April 30, 2024
Mr. Hong-Lei Tao
Utah Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, UT 84114
Mr. Brett Gurney, Program Manager
Utah State Fuel Network
PO Box 141152
Salt Lake City, UT 84114
Re: Work Plan and Budget OCL-03 for Monitoring Wells Abandonment
Utah Department of Transportation Tabiona Maintenance Station No. 3433
3652 North 37900 West, Tabiona, Utah
Facility Identification No. 9000145, Release OCL
Dear Mr. Tao and Mr. Gurney:
WSP USA Environment & Infrastructure Inc. (WSP) is pleased to present this Work Plan and Budget (WP&B) for
monitoring wells abandonment at the Utah Department of Transportation (UDOT) Station No. 3433 (Site), located at
3652 North 37900 West, Tabiona, Utah. The Site has Facility ID No. 9000145, Release OCL. This WP&B was prepared
in response to the Utah Division of Environmental Response and Remediation (DERR) request via email
communication on April 25, 2024.
The Site is the location of two former underground storage tanks (USTs) that were closed by removal on October
12, 2021. In November 2022, at the request of the DERR, WSP completed a Site investigation by installing four
monitoring wells in the vicinity of the former UST basin and collecting soil and groundwater samples to determine
the degree and extent of contamination. In November 2023 WSP collected additional groundwater samples from
the monitoring wells at the Site. Findings of these investigations were summarized in Site Investigation Report
(SIR) dated March 16, 2023 and Groundwater Monitoring Report dated February 6, 2024, respectively.
Based on the findings of the SIR and the 2023 Groundwater Monitoring Report, the DERR determined that no
further action is required at the Site (DERR document ERRL-0139-24, dated April 10, 2024).
For the purposes of properly abandoning the four monitoring wells at the Site, as required in the Utah Rules (R655-
4), WSP will sub-contract a Utah licensed well driller who will perform the following tasks:
• Submit the required notification and reporting to the Division of Water Rights.
• Plug the wells in place with 30% solids grout from the bottom of the well to the surface via tremie pipe
using grout pump.
• Complete the surface with concrete.
10876 South River Front Parkway
Suite 250
South Jordan, Utah 84095
wsp.com
Page | 2
The total estimated cost to complete the monitoring well abandonment is $6,975. Estimated costs detail is provided
in Table 1 and include costs for this WP&B preparation, subcontractor procurement, field oversight, documentation
and reporting, and submittal of the petroleum trust fund reimbursement package. Subcontractor costs are based on
bids received and included in Table 1. Backup documentation for bids received for this WP&B are included as an
attachment to this document.
WSP is prepared to mobilize to the Site within 15 business days after receiving DERR and SFN approval for the
WP&B. Work will be performed on a time and materials basis. Labor rates are based on the DERR Cost Guidelines for
Utah Underground Storage Tank Sites, as updated January 2023. No activities will be performed outside the
proposed SOW and budget without prior approval from the DERR.
Please contact Ehud Ardon at ehud.ardon@wsp.com if you have questions or comments regarding this WP&B.
Respectfully submitted,
WSP USA Environment & Infrastructure Inc.
Submitted By: Reviewed By:
Ehud Ardon Bryan Morse
Senior Environmental Scientist Environmental Service Line Lead
Certified UST Consultant # CC-279
Attachments:
Table 1: Cost Estimate
Documentation of Subcontractor Bids
PST Trust Fund Work Plan Approval Application and Agreement
Work Plan and Budget OCL-02
August 2023
Activity Cost
Senior Project Manager (P101) - WP&B, claim package review ####hour $152.00 hour 1,216.0$
PST Claim Specialist (P108)1 hour $78.00 hour 78.0$
Administrative Assistant (P109) - subcontractor procurement 2 hour $62.00 hour 124.0$
Senior Project Manager (P101) - kickoff meeting, documents review ####hour $152.00 hour 456.0$
Field Scientist (P104) - travel, oversight, documentation 16 hour $101.00 hour 1,616.0$
Mileage (RT from South Jordan)239 miles $0.67 mile 160.0$
Driller subcontractor 1 LS $4,750.00 each 3,325.0$
6,975.0$
^methyl tert-butyl ether, benzene, toluene, ethylbenzene, xylene, naphthalene
Monitoring Wells Abandonment
WP&B Total
Labor
Expenses
Subcontract
Hours or Units Hourly or Unit Rate
WP&B Preparation and Project Administration
Table 1: Cost Estimate for OCL-03
UDOT Maintenance Station No. 3433
3652 North 37900 West, Tabiona, Utah
Facility Id No. 9000145, Release OCL
4/29/2024
Well Abandonment - 2381400502
WSP
10876 S River Front Parkway, Ste 250
South Jordan, UT 84095
Ehud Ardon
ehud.ardon@wsp.com Tabiona
UT
Cascade Rep Contact Information
Scope of Work
Quantity Unit Sales Price Subtotal
1 Lump Sum 450.00$ 450.00$
4 Each 25.00$ 100.00$
Day 400.00$ -$
1 Day 2,550.00$ 2,550.00$
Boring Abandonment - Material 225 Feet 1.00$ 225.00$
55 Gallon Reconditioned DOT Drum Each 160.00$ -$
Pre-Tax Total
Tax Percentage
Taxes
Quote Total
Utah: 5718 W AXEL PARK RD, WEST JORDAN UT 84081 ♦ (801) 542-7159
$3,325.00
This quote is based on information provided by you and is valid for 45 days from the bid date. Unless previously agreed, Cascade requires a 2-week notice prior to
mobilization. Your firm is responsible for 1) Obtaining any site specific permits, 2) Locating and clearly marking underground installations or utilities, 3) Furnishing dig
Alert numbers at least three working days prior to scheduled start date and proof of private locating services, 4) Obtaining access to site with no overhead wires within
20' of the holes. Cascade Drilling shall not be responsible for damages to underground improvements not clearly and accurately marked. If bedrock, cobbles, flowing
sands or other adverse or unsafe drilling conditions are encountered, drilling may continue on a time and materials basis or be terminated at the discretion of Cascade.
Additional costs may apply if scope is significantly changed. Well development by others may void some or all of Cascade warranties of workmanship and materials.
Prices assume standard labor rates and no work hour restrictions.
Number
Prepared By Trent Castner Email tcastner@cascade-env.com
Description
$3,325.00
Mobilization/Demobilization - Sonic
Abandonment Logs
Per diem
Abandonment Drilling Daily Rate - Up to 10 Hours per Day
Account Name Bid Date
Address Quote Number
Quote Revision Date
Bill To Account Project Zip
Project Name
Contact Name Project Address
Email Project City
Phone Project State(801) 448-1559
Four (4) monitoring wells will be abandon in place using bentonite chips
• The flush manholes will remain in place, the inside of the monument will be filled with concrete
• ROW and Traffic Control if required will be provided by others
Expect reasonable drill rig access. Well and borings seals that take more than 125%-hole volume, will be sealed on a time and material basis. Assume 7:00AM to
5:30PM work hours and no prevailing wage requirements.
WSP 4/29/2024
10876 S River Fon Parkway, Ste 250
South Jordan, UT 84095
Well Abandonment - 2381400502
Ehud Ardon
ehud.ardon@wsp.com Tabiona
UT
Cascade Rep Contact Information
Number
Prepared By Trent Castner Email tcastner@cascade-env.com
Account Name Bid Date
Address Quote Number
Quote Revision Date
Bill To Account Project Zip
Project Name
Contact Name Project Address
Email Project City
Phone Project State(801) 448-1559
Signature of Authorized Cascade Representative
Name & Title of Authorized Cascade Representative
Date Date
Name & Title of Authorized Representative and Company
Cascade provides management of investigation derived waste. Call us today for information on a full range of additional
options to meet your drilling needs.
Signature of Client/Owner Authorized Representative
Cascade will perform the Work as described in this proposal subject to the terms and conditions posted at https://www.cascade-env.com/resources/other/terms-and-
conditions/ unless MSA is already established between Cascade and Client in which case MSA takes precedence over the aforementioned terms and conditions. By
signing this proposal, Client agrees that this proposal together with the terms and conditions referenced above constitute a Subcontract. Client acknowledges that
Client has received and agrees with all such documents in the form provided by Cascade. Terms and Conditions are posted and accessible at the website location set
forth above.
Pacific West Environmental & Infrastructure, LLC
P.O. Box 70
Azle, TX 76098 US
+1 2148842096
poates@pwenviro.com
Estimate
ADDRESS
WSP USA
4139 Oregon Pike
Ephrata, PA 17522
SHIP TO
WSP USA
UDOT Station
Project #2381400502
Tabiona, UT
ESTIMATE #DATE
214341 04/26/2024
ACTIVITY QTY RATE AMOUNT
Drilling
Mobilization
1 1,200.00 1,200.00
Drilling
Grout Pump Rental Day Rate
1 550.00 550.00
Drilling
Plug and Abandon 2-inch Monitor Well
4 750.00 3,000.00
project # 2381400502
Includes Plugging and Abandoning Three (3) Monitor wells (2-inch) to 55 feet
and one (1) monitor well (2-inch) to 60 feet.
PVC well casing will be plugged in place with 30% solids grout from TD to
surface.
Grout will be placed via tremie pipe using a grout pump.
Manhole Ring will remain in place as well.
All work will be overseen by a licensed utah water well driller. State well
abandonment reports will be provided.
TOTAL $4,750.00
Accepted By Accepted Date
20-1339913 | www.directpushservices.com
Direct Push Services LLC
PO Box 25784
Salt Lake City, UT 84125
(801)230-1721
sean@directpushservices.com
Estimate
ADDRESS
Ehud Ardon
WSP USA
10876 S River Front
Parkway, Suite 250
South Jordan, Utah 84095
USA
ESTIMATE #240152
DATE 04/30/2024
EXPIRATION DATE 08/31/2024
P.O. NUMBER SALES REP
Tabiona Well Abandonment Sean Bromley
DATE ACTIVITY QTY RATE AMOUNT
Per Foot Abandonment of 2" monitoring wells below 30'.
Each well is assumed to be 55' bgs and will be abandoned
per Utah Code R655-4-14
220 20.00 4,400.00
Mob/Demob 1 550.00 550.00
Site 1: UDOT Station in Tabiona, Utah- reference project #
2381400502.
Site includes 4 monitoring wells at total depth of 55 feet (3 wells)
and 60’ (one well).
Wells are flush mounted in asphalt pavement with 8” surface
casing.
Complete with the following:
All work must be overseen by a licensed Utah water well driller.
Submit required notification and reporting to the Division of Water
Rights.
Plug wells in place with 30% solids grout from TD to surface via
tremie pipe using grout pump.
Manhole ring may remain in place; complete the surface with
Quikrete or similar.
TOTAL $4,950.00
Accepted By Accepted Date
Petroleum Storage Tank Trust Fund
Work Plan Approval Application and Agreement
Work Plan No. __________, Amendment No. __________
Facility Name: ____________________________________
Address: _________________________________________
Facility ID No.: ____________________________________
Release ID: _______________________________("Release")
Owner/Operator, responsible party, or other person seeking PST Trust Fund Reimbursement:
_________________________________________________________________________("Claimant")
Utah-Certified UST Consultant: ______________________________________________("Contractor")
In submitting Work Plans_____________________ and amendments thereto for the above referenced
Release ___________ for approval, the Claimant and the Contractor collectively, the "Parties," represent
and agree to the following:
Definitions:
"Contractor" means the person identified as such above.
"Claimant" means the person identified as such above.
“Parties” means Claimant and Contractor.
"Division Director" means the Division Director of the Division of Environmental Response and
Remediation.
“PST Fund" means the Petroleum Storage Tank Trust Fund.
"Release" means the release identified above.
"State" means the State of Utah including its agencies, officers, employees, volunteers and specifically,
the Division of Environmental Response and Remediation (DERR), the Division Director of the
Division or Environmental Response and Remediation, and the Petroleum Storage Tank Trust Fund.
"Work Plan" means the work plan identified above.
1. The key personnel, for which qualifications are submitted under R311-207-3(c), are:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
2. The Claimant acknowledges that the Claimant is required to obtain a payment bond from the
Contractor under Section 14-2-1 of the Utah Code. If the Claimant fails to do so, the Claimant is
liable to each person who performed labor or services or supplied equipment or materials
("Subcontractors") in the event the Contractor does not pay the subcontractors, even if the Claimant
has paid the Contractor (Utah Code Section 14-2-2). The Claimant acknowledges and agrees that the
PST Fund will not reimburse the Claimant for such Subcontractors’ claims for payment against the
Claimant if the PST Fund has already made payment to the Claimant or Contractor. The Claimant
understands that the premium paid for a payment bond is reimbursable. Therefore, the Claimant:
a.Has required the Contractor to obtain 100 percent payment bond through a United States
Treasury-listed bonding company, and attached a copy, or;
b. Has obtained other equivalent assurance and waives all claims and remedies against the
State if the equivalent assurance does not adequately protect the Claimant.
The equivalent assurance is described as follows:
________________________________________________________________________
________________________________________________________________________
________________________________________________________________________
3. The Parties agree that the Contractor shall have no cause of action against the State for payment.
The Parties acknowledge and agree that the State is not a party to any contract with the Claimant or
the Contractor for reimbursement from the PST Fund in the execution of this Work Plan, except to
the extent provided by a contract signed by the Division Director. Instead, the Claimant’s
reimbursement is governed by the Utah Underground Storage Tank Act and the Utah Underground
Storage Tank Rules. The Contractor is entitled to reimbursement solely under his/her contract with
the Claimant.
4. The Parties agree that they will use a subcontracting method consistent with the requirements of
R311-207.
5. The Parties agree that, as a condition of performing the work under the work plan, the Contractor
shall carry the insurance specified in R311-207-3(c)(4). The Contractor represents that the
Certificate of Insurance documenting the required insurance is attached or that a current certificate is
on file with the Division Director and has been provided to the Claimant. The Parties assume the
risk and responsibility of ensuring that the appropriate insurance coverage is in place.
6. The Parties agree that payments from the PST Trust Fund shall be limited to amounts that are
customary, legitimate, reasonable and consistent with R311-207. Unless the Parties and the Division
Director have entered into a written Pay-for-Performance agreement, the Parties acknowledge that
payments will be for actual time and materials expended up to, but not exceeding, the amount of the
Division Director approved work plan and Division Director approved change orders, if any.
7. The Parties shall maintain financial and operation records in sufficient detail to document all
transactions relating to PST Fund reimbursement for the execution of this work plan. The Parties
shall make available for audit and inspection all such records relating to the completion of the work
plan and related services, requirements, and expenditures until all audits initiated by State auditors
are completed, or for a period of five years from the date of PST Fund reimbursement related to the
execution of this work plan. Records which relate to disputes, litigation, or the settlement of claims
arising out of the performance of this work plan, or to cost and expenses of this work plan as to
which exception has been taken by the Division Director, shall be retained by the Parties until
disposition has been made of such disputes, litigation, claims, or exceptions.
8. The Parties certify that there is a contract between the Claimant and the Contractor for the
performance of work under the work plan for which approval is sought ("Contract") and incorporate
the provisions herein into that Contract. To the extent that the Contract or amendments thereto
conflict with any provisions herein, the provisions herein govern. The Parties shall provide the
Contract to the Division Director upon request.
9. The Division Director is a third party beneficiary of this Petroleum Storage Tank Trust Fund Work
Plan Approval Application and Agreement and may enforce its provisions.
10. This Petroleum Storage Tank Trust Fund Work Plan Approval Application and Agreement does not
limit the Division Director’s rights and remedies under applicable law.
Contractor______________________________________________________________________
Signature, Printed Name, and Date
Claimant_______________________________________________________________________
Signature, Printed Name, and Date
Brett Gurney,
Ehud Ardon 04/30/2024