HomeMy WebLinkAboutDERR-2024-007804Southw est Groundw ater
Project Stakeholders Meeting
January 12, 2005
Jordan Valley W ater Conservancy District
Southw est Groundw ater Project
Status and Schedule Outlook
Agreements with Trustee and Kennecott Signed –
August 31, 2004
Zone A Reverse Osmosis Treatment Plant
Complete and Operational – Spring 2006
Zone B Reverse Osmosis Treatment Plant
Complete and Operational – Spring 2009
Southw est Groundw ater Project
2004 Project Activities
• Sign agreement with Trustee and Kennecott
• Sign agreement with Kennecott
• Issue a request for Proposal for a consulting
engineering firm
• Select a consulting engineering firm (Carollo
Engineers)
• Negotiate an agreement with Carollo Engineers
Southw est Groundw ater Project
2005 Project Activities
• Complete acquisition of four deep well sites
• Acquire pipeline easements
• Drill deep exploratory wells
• Submit Jordan River UPDES permit (feed
water)
• Begin drilling deep production wells
• Begin drilling shallow production wells
Southw est Groundw ater Project
2005 Project Activities
• Begin design work for:
– Reverse osmosis treatment plant
– Byproduct pump stations
– Feed water collection pipelines
• Continue construction of Zone B finished
water pipeline (7800 South)
• Construct Zone A finished water pipeline
(10200 South)
Cont.
Southw est Groundw ater Project
2006 Project Activities
• Complete acquisition of pipeline easements.
• Complete drilling, development, and pump
testing of deep production wells.
• Complete drilling, development, and pump
testing of shallow production wells.
• Complete design work for:
– Reverse osmosis treatment plant
– Byproduct pump stations
– Feed water collection pipelines
• Begin construction of feed water collection
pipelines.
• Complete construction of Zone B finished water
pipeline
• Begin design of byproduct pump stations
• Make treatment plant decision: (based on water
right change application status)
– Minimum Integrated Design vs. Integrated Design
Southw est Groundw ater Project
2006 Project Activities
Cont.
• Complete construction of feed water collection
pipelines.
• Complete construction of byproduct pump
stations.
• Begin construction of reverse osmosis treatment
plant.
• September 2007 – make treatment plant design
– Integrated Design vs. Separate Design
• Begin construction of byproduct pipeline.
Southw est Groundw ater Project
2007 Project Activities
• Complete construction of reverse osmosis
treatment plant.
• Complete construction of byproduct
pipeline
Southw est Groundw ater Project
2008 Project Activities
• Initiate startup of Zone B facilities – Winter
– Shallow wells
– Deep wells
– Reverse osmosis treatment plant
– Byproduct pump stations
• Complete and operational Spring
Southw est Groundw ater Project
2009 Project Activities
Southw est Groundw ater Project
Well Drilling Details
• Exploratory Wells
1. Notify City planning staff
2. Notify property owners within 300 feet
3. Complete exploratory drilling (daytime work)
• Conditional Use Permits
1. Prepare site plans
2. Meet with City planning staff
3. Meet with property owners within 300 feet
4. Attend planning commission meeting
• Deep production wells and shallow production
wells
1. Notify property owners within 300 feet
2. Notify potentially affected water right owners
3. Receive indication from water right owners
interested in monitoring water levels
4. Notify City planning staff
5. Complete 24 hour drilling
6. Install well casing, screen and gravel pack
Southw est Groundw ater Project
Well Drilling Details
Southw est Groundw ater Project
Well Drilling Details
7. Complete well development by surging and
pumping
8. Measure surrounding well water levels
9. Complete a 24 hour well pump test
10. Measure surrounding well water levels
11. Turn off well pump
12. Construct surface improvements and install
permanent pump
13. January 2009 – turn on pump
14. Run pumps constantly (except for electrical or
mechanical failure)
Cont.