Loading...
HomeMy WebLinkAboutDRC-2009-003102 - 0901a0688012bd2e•p.l?^u> (::£.C'.^CfvOOZiO-J- DENISON^i MINES Danison Mines (USA) Corp. 10S0 17th Street, Suite 950 Denver, CO 8026S USA Tel: 303 628-7798 Fax : 303 389-412S www.denisonmine8.com July 27, 2009 VIA E-MAIL AND OVERNIGHT DELIVERY Mr. Dane L. Finerfrock Executive Secretary Utah Radiation Control Board Department of Environmental Quality 168 North 1950 West PO Box 144810 Salt Lake City, Utah 84114-4810 '„'^^s2^zo BeceWe^ Kadw^^o" Com Re: Denison Mines (USA) Corp. State of Utah 11e.(2) Byproduct Material License # UT1900479 White Mesa Mill, Blanding, Utah License Condition Number 9.5 - Surety Update - REVISION Dear Mr. Finerfrock: Pursuant to License Condition No. 9.5 of State of Utah 11e.(2) Byproduct Material License #UT1900479, please find enclosed two (2) copies, and a CD containing a scanned image, of the newly revised reclamation and decommissioning cost estimate in support of the surety bond on the White Mesa Mill. The revision is in response to the May 21, 2009, letter from Dave Rupp, requesting clarification and additional information on the February 2009 surety update. Individual comments from Mr. Rupp are restated, in italics, below, followed by an explanation of the changes or modifications made to the cost estimate. 1. Under the Mill Decommissioning tab in the report, please include the costs for: a. The decommissioning and removal of all additional new tank facilities. Additional costs have been included in the Mill Decommissioning section, "Misc. Tankage & Spare Parts Removal", of the estimate, to cover the demolition and disposal of the newly constructed uranium and vanadium SX feed tanks and the SX raffinate tank. The total manpower and equipment hours were increased by 50% to cover the additional work effort required. Letter to Dane Finerfrock July 27, 2009 Page 2 Under the Mill Decommission section, a new task has been added for removal of the newly constructed Alternate Feed Circuit. b. Decommissioning and closure of all septic tanks and their associated drain fields. Under the Mill Decommission section, a new task has been added for removal of the septic tanks and drain fields. c. Appropriate seed for revegetation of the mill yard and ore pads. Costs have been added for seed mix under the Mill Decommissioning section, "Revegetate Mill Yard & Ore Pad", to cover the purchase cost of seed mix. The cost and application rate is based on current information from our ongoing reclamation activities at Denison's mining and exploration sites. The average seed cost has been $21.50 per pound, applied at 15 pounds per acre. d. Equipment maintenance costs for disposal of Cameco and Honeywell barrels. Equipment maintenance costs were included for other alternate feeds. Under the Mill Decommission section, equipment maintenance costs have been included for disposal of the Cameco and Honeywell alternate feed barrels. e. Equipment maintenance costs for demolition of the two new decontamination pads. Under the Mill Decommission section, equipment maintenance cost has been added for demolition and disposal of the materials from the two (2) decontamination pads. 2. Under the Rock Production tab in the report: a. The estimate shows 146,000 CY of rip-rap type rock will be required. The Bureau of Land Management (BLM) public pit is listed as the source of rock. There is no purchase cost listed for the rock, and no cost for satisfying NEPA requirements for such a large size removal of material from BLM property. Please justify why there will be no purchase cost for the material, no NEPA costs related to BLM, and provide supporting documentation from the BLM. In lieu of these items please incorporate the appropriate corresponding costs in the estimate. We spoke with Ted McDougle of the Monticello, Utah ,BLM office. Ted indicated that the "public pit" material is sold on the basis of fair market value, with the current cost being $0.50 per bank cubic yard. He indicated that there are several pits located near the White Mesa Mill and all of them would be available for rock production. There would be no permitting cost unless a new pit was located and opened for production. A cost of $0.60 per bank cubic yard has been included in the estimate to cover the cost of the material and any additional costs for access or clearance issues. OENISO MINES l/)jj Letter to Dane Finerfrock July 27, 2009 Page 3 b. From the submittal DUSA received from Power Motive Corporation, it appears two conveyors are necessary to stack the two separate screened products, rather than only the one included in the estimate. Also, the screen cloth setup expense of $2,000 was not included in estimate. Costs have been added under the Rock Production section for rental of an additional conveyor, and for the setup expense of the screen cloth. 3. Under the Miscellaneous Costs tab, please include: a. Demobilization of all power equipment from North Central Rental and Leasing (NCRL). Attachment A in the February 2, 2009 letter from NCRL has a table, which lists the "Total Freight Charges To and From," and a double asterisk footnotes states this "Includes Assembly and Disassembly." However, under the Equipment Costs tab, on page 2 ofthe February 2, 2009 NCRL letter, it states, "Denison would be responsible for demobilization including disassembly and return freight on all machines. Parts, vehicles and equipment, at the end, or at time during the rental period to Rapid City, S.D." Please add appropriate related demobilization costs for the power equipment, and clarify this issue, if necessary, by providing supporting documentation from NCRL. Attachment A to the equipment quote from NCRL includes the total freight charges for delivery of the equipment to the White Mesa Mill site and for freight charges back to Fargo, ND. The note is included that the "Total Freight Charges To & From" includes assembly of the equipment upon arrival at the White Mesa Mill site, and disassembly of the equipment for shipment back to Fargo, ND. Adding an additional demobilization cost would result in doubling ofthe demobilization cost. All mobilization and demobilization costs, including assembly and disassembly were included in the February 2009 estimate. b. Mobilization and demobilization (mob/demob) charges for NCRL maintenance service personnel and vehicles of $30,820 each way. (Per page 2 of the February 2, 2009 NCRL letter and Attachment A). Mobilization and demobilization charges for NCRL maintenance service personnel and vehicles of $30,820 each way has been added to the estimate c. Mob/demob ofthe PC300 excavator with shears from WRS rental services. Include documentation from the company. Mob/demob cost of $2,275 for the PC300 excavator with shears has been added to the estimate. A revised quote from WRS Rental Services is included in the updated estimate. d. Probable costs for damages, including glass breakages, bent rails, ladders, fenders, etc., as well as tire wear on applicable NCRL power equipment, as well as service vehicles, per page 3 ofthe February 2, 2009 letter from NCRL. Costs for damages, including glass breakages, bent rails, ladders, fenders, etc., are considered abuse items and would not be paid by a responsible project manager or owner. Equipment abuse is a training DENiSO MINES •Ai Letter to Dane Finerfrock July 27, 2009 Page 4 and management issue for the contractor and should be covered out of his profit and overhead allowance for the project. Costs for tire wear and replacement has been added to the hourly operating cost for the NCRL equipment at $4.00 per operating hour. This rate is based on information from KGL Associates, Inc., a contractor with extensive experience utilizing NCRL equipment. A copy of the correspondence with KGL Associates is attached to the estimate. e. Material costs for repair of ground engaging tools (G.E. T.) and replacement of G.E. T. with new tools after completion ofthe work, per page 3 ofthe February 2, 2009 NCRL letter. Costs for ground engaging tools such as cutting edges and bucket teeth have been added to the hourly operating cost for the NCRL equipment at $1.00 per operating hour. This rate is based on information from KGL Associates, Inc., a contractor with extensive experience utilizing NCRL equipment. A copy of the correspondence with KGL Associates is attached to the estimate. f. Fuel for service vehicles, per top of page 3 of the February 2, 2009 letter from NCRL. Fuel for the NCRL service vehicles has been added to the estimate. The consumption was estimated at 20 gallons per day, 21 days per month. Additional costs have also been included for the disposal cost of the estimated volume of conventional ore that will be stored on the ore pad at the end of the year. This revision was due to a recent change in the projected rhilling rate for the remainder of 2009. The revision was made to ensure that the company is in compliance with conditions of the Groundwater Discharge Permit. The revised reclamation estimate and surety amount is $15,560,808, which is an increase from the current approved surety amount of $15,017,128. The attached estimate represents a total revision to Attachment C of Revision 3.0 to the approved July 2000 Reclamation Plan. If you have any questions on the attached revised reclamation and decommissioning cost estimate please feel free to contact me at (303) 389-4132. Yours very truly, DENisofj Mn^s (USA) CORP. Jen p. Landau "Manager Environmental Affairs Enclosures cc: Ron F. Hochstein, w/ attachment Harold R. Roberts, w/ attachment Rich E. Bartlett, w/ attachment David Turk, w/o attachment DENISO MINES tf^mM OEN.SONI)~ MINES Denison Minos (USA)Corp. 1050 171h Stree~Suite 950 Denver,CO 80265 USA rei:303 628·7798 Fax:303 389-4125 www.denisonmines.com Revised Cost Esti mates for Reclamation of the White Mesa Mill and Tailings Management System Blanding,Utah July 2009 State of Utahlle.(2)Byproduct Material License #UT1900479 Copy 1 Slale of Utah Denison Mines (USA)Corp. www.denisonmines.com 1050 17th Street,Suite 950 Denver.CO.USA 80265 rei:303 628·7798 Fax:303 389-4125 Cost Summary WHITE MESA MILL RECLAMATION COST ESTIMATE July 2009 Revision Mill Decommissioning Cell 1 Cell 2 Cell 3 Cell4A Miscellaneous Subtotal Direct Costs Profit Allowance Contingency Licensing &Bonding UDEQ Contract Administration Long Term Care Fund Total Reclamation Revised Bond Amount 7/27/2009 -9:21 AM -WMM Rec Plan Est July 2009 (1).xls $2,073,092 $1,747,835 $1,513,709 $1,908,627 $1,427,814 $2,614,790 $11,285,867 10.00%$1,128,587 15.00%$1,692,880 2.00%$225,717 4.00%$451,435 $776,322 $15,560,808 $15,560,808 Denison Mines (USA)Corp. White Mesa Mill Mill Decommissioning MILL DECOMMISSIONING MILL DECOMMISSIONING Mill Building Demolition Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 720 $13,273 Mechanics hrs $15.59 640 $9,976 Laborers hrs $12.17 320 $3,895 Small Tools hrs $1.35 960 $1,296 Cat 769 Haul Truck hrs $93.45 640 $59,808 Truck Drivers hrs $16.23 640 $10,387 Cat 988 Loader hrs $133,06 160 $21,289 Cat 365 Excavator hrs $128.54 160 $20,567 Cat 330 wi PC-400 metalShears hrs $172.17 160 $27,547 65 Ton Crane hrs $96.82 160 $15,492 30 Ton Crane hrs $59.58 80 $4,767 Equipment Maintenance (Butler)hrs $18.58 1,360 $25,274 Concrete Removal sf $3.30 37,500 $123,750 Total Mill Building Demolition $337,321 Task CostTaskUnitsCost/UnitUnits Ore Feed Demolition Resource Description Equipment Operators hrs $18.43 48 $885 Mechanics hrs $15.59 64 $998 Laborers hrs $12.17 32 $390 Small Tools hrs $1.35 96 $130 Cat 769 Haul Truck hrs $93.45 64 $5,981 Truck Drivers hrs $16.23 64 $1,039 Cat 988 Loader hrs $133.06 16 $2,129 Cat 365 Excavator hrs $128.54 16 $2,057 Cat 330 wi PC-400 metalShears hrs $172.17 16 $2,755 30 Ton Crane hrs $59.58 0 $0 Equipment Maintenance (Butler)hrs $18.58 112 $2,081 Total Ore Feed Demolition $18,443 SX BUilding Demolition Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 240 $4,424 Mechanics hrs $15.59 320 $4,988 Laborers hrs $12.17 160 $1,948 Small Tools hrs $1.35 480 $648 Cat 769 Haul Truck hrs $93.45 320 $29,904 Truck Drivers hrs $16.23 320 $5,194 Cat 988 Loader hrs $133.06 80 $10,645 Cat 365 Excavator hrs $128.54 80 $10,283 Cat 330 wi PC-400 metalShears hrs $172.17 80 $13,774 65 Ton Crane hrs $96.82 0 $0 30 Ton Crane hrs $59.58 0 $0 Equipment Maintenance (Butler)hrs $18,58 560 $10,407 Concrete Removal sf $3.30 55,970 $184,701 Total SX BUilding Demolition $276,915 7127/2009 -11 :12 AM·WMM RecPlan EstJuly2009(1).xls Denison Mines(USA)Corp. White Mesa Mill MILL DECOMMISSIONING CCD Circuit Removal Resource Description Units CosVUnit Task Units Task Cost Equipment Operators hrs $18.43 135 $2,489 Mechanics hrs $15,59 120 $1,870 Laborers hrs $12,17 60 $730 Small Tools hrs $1,35 180 $243 Cat 769 Haul Truck hrs $93.45 120 $11,214 Truck Drivers hrs $16.23 120 $1,948 Cat 988 Loader hrs $133,06 30 $3,992 Cat 365 Excavator hrs $128,54 30 $3,856 Cat 330 wi PC-400 metalShears hrs $172.17 30 $5,165 65 Ton Crane hrs $96,82 30 $2,905 30 Ton Crane hrs $59,58 15 $894 Equipment Maintenance (Butler)hrs $18.58 255 $4,739 Concrete Removal sf $3.30 15,000 $49,500 Total CCD Circuit Removal Sample Plant Removal Resource Description Units CosVUnit Task Units $89,545 Task Cost Equipment Operators hrs $18.43 24 $442 Mechanics hrs $15.59 32 $499 Laborers hrs $12.17 16 $195 Small Toots hrs $1,35 48 $65 Cat 769 Haul Truck hrs $93.45 32 $2,990 Truck Drivers hrs $16.23 32 $519 Cat 988 Loader hrs $133.06 8 $1,064 Cat 365 Excavator hrs $128.54 8 $1,028 Cat 330 wi PC-400 metalShears hrs $172.17 8 $1,377 30 Ton Crane hrs $59.58 0 $0 Equipment Maintenance (Butler)hrs $18.58 56 $1,041 Concrete Removal sf $3.30 4,200 $13,860 Total Sample Plant Removal Boiler Demolition Resource Description Units CosVUnit Task Units $23,081 Task Cost Equipment Operators hrs $18.43 120 $2,212 Mechanics hrs $15.59 160 $2,494 Laborers hrs $12,17 80 $974 Small Tools hrs $1.35 240 $324 Cat 769 Haul Truck hrs $93.45 160 $14,952 Truck Drivers hrs $16.23 160 $2,597 Cat 988 Loader hrs $133.06 40 $5,322 Cat 365 Excavator hrs $128.54 40 $5,142 Cat 330 wi PC-400 metalShears hrs $172.17 40 $6,887 65 Ton Crane hrs $96.82 0 $0 30 Ton Crane hrs $59.58 0 $0 Equipment Maintenance (Butler)hrs $18.58 280 $5,203 Concrete Removal sf $3.30 2,900 $9,570 Total Boiler Demolition 7/27f2009·11:12 AM-WMM Rec Plan Est July 2009 (1).xls $55,677 Denison Mines (USA)Corp, While Mesa Mill MILL DECOMMISSIONING Vanadium Oxidation Circuit Removal Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 48 $885 Mechanics hrs $15.59 64 $998 Laborers hrs $12.17 32 $390 Small Tools hrs $1.35 96 $130 Cat 769 Haul Truck hrs $93.45 64 $5,981 Truck Drivers hrs $16.23 64 $1,039 Cat 988 Loader hrs $133.06 16 $2,129 Cat 365 Excavator hrs $128.54 16 $2,057 Cat 330 wi PC-400 metalShears hrs $172.17 16 $2,755 65 Ton Crane hrs $96.82 0 $0 30 Ton Crane hrs $59.58 0 $0 Equipment Maintenance (Butler)hrs $18.58 112 $2,081 Concrete Removal sf $3.30 1,200 $3,960 Total Vanadium Oxidation Circuit Removal Main ShoplWarehouse Demolition Resource Description Units Cost/Unit Task Units $22,403 Task Cost Equipment Operators hrs $18.43 96 $1,770 Mechanics hrs $15.59 128 $1,995 Laborers hrs $12.17 64 $779 Small Tools hrs $1.35 192 $259 Cat 769 Haul Truck hrs $93.45 128 $11,962 Truck Drivers hrs $16.23 128 $2,077 Cat 988 Loader hrs $133.06 32 $4,258 Cat 365 Excavator hrs $128.54 32 $4,113 Cat 330 wi PC-400 metalShears hrs $172.17 32 $5,509 Equipment Maintenance (Butler)hrs $18.58 224 $4,163 Concrete Removal sf $3.30 19,300 $63,690 Total Main Shop/Warehouse Demolition Decon Pads (2)Demolition Resource Description Units Cost/Unit Task Units $100,576 Task Cost Equipment Operators hrs $18.43 48 $885 Mechanics hrs $15.59 64 $998 Laborers hrs $12.17 32 $390 Small Tools hrs $1.35 96 $130 Cat 769 Haul Truck hrs $93.45 64 $5,981 Truck Drivers hrs $16.23 64 $1,039 Cat 988 Loader hrs $133.06 16 $2,129 Cat 365 Excavator hrs $128.54 16 $2,057 Cat 330 wi PC-400 metalShears hrs $172.17 16 $2,755 Equipment Maintenance (Butler)hrs $18.58 112 $2,081 Concrete Removal sf $3.30 1,350 $4,455 Total Decon Pads (2)Demolition 7/27/2009 -11:12 AM-WMM Rec Plan Est July 2009 (1).xls $22,898 Denison Mines (USA)Corp. While Mesa Mill MILL DECOMMISSIONING Office Building Demolition Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 72 $1,327 Mechanics hrs $15.59 96 $1,496 Laborers hrs $12.17 48 $584 Small Tools hrs $1.35 144 $194 Cat 769 Haul Truck hrs $93.45 96 $8,971 Truck Drivers hrs $16.23 96 $1,558 Cat 988 Loader hrs $133.06 24 $3,193 Cat 365 Excavator hrs $128.54 24 $3,085 Cat 330 wi PC-400 metalShears hrs $172.17 24 $4,132 Equipment Maintenance (Butler)hrs $18.58 168 $3,122 Concrete Removal sf $1.25 12,100 $15,125 Total Office BUilding Demolition Septic Tanks and Drain Fields Resource Description Units Cost/Unit Task Units $42,789 Task Cost Equipment Operators hrs $18.43 16 $295 Mechanics hrs $15.59 0 $0 Laborers hrs $12.17 16 $195 Small Tools hrs $1.35 32 $43 Cat 769 Haul Truck hrs $93.45 16 $1,495 Truck Drivers hrs $16.23 16 $260 Cat 988 Loader hrs $133.06 8 $1,064 Cat 365 Excavator hrs $128.54 8 $1,028 Cat 330 wi PC-400 metalShears hrs $172.17 0 $0 Equipment Maintenance (Butler)hrs $18.58 32 $595 Total Septic Tanks and Drain Fields Misc.Tankage &Spare Parts Removal Resource Description Units Cost/Unit Task Units $4,975 Task Cost Equipment Operators hrs $18.43 24 $442 Mechanics hrs $15.59 16 $249 Laborers hrs $12.17 16 $195 Small Tools hrs $1.35 32 $43 Cat 769 Haul Truck hrs $93.45 32 $2,990 Truck Drivers hrs $16.23 32 $519 Cat 988 Loader hrs $133.06 8 $1,064 Cat 365 Excavator hrs $128.54 8 $1,028 Cat 330 wi PC-400 metalShears hrs $172.17 8 $1,377 Equipment Maintenance (Butler)hrs $18.58 56 $1,041 Total Misc.Tankage &Spare Parts Removal 7f27{2009·11:12 AM-WMM Rec Plan EstJuly 2009{i).xIS $8,950 Denison Mines (USA)Corp. White Mesa Mill MILL DECOMMISSIONING Alternate Feed Circuit Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 112 $2,065 Mechanics hrs $15.59 48 $748 Laborers hrs $12.17 48 $584 Small Tools hrs $1.35 96 $130 Cat 769 Haul Truck hrs $93.45 48 $4,486 Truck Drivers hrs $16.23 48 $779 Cat 988 Loader hrs $133.06 32 $4,258 Cat 365 Excavator hrs $128.54 32 $4,113 Cat 330 wi PC-400 metalShears hrs $172.17 48 $8,264 Equipment Maintenance (Butler)hrs $59.58 160 $9,533 Concrete Removal sf $3.30 2,500 $8,250 Total Decon Pads (2)Demolition Mill Yard Decontamination Resource Description Units Cost/Unit Task Units $43,210 Task Cost Equipment Operators hrs $18.43 582 $10,729 Cat 637 Scraper hrs $206.83 257 $53,156 Cat 988 Loader hrs $133.06 65 $8,649 Cat D8N Dozer With Ripper hrs $95.08 65 $6,180 Cat 07 Dozer hrs $80.39 65 $5,226 Cat 651 Waterwagon hrs $110.06 65 $7,154 Cat 148 Motorgrader hrs $70.1 9 65 $4,562 Equipment Maintenance (Butler)hrs $18.58 582 $10,816 Total Mill Yard Decontamination Ore Storage Pad Decontamination Resource Description Units Cost/Unit Task Units $106,472 Task Cost Equipment Operators hrs $18.43 429 $7,908 Cat 637 Scraper hrs $206.83 189 $39,091 Cat 988 Loader hrs $133.06 48 $6,387 Cat D8N Dozer With Ripper hrs $95.08 48 $4,564 Cat 07 Dozer hrs $80.39 48 $3,859 Cat 651 Waterwagon hrs $110.06 48 $5,283 Cat 148 Motorgrader hrs $70.19 48 $3,369 Equipment Maintenance (Butler)hrs $18.58 429 $7,972 Total Ore Storage Pad Decontamination Equipment Storage Area Cleanup Resource Description Units Cost/Unit Task Units $78,434 Task Cost Equipment Operators hrs $18.43 153 $2,820 Cat 637 Scraper hrs $206.83 68 $14,065 Cat 988 Loader hrs $133.06 17 $2,262 Cat D8N Dozer With Ripper hrs $95.08 17 $1,616 Cat 07 Dozer hrs $80.39 17 $1,367 Cat 651 Waterwagon hrs $110.06 17 $1,871 Cat 148 Motorgrader hrs $70.19 17 $1,1 93 Equipment Maintenance (Butler)hrs $18.58 153 $2,843 Total Equipment Storage Area Cleanup 7/27/2009·11:12 AM-WMM Rec Plan Est July 2009 (1).xls $28,038 Denison Mines (USA)Corp, While Mesa Mill MILL DECOMMISSIONING Revegetate Mill Yard &Ore Pad Resource Description Units CosUUnit Task Units Task Cost Equipment Operators hrs $18.43 231 $4,258 Cat 637 Scraper hrs $206.83 132 $27,302 Cat 988 Loader hrs $133.06 0 $0 Cat 08N Dozer With Ripper hrs $95.08 33 $3,138 Cat 07 Dozer hrs $80.39 33 $2,653 Cat 651 Waterwa90n hrs $110.06 0 $0 Cat 14G Motorgrader hrs $70.19 33 $2,316 Seed Mix Acre $322.50 50 $16,125 Equipment Maintenance (Butler)hrs $18.58 231 $4,293 Total Revegetate Mill Yard &Ore Pad Total Demolition and Decontamination CLEANUP OF WINDBLOWN CONTAMINATION Seoping Survey Resource Description Units CosUUnit Task Units $60,085 $1,319,8121 Task Cost Soil Samples each $50.00 100 $5,000 Survey Crew hrs $15.00 752 $11,281 Sample Crew hrs $15.00 1,312 $19,682 Total Seaping Survey $35,964 Characterization Survey Resource Description Units CosUUnit Task Units Task Cost Soil Samples each $50.00 472 $23,600 Sample Crew hrs $15.00 1,136 $17,042 Total Characterization Survey $40,642 Final Status Survey Resource Description Units CosUUnit Task Units Task Cost Soil Samples each $50.00 300 $15,000 Sample Crew hrs $15.00 3,552 $53,287 Total Final Status Survey $68,287 7/27f2009-11 :12 AM-WMM Ree Plan Est July 2009 (1).xls Denison Mines (USA)Corp. White Mesa Mill MILL DECOMMISSIONING Windblown Cleanup Resource Description Units CosVUnit Task Units Task Cost Equipment Operators hrs $18.43 1,190 $21,937 Cat 637 Scraper hrs $206.83 680 $140,646 Cat D8N Dozer With Ripper hrs $95.08 170 $16,164 Cat 07 Dozer hrs $80.39 170 $13,667 Cat 14H Motorgrader hrs $70.19 170 $11,932 Soil Samples each $50.00 500 $25,000 Survey Crew hrs $15,00 163 $2.445 Sample Crew hrs $15.00 83 $1,245 Equipment Maintenance (Butler)hrs $18.58 1,190 $22,114 Units Total Windblown Cleanup Quality Control Resource Description Quality Control Contractor Total Quality Control Total Cleanup Windblown Contamination Conventional Ore Disposal $255,152 CosVUnit Task Units Task Cost Icc;hrc:.s c:.$6-"2,,,.0:.;:01__--'2=:.,0'-'8c:.0IL_-,--$1:.::2;;",8,;:..::96:.::0I $128,960 $529,0051 Resource Description Units CosVUnit Task Units Task Cost Equipment Operators hrs $18.43 1,310 $24,145 Cat 769 Haul Truck (3)hrs $93.45 756 $70,635 Cat 988 Loader hrs $133.06 252 $33,525 Cat 651 Waterwagon hrs $110.06 252 $27,731 Cat 14G Motorgrader hrs $70.19 50 $3,509 Equipment Maintenance (Butler)hrs $18.58 1,310 $24,340 Total Conventional Ore Disposal Total Quantity 148,148 Cubic Yards' 196 Cubic Yards per Truck per hour 756 Truck Hours $183,8851 Alternate Feed Disposal •200,000 tons maximum projected for December 2009 Cabot and FMRI Material Resource Description Units CosVUnit Task Units Task Cost Equipment Operators hrs $18.43 153 $2,821 Cat 769 Haul Truck (3)hrs $93.45 62 $5,778 Cat 988 Loader hrs $133.06 21 $2,742 Cat 651 Waterwagon hrs $110.06 21 $2,268 Cat 14G Motorgrader hrs $70.19 50 $3,509 Equipment Maintenance (Butler)hrs $18.58 153 $2,844 Total Cabot &FMRI Material Total Quantity 7/2712009 -11:12 AM·WMM Rec Plan EstJuly 2009 (i),xls 12,119 Cubic Yards'(as of 01131109) 196 Cubic Yards per Truck per hour 62 Truck Hours $19,964 Denison Mines(USA)Corp. White Mesa Mill MILL DECOMMISSIONING "Includes Linde,Cabot and FMRI Cameco Barrels and Honeywell Barrels Resource Description Units CosVUnit Task Units Task Cost Equipment Operators hrs $16.23 190 $3,092 Flat Bed Trailer and Tractor"hrs $55.00 190 $10,477 Fork Lift (2)hrs $18.00 381 $6,858 Equipment Maintenance (Butler)hrs $18.58 190 $3,531 Total Cameco and honeywell Barrels *includes operator Sub-Total Alternate Feed Disposal 19,049 Barrels (as of 01/31/09) 40 Barrels per load 0.4 Hours per load 190 Truck Hours $20,426 $40,39°1 TOTAL MILL DECOMMISSIONING 7/27/2009·11:12 AM-WMM Rec Plan EstJuly 2009 (1).xls I $2,073,0921 Denison Mines (USA)Corp. While Mesa Mill Mill Decommissioning 1)Removal of contaminated material from Mill Yard Assume: --18 inches (1.5 feet)will have to be removed --Area (from CAD takeoff)=1,643,453 sq.feet 37.7 acres Reviewed 07/17/09 ~ Therefore:Volume moved =1,643,453 x 1.5]/27 =91,303 cubic yards (use 91,300) 91,300 /355 cubic yards per hour = IHaul route #2 2)Removal of contaminated material from Ore Pad Assume: --18 inches (1.5 feet)will have to be removed --Area (from CAD takeoff)=976,780 sq.feet 22,4 acres 257 machine hours Therefore:Volume moved =976,780 x 1.5]/27 =54,266 cubic yards (use 54,300) 54,300 /287 cubic yards per hour = IHaul route #3 3)Demolition Equipment 189 machine hours --Kamatsu PL400 (or Cat equivalent)with LaBounty Sheers (hydraulic) --Cat 365 Trackhoe with Grapples --Cat 769 Rock Trucks (4 each) --Cat 988 Loader (1 each) 4)Demolition Crew --Heavy Equipment Operators -PC400,Cat 365,Cat 988 --Dust Control - 2 Laborers --Mechanics -Cut debris to reduce/avoid oversize and voids - 4 each --Truck Drivers - 4 each Mill Decommissioning (con't) 5)Tool and Expendable Allowance,covering the following items: page 2 --Safety gear and supplies --Hand tools --Bottled Gases and Torches --Allow $1.30 per man-hour for all but Heavy Equipment Operators and Truck Drivers 6)Demolition Time Estimates --Mill Building --Ore Bin --SX Building --CCD,Pre-Leach, Claricone --Sample Plant --Boiler House --Vanadium EMF/Ox --Shop/Warehouse --Office/Lab Building --Misc.&Bone Yard --Decon Pads (2) 7)Foundation Demolition 20 Days 2 Days 10 Days 5 Days 1 Day 5 Days 2 Days 4 Days 3 Days 4 Days 2 Days --Assume area of structure times $3.30 per square foot --Areas by building as follows: Area,sq It $Cost Mill Building SX Building CCD,Pre-Leach, Claricone Shop/Warehouse Office* Sample Plant Vanadium EMF/Ox Boiler house Decon Pads 37,500 $123,750 55,970 $184,701 15,000 $49,500 19,300 $63,690 12,100 $15,125 4,200 $13,860 1,200 $3,960 2,900 $9,570 1,350 $4,455 --Labor at $2.75,Equipment at $0.55 --*Labor at $0.70,Equipment at $0.55 8)Revegetation Assume: Mill Decommissioning (con'!)page 3 --Mill Yard Area --Ore Pad Area 1,643,453 sq.feet 976,780 sq.feet [1,643,453 --Place 6 inches ofTopsoil --Cat 637 Scrapper,Haul Route #4 976,780 ]sq.feet x 0.5 feet]I [27 cubic feet I cubic Yard] Use 48,600 Cubic Yards 48,523 cu yds 48,600 1368 cu yds per hour =132 Scrapper hours COST ESTIMATE I d s+o r_.//.)•..J;/I"iIAt.-'::;;-t/,lft;~7 '",h('-6~addoc?'L'';;o,.v t:{c:;.r!:4 7".:;>b~ 2""...,--£""r-h~e~-h-<J-r~/.//;c:/c/A/o./c;:<......>~~c;'r~""~"""'''::(.IPt-?7.e'"''''' bJ .:';o¢r/.-n.~-;G.r-/000..;6...:::7 (J(A7'S74Jr!!'c/41>kJ7rll<:7C:>-.-J /J-?!!"-9 )?':Jl.hvdr-,,· 7At.J /.::~A/.sc::-<"'l,..."-)7nJr:;S/..-vc€..:-v/I'Vclt5/f/..-./'-c:::.......~.....~.0<3'T/(.../w(J(A/,/h7,:7....,! /;k.7 i,..,('..tNd .oow-'/b."""d cd'/A:.../I7C-'wh'.'d .;.(1_4 C"'O./_"2« u./-l"Ao red k('ax:ct::.>././'Ar;;.c . 70=<-~ ~-IA C,,;/..3 Call Z C ../// /'?/U-Y4.-tO C?/tcP .;)ToM';6 AI:! 38/726;000 j.;.z.. / J 70'7 I aUO .f:J" 3 /2 3</I C)"u II Z 2;987/000.(./2- 2;57(.,,000#2- I I .;,4 ~I GO 0 .[~" '117,000/-/2.. 4:5f</,,"O'!i.oUn?o-v7 OF";5"7.<'...,0-0/10 #I2C/EI"4 /0 x 10 m',{,'"fJ.nd (JO is A:5$U.->1e-.:::sc.o/,/,,:/::;;;,,,v,/Co_/,IoI,J ~7 sc-<vv.-v.....1 W17#';//l'pU·./or Mid e<....s~/D ,;J/c <I~d e.u;;~4 .,'...."'v./"/'at"?'::t:tl,S M/..fcC.",or j"","Y G<I<dd~Co -,.-.I ;V«e5G-S',s;L9, CcTW cJ./'..?c./""....;;.../zra-;;rr/~.500 JrrCF ,Ro,,,r,,/a' ,25/#2(000 -J1:2.:=- /"7~-fI" .<';;';;'00 f't,.",rJ :;:)00 /",1-'>'7-'/))"7 .2""""X 84rs x -17 .J)")s _j 75'';:;/?J",,,,.Ir..r 1-SW<lC7 ,.-.".-- COST ESTIMATE-----··----------r------------- i tujr"/-:I t>1?..v~1 c:.N7,~r-n,'.",::>-/)"_'-...:;-c·/#....',.::'_':,.,..",.::-/ ) "?.;S$'o//hC 30 rntS...rr;r-,,;::;;,;.:70.......zu...:4 /0 X"/..:J Cir.u7 tc ::~.,./C'"/0 /"':;O~<..f?..i....h.c.e /iYiC.-t7 {'~C"1.N~1l.-5--6 5819.,..J 11/.520".,/':>...7'_334 ~"-I':;:j,:J""'1 30m/':;r,o .·..23,<'00 G~IO.:s. 384 G;,.-IOS /04l , 62,i:v;7-S'X Z~.,~x e4rz:=/9'7~/nQ-I/'<-s J On; A,:;;:s-(/r>t~/h""/",,!J"z<JC,;,<e-7/PN +-~...Bd",-<..T"7,;,,/?!,k;, "::;-"'''''''''''17 C'n:.w ~-"?"""",7.f{""""(,..20 D ..?S 70 c:;......("';.* ..:?O.P~7.s)<'2,..,,0...,x.8/4"--0/.00';1 -j.5Zo _"""~.. S~r'/""J .f?-,rdry .s;.,~/~"'-./"" 70.".....<.-~e:....-v,..,'Nf';'YJ..,.;/'r.r ..",f 1.3 /2./ N///r~.Jv,,,,,,,,/00 a .....".(..'"',,;....7 .5'0/1..- c::...'/.;/f!'::ro,<7""/c'"U/(u",•.;.".A:P 2'Z"') • .2.)~/"'G7C-n..'7 __7"'.-../sv""'~ $"'''''''7 .../fff"'C-.".J ,d....,,(.(../"""d/~"'''''',,,,....."s.06;, "::><..-...';?..r::;e v ~ ,4:s.s",.-n<!F .' ,.20%"./4~M71 ro;v/!ff,cux'c/'*""'_s:;._"f~l •?r~.J "IV";w"/~,;:,-..re /-f ;a""~••,.,to ~.../'"(8.";1 ""-- •sC/<-s;.,"Y/~';w.il 6~rOI//lred <!I'd /oX "'?6'...dJi,~ ..s~~~.II bo .J:,.U;rn<'1',e.t-u. C~'//.J'~:#:)<)(L~""J • 25;'/0 '2;ooo,,¥'~ /<::>76./1::500 - 4-~c......;Gvc~ er~c,....;-r.;,k.. /(XJ <:;".",oS ICJ~7 'p4'>OJ'''J :25 S <l"s,;....,.4.1,,"7 ?rd/N./lo~1-722-C".,/..::::: /00 G-"1"7 47>(2..>(S .::/752 ),e..£/ ·_·"~...,,v,.r._........"......,\_~ COST ESTIMATE />:,,&7/"er~/~r"-?7/I..J -I-p~~.-?::-.ouc:-r/JrJ r:..}~,d~"""."J?'~C47~~ J)n 7 ""(1 j,/I~i~r5X'c..x s.:?c)''''~s • 1----- j //~",.,.,.....,},r.$/ A)HN_~......~~~ ..I"o~'ie>G",..;'"1="""""tzmc"e;,Wl.....~rUe 4 C........IAA e"....~ ~~i.CO ....7..:;.-,g,;"~"'Ile;,...,~~.,,;:o M<'Q.(~~.w-) ~"2ClO ~~~.~'l>Q""''P~,"',.....~~..:;t~~I TI>1€ J-J~-=~(eo;l.,"b~) •Y-,/lu..~u'Q4 10Q ~rw"""""'-'r SAM_UiI':.~........A......,;.'I"'l!tl ~ 22:::,40'--:-iOi~(+~oo..,2 1.3,"'0,><O'W 4)72./"4 .23/0 07 C..,.~;O:IQ""'­ 4,1'-1 ~e.Os ~5 !ij:t> -=-i6,8&'::>t!-<C>'A"'l>~"'t>~. .c~(.t:>-J ~!DO ~~~,'ti..-:./OAT ~'..ieea:,..;-J.a:1 '"ie6,e,~~"'1~j'30<:k1~ •()e..J (I;...)T~~_'..s...-~/~~ e',r ZOO"UlOJ ~'ZS',.i'?d""l ~, '. INTERNA TIONAl URANIUM (USA)CORP.~·M .,:i.~ ...;,,_....._....~C~O:S:T~E~S~T~IM~A~T~E~~.....;~'~-~,'!1~~;~-"".;..~'i;;;~ ~T .PtIUJ e.atG 1::oJ SI1eflt of . Mlu.~Iss,~",IIVO W,N 0"&.owN lbN",.,..,'''---''''nO''''((0...,"1), 5)iuCW -w,:>• •~~20'"C'If"A~'Wt.v~~I~~".a·I''''JE': AcMOw e G'0 r:~l..Wlu.,.!E.:~"l'lE.l ~ .. ~~/~ttd' ~1:34/100 'ldll\ "~IT IS Ncr ((...."»J WH~.PHl:"~#JA.'i'~Er c:"ol\n~(~.~"-'WM-e;;,~'tJ~o~<'~1 .~Oib..~....~"n:!l k ~ "~Ulj::<:.l~~~.....~IU·I9".<''-'''''4 ~'t::>1"""","'~ ~,E"+;'-'-~'-"....'IS<w'""""'-T S~to""~..-.. <.:i;7 ~~. ~217 l;)d 3/11..""C),SO,0 ~..1aO ~~~{~trd3ftv"G:>8i ~~ ~}(gff)~1 . ~.!j~~N mS~N~mJJLli g~rn I§',,!H~S "~\'lIw:[IvlI }[rmVe1ffif:Olirj Accolili'nl1:i;mg §mnmarfY Janua..-j 2009 WMM ALTERNATE FEED RECEIPTS FOR THEMONTHENDfNGJanuary $1,2009 J~l:1iJar1!S:e1::lrl.l~i'..'ft,are[~.!:lori!~ DryTons Received June iliili!AUQust Semember ~November iJ?@mber TO'1&1 YTD Receillro 379.'" C<Jj;;~t Cak;jned Pr.;.;doct·C.aw.e=;; CaF2 i?"anst<:ellRulRt J">:F f'iOduCZ·Gameco Regen ProdlJQ-Cameco UF4 !vi2teri2l-C;ameco ='3790 ~379 WMM 11e2 Materoa!Receipts FOR THE lv;UN1H ENDIM3JarttI2>y 31,2009 Jam.:an.'!;;\:;;'~<n'"V [\~a;,(;l'il dE!E Mav ~:!!:!.!!~September October r~o\l"ember ~T~:;;;rnoReceiVEd Meslena 1g.i9 URi 33 3S ~~ WfilJJIij A!.TI:RNATE FEED Ending Illvent"", FORTHE MONTHEi\JDlNG January 31,2OG9 P~jO?Vear Ending Encllnu 2008TID 200STons l\Il~terlaJ Balance RecQjtred Fed ~ cabol 5,184 5,184- CaF2-Honej'oNel1 1,083 i ,083 Ca:cirled ?rodut:l·Cameoo 1,247 1,247 Fe.ns~es!iFfJ',FII 10,790 379 i1,177 KF PWc!lJe!·Cameco i /.107 1,007 R,;gom Produc;.Cameco iSS 185 UF4 rvlaterial~Cameco 202 .202 19,70S 379 20,O(;q. Avaaae WOS .fuE9g IJ.S·(}.5%rontent o.s -3.0%coole"l 4.5%.c-on!en! 0.25-0.5%c.onient 1'>f.content 7..g.~;,cortenl 75-80%content Harold Roberts From: Sent: To: SUbject: Harold, This is what I found: Ryan Palmer Monday,February 16,20092:35 PM Harold Roberts RE:Alternate feed barrels Alternative Feed Materials Total Drum count in Inventory Alternative Feed K-F Calcine Regen UF4 CaF-2 Wally B.ending balance 2007 6,001 3,600 568 1 3,005 #Drums Received 07- current 517 4,200 342 815 Total Inventory 6,518 7,800 910 816 3,005 Ryan Palmer r:"rl Iji(o-!rH:!J//\('cnu/)tili,lj t:435·678·2221 x102 I I:435·678·2224 6425 S.Highway 191,PO Box 809,Blanding,UT 84511 DENISON MINES (USA)CORP www.denisonmines.com This e-mail is intended lor exclusive use theperson(s)mentioned as the recipient(s).This message and any attached liles with it are confidential and may contain privileged or proprietary information.If you are not the intended recipient(s) please delete this message and notify the sender.You may not use,distribute print orcopy this message if you are not the intended redpienl(s). From:Harold Roberts Sent:Monday,February 16,2009 1:41 PM To:Ryan Palmer Subject:Re:Alternate feed barrels Ryan: I need the total number of barrels of UF4,calcined,KF,regen and Honeywell alternate feed material on site as of January 31,2009. Thanks, Harold Roberts L:"){oClllive Vice'ef(\'.,ido!)t,1/-'3 t:(303)389·4160 I I:(303)389·4125 1050 17th Street,Suite 950,Denver,CO 80265 DENISON MINES (USA)CORP www.denisonmines.com CnPi,'jr\F,:"j':'::,1',1':, 1'.',(1,I:-:'.U/,r::, SOLD TO: II\!VOIC[NUMBEFl I!\!VOICE D/J,TE S/\LESPE:HSON I\!O. DUE DATE DiSCOUNT D/,TE P/-\GE 0/:,,J:L "(:, c:;:;;C',cc, .<:>,1"1 ,,(J(-.j f";Ti\:1..-~:'..(U::.:1'\ 1050 ~j'lf-l "j'REi::": ,(',-,,',' ~:"u:r,'rr ')C,« L)['I\!'·../[f-,:("r, ;"~'C .',? /:-()., 837;>3 Vendor 10 'IName ·1 Payment Number Cheque Date IDocument Number CAR004 ICarhart Feed and Seed 100000000000009491 4/17/2009 10037238 Our Voucher Number IDate I Amount!Amount Paid Discount!NetAmountPaid DENISON MINES (USA)CORR 311190 311687 3/30/2009 4/712009 $2,430,83 $9.47 $2,430,83 $9.47 $0,00 $0.00 $2,430.83 $9.47 $2,440,30 $2,440,30 $0.00 $2,440.30 REORDERFROMYOUR LOCAL SAfEGUARDDISTRIBUTOR,If'UNKNOWN,CALLBoo.sn.2422 Ii0005R00100tH,M04SI'020420 Harold Roberts From: Sent: To: Subject: Christy Woodward Thursday,June 25,2009 3:45 PM Harold Roberts Seed On average,we have been paying $21 per pound of seed and apply it at $15 Ibs per acre (also an average). Christy Woodward F~"()IIironmontalCoordinator t:(303)389-4136 ic:(303)549-97221 f:(303)389-4125 1050 17th Street,Suite 950,Denver,CO 80265 DENISON MINES (USA)CORP ~~Yi.,.9_eniso nmi.!les.co111 This e-mail is intended for exclusive use the person(s)mentioned as the recipienl{s).This message and any attached files with it are confidential and may contain privileged or proprietary information.If you are not the intended recipient(s)please delete this message and notify the sender.You may not use,distribute print orcopy this message jf you are not the intended recipient(s). 1 Cell! RECLAMATION OF CELL 1 RECLAMATION OF CELL 1 Units Dewatering of Cell 1 Resource Description Dewatering of Cell 1 Total Dewatering of Cell 1 Cost/Unit Task Units Task Cost lc..::hr:.::.s $:::.:0c.;.4:.::.8IL_--=6.::c2,..:.:40:..:.01_------'$:..:.3"-'0,0::.:0:.::.01 $30,000 Crystal Removal Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 2,695 $49,681 Cat 769 Truck hrs $93.45 2,157 $201,573 Truck Drivers hrs $16.23 2,157 $35,008 Cat 988 Loader hrs $133.06 539 $71,719 Cat D8N Dozer With Ripper hrs $95.08 539 $51,251 Cat 365 Excavator hrs $128.54 539 $69,284 Cat 651 Waterwagon hrs $110.06 539 $59,325 Cat 14G Motorgrader hrs $70.19 539 $37,832 Equipment Maintenance (Butler)hrs $18.58 4,852 $90,168 Total Crystal Removal $665,839 Task CostTaskUnitsCost/UnitUnits Contaminated Materials Removal Resource Description Equipment Operators hrs $18.43 616 $11,356 Cat 637 Scraper hrs $206.83 308 $63,704 Cat D8N Dozer With Ripper hrs $95.08 77 $7,322 Cat 825C Compactor hrs $95.38 77 $7,344 Cat 651 Waterwagon hrs $110.06 77 $8,475 Cat 14G Motorgrader hrs $70.19 77 $5,405 Equipment Maintenance (Butler)hrs $18.58 616 $11,447 Total Contaminated Materials Removal $115,053 Task CostTaskUnitsCost/UnitUnits Topsoil Application Resource Description Equipment Operators hrs $18.43 240 $4,424 Cat 637 Scraper hrs $206.83 120 $24,820 Cat D8N Dozer With Ripper hrs $95.08 40 $3,803 Cat 651 Waterwagon hrs $110.06 40 $4,403 Cat 14G Motorgrader hrs $70.19 40 $2,808 Equipment Maintenance (Butler)hrs $18.58 240 $4,460 Total Topsoil Application $44,718 7/27/2009 -11:13 AM -WMM Rec Plan Est July 2009 (1 ).xls Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 1 Construct Channel Resource Descr'lption Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 858 $15,817 Cat 637 Scraper hrs $206.83 272 $56,258 Cat 769 Truck hrs $93.45 450 $42,053 Truck Drivers hrs $16.23 450 $7,304 Cat 988 Loader hrs $133.06 150 $19,959 Drilling &Blasting Contractor BCY $2.33 89,100 $207,475 Cat 14G Motorgrader hrs $70.19 218 $15,301 Cat D8N Dozer With Ripper hrs $95.08 218 $20,728 Equipment Maintenance (Butler)hrs $18.58 1,308 $24,307 Total Construct Channel $409,202 Place Clay Liner Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 355 $6,544 Cat 637 Scraper hrs $206.83 0 $0 Cat 825 Compactor hrs $95.38 60 $5,723 Cat D8N Dozer With Ripper hrs $95.08 60 $5,705 Cat 07 Dozer hrs $80.39 0 $0 Cat 651 Waterwagon hrs $110.06 60 $6,604 Cat 980 Loader hrs $103.73 60 $6,224 5000 Gallon Water Truck hrs $63.90 30 $1,917 Highway Trucks hrs $63.77 435 $27,740 Truck Drivers hrs $16.23 435 $7,060 Cat 14G Motorgrader hrs $70.19 85 $5,966 Equipment Maintenance (Butler)hrs $18.58 1,225 $22,765 Total Place Clay Liner $96,248 Task CostTaskUnitsCost/UnitUnits Place Lower Random Fill Resource Description Equipment Operators hrs $18.43 602 $11,098 Cat 637 Scraper hrs $206.83 172 $35,575 Cat 825 Compactor hrs $95.38 86 $8,202 Cat D8N Dozer With Ripper hrs $95.08 86 $8,177 Cat 07 Dozer hrs $80.39 86 $6,914 Cat 651 Waterwagon hrs $110.06 86 $9,466 Cat 14G Motorgrader hrs $70.19 86 $6,036 Equipment Maintenance (Butler)hrs $18.58 602 $11,187 Total Place Lower Random Fill $96,656 7/27/2009 -11:13 AM ~WMM Ree Plan Est July 2009 {1 ).xls Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 1 Clay Cap Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 305 $5,623 Cat 637 Scraper hrs $206.83 0 $0 Cat 825 Compactor hrs $95.38 55 $5,246 Cat D8N Dozer With Ripper hrs $95.08 55 $5,230 Cat 07 Dozer hrs $80.39 0 $0 Cat 651 Waterwagon hrs $110.06 55 $6,054 Cat 14G Motorgrader hrs $70.19 55 $3,860 Cat 980 Loader hrs $103.73 55 $5,705 5000 Gallon Water Truck hrs $63.90 30 $1,917 Highway Trucks hrs $63.77 440 $28,059 Truck Drivers hrs $16.23 440 $7,141 Equipment Maintenance (Butler)hrs $18.58 305 $5,668 Total Place Clay Cap Upper Random Fill Resource Description Units Cost/Unit Task Units $74,502 Task Cost Equipment Operators hrs $18.43 688 $12,683 Cat 637 Scraper hrs $206.83 172 $35,575 Cat 825 Compactor hrs $95.38 86 $8,202 Cat D8N Dozer With Ripper hrs $95.08 86 $8,177 Cat 07 Dozer hrs $80.39 86 $6,914 Cat 651 Waterwagon hrs $110.06 86 $9,466 Cat 14G Motorgrader hrs $70.19 86 $6,036 5000 Gallon Water Truck hrs $63.90 86 $5,496 Equipment Maintenance (Butler)hrs $18.58 688 $12,786 Total Place Upper Random Fill 7/27/2009 -11:13 AM -WMM Rec Plan Est July 2009 (1 ).xls $105,335 Denison Mines (USA)Corp. While Mesa Mill RECLAMATION OF CELL 1 Rock Armor Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 90 $1,659 Cat 07 Dozer hrs $80.39 30 $2,412 Cat 651 Waterwagon hrs $110.06 30 $3,302 Cat 14G Motorgrader hrs $70.19 30 $2,106 Rock Cost Delivered CY $5.75 8,607 $49,532 Equipment Maintenance (Butler)hrs $18.58 90 $1,673 Units Total Place Rock Armor Quality Control Resource Description Quality Control Contractor Total Quality Control TOTAL RECLAMATION OF CELL 1 7/27/2009 ~11:13 AM -WMM Rec Plan Est July 2009 (1 ).xIS $60,683 Cost/Unit Task Units Task Cost I,--h_rs -'..$_62_.0_01 8_0_01'--__$-'..4-'9,_60_01 $49,600 1 $1,747,8351 Denison Mines (USA)Corp. White Mesa Mill Franklin Drilling &Blastiing~Inc P.O.BOl<2246 Durango,CO 81392 Phone:970-259-5620 Fax:970-259-1304 Mobile:970·259-4167 Email:office@franklinblastlng.com February 24,2009 Ms.Amy Bushman Denison Mines Re:Spillway blasting in Blanding,Utah Wally Bryce gave us this information to base our bid on: Quantity of approximately 89,000 In-bank cubic yards. Average depth of cut:approximately 10 feet deep Working the numbers backwards,10 feet deap by 40 faet wide would require a spillway of approximately 6000 feet in length.Is this about right? If this is correct,with a 9 feet by 9 feet pattern our price would be $2.25 per in-bank cubic yard for dry conditions.If water infiltrates into the bore holes and requires wet hole product,we will charge an additional fee.Tha fea will ba the invoice cost of wet hole product delivered,plus 25%mark up to cover additional labor. Our mobilization for 2 drills and supplies will be $7000. Production ratas of about 2000 cubic yards per drill can be expectad.With two drills drilling,and a 90%availability rate,that will ba about 3600 cubic yards drilled par day.This should amount to about 25 working days.Will that be fast enough for your needs? Please call if you have any further questions. Regards, Jeff 9NI1S~lH NIl~N~~~ INTERNA TIONAL URANIUM (USA)CORP. COST ESTIMATE + + + + + + {6t-Jc,,.::!tt.CA':6'ct,1 Ac.A..IIES (JIVr::~<;f!!f'C z.,J.<..~~..,.I!.-:J"t:.::') CFi.t...t-r .... l:VA I"0"'"'170'.j + ....~~~.....J':~ e.~.t Sed>""1/=:>90/ PI-tONNE.~ ourt.e'7 c;.;.-"""''''e<... !.J /) •C..."?..r ".-......",,"ka.,.,~.ss C74"7<IH-L.-7 'tn!'~~ ,6,.,;;H PAl /,.u ~~r(,..c.4I""c:.ivlO7"Nd ilr 7ar'""n-_..m "'7'/'7 .,.-.##-=.a.#"""= ;.7./1 tl(7 .:..L.:·. .---+r:;"ll 300 C1\ 2)t~!t;·~~.·~lt~""~"7.Q "'.,,.,,-.,-./,n-'__t-m "!i~k):~~~L;I'<kl'~".t ,/-It#ewf-7r.j;:J /v4I ~/c.rll.~,",,,7C' ......:·./;';;'17:fr.",..."........I.i..ro,...,;,,"/";;:<J>vJ...v/u4'f!../.~"".;;...,bI.JwI.411 .2,57fi,703 ./lz.X.·I./!- ,z7-11lc:; '. .5)71........;e..t",..~"7".4..,,,,(.:.X'jl.r of-L<VPl t:./v"",.A'U'v'C'Nv)~ tn.0";:-1--7{:,9 T7W.U<J J a R7,s-(....'T-""'-~I!;'?~6 '-0",,,,..,.., ,4-5"'<I~e AN.....',e....,.ft,:#-i...;:;,..;:>e''¢<lv..r/J-.I (/'iT'?cy!J.,r)"TM/.e/i:.J ,.I/?'-'.~......- ..~.........,..,1 '....1"1"'11-vnl"\l'lItVtn \v.,;o"",1 ,,",vnr. COST ESTIMATE / 71/Y?6 b/(/~t:"C"e'7b rO/7'-fii/e ,rn.,rc'l,"'"'-F.-u........tJA.l47H .c.....-v~/.-.J ~(...4 c&' ,IN C='-#$-UJ'e:J!-,,,,,,-;e.~-r6'#$-1:rC/'OdI'&1..S 4) 0/5;t500 c.7 _.Bog ,f"""/,C~£"V«s 3 joey/.Iv!s'''''I''~ -2,57"/70.3 .,//2 X •s.f'+~,4/1 '='1~'-I Z 7 -I-t'leo .,......"441 I boo <-'1 5) -....,.11IlI1i/lIlG'......,...~N~...........J I- I • 1'8,O<J 0 "-'j .d;\'5-'5',~",so ,~"':l\v..\~ 1'.[u.....',4 %"'~....,...... v.~J ~.<0:",'('" 1. ;;~o~/".Jl"(.-' .:l:1 ·"L .~~. • I,- i 1- INTERNA TIONAL URANIUM (USA)CORP. COST ESTIMA TE ~e~"'wwww%%%"'''''''000 !.J "'00-'"_...........---Nn~"'...... @ -" -- M"':r-p,,-Jt,1,I /-,;J/---yRoc"<:'ON"TAC-r'1'__ .'2>o;::.Lc:..f _ -A!Qa"D..,.Ji 10 Rtlt.l<-"..:rNU!f:.7 "'" ·4;.8(:"0 '<::7"~ ,{p0j't''{).o·Ct..so"'- ",ii;:itt ':s;,e~ii"f1;~'~"".s-:...,.....-..e...-__,,_-.'.'. ...............- ". ,"'" (0;.... If'!c'l /r.-'/J.. .3)Q7/k INTERNATIONAL URANIUM (USA)CORP. COST ESTIMATE 6?,800 c'j 3/0 e71k ~/'i&,Sc'"".~,.he.r ::::;:,50 A"r~N':UW~tjt..S 7'-.sc:..Y~/~<:.-o. ~..'""1Ilt'llf'llt-~-~~t14C!'lC"4:~ &'1/6 =<''1 ~ /77C7/~ -0",<11,,,,).1-l5l.o.",-riNj ~'_ .\ I0 4-I',,,,~..»"1"ti..~~0.9Die y ~-=.:l <>-l ~~~'Q~.-z'iS (See RevlseJ $"oj~) ....,'.. ..~."-".~.,.-';".'--..,. ,, OF CELL BREACHED AREA TO BE __Top ofBedrock (sandstone)5615 MSL (from drill hole #95 and Construction Report) Cell 1-1 Outlet Channel x z too = ~f·.l "-IS 000 '/".,/y-,,/ -''J o. I (A,,"'e. P /S,;,v "z-so-; 5 "J /.- -of /.v Ci.4M /ke (CnJJ4..-voJ'L ; /?J "/"<1 4C. vUe (,:- /~/./-1'-<"",,-.J,k ~seu/-,Ji .:bO -/,f;.-,,/'7 /.1.CRP.:r T:JJ t/"It.'7'0/'r '"-';-'~'"x tJJ /,,t 3~'If}Ii.::-:: x .:5 • //po If £,h-I j So,-j )2&"""'<''" .:0:>c oe-I. 83 (;;00 c .>'0,1 •• .3 290 J2~ ~e-h S'c"'yed 89,,/1'0 ~/.J /97 ~j f?3 {po<'-=3/0 •/f-Z .J I'"90 -/9t /////"/." 11.' • .J •••J 2r;{,,J:~oX /2 I,x 260=',£;1 co (;,'9 /;OJ).p.> 2S ("JS ;y/!AJe.G . C/o .10;";[arl--",,,,,,,,,red z /"#1:.h 22 /y C'c/~2.7'~b =5'7.'I ) ed.e /ee.L~/"{,,L uSC 8 1'<1,.<.f '""1'7.$-~-fa,,Y 2SjfJIS I Jut:0 S'f i,e,Uje ~o?/7..j- Ell .J /'i'J' \"J. SO 5S&> 29 j.l ~-/h"'- JR.We.IIW'z 5c M.s -.;;. -P-1J.-4 '.," .1 •.1 .x: 5<:. d·• '.)'.C'.11---------------------------11 ?I"/""-0 /A/-- Ro. 600 x I "/'/J-0 -/3"00 >0" =S"/03'7-/~ ?-2 ~_ -e Sc ~ ~I 0 Z'Guo ,['1- 6 '//-;;tj /J!,:;-x-c 60tJ XC.S - 8'1'2&\(ifj .' k ,v 6""pi -v.,.P MJI see.-.';:~J _///7/'.;(tf fi-~J..,.>r-Ae X?~= 7/J 8 38 Z8.3/i-e.-toe 30 Cell 2 RECLAMATION OF CELL 2 Total Obtain Permits for Clay Borrow Site -Section 16 Obtain Permits for Clay Borrow Site -Section 16 Resource Description _---:u::.:n:.:.it::::s_~-C=os::.:U:..:U::.:n:.:.it'---,-__T:..:a:::s::.:k:..:U::.:n:.:.it::::s-=_T:..:a:::s::;k.-:C",o::;s;;;t:::- Permits &Licenses l.::::ea"--__........J._~$1:..::0!:::,0.:::00::.:.0::.::01 .:::.5LI_.......=$.::::50:.c,0::.:0:.:::.01 $50,000 Task CostTaskUnitsCosUUnitUnits Place Remainder of Bridging (Platform)Lift Resource Description Equipment Operators hrs $18.43 0 $0 Cat 627F Scraper hrs $206.83 0 $0 Cat 815C Compactor hrs $95.38 0 $0 Cat D8N Dozer With Ripper hrs $95.08 0 $0 Cat D7 Dozer hrs $80.39 0 $0 Cat 651 Waterwagon hrs $110.06 0 $0 Cat 14G Motorgrader hrs $70.19 0 $0 Equipment Maintenance (Butler)hrs $18.58 0 $0 Total Place Remainder of Bridging (Platform)Lift $0 Task CostTaskUnitsCosUUnitUnits Place Lower Random Fill (12") Resource Description Equipment Operators hrs $18.43 902 $16,628 Cat 637 Scraper hrs $206.83 402 $83,147 Cat 825 Compactor hrs $95.38 100 $9,538 Cat D8N Dozer With Ripper hrs $95.08 100 $9,508 Cat D7 Dozer hrs $80.39 100 $8,039 Cat 651 Waterwagon hrs $110.06 100 $11,006 Cat 14G Motorgrader hrs $70.19 100 $7,019 Equipment Maintenance (Butler)hrs $18.58 902 $16,762 Total Place Lower Random Fill (12")$161,648 Clay Layer Task CostTaskUnitsCosUUnitUnitsResourceDescription Equipment Operators hrs $18.43 1,720 $31,707 Cat 825 Compactor hrs $95.38 325 $30,998 Cat D8N Dozer With Ripper hrs $95.08 300 $28,525 Cat D7 Dozer hrs $80.39 0 $0 Cat 651 Waterwagon hrs $110.06 300 $33,019 Cat 14G Motorgrader hrs $70.19 320 $22,460 Cat 980 Loader hrs $103.73 300 $31,119 5000 Gallon Water Truck hrs $63.90 175 $11,183 Highway Trucks hrs $63.77 2,400 $153,048 Truck Drivers hrs $16.23 2,400 $38,952 Equipment Maintenance (Butler)hrs $18.58 1,720 $31,964 Total Place Clay Layer $412,976 7/27/2009 ~11:13 AM -WMM Rec Plan Est July 2009 {1 ).xls Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 2 Task CostTaskUnitsCost/UnitUnits Upper Random Fill Resource Description Equipment Operators hrs $18.43 1,990 $36,685 Cat 637 Scraper hrs $206.83 796 $164,639 Cat 825 Compactor hrs $95.38 199 $18,980 Cat D8N Dozer With Ripper hrs $95.08 199 $18,922 Cat D7 Dozer hrs $80.39 199 $15,998 Cat 651 Waterwagon hrs $110.06 199 $21,903 Cat 14G Motorgrader hrs $70.19 199 $13,968 5000 Gallon Water Truck hrs $63.90 199 $12,717 Equipment Maintenance (Butler)hrs $18.58 1,990 $36,981 Total Place Upper Random Fill $340,793 Rock Armor Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 825 $15,209 Cat D7 Dozer hrs $80.39 275 $22,108 Cat 651 Waterwagon hrs $110.06 275 $30,268 Cat 14G Motorgrader hrs $70.19 275 $19,302 Rock Cost Delivered CY $5.75 66,200 $380,974 Equipment Maintenance (Butler)hrs $18.58 825 $15,331 Total ptace Rock Armor $483,192 Units Quality Control Resource Description Qual'lty Control Contractor Total Quality Control Cost/Unit Task Units Task Cost l:.:.:,hr:::..,s ~$6~2~.0:.::.01__--:..:.1,0:::,::5:.::.01_--,$:.:::6::!5,-.:..:10:.:::0I $65,100 TOTAL RECLAMATION OF CELL 2 $1,513,7091 7/27/2009 -11:13 AM -WMM Rec Plan Est July 2009 {1 ).xls Denison Mines (USA)Corp. While Mesa Mill Volume Calculation -Cell 2 ? 1)Area of Cell 2 -2,986,660 sq ft =68.56 acres Reviewed 02/16/09 I~ 2)Area of Cell 2 stili open as of February 21,2008 (see Figure A) Area totally covered 3)Assumptions Use sq ft 0.0 acres -Bridging layer is placed using random fill from piles west of Cell 2 -Cell will be graded to Design elevation utilizing finer materials in random fill stockpiles and from "clay"stockpiles. -Clay will be mined,blended,and hauled from borrow site location in Section 16 - four miles south of the mill area,using belly dump trucks,clay layer on top of Cell only, except on south slope common to Cell 3. -The upper 1 foot of random fill will be placed utilizing the fine random fill and clay stockpiles -Rock for side armor,top armor and toe aprons will come from an off-site gravel source one (1)mile north of Blanding.Rock will be produced through screening,stockpiled and trucked to the site at the time of use.Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 4)Bridging Layer (Platform Fill)Remaining to be placed sq ft X 3 ft./27 cubic feet per cubic yard = 5)Bring Platform Fill up to Design elevation (Lower Random) Assume full area of Cell X one (1)foot thick 2,986,660 sq ft X 1 ft./27 cubic feet per cubic yard = 6)Placement of Clay Layer (One (1)foot thick on top of Cell only) Assume full area of Cell X one (1)foot thick 2,986,660 sq ft X 1 ft./27 cubic feet per cubic yard = cubic yards Use 1 .::c:::ub:::i:::cJ.y~ar:.:;d:;;s_ 110,617 cubic yards Use I 110,700 cubic yards 110,617 cubic yards Use I 110,700 cubic yards Volume Calculation -Cell 2 (can't)page 2 7)Upper Random Fill Volume -Top of Cell area Assume full area of Cell X one (2)foot thick 2,986,660 sq ft X 2 ft.1 27 cubic feet per cubic yard =221,234 cubic yards Use I 221,300 cubic yards 8)Armor Protection -Top of Cell Assume full area of Cell X one-half (0.5)foot thick 2,986,660 sq ft X 0.5 ft.1 27 cubic feet per cubic yard =55,309 cubic yards Use I 55,400 cubic yards 9)Cell 2 North Slope (Siope #1 )common with Cell 1-1 Average height Length 12 feet 2600 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [12X12X5)/2 -(12X12X3)/2]X2600 13,867 cubic yards Use 1_.;.13;;:,;;,90;";0;.,,.;c;;,ub;,;i;;,c.<,;ya;;;.r.;:,;ds:.....J =374,400 cubic feeU 27 = Remaining Random Fill [15 X 15 X 5)/2 -(12 X 12 X 5)/2]X 2600 =526,500 cubic feeU 27 =19,500 cubic yards Use I 19,500 cubic yards Total Random Fill North Slope 33,400 cubic yards b)Rock Armor 8"thick -0.67 feet [15.67 X 15.67 X 5)/2 -(15 X 15 X 5)/2J X 2600 =133,568 cubic feeU 27 =4,947 cubic ards Use 1-....:5;:;,0;;;0;,;0...;;c;;;ub;;;;i;;;,c.:;ya;.:r,::ds::....J c)Toe Apron 2 X 7 X 2600 127 =1,348 cubic yards Use 1__1;.:,4.;.0;";0;.,,.;c.;:,;ub;,,;ic;,;.<,;~a;;;.rd;;:s:.....J Total Rock Armor Cell 2 north Slope 6,400 cubic yards Volume Calculation -Cell 2 (can't)page 3 10)North Slope common with Mill yard (Slope #2 ) Average height Length 1 feet 900 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [1 X 1 X 5)/2 -(1 X 1 X 3)/2]X 900 =900 cubic feet/27 =33 cubic yards Use I 100 cubic yards Remaining Random Fill [4 X 4 X 5)/2 -(1 X 1 X 5)/2]X 900 =33,750 cubic feet/27 =1,250 cubic yards Use I 1,300 cubic yards Total Random Fill North Slope 1,400 cubic yards b)Rock Armor 8"thick -0.67 feet [4.67 X 4.67 X 5)/2 -(5 X 5 X 5)/2]X 900 =13,070 cubic feet/27 =484 cubic yards Use 1__..::5,;:,00::...:c;;;u;,;:b;.:ic"",y;,;:a:;;rd;;;s;... c)No Toe Apron on fill common with Mill Yard Total Rock Armor on slope commmon to Mill Yard 500 cubic yards I 11)Cell 2 West Dike (Slope #3 ) Average height Length 2 feet 500 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [2 X 2 X 5)/2 -(2 X 2 X 3)/2]X 500 74 cubic yards Use 1__..:.1,;:,00::...:c;;;u;,;:b;.:ic"",y;,;:a:;;rd;;;s;... 2,000 cubic feet/27 == Volume Calculation -Cell 2 (can't)page 4 Remaining Random Fill [2 X 2 X 5)/2 -(2 X 2 X 3)/2]X 500 2,000 cubic feet!27 =74 cubic yards Use 1__..:1..::0..::0...::c:::ub:::i;;,c.l.y;;:a::rd:::s~ Total Random Fill North Slope 200 cubic yards I b)Rock Armor 8"thick -0.67 feet [5.67 X 5.67 X 5)/2 -(5 X 5 X 5)/2]X 500 8,936 cubic feet!27 =331 cubic yards Use 1__.;:4;;:0,;:0...::c:::ub:::i;;,c.l.y;;:a::rd:::s~ c)Toe Apron Not required for slope 10 feet long -Drainage from Cell goes south to Cell 3 and then off of south slope of Cell 3 Total Rock Armor Cell 2 north Slope 400 cubic yards I 12)Cell 2 East Dike (Slope #4 ) Average height Length 1 feet 1250 feet a)Random Fill Wedge from #10 1 cubic foot per linear foot X 1250 46 cubic yards Use 11..__1::0:.::0;..:;C::;U;;:b:::ic~y:::a:.;rd::;s:.... b)Remaining Random Fill from #10 37.5 cubic foot per linear foot X 1250/27 1,736 cubic yards Use 11.._.:1.:.:,8::;0:.::0;..:;c::;u;;:b:::ic~y:::a:.;rd::;s:.... Total Random Slope #4 1,900 cubic yards c)Rock Armor 8"thick -0.67 feet from #10 14.52 cubic feet per linear foot of dike 14.52 cubic foot per linear foot X 1250 /27 672 cubic yards Use LI__7:.;0:::0:....:c~u:::b:::ic:.yl:.:a::.r:;ds::... 672 cubic feet!27 = c)Toe Apron Not required Total Rock Armor Cell 2 north Slope 700 cubic yards Volume Calculation -Cell 2 (con't)page 5 13)South Slope Cell 2 commom with Cell 3 (Slope #5) Average height Length 3 feet 3500 feet a)Random fill to reduce slope from 3:1 to 5:1 Random Fill [3 X 3 X 5)/2 -(3 X 3 X 3)/2J X 3500 =31,500 cubic feet!27 =1,167 cubic yards Use I 1,200 cubic yards Random Fill Upper [6 X 6 X 5)/2 -(4 X 4 X 5)/2J X 3500 =175,000 cubic feet!27 =6,481 cubic yards Use I 6,500 cubic yards b)Clay Layer [4 X 4 X 5)/2 -(3 X 3 X 5)/2]X 3500 =61,250 cubic feet!27 =2,269 cubic yards Use I 2,300 cubic yards c)Rock Armor 8"thick -0.67 feet [6.67 X 6.67 X 5)/2 -(6 X 6 X 5)/2]X 3500 =74,278 cubic feet!27 =2,751 cubic yards Use I 2,800 cubic yards No Toe Apron Total Rock Armor on slope Cell 2 Slope commmon to Cell 3 2,800 cubic yards I + CELL f:I + + Cell 2 Volume Calculations Scale 1"=300 feet + ,,'- ~~~~--~---~-----~--==-------------- ,"., \+= "'-I~zJ Section A - A (not to scale) Showing Cover Typical Section through Exterior Dike Rock Armor (6"Top) Random Fill Clay Rock Annor (8"on Slope) RandomFill Tailings Dike 3:1 Wedge 5:1 Toe Apron 3:1 Bottom ofeell 1-1 After crystal and Liner Removal A A' Area Modified for Cell1·!Disposal Area Top of Cell North (Slope #1 ) North (Slope #2 ) West (Slope #3 ) East (Slope #4 ) South (Slope #5 ) Totals Volume Summary·Cell 2 Lower Upper Rock BridQinQ Layer Random Clay Random Armor -110,700 110,700 221,300 55,400 13,900 19,500 6,400 100 1,300 500 100 100 400 100 1,800 700 1,200 2,300 6,500 2,800 -126,100 113,000 250,500 66,200 Cell 2 Reclamation Cat 637Resource Requirements Volume Route Yds/hr %Equip.Hr. Cell 2 Bridging Lift Tailings Surface -5 296 100%0.0 Cell 2 Lower Random Fill Tailings Surface 110,700 5 296 67%250.6 Tailings Surface 110,700 4 368 33%99.3 Slope 1 13,900 5 296 100%47.0 Slope 2 100 4 368 100%0.3 Slope 3 100 5 296 100%0.3 Slope 4 100 4 368 100%0.3 Slope 5 1,200 5 296 100%4.1 Total 401.7 Cell 2 Lower Random Fill Tailings Surtace 221,300 5 296 67%500.9 Tailings Surface 221,300 4 368 33%198.4 Slope 1 19,500 5 296 100%65.9 Slope 2 1,300 4 368 100%3.5 Slope 3 100 5 296 100%0.3 Slope 4 1,800 4 368 100%4.9 Slope 5 6,500 5 296 100%22.0 Total 796.0 Cell 2 Rock Armor --use Highway Trucks Clay Volume = = Trucking Clay Production Cell 2 (use same assumptions as Cell 3 ) 113,000 Bank Cubic Yards (BCY) 0.8 Swell Factor 141,250 Loose Cubic Yards (LCY) 475 LCYlhr 8 trucks pius one (1)Loader 150,000 LCY I 475 LCYlhr = use 297 hours 300 hours 980 Loader D8N wi ripper Cat 651 WW Cat 825 Compo 14G Patrol 5000 gal WW 300 X 8 Trucks =2400 hours Hours 300 300 300 325 325 175 Rock Armor Production Cell 2 66,200 cubic yards (cy) 38 cy per hour times 8 trucks 304 cy per hour delivered Assume 25%extra time tor spreading,loading and screen wait 30411.25 243.2 cy per hour 272 Hours I INTERNA TJONAL URANIUM (USA)CORP. COST ESTIIoIA TE ~~~.".~~ww::c::c::c"'''''''ccc",cc~..-.......... ~~~c4c:.N...... """S~~,.,.,.~LCN~"'"~.c:;t"'-!t'Q:f, }.2000'4% 2 /8~o '//~ 3 120 0 1 l,sX 4-s,oo'0.:;% s 570a J )·4% t 520<::>.1 O.Q% ..:?f-I sao I 4,~M><If 7?2.';"4 __ 9,2 ~/,-",£0_'lJ""!> ~~.E:::L!? k>o ",./>"'?IN ,,,,5 5'fP .....I.of".,w /MJ'.v 12100 1?1 j,tf-n?J"-I /'2 />1" /'-'OOn1 /.(.h'I/,v I.S "., /710 hl 1.1$MiN 1,'-8 nu-, Its(",q)"'"/#.5 .-.?,I'"/.'M- 9.~S"'/N 7.'!-3,., /6,#t",,:.v •/.5 ""IN~...4.l.,...,/;(8 7"~'"1.2 "",'.v""", 0'<:4 k lf3""INUn"+'{'~/#~-f,,r FiK€<P 7)..06'$-LD_S-~. ~7,y.8JCiu/3~"" ,S.."../"",,4 '"4-Sn,/AI p,,~;,.-1I='7~0Po.."",-i>C",.,/.. c)':'~~-u>::=-je ,"/"V.utN/7.-z~ So ........-I.4..''"Z.7C~~ 22 G!y/9'd..;>(7.7 c;,/.,~r x'g I. =~y/~..., 2 ""IIP'J:8.ft!j;'<:''-'7 ::or._2 t .41P:F k-~...J-...,;•..,L 2<zp.<..,......"V /"'---R.r~('.IllS;)-':..~+:-...._......--_.,-......_...~.4'".~.•.j/pr '7= 1 : ',':::"41 d:Lf:t~(~~).~~,:~t:~~*~/0'-' ~:fi:::tt..::__..L::~~'':"~._..Z~,.,~~';~.i~.4r:_~·~.~~~~1~-:~' biiiof.~_~~J '~::.$~~£~k 70 :r,.-....,.QB.i'·"~.L_".f'l.k:~.~.~'.:.:(~+,;2.,1.£:.i<W ~'9"".:z::s'l.'><I"t~.b ;;'11'.~~F<>'zo /(M .2U-"t t'""2'117)..'2'"1'1 s.., ."~.....-rv(...,...........,'"..3~....-z" 22 . 27 • INTERNATIONAL URANIUM (USA)CORP. COST 'ESTIMATE <E/P'i'l..O~j ~~~_.DIlt.e c.a!G blJ···5I1eet of . UJ.,(~~O>..I ~"T"~ ~ON Ib~w~- t).c:<...6.r'hot>'-!CTlO"-J ...a...r;,W'l.J-li."-12,~~·~ueG>S«'TlOAJ Ie.. ..b~ll.o<.4co ~~"".~1O.·H"'E1A1'~e..t:bSc ~ 'Feoo-'I GA...,..\>IAN ()~_..._ H to><~t\"'I<;'"V~"'"',.,..0 I'"c::..........~~<1>!:>0 F+/~ Oil ",1m SI"'G'E ~ ....-"'"-"" "'""'"I A J...,,,.. ".~...I.... .~,,,. t..........,I ,..,II -.."'"...... ."... "'"......A-.......-- ..~-~A~I 'P!l GAT ~~A&.£TO ~b,T'~zs::\~'I'I~WI~.A..l .<\Ma"l'::of"- 1500~/~J D WO%.W •.........,b,uu...,g ~T ""l"Wf G,;;..""is 1JTl1..1~~~ OF &AT'~~T1CW t:</€,'eIPPlI$I'"""'to ae."tla."-"'i>~>..lC!?/ 'Fk-p,o.m ~. Cell 3 RECLAMATION OF CELL 3 RECLAMATION OF CELL 3 Units Dewatering of Cell 3 Resource Description Dewatering of Celi 3 Total Dewatering of Cell 3 Cost/Unit Task Units Task Cost 1",hr",s -.:::..:$0:.:-.4:.:081__..::.:62=,-,4:..::0.::.101_---::$:.:03°"-',°::..:°:.:0°I $30,000 Place Remainder of Bridging (Platform)Lift Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,402 $25,841 Cat 637 Scraper hrs $206.83 623 $128,857 Cat 825 Compactor hrs $95.38 156 $14,855 Cat D8N Dozer With Ripper hrs $95.08 156 $14,809 Cat D7 Dozer hrs $80.39 156 $12,521 Cat 651 Waterwagon hrs $110.06 156 $17,143 Cat 14G Motorgrader hrs $70.19 156 $10,932 Equipment Maintenance (Butler)hrs $18.58 1,402 $26,050 Total Place Remainder of Bridging (Platform)Lift Place Lower Random Fill (12") Resource Description Units Cost/Unit Task Units $251,007 Task Cost Equipment Operators hrs $18.43 1,422 $26,214 Cat 637 Scraper hrs $206.83 452 $93,488 Cat 825 Compactor hrs $95.38 194 $18,503 Cat D8N Dozer With Ripper hrs $95.08 194 $18,446 Cat D7 Dozer hrs $80.39 194 $15,597 Cat 651 Waterwagon hrs $110.06 194 $21,353 Cat 14G Motorgrader hrs $70.19 194 $13,617 Equipment Maintenance (Butler)hrs $18.58 1,422 $26,426 Total Place Lower Random Fill (12") Clay Layer Resource Description Units Cost/Unit Task Units $233,643 Task Cost Equipment Operators hrs $18.43 1,835 $33,827 Cat 637 Scraper hrs $20683 0 $0 Cat 825 Compactor hrs $95.38 350 $33,382 Cat D8N Dozer With Ripper hrs $95.08 320 $30,427 Cat D7 Dozer hrs $80.39 0 $0 Cat 651 Waterwagon hrs $110.06 320 $35,221 Cat 14G Motorgrader hrs $70.19 350 $24,566 Cat 980 Loader hrs $103.73 320 $33,194 5000 Galion Water Truck hrs $63.90 175 $11,183 Highway Trucks hrs $63.77 2,560 $163,251 Truck Drivers hrs $16.23 2,560 $41,549 Equipment Maintenance (Butler)hrs $18.58 1,835 $34,101 Total Place Clay Layer 7/27f2009 -11 :13AM -WMM Rec Plan Est July 2009 {1 ).xfs $440,701 Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 3 Task CostTaskUnitsCost/UnitUnits Upper Random Fill Resource Description Equipment Operators hrs $18.43 2,364 $43,570 Cat 637 Scraper hrs $206.83 868 $179,531 Cat 825 Compactor hrs $95.38 249 $23,773 Cat D8N Dozer With Ripper hrs $95.08 249 $23,700 Cat D7 Dozer hrs $80.39 249 $20,038 Cat 651 Waterwagon hrs $110.06 249 $27,434 Cat 14G Motorgrader hrs $70.19 249 $17,494 5000 Galion Water Truck hrs $63.90 249 $15,928 Equipment Maintenance (Butler)hrs $18.58 2,364 $43,922 Total Place Upper Random Fill $395,390 Rock Armor Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 819 $15,098 Cat D7 Dozer hrs $80.39 273 $21,948 Cat 651 Waterwagon hrs $110.06 273 $30,048 Cat 14G Motorgrader hrs $70.19 273 $19,161 Rock Cost Delivered CY $5.75 66,380 $382,010 Equipment Maintenance (Butler)hrs $18.58 819 $15,220 Total Place Rock Armor $483,485 Units Quality Control Resource Description Quality Control Contractor Cost/Unit Task Units Task Cost I......hr-'-s .::.;$6:.::2:..;;,'0..:.J01__---"-1,2::..:0-'-01_---.--.:$:.:.;742,4:::::°.::.1°I Total Quality Control $74,400 TOTAL RECLAMATION OF CELL 3 I $1,908,6271 7/27/2009 -11:13 AM -WMM Rec Plan Est July 2009 (1).xls Denison Mines (USA)Corp. White Mesa Mill Volume Calculation -Cell 3 IUpdated 02/26/09 1)Area of Cell 3 -3,234,252 sq It 74,25 acres I 2)Area of Cell 3 still open as of February 21,2008 (see Figure A) 900 It X 1725 It =1,552,500 3)Assumptions Use 1,552,500 sq It 35.6 acres ~Bridging layer is placed using random fill from piles east and west of Cell 3 ~Cell will be graded to Design elevation utilizing finer materials in random fill stockpiles and from "clay"stockpiles. ~Clay will be mined,blended,and hauled from borrow site location in Section 16 - four miles south of the mill area,using belly dump trucks,clay layer on top of Cell only. -The upper 1foot of random fill will be placed utiliZing the fine random fill and clay stockpiles -Rock for side armor,top armor and toe aprons will come from an off-site gravel source one (1)mile north of Blanding.Rock will be produced through screening,stockpiled and trucked to the site at the time of use,Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 4)Bridging Layer (Piatform Fill)Remaining to be placed 1,552,500 sq It X 3 ft.1 27 cubic feet per cubic yard =172,500 cubic yards Use I 172,500 cubic yards 5)Bring Platform Fill up to Design elevation (Lower Random) Assume full area of Cell X one (1)foot thick 3,234,252 sq It X 1 ft.1 27 cubic feet per cubic yard =119,787 cubic yards Use I 120,000 cubic yards 6)Placement of Clay Layer (One (1)foot thick on top of Cell only) Assume full area of Cell X one (1)foot thick 3,234,252 sq It X 1 ft.1 27 cubic feet per cubic yard =119,787 cubic yards Use I 120,000 cubic yards Volume Calculation -Cell 3 (con't)page 2 7)Upper Random Fill Volume -Top of Cell area Assume full area of Cell X one (2)foot thick 3,234,252 sq ft X 2 ft./27 cubic feet per cubic yard =239,574 cubic yards Use I 240,000 cubic yards 8)Armor Protection -Top of Cell Assume full area of Cell X one-half (0.5)foot thick 3,234,252 sq ft X 0.5 ft./27 cubic feet per cubic yard =59,894 cubic yards Use I 60,000 cubic yards 9)Cell 3 North Slope (Slope #6)common with Cell 2 Average height Len9th 2 feet t 100 feet No clay on slopes.Toe apron only at base of long slope or where drainage is directed. a}Random fill to reduce slope from 3:1to 5:1 First Wedge [2 X 2 X 5)/2]X 1100 11,000 cubic feeV 27 =407 cubic yards Use 1__.;.4.;;10:;..,;C;;:U;::b;,:ic;..y"a::.rd:;s,- Remaining Random Fill [5 X 5 X 5)/2 -(2 X 2 X 5)/2]X 1100 =57,750 cubic feeV 27 =2,139 cubic ards Use '-;;2:':,2':i0:;;0:-:c'7ubi:ii"'c'5:ar:::di"s-' Total Random Fill North Slope 2,610 cubic yards I b)Rock Armor 8"thick -0.67 feet [5.67 X 5.67 X 5)12 -(5 X 5 X 5)/2J X 1100 728 cubic yardS Use 1__.;;73::.0:;..,;c;;:u;::b;,:ic;..c:a::.rd:;s,- 19,659 cubic feeV 27 = c)Toe Apron No rock required Total Rock Armor Cell 3 north Slope 730 cubic yards I Volume Calculation -Cell 3 (can't)page 3 10)Cell 3 South Dike,west end (Slope #7 ) Average height Length 16 feet 1750 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [16 X 16 X 5)/2 -(16 X 16 X 3)/2]X 1750 448.000 cubic feeV 27 =16.593 cubic yards Use I 16.600 cubic yards Remaining Random Fill [19 X 19 X 5)/2 -(16 X 16 X 5)/2]X 1750 =459.375 cubic feeV 27 =17.014 cubic yards Use I 17.100 cubic yards Total Random Fill North Slope 33.700 cubic yards I b)Rock Armor 8"thick -0.67 feet [19.67 X 19.67 X 5)/2 -(19 X 19 X 5)/2)X 1750 113.351 cubic feeV 27 =4,198 cubic yards Use 1_..;:,4,",2;;;0::,0_C::,:U;::b::;ic:,.y!;a::.rd::;s,- c)Rock Apron at toe of slope Total Rock Armor Slope #7 [2ft X 7ft wide X 1750 long]/27 =907 Use 1_....;.1.c;O,;;.00'-C:.;u:.;b;;;ic;,.y"a;,.rd:.;s'- 5.200 cubic yards I 11)Cell 3 South Dike (Slope 118 ) Average height Length VOLUME DELETED.AREA FILLED WITH CELL 4A TAILINGS o feet o feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge cubic yards Use 1 C:.;u;;;;b;;;ic;,.y"a;,.rd:.;s'- Volume Calculation -Cell 3 (con't)page 4 Remaining Random Fill cubic yards Use 1 C:.;u;;;;b;;;ic;,.y"a;;;.rd;;;s'- Total Random Fill North Slope cubic yards I b)Rock Armor 8"thick -0.67 feet c)Rock Apron at toe of slope Total Rock Armor Cell 3 South Dike 12)Cell 3 East Slope (Slope #9) cubic yards Use 1 .....;C:.:U::;b;.:ic,-,y:.:a:.:rd:.:s'-J Use 1 C;:;u;;,:b:;;ic;.y!,;a:;.rd::;s::...J cubic yards I Average height Length a)Random Fill No existing Dike Total Random Slope #4 4 feet 800 feet [(4 X 4 X5)12J X 800/27 =1185 cubic yards Use 1_....;.1""2",0",0_c;;,;u::;;b;;;ic;.y,,a::;.rd::;.s:...J 1,200 cubic yards I b)Rock Armor 8"thick -0.67 feet 14.52 cubic feet per linear foot of dike 14.52 cubic foot per linear foot X 800 127 c)Toe Apron Not required =430 cubic feeU 27 =430 cubic yards Use 1L-_..:4:::5:::0~c::;ub:::ic::.::ya;::r;;;d::.s...J Total Rock Armor Cell 3 East Slope Volume Summary -Cell 3 450 cubic yards 1 Top of Cell West (Slope 116 ) South (Slope #7 ) South (Slope #8 ) East (Slope #9 ) Totals Lower Upper Rock Bridqinq Layer Random Clay Random Armor 172,500 120,000 120,000 240,000 60,000 410 2,200 730 16,600 17,100 5,200 --- 1,200 450 172,500 137,010 120,000 260,500 66,380 Cell 3 Reclamation Cat 637Resource Requirements Volume Route Yds/hr %Equip.Hr. Cell 3 Bridging Lift Tailings Surface 172,500 6 277 100%622.7 Cell 3 Lower Random FiiI Tailings Surface 120,000 5 296 100%405.4 Slope 6 410 5 296 100%1.4 Slope 7 16,600 4 368 100%45.1 Slope 8 -5 296 100%0.0 Slope 9 -4 296 100%0.0 Total 451.9 Cell 3 Lower Random Fill Tailings Surface 240,000 4 296 100%810.8 Slope 6 2,200 4 296 100%7.4 Slope 7 17,100 5 368 100%46.5 Slope 8 4 296 100%0.0 Slope 9 1,200 5 368 100%3.3 Total 868.0 Cell 3 Rock Armor **use Highway Trucks Clay Volume = Clay Production Cell 3 (use same assumptions as Cell 2 ) 120,000 Bank Cubic Yards (BCY) 0.8 Swell Factor 150,000 Loose Cubic Yards (LCY) Trucking 475 LCYlhr 150,000 LCY I 475 LCYlhr = use 8 trucks plus one (1)Loader 316 hours 320 hours 980 Loader D8N wi ripper Cat 651 WW Cat 825 Camp. 14G Patrol 5000 gal WW 320 X 8 Trucks =2560 hours Hours 320 320 320 350 350 175 Rock Armor Production Cell 3 66,380 cubic yards (cy) 38 cy per hour times 8 trucks 304 cy per hour delivered Assume 25%extra time for spreading,loading and screen wait 304/1.25 243.2 cy per hour 273 Hours Cell4A RECLAMATION OF CELL 4A·Total Dewatering of Cell 4A Resource Description Dewatering of Cell 4A Total Dewatering of Cell 4A Place Bridging (Platform)Lift Resource Description lhrs Units Units Cost/Unit Task Units Task CostI$0.481 62,4001 $30,0001 $30,000 Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $206.83 689 $142,547 Cat 637 Scraper Operators hrs $17.24 689 $11,885 Cat 825 Compactor hrs $95.38 172 $16,433 Cat 825 Compactor Operator hrs $12.74 172 $2,195 Cat D8N Dozer With Ripper hrs $95.08 172 $16,383 Cat D8N Dozer Operator hrs $12.74 172 $2,195 Cat 07 Dozer hrs $80.39 172 $13,852 Cat 07 Dozer Operator hrs $12.74 172 $2,195 Cat 651 Waterwagon hrs $110.06 172 $18,964 Cat 651 Waterwagon Operator hrs $16.23 172 $2,796 Cat 14G Motorgrader hrs $70.19 172 $12,093 Cat 14G Motorgrader Operator hrs $18.41 172 $3,172 Equipment Maintenance (Butler)hrs $18.58 2,929 $54,432 Total Place Bridging (Platform)Lift Place Lower Random Fill Resource Description Units $299,142 Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,122 $20,682 Cat 637 Scraper hrs $206.83 499 $103,134 Cat 825 Compactor hrs $95.38 125 $11,890 Cat D8N Dozer With Ripper hrs $95.08 125 $11,853 Cat 07 Dozer hrs $80.39 125 $10,022 Cat 651 Waterwagon hrs $110.06 125 $13,720 Cat 14G Motorgrader hrs $70.19 125 $8,750 Equipment Maintenance (Butler)hrs $18.58 1,122 $20,849 Total Place Lower Random Fill $200,900 Clay Layer Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,020 $18,803 Cat 637 Scraper hrs $206.83 0 $0 Cat 825 Compactor hrs $95.38 180 $17,168 Cat D8N Dozer With Ripper hrs $95.08 180 $17,115 Cat D7 Dozer hrs $80.39 0 $0 Cat 651 Waterwagon hrs $110.06 180 $19,812 Cat 14G Motorgrader hrs $70.19 180 $12,634 Cat 980 Loader hrs $103.73 150 $15,560 5000 Gallon Water Truck hrs $63.90 150 $9,586 Highway Trucks hrs $38.77 1,600 $62,032 Truck Drivers hrs $16.23 1,600 $25,968 Equipment Maintenance (Butler)hrs $18.58 2,620 $48,689 Total Place Clay Layer Upper Random Fill Resource Description Units $247,366 Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,360 $25,062 Cat 637 Scraper hrs $206.83 544 $112,477 Cat 825 Compactor hrs $95.38 136 $12,967 Cat D8N Dozer With Ripper hrs $95.08 136 $12,927 Cat D7 Dozer hrs $80.39 136 $10,930 Cat 651 Waterwagon hrs $110.06 136 $14,964 Cat 14G Motorgrader hrs $70.19 136 $9,542 5000 Gallon Water Truck hrs $63.90 136 $8,688 Equipment Maintenance (Butler)hrs $18.58 1,360 $25,265 Total Place Upper Random Fill Rock Armor Resource Description Units $232,822 Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 597 $11,005 Cat D7 Dozer hrs $80.39 199 $15,998 Cat 651 Waterwagon hrs $110.06 199 $21,903 Cat 14G Motorgrader hrs $70.19 199 $13,968 Rock Cost Delivered CY $5.75 48,450 $278,825 Equipment Maintenance (Butler)hrs $18.58 597 $11,094 Total Place Rock Armor $352,794 Quality Control Resource Description Quality Control Contractor Total Quality Control TOTAL RECLAMATION OF CELL 4A Units Cost/Unit Task Units Task Cost I;-hr-s..::....c.:-=--'1----'-'-,$'"""62~.O~OI 1,0451 $64,790I $64,790 I $1,427,814~ Volume Calcu[ation -Cell 4 1)Area of Cell4A - 2)Assumptions 1,829,520 sq ft =42.00 acres IUpdated 02/27/09 7 -Bridging layer is placed using random fil[from piles east of Cell 4A -Cell will be graded to Design elevation utilizing finer materials in random fi[1 stockpiles and from "clay"stockpiles. -Clay wil[be mined,blended,and hauled from borrow site location in Section 16 - four miles south of the mill area,using belly dump trucks,clay layer on top of Cell only. -The upper 1 foot of random fiI[wil[be placed utilizing the fine random fill and clay stockpiles -Rock for side armor,top armor and toe aprons will come from an off-site gravel source one (1)mile north of B[anding.Rock wi[1 be produced through screening,stockpiled and trucked to the site at the time of use.Belly dump trucks wil[dump gravel in windrows on the top and sides of the Ce[1. 3)Bridging Layer (Platform Fill)Remaining to be placed 1,829,520 sq ft X 3 ft./27 cubic feet per cubic yard =203,280 cubic yards Use I 204,000 cubic yards 4)Bring Platform Fill up to Design elevation (Lower Random) Assume full area of Cell X one (1)foot thick 1,829,520 sq ft X 1 ft./27 cubic feet per cubic yard =67,760 cubic yards Use I 68,000 cubic yards 5)Placement of Clay Layer (One (1)foot thick on top of Cell only) Assume full area of Cell X one (1)foot thick 1,829,520 sq ft X 1 ft./27 cubic feet per cubic yard =67,760 cubic yards Use I 68,000 cubic yards Volume Calculation -Cell 4A (can't)page 2 6)Upper Random Fill Volume -Top of Cell area Assume full area of Cell X one (2)foot thick 1,829,520 sq ft X 2 ft.1 27 cubic feet per cubic yard = 7)Armor Protection -Top of Cell Assume full area of Cell X one-half (0.5)foot thick 135,520 cubic yards Use I 136,000 cubic yards 1,829,520 sq ft X 0.5 ft.1 27 cubic feet per cubic yard =33,880 cubic yards Use I 34,000 cubic yards 8)Cell 4A South Dike,(Slope #1 ) Average height Length 36 feet 1600 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [36 X 36 X 5)/2 -(36 X 36 X 3)/2]X 1600 =2,073,600 cubic feeV 27 = Remaining Random Fill [39 X 39 X 5)/2 -(36 X 36 X 5)/2]X 1600 76,800 cubic yards Use 1L-..:.7.:.;7'.:;O.::;OO::.....:;c::;u.::;bi.::,c.!,;ya::;r.::;ds:;.... Total Random Fill South Slope =900,000 cubic feeV 27 =33,333 cubic yards Use 1L.-:::3;:;4,::;0;:;00::.....:;c::;u;:;bi;:,cl;ya;::r;;:;ds::.- 111,000 cubic yards b)Rock Armor 8"thick -0.67 feet [39.67 X 39.67 X 5)/2 -(39 X 39 X 5)/2]X 1600 210,836 cubic feeV 27 =7,809 cubic yards Use 1L._,:.;7,::;8;:;00::.....:;c::;u~bi;:,cl;ya;::r;;:;ds::.- c)Rock Apron at toe of slope Total Rock Armor South Slope [2ft X 7ft wide X 1600 long]127 =830 Use 1L-_:::8.::;50::.....:;c::;u.::;bi.::,C.!,;ya::;r.::;ds:;.... 8,650 cubic yards Volume Calculation -Cell 4A (can't)page 3 9)Cell 4A West Dike (Slope #2 ) Average height Length 26 feet 1200 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [26 X 26 X 5)/2 -(26 X 26 X 3)/2]X 1200 Remaining Random Fill =811,200 cubic feet!27 = Use I 30,044 cubic yards 30,000 cubic yards [29 X 29 X 5)/2 -(26 X 26 X 5)/2]X 1200 =495,000 cubic feet!27 = Total Random Fill North Slope 18,333 cubic yards Use I 19,000 cubic yards 49,000 cubic yards b)Rock Armor 8"thick -0.67 feet [29.67 X 29.67 X 5)/2 -(29 X 29 X 5)/2]X 1200 117,927 cubic feet!27 =4,368 cubic yards Use 1__4,::,;:,;50::,:0:...;;c;:,;ub::;ic:::..l,;ya::;r::;ds;;..J c)Rock Apron at toe of slope [2ft X 7ft wide X 1200 long]/27 =622 Use 1__,;;;65;.;0;...;;c,;;;ub;,;ic;..:,;ya;,;rd:;:;s:....J Total Rock Armor Cell 4A South Dike 10)Cell 4A East Slope (Slope #3 ) 5,150 cubic yards I Average height Length 8 feet 1200 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [8 X 8 X 5)/2 -(8 X 8 X 3)/21 X 1200 =76,800 cubic feet!27 =1185 cubic yards Use 1__1,;,,:,;;;20::,:0:...;;c;:,;ub;,;ic;..:,;ya::;rd:;:;s;;..J Volume Calculation -Cell 4A (can't)page 4 Remaining Random Fill [11 X 11 X 5)/2 -(8 X 8 X 5)/2J X 1200 6,333 cubic yards Use 1L.._::.6,~50::.;0:...:c~ub::.;i;;.c.z.;ya;;;.r;::ds:.... ~171,000 cubic feeV 27 ~ Total Random Slope #3 7,700 cubic yards b)Rock Armor 8"thick -0.67 feet 14.52 cubic feet per linear foot of dike 14.52 cubic foot per linear foot X 1200/27 645 cubic feetl 27 ~645 cubic yards Use 1L-_~65::.;0:...:C~ub::.;i;;.c.z.;ya;;;.r;::ds:.... c)Toe Apron Not required Total Rock Armor Cell 4A East Slope 650 cubic yards I Volume Summary -Cell 4A Top of Cell South (Slope #1 ) West (Slope #2 ) East (Slope #3 ) Totals Lower Upper Rock Bridqinq Laver Random Clav Random Armor 204,000 68,000 68,000 136,000 34,000 77,000 34,000 8,650 30,000 19,000 5,150 1,200 6,500 650 204,000 176,200 68,000 195,500 48,450 Cell 4A Reclamation Cat 637 Resource Requirements Volume Calculation -Cell 4A (con't)page 5 Volume Route Yds/hr %Equip.Hr. Cell 4A Bridging Lift Tailings Surface 204,000 4 296 100%689.2 Cell 4A Lower Random Fill Tailings Surface 68,000 5 368 100%184.8 Slope 1 77,000 5 368 100%209.2 Slope 2 30,000 4 296 100%101.4 Slope 3 1,200 5 368 100%3.3 Total 498.6 Cell 4A Upper Random Fill Tailings Surface 136,000 5 368 100%369.6 Slope 1 34,000 5 368 100%92.4 Slope 2 19,000 4 296 100%64.2 Slope 3 6,500 5 368 100%17.7 Total 543.8 Cell 3 Rock Armor --use Highway Trucks Clay Volume ~ ~ Clay Production Cell 4A (use same assumptions as Cell 2 ) 68,000 Bank Cubic Yards (BCY) 0.8 Swell Factor 85,000 Loose Cubic Yards (LCY) Trucking 475 LCY/hr 150,000 LCY /475 LCY/hr ~ use 8 trucks plus one (1)Loader 179 hours 320 hours 980 Loader D8N w/ripper Cat 651 WW Cat 825 Camp. 14G Patrol 5000 gal WW 320 X 8 Trucks ~2560 hours Hours 320 320 320 350 350 175 Rock Armor Production Cell 4A 48,450 cubic yards (cy) 38 cy per hour times 8 trucks 304 cy per hour delivered Assume 25%extra time for spreading,loading and screen wait 304/1.25 243.2 cy per hour 199 Hours Miscellaneous MISCELLANEOUS ITEMS MISCELLANEOUS ITEMS Equipment Mobilization Resource Description Units Cost/Unit Task Units Task Cost Butler Machinery Mobilization LS $334,240 I 1 $334,240 Other Equipment Mobilization LS $2,2751 1 $2,275 Cranes LS $2,700 2 $5,400 Total Equipment Mobilization Office Facilities Resource Description Units Cost/Unit Task Units $341,915 Task Cost Install New Powerline LS $15,000 1 $15,000 Utilities for Offices months $1,000 36 $36,000 Temporary Office Trailer months $1,500 3 $4,500 Temporary Office Trailer,mob,demob &setup LS $3,000 1 $3,000 Total Office Facilities Decontamination Pad Resource Description Laborers Construct Wheel Wash Facility Units Cost/Unit hrs $12 LS $180,000 Task Units 8,320 1 $58,500 Task Cost $101,275 $180,000 Total Wheel Wash Facility Facilities constructed in 2000 &2008 ($180,000) $101,275 MANAGEMENVSUPPORT Resource Description Units Cost/Unit Task Units Task Cost Manager/Engineer hrs $54.88 6,240 $342,482 Radiation Safety Officer hrs $42.88 6,240 $267,593 Secretary hrs $17.34 6,240 $108,224 Clerk hrs $14.27 4,866 $69,438 Environmental Technician (Part time,4.5 years)hrs $24.15 4,866 $117,511 Maintenance Foreman hrs $31.47 6,240 $196,356 Chemist hrs $25.25 2,080 $52,514 Security hrs $9.29 18,720 $173,981 Safety Engineer hrs $24.15 4,160 $100,461 Misc.Materials &Supplies hrs $36.45 6,240 $227,448 Health Physics Costs hrs $64.81 2,080 $134,800 Environmental Monitoring Costs,Laboratory years $71,620.00 4.5 $322,290 Total Management/Support TOTAL MISCELLANEOUS ITEMS 7/27/2009 -11',20 AM ~WMM Rec Plan Est July 2009 (1 ).xls $2,113,100 $2,614,790 1 Denison Mines (USA)Corp. White Mesa Mil! Rock Production ROCK PRODUCTION COST Assumptions: Rock is obtained from gravel source north of Blanding,Utah.BLM Public Pit Rock is processed by screening only,no crushing is required,1.25 CY offeed for 1 CY of product Rock is produced and stockpiled at the site Site is 7 road miles from the miil;6 miles of which is paved public highway Rock wili be hauled in 22 CY beilydump trucks,contract haulers ($80.00/hr) Rock will be dumped in windrows on Tailings Cells by trucks,spread by grader,and spread by D7 Dozer Trucks can average 30 MPH (1.75 rounds/hr) Material fed to plant PRODUCTION OF RIPRAP Resource Description Product Required (CY) 146,000 Units Reject Factor 25.0% Cost/Unit Material Feed to Plant (CY) 182,500 Task Units Plant Throughput (CY/hr) 122 Task Cost Plant Operating Hours 1,500 Equipment Operators hrs $18.43 2,340 $43,137 Laborer hrs $12.17 1,500 $18,259 Cat D8N Dozer With Ripper hrs $95.08 365 $34,706 Cat 980 Loader hrs $103.73 1,975 $204,869 Screening Plant w/conveyors*hrs $69.44 1,500 $104,159 BLM Usage Fee CY $0.60 146,000 $87,600 Contract Highway Trucks -Bellydumps**hrs $80.00 3,800 $304,000 Equipment Maintenance (Butler)hrs $18.58 2,340 $43,486 Total Production of RipRap RIPRAP COST PER CUBIC YARD DELIVERED $840,215 $5.751 *Cost Quoted from Power Motive Corporation,Denver,Colorado updated February 24,2009 $7,000 plus $4,400 for conveyors,176 hours per month for one month,plus screen set up at $2,000. Mob and Demob - $5,000.00 **Cost quoted from Dennis Cosby,Cosby Trucking,Inc.,Blanding,Utah,Updated February 16,2009 (includes ownership expense,fuel,maintanence and operator) 7/27/2009 -11 :21 AM ~WMM Rec Plan Est July 2009 (1 ).xls International Uranium (USA)Corp. White Mesa Mill Amy Bushman From: Sent: To: Cc: Subject: Attachments: Dear Arrty, Brad Neptune [bneptune@powermotivecorp.comj Tuesday,February 24,2009 9:33 AM Amy Bushman Mike Norris 2512KT Screen FNG_2512kt_2512k.pdf;FT_271K_291 K.pdf Thank you for the opportunity to quote a rental screen to Denison Mines. Last year,per the February 22,2008 quote,we quoted our 271 K plant and our 2512KT plant.i'm attaching spec sheets on each so you can see what each screen and plant looks like. The 271K plant does NOT have anyon-plant stackers,but does have a 4'x 10'two deck screen.You would need to rent off plant hydraulic stackers to stack out two products.It is also a rubber tired plant. The 2512KT is a Track Mounted plant that DOES have on-plant stackers and can stack out three products right off of the plant.You do not need additional conveyors. Rental rates are the same as quoted last year. 271 K Screen 2512KT Screen 36"x 60'Hyd Stacker 30"x 80'Hyd Stacker $7,000 I mo $12,800 I mo $1,500 I mo $2,200 I mo The 271K Screen is presently tied up on a rental.The 2512KT plant is sitting idle in Colorado Springs.I'd estimate delivery from C Spgs to Blanding to be approximately $2,500.The present purchase price we have on the 2512KT is $135,000,thus you may want to consider purchasing the plant as opposed to renting it for $12,800 per month. Screen cloth and installation of screen cloth will run about $2,000 total. Please feel free to email or call with any additional questions. Sincerely, Brad Neptune 970-985-5875 SCREENSMOSILE ••••••ASTEC•• The Fold'nGo 2512KT is amobile track screening plant that features a Kolberg@ double deck screen for processing sand & gravel,topsoil,slag,crushed stone and recycled materials,This plant offers astandard inlet hopper chute for inline processing feed from crushing plant or feed conveyor.As with all Fold 'n Go@mobilescreening plants,this plant provides easy to reach engine controls and grease points for routine service. For material producers that prefer wheels and need more site to site mobility,the Fold 'n Go 2512K is available,Both plants provide simple- to-use hydraulic leveling gears,hydraulic plant controls and screen angle adjustment. Fold 'n Go 2512KT/2512K SCREEN: Kolberg0 2512K doubledeck screen:5'x 12'screanlop and hallam deck driven by 1200 RPM Vibrating mechanism rnounted OIl screen;Variableeccentric shaft\Vilh fIVe (5) force amplitude settings on adjustable slip counterweights; Hubberisolator blocks:Hydraulic conlrols forvariable angle operation.Top and baltom discharge chutes,aggregate spreader,and fixed access ladder wilh wrap-around walkway for easy screen access.Standard material separations range from 3"1010M depending on <lpplicalion. POWER SYSTEM: 125 HP (100 HP for 2512K)Tier II John Deere l'Ialer- cooled diesel engine to power all plant functions and three on-boardstacking conveyors;1211011baltef'{. Engine mounted pumps to operate all plant fllHctiOllS, NEMA-4 rated instrumentpanel,Iachomel€f,hour meIer.voltmeler,oil pressure gauge,oil temperalura gauge and emergency stop.Auxiliary power for up 10 30 HP Off-plant conveyors. PLANT CAPACITY: Screening plant can process up to 350 TPH Ofmore of feed malalia!.AcltlaJ tonnages will vary depending on application requirements:feed rnaterial size,material separations,type of screens used,weight of product and other materialOOI1siderations. CONVEYOR SYSTEM; 2512KT:Delivery Conveyor-28'x42"conveyorwilh hydraulic drive (350 FPM):Full·length skirt boards. Side Conveyors-Two(2)27'x24-swingout conveyors with hydraulic variable spood drive (0-350 FPM): Fines Conveyor--20'x48"COI1veyorwith hydraulic drive (350 FPM);All conveyors have220 PIW,'lf8x 1/16 cover belting,bell cleaners and fold for Iransport. 2512K:Oellvery Conveyor-38'x 36"OOI1voyorwith hydraulic drive (350 FPM).Side Conveyors--Tw<> (2)27'x 24"swingalitconveyors with hydra\llic variable speed drive (0-350 FPM):Fint*!Conveyor·-23'x 42- conveyorwith hydraulic drive (350 FPM);All COIWGYors have 220 PIW,1/8 x1/16 cover belting,belt cleaners and fold for transport FEEDER SYSTEM: 12 cubic yard heaped capacity hopper wilh 6'x13'top opening:Heavy-<fuly 25·sloped grizzlywith 6"nominal opening;Hydraulic dUmp with patented scissoractioo (or easycleaning;Adjustable gale;14'x42'beH feederwilh hydraulic variablespeed drive(0.$0 FPM): Belling is 330 PIW,3116 x1/16 cover. CHASSIS: 2512KT:24"I-beam:Hydraulic landing gear for leveling of plant;Inter-Trac FL6 tracks with wireless remote conlrolfor easyjobsite rnoverrrent. 2512K:21"I-beam with king pin typo hitch;HydraUlic landing gearfor laveling of plan;Tandem axle assembly ,'lith eight (8)11 R22.5 tires and mud Raps;Leaf spring type suspensioo,air brakes,roar taillighls and side marlter lights. SERVlCE CAPACITY: Fuel.140gal Hydratllic Tank 100 gar (150 galfor 2512K) TRANSPORTATION:2512KT 2512K Weight 61'OO0 Ibs 54,6001bs Heighl 13'11·(onlowbO'f}13'0" L®gth......49'8'62'2" Width....11'11"11'11' Axles N/A Tandem OPTIONS: 8ulkhead--Assists io ramping forloader feed tofeed hopper. Remote Control Grlzlly-Assists in dumping oVei"sizo material off food hopper from loader. Wings·-Assisls in funneling feed material onto feed hopper griZZly. Hammermill Shredder·-Helps break food malerial apart forimprovedprocessing.Hydraulic controls can retract shredderup and awayfrom drop lone of feed conveyor to delivery conveyor formalerial bypass ofshredder. Screen Cloth @7.00iiAslooM:lbiQSae«ls-Mrijll>m!m\'lld SllOOflcaHo\1s.[lfOsubja<:l to change. Ii L I:I .AllIEASTECMOBILESCREENSanAstecIndustriesCompany.-W ~ 2104 WEST LEFEVRE RD •STERLING,IL61001 •800.545 2125 FAX 815.626.6430'aslecmobJklscroons,COOl Call to:J)eA/A//s Gstty7 Company:Gsiv /af:t{keNS / Phone No:(q'~;r)6 rf:3-2890 Date:02,liP -oCj Subject: Notes: Comments: Call to:tid cl j)ou,/e Company:US.!5!.tt1 -$"jlce!t t2f(;cf; Phone No:(1f2:f).58 r-;SI? Date:7:S!&I",!t Z(%J 2 / 7 Subject:Irtiett!Afs C.d.81tt!Rtl,,,r:l:s, Notes:7eJ IS c<Jfltwle",!s: -!l1a{eIlIJ IJ solJ 0"-'u .[;.,&rMc<&ke!I/l1lt.e ~,4s/s. -CU4l!!!,..,.';'/JIt,;-e,/$JfcJ,S'r?/e/t-64"'1c yad ,eer1foveJ -7httee (3)Ott-h<t>2-(-i)ItJle~flJ $"'Mces ctsc £;til! 73t?vwv rA"-;7'tJA/-Md "I dl/ l.e,</.>DR",.,;,A/MI!.of i3h...J,";r -'7':>-,lowM.!;(d~J Pa/l.-k.,.f.eerlude W/lfJ --6~eL die _relZ-ffllfli0 '1'-1>1 fVJJ tw!esJ.'l.levU (uec<ey<'NJ Comments: U:5C-#tJ.hO IJeIt--i3C-T /Iv PJltm",!e .j;>L ;'Wale"J co.>I J Ai,ll;'/""..P cIeU&tf.Nce III ;l¢cCPf>/;".>~·"e5. Equipment Costs EQUIPMENT COSTS WHITE MESA MILL RECLAMATION COST HOURLY EQUIPMENT COSTS 2009 DOLLARS Actual equipment rates quoted from North Central Rental &Leasing,LLC,12 month rental period February 2,2009 RATE MTCE FUEL I FUEL@ Tiresand GET TOTAL MobJDemob Mob/Demob I Ooeratinq Hrs ,I MONTHLY I HOURLY EXPENDABLES I USAGE 1 $2.107 COST per machine Totals I per Month 25,400 144.32 8.00 23.5 49.51 5.00 $206.83 $21,200 $84,800 704 12,650 71.88 4.30 8.5 17.91 1.00 $95.08 $14,100 $14,100 176 10,700 60.80 3.85 7.0 14.75 1.00 $80.39 $12,450 $12,450 176 11,200 63.64 3.85 13.0 27.39 0.50 $95.38 $13,000 $13,000 176 13,300 75.57 4.20 9.0 18.96 5.00 $103.73 $12,800 $12,800 176 17,500 99.43 5.45 11.0 23.18 5.00 $133.06 $15,450 $15,450 176 11,500 65.34 6.20 8.5 17.91 4.00 $93.45 $13,250 $53,000 704 16,500 93.75 6.40 13.0 27.39 1.00 $128.54 $24,000 $24,000 176 11,800 67.05 5.20 17.0 35.82 2.00 $110.06 $14,300 $14,300 176 6,650 37.78 3.05 10.0 21.07 2.00 $63.90 $6,450 $6,450 176 8,800 50.00 3.60 5.5 11.59 5.00 $70.19 $10,150 $10,150 176 12,650 71.88 4.35 8.5 17.91 5.00 $99.13 512,100 $12,100 176 Units 4 1 1 1 1 1 4 1 1 1 1 1 637E Scraper D8R Dozer D7R Dozer 8258 Compactor 980 G Loader 988 G Loader 770 Haul Truck 365BL Excavator 651 Water Wagon 5000gal Water Truck 14H/Ripper Motor Grader 16HfRipper Motor Grader I $272,600]3,168 Equipment Rental Rate Quoted by WorldWide Rental Services (06/25/2009)for Cat 330 Excavator with Demo-Pro 900 Shear Cat 330w/Shear 22,500.00 127.84 17.99 12.5 26.34 I $172.171 Meb/Demob $2,275 Small tools allocation -Demolition - $1.35/mechanic labor hour for oxygen/acetylene,expendables Q ButlerEquipment Maintenance Cost Monthly Maintenance Flat Rate $62,315.00 Buller Maintained Equipment Planned Operating Hours/month 3,394 Planned Operating hours/month (other equipment 570 Total Operating hours per month 3,964 FueJUsage per day,gal, 20 Fuel Cost per month,21 days 885 Maintenance Cost per Operating Hour $18.58 Mob/Demob $61,640 Crane Rental Rates 65ton Hydraulic Crane 30ton Hydraulic Crane RATE MTCE I FUEL FUEL@ TOTAL I MONTHLY I HOURLY EXPENDABLES I USAGE 1 $2.107 COST 11,100 63.07 2.15 15.0 31.61 $96.82 6,400 36.36 2.15 10.0 21.07 $59.58 Meb/Demob $2,000 $700 Rental Rates updated from Hennen Equipment,02/25/09 712712009 -11:21AM -WMMRecPlanEstJuly2009(1 }.>:Js InternationalUranium(USA)Corp. WhiteMesaMill RENTAL &LEASING LLC A SubsidiaryofButlerMachinery Co. 3401 33'"Street Southwest Po Box 9559 Fargo,ND 58106-9559 Phone (701)232-0033 Fax (701)298-1717 .February 2,2009 Denison Mines Attn:Harold Roberts E-Mailedto:hroberts@denisonmines.com Dear Harold: Thank you for the invitation to qnote Denison Mines (Denison)the equipment needed for their mining project in Blanding,Utah.North Central Rental &Leasing,(NCRL) respectfully submits our proposal for a maintained fleet of Caterpillar machines. Listed on Attachment A,you will find the models,quantities,monthly I'ental rates,hours allowed per month,excess hour charge,guaranteed number of months rates are based upon,total freight charges and the maintenance rate per hour for materials only. All rates shown on Attachment A do not include any state,local,property or any other taxes that may be applicable. Rates are based upon electric hoUl'meter readings that are attached to the dash of each machine.Rates are based on 176 hours of use each month.Excess hour charges,if any, will be calculated and invoiced at the end of the project.There would be no credit issued for any hours under the allowed during the term ofthis proposal.If Denison elects to double shift machines,then NCRL would invoice those hours at the end of each month.(To figure the double shift rates,take the excess hour rate shown on Attachment A times the number of hours). Rates are based upon a minimum guarantee of 12 months and a package deal.This quote is valid for 90 days. Maintenance and Repairs: Maintenance:The maintenance rates per hour listed on Attachment A includes the material part items only,such as air,oil,and fuel filters,lubricant oils,grease,anti-freeze, batteries,fan belts,lights and make-up oils.NCRL would invoice Denison actual hours used on machines at the end of each month.Our monthly maintenance charge would be $62,315 which includes our labor,specialized lube trucks,support vehicles and equipment, specialized tooling,scheduled oil sampling,parts trailers and inventories,mileage and travel expense. February 2,2009 Denison Mines Page 2 Maintenance (cont.):NCRL will provide two (2)full-time maintenance technicians on site fifty (50)hours per week on a schedule to be determined,Monday through Friday. Denison would have to schedule the machines available for a time frame yet to be determined adequate for NCRL maintenance personnel to perform the required maintenance.NCRL would invoice Denison for the monthly maintenance chal'ge at the end of each month. Repairs:NCRL would be responsible for all repairs including parts and labor on our machines other than failures caused by damages or mis-use.Repail's include items as minor as starters, alternators,water pumps,hydraulic hoses,etc.to the majOi'items such as engines,transmissions, differentials,brakes,hydraulic pumps and cylinders,etc.If time permits and Denison requests NCRL's technician to perform repairs or maintenance on theil'machines,our hourly charge would be $95.00 per hour for standard time,$122.00 per hour for overtime and $140.00 per hour for Sundays and holidays plus materials. Mobilization,Freight and Assembly Charges: Mobilization:The mobilization charge of $30,820 includes the moving expense of our support personnel,set up the job site,and transportation costs of our vehicles,parts and tooling inventory to the job site.NCRL would charge the same amount to demobilize at the end of the project. Freight and Assembly Charges:The freight and assembly charges listed on Attachment A are based upon all machines shipped by truck to the job site. Denison would be responsible for demobilization including disassembly and return freight on all machines.Parts,vehicles and equipment,at the end,or at time during the rental period to Rapid City,SO NCRL would be responsible for freight to the job site for all stock order parts shipments, emergency repair parts,maintenance parts,and G.E.T.and bulk oil shipments. Once the equipment has been delivered and assembled,an inspection would take place.During the inspection,a representative of NCRL and a representative of Denison will verify on the Acceptance Report the condition of the equipment. Denison's Responsibilities Include: Operators:Provide the operators as needed to operate machines as stated in Caterpillar's operating guide.NCRL will pl'Ovide,at no expense to Denison,qualified training instructors for the purposes of training operators.This training would take place on the jobsite at the initial start up of the job and would include classroom,walk around,and in iron demonstrations. February 2,2009 Denison Mines Page 3 Fuel:Supply and fill all fuel for equipment including NCRL's service vehicles. Damages:This includes glass bl'eakage,bent handrails,stepladders,fenders,etc.NCRL's normal policy for repairing damages to rental machines is to repair them when the rental period is completed,however,if the damaged item is ofa safety concern,we would repair the damages as soon as possible after they occurI'ed.An itemized list of the parts and labor required would be provided to Denison prior to starting the repair,and invoiced at current list prices plus freight upon completion. Undercarriage and Tires:Denison would be responsible for all tire wear including tire damages on the machines with an asterisk listed on Attachment A.Equipment would have to be returned with same brand and model tires as when delivered,or prorated accordingly by percentage of tire wear and condition at termination of rental period. Upon delivel'y of machines,a representative of NCRLIBMC,a representative of Denison and a representative from an independent tire dealer or manufacturer would jointly verify in writing the condition,percentage of wear,and tire value.Upon termination of rental,we would again have the representatives mentioned above determine the condition,percentage of wear,and tire values.Any differences noted,would then be charged or credited to Denison including both materials and labor. Undercarriage wear on all track type machines would be NCRL's expense. Ground Enl!.al!.inl!.Tools:Denison would be responsible for all p31'ts relating to gl'ound engaging tools (G.E.T.),i.e.cutting edges,ripper tips and protectors,bucket tips and adapters,edges between adapters,weal'plates on bottom of buckets and all mounting hardware.NCRL would install these items on an as needed basis at the current Caterpillar list price plus freight at no additional labor costs.All machines would be delivel'ed with new G.E.T.items and are to be returned with new. We wish to thank Denison and you for giving us the opportunity to present our proposal and for all the consideration we receive. Sincerely yours, North Central Rental &Leasing Butler Machinery Company Oscar fJJ.Swenson Rental Fleet Marketing Manager ODS:hnc Attachment cc:Joel Nikle,Rental Fleet Manager Joyce Wittkopp,Assl.Rental Fleet Manager Attachment A Denison Mine I---~E_q~u_i_Lp_m_~_ntPackage Quote:BlandingL~~ah __ 1----------,-----"_February 2,20_0T~-------,----,_,_----_j i !1-------+--+1--------+-I--=MC::I:C:N:-:IM~U:-:Mc;---------+-------l !I GUARANTEED TOTAL" I MONTHLY HOURS EXCESS!NUMBER OF FREIGHT MAINTENANCE1-----,.-,-- ,I RENTAL ALLOWED HOUR!MONTHS RATE CHARGES RATE MODEL !QTY!RATE PER MONTH CHARGE I BASED UPON TO &FROM PER HOUR *6378 '4 $25,400 EA.176 EA.$73 EA.____12 EA.$21,200 EA.!$8.00 EA. i I "=D""9"'R""fT=-=R"'IP""P"'E"'Rc------f---;1----·15,450 176 i 44 12 15,550_i 4.85 i DBRfT RIPPER 1 12,650 __176 36 12 14,100 4.30 D7R1RIPPER 1,10,700 176 31 12 12,450 3.85 I i 825H ',1 11,200 --i 176 32 12 i 13,000,3.85 .-- !mT- I i980H"I 1 11,300 176 32 12 i 12,800 4.20 1 i *988H 1 17,500 176'50 12 '-15,450 5,45ij---i- *770 ·-·-----+-i--:-4-I 11 ,500 EA.176 EA.-..J----:3"'3""'E""A-.-+--1----c1;-:;2""'E=--=A-c.----'---1:-;3;'C,2;;-:5;-:;0""'E~A-.-+---;;6-;.2:-;:0""'E~A-.'---1 i I II.•I 3658 II I 1 '16,500 176'47'12 24,000,6,40 I I 10.000 GAL.Water Wagon 1 11,800 ---176 I 34 12'14,300 5.201-'--"'=--=::..:=...:.:.=:1:...:..'.="-+_---'.__.-- 5.000 GAL.Water Wagon 1 6,650 176 .__19 12 6,450 3.05 I--:--;.,--;;;--:--=c-==o-----+--------c--,'-----L -----c~---I14H/M RIPPER 1 8,800 176_._._25 12 10,150 __3.60 ! 16H/M RIPPER 1,12,650 176 36'12 12,100 4.35 !!1--------1 *PLUS TIRE WEAR i I i___i i __ **INCLUDES ASSEM8LY AND DISASSEM8LY L ., --;;c;;-;~_;__----'-_.,...-_;__;_______------cf-i-;--c--. The charge lor two servicetechnician's working lilty (50)hours per week,mainten<:tnce and lube trucks,parts and l-s=-;ec.;-rv"'i-'ccec.tc.ra:::i:..::le"'rs"-,.a'-c-n9 overhead would be $62,315 per month to be invoiced at the end 01 each month.__ 1--_______Maintenance rates per hour would be invoice~at the end of each month based upon,actuaI:..:h,:..::o.=u:..::rs:..:.__',------1 1----------1_---Delivery and receiving mobit'ization charge is $30,820 each way..._L'------., Harold Roberts From: Sent: To: Subject: Harold, Mark [kglinc@qwestoffice.net] Thursday,July Og,2009 3:05 PM Harold Roberts Costs Confirming our earlier conversation,our experience has shown that a conservative number for replacement of cutting edges and bucket teeth is $1.00 per operated hour.The costs may be slightly less for equipment such as compactors, verses the heavier usage for scrapers,dozers,loaders and blades.Tire wear and replacement is conservatively estimated at $4.00 per operating hour for rubber tired equipment,based on current costs for replacement tires.Costs may be slightly less for equipment such as water wagons and blades,and these cost should cover tire damage as well. These numbers cover 12 years of operations,on over 20 projects,large and small.For the past 12 years,these projects utilized equipment from North Central Rental and Leasing (Butler Machinery),involving 100s of Thousands of operating hours. Please call if you need additional information of have questions. Mark Kerr 1 KGL Associates INC KGL Associates INC Page I of I KGL is an experienced earthmover and hazardous waste contractor KGL provides a seasoned staff for industrial, environmental and contract mining services KGL places Health and Safety above all other business considerations I<GL is an 8<H1hmoving and environmental construction contractorwith extensive expertise in both hnzardous waste and mining operations.With len years ofoperational project history and over 100 years ofcombined project management experience,we are prepared to handle any earthmoving or industrial project.from straight fOf\N.;lrd dig and h<ltll oroverburden mmoval to complex hazardous waste transport Examples of these projects include' Remediation .,),Heclamation Contract ilJlining landfill sONices Pone!construction Compacted embankments Water reSOlll'CO facilities Dams Through negotiated leasing arrangements,we have access to any type of "yellow"iron equipment necessary to perfolm.These contracts allow us to use the newest equipment at the least overall cost 10 you and your project.This allows us to be the mosl competitive contractorbringing Hle best value to yourproject.Our staff is made up of seasoned personnel who understand how to save money thl"Ough their expGrience ofmoving millions oftons of dirt,rock and waste.Noproject is beyond our scope or capabilities, Ourpersonnel are OSHA '10 hour and M$H/\trained to work on both environmental i"uld mining projects. OUr"OSHA EMRis we[1 below the standard requirements and it is our philosophy to prioritize health and safely above all olhGr business consiejerations. http://www.kglassoeiates.eom/index.html 7/9/2009 About KGL Page I of I About Us Experience ~Worked for many of the largest industrial and mining companies in the country Worked for environmental, industrial and mining engineering firms A representative list ofcompanies thai KGL and its personnel have worked for includes American Gypsum "Arch Coal 'AT &T C,Atlas Minerals Beller ivlalerials Corp CENTEX CEMEX CyprusArnax -,ivll<-Ferguson (Washington Group) Rio Algol11/BHP Billiton Santa Fe Pacific (Newmon!) Southdown Industries Umelco US Silica 6§We~t7dllJffi5rin~J WO,fufuI';\;\tfJbc CEe Engineering '"Deptof Energy Harding ESE HD Knight Piesold Mactec RUST(Earth Tec)l) US Corp ofEngineers http://www.kglassoeiates.com/aboutus.html 7/9/2009 WORLDWIDE RENTAL SERVICES 1125 Legacy View St Salt Lake City,UT 84104 TEL:(801)978·3300 FAX:(801)978·3777 TOLL FREE:1·877·997·7752 W 0/LOW IDE RENTAL SERVICES RENTAL RATE QUOTE We are pleased to offer the following rates for your review.Quoted rates are good for 30 days. 25 June 2009 Name:Dennison Mines Address:Blanding,UT Phone #435-678-2221 Fax #435-678-2224 Contact:Deanne E-mail:dwalker@denisonmines.com Project Name: Est.Start Date: Description ofEquipment Equipment Serial Minimum Tenn Monthly Rate Mob/Demob Rate ~No. PC300 excavator with 22500.00 2275.00 shear _.. GENERAL TERMS AND CONDITIONS OF RENTAL 1.Machine month is defined as cost ofone machine per month.If multiple units are required,multiply the base rate times the number ofunits required. 2.Credit approval will bedetermined by credit information supplied by the contractor to Worldwide prior to job mobilization. 3.Monthly rate is based on 28 days and 200 hours ofusage.Overtime will be billed at 70%the hourly rate. 4.Payment terms are net 30. 5.All equipment is subject to availablility. 6.Excessive tire weal'and ground engaging tool wear to be billed at end ofcontract. 7.Customer must supply insurance binder covering value ofequipment We look forward to supplying your equipment requirements.Please let me know if you have any questions or ifthere is anything else you need! February 25,2009 Amy Bushman Denison Mines USA 6425 S.Hwy 191 Blanding,UT B4511 Dear Amy: We are pleased to quote rental rates on the following: 1.Grove RT530E (30 ton)Crane $6,400.00/Month 2.Grove RT760E (60 ton)Crane $l1,lOO.OO/Month 3.Grove RT875E (75 ton)Crane $14,600.00/Month We currently do not have a 75 ton available. Freight will be $700.00 for the 30 ton and $1000.00 for the 60 ton atstart and again atend of rental period. We believe the equipment as quoted will exceed your expectations.On behalf of Honnen Equipment Co.,thank you for the opportunity to quote Grove lifting machinery.Please call if you have any questions or comments. Sincerely, Shane Frazee Territory Manager 970-270-2070 cell 800-746-6636 office This proposal subject to the following conditions: 1)Quote valid for 30 days. 2)Specific quoted units subject to availability. 5055 E 72-u Avenue Commerce City,CO 80022 303-287-7506 2358/·70 FfOnlage Road Grand Junction,CO 81505 970-243-7090 16 Girord Street POBox 27 Durango,CO 81303 970·247~4460 150 Salt Creek Highway PO Box 1180 Mills,WY 82644 307-266-4474 5217 S.Highway 59 Gillette,WY 82718 307-685-4288 October 2008 to January 2009 -Fuel Cost Calculation Producer Price Index -Commodities #2 Diesel October November December January 2009 282,3 ' 224,9 ' 171,5 ' 164,1 '842,8 $2.107 per Gallon off road use '4 month Average Bureau of Labor Statistics Data www.bls.gov -J::i BUREAU OF LABOR STATISTICS Page 1 of 1 Newsroom I Tutorials I Release Calendar ffi!1l Home Subject Areas Databases &Tables Publications Economic Releases A - Z Index I AbDut BlS.--__-_. I)<itabases,...1'ables..<SL..c.:alc;ul<itorsb':l§.Ll~le(;t fONT SIZE:I:J (-iJ Change Output Options:From:11999:.3 To:120093 r Include graphs NEW! Data extracted on:March 2,2009 (12:28:39 PM) Producer Price Index~Commodities Series Id:WPU057303 Not Seasonally Adjusted Group:Fuels and related products and power Item:NO.2 diesel fuel Base Date:198200 More Formatting Opti.9.fL'i ..... Year Jan Feb;Mar Apr Mav Jun lui Aug Sep Oct Noy Dec Annual 199940.2 38.1 43.2 jS3.!53.0 53,5 59,8 65,6 68.8 67.5 71.9 72.7 57.3 2000:76.1 86.1 90.0 :84,1 82.8 85.7 89.5 ]92.1 110.8110.0 110.4 101.6 !93.3 2001,96.7 92.4 83.5 <86.4 93.1 90.2 81.6 82.0 91.6 75.9 71.3 56.2 83.4 2002:58.9 60.0 69.7 76.9 74.7 73.3 77.6 80.4 ;92.3 98.7 85.5 86.8 ;77.9 2003'97.6 123.8'129.4'102.3:87.9 89.8 92,7 96.6 91.1 101.1 95.9 98.1 100,5 2004j109.3 103.7:109.7'119.9:121.0 114.2123,0 135,1'140.9 166.6 159.7 135.3 128.2 2005:141.1 149.5.173.3,175.4,170.80187.2'189.8'200,6.212.6264.1 206.2 :198.5 189,1 2006:197,1 196.22068230.4239.6'246.9 237,5250,2201.3197.5 197.2 203.0 216.9 2007:180.9 193.5'220.2:238.0226.5,227.6,243.5,231.2:246.2 249.6 296.7 271.9 235.5 2008:278.2 287.5)53.7,365.1.398.2:421.0.431.9 346.7 342.3 282.3(p)'224,9(p):171.5(P)325.3(p)2009164,1(p)I II I II I 1 'I 'I 'I p :Preliminary.All indexes are subject to revision four months after original publication. Quick Links Tools t:l At a Glance Tables :]Economic News Releases Q Databases &Tables Cl Maps Calculators Q Inflation '')Location Quotient ,j Injury And Illness Help <i Help &Tutorials 'J A to Z Index ()FAQs Cj Glossary D About BLS Cl Contact Us Info ::J What's New»CareerS @ BLSoFindItlDOL ')Join Ollr Mailing Lists G Privacy &Security CI Linking &Copyright Information Frequently Asked Questions I Freedom of Information Act I Customer Survey U.S.Bureau oflaborStatistics 2 Nassachusetts Avenue,NE Washington,DC 20212·0001 www.bls.gov I Telephorle:(202)691-5200 I Do you have a Data question? http://data,bls,gov/PDQ/servlet/SurveyOutputServlet;jsessionid=f030403891615$3F$3F$ bls.gov 3/212009 Labor Costs LABOR COSTS 2009 Estimated Labor Rates** Specified Wages Heavy Construction Labor Classification Base Rate Mandated Fringe 13.97% Labor Burden (FICA,SUI, FUI etc 21.28% Company Benefits (medical,life insure etc)Fringe Costs Labor CosVHR Boiler Makers Millwrights Ironworkers Carpenters Cement Masons Electricians Ironworkers -Reinforcing Laborers (including pipelayers) Pipefitters POWER EQUIPMENTOPERATOR Backhoes Cranes Dozers Graders Loaders Scrapers Trackhoes Tractors Truck Drivers $25.22 $18.76 $3.52 no added cost $22.28 $47.50 $20.82 $4.28 $2.91 $0.15 $7.34 $28.16 $21.84 $9.92 $3.05 no added cost $12.97 $34.81 $14.75 $3.03 $2.06 $0.11 $5.20 $19.95 $14.00 $0.56 $1.96 $2.42 $4.94 $18.94 $14.52 $2.71 $2.03 $0.38 $5.12 $19.64 $14.00 $1.96 $2.98 $4.94 $18.94 $9.00 $0.00 $1.26 $1.92 $3.17 $12.17 $12.60 $1.76 $2.68 $4.44 $17.04 S $10.00 $1.40 $2.13 $3.53 $13.53 $10.43 $1.46 $2.22 $3.68 $14.11 $13.63 $1.90 $2.90 $4.80 $18.43 $13.61 $1.90 $2.90 $4.80 $18.41 $11.38 $1.59 $2.42 $4.01 $15.39 $12.75 $1.78 $2.71 $4.49 $17.24 $13.63 $1.90 $2.90 $4.80 $18.43 $9.42 $1.32 $2.00 $3.32 $12.74 $12.00 $1.68 $2.55 $4.23 $16.23 Note:base rates do notinclude FICA,worker camp,unemployment,orcompanybenefits which increase the cost perhour ••State of Utah -General Decision -Current Update UT20080073,4 pages,10/19/2008 2116f2009 -1:05 PM -WMM Rec Plan Est February 2009.xls Denison Mines (USA)Corp. White Mesa Mill Nonspecified Wages Base RateH * LABOR COSTS Labor Burden (FICA,SUI, Mandated Fringe FUI,etc. Company Benefits (medical,life insure,etc)Fringe Costs Labor CosVHR Survey Crew Member Sample Crew Member Mechanic (Demolition) Manager/Engineer Radiation Safety Officer Secretary Clerk Engineer Environmental Technician Safety Engineer Maintenance Foreman Security Personnel Chemist $11.09 $0.00 $1.55 $2.36 $3.91 $15.00 $11.09 $0.00 $1.55 $2.36 $3.91 $15.00 $11.52 $0.00 $1.61 $2.45 $4.06 $15.59 $40.58 $0.00 $5.67 $8.64 $14.30 $54.88 $31.71 $0.00 $4.43 $6.75 $11.18 $42.88 $12.82 $0.00 $1.79 $2.73 $4.52 $17.34 $10.55 $0.00 $1.47 $2.25 $3.72 $14.27 $31.71 $0.00 $4.43 $6.75 $11.18 $42.88 $17.86 $0.00 $2.49 $3.80 $6.29 $24.15 $17.86 $0.00 $2.49 $3.80 $6.29 $24.15 $23.27 $0.00 $3.25 $4.95 $8.20 $31.47 $6.87 $0.00 $0.96 $1.46 $2.42 $9.29 $18.67 $0.00 $2.61 $3.97 $6.58 $25.25 ***Reflects 0.0%cost of living raise for 2009 2/16/2009 "1:05PM 'WMM Ree Plan EstFebruary2009.xls Denison Mines {USA}Corp. White MesaMill Page 1 of 4 GENERAL DECISION:UT20080073 10/10/2008 UT73 Date:October 10,2008 General Decision Number:UT20080073 10/10/2008 State:Utah Construction Type:Heavy County:San Juan County in Utah. Including Natural Gas Pipeline Construction Modification Number o ENGI0003-047 07/01/2008 Publication Date 10/10/2008 Excluding Natural Gas Pipeline Construction Rates POWER EQUIPMENT OPERATOR (3)Backhoe $24.53 ENGI0003-054 11/01/2007 Natural Gas Pipeline construction Only Rates POWER EQUIPMENT OPERATOR Backhoe/Excavator/Trackhoe, Blade/Grader,Boom, Bulldozer,Crane, Mechanic,Trencher $30.25 Oiler $17.66 LAB00295-018 11/01/2007 Natural Gas Pipeline Construction Only Rates LABORER Chain Saw and Power Drill ...$18.86 Common or General,Nail gun,Pipelayer,Pot Tender..$17.61 Formworker $18.61 Powderman $19.36 Sandblaster $18.36 SUUT2008-028 08/19/2008 Rates CARPENTER,Including Form Work (Excluding Natural Gas Pipeline Construction Form Fringes 12.71 Fringes 13 .14 9.64 Fringes 4.94 4.94 4.94 4.94 4.94 Fringes http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/16/2009 Work)$14.75 CEMENT MASON/CONCRETE FINISHER ...$14.00 LABORER:Mason Tender - Cement/Concrete $9.00 LABORER:Common or General (Excluding Natural Gas Pipeline Construction)$12.00 LABORER:Pipelayer (Excluding Natural Gas Pipeline Construction)$9.00 OPERATOR:Roller (Dirt and Grade Compaction)$10.89 OPERATOR:Blade/Grader (Excluding Natural Gas Pipeline Construction)$13.61 OPERATOR:Excavator (Excluding Natural Gas Pipeline Construction)$12.75 OPERATOR:Front End Loader $11.38 OPERATOR:Trackhoe (Excluding Natural Gas Pipeline Construction)$13.63 TRUCK DRIVER (Excluding Natural Gas Pipeline Construction)$12.00 TEAM0222-020 11/01/2007 NATURAL GAS PIPELINE CONSTRUCTION ONLY Rates TRUCK DRIVER Group 1: Articulated End Dump,Low Boy,Rollagon or Similar type Equipment,Truck Mechanic $27.14 Group 2: A-Frame,Challenger(For transportation purposes)I Forklift,Fuel Truck,Gin Pole,Rubber-Tired Tractor,Tandem Float (4 &5 Axle),Track Truck/All-Track Dumper Equipment,Vacuum Truck, Winch Truck $26.68 Group 3: Ambulance I Bus,Dump 3.03 0.56 0.36 0.00 0.00 y" 0.00 0.00 y 0.00 ~ 0.00 ,/ 0.00 y 0.00 ,/ Fringes 8.74 8.74 Page 2 of 4 http://frwebgate.access.gpo.gov/cgi-binigetdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/16/2009 Truck (2 and 3 axle), Flatbed Truck (2 and 3 axle),Grease Truck,Hot Pass Truck (3 axle)I Jeep,Pick-up,Single Axle Float (3 axle),Skid Truck (2 and 3 axle), Station Wagon,Stringer Bead &Hot Pass (2 axle), Swamp Buggy/Marsh Buggy, or similar type equipment,Team Driver, Water Truck (2 and 3 axle).$26.39 Premium Pay: 8.74 Page 3 of 4 Add $1.25 to the above Rate for the following classifications Group 1:Low Boy and Truck Mechanic Group 2:Stringer Truck WELDERS -Receive rate prescribed for craft performing operation to which welding is incidental. ======================================================== Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5 (a)(1)(ii)). In the listing above,the "SUlI designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates.Other designations indicate unions whose rates have been determined to be prevailing. WAGE DETERMINATION APPEALS PROCESS 1.)Has there been an initial decision in he matter?This can be: *an existing published wage determination *a survey underlying a wage determination *a Wage and Hour Division letter setting forth a position on a wage determination matter *a conformance (additional classification and rate)ruling On survey related matters,initial contact,including requests for summaries http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/1612009 Page 4 of 4 of surveys,should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program.If the response from this initial contact is not satisfactory,then the process described in 2.)and 3.)should be followed. with regard to any other matter not yet ripe for the formal process described here,initial contact should be with the Branch of Construction Wage Determinations.Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S.Department of Labor 200 Constitution Avenue,N.W. Washington,DC 20210 2.)If the answer to the question in 1.)is yes,then an interested party (those affected by the action)can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator U.S.Department of Labor 200 Constitution Avenue,N.W. Washington,DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description,area practice material,etc.)that the requestor considers relevant to the issue. 3.)If the decision of the Administrator is not favorable,an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board).Write to: Administrative Review Board U.S.Department of Labor 200 Constitution Avenue/N.W. Washington,DC 20210 4.)All decisions by the Administrative Review Board are final. END OF GENERAL DECISION http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/16/2009 Long Term Care LONG TERM CARE CALCULATION February 2009 Base Amount (Starting in Dec.1978) CPI-U December,1978 CPI-U December 2008 $250,000 67.7 210.2 Adjusted Long Term Care =$250,000 x (CPI-U most recent /CPI-U Dec.,1978) Adjusted Long Term Care 2/16/2009 -12:36 PM -WMM Rec Plan Est February 2009.xls $776,322 Denison Mines (USA)Corp. White Mesa Mill Bureau of Labor Statistics Data www,bls.gov -:::BUREAU OF LABOR STATISTICS Page I of I Newsroom I Tutorials I Release Calendar 1illl Home Subject Areas Databases &Tables Publications Economic Releases A •Z Xndcl<I About BlS J:)<lt<l!J<ls~~,T<l!Jl~s6{c.:alculators..!Jy..Su!Jjec;t ChangeOutput Options:From:11998 iJ To:12oo8:::J $ r include graphs NEW! Data extracted on:February 16,2009 (1:32:15 PM) Consumer Price Index -All Urban Consumers Series Id:CUUROOOOSAO,CUUSOOOOSAO Not Seasonally Adjusted Area:U.S.city average Item:All items Base Period:1982"84~100 ["Im'e Formattitln Options ~ fONT SIZE:(]m Year;Jan Feb Mar Apr May Jun Jul :Aug Sep Oc'Nov Oec Annual HALF1 :HALF2 1998~161.6 :161.9 162.2 162.5 162.8 153.0 '163.2 163.4 163.6 164.0 164.0 163.9 163,0 162.3 163.7 1999:164.3 164.5 165.0 166.2 166.2 166.2 166.7 157.1 157.9 168.2 168.3 166.6 ;165.4 167.8 2000;168.8 169.8 171.2 171.3 171.5 172.4 172.8 172.8 173.7 174,0 174,1 174,0 172,2 170,8 173.6 2001:175,1 175,8 176.2 176,9 177,7 178.0 177.5 177.5 178,3 177,7 177.4 176,7 177.1 176.6 177,5 2002177.1 177,8 178.8 179,8 179,8 179,9 180,1 180,7 181.0 181.3 181.3 180,9 179,9 ;178,9 180.9 2003181.7 183.1 184.2 183,8 '183.5 183,7 :183,9 184,6 185,2 185.0 184.5 184,3 184.0 183.3 184.6 2004185.2 186.2 187.4 188,0 189,1 189.7 189.4 189.5 189.9 190.9 191.0 190.3 188.9 187.6 190.2 2005190.7 191.8 193.3 194.6 194.4 :194,5 195.4 196.4 198,8 199.2 197.6 196.8 195.3 193.2 197.4 2006:198.3:198:7 199.8 201.5:202,5 :202.9 :203.5 203.9 202.9201.8 201.5 201.8 :201.6 ,200.6 202.6 2007:202.416:203.499:205.352 206.686207.949:208.352:208.299 207.917 208.490208.936 210.177 210.036'207.342:205.709 208.976 2008:211.080:211.693;213.528 214.823:216.632:218.815219.964219.086 218.783:216.573212.425 210.228-215,303;214.429 216.177 Quick Links Tools ']At a Glance Tables iJ Economic News Releases D Datab,lses &Tables 'J Maps Calculators :'.:1 Inflation U Location Quotient '::i Injury And Illness Help 8 Help &Tutorials CI A to Z Index D FAQs :,\Glossary iJ About BLS -J Contact Us Info U What's New ,'J Careers @ BLS o Find It!DOL OJ Join our Mailing Lists ')Privacy &Security 'J Linking &Copyright Information Fre<luently Asked Questions I Freedom ofInformation Act I Customer Survey U.S.Bureau oflaborStatistics 2 ~1assachu5elts Avenue,NE Washington,DC 20212·0001 www.bls.gov I Telephone:(202)691·5200 I Do YOI)have a o"ta question' http://data.bIs.gOYIPDQ/servlet/SurveyOutputServlet;jsessionid=f030a14d5fOd$3 F$3FR$ bls·90V 2/16/2009