Loading...
HomeMy WebLinkAboutDERR-2024-007739REVISED FINAL-May 2004 6-1 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Chapter 6 TREATMENT FACILITY 6.1 INTRODUCTION The material presented in this section details the design criteria developed during pilot testing and the resulting capital and operations cost estimates for the following combined Zone B/Lost Use treatment plant alternatives: • Zone B (800 mg/L): Zone B (i.e., produces 800 mg/L TDS) / Shallow Aquifer (i.e., produces 250 mg/L TDS); • Separate Design (August 2003 Agreement): Zone B/Shallow Aquifer (i.e., each source produces 250 mg/L TDS); • Minimum Integrated Design: Zone B RO Facility/Shallow Aquifer RO By-pass (i.e., produces 250 mg/L TDS). Note that this option does not meet the full production objectives of the remediation project since the full annual volume of Lost Use water is not produced. • Integrated Design: Zone B and Deep Aquifer RO Facility/Shallow Aquifer RO By- pass (i.e., produces 250 mg/L TDS). Conveyance and disposal system costs are also presented. As indicated by the options presented above, the District also wishes to quantify the incremental cost of treating the Zone B supply from a finished water TDS of 800 mg/L to 250 mg/L. The information in this section also presents a breakdown of these incremental treatment costs. 6.2 DESIGN CRITERIA Prior to this study, little was known about the Zone B, Deep Aquifer or Shallow Aquifer water supplies and their suitability to provide water for RO treatment. Limited data was available that detailed SDI and turbidity for these supplies. Pilot tests were conducted to determine if fouling would occur and to determine design criteria for required pretreatment, chemical cleaning, and membrane life. Additionally, the District required determination of an appropriate Shallow Aquifer by-pass treatment system. A by-pass treatment system concept was developed and presented previously in Section 3. Design criteria for this system were developed based on water quality data, regulatory requirements, and industry standard practice. Table 6.1 presents design criteria for the various treatment facility alternatives based on the work previously performed by the District and the pilot study data presented in Section 5. REVISED FINAL-May 2004 6-2 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Zone B design criteria are broken down based on the treated water TDS of 800 mg/L and 250 mg/L. The design criteria for the Shallow Aquifer RO systems only result in the production of 250 mg/L water. As indicated in Table 6.1, compared to the Zone B 800 mg/L option, treatment to the 250 mg/L finished water TDS goal requires more Zone B RO capacity. However, blending flows are reduced, thus resulting in the same treated water capacity. Additionally, cleaning chemical RO process flows increase when the finished water TDS goal is lowered to 250 mg/L. These design criteria are all important due to their impact to both capital and operations costs. The Integrated Design alternatives include more Zone B RO treatment and no Shallow Aquifer RO treatment. All by-pass for the Integrated Design alternatives is from the Shallow Aquifer. Additional Deep Aquifer treatment is included for the full Integrated Design option, but excluded from the Minimum Integrated Design option. As indicated in Table 6.1, a Zone B membrane cleaning frequencies and membrane life are assumed to be longer than for the Shallow Aquifer RO systems. This is based upon the results of pilot testing presented in Section 5. High calcium concentrations were thought to have interfered with silica inhibitors. Silica fouling was experienced and required cleaning once every two months. The District plans to conduct more pilot testing to find an inhibitor that will produce less frequent cleanings, however, for the purposes of this estimate, the shorter membrane life and more frequent cleanings are assumed. REVISED FINAL-May 2004 6-3 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.1 Reverse Osmosis Treatment Process Design Criteria Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Zone B 800 mg/L Separate Design (August 2003 Agreement) Minimum Integrated Design Integrated Design Parameter Unit Zone B 800 mg/L Shallow Aquifer Zone B 250 mg/L Shallow Aquifer a Zone B 250 mg/L Shallow Aquifer Zone B 250 mg/L Deep Aquifer Shallow Aquifer Treatment Plant Operation Operating Days per Year days/year 330 330 330 330 330 330 330 330 330 RO Recovery b % 80 85 80 85 80 NA 80 NA Treatment System Recovery c % 86 87 82 87 80 100 91 100 Blend Ratio d % 66 82 91 82 100 NA 100 NA Annual Production AF/yr 3500 2300 3500 2300 3445 750 3890 842 Process Flow Rates Raw Water mgd 4.03 2.57 4.26 2.57 4.25 0.74 4.25 0.56 0.83 Process Feed mgd 2.84 2.17 3.98 2.17 4.25 NA 4.81 NA RO Capacity/Permeate mgd 2.28 1.84 3.18 1.84 3.40 NA 3.85 NA By-pass Water mgd 1.18 0.40 0.28 0.40 0 0.74 0 0.83 Finished Water mgd 3.46 2.24 3.46 2.24 3.40 0.74 3.85 0.83 Concentrate mgd 0.57 0.33 0.80 0.33 0.85 NA 0.96 NA Cartridge Filtration Cartridge Filter Loading Rate RO Feed Blend Water gpm/10-in. gpm/ft2 2.5 NA 2.5 0.125 2.5 NA 2.5 0.125 2.5 NA NA 0.125 2.5 NA NA 0.125 Cartridge Filter Replacement Frequency days 183 183 183 183 183 183 183 183 RO Equipment Pressure Vessel Array 38:14 28:14 48:24 28:14 50:25 NA 56:28 NA Membranes per Vessel No. 7 7 7 7 7 NA 7 NA Flux Rate gfd 16 16 16 16 16 NA 16 NA Cleaning Frequency No./year 3 6 3 6 3 NA 3 NA Membrane Life years 5 1.5 5 1.5 5 NA 5 NA RO Feed Pressure e,f psi 150 145 150 145 150 NA 150 NA Interstage Pump Pressure psi 50 50 50 50 50 NA 50 NA REVISED FINAL-May 2004 6-4 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.1 Reverse Osmosis Treatment Process Design Criteria Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Zone B 800 mg/L Separate Design (August 2003 Agreement) Minimum Integrated Design Integrated Design Parameter Unit Zone B 800 mg/L Shallow Aquifer Zone B 250 mg/L Shallow Aquifer a Zone B 250 mg/L Shallow Aquifer Zone B 250 mg/L Deep Aquifer Shallow Aquifer Decarbonation Decarbonation Efficiency % 90 90 90 90 90 NA 90 NA Decarbonator Loading Rate g gpm/ft2 20 20 20 20 20 NA 20 NA Air to Water Ratio 30:1 30:1 30:1 30:1 30:1 NA 30:1 NA Chemical Feed System Scale Inhibitor Dose h mg/L 4 4.3 4 4.3 4 NA 4 NA Sodium Hypochlorite Dose i mg/L 1 0.5 0.5 0.5 0.5 1.5 0.5 1.5 Sodium Hydroxide Dose j mg/L - - 14.3 14.3 14.3 14.3 14.3 14.3 Membrane Cleaning Chemicals Low pH High pH Silica lbs./year lbs./year lbs./year 2000 2000 NA 6060 6060 6060 5250 5250 NA 6060 6060 6060 6000 6000 NA NA NA NA 6800 6800 NA NA NA NA UV Disinfection System UV Dose mJ/cm2 NA 40 NA 40 NA 40 NA 40 UV Transmittance % NA 90 NA 90 NA 90 NA 90 No. of UV Lamps No./Reactor NA 7 NA 7 NA 14 NA 14 UV Lamp Replacement Freq. hours NA 10,000 NA 10,000 NA 10,000 NA 10,000 UV Electrical Draw kW NA 1.33 NA 1.33 NA 2.66 NA 2.66 UV Cleaning Frequency k No./yr NA TBD NA TBD NA TBD NA TBD UV Cleaning Chemical Demand l lbs/yr NA 280 NA 280 NA 280 NA 280 REVISED FINAL-May 2004 6-5 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.1 Reverse Osmosis Treatment Process Design Criteria Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Zone B 800 mg/L Separate Design (August 2003 Agreement) Minimum Integrated Design Integrated Design Parameter Unit Zone B 800 mg/L Shallow Aquifer Zone B 250 mg/L Shallow Aquifer a Zone B 250 mg/L Shallow Aquifer Zone B 250 mg/L Deep Aquifer Shallow Aquifer Notes: NA Not applicable TBD To be determined a Based on Lost Use blended water TDS of 250 mg/L b FeedRO PermeateRO Q QR= c WaterWell WaterFinished RO Q QR= d () ()PermeateFeed GoalFeed WaterFinished PermeateBlend CC CC Q Qr −−== e Modeled Using RODESIGN V.7.0 (assumes ESPA1 membrane or equivalent) f Feed pressure at ½ of membrane life (i.e., year 2.5 of 5 year membrane life) at fouling rate estimated by pilot testing g Blended Zone B and Lost Use permeate water. h Modeled using Water Wizard KLT V.1.1 i Based on SDS48 hr-Chlorine Demand presented in Table 5.6 j Modeled Using The Rothberg Tamburini and Winsor Model for Water Process and Corrosion Chemistry V. 4.0 k To be determined during start-up testing. l Solution can be re-used in off-line low-pressure UV cleaning. Demand based on other applications of similar quality. Cont’d REVISED FINAL - May 2004 6-6 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Unit costs for consumable items that will be used during the operation of the combined Zone B and Lost Use treatment plant are presented in Table 6.2. It should be noted that cartridge filters for the RO membranes are estimated to be significantly less expensive than those used for the Shallow Aquifer by-pass treatment system. Cartridge filters used for RO pretreatment are of the glass fiber wound variety that will provide basic protection for the RO membranes if there were an up-set in the well field or a failure of a well screen. The by- pass cartridge filters are specially engineered and highly efficient at removing particles within the 2 to 5-µm size range. The filters that are used for the purpose of this estimate are approved in the States of Alaska and Idaho for Giardia and Cryptosporidium removal. Material specification sheets are provided in Appendix C. Included in the unit costs of consumable items in Table 6.2 is a patent royalty fee for the UV disinfection process. The certified UV systems that are currently included in Carollo’s standard specifications are subject to this royalty fee. However, this patent is currently being challenged in several states and may only apply to medium and high pressure UV technologies. Carollo’s specifications include one low pressure UV system that may be exempt from this patent royalty fee. Regardless, this fee has been included in the cost estimate to provide a realistic interpretation of what the operations costs of UV treatment may be. Table 6.2 Operations and Maintenance Unit Costs Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Description Unit Cost Membrane Element Replacement $500 per element Cartridge Filter Replacement $3 per 10-inches of filter length By-pass Cartridge Filter Replacement $355 per filter Electrical Power $0.055 per kW-hr Scale Inhibitor $0.98 per lb. Caustic Soda $0.21 per lb. as NaOH Sodium Hypochlorite a 3.5 kW per lb. Cl2 Membrane Cleaning Chemicals Low pH High pH Silica $2.80 per lb. $3.18 per lb. $4.14 per lb. UV Lamps $200 each UV Cleaning Chemical $5.00 per lb. UV Patent Royalty b $0.015 per 1,000 gallons Notes: a On-site generation of hypochlorite b Patent currently under contest review. Vendors that have validated performance do not hold patent. REVISED FINAL - May 2004 6-7 C:\Documents and Settings\sfuller\Desktop\Section 6.doc 6.3 FACILITY LAYOUT Before capital costs can be estimated, a site plan and facility layout are required to more closely estimate the costs for site work and building materials. Figures 6.1 and 6.2 present the location and site plan of the combined Zone B/Lost Use treatment facility (i.e., as depicted in the Separate Design Option (August 2003 Agreement)). This site is located near the District’s main office on 8215 South 1300 West, West Jordan, Utah. As indicated in Figure 6.1, the planned Zone B/Lost Use treatment plant will be located in the southwest portion of the District’s property, in an area that is currently used as a cattle pasture. This area is assumed to have a similar soils composition as the adjacent area where the maintenance, vehicle storage, and operations buildings are located. Based on a soils study conducted by the District and previous construction in the adjacent area, this site requires over excavation to 20-feet and structural fill under the building foundations due to the potential for liquefaction. Roadways are assumed to be excavated to 1.25-feet and filled to 12-inches with road base and 3-inches of asphalt. These costs were previously unaccounted for in studies commissioned by the District and should be included in the capital cost estimate for the Zone B/Lost Use treatment facility. Figure 6.2 presents a site plan for the planned Zone B/Lost Use treatment facility. This site covers approximately 5.6-acres. Access to the Zone B/Lost Use treatment plant building is provided on the south side for chemical deliveries and equipment maintenance. As indicated in Figure 6.3, the equipment has been placed in the building in such a fashion that the Shallow Aquifer RO treatment and the decarbonation processes may be easily expanded to the north and southwest side of property. A wet well to capture water after decarbonation, blending and post treatment, that would also provide water for the finished water pump station is located sub-grade to the planned facility, under the finished water pumps and decarbonation tower. It should be noted that alternate locations for the placement of this facility have been identified. These sites include the hill located between the Administration building and the North Jordan Canal, and the hill between 1300 West and the Administration building. It may be possible to build a two-story treatment plant into the side of these hills and maximize the use of any hydraulic gradients that occur naturally. Additionally, soils conditions may be better in these locations, which will minimize the site work costs associated with over excavation and structural fill that will be incurred at the site presented in Figures 6.1 and 6.2. These alternatives should be visited during the pre-design phase of this project. REVISED FINAL - May 2004 6-11 C:\Documents and Settings\sfuller\Desktop\Section 6.doc 6.4 CAPITAL COST ESTIMATE Capital costs for the various treatment facility alternatives and the conveyance and by- product water disposal systems are detailed in Tables 6.3 through 6.10 as follows: • Tables 6.3 and 6.4 detail the capital costs associated with the Zone B 800 mg/L TDS alternative; • Tables 6.5 and 6.6 detail the capital costs associated with the Separate Design (August 2003) alternative; • Tables 6.7 and 6.8 detail the capital costs associated with the Minimum Integrated Design alternative; • Tables 6.9 and 6.10 detail the capital costs associated with the Integrated Design alternative. Some of the capital costs presented in these tables are adapted from the District’s previous study in 1999. These costs were adjusted using the Engineering News Record (ENR) 20 City Average Construction Cost Index (CCI). The 1999 costs increased by approximately 8% when this correction is applied. The District should be interested in these indices in order to determine the present day cost of previous capital cost estimates to determine if this project still meets their criteria for participation. All costs are presented in October 2003 dollars. A cost correction for the total capital cost to May 2004 dollars is also provided. Capital costs can be summarized (in May 2004 dollars) by option as follows: • Zone B 800 mg/L: Treatment Plant = $17,315,000 Conveyance System = $27,022,000 Total Project = $44,337,000 • Separate Design: Treatment Plant = $18,672,000 Conveyance System = $27,022,000 Total Project = $45,694,000 • Minimum Integrated Design: Treatment Plant = $14,387,000 Conveyance System = $24,386,000 Total Project = $38,773,000 • Integrated Design: Treatment Plant = $15,469,000 Conveyance System = $24,386,000 Total Project = $39,855,000 REVISED FINAL - May 2004 6-12 C:\Documents and Settings\sfuller\Desktop\Section 6.doc As indicated, the incremental capital cost in treatment from the 800 mg/L TDS to 250 mg/L TDS goal is estimated to vary from approximately minus $5,564,000 to $1,357,000 depending upon the treatment option. It should be noted however that the Minimum Integrated Design does not meet the objectives of the project since the full volume of Lost Use capacity is not produced. Therefore, to meet the objectives of the project, the range of incremental cost is actually minus $4,482,000 to $1,357,000. These costs include the incremental costs for the treatment and required infrastructure for conveyance of raw, finished and by-product water. Integrated Design capital costs are reduced from the Zone B 800 mg/L and Separate design alternatives by using Shallow Aquifer water as the only source of by-pass. Table 6.3 Zone B (800 mg/L) - Treatment Facility Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Building Foundation Structural & Architectural 900 15250 CY SF $400 $100 $360,000 $1,525,000 Electrical 1 1 LS $960,000 $960,000 HVAC/Plumbing 1 LS $400,000 $400,000 Instrumentation 1 LS $625,000 $625,000 RO Equipment = 2.28 + 1.88 4.12 MGD $740,000 $3,049,000 Cartridge Filters 2 EA $40,000 $80,000 Decarbonator 1 LS $300,000 $300,000 Chemical Storage/Feed System Scale Inhibitor On-site Hypochlorite Caustic Soda 2 1 1 LS LS LS $50,000 $120,000 $180,000 $100,000 $120,000 $180,000 By-pass Treatment System Cartridge Filter UV Disinfection 1 1 LS LS $80,000 $150,000 $80,000 $150,000 Product Water Pumps (770 hp) 2 1 LS $160,000 $165,000 Contact Tank (30 minutes) 640 CY $624 $400,000 REVISED FINAL - May 2004 6-13 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.3 Zone B (800 mg/L) - Treatment Facility Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Site Work Over Excavation Structural Fill Paving & Sidewalks Other 17200 16350 125740 1 CY CY SF LS $12 $20 $2.10 $35,000 $207,000 $327,000 $265,000 $35,000 Subtotal $9,328,000 Contractors Overhead & Profit 27% $2,519,000 Construction Cost Subtotal $11,847,000 Design Contingency 10% $1,185,000 Change Order Allowance 5% $593,000 Total Construction Cost $13,625,000 Pre-design & Final Design Engineering 10% $1,185,000 Engineering Services During Construction 5% $593,000 On-site Construction Services & Administration 5% $593,000 Total Engineering Services $2,371,000 TOTAL PROJECT COST ESTIMATE (October 2002) $15,996,000 TOTAL PROJECT COST ESTIMATE (May 2004) 3 $17,315,000 Notes: 1. Does not include standby power or off-site improvements 2. Includes one redundant pump 3. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Cont’d REVISED FINAL - May 2004 6-14 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.4 Zone B (800 mg/L) - Pipeline Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Source Zone B Wells and Pump Houses 7 EA $320,000 $2,240,000 District Lost Use Wells and Pump Houses 4 EA $81,000 $324,000 CDM Raw Water Conveyance Zone B (8 to 16-inch) Lost Use (8 to 12-inch) 52,800 10,000 per foot per foot $64 $43 $3,380,000 $410,000 Carollo CDM Treated Water Pipe (24-inch) 14,000 per foot $130 $1,820,000 Carollo Concentrate Pipe (8-inch) 105,600 per foot $73 $7,741,000 District Construction Cost Subtotal $17,457,000 Construction Cost + 10% Contingency 10% $19,203,000 Construction plus Engineering 30% $24,964,000 TOTAL PROJECT COST ESTIMATE (October 2002) $24,964,000 TOTAL PROJECT COST ESTIMATE (May 2004) 1 $27,022,000 Notes: 1. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Table 6.5 Separate Design (Aug 2003 Agrmt.) - Treatment Plant Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Building Foundation Structural & Architectural 900 15250 CY SF $400 $100 $360,000 $1,525,000 Electrical 1 1 LS $960,000 $960,000 HVAC/Plumbing 1 LS $400,000 $400,000 Instrumentation 1 LS $625,000 $625,000 RO Equipment = 3.14 + 1.88 4.98 MGD $740,000 $3,686,000 Cartridge Filters 2 EA $50,000 $100,000 Decarbonator 1 LS $400,000 $400,000 REVISED FINAL - May 2004 6-15 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.5 Separate Design (Aug 2003 Agrmt.) - Treatment Plant Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Chemical Storage/Feed System Scale Inhibitor On-site Hypochlorite Caustic Soda 2 1 1 LS LS LS $50,000 $120,000 $180,000 $100,000 $120,000 $180,000 By-pass Treatment System Cartridge Filter UV Disinfection 1 1 LS LS $80,000 $125,000 $80,000 $125,000 Product Water Pumps (770 hp) 2 1 LS $165,000 $165,000 Contact Tank (30 minutes) 640 CY $624 $400,000 Site Work Over Excavation Structural Fill Paving & Sidewalks Other 17200 16350 125740 1 CY CY SF LS $12 $20 $2.10 $35,000 $207,000 $327,000 $265,000 $35,000 Subtotal $10,060,000 Contractors Overhead & Profit 27% $2,717,000 Construction Cost Subtotal $12,777,000 Design Contingency 10% $1,278,000 Change Order Allowance 5% $639,000 Total Construction Cost $14,694,000 Pre-design & Final Design Engineering 10% $1,278,000 Engineering Services During Construction 5% $639,000 On-site Construction Services & Administration 5% $639,000 Total Engineering Services $2,556,000 TOTAL PROJECT COST ESTIMATE (October 2002) $17,250,000 TOTAL PROJECT COST ESTIMATE (May 2004) 3 $18,672,000 Notes: 1. Does not include standby power or off-site improvements 2. Includes one redundant pump 3. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Cont’d REVISED FINAL - May 2004 6-16 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.6 Separate Design (Aug 2003 Agrmt.) - Pipeline Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Source Zone B Wells and Pump Houses 7 EA $320,000 $2,240,000 District Lost Use Wells and Pump Houses 4 EA $81,000 $324,000 CDM Raw Water Conveyance Zone B (8 to 16-inch) Lost Use (8 to 12-inch) 52,800 10,000 per foot per foot $64 $43 $3,380,000 $410,000 Carollo CDM Treated Water Pipe (24-inch) 14,000 per foot $130 $1,820,000 Carollo Concentrate Pipe (10-inch) 105,600 per foot $88 $9,283,000 District Construction Cost Subtotal $17,457,000 Construction Cost + 10% Contingency 10% $19,203,000 Construction plus Engineering 30% $24,964,000 TOTAL PROJECT COST ESTIMATE (October 2002) $24,964,000 TOTAL PROEJCT COST ESTIMATE (May 2004) 1 $27,022,000 Notes: 1. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Table 6.7 Minimum Integrated Design - Treatment Plant Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Building Foundation Structural & Architectural 800 13400 CY SF $400 $100 $320,000 $1,340,000 Electrical 1 1 LS $750,000 $750,000 HVAC/Plumbing 1 LS $375,000 $375,000 Instrumentation 1 LS $475,000 $475,000 RO Equipment = 3.40 3.40 MGD $740,000 $2,514,000 Cartridge Filters 2 EA $35,000 $70,000 Decarbonator 1 LS $230,000 $230,000 REVISED FINAL - May 2004 6-17 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.7 Minimum Integrated Design - Treatment Plant Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Chemical Storage/Feed System Scale Inhibitor On-site Hypochlorite Caustic Soda 1 1 1 LS LS LS $50,000 $100,000 $150,000 $50,000 $100,000 $150,000 By-pass Treatment System Cartridge Filter UV Disinfection 1 1 LS LS $120,000 $160,000 $120,000 $160,000 Product Water Pumps (770 hp) 2 1 LS $150,000 $150,000 Contact Tank (30 minutes) 350 CY $624 $219,000 Site Work Over Excavation Structural Fill Paving & Sidewalks Other 13800 13000 125740 1 CY CY SF LS $12 $20 $2.10 $35,000 $166,000 $260,000 $265,000 $35,000 Subtotal $7,749,000 Contractors Overhead & Profit 27% $2,093,000 Construction Cost Subtotal $9,842,000 Design Contingency 10% $985,000 Change Order Allowance 5% $493,000 Total Construction Cost $11,320,000 Pre-design & Final Design Engineering 10% $985,000 Engineering Services During Construction 5% $493,000 On-site Construction Services & Administration 5% $493,000 Total Engineering Services $1,971,000 TOTAL PROJECT COST ESTIMATE (October 2002) $13,291,000 TOTAL PROJECT COST ESTIMATE (May 2004) 3 $14,387,000 Notes: 1. Does not include standby power or off-site improvements 2. Includes one redundant pump 3. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Cont’d REVISED FINAL - May 2004 6-18 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.8 Minimum Integrated Design - Pipeline Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Source Zone B Wells and Pump Houses 7 EA $320,000 $2,240,000 District Lost Use Wells and Pump Houses 2 EA $81,000 $162,000 CDM Raw Water Conveyance Zone B (8 to 16-inch) Lost Use (8 to 12-inch) 52,800 10,000 per foot per foot $64 $43 $3,380,000 $410,000 Carollo CDM Treated Water Pipe (24-inch) 14,000 per foot $130 $1,820,000 Carollo Concentrate Pipe (8-inch) 105,600 per foot $73 $7,741,000 District Construction Cost Subtotal $15,753,000 Construction Cost + 10% Contingency 10% $17,329,000 Construction plus Engineering 30% $22,528,000 TOTAL PROJECT COST ESTIMATE (October 2002) $22,528,000 TOTAL PROJECT COST ESTIMATE (May 2004) 1 $24,386,000 Notes: 1. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Table 6.9 Integrated Design - Treatment Plant Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Building Foundation Structural & Architectural 800 134000 CY SF $400 $100 $320,000 $1,340,000 Electrical 1 1 LS $800,000 $800,000 HVAC/Plumbing 1 LS $375,000 $375,000 Instrumentation 1 LS $500,000 $500,000 RO Equipment = 3.84 3.84 MGD $740,000 $2,846,000 Cartridge Filters 2 EA $35,000 $70,000 Decarbonator 1 LS $270,000 $270,000 REVISED FINAL - May 2004 6-19 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.9 Integrated Design - Treatment Plant Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Chemical Storage/Feed System Scale Inhibitor On-site Hypochlorite Caustic Soda 1 1 1 LS LS LS $50,000 $120,000 $180,000 $50,000 $120,000 $180,000 By-pass Treatment System Cartridge Filter UV Disinfection 1 1 LS LS $120,000 $160,000 $120,000 $160,000 Product Water Pumps (770 hp) 2 1 LS $155,000 $155,000 Contact Tank (30 minutes) 400 CY $624 $250,000 Site Work Over Excavation Structural Fill Paving & Sidewalks Other 13800 13000 125740 1 CY CY SF LS $12 $20 $2.10 $35,000 $166,000 $260,000 $265,000 $35,000 Subtotal $8,332,000 Contractors Overhead & Profit 27% $2,250,000 Construction Cost Subtotal $10,582,000 Design Contingency 10% $1,059,000 Change Order Allowance 5% $530,000 Total Construction Cost $12,171,000 Pre-design & Final Design Engineering 10% $1,059,000 Engineering Services During Construction 5% $530,000 On-site Construction Services & Administration 5% $530,000 Total Engineering Services $2,119,000 TOTAL PROJECT COST ESTIMATE (October 2002) $14,290,000 TOTAL PROJECT COST ESTIMATE (May 2004) 3 $15,469,000 Notes: 1. Does not include standby power or off-site improvements 2. Includes one redundant pump 3. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 Cont’d REVISED FINAL - May 2004 6-20 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.10 Integrated Design - Pipeline Capital Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Classification Quantity Units Unit Cost Extended Cost Source Zone B Wells and Pump Houses 7 EA $320,000 $2,240,000 District Lost Use Wells and Pump Houses 2 EA $81,000 $162,000 CDM Raw Water Conveyance Zone B (8 to 16-inch) Lost Use (8 to 12-inch) 52,800 10,000 per foot per foot $64 $43 $3,380,000 $410,000 Carollo CDM Treated Water Pipe (24-inch) 14,000 per foot $130 $1,820,000 Carollo Concentrate Pipe (8-inch) 105,600 per foot $73 $7,741,000 District Construction Cost Subtotal $15,753,000 Construction Cost + 10% Contingency 10% $17,329,000 Construction plus Engineering 30% $22,528,000 TOTAL PROJECT COST ESTIMATE (October 2002) $22,528,000 TOTAL PROJECT COST ESTIMATE (May 2004) 1 $24,386,000 Notes: 1. ENR 20 City Average CCI (October 2002) = 6526 ENR 20 City Average CCI (May 2004) = 7064 6.5 OPERATIONS AND MAINTENANCE COST ESTIMATE Operations and maintenance (O&M) costs for the various treatment plant alternatives are presented in Table 6.11 and can be summarized (in May 2004 dollars) as follows: • Zone B 800 mg/L: $4,021 per day ($705 per MG) • Separate Design: $4,379 per day ($768 per MG) • Minimum Integrated Design: $3,329 per day ($805 per MG) • Integrated Design: $3,677 per day ($786 per MG) O&M costs for the Zone B and Lost Use treatment systems are based on design criteria and unit costs presented previously in Tables 6.1 and 6.2. REVISED FINAL - May 2004 6-21 C:\Documents and Settings\sfuller\Desktop\Section 6.doc As indicated in Table 6.11, pumping costs represent approximately fifty percent of the total O&M cost. Labor, membrane replacement and chemical costs represent between thirty to forty percent of the remaining O&M cost. This distribution of cost is not uncommon for other RO treatment facilities. Incremental treatment costs from the Zone B 800 mg/L option vary from minus $692 per day to $358 per day. Both the Integrated Design options are less expensive to operate than the Zone B 800 mg/L alternative. This is because no Shallow Aquifer RO treatment is required and all Shallow Aquifer water is used as the sole source of raw water by-pass for blending. It should be noted that the Minimum Integrated Design does not meet the full requirement for annual water production. Therefore, the incremental cost of treatment, for alternatives that meet both the 250 mg/L treatment goal and the annual production requirements is minus $344 per day to $692 per day. It is important to distinguish that the while the Integrate Design alternatives have a lower operating cost, the per unit volume product cost is actually greater for these alternatives. This is because less water is produced from these alternatives. Operations and maintenance is the largest component of cost over the life of an RO treatment plant. Therefore, by finding ways to reduce these costs, the process can become more economical. O&M cost for the Zone B 800 mg/L and Separate Design treatment alternative may be reduced by either lowering the Shallow Aquifer RO recovery from 85% to reduce the silica saturation or by finding an alternate scale inhibitor that prevents silica fouling. The anticipated resulting O&M cost savings would primarily be associated with a reduced membrane replacement and chemical cleaning cost. However, pumping costs would increase when recovery is lowered. Further analysis of to determine estimated costs from a lower Shallow Aquifer RO recovery is required to weigh increased pumping costs versus savings from less cleaning and longer membrane life, but is outside the scope of this study. While pilot tests indicated that the Inhibitor 2 was not successful at controlling scale formation at a recovery rate of 85%, the industry is frequently developing new scale inhibitors that may be able to control scale (i.e., silica) formation at this recovery rate. The District should consider including pilot equipment in their RO treatment equipment procurement contract documents to test the latest developments in the RO industry. An 85% Shallow Aquifer RO recovery would lower the overall O&M costs if scale formation can be successfully controlled. REVISED FINAL - May 2004 6-22 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.11 Zone B/Lost Use Treatment Facility O&M Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Daily Costs (2004 $) Zone B 800 mg/L Separate Design (August 2003 Agreement) Minimum Integrated Design Integrated Design Description Zone B 800 mg/L Shallow Aquifer Total Project Zone B 250 mg/L Shallow Aquifer Total Project Zone B 250 mg/L Shallow Aquifer Total Project Zone B 250 mg/L Deep Aquifer Shallow Aquifer Total Project Well Water Pumping a, b 360 180 540 380 180 560 380 45 425 445 55 500 RO Feed Pumping a 200 145 345 280 145 425 300 NA 300 340 NA 340 Interstage Pumping c 40 30 70 60 30 90 65 NA 65 70 NA 70 Product Water Pumping a, d 610 610 435 495 Concentrate Pumping a, e 180 110 155 NA 155 220 NA 220 Electrical Pumping Costs Cost per MG 1,745 306 1,795 315 1,380 334 1,625 348 General Building Electric Load 79 79 79 79 Decarbonation Blower 25 25 25 25 Electrical Operating Costs (not including pumping) Cost per MG 104 22 10 4 22 104 22 104 22 Cartridge Filters 17 13 30 24 13 37 26 NA 26 29 NA 29 Scale Inhibitor 93 76 169 128 76 204 139 NA 139 156 NA 156 Sodium Hydroxide - 143 NA 103 NA 117 Sodium Hypochlorite f 46 28 NA 28 NA 32 Membrane Chemical Cleaning 36 186 222 95 186 281 109 NA 109 123 NA 123 Chemical Operating Costs Cost per MG 467 82 693 122 405 98 457 98 By-pass Cartridge Filters NA 62 62 NA 62 62 NA 124 124 NA 124 124 By-pass UV Power NA 2 2 NA 2 2 NA 4 4 NA 4 4 By-pass UV Lamp Replacement NA 3 3 NA 3 3 NA 7 7 NA 7 7 By-pass UV Chemical Cleaning NA 4 4 NA 4 4 NA 4 4 NA 4 4 Patent Royalty g NA 6 6 NA 6 6 NA 11 11 NA 12 12 By-pass Operating Costs Cost per MG 77 14 77 14 124 36 151 32 REVISED FINAL - May 2004 6-23 C:\Documents and Settings\sfuller\Desktop\Section 6.doc Table 6.11 Zone B/Lost Use Treatment Facility O&M Cost Estimate Zone B Reverse Osmosis Pilot Study Jordan Valley Water Conservancy District Daily Costs (2004 $) Zone B 800 mg/L Separate Design (August 2003 Agreement) Minimum Integrated Design Integrated Design Description Zone B 800 mg/L Shallow Aquifer Total Project Zone B 250 mg/L Shallow Aquifer Total Project Zone B 250 mg/L Shallow Aquifer Total Project Zone B 250 mg/L Deep Aquifer Shallow Aquifer Total Project Membrane Replacement h 160 368 528 220 368 588 239 239 270 270 Labor i 732 732 732 732 Laboratory Testing 65 65 65 65 General Building Utilities 21 21 21 21 Equipment Replacement Parts and Consumables 283 305 235 252 Indirect Operating Costs Cost per MG 1,628 285 1,710 300 1,291 312 1,340 287 JVWCD Overhead Allocation Cost per MG 100 18 100 18 100 24 100 21 TOTAL COST (w/o pumping) COST PER MG (w/o pumping) 2,276 399 2,584 453 1,949 471 2,052 439 TOTAL COST (with pumping) COST PER MG (with pumping) 4,021 705 4,379 768 3,329 805 3,677 786 Notes a Power cost = $0.055/kW-hr; ηpump = 0.75; ηmotor = 0.9; Hazen & William’s C = 130 (PVC = 150 psi max.) b 30 psi residual pressure at RO WTP c Interstage pumping provided to balance hydraulics, reduce overall system horsepower, lower cleaning frequency, and improve permeate water quality. d Finished water to Jordan Aqueduct, hydraulic gradient = 4700 ft H2O e 8-inch by-product pipe for 800 mg/L; 10-inch by-product pipe for 250 mg/L f On-site generation of hypochlorite g Vendors that have certified (i.e., by DVGW) reactor performance do not hold patent. Patent is currently being challenged. h Interest/Inflation = 2.5% i Includes 2 operators and one supervisor. Cont’d REVISED FINAL - May 2004 6-24 C:\Documents and Settings\sfuller\Desktop\Section 6.doc 6.6 SUMMARY Design criteria, facility layouts and cost estimates were presented in this section based on pilot testing data presenting previously in this report. The incremental costs of RO treatment for a finished water TDS of 800 mg/L to 250 mg/L, for a project that meets all the annual production requirements, range from minus $4,482,000 to $1,357,000 in capital costs and minus $344 per day to $692 per day in operations costs. Integrated Design alternatives present the lowest capital costs of all treatment alternatives, and while they have a lower operating cost, because less water is produced, they have a higher per unit volume treatment cost. The District should consider that additional alternatives exist that hold further potential for reducing both capital and operating costs. During the pre-design phase of this project the District should consider: • Alternate sites for the treatment facility. Locating the treatment plant in a two story structure on the hill to the east or west side of the District’s main office may provide cost savings due to better soils conditions and less site work and also by utilizing the hydraulic gradient of the hill to move water from the RO through the post treatment processes. • Operating the Lost Use treatment facility at a lower recovery. Operating the Shallow Aquifer RO system at a lower recovery may lower O&M costs. These savings are the result of an estimated reduction in chemical cleaning frequency and an extended membrane life. • Conduct further pilot testing to select a more effective scale inhibitor. Operating costs for the Shallow Aquifer RO system are high due to the silica fouling that was experienced during pilot testing. Additional pilot testing may indicate that a more effective scale inhibitor exists and costs can be reduced while still operating at an 85% recovery.