Spring Creek Well REPL-1 (WS004) Equipping - Review Comments File #12623
James Saunders <james.s@jonesanddemille.com>Thu, Apr 25, 2024 at 5:35 PM
To: "J. Paul Wright" <pwright@utah.gov>, Daniel Hawley <daniel.h@jonesanddemille.com>
Cc: Heather Pattee <hpattee@utah.gov>, "tracyfeltner04@gmail.com" <tracyfeltner04@gmail.com>, Hunter Cornelius
<hunter.c@jonesanddemille.com>
Paul,
Thanks for your review. We have addressed your comments and have made some clarifications to the
drawings and the manual. We have talked with Heather and All Wells, and we intend to change order this
work into All Wells well drilling contract. This will save the project time and cost from bidding this work out.
Below are our responses to your comments.
Thanks,
James
1. Sheet C102 says that the 3" pump to waste line will be "reinstalled". Is there a detail of how this is configured? I
need to be sure that at its discharge point it is downturned, has an adequate freefall to the ground or receiving
basin, and that the end is covered with a #4 mesh screen.
a. Detail D1 on Sheet C503 has been added for clarity. The discharge will be downturned and screened.
2. On Sheet C103, is the air valve that will be reinstalled downturned and with a #14 mesh screen on the end?
a. Detail A1 on Sheet C103 has been updated to indicate a #14 mesh screen.
3. Is the sample tap to be reinstalled a smooth nosed sample tap?
a. The sample tap is smooth nosed.
Let me know if you have any questions.
Thanks,
James
James Saunders, PE
Project Engineer
Jones & DeMille Engineering, Inc.
p: (435) 637-8266 | m: (435) 757-0308
[Quoted text hidden]
5/1/24, 8:32 AM State of Utah Mail - Spring Creek Well REPL-1 (WS004) Equipping - Review Comments File #12623
https://mail.google.com/mail/u/0/?ik=f3bcb897f8&view=pt&search=all&permmsgid=msg-f:1797351715983629155&simpl=msg-f:1797351715983629155 1/3
From: J. Paul Wright <pwright@utah.gov>
Sent: Wednesday, April 17, 2024 3:15 PM
To: Daniel Hawley <daniel.h@jonesanddemille.com>
Cc: James Saunders <james.s@jonesanddemille.com>; Heather Pa ee <hpattee@utah.gov>;
tracyfeltner04@gmail.com
Subject: Spring Creek Well REPL-1 (WS004) Equipping - Review Comments File #12623
Daniel and James,
I have reviewed the plans that were submitted for equipping this replacement well. It appears, in general, that the plan is
to use the discharge piping and valving from the existing well. I have a couple of comments/questions based on what was
shown in the plans:
1) Sheet C102 says that the 3" pump to waste line will be "reinstalled". Is there a detail of how this is configured? I need
to be sure that at its discharge point it is downturned, has an adequate freefall to the ground or receiving basin, and that
the end is covered with a #4 mesh screen.
2) On Sheet C103, is the air valve that will be reinstalled downturned and with a #14 mesh screen on the end?
3) Is the sample tap to be reinstalled a smooth nosed sample tap?
Once I have confirmation that these items are compliant, I can move forward with preparing the equipping plan approval
letter.
Paul
On Mon, Mar 18, 2024 at 3:41 PM Daniel Hawley <daniel.h@jonesanddemille.com> wrote:
Good Afternoon Paul,
We have been working with Spring Creek to wrap up a project where they had drilled a new well. The last item
remaining on the project is to tie the new well into the system. Sorry for the delay on this one. The Owner was
investigating options to increase flow and put in a larger pump which would require larger power to the pump house.
They don’t need that and with the remaining funding be tight they plan to just take the pump from the old well and
install it and then just raise the existing piping in their building so that it is over 18 inches off the floor.
Should we send that to you or go through Heather Pattee to send the drawings for review?
Thanks Paul,
5/1/24, 8:32 AM State of Utah Mail - Spring Creek Well REPL-1 (WS004) Equipping - Review Comments File #12623
https://mail.google.com/mail/u/0/?ik=f3bcb897f8&view=pt&search=all&permmsgid=msg-f:1797351715983629155&simpl=msg-f:1797351715983629155 2/3
Daniel Hawley, PE
Project Manager
Jones & DeMille Engineering, Inc.
p: (435) 637-8266 | m: (435) 201-2507
Shaping the Quality of Life.
--
J. Paul Wright, P.E. | District Engineer | Southwest Utah District
435.986.2590 (office) | 435.680.0163 (cell) | 435.986.2595 (fax)
620 S 400 E #400, St. George, UT 84770
DEQ WEBSITE
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
3 attachments
2009-071 Project Drawings.pdf
4619K
2009-071 Well Equipping Bid Schedule.pdf
13K
2009-071 Well Equipping Project Manual.pdf
2066K
5/1/24, 8:32 AM State of Utah Mail - Spring Creek Well REPL-1 (WS004) Equipping - Review Comments File #12623
https://mail.google.com/mail/u/0/?ik=f3bcb897f8&view=pt&search=all&permmsgid=msg-f:1797351715983629155&simpl=msg-f:1797351715983629155 3/3