HomeMy WebLinkAboutDAQ-2024-0077371 DAQC-394-24 Site ID 10237 (B1) MEMORANDUM TO: FILE – PACIFICORP – Hunter Power Plant THROUGH: Harold Burge, Major Source Compliance Section Manager FROM: Joseph Randolph, Environmental Scientist DATE: April 29, 2024 SUBJECT: FULL COMPLIANCE EVALUATION, Major, Emery County, FRS #UT0000004901500101 INSPECTION DATE: April 17, 2024 SOURCE LOCATION: 2 Miles South on Utah Highway 10, Castle Dale, Utah MAILING ADDRESS: P.O. Box 569, Castle Dale, Utah 84513 SOURCE CONTACT: Terry Guthrie, Senior Engineer: 435-748-6059 P.O. Box 569, Castle Dale, UT 84513 Jay Howard, Sr. Environmental Analyst OPERATING STATUS: Operating PROCESS DESCRIPTION: PacifiCorp’s Hunter site consists of three coal-fired electric steam generating units. The boiler fuel systems consist of coal handling and fuel oil (diesel) for boiler cold starts after downtime and main boiler flame stabilization: Coal enters the plant via covered conveyors or by trucks from the adjacent Energy West coal prep plant and is poured into coal mills where it is pulverized to a talcum powder consistency. Pipes carry the pulverized coal to the boiler burners where it ignites in a large fireball. Bottom ash left from the coal combustion process (clinkers), collect at the bottom of the boiler, which are crushed and slurried away. Fly ash, also a combustion by-product, is removed by capturing the particulate matter (PM) on electrostatic precipitators (ESP) or a baghouse. The sulfur dioxide remaining in the hot flue gas from the combustion process is removed at the scrubber by neutralizing the acid gases with a slake lime shower. For steam production, water is gradually pre-heated to raise the temperature before it enters the boiler. As the water passes through the steel tubes in the boiler wall, it is transformed to steam at approximately 1000 degrees F and at a pressure of 2,400 psi. This high-pressure steam blows on fan blades of the turbine generator, spinning them at 3600 0 ( 8 2 RPM. The generator, a magnet spinning within a coil of wire, turns the energy of motion into electricity. Transformers step up voltage from 24,000 to 345,000 volts, first to the step-up unit on site and then for transmission to distant recipients. The used boiler steam is condensed, stored, and recycled. Cooling water lowers the heat of the steam at the condenser and is carried to the cooling towers where it is further cooled by evaporation. The facility has continuous emission monitors (CEM) and continuous opacity monitoring (COM) in the emission exit stacks. Further, a fugitive dust plan is in effect to control fugitive dust emissions at the coal storage and handling areas, landfill, and on access roads. APPLICABLE REGULATIONS: Title V Permit #1500101004, last revised November 19, 2021 NSPS (Part 60), A: General Provisions NSPS (Part 60), D: Standards of Performance for Fossil-Fuel-Fired Steam Generators for Which Construction is Commenced After August 17, 1971 NSPS (Part 60), Y: Standards of Performance for Coal Preparation and Processing Plants NSPS (Part 60), IIII: Standards of Performance for Compression Ignition Internal Combustion Engines (Part 64) Compliance Assurance Monitoring MACT (Part 63), A: General Provisions MACT (Part 63), ZZZZ: National Emissions Standards for Hazardous Air Pollution for Stationary Reciprocating Internal Combustion Engines MACT (Part 63), UUUUU: National Emissions Standards for Hazardous Air Pollution: Coal and Oil- Fired Electric Utility Steam Generating Units SECTION I: GENERAL PROVISIONS I.A Federal Enforcement. All terms and conditions in this permit, including those provisions designed to limit the potential to emit, are enforceable by the EPA and citizens under the Clean Air Act of 1990 (CAA) except those terms and conditions that are specifically designated as "State Requirements". (R307-415-6b) Status: Not evaluated. This is a statement of fact and not an inspection item. I.B Permitted Activity(ies). Except as provided in R307-415-7b(1), the permittee may not operate except in compliance with this permit. (See also Provision I.E, Application Shield) Status: In compliance. See status of each condition below for more specific details. 3 I.C Duty to Comply. I.C.1 The permittee must comply with all conditions of the operating permit. Any permit noncompliance constitutes a violation of the Air Conservation Act and is grounds for any of the following: enforcement action; permit termination; revocation and reissuance; modification; or denial of a permit renewal application. (R307-415-6a(6)(a)) I.C.2 It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit. (R307-415-6a(6)(b)) I.C.3 The permittee shall furnish to the Director, within a reasonable time, any information that the Director may request in writing to determine whether cause exists for modifying, revoking and reissuing, or terminating this permit or to determine compliance with this permit. Upon request, the permittee shall also furnish to the Director copies of records required to be kept by this permit or, for information claimed to be confidential, the permittee may furnish such records directly to the EPA along with a claim of confidentiality. (R307-415-6a(6)(e)) I.C.4 This permit may be modified, revoked, reopened, and reissued, or terminated for cause. The filing of a request by the permittee for a permit modification, revocation and reissuance, or termination, or of a notification of planned changes or anticipated noncompliance shall not stay any permit condition, except as provided under R307-415- 7f(1) for minor permit modifications. (R307-415-6a(6)(c)) Status: In compliance. It appears that all conditions have been complied with. I.D Permit Expiration and Renewal. I.D.1 This permit is issued for a fixed term of five years and expires on the date shown under "Enforceable Dates and Timelines" at the front of this permit. (R307-415-6a(2)) I.D.2 Application for renewal of this permit is due on or before the date shown under "Enforceable Dates and Timelines" at the front of this permit. An application may be submitted early for any reason. (R307-415-5a(1)(c)) I.D.3 An application for renewal submitted after the due date listed in I.D.2 above shall be accepted for processing, but shall not be considered a timely application and shall not relieve the permittee of any enforcement actions resulting from submitting a late application. (R307-415-5a(5)) I.D.4 Permit expiration terminates the permittee's right to operate unless a timely and complete renewal application is submitted consistent with R307-415-7b (see also Provision I.E, Application Shield) and R307-415-5a(1)(c) (see also Provision I.D.2). (R307-415-7c(2)) Status: In compliance. This permit was revised November 19, 2021, and expires September 4, 2025. The application for renewal deadline has not passed (March 25, 2025). 4 I.E Application Shield. If the permittee submits a timely and complete application for renewal, the permittee's failure to have an operating permit will not be a violation of R307-415, until the Director takes final action on the permit renewal application. In such case, the terms and conditions of this permit shall remain in force until permit renewal or denial. This protection shall cease to apply if, subsequent to the completeness determination required pursuant to R307- 415-7a(3), and as required by R307-415-5a(2), the applicant fails to submit by the deadline specified in writing by the Director any additional information identified as being needed to process the application. (R307-415-7b(2)) Status: In compliance. This permit was issued November 19, 2021, and expires September 4, 2025. The application for renewal deadline has not passed. I.F Severability. In the event of a challenge to any portion of this permit, or if any portion of this permit is held invalid, the remaining permit conditions remain valid and in force. (R307-415-6a(5)) Status: Not evaluated. This is a statement of fact and not an inspection item. I.G Permit Fee. I.G.1 The permittee shall pay an annual emission fee to the Director consistent with R307-415-9. (R307-415-6a(7)) I.G.2 The emission fee shall be due on October 1 of each calendar year or 45 days after the source receives notice of the amount of the fee, whichever is later. (R307-415-9(4)(a)) Status: In compliance. Permit fees have been paid as invoiced. I.H No Property Rights. This permit does not convey any property rights of any sort, or any exclusive privilege. (R307-415-6a(6)(d)) Status: Not evaluated. This is a statement of fact and not an inspection item. I.I Revision Exception. No permit revision shall be required, under any approved economic incentives, marketable permits, emissions trading and other similar programs or processes for changes that are provided for in this permit. (R307-415-6a(8)) Status: Not evaluated. This is a statement of fact and not an inspection item. I.J Inspection and Entry. I.J.1 Upon presentation of credentials and other documents as may be required by law, the permittee shall allow the Director or an authorized representative to perform any of the following: 5 I.J.1.a Enter upon the permittee's premises where the source is located or emissions related activity is conducted, or where records are kept under the conditions of this permit. (R307-415-6c(2)(a)) I.J.1.b Have access to and copy, at reasonable times, any records that must be kept under the conditions of this permit. (R307-415-6c(2)(b)) I.J.1.c Inspect at reasonable times any facilities, equipment (including monitoring and air pollution control equipment), practice, or operation regulated or required under this permit. (R307-415-6c(2)(c)) I.J.1.d Sample or monitor at reasonable times substances or parameters for the purpose of assuring compliance with this permit or applicable requirements. (R307-415- 6c(2)(d)) I.J.2 Any claims of confidentiality made on the information obtained during an inspection shall be made pursuant to Utah Code Ann. Section 19-1-306. (R307-415-6c(2)(e)) Status: In compliance. Entry into the source was allowed for inspection and a records review. I.K Certification. Any application form, report, or compliance certification submitted pursuant to this permit shall contain certification as to its truth, accuracy, and completeness, by a responsible official as defined in R307-415-3. This certification shall state that, based on information and belief formed after reasonable inquiry, the statements and information in the document are true, accurate, and complete. (R307-415-5d) Status: In compliance. All applications, forms, reports, and compliance certifications submitted pursuant to this permit contain certification as to truth, accuracy, and completeness by a responsible official. I.L Compliance Certification. I.L.1 Permittee shall submit to the Director an annual compliance certification, certifying compliance with the terms and conditions contained in this permit, including emission limitations, standards, or work practices. This certification shall be submitted no later than the date shown under "Enforceable Dates and Timelines" at the front of this permit, and that date each year following until this permit expires. The certification shall include all the following (permittee may cross-reference this permit or previous reports): (R307-415-6c(5)) I.L.1.a The identification of each term or condition of this permit that is the basis of the certification; I.L.1.b The identification of the methods or other means used by the permittee for determining the compliance status with each term and condition during the certification period. Such methods and other means shall include, at a minimum, the monitoring and related recordkeeping and reporting requirements in this permit. If necessary, the permittee also shall identify any other material 6 information that must be included in the certification to comply with section 113(c)(2) of the Act, which prohibits knowingly making a false certification or omitting material information; I.L.1.c The status of compliance with the terms and conditions of the permit for the period covered by the certification, including whether compliance during the period was continuous or intermittent. The certification shall be based on the method or means designated in Provision I.L.1.b. The certification shall identify each deviation and take it into account in the compliance certification. The certification shall also identify as possible exceptions to compliance any periods during which compliance is required and in which an excursion or exceedance as defined under 40 CFR Part 64 occurred; and I.L.1.d Such other facts as the Director may require to determine the compliance status. I.L.2 The permittee shall also submit all compliance certifications to the EPA, Region VIII, at the following address or to such other address as may be required by the Director: (R307- 415- 6c(5)(d)) Environmental Protection Agency, Region VIII Office of Enforcement, Compliance and Environmental Justice (mail code 8ENF) 1595 Wynkoop Street Denver, CO 80202-1129 Status: In compliance. The most recent annual certification was received March 29, 2024 (due date of April 1, 2024). The certification was reviewed by DAQ and found in compliance with the requirements of this condition. I.M Permit Shield. I.M.1 Compliance with the provisions of this permit shall be deemed compliance with any applicable requirements as of the date of this permit, provided that: I.M.1.a Such applicable requirements are included and are specifically identified in this permit, or (R307-415-6f(1)(a)) I.M.1.b Those requirements not applicable to the source are specifically identified and listed in this permit. (R307-415-6f(1)(b)) I.M.2 Nothing in this permit shall alter or affect any of the following: I.M.2.a The emergency provisions of Utah Code Ann. Section 19-1-202 and Section 19- 2- 112, and the provisions of the CAA Section 303. (R307-415-6f(3)(a)) I.M.2.b The liability of the owner or operator of the source for any violation of applicable requirements under Utah Code Ann. Section 19-2-107(2)(a)(xiii) and Section 19- 2-110 prior to or at the time of issuance of this permit. (R307-415-6f(3)(b) I.M.2.c The applicable requirements of the Acid Rain Program, consistent with the CAA Section 408(a). (R307-415-6f(3)(c)) 7 I.M.2.d The ability of the Director to obtain information from the source under Utah Code Ann. Section 19-2-120, and the ability of the EPA to obtain information from the source under the CAA Section 114. (R307-415-6f(3)(d)) Status: Section III contains requirements determined to be not applicable to this source in accordance with Provision I.M. I.N Emergency Provision. I.N.1 An "emergency" is any situation arising from sudden and reasonably unforeseeable events beyond the control of the source, including acts of God, which situation requires immediate corrective action to restore normal operation, and that causes the source to exceed a technology-based emission limitation under this permit, due to unavoidable increases in emissions attributable to the emergency. An emergency shall not include noncompliance to the extent caused by improperly designed equipment, lack of preventive maintenance, careless or improper operation, or operator error. (R307-415-6g(1)) I.N.2 An emergency constitutes an affirmative defense to an action brought for noncompliance with such technology-based emission limitations if the affirmative defense is demonstrated through properly signed, contemporaneous operating logs, or other relevant evidence that: I.N.2.a An emergency occurred and the permittee can identify the causes of the emergency. (R307-415-6g(3)(a)) I.N.2.b The permitted facility was at the time being properly operated. (R307-415- 6g(3)(b)) I.N.2.c During the period of the emergency the permittee took all reasonable steps to minimize levels of emissions that exceeded the emission standards, or other requirements in this permit. (R307-415-6g(3)(c)) I.N.2.d The permittee submitted notice of the emergency to the Director within two working days of the time when emission limitations were exceeded due to the emergency. This notice must contain a description of the emergency, any steps taken to mitigate emissions, and corrective actions taken. This notice fulfills the requirement of Provision I.S.2.c below. (R307-415-6g(3)(d)) I.N.3 In any enforcement proceeding, the permittee seeking to establish the occurrence of an emergency has the burden of proof. (R307-415-6g(4)) I.N.4 This emergency provision is in addition to any emergency or upset provision contained in any other section of this permit. (R307-415-6g(5)) Status: In compliance. No emergency events were recorded or reported during the 12-month period preceding this inspection. 8 I.O Operational Flexibility. Operational flexibility is governed by R307-415-7d(1). Status: Not evaluated. This is a statement of fact and not an inspection item. I.P Off-permit Changes. Off-permit changes are governed by R307-415-7d(2). Status: Not evaluated. This is a statement of fact and not an inspection item. I.Q Administrative Permit Amendments. Administrative permit amendments are governed by R307-415-7e. Status: Not evaluated. This is a statement of fact and not an inspection item. I.R Permit Modifications. Permit modifications are governed by R307-415-7f. Status: Not evaluated. This is a statement of fact and not an inspection item. I.S Records and Reporting. I.S.1 Records. I.S.1.a The records of all required monitoring data and support information shall be retained by the permittee for a period of at least five years from the date of the monitoring sample, measurement, report, or application. Support information includes all calibration and maintenance records, all original strip-charts or appropriate recordings for continuous monitoring instrumentation, and copies of all reports required by this permit. (R307-415-6a(3)(b)(ii)) I.S.1.b For all monitoring requirements described in Section II, Special Provisions, the source shall record the following information, where applicable: (R307-415- 6a(3)(b)(i)) I.S.1.b.1 The date, place as defined in this permit, and time of sampling or measurement. I.S.1.b.2 The date analyses were performed. I.S.1.b.3 The company or entity that performed the analyses. I.S.1.b.4 The analytical techniques or methods used. I.S.1.b.5 The results of such analyses. 9 I.S.1.b.6 The operating conditions as existing at the time of sampling or measurement. I.S.1.c Additional record keeping requirements, if any, are described in Section II, Special Provisions. I.S.2 Reports. I.S.2.a Monitoring reports shall be submitted to the Director every six months, or more frequently if specified in Section II. All instances of deviation from permit requirements shall be clearly identified in the reports. (R307-415-6a(3)(c)(i)) I.S.2.b All reports submitted pursuant to Provision I.S.2.a shall be certified by a responsible official in accordance with Provision I.K of this permit. (R307-415- 6a(3)(c)(i)) I.S.2.c The Director shall be notified promptly of any deviations from permit requirements including those attributable to upset conditions as defined in this permit, the probable cause of such deviations, and any corrective actions or preventative measures taken. Prompt, as used in this condition, shall be defined as written notification within the number of days shown under "Enforceable Dates and Timelines" at the front of this permit. Deviations from permit requirements due to breakdowns shall be reported in accordance with the provisions of R307-107. (R307-415-6a(3)(c)(ii)) I.S.3 Notification Addresses. I.S.3.a All reports, notifications, or other submissions required by this permit to be submitted to the Director are to be sent to the following address or to such other address as may be required by the Director: Utah Division of Air Quality P.O. Box 144820 Salt Lake City, UT 84114-4820 Phone: 801-536-4000 I.S.3.b All reports, notifications or other submissions required by this permit to be submitted to the EPA should be sent to one of the following addresses or to such other address as may be required by the Director: For annual compliance certifications: Environmental Protection Agency, Region VIII Office of Enforcement, Compliance and Environmental Justice (mail code 8ENF) 1595 Wynkoop Street Denver, CO 80202-1129 10 For reports, notifications, or other correspondence related to permit modifications, applications, etc.: Environmental Protection Agency, Region VIII Air Permitting and Monitoring Branch (mail code 8ARD-PM) 1595 Wynkoop Street Denver, CO 80202-1129 Phone: 303-312-6927 Status: In compliance. Records are kept as required. Monitoring reports have been submitted every six months. Deviation reports have been submitted when necessary. I.T Reopening for Cause. I.T.1 A permit shall be reopened and revised under any of the following circumstances: I.T.1.a New applicable requirements become applicable to the permittee and there is a remaining permit term of three or more years. No such reopening is required if the effective date of the requirement is later than the date on which this permit is due to expire, unless the terms and conditions of this permit have been extended pursuant to R307-415-7c(3), application shield. (R307-415-7g(1)(a)) I.T.1.b The Director or EPA determines that this permit contains a material mistake or that inaccurate statements were made in establishing the emissions standards or other terms or conditions of this permit. (R307-415-7g(1)(c)) I.T.1.c EPA or the Director determines that this permit must be revised or revoked to assure compliance with applicable requirements. (R307-415-7g(1)(d)) I.T.1.d Additional applicable requirements are to become effective before the renewal date of this permit and are in conflict with existing permit conditions. (R307-415- 7g(1)(e)) I.T.2 Additional requirements, including excess emissions requirements, become applicable to a Title IV affected source under the Acid Rain Program. Upon approval by EPA, excess emissions offset plans shall be deemed to be incorporated into this permit. (R307-415- 7g(1)(b)) I.T.3 Proceedings to reopen and issue a permit shall follow the same procedures as apply to initial permit issuance and shall affect only those parts of this permit for which cause to reopen exists. (R307-415-7g(2)) Status: Not evaluated. This is a statement of fact and not an inspection item. I.U Inventory Requirements. An emission inventory shall be submitted in accordance with the procedures of R307- 150, Emission Inventories. (R307-150) Status: In compliance. Emission inventories have been submitted as required. 11 I.V Title IV and Other, More Stringent Requirements Where an applicable requirement is more stringent than an applicable requirement of regulations promulgated under Title IV of the Act, Acid Deposition Control, both provisions shall be incorporated into this permit. (R307-415-6a(1)(b)) Status: Not evaluated. This is a statement of fact and not an inspection item. SECTION II: SPECIAL PROVISIONS II.A Emission Unit(s) Permitted to Discharge Air Contaminants. (R307-415-4(3)(a) and R307-415-4(4)) II.A.1 Permitted Source Source-wide II.A.2 Steam Generating Unit #1 (Emission unit #1) Nominal 480 MW gross capacity dry bottom, tangentially-fired boiler fired on subbituminous & bituminous coal using distillate fuel oil during start-up & flame stabilization. System is equipped with a low NOx burner/overfire air system (OFA), baghouse and SO2 Wet FGD (WFGD) scrubber with no scrubber bypass. NSPS D II.A.3 Steam Generating Unit #2 (Emission unit #2) Nominal 480 MW gross capacity dry bottom, tangentially-fired boiler fired on subbituminous & bituminous coal using distillate fuel oil during start-up & flame stabilization. System is equipped with a low NOx burner/OFA, baghouse and SO2 WFGD scrubber (WFGD) with no scrubber bypass. NSPS D II.A.4 Subpart D Boilers, Units #1 & #2 (Emission unit #4) Steam generating Units #1 and #2. II.A.5 Steam Generating Unit #3 (Emission unit #3) Nominal 495 MW gross capacity dry bottom, wall-fired boiler fired on subbituminous & bituminous coal using distillate fuel oil during start-up & flame stabilization. System is equipped with baghouse & SO2 FGD scrubber, and a low NOx burner/OFA. NSPS Da II.A.6 Circulating Water Cooling Tower for Unit #1 (Emission unit #7) Cooling tower for steam generating boiler #1. No unit-specific applicable requirements. II.A.7 Circulating Water Cooling Tower for Unit #2 (Emission unit #8) Cooling tower for steam generating boiler #2. No unit-specific applicable requirements. II.A.8 Circulating Water cooling Tower for Unit #3 (Emission unit #9) Cooling tower for steam generating boiler #3. No unit-specific applicable requirements. II.A.9 Coal Pile (Emission unit #10) Coal pile operations and associated fugitive emissions and fugitive dust No unit-specific applicable requirements. II.A.10 Coal Conveyors (Emission unit #11) Coal transfer operations via conveyors. 12 II.A.11 Unpaved Ash Haul Road (Emission unit #13a) Dirt haul road for ash disposal. No unit-specific applicable requirements. II.A.12 Paved Ash Haul Road (Emission unit #13b) Paved haul road for disposal of ash. No unit-specific applicable requirements. II.A.13 Ash Landfill (Emission unit #14) Ash landfill operations and associated fugitive emissions and fugitive dust. No unit-specific applicable requirements. II.A.14 #1 Emergency Diesel Generator for Unit #1 (Emission unit #15) Emergency diesel generator (1050 hp) for Unit #1, Constructed prior to December 19, 2002. No unit- specific applicable requirements. II.A.15 #2 Emergency Diesel Generator for Unit #2 (Emission unit #16) Emergency diesel generator (1050 hp) for Unit #2, Constructed prior to December 19, 2002. No unit-specific applicable requirements. II.A.16 #3 Emergency Diesel Generator for Unit #3 (Emission unit #17) Emergency diesel generator (915 hp) for Unit #3, Constructed prior to December 19, 2002. No unit- specific applicable requirements. II.A.17 #1 Emergency Diesel Fire Pump #1 (Emission unit #18) Emergency diesel fire pump #1 (229 hp). It is Tier 3 certified and was installed on December 1, 2011). Subject to 40 CFR 60 Subpart IIII. II.A.18 #2 Emergency Diesel Fire Pump #2 (Emission unit #19) Emergency diesel fire pump #2 (235hp). Constructed prior to December 19, 2002. Subject to NESHP ZZZZ II.A.19 Coal Silo System Exhauster for Unit #1 (Emission unit #21) Exhauster and centrifugal dust collector for Unit #1 coal silos distribution system. No unit- specific applicable requirements. II.A.20 Coal Silo System Exhauster for Unit #2 (Emission unit #22) Exhauster and centrifugal dust collector for Unit #2 coal silo distribution system. No unit-specific applicable requirements. II.A.21 Coal Silo System Exhauster for Unit #3 (Emission unit #23) Exhauster and centrifugal dust collector for Unit #3 coal silo distribution system. No unit-specific applicable requirements. II.A.22 Lime Silo Bin Vents (water treatment plant) (Emission unit #24) Bin vent dust collectors for lime storage silos for water treatment plant. No unit-specific applicable requirements. II.A.23 Lime Silo Bin Vents (SO2 scrubber) (Emission unit #27) Bin vent dust collectors for scrubber lime silos for Units #1, #2, and #3. No unit-specific applicable requirements. 13 II.A.24 Distillate Fuel Oil Tanks (Emission unit #28) Four 70,000-gallon tanks and the day tanks for the emergency diesel generators and fire pumps. No unit- specific applicable requirements. II.A.25 Lube Oil Storage Tanks (Emission unit #29) Four 10,000-gallon tanks that store lubricating oil. No unit-specific applicable requirements. II.A.26 Oil Storage Area (Emission unit #30) Storage area for oil contained in closed 55-gallon drums. No unit-specific applicable requirements. II.A.27 Electro-hydraulic Control Reservoirs (Emission unit #31) Three 400-gallon hydraulic oil reservoirs. No unit-specific applicable requirements. II.A.28 Paved Access Road and Parking Area (Emission unit #32) Paved access road from the plant entrance to the administration building and parking area. No unit- specific applicable requirements. II.A.29 Cold Degreasing Operations (Emission unit #33) "Bench-top" cold degreasing units using "Safety-Kleen" or other comparable degreasing agents. No unit- specific applicable requirements. II.A.30 Miscellaneous Electrical Equipment (Emission unit #34) Fugitive emission units including transformer insulating oil. No unit-specific applicable requirements. II.A.31 Water Treatment Chemical Tanks (Emission unit #35) Tank storage including aluminum sulfate, lime, sodium sulfite, soda ash, calcium hypochlorite, sodium hydroxide, anti-scale, aqueous ammonia. No unit-specific applicable requirements. II.A.32 Paint Storage Area (Emission unit #37) Various storage areas for sealed paint containers. No unit-specific applicable requirements. II.A.33 Boiler Feed Pump Lube Oil Conditioners (Emission unit #41) Boiler feed pump lube oil conditioners. No unit-specific applicable requirements. II.A.34 Lube Oil Conditioners (Emission unit #42) Lube oil conditioners with vapor extractors. No unit-specific applicable requirements. II.A.35 Lube Oil Reservoirs (Emission unit #43) Lube oil reservoirs with vapor extractors. No unit-specific applicable requirements. II.A.36 Diesel Refueling Stations and Storage Tanks (Emission unit #44) Three 5,200-gallon aboveground diesel tanks and dispensing equipment to refuel vehicles and mobile equipment. No unit-specific applicable requirements. II.A.37 Truck Mounted Vacuum System (Emission unit #45) Mobile truck mounted vacuum to clean up spilled material such as ash. No unit-specific applicable requirements. 14 II.A.38 Ash Unloader for Unit #1 (Emission unit #46) Equipment for unloading ash from silos and into trucks for transport to the ash landfill. No unit- specific applicable requirements. II.A.39 Ash Unloader for Unit #2 (Emission unit #47) Equipment for unloading ash from silos and into trucks for transport to the ash landfill. No unit- specific applicable requirements. II.A.40 Ash Unloader for Unit #3 (Emission unit #48) Equipment for unloading ash from silos and into trucks for transport to the ash landfill. No unit- specific applicable requirements. II.A.41 Unleaded Gasoline Refueling Station and Storage Tank (Emission unit #39) Gasoline refueling for fleet vehicles from a 5,200-gallon aboveground tank. No unit-specific applicable requirements. II.A.42 Gypsum Off-loading Conveyor (Emission unit #49) Conveyor for off-loading spent reagent from scrubber system along with fabric control system for control of fugitive emissions. II.A.43 Refined Coal System (Emission unit #50) A refined coal system will treat the coal with chemical M45-PC-A, including two storage silos, conveyors, feed hoppers, product totes, pumps, piping and spray equipment. Status: In compliance. No unapproved equipment was observed. II.a.11 haul road is paved, and the only unpaved areas are part of an ash pile. II.A.32 Paint storage area no longer used as all paint work is contracted out. II.B Requirements and Limitations The following emission limitations, standards, and operational limitations apply to the permitted facility as indicated: II.B.1 Conditions on permitted source (Source-wide). II.B.1.a Condition: The permittee shall not discharge into the atmosphere from any abrasive blasting any air contaminant for a period or periods aggregating more than three minutes in any one hour which is a shade or density darker than 40% opacity. [R307-206]. [R307-206] II.B.1.a.1 Monitoring: Visible emission evaluation shall be conducted every six months if abrasive blasting operations are conducted. Visible emission evaluation of abrasive blasting operations shall be conducted in accordance with the following provisions: (a) Visible emissions shall be measured using EPA Method 9. Visible emissions from intermittent sources shall use procedures similar to Method 9, but the requirement for observations to be made at 15 second intervals over a six-minute period shall not apply. 15 (b) Emissions from unconfined blasting shall be read at the densest point of the emission after a major portion of the spent abrasive has fallen out, at a point not less than five feet nor more than twenty-five feet from the impact surface from any single abrasive blasting nozzle. (c) Emissions from unconfined blasting employing multiple nozzles shall be judged as a single source unless it can be demonstrated by the owner or operator that each nozzle, evaluated separately, meets the emission and performance standards provided for in R307-206. (d) Emissions from confined blasting shall be read at the densest point after the air contaminant leaves the enclosure. II.B.1.a.2 Recordkeeping: Results of monitoring shall be maintained in accordance with Provision I.S.1 of this permit. II.B.1.a.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. Only confined abrasive blasting was conducted during the 12-month period preceding this inspection. Records have been kept. II.B.1.b Condition: At all times, including periods of startup, shutdown, and malfunction, the permittee shall, to the extent practicable, maintain and operate any permitted plant equipment, including associated air pollution control equipment, in a manner consistent with good air pollution control practice for minimizing emissions. Determination of whether acceptable operating and maintenance procedures are being used will be based on information available to the Director which may include, but is not limited to, monitoring results, opacity observations, review of operating and maintenance procedures, and inspection of the source. [AO DAQE-AN102370028-18 and 40 CFR 60.11(d)]. [40 CFR 60, R307-401-8(2)] II.B.1.b.1 Monitoring: Records required for this permit condition will serve as monitoring. II.B.1.b.2 Recordkeeping: Records documenting scheduled and unscheduled maintenance shall be maintained. A copy of all manufacturers' operating instructions or established maintenance practices for pollution control equipment and pollution emitting equipment shall be kept on site. These instructions shall be available to all employees who operate the equipment and shall be made available to compliance inspectors upon their request. 16 II.B.1.b.3 Reporting: In addition to the reports required in Section I of this permit, the following reports shall be submitted: (a) An annual projection of planned outages for steam boilers and associated pollution control equipment shall be submitted to the Director not later than January 30th for each calendar year. (b) Changes to the schedule of planned outages shall be reported to the Director within 96 hours after the start of the outage. (c) Maintenance outages shall be reported promptly or according to other applicable reporting criteria in Provision I.S. Status: In compliance. The facility appeared to be maintained in a manner consistent with good air pollution control practices for minimizing emissions. A preventative work order system is in place utilizing SAP software. Annual projections of planned outages have been submitted. II.B.1.c Condition: Visible fugitive dust emissions from haul-road traffic and mobile equipment in operational areas shall not exceed 20% opacity. [AO DAQE-AN102370028-18]. [R307-401-8] II.B.1.c.1 Monitoring: Adherence to the most recently approved fugitive dust control plan shall be monitored to demonstrate that appropriate measures are being implemented to control fugitive dust. Visible emission observation shall be performed at the frequency as required in the most recently approved fugitive dust control plan to assure compliance of the 20% opacity limitation. II.B.1.c.2 Recordkeeping: Records of measures as required in the fugitive dust control plan for minimizing fugitive dust and the results of opacity observations shall be maintained as described in Provision I.S.1 of this permit. II.B.1.c.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. The facility contracts out road watering and maintains records of applications. Records indicated watering during dry conditions of about one load every fifteen minutes to one half hour. The most current dust plan is dated January 17, 2013. 17 II.B.1.d Condition: A Risk Management Plan (RMP) developed in accordance with 40 CFR Part 68 shall be submitted to the United States Environmental Protection Agency not later than the applicable date in 40 CFR 68. [40 CFR Part 68]. [40 CFR 68] II.B.1.d.1 Monitoring: A copy of the Risk Management Plan shall be available upon request along with a copy of the transmittal letter to EPA. II.B.1.d.2 Recordkeeping: A copy of the Risk Management Plan shall be available to the Director upon request along with a copy of the transmittal letter to EPA. II.B.1.d.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: Not applicable. The facility is no longer required to keep a Risk Management Plan. Any additional details should be obtained from the US EPA. II.B.1.e Condition: The permittee shall comply with the applicable requirements for recycling and emission reduction for class I and class II refrigerants pursuant to 40 CFR 82, Subpart F - Recycling and Emissions Reduction. [40 CFR 82.150(b)]. [40 CFR 82 Subpart F] II.B.1.e.1 Monitoring: The permittee shall certify, in the annual compliance statement required in Section I of this permit, its compliance status with the requirements of 40 CFR 82, Subpart F. II.B.1.e.2 Recordkeeping: All records required in 40 CFR 82; Subpart F shall be maintained consistent with the requirements of Provision S.1 in Section I of this permit. II.B.1.e.3 Reporting: All reports required in 40 CFR 82; Subpart F shall be submitted as required. There are no additional reporting requirements except as outlined in Section I of this permit. Status: In compliance. The permittee certified compliance with this condition in the most recent certification. All refrigerant work is contracted out. 18 II.B.1.f Condition: Sulfur content of the fuel oil or diesel combusted shall be no greater than 0.0015 percent by weight. [AO DAQE-AN102370028-18]. [R307-401-8] II.B.1.f.1 Monitoring: The following specifications shall be recorded for each purchase of fuel: weight percent sulfur, gross heating value (Btu per unit volume), and density. All specifications shall be ascertained in accordance with methods of American Society for Testing and Materials. Sulfur content in lbs/MMBtu shall be determined by the following equation: S lbs/MMBtu = [(Weight percent sulfur/100) x Density (lb/gal)] / [(gross heating value (Btu/gal)) x (1 MMBtu/1,000,000 Btu)] The permittee may obtain the above specifications by testing each purchase of fuel in accordance with the required methods; by inspection of the specifications provided by the vendor for each purchase of fuel; or by inspection of summary documentation of the fuel sulfur content from the vendor, provided that the above specifications are available from the vendor for each purchase if requested. II.B.1.f.2 Recordkeeping: The records required for monitoring shall be maintained as described by Provision S.1 in Section I of this permit. II.B.1.f.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. Monthly certifications from the vendor (Sinclair’s Wyoming refinery) are kept on record and indicated compliance. II.B.1.g Condition: Visible emissions shall be no greater than 20 percent opacity for all emission units unless otherwise noted in this permit and for diesel engines as described in R307-201-3. [R307-201-3]. [R307-201-3] II.B.1.g.1 Monitoring: A visual opacity survey of each affected emission unit shall be performed on a monthly basis by an individual trained on the observation procedures of 40 CFR 60, Appendix A, Method 9. If visible emissions other than steam are observed from an emission unit, an opacity determination of that emission unit shall be performed by a certified observer within 24 hours of the initial survey. The opacity determination shall be performed in accordance with 40 CFR 60, Appendix A, Method 9. If opacity exceeds the limit, maintenance shall be performed on the affected unit to correct the problem. 19 II.B.1.g.2 Recordkeeping: A log of the visual opacity survey(s) shall be maintained in accordance with Provision I.S.1 of this permit. If an opacity determination is indicated, a notation of the determination shall be made in the log. All data required by 40 CFR 60, Appendix A, Method 9 shall also be maintained in accordance with Provision I.S.1 of this permit. If excess visible emission is indicated, a notation of the resulting maintenance activity shall also be made in the log, and shall include the date of the maintenance request, the date the maintenance was performed, the type of maintenance performed, and the name of the person responsible for the maintenance. II.B.1.g.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. Monthly surveys have been performed and recorded. II.B.1.h Condition: The permittee shall develop, maintain, and implement a written Hunter Emissions Minimization Plan (Hunter Plan) that describes, in detail, procedures for operating and maintaining the Units #1, #2 and #3 boilers, including associated air pollution control and monitoring equipment, during events of startup and shutdown. The Hunter Plan shall define the startup and shutdown events and shall contain the minimum requirements as follows: (1) Startup is defined as the period beginning with the introduction of fuel into the boiler and ending no later than when two coal feeders have been placed in service and the flue gas temperature at the outlet ducts to both sides of the baghouse outlet (Units #1, #2 or #3 boilers) have reached a temperature of 220oF and less than 20 percent of the boiler heat input is being furnished by fuel oil. (2) Bypass of associated control equipment shall only be used to prevent loss of life, personal injury, or severe property damage. (3) Shutdown is defined as the period beginning when the unit load or output is reduced with the intent of removing the unit from service, or when the unit trips as the result of a sudden and unforeseen failure or malfunction and ending when fuel flow to the boiler ceases. (4) The Hunter Plan shall contain detailed steps to minimize, to the maximum extent practicable, the frequency and duration of operation in startup or shutdown mode and shall be followed at all times. This shall include, but not necessarily be limited to, careful and detailed design, planning, operation, and maintenance so as to avoid unnecessary, preventable, or unreasonably frequent or lengthy startup and shutdown. (5) The duration of a boiler startup event shall not extend beyond 20 hours per startup period or 300 hours per year per boiler and 750 hours per year combined for the Unit #1, #2 and #3 boilers. 20 (6) During periods of startup and shutdown, the permittee shall operate and maintain the boilers, including associated air pollution control and monitoring equipment, in accordance with procedures specified in the Hunter Plan based on equipment manufacturer/plant operating procedures. (7) The permittee shall periodically revise the Hunter Plan for the affected source as necessary to satisfy the requirements of this Condition or to reflect changes in equipment or procedures at the affected source. Each such revision must be submitted to the Director. [ AO DAQE- AN102370028-18]. [R307-401-8] II.B.1.h.1 Monitoring: Recordkeeping requirements required in this permit condition shall serve as monitoring requirement. II.B.1.h.2 Recordkeeping: The permittee shall maintain records demonstrating that the procedures in the Hunter Plan were followed. These records shall include the date and time of occurrence and duration of each startup and shutdown, total hours of startup and shutdown every calendar year for each boiler, emissions during startup and shutdown as well as other pertinent information. II.B.1.h.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. A Hunter Emissions Minimization Plan has been developed and maintained. Records of startup events during calendar year 2023 were provided and reviewed. No exceedances were documented. A total of 283 combined boiler startup hours were recorded; 53.82 hours on Unit 1, 133.45 hours on Unit 2, and 95.97 hours on Unit 3. II.B.1.i Condition: The plant-wide applicability limitation (PAL) of SO2 emission shall be no greater than 5,537.5 tons per year and the PAL of NOx emission shall be no greater than 15,095 tons per year, based on 12-month rolling total for the entire Hunter Plant from all point sources and fugitive emission. The PAL limits shall be effective for ten years from July 13, 2018, and will expire on July 13, 2028. If the permittee applies for PAL renewal, the permittee shall submit an application in accordance with 40 CFR Subpart 52.21(aa)(10) at least 6 months prior to, but no earlier than 18 months before July 13, 2028. If the permittee submits a complete application to renew the PAL within this time period, the PAL shall remain effective until a revised approval order is issued. Once the PAL expires, the permittee shall be subject to the requirements of 40 CFR Subpart 52.21(aa)(9)(i) through (v). [40 CFR Subpart 52.21(aa) and AO DAQE- AN102370028-18]. [R307-401-8] 21 II.B.1.i.1 Monitoring: SO2 and NOx emissions shall be monitored in accordance with 40 CFR part 52.21(aa)(12), Monitoring Requirements for PALs, and as a minimum, all reported NOx and SO2 emissions, including emissions associated with startups, shutdowns, and malfunctions, in pounds per hour, shall be summed to get monthly total emissions and shall be calculated as follows: (a) For Units #1, #2 and #3 main boiler stacks, the permittee's reporting to EPA's Acid Rain Emissions data base for NOx and SO2 in pounds per hour obtained from the boilers' CEM data shall be used to calculate NOx and SO2 emission rates. All reported NOx and SO2 emissions, including emissions associated with startup, shutdowns, and malfunctions, in pounds per hour, shall be summed to get monthly total emissions. (b) For Units #1, #2 and #3 emergency diesel-fired generators, emissions shall be calculated by multiplying the SO2 and NOx emission factors from the latest edition of EPA's emission factors compilation AP-42 in accordance with 40 CFR part 52.21(aa)(12)(vi), hours of operation, and engine site rating or design rating. Records documenting generator usage shall be kept in a log that shall include the date the generator is used and the duration in hours of generator usage and engine site rating or design rating. (c) For Units #1 and #2 emergency diesel-fired fire pumps, emissions shall be calculated by multiplying the SO2 and NOx emission factor from the latest edition of EPA's emission factors compilation AP-42 in accordance with 40 CFR part 52.21(aa)(12)(vi), hours of operation, and engine site rating or design rating. Records documenting generator usage shall be kept in a log, that shall include the date the pump is used and the duration in hours of pump usage, and engine site rating or design rating. (d) The permittee shall calculate new 12-month total NOx and SO2 emissions by the twentieth day of each month using data from the previous 12 months. Records of emissions shall be kept for all periods when the plant is in operation. II.B.1.i.2 Recordkeeping: The results of monitoring shall be kept in accordance with Provision I.S.1 of this permit. In addition, permittee shall comply with 40 CFR Subpart 52.21(aa)(13), Recordkeeping Requirements for PALs. II.B.1.i.3 Reporting: In addition to the reporting requirement described in Provision I.S.2 of this permit, the permittee shall comply with 40 CFR Subpart 52.21(aa)(14), Reporting and notification requirements for PALs. Status: In compliance. 12-month rolling totals of SO2 and NOx emissions are kept and were reviewed during this inspection. No exceedances of these limits were recorded. During the 12-month period ending March 31, 2024; 1,633 tons SOX and 3,772 tons of NOX were emitted. PAL reports have been submitted on time in the past year. 22 II.B.2 Conditions on Subpart D Boilers, Units #1 & #2 (Emission unit #4). II.B.2.a Condition: Emissions of particulate matter (PM) shall not be greater than 0.015 lb/MMBtu based on a 3-test average from each boiler. [40 CFR 60.42 (a) and DAQE-AN102370028-18]. [40 CFR 60 Subpart D, R307-401-8] II.B.2.a.1 Monitoring: (a) Stack testing to show compliance with the PM emission limitations shall be performed as specified below: (1) Testing and Frequency. Emission shall be tested each year. The source may also be tested at any time if directed by the Director. (2) Notification. The permittee shall provide a notification of the test date at least 30 days before the test. A pretest conference shall be held, if directed by the Director, between the permittee, the tester, and the Director. (3) Compliance determination procedures and stack test methods shall be performed according to 40 CFR 60 Subpart D, 60.46. (b) Opacity shall be used as a performance indicator of the baghouse to provide a reasonable assurance of compliance with the PM emission limitation as specified below: (1) Measurement Approach: Opacity is measured directly by COMS installed in each baghouse outlet duct. (2) Indicator Range: (i) An excursion is defined as a 24-hour daily average opacity value greater than the baseline level of 5%. Annually, the permittee should develop a new excursion level during annual performance test using the modified method under 60.48Da(o)(2)(iii) and (iv) (NSPS Subpart Da). The new value of the opacity excursion level shall be determined by averaging all of the 6- minute average opacity values from the COMS measurements recorded during each of the test run intervals conducted for the performance test plus 2.5 percent, or a total opacity value of 5.0%, whichever is greater. (ii) Excursions trigger a baghouse inspection, corrective actions and a reporting requirement. The permittee must initiate investigation of the relevant equipment and control systems within 24 hours of the first discovery of the high opacity incident and take the appropriate corrective action as soon as practicable to adjust control settings or repair equipment to reduce the measured 24- hour average opacity to a level below the baseline opacity level. If the measured 24-hour average opacity remains at a level greater than the opacity baseline level after seven boiler operating days, a new particulate matter performance test will be conducted to establish a new opacity baseline value. This new performance test will be conducted within 60 days of the date that the measured 24-hour average opacity was first determined to exceed the baseline opacity level unless a waiver is granted by the Director. (40 CFR 60.8Da(o)(2)(iv) and (vi)) 23 (3) Performance Criteria: (i) Data Representativeness: Measurements made by COMS shall provide a direct indicator of the baghouse performance. COMS shall be installed and operated in accordance with 40 CFR Part 60, Appendix B, Performance Specification 1 and R307- 170. (ii) QA/QC Practices and Criteria: COMS shall be operated, calibrated, and maintained to meet 40 CFR 60, Appendix B, Performance Specification 1. (iii) Monitoring Frequency: Opacity shall be monitored continuously with opacity values averaged every minute. (iv) Data Collection Procedure: Opacity data shall be recorded and stored electronically. (v) Averaging Period: Use continuous opacity data to calculate 6-minute averages and the 6-minute averages to calculate the 24-hour daily average opacity. II.B.2.a.2 Recordkeeping: In addition to the recordkeeping requirement described in Provision I.S.1 of this permit, (a) The permittee shall maintain a file of all stack testing and all other information required by permit provision I.S.1. (b) The permittee shall maintain a file of all COMS measurements, including performance testing measurements, all COMS performance evaluations, all COMS calibration checks, all COMS adjustments and maintenance, and all other information required by applicable portions of 40 CFR Part 60, Subparts A recorded in a permanent form suitable for inspection. (40 CFR 60.7(f)) (c) The permittee shall maintain a file of the occurrence and duration of any excursion, corrective actions taken, and any other supporting information required to be maintained under 40 CFR 64 (such as data used to document the adequacy of monitoring, or records of monitoring maintenance or corrective actions). Instead of paper records, the permittee may maintain records on alternative media, such as microfilm, computer files, magnetic tape disks, or microfiche, provided that the use of such alternative media allows for expeditious inspection and review, and does not conflict with other applicable recordkeeping requirements. (40 CFR 64.9(b)) (d) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; or any malfunction of the air pollution control equipment. II.B.2.a.3 Reporting: (a) The monitoring report required in Provision I.S.2 of this permit shall include, at a minimum, the following information, as applicable: 24 (1) Summary information on the number, duration and cause (including unknown cause, if applicable) of excursions or exceedances, as applicable, and the corrective actions taken; (2) Summary information on the number, duration and cause (including unknown cause, if applicable) for monitor downtime incidents (other than downtime associated with zero and span or other daily calibration checks, if applicable). (b) The results of stack testing shall be submitted to the Director within 60 days of completion of the testing. Reports shall clearly identify results as compared to permit limits and indicate compliance status. Status: In compliance. The most recent emission testing data available shows the test was conducted on February 13-14, 2024. Results were submitted to DAQ and audited in DAQC-276-24. DAQ calculated particulate emissions from Unit 1 were 0.003 lb/MMBtu, and Unit 2 were 0.005 lb/MMBtu. II.B.2.b Condition: Emissions of NOx shall be no greater than 0.70 lb/MMBtu heat input for any 3-hour period as determined by the arithmetic average of three contiguous one-hour periods [40 CFR 60.44(a)(3), 60.45(g)(3), 60.8(c), and DAQE-AN102370028-18]. [40 CFR 60 Subpart D, R307-401-8] II.B.2.b.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system for measuring nitrogen oxides emissions. The permittee shall determine compliance by periodic monitoring using procedures in 40 CFR Part 60.45, Emission and fuel monitoring subparagraphs (a), (e), and (f)) and 60.13(e). (b) Each continuous emission monitoring system shall meet the following requirements in 40 CFR Part 75, Appendix A, Specification and Test Procedures (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications (4) Data Acquisition and Handling Systems (5) Calibration Gas (c) The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program, may be used to fulfill the 40 CFR 60.13(d)(1) continuous emission monitor data quality assurance requirements. II.B.2.b.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and D recorded in a permanent form suitable for inspection. 25 (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.2.b.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.45(g), Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60, or by 40 CFR 75 Appendix B, shall be submitted with the excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director (permitting authority) shall also be submitted to USEPA, Region VIII, if requested. (d) The reports required in paragraphs (a), (b), and (c) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. NOx lb/MMBtu three-hour readings at inspection were 0.138 Unit 1, 0.164 Unit 2, and Unit 3 offline. II.B.2.c Condition: Emissions of NOx shall be no greater than 0.26 lb/MMBtu heat input for a 30-day rolling average [40 CFR 60.44(a), 60.45(g), 60.8(c), and DAQE-AN102370028-18]. [40 CFR 60 Subpart D, R307-401-8] II.B.2.c.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system for measuring nitrogen oxides emissions. The permittee shall determine compliance by periodic monitoring using procedures in 40 CFR Part 60.45, Emission and fuel monitoring (subparagraphs (a), (e), and (f)) and 60.13(e). (b) Each continuous emission monitoring system shall meet the following requirements: 40 CFR Part 75, Appendix A, Specification and Test Procedures (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications. (4) Data Acquisition and Handling Systems (5) Calibration Gas (c) The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program, may be used to fulfill the 40 CFR 60.13(d)(1) continuous emission monitor data quality assurance requirements. 26 (d) A 30-day rolling average shall be calculated every day for NOx emissions by using daily average emission rates. II.B.2.c.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and D recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.2.c.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.45(g), Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60, or by 40 CFR 75 Appendix B, shall be submitted with the excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director (permitting authority) shall also be submitted to USEPA, Region VIII, if requested. (d) The reports required in paragraphs (a), (b), and (c) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. NOx lb/MMBtu thirty-day readings at inspection were 0.173 Unit 1, 0.162 Unit 2, and 0.287 Unit 3. II.B.2.d Condition: Emissions of SO2 shall be no greater than 1.2 lb/MMBtu heat input for any 3-hour period as determined by the arithmetic average of three contiguous one-hour average [40 CFR 60.43(a), 60.45(g), 60.8(c), and DAQE-AN102370028-18]. [40 CFR 60 Subpart D, R307-401-8] II.B.2.d.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system for measuring sulfur dioxide emissions. The permittee shall determine compliance by periodic monitoring using procedures in 40 CFR Part 60.45, Emission and fuel monitoring (subparagraphs (a), (e), and (f)) and 60.13(e). 27 (b) Each continuous emission monitoring system shall meet the following requirements in 40 CFR Part 75, Appendix A, Specification and Test Procedures (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications (4) Data Acquisition and Handling Systems (5) Calibration Gas (c) The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program, may be used to fulfill the 40 CFR 60.13(d)(1) continuous emission monitor data quality assurance requirements. II.B.2.d.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and D recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.2.d.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.45(g), Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60, or by 40 CFR 75 Appendix B, shall be submitted with the excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director (permitting authority) shall also be submitted to USEPA, Region VIII, if requested. (d) The reports required in paragraphs (a), (b), and (c) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. SO2 lb.MMBtu three-hour readings at inspection were 0.083 Unit 1, 0.084 Unit 2, and Unit 3 offline. 28 II.B.2.e Condition: Emissions of SO2 shall be no greater than 0.12 lb/MMBtu heat input for a 30-day rolling average. [40 CFR 60.8(c) and DAQE-AN102370028-18]. [40 CFR 60 Subpart D, R307-401-8] II.B.2.e.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system for measuring sulfur dioxide emissions. The permittee shall determine compliance by periodic monitoring using procedures in 40 CFR Part 60.45, Emission and fuel monitoring (subparagraphs (a), (e), and (f)) and 60.13(e). (c) Each continuous emission monitoring system shall meet the following requirements: 40 CFR Part 75, Appendix A, Specification and Test Procedures (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications (4) Data Acquisition and Handling Systems (5) Calibration Gas (b) The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program, may be used to fulfill the 40 CFR 60.13(d)(1) continuous emission monitor data quality assurance requirements. (c) A 30-day rolling average shall be calculated every day for SO2 emissions by using daily average emission rates. II.B.2.e.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and D recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.2.e.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.45(g), Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60, or by 40 CFR 75 Appendix B, shall be submitted with the excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. 29 (c) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director (permitting authority) shall also be submitted to USEPA, Region VIII, if requested. (d) The reports required in paragraphs (a), (b), and (c) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. SO2 ln/MMBtu Thirty-day readings at inspection were 0.083 Unit 1, 0.089 Unit 2, and 0.091 Unit 3. II.B.2.f Condition: Visible emissions shall be no greater than 20 percent opacity (six-minute average) except during periods of startup, shutdown, and malfunction and except for one 6-minute period per hour of not more than 27 percent opacity. During startup and shutdown events, the permittee shall demonstrate compliance with the requirements under Provision II.B.1.h of this permit. [40 CFR 60.42(a)(2), 60.45(g)(1), 60.8(c), 60.11(c), and R307-201-3]. [40 CFR 60 Subpart D, R307-201-3] II.B.2.f.1 Monitoring: (a) The permittee shall determine compliance with the visible emission limit by a continuous opacity monitoring (COM) system installed and operated in accordance with 40 CFR 60.45, Emission and fuel monitoring (subparagraphs (a) and (g)) and 60.13(e). (b) Each continuous opacity monitoring system shall meet the following quality assurance requirements: (1) 40 CFR 60.13, Monitoring requirements (subparagraphs (d) and (f)) (2) 40 CFR Part 60, Appendix B, Performance Specification 1, Specifications and Test Procedures for Opacity Continuous Emission Monitoring Systems in Stationary Sources (3) R307-170, Continuous Emission Monitoring System Program. II.B.2.f.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and D recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. 30 II.B.2.f.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.45(g), Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60, or by 40 CFR 75 Appendix B, shall be submitted with the excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director (permitting authority) shall also be submitted to USEPA, Region VIII, if requested. (40 CFR 60.4 and 60.7(c)) (d) The reports required in paragraphs (a), (b), and (c) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. (origin: 40 CFR 60.4, 60.7(c), and 60.45(g)). Status: Not evaluated. COM and CEM requirements are evaluated by DAQ’s CEM specialist. Opacity (6 minute) readings during inspection were: 3.8 - Unit 1, 4.4 - Unit 2, and Unit 3 offline. II.B.2.g Condition: Emissions of SO2 shall be no greater than 20 percent of the potential combustion concentration based on the average inlet and average outlet SO2 emissions determined as the arithmetic average of all hourly emission rates for the 30 successive boiler operating days. [DAQE-AN102370028- 18]. [R307-401-8] II.B.2.g.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring sulfur dioxide emissions. The permittee shall determine compliance with the SO2 reduction limit by periodic monitoring using procedures in 40 CFR Part 60.46a, Compliance provision (subparagraph (c), (d), (e), (g) and (h)), 60.47a, Emission monitoring (subparagraph (b), (d), (e), (f), (g), (h), (i) and (j)), and 60.48a, Compliance determination procedures and methods (subparagraph (c)). (b) Each continuous emissions monitoring system shall meet the following requirements in 40 CFR Part 75, Appendix A, Specification and Test Procedures (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications (4) Data Acquisition and Handling Systems (5) Calibration Gas (c) The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program, may be used to fulfill the 40 CFR 60.13(d)(1) continuous emission monitor data quality assurance requirements. 31 (d) An "as-fired" fuel testing program (upstream of coal pulverizers) meeting the requirements of Method 19 (40 CFR Part 60 Appendix A) may be used as an alternative method to determine potential sulfur dioxide emissions in place of a continuous sulfur dioxide emission monitor at the inlet to the sulfur dioxide control device. The permittee shall prepare a quality assurance (QA) plan for the coal sampling equipment, coal custody procedures, and laboratory analysis. Method 19 and ASTM QA procedures shall be used as part of the plan. II.B.2.g.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and D recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. (c) The permittee shall maintain records demonstrating adherence to the fuel testing program QA plan if fuel testing is performed. II.B.2.g.3 Reporting: (a) The permittee shall report 30-day periods during which the SO2 reduction requirement was not met in the next NSPS excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) The reports required in paragraphs (a) and (b) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. II.B.2.h Condition: Emissions of CO shall be no greater than 0.34 lb/MMBtu heat input for a 30-day rolling average and no greater than 3990 lb/hr for an 8-hour block average. [DAQE-AN102370028-18]. [R307-401-8] 32 II.B.2.h.1 Monitoring: The emission of CO shall be monitored by continuous emission monitoring system (CEMS). The permittee shall calibrate, maintain, and operate a CEMS as required by R307-170 to determine compliance with CO concentration. The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program shall be used to fulfill data quality assurance requirements. The hourly average of CO emissions shall be calculated every hour and the 8-hour block average and daily average shall be calculated using the hourly average data. The daily average of CO emission shall be used to calculate 30-day rolling average. II.B.2.h.2 Recordkeeping: In addition to the recordkeeping requirement described in Provision I.S.1 of this permit, the permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable requirements of R307-170. II.B.2.h.3 Reporting: (a) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) The reports required in paragraph (b) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. (b) The reports required in paragraph (a) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. The initial stack test has been performed. The 30 Day lb/MMBtu during inspection were 0.14 Unit 1, 0.02 Unit 2 and .001 Unit 3(shutdown). II.B.2.i Condition: At all times the permittee must operate and maintain any affected source, including associated air pollution control equipment and monitoring equipment, in a manner consistent with safety and good air pollution control practices for minimizing emissions. Determination of whether such operation and maintenance procedures are being used will be based on information available to the EPA Administrator which may include, but is not limited to, monitoring results, review of operation and maintenance procedures, review of operation and maintenance records, and inspection of the source. [40 CFR 63.10000(b)]. [40 CFR 63 Subpart UUUUU] 33 II.B.2.i.1 Monitoring: Records required for this permit condition will serve as monitoring. II.B.2.i.2 Recordkeeping: The permittee shall keep the records described in 40 CFR 63.10032(a) through (j), as applicable. [40 CFR 63.10032] The permittee shall document activities performed to assure proper operation and maintenance. Records shall be maintained in accordance with 40 CFR 63.10033 and Provision I.S.1 of this permit. II.B.2.i.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. The facility appeared to be maintained in a manner consistent with good air pollution control practices for minimizing emissions. A preventative work order system is in place utilizing SAP software. Annual projections of planned outages have been submitted. II.B.2.j Condition: (1) The permittee shall comply with the following requirements for each affected emission unit: (a) Emission of filterable particulate matter (PM) shall be no greater than 3.0E-02 lb/MMBtu; (b) Emission of sulfur dioxide (SO2) shall be no greater than 2.0E-01 lb/MMBtu; (c) Emission of mercury (Hg) shall be no greater than 1.2E0 lb/TBtu; (d) The permittee shall conduct a tune-up of the EGU burner and combustion controls at least each 36 calendar months, or each 48 calendar months if neural network combustion optimization software is employed; (e) The permittee shall comply with the emission limits at all times except during periods of startup and shutdown. The permittee shall meet the work practice in Table 3(3) and (4) of 40 CFR 63 Subpart UUUUU during periods of startup, or shutdown; (2) As provided in 40 CFR 63.6(g), the Administrator may approve use of an alternative to the work practice standards in this section; [40 CFR 63.9991, 63.10000(a), tables 2, 3, and 4]. [40 CFR 63 Subpart UUUUU] 34 II.B.2.j.1 Monitoring: (a) General Compliance Requirement: (1) Filterable PM: The permittee shall demonstrate compliance through performance stack testing repeated quarterly; (2) SO2: The permittee shall demonstrate continuous compliance through use of a SO2 CEMs in accordance with 40 CFR Subpart 75; (3) Hg: The permittee shall demonstrate continuous compliance through use of a Hg CEMs in accordance with appendix A to 40 CFR 63 Subpart UUUUU. The permittee shall operate and maintain the CEMs according to the site-specific monitoring plan as required in 40 CFR 63.10000(d)(5)(i) through (vii); (4) The permittee shall perform periodic tune-up of EGU in accordance with 40 CFR 63.10021(e). (b) Testing Requirements: the compliance performance test shall be conducted according to the procedures described in 43 CFR 63.10006 for continuous compliance. The permittee shall conduct all required performance tests according to 40 CFR 63.10007 (c) Continuous Compliance: (1) The permittee shall monitor and collect data according to 43 CFR 63.10020(b) through (d) and the site-specific monitoring plan required by 40 CFR 63.10000(d). (2) The permittee shall demonstrate continuous compliance with each emissions limit, operating limit, and work practice standard in Tables 2 through 4 to the subpart UUUUU of 40 CFR 63 that applies to you, according to the monitoring specified in Tables 6 and 7 to subpart UUUUU of 40 CFR 63, and paragraphs 40 CFR 63.10021 (b) through (g). (d) Alternate compliance monitoring for the EGU qualified as low emitting EGU (LEE): The permittee may pursue the LEE option for filterable PM and Hg for the qualified LEE which meets the requirement of 40 CFR 63.10005(h) (1) Filterable PM: The permittee shall conduct a performance test at least once every 36 calendar months to demonstrate continued LEE status. (2) Hg: The permittee shall conduct a 30-day performance test using method 30B at least once every 12 calendar months to demonstrate continued LEE status. (e) The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 9 of 40 CFR 63 Subpart UUUUU. [40 CFR 63.10040]. II.B.2.j.2 Recordkeeping: The permittee shall keep the records described in 40 CFR 63.10032(a) through (j), as applicable. [40 CFR 63.10032] 35 The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 9 of 40 CFR 63 Subpart UUUUU. [40 CFR 63.10040] Records shall be maintained in accordance with 40 CFR 63.10033 and Provision I.S.1 of this permit. II.B.2.j.3 Reporting: The permittee shall submit a Notification of Compliance Status summarizing the results of the initial compliance demonstration according to 40 CFR 63.9(h)(2)(ii). The Notification of Compliance Status report must contain all the information specified in 40 CFR 63.10030(e)(1) through (7), as applicable. The permittee shall submit the compliance report as required in 40 CFR 63.10031. The compliance report shall contain the requirements as described in 40 CFR 63.10031(c)(1) through (4) and Table 8 of 40 CFR 63 Subpart UUUUU semiannually according to the requirements in 40 CFR 63.10031(b). The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 9 of 40 CFR 63 Subpart UUUUU. [40 CFR 63.10040] There are no additional reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. The permittee has attained LEE status for Mercury and PM on Units 1 and 2. Mercury is tested using Method 30B every 12 calendar months. 40 CFR 63.10031(f)(6) requires this test report be submitted to EPA only thru the ECMPS client tool. Hg rate calculations are submitted to DAQ annually in the report required by II.B.2.k and II.B.3.i. Semi-annual Subpart UUUUU reports have been submitted and summarize these tests as well as boiler tune-ups. SO2 is monitored by CEM. The annual Mercury Method 30B was completed in November 2023. Results are listed in DAQC-1361-23 as follows: Source Test Date RM/Pollutant DAQ Result Test Result Limit Unit 1 10/25-11/28 RM 30B/HG 1.1E-8 lb/MMBtu 1.0E-8 lb/MMBtu 6.5E-7 lb/MMBtu 0.01 lb/TBtu 0.01 lb/TBtu 1.2 lb/TBtu 0.0001 lb/GW-hr 0.0001 lb/GW-hr 0.013 lb/GW-hr 0.5 lbs/yr* 0.6 lbs/yr* 29 lbs/yr* 0.4 lbs/yr** 0.4 lbs/yr** 29 lbs/yr** Unit 2 10/25-11/28 RM 30B/HG 1.9E-8 lb/MMBtu 1.7E-8 lb/MMBtu 6.5E-7 lb/MMBtu 0.02 lb/TBtu 0.02 lb/TBtu 1.2 lb/TBtu 0.0002 lb/GW-hr 0.0002 lb/GW-hr 0.013 lb/GW-hr 0.6 lbs/yr* 0.7 lbs/yr* 29 lbs/yr* 0.7 lbs/yr** 0.7 lbs/yr** 29 lbs/yr** 36 Unit 3 10/25-11/28 RM 30B/HG 5.7E-8 lb/MMBtu 5.4E-8 lb/MMBtu 6.5E-7 lb/MMBtu 0.05 lb/TBtu 0.05 lb/TBtu 1.2 lb/TBtu 0.0006 lb/GW-hr 0.0006 lb/GW-hr 0.013 lb/GW-hr 2.7 lbs/yr* 2.6 lbs/yr* 29 lbs/yr* 2.3 lbs/yr** 2.3 lbs/yr** 29 lbs/yr** *Emission rate calculated based on maximum electrical output per year **Emission rate calculated based on maximum heat input per year II.B.2.k Condition: Emissions of mercury shall be no greater than 6.5E-07 lb/MMBtu heat input based on an annual averaging period beginning January 1st and ending December 31st. [R307-424-4]. [R307-424-4] II.B.2.k.1 Monitoring: (a) The permittee shall install, calibrate, maintain and operate a continuous monitoring system for measuring emissions in accordance with Appendix A to 40 CFR 63 Subpart UUUUU. (b) Each continuous emission monitoring system shall meet the quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program and Appendix A to 40 CFR 63 Subpart UUUUU. (c) Alternate compliance monitoring for the EGU qualified as low emitting EGU (LEE): the permittee may pursue the LEE option for the qualified LEE which meets the requirement of 40 CFR 63.10005(h). The permittee shall conduct a 30-day performance test using method 30B at least once every 12 calendar months to demonstrate continued LEE status. II.B.2.k.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.2.k.3 Reporting: (a) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program and comply with the reporting provision in Appendix A to 40 CFR 63 Subpart UUUUU. 37 (b) Upon completion of each year's fourth quarterly report, an assessment shall be made for the entire calendar year and reported to the Director within 30 days. (c) The reports required in paragraph (a) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: In compliance. PacifiCorp has obtained LEE status and monitors Hg emissions using option (c). Annual reports have been submitted and include emission rate calculations. See Condition II.B.2.j for test results. II.B.3 Conditions on Steam Generating Unit #3 (Emission unit #3). II.B.3.a Condition: Emissions of particulate matter (PM) shall not be greater than 0.02 lb/MMBtu heat input based on a 6- hour test average. [40 CFR 60.42Da(a), 60.48Da(c), and DAQE-AN102370028-18]. [40 CFR 60 Subpart Da, R307-401-8] II.B.3.a.1 Monitoring: (a) Stack testing to show compliance with the PM emission limitations shall be performed as specified below: (1) Testing and Frequency. Emissions shall be tested each year. The source may also be tested at any time if directed by the Director. (2) Notification. The permittee shall provide a notification of the test date at least 30 days before the test. A pretest conference shall be held, if directed by the Director, between the permittee, the tester, and the Director. (3) Compliance determination procedures and stack test methods shall be performed according to 40 CFR 60 Subpart Da, 60.50a(b) and (e). (b) Opacity shall be used as a performance indicator of the baghouse to provide a reasonable assurance of compliance with the PM emission limitation as specified below: (1) Measurement Approach: Opacity is measured directly by COMS installed in each baghouse outlet duct. (2) Indicator Range: (i) An excursion is defined as a 24-hour daily average opacity value greater than the baseline level of 5.33% . Annually, the permittee should develop a new excursion level during annual performance test using the modified method under 60.48Da(o)(2)(iii) and (iv) (NSPS Subpart Da). The new value of the opacity excursion level shall be determined by averaging all of the 6- minute average opacity values from the COMS measurements recorded during each of the test run intervals conducted for the performance test plus 2.5 percent, or a total opacity value of 5.0%, whichever is greater. 38 (ii) Excursions trigger a baghouse inspection, corrective actions and a reporting requirement. The permittee must initiate investigation of the relevant equipment and control systems within 24 hours of the first discovery of the high opacity incident and take the appropriate corrective action as soon as practicable to adjust control settings or repair equipment to reduce the measured 24- hour average opacity to a level below the baseline opacity level. If the measured 24-hour average opacity remains at a level greater than the opacity baseline level after seven boiler operating days, a new particulate matter performance test will be conducted to establish a new opacity baseline value. This new performance test will be conducted within 60 days of the date that the measured 24-hour average opacity was first determined to exceed the baseline opacity level unless a waiver is granted by the Director. (40 CFR 60.8Da(o)(2)(iv) and (vi)) (3) Performance Criteria: (i) Data Representativeness: Measurements made by COMS shall provide a direct indicator of the baghouse performance. COMS shall be installed and operated in accordance with 40 CFR Part 60, Appendix B, Performance Specification 1 and R307- 170. (ii) QA/QC Practices and Criteria: COMS shall be operated, calibrated, and maintained to meet 40 CFR 60, Appendix B, Performance Specification 1. (iii) Monitoring Frequency: Opacity shall be monitored continuously with opacity values averaged every minute. (iv) Data Collection Procedure: Opacity data shall be recorded and stored electronicall y. (v) Averaging Period: Use continuous opacity data to calculate 6-minute averages and the 6-minute averages to calculate the 24-hour daily average opacity. II.B.3.a.2 Recordkeeping: In addition to the recordkeeping requirement described in Provision I.S.1 of this permit, (a) The permittee shall maintain a file of all stack testing and all other information required by permit provision I.S.1. (b) The permittee shall maintain a file of all COMS measurements, including performance testing measurements, all COMS performance evaluations, all COMS calibration checks, all COMS adjustments and maintenance, and all other information required by applicable portions of 40 CFR Part 60, Subparts A recorded in a permanent form suitable for inspection. (40 CFR 60.7(f)) (c) The permittee shall maintain a file of the occurrence and duration of any excursion, corrective actions taken, and any other supporting information required to be maintained under 40 CFR 64 (such as data used to document the adequacy of monitoring, or records of monitoring maintenance or corrective actions). Instead of paper records, the permittee may maintain records on alternative media, such as microfilm, computer files, magnetic tape disks, or microfiche, provided that the use of such alternative media allows for expeditious inspection and review, and does not conflict with other applicable recordkeeping requirements. (40 CFR 64.9(b)) 39 (d) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; or any malfunction of the air pollution control equipment. II.B.3.a.3 Reporting: (a) The monitoring report required in Provision I.S.2 of this permit shall include, at a minimum, the following information, as applicable: (1) Summary information on the number, duration and cause (including unknown cause, if applicable) of excursions or exceedances, as applicable, and the corrective actions taken; (2) Summary information on the number, duration and cause (including unknown cause, if applicable) for monitor downtime incidents (other than downtime associated with zero and span or other daily calibration checks, if applicable). (b) The results of stack testing shall be submitted to the Director within 60 days of completion of the testing. Reports shall clearly identify results as compared to permit limits and indicate compliance status. Status: In compliance with stack testing requirements. CEM and COM requirements are evaluated by DAQ’s CEM specialist. The stack test was completed on November 1, 2023, and reviewed under DAQC-1315-23 as follows: Source Test Date DAQ Result Test Result Limit Unit 3 11/01/2023 0.007 lb/MMBtu 0.006 lb/MMBtu 0.02 b/MMBtu CAM reports have been submitted on time. II.B.3.b Condition: Emissions of SO2 shall be no greater than 0.12 lb/MMBtu heat input based on a 30-day rolling average as determined by the arithmetic average of all hourly emission rates for the 30 successive boiler operating days. [40 CFR 60.43Da and DAQE-AN102370028-18]. [40 CFR 60 Subpart Da, R307-401-8] II.B.3.b.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring sulfur dioxide emissions. The permittee shall determine compliance in accordance with 40 CFR Part 60.48a, Compliance provision (subparagraph (c), (d), (e), (g) and (h)), 60.49a, Emission monitoring (subparagraph (b), (d), (e), (f), (g), (h), (i) and (j)), and 60.50a, Compliance determination procedures and methods (subparagraph (c)). 40 (b) Each continuous emission monitoring system shall meet the following requirements in 40 CFR Part 75, Appendix A, Specification and Test Procedures (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications (4) Data Acquisition and Handling Systems (5) Calibration Gas (c) The permittee shall implement a Quality Control program according to 40 CFR Part 75, Appendix B, Procedure 1, Quality Control Program and Appendix B, Procedure 2, Frequency of Testing except Procedure 2.1.5, Procedure 2.2.3 and Procedure 2.3.2, which define the out-of control periods for the daily, quarterly, semiannual and annual assessments, respectively. The following requirements shall be used to define the out-of- control criteria for the emission data: (1) 40 CFR Part 60, Appendix F, Procedure 4.3, Criteria for Excessive Calibration Drift (2) 40 CFR Part 60, Appendix F, Procedure 5.2, Excessive Audit Inaccuracy (3) 40 CFR Part 60, Appendix F, Procedure 6, Calculations for CEMS Data Accuracy. II.B.3.b.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and Da recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.3.b.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.51Da, Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60 shall be submitted with the excess emission report. (b) Relative Accuracy Test Audit notifications shall be made in accordance with R307- 170, Continuous Emission Monitoring System Program. (c) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (d) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director shall also be submitted to USEPA, Region VIII, if requested. 41 (e) The reports required in paragraphs (a), (b), (c), and (d) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. Unit 3 was offline during this inspection. The lb/MMBtu SO2 30-Day reading during inspection was 0.091. II.B.3.c Condition: Emissions of SO2 shall be no greater than 10 percent of the potential combustion concentration based on the average inlet and average outlet SO2 emissions determined as the arithmetic average of all hourly emission rates for the 30 successive boiler operating days. [40 CFR 60.43Da, 60.48Da, and DAQE- AN102370028-18]. [40 CFR 60 Subpart Da, R307-401-8] II.B.3.c.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring sulfur dioxide emissions. The permittee shall determine compliance in accordance with 40 CFR Part 60.48Da, Compliance provision (subparagraph (c), (d), (e), (g) and (h)), 60.49Da, Emission monitoring (subparagraph (b), (d), (e), (f), (g), (h), (i) and (j)), and 60.50Da, Compliance determination procedures and methods (subparagraph (c)). (b) SO2 inlet monitor shall meet the following requirements: (1) 40 CFR Part 60, Appendix B, Specifications and Test Procedures for SO2 and NOx Continuous Emission monitoring Systems in Stationary Sources (2) 40 CFR Part 60, Appendix F, Quality Assurance Procedures (c) The permittee shall implement a Quality Control program for the SO2 outlet monitors according to 40 CFR Part 75, Appendix B, Procedure 1, Quality Control Program and Appendix B, Procedure 2, Frequency of Testing except Procedure 2.1.5, Procedure 2.2.3 and Procedure 2.3.2, which define the out of control periods for the daily, quarterly, semiannual and annual assessments, respectively. The following requirements shall be used to define the out-of-control criteria for the emission data: (1) 40 CFR Part 60, Appendix F, Procedure 4.3, Criteria for Excessive Calibration Drift (2) 40 CFR Part 60, Appendix F, Procedure 5.2, Excessive Audit Inaccuracy (3) 40 CFR Part 60, Appendix F, Procedure 6, Calculations for CEMS Data Accuracy (d) An "as-fired" fuel monitoring system (upstream of coal pulverizers) meeting the requirements of Method 19 (40 CFR Part 60 Appendix A) may be used as an alternative method to determine potential sulfur dioxide emissions in place of a continuous sulfur dioxide emission monitor at the inlet to the sulfur dioxide control device. II.B.3.c.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed 42 on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and Da recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.3.c.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.51Da, Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60 shall be submitted with the excess emission report. (b) Relative Accuracy Test Audit notifications shall be made in accordance with R307- 170, Continuous Emission Monitoring System Program. (c) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (d) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director shall also be submitted to USEPA, Region VIII, if requested. (e) The reports required in paragraphs (a), (b), (c), and (d) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. II.B.3.d Condition: Visible emissions shall be no greater than 20 percent opacity (six-minute average) except during periods of startup, shutdown, and malfunction and except for one 6-minute period per hour of not more than 27 percent opacity. During startup and shutdown events, the permittee shall demonstrate compliance with the requirements under Provision II.B.1.h of this permit. [60.42Da(b), 60.11(c), and DAQE- AN102370028-18]. [40 CFR 60 Subpart Da, R307-203-3, R307-401-8] II.B.3.d.1 Monitoring: (a) The permittee shall determine compliance with the visible emission limit by periodic monitoring using a continuous opacity monitoring (COM) system installed and operated in accordance with 40 CFR 60.49a, Emission monitoring (subparagraphs (a), (e), (f), and (i)), and 60.13, Monitoring requirements (subparagraphs (e) and (h)). (b) Each continuous opacity monitoring system shall meet the following quality assurance requirements: (1) 40 CFR 60.13, Monitoring requirements (subparagraphs (d) and (f)) 43 (2) 40 CFR Part 60, Appendix B, Performance Specification 1, Specifications and Test Procedures or Opacity Continuous Emission Monitoring Systems in Stationary Sources (3) R307-170, Continuous Emission Monitoring System Program. II.B.3.d.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and Da recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.3.d.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.51Da, Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60 shall be submitted with the excess emission report. (b) Relative Accuracy Test Audit notifications shall be made in accordance with R307- 170, Continuous Emission Monitoring System Program. (c) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (d) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director shall also be submitted to USEPA, Region VIII, if requested. (e) The reports required in paragraphs (a), (b), (c), and (d) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. Unit 3 was offline during this inspection. II.B.3.e Condition: Emissions of CO shall be no greater than 0.2 lb/MMBtu heat input for a 30-day rolling average and no greater than 2406 lb/hr for an 8-hour block average after the startup of the new low NOx burner/OFA. [DAQE-AN102370028-18]. [R307-401-8] 44 II.B.3.e.1 Monitoring: The emission of CO shall be monitored by continuous emission monitoring system (CEMS). The permittee shall calibrate, maintain, and operate a CEMS as required by R307-170 to determine compliance with CO concentration. The quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program shall be used to fulfill data quality assurance requirements. The hourly average of CO emissions shall be calculated every hour and the 8-hour block average and daily average shall be calculated using the hourly average data. The daily average of CO emission shall be used to calculate 30-day rolling average. II.B.3.e.2 Recordkeeping: In addition to the recordkeeping requirement described in Provision I.S.1 of this permit, the permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable requirements of R307-170. II.B.3.e.3 Reporting: (a) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (b) The reports required in paragraph (a) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. The initial stack test has been performed. Unit 3 was offline during this inspection. The 30-day CO lb/MMBtu reading was 0.074. II.B.3.f Condition: Emissions of NOx shall be no greater than 0.34 lb/MMBtu based on a 30-day rolling average as determined by the arithmetic average of all hourly emission rates for the 30 successive boiler operating days. [40 CFR 60.44Da and DAQE-AN102370028-18]. [40 CFR 60 Subpart Da, R307- 401-8] II.B.3.f.1 Monitoring: (a) The permittee shall install, calibrate, maintain, and operate a continuous monitoring system, and record the output of the system, for measuring nitrogen oxides emissions. The permittee shall determine compliance in accordance with 40 CFR Part 60.48Da, Compliance provision (subparagraphs (b), (c), (e), (g) and (h), 60.49Da, Emission monitoring (subparagraphs (c), (d), (e), (f), (g), (h), (i), and (j)), and 60.50Da, Compliance determination procedures and methods (subparagraph (d)). 45 (b) Each continuous emission monitoring system shall meet the following requirements: 40 CFR Part 75 Appendix A, Specification and Test Procedures, (1) Installation and Measurement Location (2) Equipment Specifications (except the requirement for a low range in 2.1.1.2) (3) Performance Specifications (4) Data Acquisition and Handling Systems (5) Calibration Gas (c) The permittee shall implement a Quality Control program according to 40 CFR Part 75 Appendix B, Procedure 1, Quality Control Program, and Appendix B, Procedure 2, Frequency of Testing, except Procedure 2.1.5, Procedure 2.2.3 and Procedure 2.3.2, which define the out-of control periods for the daily, quarterly, semiannual and annual assessments, respectively. The following requirements shall be used to define the out-of- control criteria for the emission data: (1) 40 CFR Part 60, Appendix F, Procedure 4.3, Criteria for Excessive Calibration Drift (2) 40 CFR Part 60, Appendix F, Procedure 5.2, Excessive Audit Inaccuracy (3) 40 CFR Part 60, Appendix F, Procedure 6, Calculations for CEMS Data Accuracy. (d) A 30-day rolling average shall be calculated every day for NOx emissions by using daily average emission rates. II.B.3.f.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices; and all other information required by applicable portions of 40 CFR Part 60, Subparts A and Da recorded in a permanent form suitable for inspection. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.3.f.3 Reporting: (a) The permittee shall submit excess emission reports required by 40 CFR 60.7(c) and (d) and 40 CFR 60.51Da, Reporting requirements. A data assessment report required by Appendix F, Procedure 1, Section 7 to 40 CFR Part 60 shall be submitted with the excess emission report. (b) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program. (c) A copy of all reports required by 40 CFR Part 60 to be submitted to the Director shall also be submitted to USEPA, Region VIII, if requested. (40 CFR 60.4 and 60.7(c)) 46 (d) The reports required in paragraphs (a), (b), and (c) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: Not evaluated. CEM requirements are evaluated by DAQ’s CEM specialist. The initial stack test has been performed. Unit 3 was offline during this inspection. The 30-day NOx Lb/MMBtu reading was 0.287. II.B.3.g Condition: At all times the permittee must operate and maintain any affected source, including associated air pollution control equipment and monitoring equipment, in a manner consistent with safety and good air pollution control practices for minimizing emissions. Determination of whether such operation and maintenance procedures are being used will be based on information available to the EPA Administrator which may include, but is not limited to, monitoring results, review of operation and maintenance procedures, review of operation and maintenance records, and inspection of the source. [40 CFR 63.10000(b)]. [40 CFR 63 Subpart UUUUU] II.B.3.g.1 Monitoring: Records required for this permit condition will serve as monitoring. II.B.3.g.2 Recordkeeping: The permittee shall keep the records described in 40 CFR 63.10032(a) through (j), as applicable. [40 CFR 63.10032] The permittee shall document activities performed to assure proper operation and maintenance. Records shall be maintained in accordance with 40 CFR 63.10033 and Provision I.S.1 of this permit. II.B.3.g.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. The facility appeared to be maintained in a manner consistent with good air pollution control practices for minimizing emissions. A preventative work order system is in place utilizing SAP software. Annual projections of planned outages have been submitted. 47 II.B.3.h Condition: (1) The permittee shall comply with the following requirements for each affected emission unit: (a) Emission of filterable particulate matter (PM) shall be no greater than 3.0E-02 lb/MMBtu; (b) Emission of sulfur dioxide (SO2) shall be no greater than 2.0E-01 lb/MMBtu; (c) Emission of mercury (Hg) shall be no greater than 1.2E0 lb/TBtu; (d) The permittee shall conduct a tune-up of the EGU burner and combustion controls at least each 36 calendar months, or each 48 calendar months if neural network combustion optimization software is employed; (e) The permittee shall comply with the emission limits at all times except during periods of startup and shutdown. The permittee shall meet the work practice in Table 3(3) and (4) of 40 CFR 63 Subpart UUUUU during periods of startup, or shutdown; (2) As provided in 40 CFR 63.6(g), the Administrator may approve use of an alternative to the work practice standards in this section. [40 CFR 63.9991, 63.10000(a), tables 2, 3, and 4]. [40 CFR 63 Subpart UUUUU] II.B.3.h.1 Monitoring: (a) General Compliance Requirement: (1) Filterable PM: The permittee shall demonstrate compliance through performance stack testing repeated quarterly; (2) SO2: The permittee shall demonstrate continuous compliance through use of a SO2 CEMs in accordance with 40 CFR Subpart 75; (3) Hg: The permittee shall demonstrate continuous compliance through use of a Hg CEMs in accordance with appendix A to 40 CFR 63 Subpart UUUUU. The permittee shall operate and maintain the CEMs according to the site-specific monitoring plan as required in 40 CFR 63.10000(d)(5)(i) through (vii); (4) The permittee shall perform periodic tune-up of EGU in accordance with 40 CFR 63.10021(e). (b) Testing Requirements: the compliance performance test shall be conducted according to the procedures described in 43 CFR 63.10006 for continuous compliance. The permittee shall conduct all required performance tests according to 40 CFR 63.10007 (c) Continuous Compliance: (1) The permittee shall monitor and collect data according to 43 CFR 63.10020(b) through (d) and the site-specific monitoring plan required by 40 CFR 63.10000(d). (2) The permittee shall demonstrate continuous compliance with each emissions limit, operating limit, and work practice standard in Tables 2 through 4 to the subpart UUUUU 48 of 40 CFR 63 that applies to you, according to the monitoring specified in Tables 6 and 7 to subpart UUUUU of 40 CFR 63, and paragraphs 40 CFR 63.10021 (b) through (g). (d) Alternate compliance monitoring for the EGU qualified as low emitting EGU (LEE): The permittee may pursue the LEE option for filterable PM and Hg for the qualified LEE which meets the requirement of 40 CFR 63.10005(h) (1) Filterable PM: The permittee shall conduct a performance test at least once every 36 calendar months to demonstrate continued LEE status. (2) Hg: The permittee shall conduct a 30-day performance test using method 30B at least once every 12 calendar months to demonstrate continued LEE status. (e) The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 9 of 40 CFR 63 Subpart UUUUU. [40 CFR 63.10040]. II.B.3.h.2 Recordkeeping: The permittee shall keep the records described in 40 CFR 63.10032(a) through (j), as applicable. [40 CFR 63.10032] The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 9 of 40 CFR 63 Subpart UUUUU. [40 CFR 63.10040] Records shall be maintained in accordance with 40 CFR 63.10033 and Provision I.S.1 of this permit. 49 II.B.3.h.3 Reporting: The permittee shall submit a Notification of Compliance Status summarizing the results of the initial compliance demonstration according to 40 CFR 63.9(h)(2)(ii). The Notification of Compliance Status report must contain all the information specified in 40 CFR 63.10030(e)(1) through (7), as applicable. The permittee shall submit the compliance report as required in 40 CFR 63.10031. The compliance report shall contain the requirements as described in 40 CFR 63.10031(c)(1) through (4) and Table 8 of 40 CFR 63 Subpart UUUUU semiannually according to the requirements in 40 CFR 63.10031(b). The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 9 of 40 CFR 63 Subpart UUUUU. [40 CFR 63.10040] There are no additional reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance with stack testing requirements. CEM requirements are evaluated by DAQ’s CEM specialist. See status of II.B.3.a above for PM emission testing results. SO2 is monitored by CEM. Hunter Power Plant has attained LEE status for Mercury (see DAQC-346-17) and is using the alternate compliance option listed under (d) of monitoring. Mercury is tested using Method 30B every 12 calendar months. 40 CFR 63.10031(f)(6) requires this test report be submitted to EPA only thru the ECMPS client tool. Hg rate calculations are submitted to DAQ annually in the report required by II.B.2.k and II.B.3.i. Semi-annual Subpart UUUUU reports have been submitted and summarize these tests as well as boiler tune-ups. The stack test was completed on November 28, 2023, and reviewed under DAQC-1361-23 as follows: Source Test Date DAQ Result Test Result Limit Unit 3 10/25-11/28 5.7E-8 lb/MMBtu 5.4E-8 lb/MMBtu 6.5E-7 lb/MMBtu 0.05 lb/TBtu 0.05 lb/TBtu 1.2 lb/TBtu 0.0006 lb/GW-hr 0.0006 lb/GW-hr 0.013 lb/GW-hr 2.7 lbs/yr* 2.6 lbs/yr* 29 lbs/yr* 2.3 lbs/yr** 2.3 lbs/yr** 29 lbs/yr** *Emission rate calculated based on maximum electrical output per year **Emission rate calculated based on maximum heat input per year II.B.3.i Condition: Emissions of mercury shall be no greater than 6.5E-07 lb/MMBtu heat input based on an annual averaging period beginning January 1st and ending December 31st. [R307-424-4]. [R307-424-4] 50 II.B.3.i.1 Monitoring: (a) The permittee shall install, calibrate, maintain and operate a continuous monitoring system for measuring emissions in accordance with Appendix A to 40 CFR 63 Subpart UUUUU. (b) Each continuous emission monitoring system shall meet the quality assurance requirements of R307-170, Continuous Emission Monitoring Systems Program and Appendix A to 40 CFR 63 Subpart UUUUU. (c) Alternate compliance monitoring for the EGU qualified as low emitting EGU (LEE): the permittee may pursue the LEE option for the qualified LEE which meets the requirement of 40 CFR 63.10005(h). The permittee shall conduct a 30-day performance test using method 30B at least once every 12 calendar months to demonstrate continued LEE status. II.B.3.i.2 Recordkeeping: (a) The permittee shall maintain a file of all measurements, including continuous monitoring system, monitoring device, and performance testing measurements; all continuous monitoring system performance evaluations; all continuous monitoring system or monitoring device calibration checks; adjustments and maintenance performed on these systems or devices. (b) The permittee shall maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of the unit; any malfunction of the air pollution control equipment; or any periods during which a continuous monitoring system or monitoring device is inoperative. II.B.3.i.3 Reporting: (a) The permittee shall submit notifications and reports to the Director as required by R307-170, Continuous Emission Monitoring Systems Program and comply with the reporting provision in Appendix A to 40 CFR 63 Subpart UUUUU. (b) Upon completion of each year's fourth quarterly report, an assessment shall be made for the entire calendar year and reported to the Director within 30 days. (c) The reports required in paragraph (a) above are considered prompt notification of permit deviations required in provision I.S.2.c of this permit if all information required by provision I.S.2.c is included in the report. Status: In compliance. PacifiCorp has obtained LEE status and monitors Hg emissions using option (c). Annual reports have been submitted and include emission rate calculations. See condition II.B.3.h above for test results. 51 II.B.4 Conditions on Coal Conveyors (Emission unit #11). II.B.4.a Condition: All coal conveyors and drop points, the live coal handling and storage shall be enclosed. [DAQE- AN102370028-18] [R307-401-8]. II.B.4.a.1 Monitoring: The permittee shall ensure the required covers are installed. II.B.4.a.2 Recordkeeping: A log shall be maintained for any periods of operation when the required covers are removed. II.B.4.a.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. All coal conveyors are enclosed. II.B.5 Conditions on #1 Emergency Fire Pump (Emission unit #18) II.B.5.a Condition: The permittee shall comply with the following operating limitations at all times for each emergency affected emission unit: The permittee shall operate the affected emission unit according to the requirements in 40 CFR 60.4211(f)(1) through (3). Each emergency affected emission unit shall not exceed 100 hours of maintenance checks and readiness testing per year unless the permittee maintains records indicating that Federal, State, or local standards require maintenance and testing of affected emission units beyond 100 hours per year. There is no time limit on the use of emergency stationary ICE in emergency situations. Emergency engines may operate up to 50 hours per year in non-emergency situations, but those 50 hours are counted towards the 100 hours per year provided for maintenance and testing. The 50 hours per year for non-emergency situations cannot be used for peak shaving or to generate income for a facility to supply power to an electric grid or otherwise supply non-emergency power as part of a financial arrangement with another entity. Any operation other than emergency operation, maintenance and testing, and operation in non- emergency situations for 50 hours per year, as permitted in 40 CFR 60.4211(f), is prohibited. If the engine is not operated in accordance with paragraphs 40 CFR 60.4211(f)(1) through (3), it will not be considered an emergency engine and shall meet all requirements for non-emergency engines. [40 CFR 60.4211(f)]. [40 CFR 60 Subpart IIII] 52 II.B.5.a.1 Monitoring: The permittee shall install a non-resettable hour meter if one is not already installed. [Origin: 40 CFR 60.4209(a)]. Records required for this permit condition will serve as monitoring. II.B.5.a.2 Recordkeeping: Records of each affected emission unit shall be kept on a monthly basis in an operation and maintenance log. Records shall distinguish between maintenance-related hours and emergency used-related hours. If maintenance and testing beyond 100 hours per year and required by Federal, State, or local standards, records of these standards shall also be kept. Records shall be maintained as described in Provision I.S.1 of this permit. II.B.5.a.3 Reporting: There are no additional reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. Generator use logs have been kept and showed no exceedances of permitted limits. II.B.5.b Condition: Affected emission units with a displacement of less than 30 liters per cylinder shall comply with the emission standards in Table 4 of 40 CFR 60 Subpart IIII, for all pollutants. If the permittee conducts performance tests in-use on emergency stationary CI ICE with a displacement of less than 30 liters per cylinder they shall meet the not-to-exceed (NTE) standards as indicated in 40 CFR 60.4212. The performance test must be conducted according to the in-use testing procedures in 40 CFR part 1039, subpart F, for stationary CI ICE with a displacement of less than 10 liters per cylinder, and according to 40 CFR part 1042, subpart F, for stationary CI ICE with a displacement of greater than or equal to 10 liters per cylinder and less than 30 liters per cylinder. [40 CFR 60.4204(b) and 40 CFR 60.4212]. [40 CFR 60 Subpart IIII] II.B.5.b.1 Monitoring: The permittee shall comply by purchasing an engine certified to the emission standards in 40CFR 60.4204(b) for the same model year and maximum engine power. The engine must be installed and configured according to the manufacturer's emission-related specifications, except as specified below. The permittee can only change those emission- related settings that are permitted by the manufacturer. (Origin: 40 CFR 60.4211(c)) The permittee shall document activities performed to assure proper operation and maintenance. 53 If the permittee does not install, configure, operate, and maintain affected emission units and control devices according to the manufacturer's emission-related written instructions, or changes emission-related settings in a way that is not permitted by the manufacturer, the permittee shall demonstrate compliance as follows: (a) Keep a maintenance plan and records of conducted maintenance to demonstrate compliance; and (b) To the extent practicable, maintain and operate the engine in a manner consistent with good air pollution control practice for minimizing emissions; and (c) If the permittee does not install and configure the engine and control device according to the manufacturer's emission-related written instructions, or changes the emission- related settings in a way that is not permitted by the manufacturer, the permittee shall conduct an initial performance test to demonstrate compliance with the applicable emission standards within 1 year of such action. (Origin: 40 CFR 60.4211(g)(1)). [40 CFR 60 Subpart IIII] II.B.5.b.2 Recordkeeping: Records required for this permit condition will serve as monitoring requirement. II.B.5.b.3 Reporting: Reports shall be submitted as specified in Section I of this permit. Status: In compliance. A certified engine has been permitted, purchased, and installed. II.B.5.c Condition: The permittee shall purchase diesel fuel that meets the following standards of 40 CFR 80.510(b) for non- road diesel fuel: (1) Sulfur content no greater than 15 ppm (0.0015 percent) by weight and (2) A minimum cetane index of 40 or a maximum aromatic content of 35 volume percent. [40 CFR 60.4207(b)]. [40 CFR 60 Subpart IIII] II.B.5.c.1 Monitoring: Records required for this permit condition will serve as monitoring requirement. II.B.5.c.2 Recordkeeping: For each fuel load received, the permittee shall maintain either fuel receipt records or other documentation showing fuel meets the specifications of ASTM D975 for the cetane index and sulfur content for Grades No. 1-D S15 or 2-D S15 diesel. The permittee shall maintain documentation demonstrating compliance with the condition. These records shall be maintained in accordance with Provision I.S.1. of this permit. 54 II.B.5.c.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. Fuel records were provided and included sulfur content and cetane index values. II.B.6 Conditions on #2 Emergency Fire Pump (Emission unit #19) II.B.6.a Condition: The permittee shall comply with the following operating limitations at all times for each emergency affected emission unit: (1)The permittee shall operate the affected emission unit according to the requirements in 40 CFR 63.6640(f)(1) through (4). Any operation other than emergency operation, maintenance and testing, emergency demand response, and operation in non-emergency situations for 50 hours per year, paragraphs 40 CFR 63.6640(f)(1) through (4), is prohibited. If the engine is not operated in accordance with paragraphs 40 CFR 63.6640(f)(1) through (4), it will not be considered an emergency engine and shall meet all requirements for non-emergency engines. (2) The permittee shall meet the following requirements at all times, except during periods of startup: (a) Change oil and filter every 500 hours of operation or annually, whichever comes first. (b) Inspect air cleaner every 1,000 hours of operation or annually, whichever comes first; (c) Inspect all hoses and belts every 500 hours of operation or annually, whichever comes first, and replace as necessary. (3) The permittee have the option to utilize an oil analysis program as described in 40 CFR 63.6625(i) in order to extend the specified oil change requirement in paragraph (2)(a) of this condition. (4) During periods of startup the permittee shall minimize the engine's time spent at idle and minimize the engine's startup time to a period needed for appropriate and safe loading of the engine, not to exceed 30 minutes, after which time the non-startup emission limitations apply. (5) The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 8 of 40 CFR 63 Subpart ZZZZ. [40 CFR 63.6595(a)(1), 40 CFR 63.6602, 40 CFR 63.6605(a), 40 CFR 63.6625(h), 40 CFR 63.6640(f), 40 CFR 63.6665, 40 CFR 63 Subpart ZZZZ Table 2c, 40 CFR 63 Subpart ZZZZ Table 8]. [40 CFR 63 Subpart ZZZZ] 55 II.B.6.a.1 Monitoring: The permittee shall install a non-resettable hour meter if one is not already installed. [40 CFR 63.6625(f)] If an emergency engine is operating during an emergency and it is not possible to shut down the engine in order to perform the work practice requirements on the required schedule, or if performing the work practice on the required schedule would otherwise pose an unacceptable risk under Federal, State, or local law, the work practice can be delayed until the emergency is over or the unacceptable risk under Federal, State, or local law has abated. The work practice shall be performed as soon as practicable after the emergency has ended or the unacceptable risk under Federal, State, or local law has abated. [40 CFR 63 Subpart ZZZZ Table 2c Footnote 1] The permittee shall demonstrate continuous compliance by operating and maintaining the stationary RICE and after-treatment control device (if any) according to the manufacturer's emission-related written operation and maintenance instructions or develop and follow their own maintenance plan which must provide to the extent practicable for the maintenance and operation of the engine in a manner consistent with good air pollution control practice for minimizing emissions. [40 CFR 63.6625(e), 40 CFR 63.6640(a), 40 CFR 63 Subpart ZZZZ Table 6] The permittee has the option of utilizing an oil analysis program in order to extend the specified oil change requirement in accordance with 40 CFR 63.6625(i). The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 8 of 40 CFR 63 Subpart ZZZZ. [40 CFR 63.6665]. II.B.6.a.2 Recordkeeping: The permittee shall keep the records described in 40 CFR 63.6655(a)(1)-(5) as applicable. [40 CFR 63.6655(a)] For each affected emission unit that does not meet the standards applicable to non- emergency engines, the permittee shall keep records of the hours of operation of the engine that are recorded through the non-resettable hour meter. The permittee shall document how many hours are spent for emergency operation, including what classified the operation as emergency and how many hours are spent for non-emergency operation. If the engines are used for demand response operation, the permittee shall keep records of the notification of the emergency situation, and the time the engine was operated as part of demand response. [40 CFR 63.6655(f)] If additional hours are to be used for maintenance checks and readiness testing, the permittee shall maintain records indicating that Federal, State, or local standards require maintenance and testing of emergency RICE beyond 100 hours per year. [40 CFR 63.6640(f)(1)(ii)] The permittee shall keep records that demonstrate continuous compliance with each applicable operating limitation including, but not limited to, the manufacturer's emission- related operation and maintenance instructions or the permittee-developed maintenance plan. [40 CFR 63.6655(d), 40 CFR 63 Subpart ZZZZ Table 6] 56 Records of the maintenance conducted shall be kept in order to demonstrate that the permittee operated and maintained the affected emission unit and after-treatment control device (if any) according to their own maintenance plan. [40 CFR 63.6655(e)] The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in Table 8 of 40 CFR 63 Subpart ZZZZ. [40 CFR 63.6665] Records shall be maintained in accordance with 40 CFR 63.6660 and Provision I.S.1 of this permit. II.B.6.a.3 Reporting: The permittee shall report any failure to perform the work practice on the schedule required and the Federal, State or local law under which the risk was deemed unacceptable. [40 CFR 63 Subpart ZZZZ Table 2c Footnote 1] The permittee shall report each instance in which it did not meet an applicable operating limitation in 40 CFR 63 Subpart ZZZZ Table 2c. These instances are deviations from the operating limitations. These deviations shall be reported according to the requirements in 40 CFR 63.6650. [40 CFR 63.6640(b)] The permittee shall submit each report in 40 CFR 63 Subpart ZZZZ Table 7 as applicable. [40 CFR 63.6650(a)] If there are no deviations from any applicable operating limitations, the permittee shall submit a compliance report semiannually for affected emission units according to the requirements of 40 CFR 63.6650(b)(1)-(5) that contains the information required in 40 CFR 63.6650(c)(1)-(3) and a statement that there were no deviations from the operating limitations during the reporting period. [40 CFR 63 Subpart ZZZZ Table 7.1.a] If a deviation from any operating limitation occurs during the reporting period, the permittee shall submit a compliance report semiannually according to the requirements of 40 CFR 63.6650(b), (f) that contains the information required in 40 CFR 63.6650(c)(1)- (3), (d). [40 CFR 63 Subpart ZZZZ Table 7.1.b] If a malfunction occurs during the reporting period, the permittee shall submit a compliance report semiannually according to the requirements of 40 CFR 63.6650(b) that contains the information required in 40 CFR 63.6650(c)(1)-(4). [40 CFR 63 Subpart ZZZZ Table 7.1.c] The permittee shall comply with the applicable general provisions in 40 CFR 63.1-15 as identified in 40 CFR 63 Subpart ZZZZ Table 8. The permittee shall also report each instance in which it did not meet the applicable requirements in Table 8. [40 CFR 63.6640(e)] There are no additional reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. Maintenance requirements have been entered into the permittee’s preventative maintenance work order system. A non-resettable hour meter has been installed. Operating hours are recorded. 57 II.B.6.b Condition: At all times the permittee shall operate and maintain any affected source, including associated air pollution control equipment and monitoring equipment, in a manner consistent with safety and good air pollution control practices for minimizing emissions. The general duty to minimize emissions does not require the permittee to make any further efforts to reduce emissions if levels required by this standard have been achieved. Determination of whether such operation and maintenance procedures are being used will be based on information available to the Director which may include, but is not limited to, monitoring results, review of operation and maintenance procedures, review of operation and maintenance records, and inspection of the source. [40 CFR 63.6595(a)(1), 40 CFR 63.6605(b)]. [40 CFR 63 Subpart ZZZZ] II.B.6.b.1 Monitoring: Records required for this permit condition will serve as monitoring. II.B.6.b.2 Recordkeeping: The permittee shall keep the records described in 40 CFR 63.6655(a)(1)-(5) as applicable. [40 CFR 63.6655(a)] The permittee shall document activities performed to assure proper operation and maintenance. Records shall be maintained in accordance with 40 CFR 63.6660 and Provision I.S.1 of this permit. [40 CFR 63 Subpart ZZZZ] II.B.6.b.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. The facility appeared to be well maintained. II.B.7 Conditions on Gypsum Off-loading Conveyor (Emission unit# 49) II.B.7.a Condition: All conveyors and drop points shall be enclosed in a structure. Fugitive dust and emissions shall be minimized. [DAQE-AN102370028-18]. [R307-401-8] II.B.7.a.1 Monitoring: The permittee shall ensure the required covers are installed. II.B.7.a.2 Recordkeeping: A log shall be maintained for any periods of operation when the required covers are removed. 58 II.B.7.a.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. All conveyors and drop points are enclosed. II.B.8 Conditions on Refined Coal System (Emission unit # 50) II.B.8.a Condition: All conveyors, drop points, live coal handling and storage shall be enclosed in a structure. Fugitive dust and emissions shall be minimized. [DAQE-AN102370028-18]. [R307-401-8] II.B.8.a.1 Monitoring: The permittee shall ensure the required covers are installed. II.B.8.a.2 Recordkeeping: A log shall be maintained for any periods of operation when the required covers are removed. II.B.8.a.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. All conveyors and drop points are enclosed. II.B.8.b Condition: The amount of M45-PC-A used at the Refined Coal System shall be limited to 12, 533 tons per rolling 12-month period. [DAQE-AN102370028-18]. [R307-401-8] II.B.8.b.1 Monitoring: The permittee shall calculate a new 12-month total by the 20th day of each month using throughput data from the previous 12 months. Throughput shall be determined by purchase records or any other methods approved by the Director. II.B.8.b.2 Recordkeeping: The records of material throughput shall be kept on a daily basis and for all periods when the plant is in operation. 59 II.B.8.b.3 Reporting: There are no reporting requirements for this provision except those specified in Section I of this permit. Status: In compliance. The permittee discontinued using M45-PC-A in December, 2021. During the 12-month period ending March 30, 2024, the amount was 0 tons of M45-PC-A. II.C Emissions Trading (R307-415-6a(10)) Not applicable to this source. II.D Alternative Operating Scenarios. (R307-415-6a(9)) Not applicable to this source. II.E Source-specific Definitions. The following definitions apply to the permittee. They include terms not defined in state or federal rules or clarify or expand on existing definitions. II.E.1 Startup. Startup is defined as the period beginning with the introduction of fuel into the boiler and ending no later than when two coal feeders have been proven in service and the flue gas temperature at the outlet ducts to both sides of the baghouse outlet (Units #1, #2 or #3 boilers) have reached a temperature of 220oF and less than 20 percent of the boiler heat input is being furnished by fuel oil. II.E.2 Shutdown. Shutdown is defined as the period beginning when the unit load or output is reduced with the intent of removing the unit from service, or when the unit trips as the result of a sudden and unforeseen failure or malfunction and ending when fuel flow to the boiler ceases. II.E.3 Downtime. Downtime is that time between the end of shutdown and the beginning of startup in which the affected source has temporarily ceased operation. II.E.4 Planned Outage. Removing the equipment from service availability for inspection and/or general overhaul of one or more major equipment groups. This outage usually is scheduled well in advance. II.E.5 Maintenance Outage. The removal of equipment from service availability to perform work on specific components that can be deferred beyond the end of the next weekend, but requires the equipment be removed from service before the next planned outage. Typically, a Maintenance Outage may occur anytime during the year, have a flexible start date, and may or may not have a predetermined duration. 60 SECTION III: PERMIT SHIELD The following requirements have been determined to be not applicable to this source in accordance with Provision I.M, Permit Shield: III.A. 40 CFR, Part 60, Subpart O (NSPS for Sewage Treatment Plants) This regulation is not applicable to the Permitted Source for the following reason(s): an affected facility as defined in these regulations (incinerator that combusts wastes > 10% of sewage sludge or > 2205 lb/day of sewage sludge) is not located at this source III.B. 40 CFR, Part 60, Subpart OOO (NSPS for Non-metallic Mineral Processing) This regulation is not applicable to the Permitted Source for the following reason(s): the process of crushing and grinding nonmetallic minerals is not performed at this source III.C. 40 CFR, Part 60, Subpart Y (NSPS for Coal Preparation Plants) This regulation is not applicable to the Permitted Source for the following reason(s): the source does not include equipment to crush, break, screen, wet or dry clean, or thermal dry coal that is required for applicability as described in EPA applicability determination #NS48 dated 5/17/85 III.D. 40 CFR, Part 63, Subpart Q (NESHAP for Industrial Process Cooling Towers) This regulation is not applicable to the Permitted Source for the following reason(s): the cooling towers are not operated with chromium-based water treatment chemicals III.E. 40 CFR, Part 60, Subparts K, Ka, Kb (NSPS for Volatile Organic Liquid Storage Vessels) This regulation is not applicable to the Distillate Fuel Oil Tanks (Emission unit #28) for the following reason(s): the tanks were constructed prior to 1984. Subpart K, 60.111(b) and Ka, 60.111a(b) state that the standard does not apply to Nos. 2 through 6 fuel oils or diesel fuel oil III.F. 40 CFR, Part 60, Subpart Da (NSPS for Electric Utility Steam Generating Units for Which Construction is Commenced After September 18, 1978) This regulation is not applicable to the Steam Generating Unit #1 (Emission unit #1) for the following reason(s): this unit was constructed prior to September 18, 1978 III.G. 40 CFR, Part 60, Subpart Da (NSPS for Electric Utility Steam Generating Units for Which Construction is Commenced After September 18, 1978) This regulation is not applicable to the Steam Generating Unit #2 (Emission unit #2 for the following reason(s): this unit was constructed prior to September 18, 1978 61 III.H. 40 CFR, Part 60, Subpart D (NSPS for Fossil-Fuel-Fired Steam Generators for Which Construction is Commenced After August 17, 1971) This regulation is not applicable to the Steam Generating Unit #3 (Emission unit #3) for the following reason(s): 40 CFR 40(e) excludes facilities regulated by Subpart Da from regulation by Subpart D SECTION IV: ACID RAIN PROVISIONS IV.A Utah Acid Rain Program Authority. Authority to implement the Acid Rain Program is contained in R307-417, Permits: Acid Rain Sources, and R307-415-6a(4), Standard permit requirements [for operating permits]. Status: For informational purposes only. IV.B Permit Requirements. IV.B.1 The designated representative of the source and each affected unit at the source shall: IV.B.1.a Submit a complete Acid Rain permit application (including a compliance plan) under R307-417 and 40 CFR Part 72 in accordance with the deadlines specified in 40 CFR 72.30; and IV.B.1.b Submit in a timely manner any supplemental information that the Director determines is necessary in order to review an Acid Rain permit application and issue or deny an Acid Rain permit; IV.B.2 The owners and operators shall: IV.B.2.a Operate each affected unit at the source in compliance with a complete Acid Rain permit application or a superseding Acid Rain permit issued by the Director; and IV.B.2.b Have an Acid Rain Permit. Status: In compliance – The source is part of the Acid Rain program. IV.C Sulfur Dioxide Requirements. IV.C.1 The owners and operators of each affected unit at the source shall: IV.C.1.a Hold allowances, as of the allowance transfer deadline, in the unit's compliance subaccount (after deductions under 40 CFR 73.34(c)) not less than the total annual emissions of sulfur dioxide for the previous calendar year from the unit; and IV.C.1.b Comply with the applicable Acid Rain emissions limitations for sulfur dioxide. 62 IV.C.2 Each ton of sulfur dioxide emitted in excess of the Acid Rain emissions limitations for sulfur dioxide shall constitute a separate violation of the Act. IV.C.3 An affected unit shall be subject to the requirements under Provision IV.C.1. of the sulfur dioxide requirements as follows: IV.C.3.a Starting January 1, 2000, an affected unit under 40 CFR 72.6(a)(2); or IV.C.3.b Starting on the later of January 1, 2000 or the deadline for monitor certification under 40 CFR Part 75, an affected unit under 40 CFR 72.6(a)(3). IV.C.4 Allowances shall be held in, deducted from, or transferred among Allowance Tracking System accounts in accordance with the Acid Rain Program. IV.C.5 An allowance shall not be deducted in order to comply with the requirements under Provision IV.C.1.a. of the sulfur dioxide requirements prior to the calendar year for which the allowance was allocated. IV.C.6 An allowance allocated by the Administrator, USEPA, under the Acid Rain Program is a limited authorization to emit sulfur dioxide in accordance with the Acid Rain Program. No provision of the Acid Rain Program, the Acid Rain permit application, the Acid Rain permit, or the written exemption under 40 CFR 72.7 and 72.8 and no provision of law shall be construed to limit the authority of the United States to terminate or limit such authorization. IV.C.7 An allowance allocated by the Administrator, USEPA, under the Acid Rain Program does not constitute a property right. Status: In compliance – The source is part of the Acid Rain program. IV.D Nitrogen Oxides Requirements. The owners and operators for each affected unit at the source shall be compliance with the applicable Acid Rain emissions limitations for nitrogen dioxide. Status: In compliance – The source is part of the Acid Rain program. IV.E Monitoring Requirements. IV.E.1 The owners and operators and, to the extent applicable, designated representative of each affected unit at the source shall comply with the monitoring requirements as provided in 40 CFR Parts 74, 75, and 76. IV.E.2 The emissions measurements recorded and reported in accordance with 40 CFR Part 75 shall be used to determine compliance by the unit with the Acid Rain emissions limitations and emissions reduction requirements for sulfur dioxide and nitrogen oxides under the Acid Rain Program. 63 IV.E.3 The requirements of 40 CFR Parts 74 and 75 shall not affect the responsibility of the owners and operators to monitor emissions of other pollutants or other emissions characteristics at the unit under other applicable requirements of the Act and other provisions of the operating permit for the source. Status: In compliance – Acid Rain monitoring and reporting is performed. IV.F Recordkeeping and Reporting Requirements. IV.F.1 Unless otherwise provided, the owners and operators for each affected unit at the source shall keep on site at the source each of the following documents for a period of 5 years from the date the document is created. This period may be extended for cause, at any time prior to the end of 5 years, in writing by the Administrator, USEPA, or Director: IV.F.1.a The certificate of representation for the designated representative for the source and each affected unit at the source and all documents that demonstrate the truth of the statements in the certificate of representation, in accordance with 40 CFR 72.24; provided that the certificate and documents shall be retained on site at the source beyond such 5-year period until such documents are superseded because of the submission of a new certificate of representation changing the designated representative; IV.F.1.b All emissions monitoring information, in accordance with 40 CFR Part 75; IV.F.1.c Copies of all reports, compliance certifications, and other submissions and all records made or required under the Acid Rain Program; and, IV.F.1.d Copies of all documents used to complete an Acid Rain permit application and any other submission under the Acid Rain Program or to demonstrate compliance with the requirements of the Acid Rain Program. IV.F.2 The designated representative of each affected unit at the source shall submit the reports and compliance certifications required under the Acid Rain Program, including those under 40 CFR Part 72 Subpart I and 40 CFR Part 75. Status: In compliance – Acid Rain reporting is performed. IV.G Excess Emissions Requirements. IV.G.1 The designated representative of an affected unit that has excess emissions in any calendar year shall submit a proposed offset plan to the Administrator, USEPA, as required under 40 CFR Part 77. IV.G.2 The owners and operators of an affected unit that has excess emissions in any calendar year shall: IV.G.2.a Pay without demand the penalty required, and pay upon demand the interest on that penalty, to the Administrator, USEPA, as required by 40 CFR Part 77; and 64 IV.G.2.b Comply with the terms of an approved offset plan, as required by 40 CFR Part 77. Status: In compliance – No excess emissions were reported. IV.H Liability. IV.H.1 Any person who knowingly violates any requirement or prohibition of the Acid Rain Program, a complete Acid Rain permit application, an Acid Rain permit, or a written exemption under R307-417, 40 CFR 72.7 or 40 CFR 72.8, including any requirement for the payment of any penalty owed to the United States, shall be subject to enforcement pursuant to section 113(c) of the Act. IV.H.2 Any person who knowingly makes a false, material statement in any record, submission, or report under the Acid Rain Program shall be subject to criminal enforcement pursuant to section 113(c) of the Act and 18 U.S.C. 1001. IV.H.3 No permit revision shall excuse any violation of the requirements of the Acid Rain Program that occurs prior to the date that the revision takes effect. IV.H.4 Each affected source and each affected unit shall meet the requirements of the Acid Rain Program. IV.H.5 Any provision of the Acid Rain Program that applies to an affected source (including a provision applicable to the designated representative of an affected source) shall also apply to the owners and operators of such source and of the affected units at the source. IV.H.6 Any provision of the Acid Rain Program that applies to an affected unit (including a provision applicable to the designated representative of an affected unit) shall also apply to the owners and operators of such unit. Except as provided under 40 CFR 72.44 (Phase II repowering extension plans) and 40 CFR 76.11 (NOx averaging plans), and except with regard to the requirements applicable to units with a common stack under 40 CFR part 75 (including 40 CFR 75.16, 75.17, and 75.18), the owners and operators and the designated representative of one affected unit shall not be liable for any violation by any other affected unit of which they are not owners or operators or the designated representative and that is located at a source of which they are not the owners and operators, owners or operators, or the designated representative. IV.H.7 Each violation of a provision of 40 CFR Parts 72, 73, 74, 75, 76, 77, and 78 by an affected source or affected unit, or by an owner or operator or designated representative of such source or unit, shall be a separate violation of the Act. IV.H.8 The owners and operators of a unit governed by an approved early election plan shall be liable for any violation of the plan or 40 CFR 76.8 at that unit. The owners and operators shall be liable, beginning January 1, 2000, for fulfilling the obligations specified in 40 CFR Part 77. Status: For informational purposes only. 65 IV.I Effect on Other Authorities. No provision of the Acid Rain Program, an Acid Rain permit application, an Acid Rain permit, or a written exemption under 40 CFR 72.7 or 72.8 shall be construed as: IV.I.1 Except as expressly provided in Title IV of the Act, exempting or excluding the owners and operators and, to the extent applicable, the designated representative from compliance with any other provision of the Act, including the provisions of Title I of the Act relating to applicable National Ambient Air Quality Standards or the Utah State Implementation Plan; IV.I.2 Limiting the number of allowances a unit can hold; provided, that the number of allowances held by the unit shall not affect the source's obligation to comply with any other provisions of the Act; IV.I.3 Requiring a change of any kind in any State law regulating electric utility rates and charges, affecting any State law regarding such State regulation, or limiting such State regulation, including any prudence review requirements under such State law; IV.I.4 Modifying the Federal Power Act or affecting the authority of the Federal Energy Regulatory Commission under the Federal Power Act; or, IV.I.5 Interfering with or impairing any program for competitive bidding for power supply in a State in which such program is established. Status: For informational purposes only. EMISSION INVENTORY: Taken from DAQ’s 2022 emissions inventory database: Pollutant Code/CAS # Pollutant Name Emissions (tons, excluding tailpipe) Tailpipe Emissions (tons) Total Emissions (tons)* PM10-PRI PM10 Primary(Filt + Cond) 580.10483 0.14849 580.25332 PM10-FIL PM10 Filterable 474.26867 <.00001 474.26867 PM25-PRI PM2.5 Primary(Filt + Cond) 306.2462 0.14404 306.39024 PM25-FIL PM2.5 Filterable 200.32631 <.00001 200.32631 PM-CON PMCondensible 106.07399 <.00001 106.07399 SO2 Sulfur Dioxide 3,274.50013 0.00444 3,274.50456 NOX Nitrogen Oxides 9,517.27549 2.94465 9,520.22014 VOC Volatile Organic Compounds 116.0535 0.23418 116.28768 CO Carbon Monoxide 4,396.24281 1.18588 4,397.42869 7439921 Lead 0.07425 <.00001 0.07425 NH3 Ammonia 1.31103 <.00001 1.31103 CRITERIA AIR POLLUTANT (CAP) EMISSIONS TOTALS 66 Pollutant Code/CAS # Pollutant Name Is VOC/PM? Total Emissions (tons)* 107028 Acrolein (HAP) VOC 0.15996 7440360 Antimony (HAP) PM 0.01329 7440382 Arsenic (HAP) PM 0.01787 71432 Benzene (HAP) VOC 0.09156 100447 Benzyl Chloride (HAP) VOC 0.08683 7440417 Beryllium (HAP) PM 0.00143 117817 Bis(2-Ethylhexyl)Phthalate (HAP) VOC 0.10968 75252 Bromoform (HAP) VOC 0.07479 7440439 Cadmium (HAP) PM 0.02415 532274 2-Chloroacetophenone (HAP) VOC 0.01342 7440473 Chromium (HAP) PM 0.15339 7440484 Cobalt (HAP) PM 0.01519 57125 Cyanide (HAP) PM 4.79577 132649 Dibenzofuran (HAP) VOC 0.12797 77781 Dimethyl Sulfate (HAP) VOC 0.09204 121142 2,4-Dinitrotoluene (HAP) VOC 0.01234 106934 Ethylene Dibromide (HAP) VOC 0.00226 50000 Formaldehyde (HAP) VOC 0.01836 7647010 Hydrochloric Acid (HAP) - 6.52354 7664393 Hydrogen Fluoride (HAP) - 7.52429 7439965 Manganese (HAP) PM 0.23973 7439976 Mercury (HAP) - 0.00197 74839 Methyl Bromide (HAP) VOC 0.30698 74873 Methyl Chloride (HAP) VOC 1.0167 60344 Methylhydrazine (HAP) VOC 0.32532 108101 Methyl Isobutyl Ketone (HAP) VOC 0.13226 75092 Methylene Chloride (HAP) - 0.5563 7440020 Nickel (HAP) PM 0.15548 123386 Propionaldehyde (HAP) VOC 0.22851 7782492 Selenium (HAP) PM 0.39885 PREVIOUS ENFORCEMENT ACTIONS: None in the past 5 years. CURRENT STATUS & RECOMMENDATIONS: PacifiCorp’s Hunter Plant should be considered in compliance with the Title V permit conditions evaluated during this inspection. HPV STATUS: Not applicable HAZARDOUS AIR POLLUTANT (HAP) and/or OTHER POLLUTANT EMISSIONS TOTALS 67 RECOMMENDATIONS FOR NEXT INSPECTION: Inspect as usual ATTACHMENTS: VEO form