative to
pursue in the summer of 2006. A decision to proceed with the Separate
Design and implement a discharge of reverse osmosis concentrate to
Great Salt Lake is dependent on the studies concluding that this is an
option that will not cause environmental degradation to Great Salt Lake
and its surrounding environment. While completing these studies JVWCD
will complete other activities related to the project such as engineering
designs and construction of wells and pipelines.
CONCENTRATE DISPOSAL
· The concentrate disposal provisions of the August 7, 2003 Proposal and Project
Agreement have been modified to clarify the circumstances under which
JVWCD is able to deliver Zone B Deep Well concentrates to Kennecott’s
Tailings Impoundment. These circumstances are described in Section 5.6 of
this Proposal.
PIPELINE EASEMENTS
· Kennecott will provide easements to JVWCD for delivery of:
o Deep Well concentrates to the Tailings Impoundment, and
o Deep Well and shallow aquifer concentrates in the event concentrate
discharges to the Great Salt Lake are eventually approved.
2.0 BACKGROUND
2.1 Natural Resource Damage Claim and Consent Decree (UDEQ)
The Utah Department of Health filed a complaint in 1986 under the provisions of
CERCLA seeking damages from KUCC “for injury to, destruction of, and loss of
natural resources.” The Utah Department of Health was acting as the CERCLA
June 11, 2004 5
Trustee in making this claim. The claim pertained to injury to surface and
groundwater resulting from the release of pollutants and hazardous substances from
milling and mining activities by KUCC and its predecessors in the southwestern part
of the Salt Lake Valley.
In 1990, UDEQ, the successor Trustee, arrived at an NRD settlement with KUCC.
An NRD Consent Decree was proposed to the United States District Court for the
District of Utah.
JVWCD (then the Salt Lake County Water Conservancy District) petitioned the court
to allow JVWCD to intervene, claiming that the proposed Consent Decree was
insufficient to address damages to the groundwater aquifer. Following a hearing in
1991, the District Court allowed JVWCD to intervene, finding JVWCD uniquely
situated to contribute to resolving the underlying factual and legal issues associated
with the UDEQ claim. The court did not approve the Consent Decree proposed in
1991.
An appeal to the 10th Circuit Court of Appeals followed, which was dismissed for
lack of jurisdiction. The subsequent petition for a writ of certiorari to the United
States Supreme Court also was denied.
The three parties (KUCC, UDEQ and JVWCD) then entered into negotiations for a
revised settlement. Numerous technical discussions were held regarding potential
remedial responses. These discussions resulted in a proposed Consent Decree
dated May 30, 1995. In August 1995, the District Court approved and entered the
final NRD Consent Decree.
The 1995 Consent Decree required KUCC to complete all source control efforts it
had been pursuing since 1990. It also created a trust fund for administration by the
State CERCLA Trustee for natural resource damage. KUCC has now completed all
source control work.
The Trustee utilized the cost of restoration methodology in computing the amount of
damage. The value of the settlement was based on the cost of a possible alternative
for returning the volume of contaminated water (8,235 afy) to beneficial use. This
method is to extract water through wells, and build and operate a treatment plant to
produce municipal quality water. It was calculated that a treatment plant using
nanofiltration or reverse osmosis technology would have an 85 percent net output of
municipal quality water. This equates to 7,000 acre-feet of water as provided for in
the Consent Decree, with a loss of 1,235 acre-feet of water in the treatment process.
The treatment system concept used for damage calculation requires extraction wells
and related facilities, collection pipelines, a treatment plant, a brine discharge
pipeline and a distribution pipeline. The costs of producing 7,000 acre-feet of water
June 11, 2004 6
annually for 50 years in 1995 dollars, was calculated to be $4,000 per acre-foot. The
$4,000 per acre-foot cost of treatment includes the capital costs of construction of a
treatment plant (40%) and the cost to operate, maintain and replace facilities over
an estimated life of 50 years (60%). The present value of funding for such a project
was estimated at $28 million in 1995 dollars.
The Consent Decree required that KUCC provide funding for a Natural Resource
Damages Trust Fund with two components. First, KUCC provided the ILC in the
amount of $28 million, escalating annually at seven percent. The $28 million was
equivalent to the present value of the cost of restoring the ground water through the
restoration methodology described above. Second, the Trust Fund included a cash
payment of $9 million that was provided to the State Trustee. The $9 million was
estimated as the cost of replacing that amount of ground water that would be lost in
the concentrate from the treatment process and is sometimes referred to as the “lost
use” component of the NRD Trust Fund. The Consent Decree provides that the $9
million “shall be expended only to restore, replace or acquire the equivalent of the
surface or groundwater resources for the benefit of the public in the affected area…”
The $9 million has been invested by the State of Utah and has increased in value.
This portion of the Trust Fund, also sometimes referred to as the cash portion, is to
be used for the Lost Use component of the Project or Lost Use Facilities as more
fully described in Sections 5 and 10 below.
The following table shows the increasing value of the $28 million ILC and the $9
million cash payment from January 1995 through January 2004:
Table 2.1
State NRD Trust Fund
Date KUCC Irrevocable
Letter of Credit Value (a)
(Millions)
$9 Million Cash
Payment Value (b)
(Millions)
Total Value
(Millions)
September 1995 $28.0 $9.0 $37.0
January 2004 $49.382 $13.227 $62.609 (a) Increases at seven percent annually
(b) Increase at PTIF rate as invested by UDEQ.
The NRD Consent Decree acknowledges the separate CERCLA remedial action
process by the USEPA. The Consent Decree contemplates the likelihood of
formulating a remedial response for the NRD that would correlate with the remedial
response required by USEPA under federal CERCLA requirements. Because of this,
the Consent Decree requires that “the Trustee shall not expend funds secured by
the letter of credit until the earlier of two years after the issuance of the Record of
Decision (ROD) or July 1, 2000, unless the Trustee determines that there exists a
June 11, 2004 7
direct and immediate threat to the public health or the environment that necessitates
expenditures to restore, replace or acquire the equivalent of the resource.”
Prior to the expenditure of such funds, KUCC can obtain a reduction in the amount
of the ILC if KUCC provides and delivers municipal quality water through treatment
of contaminated water to a system of a purveyor of municipal and industrial (M&I)
water in a manner that is acceptable to the Trustee, and in a manner that meets the
specific requirements of the credit provisions. “Municipal Quality Water” is defined
in the Consent Decree as water originating west of the Welby Canal with total
dissolved solids (TDS) concentration of 500 mg/L (and 250 mg/L sulfate), and water
originating east of the Welby Canal to 800 mg/L TDS (and 250 mg/L sulfate).
Allocation of the right to use surface or groundwater resources “shall be by the Utah
State Engineer pursuant to Utah water law.”
The other requirements that KUCC must satisfy to receive the reduction described
above include the following:
a. The water must be accepted by the M&I purveyor with the water right to put the
water to beneficial use, in exchange for which the purveyor is to pay KUCC no
more than the operation and maintenance costs absent the contamination up
to $49 per acre-foot in 1995 dollars;
b. The extraction of the contaminated water must proportionately prevent or
reduce the spread of aquifer contamination;
c. The municipal quality water must be a sustainable water supply of 40 years or
more; and
d. KUCC’s project cannot increase materially the Trustee’s unit cost to produce
the remainder of the 7000 afy of municipal quality water.
As indicated above, two years after the issuance of the ROD or July 1, 2000,
whichever is later, the ILC portion of the Trust Fund not allocated for a KUCC project
may, at the Trustee’s option, be converted to cash which shall be used by the
Trustee to restore, replace or acquire the equivalent of the natural resource for the
benefit of the public in the Affected Area.
The Project outlined in this Proposal seeks to utilize one half of the ILC for a KUCC
project and one half of the ILC for a JVWCD project. The KUCC project is generally
referred to as the Zone A Plant and the JVWCD project is generally referred to as
the Zone B Facilities, which are more fully discussed in Sections 5 and 10 below.
2.2 Federal CERCLA Requirements Design (USEPA)
Substantial commencement of remedial studies under the federal requirements of
CERCLA (also known as Superfund) followed the approval of the NRD Consent
Decree. The main concern of the CERCLA process is the protection of human
health and the environment.
June 11, 2004 8
In 1995, the USEPA Remedial Project Manager (of Region VIII) formed a Technical
Review Committee (TRC) to oversee the remedial studies. Represented on the
TRC are UDEQ, USEPA, Utah Department of Natural Resources, Utah State
Engineer, Salt Lake City-County Health Department, JVWCD, US Geological Survey
(USGS), University of Utah, local municipalities, a local chapter of the Sierra Club
and other community stakeholders.
During 1995-1998, KUCC conducted many studies as part of a remedial
investigation/feasibility study (RI/FS). The TRC provided oversight during this
process. Much information and data were produced and provided by KUCC
regarding the characteristics of the Affected Area, including hydrogeology,
groundwater quality, groundwater recharge sources, a well inventory and future
groundwater and contaminant movement in the Affected Area.
The feasibility study portion of the RI/FS included groundwater modeling by KUCC
to project various scenarios of future groundwater and contaminant movement. This
modeling involved groundwater flow modeling, particle tracking and solute transport
modeling. Various scenarios of remedial action were modeled, addressing future
time periods of 25, 50 and 150 years. A groundwater model provided by the USGS
served as the basis of this modeling, and the final results were reviewed and
approved by the USGS. A summary of this modeling is attached (Appendix A).
The final draft RI/FS reports were issued by KUCC in March 1998. In March 2000,
KUCC formulated a remedial response that correlates with the NRD Consent
Decree requirements and presented this response to the USEPA, UDEQ and TRC.
The USEPA Remedial Project Manager accepted this proposed remedial action plan
and submitted the integrated remedial response program to the federal Remedy
Review Board for their consideration and approval in May 2000. The next steps in
the federal CERCLA process involved public hearings and ultimately issuance of a
ROD by USEPA, which occurred on December 13, 2000 (Appendix B).
Following the issuance of the ROD, KUCC prepared a Remedial Design Work Plan,
Preliminary Design and Final Remedial Design and submitted these to USEPA and
the State of Utah. The Final Remedial Design (December 2002) details the
technical and operating design of the ground water remediation program, including
the Zone A Plant discussed in Section 5 below. The Final Remedial Design also
includes a groundwater monitoring plan and third party mitigation plan in the event
of quantity or quality related issues at third party sites. This document is available at
the West Jordan library or at UDEQ offices.
As a result of details presented in the Final Remedial Design, USEPA issued a draft
“Explanation of Significant Differences” dated June 23, 2003 (Appendix B), for the
selected remedy in the ROD. Generally, the differences do not change the overall
June 11, 2004 9
approach, which uses barrier wells to prevent the spread of contamination;
treatment and beneficial u se of the sulfate contaminated water; and extraction of the
low pH plume.
2.3 KUCC/JVWCD Study and Conceptual Design
KUCC and JVWCD jointly commissioned a study to determine the best method of
accomplishing the goals of the NRD Consent Decree and federal CERCLA remedial
requirements for contaminated groundwater in the southwestern Salt Lake Valley.
KUCC and JVWCD retained the firm of Camp Dresser and McKee (CDM) to perform
this study, which resulted in a conceptual design for an extraction well and treatment
project that meets State and Federal expectations (see Attachment). The conceptual
design will produce 7,000 afy1 of municipal quality water, as was contemplated for
the treatment component of the State NRD Consent Decree. It also provides for
additional replacement of water beyond that contemplated by the Consent Decree,
including the 1,235 afy of water otherwise lost in the treatment process. This “Lost
Use” water will result from treatment of shallow groundwater or of water from the
Zone B Deep Wells under JVWCD water rights, depending on the option regarding
the Lost Use Facilities selected by JVWCD as described in Section 1.2.
KUCC and JVWCD requested that CDM consider a 50-year operating period for the
Project. CDM has shown net present value of costs for construction and 50 years of
operation, maintenance and replacement for the Project. This exceeds the 40-year
operation period specifically required in the Consent Decree. Later sections in this
Proposal will show that some of these costs based on the 40-year period will exceed
the Trust Fund amounts. KUCC and JVWCD will provide additional funds to make
up this difference.
Since the completion of the CDM report, pilot studies, additional preliminary design
and cost estimates have been completed by Carollo Engineering (Zone B and Lost
Use) and KUCC Engineering Services (Zone A). The CDM, Carollo and KUCC
estimates have been further updated as indicated in Section 8.0.
2.4 JVWCD System and Service Area
JVWCD is a political subdivision of the State of Utah. It was created in 1951 by the
State Legislature under the Water Conservancy Act. The District remains under the
jurisdiction of the Third District Court of the State of Utah. A board of eight trustees,
who represent seven geographical divisions, governs JVWCD. Board members are
1CDM noted that the recovery rate (85%) assumed in the supporting document for the Consent Decree
would likely not be achieved for a portion of the project. Thus additional groundwater extraction may be
required to produce the 7,000 AF of treated water as required under the Consent Decree.
June 11, 2004 10
nominated by either the county commission or city council, depending upon the
division they represent. The Governor appoints each trustee for a four-year term.
JVW CD provides M&I water to most areas of Salt Lake County that lie outside of the
Salt Lake City service area. Parts of northern Utah County are also served by
JVWCD. Figure 2.4A shows this service area.
JVWCD provides water under wholesale water purchase contracts to nineteen
member agencies, including cities, improvement districts, state agencies and private
companies. JVWCD also provides and distributes water to individual homes and
businesses on a retail basis in areas where no viable retail agency exists. JVWCD
also provides wholesale service indirectly to High Country Estates Phase II
Homeowners Associates. JVWCD treats and transports water to the Metropolitan
Water District of Salt Lake & Sandy.
JVWCD operates a raw water collection system that collects water not only from
local mountain streams in Salt Lake Valley, but also imports water from the Weber,
Provo and Duschesne Rivers. JVWCD operates two water-treatment plants and a
treated-water transmission system within Salt Lake Valley. This system is shown in
Figure 2.4B. The system contains hundreds of miles of aqueduct, transmission and
distribution pipelines, and can convey water from any source to virtually any point
within Salt Lake Valley. The system also involves wells, booster pump stations and
treated water storage reservoirs.
3.0 PURPOSES OF PROPOSED PROJECT
KUCC and JVWCD have formulated the Project to meet the intent of the NRD
Consent Decree, as well as the requirements and intent of the federal CERCLA
process. These purposes are described in the following paragraphs.
3.1 Meet the Requirements and Intent of the NRD Consent Decree
The purposes of this Project include the following:
· Reduce the spread of aquifer contamination through e xtraction of contaminated
water that will proportionately prevent or reduce the spread of contamination.
· Restore the ground water resource by treating contaminated water and providing
drinking quality water for the public in the Affected Area, and
· Remediate the aquifer over the long term.
June 11, 2004 11
3.2 Meet the Intent and Remedial Requirements of CERCLA
The ROD detailed the preferred remedy addressing groundwater contamination in
the southwestern Jordan Valley. The preferred remedy includes groundwater
treatment and is intended to work in conjunction with this Proposal. The Project
includes the following elements outlined in the ROD and reconfirmed in the draft
“Explanation of Significant Differences” dated June 23, 2003 (Appendix B).
· Protect human health and the environment,
· Withdraw and treat the heavily contaminated waters from the core of the acid
plume in Zone A (discussed in Section 4 below),
· Install barrier wells at the leading edge of the contamination (1500 ppm sulfate or
less) and pump and treat the waters to prevent further plume movement,
· Provide reverse osmosis treated water for municipal use,
· Monitor the plume,
· Dispose of treatment concentrates in pipeline used to slurry tailings to the
tailings impoundment prior to mine closure, and
· Develop a post-mine closure plan to handle treatment residues.
3.3 KUCC/JVWCD Purposes
KUCC and JVWCD have additional purposes that will benefit the public beyond the
requirements of the State NRD Consent Decree or federal CERCLA requirements,
which are included in the Proposal. These purposes are to:
· Implement a project that is comprehensive and efficient in groundwater
development, water delivery, operational and political issues,
· Improve the treated water quality delivered to JVWCD beyond the 500-800 mg/L
total dissolved solids (TDS) level contemplated in Section I.D. of the Consent
Decree, to 250 mg/L TDS,
· Restore and replace groundwater from the Affected Area (see Consent Decree
for definition of Affected Area) that is lost as a concentrate stream resulting from
membrane treatment processes. JVWCD proposes a shallow groundwater
membrane treatment project under its own water rights to accomplish this
purpose, which is contemplated in the Consent Decree,
· Initially utilize existing facilities for concentrate disposal, in order to create
additional cost savings and permitting efficiency.
June 11, 2004 12
4.0 AFFECTED AREA AND PUBLIC IN THE AFFECTED AREAS
4.1 Affected Area
The NRD Consent Decree requires that the Trustee use the benefits of the Trust
Fund to “restore, replace or acquire the equivalent of the natural resource for the
benefit of the public in the Affected Area...” (V.D.4). The Consent Decree further
defines “injury to...groundwater” as contamination caused by KUCC’s mining and
leaching operations resulting in: 1) increased levels over baseline of total dissolved
solids, including sulfates, 2) pH levels lower than baseline, 3) metals concentrations
exceeding baseline, or 4) solid phase contamination in the aquifer that can be re-
dissolved in the future.” (Section I(c))
For purposes of the Proposal, the total affected area is divided into two zones, Zone
A and Zone B as shown on Figure 4.1A. Zone A encompasses approximately the
western half of the Affected Area, and includes a sulfate plume with a low pH core
emanating from the Bingham Canyon area. Zone A includes the area commonly
referred to as the “acid plume.”
Zone B encompasses approximately the eastern half of the Affected Area, and
includes areas affected by the former evaporation ponds in South Jordan. It
includes the majority of the area referred to by the TRC as the “sulfate plume.”
5.0 PROPOSED PROJECT
5.1 General
The physical facilities of the proposed Project are described in the conceptual
design report by CDM (See Attachment). That report provides substantial detail
regarding extraction, treatment process, pipelines, water treatment plants, treated
water delivery locations and concentrate disposal provisions.
The proposed Project facilities are divided into Zone A Plant, Zone B Facilities and
Lost Use Facilities. The CDM conceptual design report explains the cost-effective
reasons for this segregation. Since the completion of the CDM report, additional
preliminary designs and cost estimates have been completed by Carollo Engineers
(Zone B and Lost Use) and KUCC Engineering Services (Zone A).
5.2 Groundwater Extraction
Estimated annual volumes of groundwater extraction to support the project are
tabulated in Tables 5.2a and 5.2b.
June 11, 2004 13
KUCC plans to utilize existing extraction wells 1193 and 12002 in Zone A.
Additionally, KUCC will operate well 1147, its “sulfate extraction well”, north of
Herriman, which will contain and contract the plume in the Lark area. Extraction of
up to 4670 afy from these wells will provide sufficient feed water to the Zone A Plant
to provide 3,500 afy of treated water from the deep, principal aquifer.
KUCC plans to operate its acid plume extraction wells 1146 and 1201 and possibly
other acid extraction wells . KUCC is required as part of the Consent Decree to
extract 400 afy annually from the acid plume. KUCC intends to exceed this
requirement in order to remove the majority mass of the acid plume as quickly as
possible (see Appendix D). However, the extraction rate from these wells will be
constrained by the capacity of KUCC’s water rights and the safe yield of the aquifer.
KUCC’s existing water rights (Section 7.2) will allow for extraction of 2020 afy per
year from the acid wells.
If necessary, additional extractions may be made by KUCC to contain and contract
critical portions of the acid and highly elevated sulfate plume to protect human
health and the environment. These extractions would require transfer of additional
water rights to the remedial area.
JVWCD will utilize new extraction wells B1 through B7 in Zone B (collectively
designated the Zone B Deep Wells) for groundwater extraction from the principal
aquifer for treatment at the Zone B Facilities and the Lost Use Facilities, if
constructed on an Integrated Design basis, as shown in Figure 5.2A. Table 2-1 in
the CDM report gives more information on each well. (Note that wells B6 and B7
from the CDM report have been combined to a single, higher production well shown
as B6 in Figure 5.2A. Well B8 from the CDM report is shown as B7 in Figure 5.2A.)
Whether JVWCD proceeds with the Lost Use Facilities on an Integrated Design
basis or a Separate Design basis, JVWCD will use some water from the shallow
aquifer (which lies above the deeper principal aquifer in areas just west of the
Jordan River) to remineralize the permeate produced from the reverse osmosis
process. New wells SW1 through SW4 are additional shallow wells that will be
used for that purpose. Additional shallow wells may be used if JVWCD proceeds
with the Lost Use Facilities on a Separate Design basis. Table 5.2A tabulates the
average annual extractions from these wells. The annual extraction volumes from
individual shallow wells and Deep Wells may vary, based upon operating experience
that will be gained by KUCC and JVWCD over the forty year life of the Project.
2 In the past, or in other documents, KUCC wells 1193 and 1200 were previously referred to as wells K60
and K109.
June 11, 2004 14
TABLE 5.2A
Zone A Annual Groundwater Extraction Volumes
Wells Annual Extraction (AF)
Acid (1146 and 1201) 2020
Sulfate (1193, 1200, and 1147) 4670
TABLE 5.2B
Zone B Annual Groundwater Extraction Volumes
Annual Extraction (AF)
Wells
Separate
Design
Minimum
Integrated Design
Full Integrated
Design
Zone B Deep 4300 4300 4867
Shallow Aquifer 1400 750 842
JVWCD will monitor metals in the shallow aquifer wells. This monitoring will be
done on a quarterly basis for five years and a yearly basis thereafter. These results
will be reported to DEQ on an annual basis showing the trends of all previous data
collection. This data will enable the tracking of metals migration into JVWCD's
shallow wells if it occurs.
5.3 Collection Pipelines
Collection pipelines ranging in diameter from 8 -16 inches will collect extracted water
from Project extraction wells and convey the feed water to either the Zone A Plant or
Zone B/Lost Use Facilities. Collection pipelines for the Project are shown in Figure
5.2A.
5.4 Water Treatment Plants
CDM originally evaluated the treatment process required to produce municipal
quality water from groundwater in the Affected Area in their 1999 study and report.
The membrane process known as reverse osmosis (RO) was selected by CDM.
JVWCD has selected a treated water quality with a maximum TDS concentration of
250 mg/L. The process to accomplish this has been further studied through pilot
testing by KUCC and JVWCD.
June 11, 2004 15
Two RO water treatment plants are proposed. Figure 5.2A shows a Zone A Plant,
located south of the Bingham Reservoir, at approximately 8400 West 10400 South.
The Zone A Plant will be constructed on land owned by KUCC. The Zone B
Facilities and Lost Use Facilities will be constructed on land owned by JVWCD, at
8300 South 1000 West and will be combined in a common treatment plant building.
This location is also shown in Figure 5.2A.
Figure 5.4A is a treatment flow chart for the Zone A Plant that schematically shows
water flows and facility relationships. Figures 5.4B through 5.4D are treatment flow
charts of the proposed options for Zone B and Lost Use Facilities.
KUCC has prepared design criteria and a preliminary site layout for the Zone A
Plant. Carollo Engineers has prepared design criteria for the Zone B/Lost Use
Facilities processes. These design criteria are explained in Table 6.1 in Appendix
H. Carollo has also prepared site layouts for the Zone B/Lost Use Facilities, which
are shown on Figures 6.1 and 6.3 in Appendix H.
As described in Section 1.2, JVWCD will proceed with the Zone B Facilities and Lost
Use Facilities either as separate operations (i.e., the Separate Design basis) or as
an integrated operation (i.e., the Integrated Design basis), depending on JVWCD’s
assessment, during the design stage, of the best way for it to proceed with the Lost
Use Facilities. For purposes of plant flows in Table 5.4A, it has been assumed that
JVWCD will proceed on an Integrated Design basis. Treatment plant flow rates are
shown on Table 5.4A. Abbreviations in this table include acre-feet per year (afy)
and million gallons per day (MGD).
Table 5.4A
Treatment Plant Flows
Feed Water
Product (Treated) Water
Source
(afy)
(MGD)b
(afy)
(MGD)b
Zone A
4600a
4.46
3500
3.46
Zone B
4300
4.26
3445-3890
2.78-3.13
Shallow Aquifer
750-842
0.61-0.68
750-842
0.61-0.68
(a) Approximate. Zone A will deliver sufficient feed water to produce 3500 AF/yr of permeate.
(b) Based on treated volume produced in 330 to 333 days per year.
The feed water and treated water rates from Zone B Deep Wells and the shallow
aquifer are shown in Table 5.4A by ranges. The lower range corresponds to the
volume that can be produced using existing JVWCD water rights in Zone B. This is
the first option available to JVWCD as described in Section 1.2. The upper range
corresponds to the minimum treated water annual volume of 1,235 acre-feet, as
required by the Consent Decree to offset lost use of concentrate and will require
additional water rights in Zone B. This is the second option available to JVWCD as
described in Section 1.2.
June 11, 2004 16
KUCC and JVWCD have completed pilot/demonstration RO plants for Zone A and
Zone B over the last three years. Results from these pilot plant studies have
demonstrated the technical and economical feasibility for the use of RO technology
as proposed in this document. Scale up of RO technology is not difficult, as the RO
plants will be constructed in a modular fashion (i.e. larger RO plants require
additional banks of membranes and additional pumps to feed them). Both pilot
plants produced permeate for several months, the quality of which was significantly
better than primary drinking water standards.
The pilot study report for the Zone B RO plant is attached as Appendix H. A copy of
the Zone A Plant pilot study report is available for review at the State Division of
Environmental Response and Remediation upon request.
5.5 Treated Water Deliveries
The two treatment plants are located within the service area of the JVWCD
infrastructure for treated water conveyance. The delivery of treated water to the
JVWCD system is shown in Figures 5-5 and 5-8 of the CDM report, and slightly
modified in Figure 5.2A herein.
The Zone A Plant will produce water at a relatively high elevation, in JVWCD’s
pressure zone C or higher. This plant will produce water that will be conveyed to the
Zone A metering station along 10200 South. From this point, JVWCD will route
water into their distribution system. This will be a substantial benefit to the public in
the Affected Area by receiving treated water at a high elevation to allow for
westward land development in Herriman, Riverton, South Jordan, and West Jordan.
The Zone B treated water will be conveyed westward to JVWCD’s 78-inch Jordan
Aqueduct at 7800 South 3600 West. This will provide water to the public in the
Affected Area, either directly or by exchange.
5.6 Concentrate Disposal
KUCC proposes to use its existing tailings slurry conveyance pipeline from Bingham
Canyon to the North Tailings Impoundment for conveyance of concentrate from the
Zone A Plant (see Figure 5.4A). The much greater flow of KUCC tailings slurry in
this pipeline will serve to stabilize the Project concentrate streams (Table 5.6A).
Table 5.6A indicates that the change in chemistry in tailings water from addition of
RO concentrate is very small, within the range of variability of tailings water quality.
Therefore, it is unlikely that this addition will change the characteristics of the tailings
discharge significantly.
June 11, 2004 17
Table 5.6A
Effect of Zone A Reverse Osmosis Concentrate
on Tailings Line Chemistry
Parameter Tailings Line 2002
Ave.
Zone A RO Concentrate
(Typical)
Composite
Flow*
Net Change
(percent)
SO4 4103 5971 4135 0.78
TDS 7934 10,317 7975 0.5
pH 6.97 7.3 6.97 0.00
Ca 716 2054 739 3.21
Cl 1623 680 1607 -0.99
K 142 19 140 -1.41
Mg 510 620 512 0.39
Na 940 294 929 -1.17
Al 0.094 < 0.010 0.092 -2.13
As 0.007 0.023 0.007 0.00
Cd 0.003 < 0.001 0.003 0.00
Cu 0.155 0.027 0.155 0.00
Mn 12.11 < 0.010 11.904 -1.70
Pb < 0.005 < 0.005 < 0.005 NA
Se 0.042 0.014 0.042 0.00
Zn 0.054 0.022 0.05300 -1.85
Notes: All values in mg/L except pH
*Composite flow uses MDL as concentration of metals in concentrate
Tailings water flow, 34,500 gpm; RO concentrate flow, 600 gpm. Range of tailings concentrations
typically + 20 percent.
NA = Not Applicable
Disposal of RO concentrate in the KUCC tailings impoundment is authorized under
KUCC’s existing UPDES (Utah Pollutant Discharge Elimination System) permit.
Water reporting to the tailings impoundment is largely recycled back into KUCC’s
process circuit; excess water, including meteoric water, is discharged to the Great
Salt Lake pursuant to the terms of KUCC’s UPDES permit. KUCC will be
responsible for meeting discharge requirements specified in the permit. After mine
closure or at such other time when operation of the tailings line slurry may cease,
KUCC proposes to discharge the RO concentrate directly to the Great Salt Lake
through the existing tailings pond discharge system. The composition of the
discharge after 30 years is estimated to be similar to that shown in Table 5.6A and
meets the requirements of KUCC’s existing discharge permit.
June 11, 2004 18
Sections 3 and 6 of the CDM report fully explain the recovery rate of the RO
treatment processes and the concentrate streams. Pilot studies have confirmed
these approximate rates. In summary, they will be as shown in Table 5.6B:
Table 5.6B
Project Concentrate Flows
Treatment Process
Concentrate
Flow Rate
(MGD)
Concentrate Discharge Location
Zone A Plant
1.1
Before mine closure to KUCC tailings
pipeline and tailings impoundment;
After mine closure to GSL via
concentrate discharge pipeline or
alternative disposal method.
Zone B Facilities, and
Lost Use Facilities if feed
water comes from Deep
Wells (i.e., the Integrated
Design)
0.8-1.0
Before mine closure, to KUCC tailings
impoundment; after mine closure, to
GSL via concentrate discharge pipeline
or alternative disposal method.
Lost Use Facilities if feed
water comes from shallow
aquifer (i.e., the Separate
Design)
0.0-0.3
Possibly to Great Salt Lake after
additional studies and regulatory
approvals
KUCC is willing to accept the concentrate stream from treatment of Zone B deep
groundwater in its tailings impoundment (see Figure 5.4B) for the operational period
of the Zone B Facilities, provided JVWCD satisfies various requirements, including
the following:
· The concentrates must comply with the specifications of KUCC’s UPDES permit
and other specifications; and
· JVWCD may only deliver 1000 acre feet of concentrates per year, determined
on a five year rolling average basis, with no more than 1100 acre feet delivered
in any calendar year.
JVWCD proposes, as the initial approach for the Project, to discharge the
concentrate streams resulting from the Zone B Deep Wells to the KUCC tailings
impoundment. Direct discharge to the Great Salt Lake of concentrate from either
the Zone B Facilities or the Lost Use Facilities will be considered following additional
research and verification that discharge of such concentrates will not be harmful to
June 11, 2004 19
the Great Salt Lake ecosystem. Any future discharge will be subject to permitting
and regulatory approval.
Certain assumptions concerning disposal of concentrate were made in reaching the
NRD settlement and in developing this Proposal. The following assumptions will be
important to the feasibility of this Project:
· Prior to mine closure, the concentrate streams from the Zone A Plant and, if
applicable, the Zone B Facilities, and Lost Use Facilities if its feed water comes
from the Zone B Deep Wells, can be managed in the tailings disposal system
operated by KUCC. Water decanted from the concentrate stream would be
recycled back into KUCC’s process water circuit or handled in accordance with
KUCC’s UPDES and groundwater discharge permits.
· After mine closure, or prior to that time if for any reason the concentrate stream
cannot be managed within the tailings disposal system, direct discharge to the
Great Salt Lake of the concentrate streams from the Zone A Plant and, if
applicable, the Zone B Facilities and Lost Use Facilities, if its feed water comes
from Deep Wells, will b e addressed through KUCC’s UPDES discharge permit
and after additional study of potential ecological impacts.
6.0 GROUNDWATER IMPACTS AND REMEDIATION
6.1 Groundwater Modeling
Flow Model. KUCC developed a groundwater model of the southwestern Jordan
Valley as part of the RI/FS to analyze flow paths and groundwater velocities in the
principal aquifer and to evaluate remedial options. The Affected Area is within the
southwestern Jordan Valley. The model area extends from the bedrock/alluvial
interface at the base of the Oquirrh Mountains on the west, to the bedrock/alluvial
interface at the base of the Wasatch Mountains on the east, and from approximately
6000 South on the north to the northern base of the Traverse Mountains on the
south. Model calibration closely simulated observed aquifer conditions in the
southwestern Jordan Valley. A more complete description of this model is included
in Appendices A and D.
Transport Model. KUCC’s calibrated groundwater flow model was then coupled
with a contaminant transport code to model historical and future migration of storm
and mine waste water that leaked from the former Bingham Creek reservoir. This
model combines groundwater flow with the physical aspects of contaminant
transport including advection, dispersion and chemical reactions. The transport
model was calibrated to observed 1996-1997 sulfate concentrations down gradient
of the former Bingham Creek reservoirs. Calibration was achieved by finding a set
of transport parameters (i.e., retardation, dispersivity and porosity) within an
June 11, 2004 20
accepted range that reasonably reproduced field-measured concentrations. The
model is believed to be a reasonable first approximation of the kinematics of the
Bingham Creek and former evaporation ponds plumes and allows the feasibility of
various remedial strategies to be tested.
Both the flow and transport models were extensively reviewed by USEPA, UDEQ,
the USGS, the TRC and outside international and nationally - recognized reviewers.
6.2 Hydrogeology
Groundwater Recharge. The principal aquifer is recharged from surface infiltration
of precipitation, irrigation water and canal water, bedrock inflow and to a limited
extent surface infiltration of waters emanating from Butterfield Creek. The bedrock of
the Oquirrh Mountains provides recharge to the groundwater in the western part of
the southwestern Jordan Valley, and this groundwater then travels eastward into the
basin. Aquifer recharge is greater in the eastern part of the southwestern Jordan
Valley and in the Herriman area due to recharge from surface water.
Groundwater Extraction. Most of the water extracted from the principal aquifer is
used for municipal or industrial purposes. A summary of extractions used in the
modeling is included in Appendix A.
Groundwater Elevation Changes. The average depth below ground surface to the
potentiometric surface of the principal aquifer in the southwestern Jordan Valley is
about 235 feet. Groundwater flow is predominantly west to east from the base of the
Oquirrh Mountains to the Jordan River. Groundwater elevations declined
substantially throughout the southwestern Jordan Valley from 1986 to 1996. A
noteworthy area of decline is in the region of the West Jordan City well field, to the
north of the Affected Area. A description of recent groundwater elevation changes
used in the modeling is included in Appendix A.
Groundwater Velocity. Average horizontal groundwater velocities have been
estimated by KUCC to be about 550 feet per year. Isotopic analyses were
conducted by KUCC to confirm this estimate. These analyses yielded a linear
groundwater velocity estimate of 500-650 feet per year. A more complete discussion
of these estimates and analyses is included in Appendix A.
June 11, 2004 21
6.3 Plume Contraction and Containment
Using the groundwater flow and transport models, the region adjacent to KUCC
production wells 1200 and 1193 and the West Jordan municipal well field was
investigated using the following pumping parameters: West Jordan pumping 3600
afy, well 1200 at 1930 afy, well 1193 at 1930 afy, Lark sulfate well 1147 at 800 afy,
and acid extraction wells (1146 and future wells) at 2020 afy. Zone B Deep Wells
are pumped at 5085 afy. Based on these extractions, predictions can be made
regarding the disposition of sulfate (Appendix D). The modeled extractions from the
acid plume and Zone A are consistent with KUCC’s current water rights.
The modeling runs suggest that the proposed containment and extraction system
will be effective at keeping acidic and elevated sulfate (> 1500 mg/L) groundwater
on KUCC property near the acid and sulfate extraction wells in Zone A. It also
reduces sulfate concentrations throughout Zones A and B in the Affected Area
(Figures 6.3A and 6.3B). These modeling runs also suggest that the ideal
environment for sulfate containment and restoration of the aquifer involve West
Jordan City limiting its well field pumping to less than 3,000 afy. This is close to the
sustained yield of the aquifer in that area. KUCC and West Jordan are continuing to
work together to optimize extraction amounts and investigate other mitigation
technologies such as injection. See Appendix D for further detail on plume
containment and remediation as well as potential regional drawdown from
extraction.
Modeling of the additional extraction from Zone B proposed under the Integrated
design results in negligible additional drawdown.
7.0 WATER RIGHTS AND MANAGEMENT WITHIN AFFECTED AREA
7.1 Consent Decree Requirements
The Consent Decree states that, “allocation of the right to use surface or
groundwater resources by the public shall be by the Utah State Engineer pursuant
to Utah water law.” In order to obtain a credit against the ILC, the Consent Decree
requires that groundwater be treated to municipal quality, and provided to a M&I
water purveyor. It anticipates that municipal water rights will be used for Project
groundwater extractions.
7.2 Water Rights in the Affected Area
The only water rights approved for municipal use in the area, as of the date of the
first version of this Proposal in December 1999 are shown in Table 7.2A.
June 11, 2004 22
TABLE 7.2A
Approved Municipal Water Rights in December 1999
Water Right
Number
Owner
Priority
Date
Flow Rate
(cfs)
Potential Annual
Withdrawal (AF)
59-1210
JVWCD
1955
3.55
850
59-1536
JVWCD
1959
5.0
3613
59-1572
West Jordan City
1960
1.0
723
59-1533
Riverton City
1959
1.25(a)
903 (a) One of four points of diversion lies near the Affected Area.
Since December 1999 KUCC has gained change application approvals for some of
its industrial water rights to provide municipal supply in the JVWCD service area.
JVWCD has gained approval of various change applications for shallow
groundwater rights near the Jordan River in the Affected Area. These are
summarized in Table 7.2B.
TABLE 7.2B
Approved JVWCD Shallow Groundwater Rights
Water Right
Number
Underlying Water
Right Owner
Priority
Date
Flow Rate
(cfs)
Potential Annual
Withdrawal (AF)
57-5513
(a23590)
JVWCD
1870
11.78
5000
59-5619
(a23711)
Utah & Salt Lake
Canal Co.
1870
15.48
2882
59-3500
(a23622)
South Jordan
Canal Company
1870
5.77
1205
59-5622
(a23863)
WJWUC/East
Jordan Irrigation
Company
1870
16.85
4797
59-3529
(a23486)
JVWCD
1870
5.3
31.5
The water rights listed in Table 7.2C have been approved by the State Engineer and
will be utilized to supply feed water to the treatment plants.
June 11, 2004 23
TABLE 7.2C
Approved and Pending Water Right Change Applications
Water Right
Number
Owner
Annual Volume
(AF)
Zone
Extraction Wells
59-1210
(a24623)
JVWCD
850
B
B6-8
59-1536
(a24622)
JVWCD
3613
B
B1-8a
59-1535
(Pending)
JVWCD
625
B
B1-7
59-1653
(a26312)
KUCC
2896b
A
1193, 1200, 1147, 1139,
1146, 1201
59-1042
(a26312)
KUCC
3214 b
A
1193, 1200, 1147, 1139,
1146, 1201
59-5314
(a26312)
KUCC
376 b
A
1193, 1200, 1147 and 1139,
1146, 1201
59-1671
(a25110)
KUCC
66.13
A
1147
59-1352
(a25109)
KUCC
136.45
A
1147
(a) JVWCD intends to correct the original 8 Zone B wells sites to the current 7 sites by means of a change
application.
(b) Under water right change application a26312, which includes seven potential points of diversion, KUCC
will also extract water from the acid wells (1146 and 1201) under the CERCLA response.
As indicated in Table 7.2C, JVWCD will be making an application to the State
Engineer to transfer additional water rights into the Zone B area. This will enable
JVWCD to proceed with the Integrated Design option for the Lost Use Facilities for
the full 1235 afy, as described in the second option in Section 1.2. Preliminary
evaluation by JVWCD suggests that the additional proposed extraction will not result
in appreciable additional drawdown. JVWCD’s application will provide information to
the State Engineer regarding potential impacts to other water rights holders in the
area. The water right change application will be open to public comment.
7.3 Proposal to the State Engineer Concerning Water Rights
In August 1999, KUCC proposed to the State Engineer that certain restrictions be
placed on future water development in the southwestern Jordan Valley to facilitate
the NRD remedial process proposed here and to prevent further migration of
existing contamination. These restrictions included:
· Completion depth and pumping rate restrictions on wells drilled within 3,000 feet
south of the known 250 mg/L sulfate isoconcentration line in the Herriman area
(Figure 4.1A).
June 11, 2004 24
· Completion depth and pumping rate restrictions on wells drilled within 3,000 feet
north of the known 250 mg/L sulfate isoconcentration line in the West Jordan
area (Figure 4.1A).
· Prohibition of new well development within the 250 mg/L sulfate isoconcentration
line in the former KUCC evaporation pond area (South Jordan) until KUCC
installs its NRD remediation and water supply and treatment systems, achieves
hydraulic containment of the up-gradient groundwater plume, and the system
reaches steady state and achieves a sulfate level in the area below 250 mg/L.
Appropriate completion depths and pumping rates would be determined on a case-
by-case basis using the most recent information on location and depth of
contamination, aquifer properties and user needs. KUCC would supply this
information to the State Engineer and any water user upon request. The restricted
area will shrink as remediation and natural attenuation reduce the size of the
contaminated zone.
The practical aspects of this request were incorporated in the State Groundwater
Management Plan issued by the State Engineer in 2002 (Appendix E). Specific
details regarding groundwater management in the southwestern Jordan Valley are
detailed in the plan.
KUCC is committed to assist property owners affected by KUCC remediation efforts
in obtaining an adequate water supply by identifying alternative water sources,
providing technical assistance in siting and completion of supply wells, and providing
supplemental financing in cases where the presence of contamination causes an
additional cost burden to the property owner.
8.0 COST ESTIMATES
Table 7 -2 in the CDM report shows the initial cost estimates for the Project. These
estimates were updated as of October 2002 and again as of January 2004. Unless
otherwise indicated the cost estimates used in Sections 8 and 9 of this Proposal are
based on estimates as of January 2004. (Note, however that a number of the costs
used in the Project Agreement continue to be stated in October 2002 dollars.) In
addition, the cost estimates for the Zone B Facilities and Lost Use Facilities used in
this Proposal assume that JVWCD proceeds with the Lost Use Facilities on an
Integrated Design basis.
8.1 Capital Costs for Water Treatment
The Zone A Plant and the Zone B Facilities are involved in deep groundwater
extractions for the Project. This is the base project that was initially contemplated by
June 11, 2004 25
the State NRD Consent Decree. The Lost Use Facilities also may involve
extractions from Deep Wells, as well as extractions from the shallow aquifer
As previously mentioned, additional design and cost estimates have been
completed since the original CDM report. JVWCD retained the engineering firm of
Carollo Engineers to perform membrane treatment pilot testing and to prepare a
cost estimate for the Zone B component of the proposed Project. Table 9.0A
summarizes the capital costs, for both the Zone A Plant and the Zone B/Lost Use
integrated facilities
8.2 Concentrate Disposal Costs
As indicated above, Zone A concentrates are to be disposed in KUCC’s tailings
impoundment. Zone B Deep Well concentrates also may be disposed in KUCC’s
impoundment if JVWCD so elects and certain conditions are satisfied. If the
concentrates cannot be disposed in the impoundment for various reasons, such as
permitting or after mine closure (estimated to occur in 2015-2030), it is anticipated
the concentrates will be conveyed to the Great Salt Lake via a concentrate
discharge line, provided the water chemistry at that time meets regulatory discharge
limits. Bench scale testing of this alternative indicate that disposal of such
concentrates to the Great Salt Lake is technically feasible without exceeding current
KUCC UPDES discharge criteria or generating aesthetic issues due to low-density
precipitates. If one or both of the concentrates is not suitable for direct discharge,
then alternative disposal will be needed. If Zone B Deep Well concentrates are
being managed through KUCC’s operations, and an alternative disposal option is
necessary, JVWCD and KUCC will share costs, subject to the cap on JVWCD’s
contribution specified in the Project Agreement, to develop the alternative disposal
project based on the relative flows of each.
8.3 Operation, Maintenance and Replacement Costs
Current operation, maintenance and replacement (OM&R) costs for the Zone A
Plant and Zone B and Lost Use Facilities (assuming and Integrated Design) are
summarized in Table 9.0A. The OM&R costs for Zone A Plant, Zone B Facilities,
and Lost Use Facilities, constructed based on the integrated design are shown in
Table 9.0A on an net present value (NPV) basis over a 40-year operational period.
8.4 Avoided Capital Costs
The NRD Trust Fund was created to address contamination of groundwater that
might otherwise have been developed for municipal purposes by M&I water
purveyors. The Consent Decree contemplates that the water purveyor(s) receiving
the Trust Fund benefits would pay the avoided cost of developing groundwater,
June 11, 2004 26
absent contamination. This is referred to as “cost of development without
contamination” in Attachment 16 of the Consent Decree and as the “avoided” costs
herein.
JVWCD has performed a more detailed estimate of this avoided capital cost of
development without contamination than was provided in the Consent Decree.
Figure 8.5A shows the location of four wells that would have been developed by
JVWCD (to extract 7000 AF annually) if contamination had not been present. The
location of JVWCD transmission pipelines, pump station and reservoir facilities
throughout the Affected Area would have made this an efficient endeavor. Table
8.5A lists the assumptions, and provides the details for the avoided capital cost
estimate. The estimated avoided capital cost was estimated as $2.801 million in
September 1999 dollars. This amount is indexed to January 2004 dollars, resulting
in an estimate of $3.413 million.
June 11, 2004 27
TABLE 8.5A
Estimate for Avoided JVWCD Capital Cost of
Groundwater Development, Absent Mining Contamination
September 1, 1999
1. Typical Well Drilling Cost Estimate:
Mobilize/Demobilize
1 LS
$27,000
Special conditions
1 LS
$6,480
Conductor casing
120 LF @ $223
$26,760
Drill 24" borehole
580 LF @ $59.40
$34,452
Geophysical logging
1 LS
$2,700
Caliper survey
1 LS
$1,080
Well installation:
- 16" steel casing
500 LF @ $41.28
$20,640
- 16" well screen
200 LF @ $183.34
$36,668
- 2" gravel feed tube
300 LF @ $4.32
$1,296
Install gravel pack
500 LF @ $32.40
$16,200
Install annular grout seal
200 LF @ $40.42
$8,084
Initial well development
40 hr @ $243
$9,720
Install test pump
1 LS
$4,235
Well development pumping
40 hr @ $135
$5,400
Well pump testing
34 hr @ $135
$4,590
Video camera survey
1 LS
$1,945
Plumbeus/alignment testing
1 LS
$1,080
Disinfection/capping
1 LS
$1,570
Fluids/cuttings disposal
1 LS
$2,700
Total for typical well:
$212,600
June 11, 2004 28
2. Pump building and site improvements:
Land purchase
$50,000
Mobilize/demobilize
$15,060
Site improvements
$15,000
Landscaping/irrigation system
$20,800
Yard piping/structures
$6,100
Pump building/architecture
$43,420
Pump station mechanical
$41,260
Supply/install pump/motor
$41,800
Electrical systems
$28,680
Instrumentation/controls
$9,500
JVWCD RTU
$12,000
Change orders
$6,000
Total for typical well:
$289,620
III. Summary of total project costs:
Pipelines - 16,500 LF 10" PVC pipe at $4.00/LF
$66,000
Well drilling (4 wells)
$850,400
Well equipping (4 wells)
$1,158,480
Subtotal:
$2,074,880
Engineering @ 25%
$518,720
Contingency @ 10%
$507,488
Total Cost Estimate (rounded):
Total Cost Indexed to January 2004 Dollars:
$2,801,000
$3,413,000
June 11, 2004 29
Notes:
Assumptions:
Ø 7000 AF per year extraction
Ø Constant flow over 330 days per year (this is equivalent to flow pattern from NRD project)
Ø Total flow rate = 10.7 cfs
Ø 4 wells, each at average flow rate of 2.7 cfs (1200 gpm)
Ø Average well depth of 700 feet
Ø Brick pump building and site improvements/landscaping at each well
Ø Discharge to existing JVWCD transmission system.
Ø Well drilling costs are based on JVWCD’s 1997 1159 East 4500 South well drilling costs, plus 8%.
Facilities:
(See Figure 8.4A)
Ø Pump building/site improvement costs are based on JVWCD’s 1998-1000 1159 East 4500 South
Well costs, plus 4%.
June 11, 2004 30
8.5 Avoided Operating Costs
The Consent Decree (article V.D.2.b.i.) requires that avoided operating costs for
groundwater development without contamination be paid to KUCC toward a KUCC-
proposed project funded from the Trust Fund. These avoided operating costs are to
be paid by the benefiting water purveyor(s). The Consent Decree sets this cost at
$49 per acre-foot in 1995 dollars. This cost is to escalate in accordance with the
ENR “20 Cities” cost index. JVWCD has calculated the net present value of this
operating cost contribution for a 40-year period, assuming a seven percent discount
rate. The net present value is calculated as $2.834 million (in January 2004 dollars),
as shown in Table 9.0A, for the Zone A Plant.
8.6 Total Cost Estimate
The total cost of the proposed Project is shown in Table 9.0A. In summary, the costs
are as follows (in thousands of January 2004 dollars):
1. Zone A (Table 9.0A) – $41,823
2. Zone B/Lost Use Integrated Facilities (Table 9.0A) - $51,450
Total $93,273
These total Project costs do not include the costs of pilot testing and Zone A
operating costs regarding the additional CERCLA response actions that KUCC has
provided. They also do not include cost of land acquisition that has been expended
by JVWCD and KUCC or the easements that KUCC is providing to JVWCD.
9.0 PROJECT FUNDING
Table 9.0A details the Project costs in January 2004 dollars. The various Project
cost components are shown, including capital, O&M, and replacement. The O&M
and replacement cost components are net present costs for 40 years of operation at
a seven percent discount rate, based upon January 2004 dollars.
KUCC and JVWCD propose that the Project be constructed, operated and
maintained by means of funding from various sources. The allocation of these
funding sources is shown in Table 9.0A. However, Table 9.0A is not intended to
reflect the timing of funding disbursements for various components of the Project.
The Project Agreement and State Agreement set forth the detailed arrangements for
funding sources and timing of funding disbursements.
June 11, 2004 31
To date, KUCC and JVWCD have funded membrane pilot testing, land acquisition
and other activities in order to advance the Project. The following generally
describes the stages of continued funding of the Project:
Stage 1:
KUCC will provide the capital costs for design and construction of the Zone A Plant
and Zone B Facilities and advance a portion of the Lost Use Facilities.
Stage 2:
Design and construction of the Lost Use components of the Project will be funded
largely from the cash portion of the Trust Fund, by means of scheduled monthly
disbursements by the Trustee directly to JVWCD. JVWCD will then reach the
“Complete and Operational” milepost for the Lost Use Facilities.
Stage 3:
When KUCC has compensated JVWCD for Zone B construction costs equal to one-
half of the Zone B ILC3, the Trustee will reduce the Zone B ILC by 50 percent and
JVWCD will commit to deliver to the Affected Municipalities 1750 afy of municipal
quality water. Incremental increases in such compensations or dispersements will
result in corresponding reductions to the Zone B ILC and increases in JVWCD’s
commitments for water delivery. When KUCC has reimbursed JVW CD for
construction costs equal to the full amount of the Zone B ILC, the ILC will be
reduced to zero and JVWCD commitment to deliver water to the Affected
Municipalities will be 3500 afy, whether or not the Zone B Facilities reach Complete
and Operational.
Stage 4:
Upon reaching Complete and Operational status for the Zone A Plant the Trustee
will reduce the Zone A ILC by 60 percent.
Stage 5:
KUCC will operate the Zone A Plant following the Complete and Operational
milepost. JVWCD will operate Zone B and Lost Use Facilities following the
Complete and Operational milepost.
Stage 6:
KUCC will fund all OM&R expenses at the Zone A Plant. However, during the first
five years of operation of the plant, the Trustee will annually release 15 percent of
the remaining balance of the Zone A ILC for OM&R expenses, with a complete
release at the end of five years. JVWCD and KUCC will fund all OM&R expenses at
the Zone B Facilities.
3 The ILC held in the Trust Fund is to be divided into two ILCs for the Project – the Zone A ILC for the
Zone A component and the Zone B ILC for the Zone B Facilities. See Section 13.4 below.
June 11, 2004 32
Stage 7:
The Trustee will release amounts from the cash portion of the Trust Fund directly to
JVWCD annually for OM&R costs incurred by JVWCD in operating and maintaining
the Lost Use Facilities until the cash portion reaches zero.
In addition to the capital, operating, maintenance and replacement costs contributed
by KUCC and JVWCD, as shown in Table 9.0A, the following contributions of land
and assets currently owned by KUCC and JVWCD, or to be acquired by JVWCD,
will be made to the Project:
· Zone A treatment plant site owned by KUCC
· Zone A wells and sites owned by KUCC
· Zone A water rights for wells 1193, 1200 and 1147 owned by KUCC
· Zone B treatment plant site owned by JVWCD
· Zone B and Lost Use wells owned by JVWCD
· Zone B and Lost Use water rights owned by JVWCD
· Additional In-kind contribution by JVWCD includes use of its water storage and
distribution system
· Additional in-kind contributions by KUCC include:
Ø Use of its tailings slurry pipeline and impoundment for concentrate disposal
Ø Acid plume well facilities and OM&R
Ø Sulfate extraction well facilities and OM&R
Ø Easements for JVWCD’s concentrate disposal pipeline across KUCC land
June 11, 2004 33
Table 9.0A
Distribution and Funding of Project Cost (in thousands of January 2004 dollars)a
Funding Allocation Net Present Cost of
40 Year Operational
Period Trust Fund
Facility Capital OM&R Total ILCb Cashc KUCC JVWCD
Overall Project
Source control 138,205 31,159 169,364 169,364
Zone A:
Acid wells 4,804 7,363 12,167 10,646
Sulfate well w/R/O wells
Pilot testing 1,632 1,632
RO feed wells 1,109 6,491 7,600 2,834 g
RO plant & pipelines 13,297 6,103 19,400 2,628 f
JVWCD process enhancementd 304 720 1,024 1,024
Subtotal Zone A 21,146 20,677 41,823 24,691 e 0 10,646 6,486
Zone B/Lost Use Integrated Design:
Pilot testing 358 358 179 179
Land and R/W 934 934 934
RO plant 15,496 4,380 19,876 4,287 7,936
Pipeline and wells 23,556 5,958 29,514 785 i
Trustee admin expenseh 815 815 815
Subtotal Integrated Design 41,159 10,338 51,497 24,691 e 12,412 4,466 9,834
Zone A and Integrated Design Totals 62,305 31,015 93,320 49,382 13,227 j 15,112 16,320
j
TOTALS 200,510 62,174 262,684 49,382 13,227 i 184,476 16,320
June 11, 2004 34
Notes:
a. Based on present cost, 10% contingency, 40 years operational period, and discount rate of 7%. Cost estimates
($x1000) are based on latest designs (October 2002) and 2004 cost estimates from Kennecott and JVWCD/
Carollo Engineering.
b. Irrevocable letter of credit, worth $28 million in 1995 dollars, to be replaced with Zone A ILC and Zone B ILC.
January 2004 value: $49,382,800.
c. Cash portion of the Trust Fund, worth $9 million in 1995. January 30, 2004 value: $13,227,045.
d. Improvements to RO Plant to produce water with TDS at 250 mg/L, rather than higher TDS allowed by Consent
Decree, (from December 2000 Table 9.0A, indexed to January 2004 per ENR index. Pursuant to the Project
Agreement, JVWCD will pay KUCC $8.36 per AF for the first 70,000 AF to reimburse capital costs and $12.30
per AF (October 2002 dollars indexed to ENR) to reimburse KUCC for OM&R costs.
e. 50 percent of Letter of Credit value as of January 20, 2004.
f. 75% of JVWCD avoided capital cost (75% of $3.413 million, or $2.628 million for groundwater development
without contamination (see Section 8.4), at January 2004 value; amortized in Project Agreement over 20 years.
g. JVWCD avoided O&M cost for groundwater development of 3,500 AF/yr without contamination - paid annually to
KUCC (see Section 8.5). Cost is $49 per AF in 1995 dollars, indexed to January 20, 2004 by ENR index.
h. Fixed amount for Trustee administrative expenses.
i. 25% of JVWCD avoided capital cost (25% of $3.413 million) for groundwater development without contamination,
at January 2004 value. See Section 8.4
j. Value of cash trust fund in January 2004 dollars.
June 11, 2004 35
10.0 OPERATION, MAINTENANCE, REPLACEMENT RESPONSIBILITIES
10.1 Zone A Plant
KUCC will construct, own, operate, maintain and replace when necessary the
following extraction wells:
1. Extraction wells 1193 and 1200 (the Zone A sulfate extraction wells)
2. Wells ECG1146 and 1201 (the “acid plume” extraction wells) and other acid
wells to be drilled 5 to 15 years after initiation of Project to continue to capture
acid plume.
3. Well LTG1147 located near 6200 West 11800 South (“the sulfate extraction
well”).
The collection pipelines from the Project extraction wells to the Zone A water
treatment plant, and the concentrate discharge pipeline (to KUCC’s tailings line) will
be owned and operated by KUCC. The Zone A RO plant will be constructed in three
phases over a period of two years. The three-phased approach of design and
construction of the Zone A Plant through 2005 will allow KUCC to gain operating
experience and reach a point of optimization in operational mode. The Zone A Plant
and the treated water (permeate) delivery pipeline to the JVWCD system will also
initially be owned and operated by KUCC. At KUCC’s discretion, the ownership,
operations and/or maintenance of the Zone A Plant may be transferred to JVWCD
or another entity at a future time.
10.2 Zone B/Lost Use Integrated Facilities (for Deep Groundwater Extraction)
The facilities for extraction and treatment of water of Zone B deep groundwater on
an Integrated Design basis will include seven extraction wells, collection pipelines,
an RO treatment plant and related facilities at 1000 West 8300 South, a concentrate
discharge pipeline to KUCC’s tailings impoundment, and a delivery pipeline to the
JVWCD system. Following construction and startup testing, ownership of these
facilities will remain with JVWCD. JVWCD will commit to operate, maintain and
replace these facilities for at least 4 0 years thereafter. If JVWCD’s operation of the
Zone B Facilities becomes infeasible due to changing drinking water regulations or
discharge permits or any other reason, JVWCD will commit to continue delivering
3,500 afy of water, from its other sources, to the Affected Municipalities for the
remainder of the Operational Period.
10.3 Lost Use Facilities (for Shallow Groundwater Extraction)
If the Lost Use Facilities proceed on a Separate Design basis, these facilities will
include shallow extraction wells, collection pipelines, RO and other membrane
treatment facilities located in an enlarged treatment building (together with the Zone
B deep groundwater treatment facilities) at 1000 West 8300 South, a concentrate
June 11, 2004 36
pipeline to the Great Salt Lake, and a delivery pipeline to the JVWCD treated water
transmission system.
Following initial construction and startup testing, ownership of these facilities will
remain with JVWCD. JVWCD will then commit to operate, maintain and replace
these facilities for at least 40 years. If JVWCD’s operation of the Lost Use shallow
groundwater facilities becomes infeasible due to changing drinking water regulations
or discharge permits or any other reason, JVWCD will commit to continue delivering
at least 1,235 acre feet of water, from its other sources, to the Affected
Municipalities for the remainder of the Operational Period.
11.0 ALLOCATION OF PROJECT BENEFITS
Half of the 7,000 afy of treated water from deep groundwater (3,500 afy) will result
from KUCC’s rights shown in Section 7.2. The 3,500 afy of treated water that is
produced by the Zone A Plant will be allocated by JVWCD to directly benefit the four
incorporated communities in the Affected Area. These “Affected Municipalities” are:
Herriman City, Riverton City, South Jordan City and West Jordan City. The benefit
to the four Affected Municipalities will be in the form of a water supply at high
elevation, with discounted water rates as further described hereafter in this Section.
Under this Project Proposal, JVWCD will use its water rights to produce half of the
7,000 afy of water from Zone B Deep Wells that will be treated at the Zone B
Facilities. In addition, it may use its Utah Lake/Jordan River rights for shallow
groundwater extraction and treatment, as well as additional groundwater rights in
the Zone B Deep Wells for treatment at the Lost Use Facilities. These treated waters
will be reserved for the four Affected Municipalities during the entire 40-year
Operational Period under wholesale contract water purchase agreements to be
executed between those Affected Municipalities and JVWCD. When not contracted
for by the four Affected Municipalities, these waters will be available for the benefit
of any of the member agencies and customers of JVWCD (see Section 14 for
further description of the rationale for this allocation).
JVWCD has performed an analysis to derive the allocation of Zone A treated water
benefits to the four Affected Municipalities. The factors considered in this evaluation
were: 1) total population of each Affected Municipality; 2) area of each Affected
Municipality within the overall Affected Area; 3) area of each Affected Municipality
within Zone A of the Affected Area, and 4) 1999 approved municipal groundwater
rights in the principal aquifer within the overall Affected Area, and within Zone A of
the Affected Area. Tables 1 through 4 in Appendix F show methods 1-4 of
comparing and evaluating these factors. The allocation percentages for methods 1 -4
are summarized in Table 11.0A. An allocation of Zone A treated water benefits is
also shown in Table 11.0A.
June 11, 2004 37
TABLE 11.0A
Allocation of Zone A Treated Water Among Affected Municipalities(a)
Affected
Municipality
Allocation
(percent)
Maximum Annual
Volume(b)
(acre-feet)
Maximum Flow
Rate(c)
(MGD)(d)
West Jordan City
35
1225
1.21
South Jordan City
30
1050
1.04
Riverton City
20
700
0.69
Herriman City
15
525
0.52
Notes:
(a) These allocations will be held for the Affected Municipalities for five years, based upon a notification by JVWCD to the Affected Municipalities at the
time of execution of Project Agreement. After the five year period, any of the Zone A waters that is not contracted for within the allocations shown
above would be held for the four Affected Municipalities for Operational Period and would available for contract with any of the four Affected
Municipalities.
(b) Each Affected Municipality may purchase up to its allocated percent of the actual Treated Water Annual Volume produced by the Zone A Plant,
which may not exceed the volumes of water shown in this column.
(c) Each Affected Municipality may purchase up to its allocated percent of the actual Treated Water flow rates produced by the Zone A Plant, which
may not exceed the flow rates of water shown in this column.
(d) Million gallons per day.
June 11, 2004 38
These four communities show differences in population and area in the Affected
Area. Other than JVWCD’s municipal water rights, only two currently approved
municipal water rights, those of West Jordan City and Riverton City, lie within or
near the Affected Area. Both of these lie at the extreme fringe areas, at the
northeast and southern edges. KUCC and JVWCD do not propose to require capital
and operating cost contributions from these municipalities. However, their benefits
will be subject to the following:
· West Jordan City will not develop its water right #59-1572 at a point of diversion
closer than 2,000 feet from the Affected Area as defined in the Consent Decree
during the Operational Period.
· Riverton City will apply to the State Engineer to move point of diversion No. 1 of
its Water Right #59-1533 to the current location of its Garamandi well, located
near 4000 West 12600 South. Riverton City will not move any point of diversion
under Water Right #59-1533 to a location closer than 2000 feet from the Affected
Area.
JVWCD will hold the allocations shown in Table 11.0A open for the four Affected
Municipalities for five years. To provide adequate time for Affected Municipalities to
contract for Zone A water, JVWCD will provide written notice no later than the date
of execution of the Project Agreement stating when the lower cost Zone A water
becomes available. The allocations will then be held open for five years.
Thereafter, throughout the Operational Period, any Affected Municipality would be
able to contract for any Zone A water amount not previously contracted for within the
allocations.
JVWCD proposes to provide benefits from treated water produced from Zone A
Plant to the four Affected Municipalities by providing treated water deliveries at
reduced water rates. JVWCD will accomplish this by providing Zone A water to the
four Affected Municipalities at less than its base wholesale rate, without surcharges
for pumping or peaking. In spite of no pumping charges, this water would be
provided at a storage elevation of at least 5,150 feet above sea level, in the JVWCD
pressure Zone C that normally includes pumping surcharges. The Zone A water will
also be delivered, by agreement with KUCC in the Project Agreement, to an
elevation of 5,350 feet above sea level, to allow for a future JVWCD pressure Zone
D.
For example, the 2002 wholesale water rates for JVWCD pressure Zone C to West
Jordan City, and South Jordan City are:
West Jordan City: $329.45/AF
South Jordan City: $324.79/AF
June 11, 2004 39
During 2002 the estimated pressure Zone D wholesale price would be at least $355
per acre foot.
In contrast, the 2002 JVWCD rate offered to the four Affected Municipalities would
have been as shown in Table 11.0B.
Table 11.0B
Illustration of Discounted Wholesale
Water Rate Methodology for Zone A Treated Water(a)
Water Rate Components
Unit Cost for
1999 (per AF)(g)
· JVWCD wholesale rate (without pumping or peaking surcharges)(b) $239.22
· Less JVWCD average water source unit cost ($142.49)
· Less JVWCD weighted average surface water treatment/wells O&M unit
cost(c) ($34.62)
· Plus JVWCD “avoided operating cost”(d) $55.15
· Plus JVWCD additional O M&R cost to reduce TDS to 250 mg/L (Zones A
and B average)(e) $25.48
· Plus JVWCD’s amortized capital contribution to the Proposal(f) $61.05
Net Discounted Water Rate: $203.79
Notes:
(a) The illustration uses actual figures from 1999.
(b) The wholesale rate is determined annually by JVWCD using its then current rate methodology. The
methodology for calculating rates in 1999, 2000 and 2001 is the “Base-Extra Capacity Method” of the
American Water Works Association, as interpreted and implemented by JVWCD . (c) Includes personnel, electricity, chemical, and equipment, calculated from the previous year. (d) As described in the Consent Decree, this is $49 per acre-foot, in 1995 dollars, escalated at the ENR
“20 Cities” cost index.
(e) See CDM Report and Proposal.
(f) $4.9 million amortized at 6%, 20 years. Thereafter, this will become a replacement sinking fund
contribution, at the amortized base, indexed to future years.
The Zone A water will be made available at this reduced rate, as calculated each
year by JVWCD under its then current wholesale water rate formulas and water rate
study, by execution of water purchase agreements with the four Affected
Municipalities. This water rate methodology will remain in effect for the Operational
Period of 40 years. Appendix 4 of the Project Agreement fully explains the price
methodology and conditions for the Zone A water.
June 11, 2004 40
Zone B and Lost Use treated water will also be reserved by JVWCD for the Affected
Municipalities throughout the Operational Period of 40 years. It will be made
available through normal wholesale water purchase agreements with the Affected
Municipalities. Appendix 4 of the Project Agreement fully explains the water rate
methodology and other conditions for these water sales to the Affected
Municipalities.
KUCC and JVWCD met with city managers, technical staff and mayors of the four
Affected Municipalities during September and October 1999. Upon invitation by the
communities, KUCC, JVWCD and city staff made presentations to the councils of
Herriman City, South Jordan City, and West Jordan City during November 1999 a nd
September 2003. KUCC and JVWCD have held numerous subsequent meetings
with officers and staff of the Affected Municipalities.
The Herriman City Council and the South Jordan City Council voted to endorse the
Project during those meetings. Enclosed in A ppendix G are the following: letters of
endorsement from Herriman City and West Jordan City, the minutes from the South
Jordan City Council meeting, and a letter expressing support for the Project and a
desire for its allocation of reduced-price water from Riverton City.
12.0 SCHEDULE, DESIGN & CONSTRUCTION, FACILITIES OWNERSHIP
12.1 Proposed Project Schedule
Section 10 of the CDM conceptual design report recommended a schedule for pilot
testing, design, construction, and startup/testing. Table 12.1A includes components
of the schedule with other updates and project elements shown. Completion of
construction would be accomplished by December of 2005 for Zone A and
December 2008 for Zone B based on the l atest available estimates and schedules
associated with this Project. The schedule shown in Table 12.1A is conditioned
upon:
· State Trustee and staff evaluation completed - June 2004.
· Trustee approval of Project (and execution of agreements) - July 2004
Any delay in any of the above referenced milepost dates (as well as any delay in the
activities mentioned in Table 12.1A) will create a corresponding delay in the overall
project schedule.
June 11, 2004 41
TABLE 12.1A
Proposed Project Schedule
Completed By
Activity
Zone A
Zone B
Land purchases by KUCC and JVWCD
Sep. 2000 ü
July 2005
USEPA remedial Project manager evaluation
Dec. 2000 ü
Dec. 2000 ü
USEPA Record of Decision
Dec. 2000 ü
N/A
State Engineer change application approvals
April 2003 ü
Jan. 2003 ü
State Trustee and staff evaluation
June 2004 June 2004
State Engineer evaluation of Proposal
July 2003 ü
July 2003 ü
State public hearings
Aug-Nov 2003 ü
Aug-Nov 2003 ü
Trustee approval of Project Proposal
July 2004
July 2004
Execution of Project Agreement and State Agreement
July 2004
July 2004
Preliminary design
2004 2005
Final design 2004 2006
Division of Drinking Water approval 2004 2006
Award construction contracts 2004 2006
Complete construction 2005 2008
Startup, testing, begin operation, reach C & O status 2006 2009
Deliver Treated Water to Public 2006 2010
Notes:
ü = Completed
N/A = Not applicable
12.2 Design
The design work would be performed by, or commissioned and managed by the
parties shown in Table 12.2A, with oversight from UDEQ and USEPA:
June 11, 2004 42
TABLE 12.2A
Design Responsibility
Project Component
Designed By
Zone A Extraction Wells
Existing/KUCC
Zone A Plant
KUCC
Zone A Concentrate Pipeline
KUCC
Zone A Treated Water Discharge Pipeline
KUCC Zone B/Lost Use Deep Extraction Wells JVWCD
Lost Use Shallow Wells
JVWCD
Zone B/Lost Use Facilities
JVWCD
Zone B/Lost Use Concentrate Discharge Pipeline
JVWCD
Zone B/Lost Use Treated Water Discharge Pipelines
JVWCD
12.3 Construction
Construction may be performed, through contractors, by the same parties that
performed the design work shown in Table 12.2A. The same parties will perform
startup and testing and begin operations.
12.4 Facilities Ownership
Ownership of facilities would be as shown in Table 12.4A.
TABLE 12.4A
Ownership of Facilities for Proposed Project
Project Component
Owned By
Zone A Extraction Wells
KUCC
Zone A Plant
KUCC
Zone A Concentrate Pipeline
KUCC Zone A Treated Water Discharge Pipeline to Meter KUCC
Meter to Pressure Zone C or D reservoir
JVWCD
Zone B/Lost Use Deep Extraction Wells
JVWCD
Lost Use Shallow Wells
JVWCD
Zone B/Lost Use Facilities
JVWCD
Zone B/Lost Use Deep Well Concentrate Discharge Pipeline
JVWCD
Zone B/Lost Use Treated Water Discharge Pipeline
JVWCD
June 11, 2004 43
13.0 LIABILITY AND AGREEMENTS
13.1 Liability
KUCC has certain CERCLA liabilities in remedial actions for contaminated
groundwater. KUCC will defend, indemnify and hold JVWCD harmless from
environmental claims relating to existing contamination as described in the Consent
Decree and RI/FS, the feed water for and its treatment at the Zone A Plant before it
becomes permeate delivered to JVWCD, and concentrates KUCC disposes. The
indemnity does not apply to claims that arise from JVWCD’s own gross negligent or
intentional wrongful actions, among other claims.
13.2 Contract Mileposts
The following mileposts are important in the agreements for the Project:
· Complete and Operational - This milepost will be reached for each treatment
plant and associated facilities when the plant operator has received an operating
permit from the Utah Division of Drinking Water, the operator has notified the
Trustee that the facility is Complete and Operational, and the Trustee has
provided the notice required by the State Agreement..
· Operational Period - 40 years following the Complete and Operational status
date for each plant
13.3 KUCC/JVWCD Agreement (“The Project Agreement”)
KUCC and JVWCD have negotiated a Project Agreement to govern their
relationship and obligations during the design, construction, and Operational Period
of components of the Project. In general, the Project Agreement includes the
following provisions:
· KUCC will design, construct, operate and maintain the Zone A Plant and
associated facilities f or the Operational Period of the plant. JVWCD will deliver
the treated water from the Zone A Plant to the Affected Municipalities for the
Operational Period.
· JVWCD will design, construct, operate and maintain the Zone B and Lost Use
Facilities. JVWCD will deliver the requisite amount of water from such facilities or
alternative sources to the Affected Municipalities for 40 years.
· KUCC has advanced certain capital funds during the right-of-way acquisition and
pilot testing phases of the Project. KUCC will advance additional capital funds
June 11, 2004 44
for the design and construction phases of the Project. These arrangements are
further described in the Project Agreement, and are partially reflected in Table
9.0A.
· JVWCD will pay to KUCC the “avoided OM&R costs” for 3500 afy of Zone A
treated water at a price defined in the Consent Decree. (See Section 8.5.)
JVWCD will also pay to KUCC its “avoided capital cost” of developing
groundwater, absent contamination, in the Affected Area. (See Section 8.4)
· JVWCD is responsible for supplemental capital funds (if any) and O M&R funds,
to construct and operate the Zone B and Lost Use Facilities.
· Concentrate disposal is also addressed, as more fully discussed under Section
5.6 of this Proposal.
13.4 KUCC/JVWCD Agreement with the State of Utah (“The State Agreement”)
KUCC and JVWCD have negotiated an agreement with the State of Utah to
implement the Project. The State Agreement includes provisions for replacement of
the Trust Fund irrevocable letter of credit with two irrevocable letters of credit (the
Zone A ILC and Zone B ILC) to be reduced in exchange for (a) KUCC’s agreement
to construct, operate and maintain the Zone A Plant and fund the construction of the
Zone B Facilities, and (b) JVWCD’s agreement to construct, operate and maintain
the Zone B and Lost Use Facilities, or alternative sources, in each case in order to
provide municipal quality water to the Affected Municipalities.
The Zone A ILC will be reduced in capital and OM&R phases. The State
Agreement provides for a 60 percent reduction of the Zone A ILC for capital
expenditures upon reaching “Complete and Operational” status. At that time, KUCC
commits to deliver 3500 afy of treated water for the Operational Period. The
remaining 40 percent of the Zone A ILC, representing OM&R, is released at 15
percent annually over the next four years with the remainder released in the fifth
year.
The Zone B ILC will be reduced by 50 percent when KUCC has compensated
JVWCD for Zone B construction costs equal to one-half of the Zone B ILC. At that
time, JVWCD commits to deliver to the Affected Municipalities 1750 afy of water for
40 years. Further reductions to the Zone B ILC will occur consistent with increases
in compensation made by KUCC and increases in JVWCD’s commitments for water
delivery. The Zone B ILC will be reduced to zero when KUCC has compensated
JVWCD for construction costs equal to the full amount of the Zone B ILC. At that
time, JVWCD’s commitment to deliver water to the Affected Municipalities will be
3500 afy for 40 years, whether or not the Zone B Facilities reach Complete and
Operational status.
June 11, 2004 45
The State Trustee will release defined amounts of the cash portion of the Trust
Fund directly to JVWCD during its design, construction, operation and maintenance
of the Lost Use Facilities. Whether or not the Lost Use Facilities are Complete and
Operational, JVWCD’s commitment to deliver water to the Affected Municipalities
will be 1235 afy for 40 years, JVWCD will provide additional OM&R funds to operate
the Lost Use Facilities throughout the Operational Period, after the cash portion of
the Trust Fund has been exhausted.
14.0 ZONES A AND B RATIONALE
14.1 Zone A
The groundwater in Zone A contains both elevated sulfate (NRD) and acid
(CERCLA) contamination, with sulfate concentrations mainly above 1500 mg/L and
acidic water containing elevated heavy metal concentrations. KUCC has designed a
hydraulic containment system to contain and extract the acid and the elevated
sulfate plumes as detailed below (see Appendix B for scope of CERCLA remedy).
The containment system will consist of acid extraction wells in the core of the acidic
plume, and sulfate barrier wells 1193 and 1200. The extracted sulfate water will be
treated by a reverse osmosis membrane-filtration plant located on KUCC property.
Concentrate reject from the reverse osmosis treatment process will be placed in the
KUCC tailings line. Extracted acidic water also will be routed to the tailings line for
neutralization by the tailings. If the tailings do not contain sufficient neutralization
potential, supplemental lime will be added to the tailings. The resulting neutralized
water will be recycled through the tailings impoundment for use at the Copperton
Concentrator. (An alternative approach will be developed if this plan for managing
concentrate streams becomes infeasible, see Final Remedial Design, Appendix A,
for analysis of conceptual options.) Figures 6.3A and 6.3B show the potential layout
of the extraction wells and the model-computed distribution of sulfate concentrations
in 2025 and 2050 based on this scenario (see also Appendix D).
The Bingham Creek sulfate plume would be pumped at approximately 2000 gpm
and the acid plume at approximately 1500-2000 gpm. The total extraction rate of a
maximum of 4000 gpm is approximately the sustained yield of the principal aquifer
in the Bingham Creek area. The pumping rate of the acid plume is well above the
rate required by the NRD Consent Decree (250 gpm or 400 afy average over a five-
year period) in order to remove the main mass of the acid plume as quickly as
possible and extend the time in which the sulfate containment system can extract
sulfate at levels below 2000 mg/L. The extraction of 2000 gpm from the sulfate
extraction wells plus another potential 1000 gpm from the Lark sulfate well has been
modeled to yield at least 3500 afy of municipal quality water after RO treatment.
June 11, 2004 46
KUCC will utilize its existing industrial groundwater rights (part of which have been
converted to municipal water rights) to extract groundwater from this zone for
treatment and will deliver 3500 afy of treated, deep groundwater to the JVWCD, who
will make the water available to the cities of Herriman, Riverton, South Jordan and
West Jordan.
The rationale for JVWCD receiving and distributing these waters is as follows:
· JVWCD owns all of the currently approved municipal groundwater rights in Zone
A
· The Consent Decree requires that the public in the Affected Area receive
benefits from the Trust Fund
· JVWCD has existing infrastructure to distribute Zone A water to the four Affected
Municipalities. This provides an efficiency and economy of scale to the proposed
Project
· JVWCD’s existing infrastructure will allow the public in the Affected Area to
obtain the benefits of the Trust Fund and the M&I water
· JVWCD has current wholesale water delivery contracts and relationships with
West Jordan, South Jordan and Riverton cities (see Table 14.1A). JVWCD
serves retail connections in Herriman, and has held discussions with Herriman
City regarding near future wholesale water deliveries from the JVWCD
Table 14.1A
2004 JVWCD Water Purchase Contracts
With Affected Municipalities (afy)
South Jordan City
8675
West Jordan City
10,400
Riverton City
620
Herriman 1000
14.2 Zone B
Groundwater in Zone B is the majority of the “sulfate plume,” with sulfate
concentrations lower than those in Zone A. JVWCD will utilize its existing municipal
groundwater rights in the Affected Area to extract principal aquifer groundwater for
treatment, will receive the 3,500 afy of treated, deep groundwater, and will make
that water available to all of its member agencies, including the four Affected
Municipalities. This water will be reserved for the four Affected Municipalities,
throughout the Operational Period, if they desire to execute wholesale water
contracts to purchase this water from the JVWCD.
June 11, 2004 47
The basis for JVWCD treating and delivering these waters, and making them
available to all of its member agencies until the Four Affected Municipalities contract
for them, includes the following issues:
· JVWCD owns 79 percent of the currently approved municipal groundwater rights
in the Affected Area.
· These JVWCD groundwater rights are assets that belong to all of the member
agencies of JVWCD throughout Salt Lake County.
· JVWCD has the existing infrastructure to convey Zone B treated groundwater
throughout Salt Lake County to benefit the member agencies that jointly own the
JVWCD municipal groundwater rights. These member agencies have paid for
the construction of infrastructure to serve Zones A and B.
· JVWCD has contributed valuable information and guidance during Consent
Decree negotiations and technical review oversight of the RI/FS process.
· JVWCD is willing to utilize its Utah Lake/Jordan River rights to accomplish the
Trust Fund purpose to “replace, restore or provide the equivalent” of the
groundwater from the Affected Area lost as concentrate streams from membrane
treatment processes in both Zones A and B, by providing Lost Use water.
· JVWCD has the expertise and staff to operate and maintain project facilities in
an efficient manner.
· West Jordan, South Jordan, Riverton, and Herriman cities are member agencies
of JVWCD, and can receive Zone B water.
15.0 MEETING INTENT OF NRD CONSENT DECREE
The following table summarizes the intent of the NRD Consent Decree and
delineates the features of this Proposal that meet this intent.
June 11, 2004 48
TABLE 15.0A
Intent of NRD Consent Decree
Actions
CD
Sect. Response Date
Meets
Intent Comments
RI/FS V.A. Completed by
KUCC
1998 Yes Reviewed and approved by USEPA
and TRC; ROD issued in 2000.
Acid Well V.B. Completed by
KUCC
1997 Yes Currently 1100 AF pumped. Meets
pumping criteria.
Source Control V.C. Completed by
KUCC
1997 Yes Eastside Collection system permitted
under UGWDP.
Trust Fund V.D.1 Paid by KUCC 1995 Yes Trust Fund established with $9 million
cash and $28 million ILC, (valued at
$13 million and $49 million as of
January 2004.)
Restoration of
aquifer, including
solid phase
contamination
V.D.1 Extraction of
sulfate and
acid
1997 Yes Installed sulfate and acid wells have
removed 58,000 tons of sulfate since
August 1997; this Proposal will
continue process perpetually.
Replace water V.D.1 This Proposal 2004 Yes Will produce 7000 AF of water
annually from Affected Area; and will
produce 1235 AF/yr to replace lost
concentrate, as “Lost Use” portion of
the project.
Acquire equivalent V.D.1 N/A N/A N/A The Ttrust Fund will only be expended
to restore, replace, or acquire the
equivalent of the surface or ground
water resources for the benefit of the
public in the Affected Area.
Treatment V.D.2b This Proposal 2004 Yes Treatment system described.
Accepted by M&I
Purveyor- with
water right put to
beneficial use
V.D.2bi This Proposal 2004 Yes 3500 afy water to be accepted by
JVWCD, a purveyor of M&I water.
Both KUCC and JVWCD are supplying
water rights for municipal purposes.
Prevent and
Replace Spread of
Contamination
V.D.2bii This Proposal 2005-2045 Yes See section 6.3 of Proposal.
Substainable
water supply for
40 years
V.D.2bii
i
This Proposal 2005-2045 Yes See section 6.1 of Proposal.
Does not
materially increase
unit cost to
produce
remainder of 7000
afy
V.D.2bi
v
This Proposal 2005 Yes This Proposal will produce all of the
7000 AF/yr, within the Trust Fund
amount. Also supplies 1,235 afy for
Lost Use.
Beneficial Use V.D.5 This Proposal 2005 Yes JVWCD agencies benefit; specifically
those in affected area. KUCC water
rights converted to municipal use.
Restore, Replace,
Acquire the
Equivalent
V.D.4 This Proposal 2010 Yes JVWCD provides 3500 AF/yr - Zone B