Loading...
HomeMy WebLinkAboutDRC-2009-000604 - 0901a06880105a68OliC/ ..PoL^i - CCOUc)L{ DENISOIsn/ MINES March 6, 2009 ^^^:3^17^^ Denison Mkms (US/^ Corp. 1050 ITU) Street, Suite 990 Denver, CO 90XU USA Tei: 303628-7798 Fax: 303 389-4135 w««w.denisomninea.coffl Sent Via Federal Express Mr. Dane Finerfrock, Executive Secretary Utah Radiation Control Board Utah Department of Enviromnental Quality 168 North 1950 West P.O. Box 144810 Salt Lake City, UT 84114-4810 Dear Mr. Finerfrock: Re: Revised Cost Estimates for Reclamation of the White Mesa MiU and Tailings Management System-Electronic Copy In accordance with the reporting requirements found at UAC R313-12-111, please fmd enclosed an electronic "test searchable" copy ofthe document Cost Estimates for Reclamation ofthe White Mesa Mill and Tailings Management System, February, 2009. If you should have any questions regarding this matter please contact me Yours very truly, n DENISON MINES (USA) CORP. Steven D. Landau Manager, Enviromnental Affairs Cc Ron Hochstein Harold Roberts David Frydenlund OENISOJ)~~ MINES Denison Mines (USA)Corp. 1050 17th Street,Suite 950 Denver,CO 80265 USA Tel:303 628-7798 Fax:303 389-4125 www.denisonmines.com Revised Cost Estimates for Reclamation of the White Mesa Mill and Tailings Management System Blanding,Utah February 2009 State of Utahlle.(2)Byproduct Material License #UT1900479 Copy 1 State of Utah Denison Mines (USA)Corp. www.denisonmines.com 1050 17th Street,Suite 950 Denver,CO,USA 80265 Tel:303 628-7798 Fax:303389-4125 Cost Summary WHITE MESA MILL RECLAMATION COST ESTIMATE February 2009 Revision Mill Decommissioning Cell 1 Cell 2 Cell 3 Cell4A Miscellaneous Subtotal Direct Costs Profit Allowance Contingency Licensing &Bonding UDEQ Contract Administration Long Term Care Fund Total Reclamation Revised Bond Amount 3/3/2009 -8:33 AM -WMM Rec Plan Est February 2009.xls $1,901,661 $1,736,609 $1,460,678 $1,854,647 $1,395,386 $2,551,975 $10,900,955 10.00%$1,090,096 15.00%$1,635,143 2.00%$218,019 4.00%$436,038 $776,322 $15,056,573 $15,056,573 Denison Mines (USA)Corp. White Mesa Mill Mill Decommissioning MILL DECOMMISSIONING Mill Building Demolition MILL DECOMMISSIONING Resource Description Units CostlUnit Task Units Task Cost Equipment Operators hrs $18.43 720 $13,273 Mechanics hrs $15.59 640 $9,976 Laborers hrs $12.17 320 $3,895 Small Tools hrs $1.35 960 $1,296 Cat 769 Haul Truck hrs $89.45 640 $57,248 Truck Drivers hrs $16.23 640 $10,387 Cat 988 Loader hrs $128.06 160 $20,489 Cat 365 Excavator hrs $127.54 160 $20,407 Cat 330 wi PC-400 metalShears hrs $172.17 160 $27,547 65 Ton Crane hrs $96.82 160 $15,492 30 Ton Crane hrs $59.58 80 $4,767 Equipment Maintenance (Butler)hrs $21.15 1,360 $28,765 Concrete Removal sf $3.30 37,500 $123,750 Total Mill Building Demolition Ore Feed Demolition Resource Description Units Cost/Unit Task Units $337,292 Task Cost Equipment Operators hrs $18.43 48 $885 Mechanics hrs $15.59 64 $998 Laborers hrs $12.17 32 $390 Small Tools hrs $1.35 96 $130 Cat 769 Haul Truck hrs $89.45 64 $5,725 Truck Drivers hrs $16.23 64 $1,039 Cat 988 Loader hrs $128.06 16 $2,049 Cat 365 Excavator hrs $127.54 16 $2,041 Cat 330 wi PC-400 metalShears hrs $172.17 16 $2,755 30 Ton Crane hrs $59.58 $0 Equipment Maintenance (Butler)hrs $21.15 112 $2,369 Total Ore Feed Demolition SX Building Demolition Resource Description Units Cost/Unit Task Units $18,378 Task Cost Equipment Operators hrs $18.43 240 $4,424 Mechanics hrs $15.59 320 $4,988 Laborers hrs $12.17 160 $1,948 Small Tools hrs $1.35 480 $648 Cat 769 Haul Truck hrs $89.45 320 $28,624 Truck Drivers hrs $16.23 320 $5,194 Cat 988 Loader hrs $128.06 80 $10,245 Cat 365 Excavator hrs $127.54 80 $10,203 Cat 330 wi PC-400 metalShears hrs $172.17 80 $13,774 65 Ton Crane hrs $96.82 $0 30 Ton Crane hrs $59.58 $0 Equipment Maintenance (Butler)hrs $21.15 560 $11,844 Concrete Removal sf $3.30 55,970 $184,701 Total SX Building Demolition 3/3/2009-8:33 AM-WMM Ree Plan Est February 2009.xls $276,593 Denison Mines (USA)Corp. White Mesa Mill MILL DECOMMISSIONING CCD Circuit Removal Resource Description Units CosVUnit Task Units Task Cost Equipment Operators hrs $18.43 135 $2,489 Mechanics hrs $15.59 120 $1,870 Laborers hrs $12.17 60 $730 Small Tools hrs $1.35 180 $243 Cat 769 Haul Truck hrs $89.45 120 $10,734 Truck Drivers hrs $16.23 120 $1,948 Cat 988 Loader hrs $128.06 30 $3,842 Cat 365 Excavator hrs $127.54 30 $3,826 Cat 330 wi PC-400 metalShears hrs $172.17 30 $5,165 65 Ton Crane hrs $96.82 30 $2,905 30 Ton Crane hrs $59.58 15 $894 Equipment Maintenance (Butler)hrs $21.15 255 $5,393 Concrete Removal sf $3.30 15,000 $49,500 Total CCD Circuit Removal Sample Plant Removal Resource Description Units CostlUnit Task Units $89,539 Task Cost Equipment Operators hrs $18.43 24 $442 Mechanics hrs $15.59 32 $499 Laborers hrs $12.17 16 $195 Small Tools hrs $1.35 48 $65 Cat 769 Haul Truck hrs $89.45 32 $2,862 Truck Drivers hrs $16.23 32 $519 Cat 988 Loader hrs $128.06 8 $1,024 Cat 365 Excavator hrs $127.54 8 $1,020 Cat 330 wi PC-400 metalShears hrs $172.17 8 $1,377 30 Ton Crane hrs $59.58 $0 Equipment Maintenance (Butler)hrs $21.15 56 $1,184 Concrete Removal sf $3.30 4,200 $13,860 Total Sample Plant Removal Boiler Demolition Resource Description Units CosVUnit Task Units $23,049 Task Cost Equipment Operators hrs $18.43 120 $2,212 Mechanics hrs $15.59 160 $2,494 Laborers hrs $12.17 80 $974 Small Tools hrs $1.35 240 $324 Cat 769 Haul Truck hrs $89.45 160 $14,312 Truck Drivers hrs $16.23 160 $2,597 Cat 988 Loader hrs $128.06 40 $5,122 Cat 365 Excavator hrs $127.54 40 $5,102 Cat 330 wi PC-400 metalShears hrs $172.17 40 $6,887 65 Ton Crane hrs $96.82 $0 30 Ton Crane hrs $59.58 $0 Equipment Maintenance (Butler)hrs $21.15 280 $5,922 Concrete Removal sf $3.30 2,900 $9,570 Total Boiler Demolition 3/3/2009 -8:33 AM-WMM Rec Plan Esl February2009.xls $55,516 Denison Mines (USA)Corp. While Mesa Mill MILL DECOMMISSIONING Vanadium Oxidation Circuit Removal Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 48 $885 Mechanics hrs $15.59 64 $998 Laborers hrs $12.17 32 $390 Small Tools hrs $1.35 96 $130 Cat 769 Haul Truck hrs $89.45 64 $5,725 Truck Drivers hrs $16.23 64 $1,039 Cat 988 Loader hrs $128.06 16 $2,049 Cat 365 Excavator hrs $127.54 16 $2,041 Cat 330 wi PC-400 metalShears hrs $172.17 16 $2,755 65 Ton Crane hrs $96.82 $0 30 Ton Crane hrs $59.58 $0 Equipment Maintenance (Butler)hrs $21.15 112 $2,369 Concrete Removal sf $3.30 1,200 $3,960 Total Vanadium Oxidation Circuit Removal Main Shop/Warehouse Demolition Resource Description Units Cost/Unit Task Units $22,338 Task Cost Equipment Operators hrs $18.43 96 $1,770 Mechanics hrs $15.59 128 $1,995 Laborers hrs $12.17 64 $779 Small Tools hrs $1.35 192 $259 Cat 769 Haul Truck hrs $89.45 128 $11,450 Truck Drivers hrs $16.23 128 $2,077 Cat 988 Loader hrs $128.06 32 $4,098 Cat 365 Excavator hrs $127.54 32 $4,081 Cat 330 wi PC-400 meta/Shears hrs $172.17 32 $5,509 Equipment Maintenance (Butler)hrs $21.15 224 $4,738 Concrete Removal sf $3.30 19,300 $63,690 Total Main Shop/Warehouse Demolition Decon Pads (2)Demolition Resource Description Units Cost/Unit Task Units $100,447 Task Cost Equipment Operators hrs $18.43 48 $885 Mechanics hrs $15.59 64 $998 Laborers hrs $12.17 32 $390 Small Too/s hrs $1.35 96 $130 Cat 769 Haul Truck hrs $89.45 64 $5,725 Truck Drivers hrs $16.23 64 $1,039 Cat 988 Loader hrs $128.06 16 $2,049 Cat 365 Excavator hrs $127.54 16 $2,041 Cat 330 wi PC-400 metalShears hrs $172.17 16 $2,755 Equipment Maintenance (Butler)hrs $0.00 112 $0 Concrete Removal sf $3.30 1,350 $4,455 Total Decon Pads (2)Demolition Office Building Demolition Resource Description Units Cost/Unit Task Units $20,464 Task Cost Equipment Operators hrs $18.43 72 $1,327 Mechanics hrs $15.59 96 $1,496 Laborers hrs $12.17 48 $584 Small Tools hrs $1.35 144 $194 Cat 769 Haul Truck hrs $89.45 96 $8,587 Truck Drivers hrs $16.23 96 $1,558 Cat 988 Loader hrs $128.06 24 $3,073 Cat 365 Excavator hrs $127.54 24 $3,061 Cat 330 wi PC-400 metalShears hrs $172.17 24 $4,132 Equipment Maintenance (Butler)hrs $21.15 168 $3,553 Concrete Removal sf $1.25 12,100 $15,125 Total Office Building Demolition 3/3/2009 -8:33 AM-WMM Rec Plan Est February 2009.xls $42,692 Denison Mines (USA)Corp. White Mesa Mill MILL DECOMMISSIONING Misc.Tankage &Spare Parts Removal Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 24 $442 Mechanics hrs $15.59 32 $499 Laborers hrs $12.17 16 $195 Small Tools hrs $1.35 48 $65 Cat 769 Haul Truck hrs $89.45 32 $2,862 Truck Drivers hrs $16.23 32 $519 Cat 988 Loader hrs $128.06 8 $1,024 Cat 365 Excavator hrs $127.54 8 $1,020 Cat 330 w/PC-400 metalShears hrs $172.17 8 $1,377 Equipment Maintenance (Butler)hrs $21.15 56 $1,184 Total Misc.Tankage &Spare Parts Removal Mill Yard Decontamination Resource Description Units Cost/Unit Task Units $9,189 Task Cost Equipment Operators hrs $18.43 582 $10,729 Cat 637 Scraper hrs $201.83 257 $51,871 Cat 988 Loader hrs $128.06 65 $8,324 Cat D8N Dozer With Ripper hrs $94.08 65 $6,115 Cat D7 Dozer hrs $79.39 65 $5,161 Cat 651 Waterwagon hrs $108.06 65 $7,024 Cat 14G Motorgrader hrs $65.19 65 $4,237 Equipment Maintenance (Butler)hrs $21.15 582 $12,310 Total Mill Yard Decontamination Ore Storage Pad Decontamination Resource Description Units Cost/Unit Task Units $105,771 Task Cost Equipment Operators hrs $18.43 429 $7,908 Cat 637 Scraper hrs $201.83 189 $38,146 Cat 988 Loader hrs $128.06 48 $6,147 Cat D8N Dozer With Ripper hrs $94.08 48 $4,516 Cat D7 Dozer hrs $79.39 48 $3,811 Cat 651 Waterwagon hrs $108.06 48 $5,187 Cat 14G Motorgrader hrs $65.19 48 $3,129 Equipment Maintenance (Butler)hrs $21.15 429 $9,074 Total Ore Storage Pad Decontamination Equipment Storage Area Cleanup Resource Description Units Cost/Unit Task Units $77,918 Task Cost Equipment Operators hrs $18.43 154 $2,839 Cat 637 Scraper hrs $201.83 69 $13,926 Cat 988 Loader hrs $128.06 17 $2,177 Cat D8N Dozer With Ripper hrs $94.08 17 $1,599 Cat D7 Dozer hrs $79.39 17 $1,350 Cat 651 Waterwagon hrs $108.06 17 $1,837 Cat 14G Motorgrader hrs $65.19 17 $1,108 Equipment Maintenance (Butler)hrs $21.15 154 $3,257 Total Equipment Storage Area Cleanup 3/3/2009 -8:33 AM-WMM Ree Plan Est February 2009.xls $28,094 Denison Mines (USA)Corp. White Mesa Mill MILL DECOMMISSIONING Revegetate Mill Yard &Ore Pad Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 231 $4,258 Cat 637 Scraper hrs $201.83 132 $26,642 Cat 988 Loader hrs $128.06 0 $0 Cat D8N Dozer With Ripper hrs $94.08 33 $3,105 Cat D7 Dozer hrs $79.39 33 $2,620 Cat 651 Waterwagon hrs $108.06 $0 Cat 14G Motorgrader hrs $65.19 33 $2,151 Equipment Maintenance (Butler)hrs $21.15 231 $4,886 Total Revegetate Mill Yard &Ore Pad Total Demolition and Decontamination CLEANUP OF WINDBLOWN CONTAMINATION Scoping Survey Resource Description Units Cost/Unit Task Units $43,662 $1,250,9431 Task Cost Soil Samples each $50.00 100 $5,000 Survey Crew hrs $15.00 752 $11,281 Sample Crew hrs $15.00 1,312 $19,682 Total Scoping Survey $35,964 Characterization Survey Resource Description Units Cost/Unit Task Units Task Cost Soil Samples each $50.00 472 $23,600 Sample Crew hrs $15.00 1,136 $17,042 Total Characterization Survey $40,642 Final Status Survey Resource Description Units Cost/Unit Task Units Task Cost Soil Samples each $50.00 300 $15,000 Sample Crew hrs $15.00 3,552 $53,287 Total Final Status Survey $68,287 Windblown Cleanup Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,190 $21,937 Cat 637 Scraper hrs $201.83 680 $137,246 Cat D8N Dozer With Ripper hrs $94.08 170 $15,994 Cat D7 Dozer hrs $79.39 170 $13,497 Cat 14H Motorgrader hrs $65.19 170 $11,082 Soil Samples each $50.00 500 $25,000 Survey Crew hrs $15.00 163 $2,445 Sample Crew hrs $15.00 83 $1,245 Equipment Maintenance (Butler)hrs $21.15 1,190 $25,169 Units Total Windblown Cleanup Quality Control Resource Description Quality Control Contractor Total Quality Control Total Cleanup Windblown Contamination 3/3/2009 -8:33 AM-WMM Rec Plan Est February 2009.xls $253,617 Cost/Unit Task Units Task Cost IL-hr_s $_62_.0_01 2:-,0_80......1__$:-1_28....;.,9_6_°1 $128,960 $527,4691 Denison Mines (USA)Corp. White Mesa Mill MILL DECOMMISSIONING Conventional Ore Disposal Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 604 $11,140 Cat 769 Haul Truck (3)hrs $89.45 333 $29,749 Cat 988 Loader hrs $128.06 111 $14,196 Cat 651 Waterwagon hrs $108.06 111 $11,980 Cat 14G Motorgrader hrs $65.19 50 $3,259 Equipment Maintenance (Butler)hrs $21.15 604 $12,781 Total Conventional Ore Disposal Total Quantity Alternate Feed Disposal 65,185 Cubic Yards' 196 Cubic Yards per Truck per hour 333 Truck Hours ,88,000 tons maximum projected for 2008 $83,1061 Cabot and FMRI Material Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 153 $2,821 Cat 769 Haul Truck (3)hrs $89.45 62 $5,531 Cat 988 Loader hrs $128.06 21 $2,639 Cat 651 Waterwagon hrs $108.06 21 $2,227 Cat 14G Motorgrader hrs $65.19 50 $3,259 Equipment Maintenance (Butler)hrs $21.15 153 $3,237 Total Cabot &FMRI Material Total Quantity 12,119 CubicYards'(as of 01/31/09) 196 Cubic Yards per Truck per hour 62 Truck Hours ,Includes Linde,Cabot and FMRI $19,716 Cameco Barrels and Honeywell Barrels Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $16.23 190 $3,092 Flat Bed Trailer and Tractor'hrs $55.00 190 $10,477 Fork Lift (2)hrs $18.00 381 $6,858 Total Cameco and honeywell Barrels ,includes operator Sub-Total Alternate Feed Disposal TOTAL MILL DECOMMISSIONING 3/3/2009 -8:33 AM-WMM Ree Plan Est February 2009.xls 19,049 Barrels (as of 01/31/09) 40 Barrels per load 0.4 Hours per load 190 Truck Hours $20,426 $40,1421 $1,901,661 1 Denison Mines (USA)Corp. White Mesa Mill iI II c/:'-1-:,r_"-,,,/.) COST ESTIMA TE ' ,J';.;I1'"IA<..'::;-th2t;o~7 e.--.h((.,6e :':;'r./'c(UC"7C'':;(1/\/t:(c:;rt:~7'"'.;;>66 2 ..-r -,c...r-J;;"erlr"""7~//I';'c/"'~.No'/a-a,.,C7~~'"~.......y.l""''17"'"'''' ,,"/_,//:/_j-h'_-by ~~Er/;?1,~-rrr ..../000 -rc"C7 cJU7S;-4J~Crr 7~~/<-C.J7r'(C7C'"--'/.J"'~,L:'0<.J,vd...." ~t ~ir ~N~'"v~"7,1<./e .:v..v <:tE::-V/NtI.i/ti-""'"c:,""''/''''''''-''V''l7'h.,;'W;;;",to/'NlQ~,L' I;b:.iz he ';;~,..,d ,t)ow/\/{.A/J/Vd d /JG,.Ji7C,;?J,{,U d;"'_~Ceo)./_'I::7e' 0/-lAo YC<k<,acc-c:>/.?AC"<Q 7074-'-~ ~fA Cell ..3 Call Z C61/I ;1'?;U ~/t~ On..&'STOdhl,ld Ao .38,/726;000 H.z... I)'707/0CJo ./l-z /j 2:3 I 2 31 I CJ Uu <tt 2/C;87 }00(,).fjZ 2)57"",6(JoliZ. ; /'43>/Da 0.[--1<: CJI7,O(J(,).(.f2... 4:s..n/rn.c ~cLb70""7OF='::5''7~rVOr.ML)#/2C:/£/'4 /0 x/o m;'';''"",fj.nd (/0 b A:::ssu<'?'tc..5C.o/".J?:;;:</ev'7 ,C::;;""""/,,lohJ "'7 $~~/'i W17.#jtl';nelar J-!.JJ eJc.o,J1!!"fb ;J..ra l./,...,e.![.A"",;h-/""~""'''''1.'/#4/d.J--ti.S p"j.J'c:c.A~'/e=r Gt./uLttNC.,IoN #ttUG-S'~.:f-9. c25/402(000 ';:;:2.::::- /(J7~-flZ ~~(..,oo h)l,4r..J ::)00 /,"';'--'7.1 /lJC7 ;2hJe~X 54,,-s;:<,17 .J).I7;;f _175":;/1)iAl,!r..r l-SIMile7 -_..,.--...- COST ESTIMATE -----.._--------------------------- h.:5"$'o/"hC ..30 r?71S..-'tS....~~.....-r'::>r"'<2<.<<.:4 /0 x·/.:J Cf",.;<:jI !;; ::,;../c,-/O/":~0";'<.J~..i.....;(,-.:....e /ir?C""'i (of"?e<.NtI~5e"rf.J ///..520-",/4?.Ry _3S4 ~YI():/()~'1 .3D m/<{;I'IO 62 A17 oS X Z,..,1:>,.,><&hr-z .::;::-/9'7:2 /n,r-i In..-s 7 Qny A.:s:s-~.nte /'?1"-(?/,,~~<.)4??Ge--r/>J,.v .,...~"""Bd",,,,t7<J.A1 ~kc Sc.-.o'-;"';/7 c:'~w ~.,Q":;~/71(NPI'=20 6)"P?:7Q C::::::;."..,~l'e~ ;?o p",,?.s-x 2/.'"l Q-?.x 8/.4.ra/C07 -:;;;:!3'zo /-"14--.1 ~S .....23,'=>00 G...,4)..s 384 (;"'10.1 /0"1; S<--C-:JrJJ .s:.-rGlry .::s;;;,-y'!e;r ~.,L.::<. 70...,.-....."'"::rC:4!!rv'NI/Vj'/i'liIW ,I;.I"'.r #'i 1..3 /2.J ?<..n/!,YI...lV/4G /00 ~.....~r~/~L"?.,:s:oh_ e...-.,/J 1I'::so.(T~/CliPc.H (Ufl';*.I..-..4-2Z(;J ,,2)~/.A-c..7C"n../747,.'N"';:;t/~v~ $",.VV7 ~(;{"'C,..,../1,%(;1"';.,<.{¢-/~d./k r-~"",,e-,:)O$.tfJ;l ..::J<-r/;;;...J:,e ....? H;:>,s(/"r;.4".' •,20%c,/4~tvdl rO;(,;/~at:/c/,*~~c.:;,~4~J . .,,Pr,;,oJ ';/Vy (,Ahll ~{,t.J'e I ..,../",<1 ~c .......,.-b ~.rI<Q (J?",,/.-...-. ..sC/<.....::s:..."Y"/.q~w.il 6~rOJt/N"'cd (/",v'/oX """T ~,nd <.J1:~ •5...~""",//be iF'V;r"L -I-,e.tu.,/j ;I ,•C.,..,to .f~.::S""O (.:....8.--J " .25/90 Z/000./7"''-_ /v 7 ,,-iI)jr,o - c:;.~c..u,...,;G ve;"'" Cr6-W c;.......;~k.c -4722 c;....Il'S /(;>0 ~1'"1e;.£/.0 ..."/,P-"OI.JTV) ~S"~#(.s;.~/0"7 ?rD~/N./-Io~'1-72..Z.c.-'/'>':::: /00 G~/~ 47 >(Z-x .6 .::/75Z he-S.7 COST ESTIMATE -~"";"'J_--.. 4 72/y ,!~= 472 "-/7'0"'1 sf:x'8h<"~x'2.. ,r'/;,<7,r""c;>-<>/-:9r-/7"/t'"J -7-.-Z"~""",-?::-"o'-<C-;7J..J -r:.J/'.J>t:f~CJI'''''''J"I''.:::-<::/";7': D->7 ...,~~<,-i~r5x2..x:S :::.J[7C)'hrs. r---- ///.3~1"""""';J.r..$) .-z.3~fc07 C-re;o~IQ-n.":" ~Ji21 6e,·~!::.~p ~8)Beb 6~/w4t.~~~~.= II>{~oeeeL Th &v...~'t=<~'E'e C"44'J ,wtlA.,.~~4 t::~MA Bn~~ ft2.~i.d;)~7.c.~e ~AU to..)~~~~(~'b~) ~~~~~.....':l>.oto-1vLes,L..JIu..,~6:O1~~,~, ~~~~(ao.1a"b~) e Wll.L..~ur~loa ~m.J~~~,)~~~!~'Y"I'O ~ z .2~14-0Z.-:--101"(~~oo,",,2 1..'3,~O()(,0 :z.o 4 J72/)1t 4. .C~(~~ioO ~~~1'tls.~~T .:co l~+-.LaJ.=l.ee,~~~-4..t~~~Dd-ul~ •CuW (~T~t$-~'b sP-~/~~ ';8 r '200 ~iOO]~-zs.,~fl d~~. o bsLw4 "Zc Cl&:J,~~'O~~~~~~~~f.~\lc.:N " INTERNA TIONAL URANIUM (USA)CORP.~-'..filYIl COST ESTIMATE ' :..,:.~:,,..,.,..>:(3<.,"________________'_'iiIIIiioiI'':'..'......~,'i'~. ~T ~c.al<:.t:::v e.nect of . Mlu.~fss.-~~/f-}Q W,NOCww,J CbN~/~A.J (~.;t) '\5)'c,U!"bAJ -uP . ..~~za2.~A~~t4~~,~t'oePcrnloJe:: ~o..., III ~'0 r:~c...~u...e.e ~~~ ::: ~94Jceo ~' ~(54}\00 '1d~\ e &s IT 's NC'F ~">O >J W~~~~MbV -ell'~()I-)"'~(~6.~I.A~~·U~Q"~"!1 .~-...~...~Tl::il k ~.. e ~s«:"c:::.~~.k-~l~t!li!Ietd~~"'~GQl..Je.J~ ~~~~Wfl..!-'l!4f ~T sCat 0-~~ ~~~.. ~2/7 ~3Ih'"~0.$0 ~"'wo ~!...;..(~c.rd3,+v;(';'8i ~~ ?J){.(£)~J 'Fil¥iITvK l[IEV0lffia@JrY A<tc~)lI]nthng SmIDlill21irJl JamJ.&-:;'2009 WMM AILIERNAT!:FEED RECEIPTS FOR THEMONTHSVDINGJanU813':';I1,ZOOiJ 379 September Dry Tons Received June .t!!!l! 379 Cabet (;a¥Gined Pr;;;duc!-GaiT'.ecn CaF2 Fans\"eUFMRI I{F f'roduc!-Gameco Regen Produc1-CameooUF4MaterEaI~Cameco =-;;-==_ 3,9 ~_.....;;.....,~__;;.......;,.__~,.;;.._=~;;...,__=~"~ WMM 11e2 Material Receipts FOR"lNElVio~rrHENDfNGJanuay31,2009 ~r,:ei»?lJm'j(~&:!.!:!!.!J!l§lL ~~August SeRternber O()tober NOllemher Deeernber TolarVTD lfleceivEd ~VleSiena 1g,19iJR,..,:'J"'·3:.-:;:3~3 •• WMM ALTERNATE FEED l:ndilf1g)Irntenf(oi"!f FORTHEMONTHEND1i\IG January31,2009 P,im Yea.eOlcllng L":ndlnQ 20GS Uk:)20na Tons ~ ~~Egg Balance Cabot 5,184 5,184 CaF2-Honeywell 1,083 i ,083 Cafcined?rOducl·cameoI'i;247 i ,247 FansteEi1!FII<'J'11 10,798 379 'l1,177 I<FPfoducl-Cameco i ,007 1,007 Reger.Pmduc:-Cameco i85 185 UF41vlateriai·Cameco_-:::;:;:2~O=2-_"""""""'~-------=;20;;2;,:_1S,70S 379 20,O8'l- AVEY8ge tl3011 ~0.3·0.6%conlenl 0.5-3.0%content 4.5~;'content (1.25·0.5%content 1'9fa.content 7·8.0%COOlent 75-80%contem Harold Roberts From: Sent: To: Subject: Harold, This is what I found: Ryan Palmer Monday,February 16,20092:35 PM Harold Roberts RE:Alternate feed barrels Alternative Feed Materials Total Drum count in Inventory Alternative Feed K-F Calcine Regen UF4 CaF-2 Ryan Palmer Wally B.ending balance 2007 6,001 3,600 568 1 3,005 #Drums Received 07- current 517 4)00 342 815 Total Inventory 6518 7,800 910 816 3,005 t:435-678-2221 x102 I f:435-678-2224 6425 S.Highway 191,PO Box 809,Blanding,UT 84511 DENISON MINES (USA)CORP www.denisonmines.com This e-mail is intended for exclusive use the person(s)mentioned as the recipient(s).This message and any attached files with it are confidential and may contain priVileged or proprietary information.If you are not the intended recipient(s) please delete this message and notify the sender.You may not use,distribute print or copy this message if you are not the intended recipient(s). From:Harold Roberts Sent:Monday,February 16,2009 1:41 PM To:Ryan Palmer Subject:Re:Alternate feed barrels Ryan: I need the total number of barrels of UF4,calcined,KF,regen and Honeywell alternate feed material on site as of January 31,2009. Thanks, Harold Roberts t:(303)389-4160 I f:(303)389-4125 1050 17th Street,Suite 950,Denver,CO 80265 1 DENISON MINES (USA)CORP www.denisonmines.com Cell! RECLAMATION OF CELL 1 RECLAMATION OF CELL 1 Units Dewatering of Cell 1 Resource Description Dewatering of Cell 1 Total Dewatering of Cell 1 Cost/Unit Task Units Task Cost l_hr_s ...J--__..:....$0_.4_81 6---:.2,_40_01_-:$_30....,:.,0_0_01 $30,000 Crystal Removal Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 2,695 $49,681 Cat 769 Truck hrs $89.45 2,157 $192,945 Truck Drivers hrs $16.23 2,157 $35,008 Cat 988 Loader hrs $128.06 539 $69,024 Cat D8N Dozer With Ripper hrs $94.08 539 $50,712 Cat 365 Excavator hrs $127.54 539 $68,745 Cat 651 Waterwagon hrs $108.06 539 $58,247 Cat 14G Motorgrader hrs $65.19 539 $35,137 Equipment Maintenance (Butler)hrs $21.15 4,852 $102,623 Total Crystal Removal Contaminated Materials Removal Resource Description Units Cost/Unit Task Units $662,120 Task Cost Equipment Operators hrs $18.43 616 $11,356 Cat 637 Scraper hrs $201.83 308 $62,164 Cat D8N Dozer With Ripper hrs $94.08 77 $7,245 Cat 825C Compactor hrs $94.88 77 $7,306 Cat 651 Waterwagon hrs $108.06 77 $8,321 Cat 14G Motorgrader hrs $65.19 77 $5,020 Equipment Maintenance (Butler)hrs $21.15 616 $13,029 Total Contaminated Materials Removal Topsoil Application Resource Description Units Cost/Unit Task Units $114,440 Task Cost Equipment Operators hrs $18.43 240 $4,424 Cat 637 Scraper hrs $201.83 120 $24,220 Cat D8N Dozer With Ripper hrs $94.08 40 $3,763 Cat 651 Waterwagon hrs $108.06 40 $4,323 Cat 14G Motorgrader hrs $65.19 40 $2,608 Equipment Maintenance (Butler)hrs $21.15 240 $5,076 Total Topsoil Application 3/3/2009 -8:32 AM -WMM Ree Plan Est February 2009.xls $44,414 Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 1 Construct Channel Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 858 $15,817 Cat 637 Scraper hrs $201.83 272 $54,898 Cat 769 Truck hrs $89.45 450 $40,253 Truck Drivers hrs $16.23 450 $7,304 Cat 988 Loader hrs $128.06 150 $19,209 Drilling &Blasting Contractor BCY $2.33 89,100 $207,475 Cat 14G Motorgrader hrs $65.19 218 $14,211 Cat D8N Dozer With Ripper hrs $94.08 218 $20,510 Equipment Maintenance (Butler)hrs $21.15 1,308 $27,665 Total Construct Channel Place Clay Liner Resource Description Units Cost/Unit Task Units $407,342 Task Cost Equipment Operators hrs $18.43 355 $6,544 Cat 637 Scraper hrs $201.83 0 $0 Cat 825 Compactor hrs $94.88 60 $5,693 Cat D8N Dozer With Ripper hrs $94.08 60 $5,645 Cat 07 Dozer hrs $79.39 0 $0 Cat 651 Waterwagon hrs $108.06 60 $6,484 Cat 980 Loader hrs $98.73 60 $5,924 5000 Gallon Water Truck hrs $61.90 30 $1,857 Highway Trucks hrs $63.77 435 $27,740 Truck Drivers hrs $16.23 435 $7,060 Cat 14G Motorgrader hrs $65.19 85 $5,541 Equipment Maintenance (Butler)hrs $21.15 1,225 $25,910 Total Place Clay Liner Place Lower Random Fill Resource Description Units Cost/Unit Task Units $98,397 Task Cost Equipment Operators hrs $18.43 602 $11,098 Cat 637 Scraper hrs $201.83 172 $34,715 Cat 825 Compactor hrs $94.88 86 $8,159 Cat D8N Dozer With Ripper hrs $94.08 86 $8,091 Cat 07 Dozer hrs $79.39 86 $6,828 Cat 651 Waterwagon hrs $108.06 86 $9,294 Cat 14G Motorgrader hrs $65.19 86 $5,606 Equipment Maintenance (Butler)hrs $21.15 602 $12,733 Total Place Lower Random Fill 3/3/2009 -8:32 AM -WMM Ree Plan Est February 2009.xls $96,524 Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 1 Clay Cap Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 305 $5,623 Cat 637 Scraper hrs $201.83 0 $0 Cat 825 Compactor hrs $94.88 55 $5,218 Cat D8N Dozer With Ripper hrs $94.08 55 $5,175 Cat 07 Dozer hrs $79.39 0 $0 Cat 651 Waterwagon hrs $108.06 55 $5,944 Cat 14G Motorgrader hrs $65.19 55 $3,585 Cat 980 Loader hrs $98.73 55 $5,430 5000 Gallon Water Truck hrs $61.90 30 $1,857 Highway Trucks hrs $63.77 440 $28,059 Truck Drivers hrs $16.23 440 $7,141 Equipment Maintenance (Butler)hrs $21.15 305 $6,451 Total Place Clay Cap Upper Random Fill Resource Description Units Cost/Unit Task Units $74,483 Task Cost Equipment Operators hrs $18.43 688 $12,683 Cat 637 Scraper hrs $201.83 172 $34,715 Cat 825 Compactor hrs $94.88 86 $8,159 Cat D8N Dozer With Ripper hrs $94.08 86 $8,091 Cat 07 Dozer hrs $79.39 86 $6,828 Cat 651 Waterwagon hrs $108.06 86 $9,294 Cat 14G Motorgrader hrs $65.19 86 $5,606 5000 Gallon Water Truck hrs $61.90 86 $5,324 Equipment Maintenance (Butler)hrs $21.15 688 $14,552 Total Place Upper Random Fill 3/3/2009·8:32 AM .WMM Rec Plan Est February 2009.xls $105,252 Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 1 Rock Armor Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 90 $1,659 Cat 07 Dozer hrs $79.39 30 $2,382 Cat 651 Waterwagon hrs $108.06 30 $3,242 Cat 14G Motorgrader hrs $65.19 30 $1,956 Rock Cost Delivered CY $4.98 8,607 $42,895 Equipment Maintenance (Butler)hrs $21.15 90 $1,904 Total Place Rock Armor Quality Control Resource Description Quality Control Contractor Total Quality Control Ihrs Units Cost/Unit $62.001 Task Units 8001 $54,038 Task Cost $49,6001 $49,600 TOTAL RECLAMATION OF CELL 1 3/3/2009 -8:32 AM -WMM Rec Plan Est February 2009.xls ~$1,736,609~ Denison Mines (USA)Corp. White Mesa Mill Franklin Drilling &Blasting~Inc P.O.Box 2246 Durango,CO 81392 Phone:970-259-5620 Fax:970-259-1304 Mobile:970-259-4167 Email:office@franklinblasting.com February 24,2009 Ms.Amy Bushman Denison Mines Re:Spillway blasting in Blanding,Utah Wally Bryce gave us this information to base our bid on: Quantity of approximately 89,000 in-bank cubic yards. Average depth of cut:approximately 10 feet deep Working the numbers backwards,10 feet deep by 40 feet wide would require a spillway of approximately 6000 feet in length.Is this about right? If this is correct,with a 9 feet by 9 feet pattern our price would be $2.25 per in-bank cubic yard for dry conditions.If water infiltrates into the bore holes and requires wet hole product,we will charge an additional fee.The fee will be the invoice cost of wet hole product delivered,plus 25%mark up to cover additional labor. Our mobilization for 2 drills and supplies will be $7000. Production rates of abolJt 2000 cubic yards per drill can be expected.With two drills drilling,and a 90%availability rate,that will be about 3600 cubic yards drilled per day.This should amount to about 25 working days.Will that be fast enough for your needs? Please call ifyou have any further questions. Regards, Jeff GO 39\;fd 9HIlS\;flH HIl>iH\;fCl.:J 02:'3S592:0L5 10:2:0 2:002:/2:0/10 , ••-1 INTERNATIONAL URANIUM (USA)CORP. COST ESTIMATE i .-J ,-, , ..J _C"I".,"'.,-_..c-4N~C"IC"If'l J) ..C~.,.J;r4c..'tf-~~ss .6~;;~PN hi.,~...r£,c....,.....::..1cv"'7Hw;'F 7'ar',,/=- C7"J7#"<-L-7 ,Q"7'",:wv~Al"2.it""i"'-/n~,47 -:-'"~V~.3 #~,c.u:.. SOH..(Al/t5Y 0(.)1:)....PVc..6~c'I ~I 6,de"~V"'"~....p.m'b.....-i.J...J [/,./C'1..UtpJhrt..J.r;.viJI ..!c.(,.C<.s\Jt;"T AJI plc.~/".,.,a..,1 .rt9....~-h~e·. 2.) I....... .J .2;5.76"/70 3 .;f;J.2.X ($'+I.;/,s-I;')::;:4'z'7;2hBfj ')..7 if z/'7 ~EO;J SoC! .5)71,H1d"~'.j,I'''~70 AA/dl c:.;.Xy/.r +-L~"'l.C-;v.C-r."..A·~,f'V~~N)~ ~t>rr.f'+-7b9 .,-nM'~J J a ~7,$''-''-r1'tA~~~;'?~8 ~"'ifP6'fP, ,4-;";,S't.//he.;'~.u.,~~#.i.;;,.;;,e~dv-t..r;l,jAl (Hi9 cY//''')''T;Wt:.~/'J //?4i!J .~.~- .....b'U"~I •.....,....1""'\....vnl"'\l"In..Im '\J~F\I ,",vnr-. COST ESTIMATE I 4) 71,-n.~K.Efv.r.t:"cl:'70 rOi?'-d i./c /?'?'"Ten,,,,,,'-,e:;..,....,(.)N~~.(.;""~i--/(,..,<1 cS:- jrJ c::et.<--#.3 -U ,n!J-t.,1,A,(..;z."'"-r"fi #$-1-:>Ci--~j?&u CiS";500 (,7 ..3Joey/J...,#V"AI'O'" V-~~o-.....r~<;c;. ;;;J;O!/•..J.-r.- 1-B,QtlO C-j -:d; .~c.~''-\'~ I'.{U at.'.~ 6!-c..c..:..i .;2(5'7'5'/70.3 '+;':2 X •S ++;;.4 1 I '='1~'"'1 :Z7-H%.:J ~4S,bod '-'1 \)...~e S"c.".....("~!-L~~=-:;~'\2....\J-.~1..~~\e c-'i tk l...· s) ...~.., \ ."'~'".."..........N~NI.J N~N ~:I \ \.... INTERNATIONAL URANIUM (USA)CORP. COST ESTIMATE • J ",,,,on......""IIJIU'"ww""'::Z:%:",,,,on ClCO.J Itlce...~ ...C'i~0l'''l''If............C'iC'i("4C'lC"'4l'l @ _J _*" /J,::2$' "~--'~..-....... '., -==-.:::-----.:...-:::---:--:-:~;_:::_-~---:..---------:--:::::::,....---·~ro"..r; 2 '.:S=~"'44"'1---~~~==='"2.=-;-~-:-.li-;-:-·j-4:-4-"---::-:----·...,,.~, .lS'(l1'.-'''~...-........~.._~-_..~....._-. .-~.....~'.',.,.~~:.'.,,:,.,....,. '"I:i ','I .'1 ti..,;.I.-.-1';:;...=-;00"....~..,..",.-~...,.'-.,-.-.'. ..:.,. \. .4/.Bpp ,Cr .~ ..ht>O.-;.!J't):C·t::1.$e.,iI '- iJ·:::.:~;/t:".~,e~~j~..~.eN..~.u.._..b:.-.l.v~,-; 1......" .,'/)v"111 ".rlifJ .~~'J~..14'~f.,KJ.~.7:,1"l:.~~..~..')-j..t.A-"'.,If.~',. .13~CQ c1A fSp#.~~~~~p>I~~~~f'S .8~~)£.'.'!€-l u,e.wI,". ;.."~j7~ S~s ..... I r,Ci ft/Ult ~liP .3:10 7 /J...r. INTERNATiONAL URANIUM (USA)CORP. COST ESTIMATE 6"'/800 c'j 3/0 c7/;:'" /9~S~"#",..<:r'"J..CJ ~50 hr~;V.f)'v/",,;,::;- '7'-;$'c r "'/'ee.,;,· bfl 600 '-'1'.... /97 c7/k "D~d\JjVJ ..t-13LA~-riNJ ~'-" M:"•:'•• "'..."'~'~~it:,;,.,.,::~":::~/!'~:.::...'":':.... ·to.4-1!N~Pv-r~~~o"'1Dl cy b.-s.<Q;l G"',.J ~~wz:.re 'QIl~ (See l2et//seJ $1,lO!l?)- ••-;0.... .....-......._.,.........-':"'.'-~.".. Bottom Elevation of Cell I-I 5604 MSL elevation 5604 MSL Outlet Channel CELL .5610.8I-T OF CELL BREACHED -..~5£3'L3.5 /__V""'~'.~~~ Cell 1-1 Top of Bedrock (sandstone)5615 MSL (from drill hole #95 and Construction Report) ;\::!@i:::i:i::::!iii:i::'i'!i)::,;=;:':::::!:!::,::i'!::!)'i:::i:,!I@!:!'::i:i,!:=:::i!::;::iiiii!:ii:;:::::ii::!!::::::i;:::'!:!::::::i:i::::}:::i:::;:@;ij:!(£;q~§:f:~Bn::!:t:::i~E:t;R!);~:h~;g~:::!:::ii:::ii:::I:i:':i:::':::::i,:!i::::;:::i:::::::i!::!)i::'!:iiii::':i:!:i:'ii:ii;:::):!iii:::fi:~':i~i::::;:i;:~:::::'::!):';!il:i!~;!!i!ii!!!!.;::!::'::!:::)j:l!:1I1'."Y."_.I1._- / VJ/<;",/,-L'sk~.r hO 4C. /...~,0.1 I' (;)/r;II / 5) 4c. (/ue /?:- 7;/J ~fi'~.~1<:~/so~;;"J .:?0 ~/6·-£/'1 4-CAi'e; /n/J t/o;;'..~..y.v )<¥~.J~O X tJ.5,t'f 3.5~'IfJ y/i.::-7.;7 =: I 3/0 y~1~//.e /m~c.£:Ve. .//.y,Site.(/5,0 .J .'~f-Z / ,J .8'1 ""'/,/'1"",./....., I ;:=90 22 cdt z ==57.J-j ) Use 8 ~/,1~.<;.J ij9~-;;AI2 ..:;)'" 2~hl$} Sif i,e.1 :::Uje 60 At-?/r...r" .J [:::::::::;::::::i:[:;['[{::::J::!:::..:,[[::,!!:!:i;::i[i!!~::;:i:i:;:i::::~!::!:W:!::!i:;:i:;:i:::!::;:!!!!::;;i:;:::::;:i::·'::!:,::;.::ili::::::::!!;i:~;~l:B:Hl~~!B:ni:i{::::~\~itg:!:!&;:D.:¥:;~:~::;i:::::::::,::[:::[::::::::::::::::::iI:::::@:::;!::::i::@:::;::::;:!';::::::::::;:;;;:::::,::::!:1::::'[;::I!;:!::;:!;;::!!::!::1::::::::::,::;:::::1::::::::::,::::::::::. II.'Wh••1ft1il••'If&__l I fd!2 &,1 (/9 .5-00 vr!~) ii:!):!:))!;:::i::,!:!::::):::;!!!(::!;:(:::::':;::::'i)::;'i:;:i(i;::::::;:!:I(!i!,!:ii:::(i:::i:i:i:;:;iii::i;ii::;:=:iI:i!iWiii:i:i::::i::::!:;:i:::ii::!:@:~'~iBig:fl;~i!IB!Mt:ii~§ifi~;:::§:iffl:~:£}::::;;::::i;!:@::!;:!:::::::::!::i,I:::i(:i:::;::!;i::!i!if:(i;:=:i::!::iii::;i':ii::i:;i;ii;ii::i:::::ii;;i:i:;ii:::::;iiiM:;::i;*:;:i;;::;:(!;;!;:::;:;)::;:::(i: ••~••I_.lilr_lI /l ,. I [..J -r(,/J -l:;z ,:)-';:f- f S;;/fP -9(){'l- F Zt...r r/I-.x:;"0 ,f,L Ud ·X 2.b VO r// 2,5,-.;;"'111 v/,) J';' Z 2 \h-I J 4e-.e-.·~ue-;:II -,i ...yo ?;:C've ~/Le...///7 / / 7:IJ'w(.;/tl /, /' 1151"?5'c -• / / ::;Ii-z k. iiJ_'liillla.iil_i / ..z;;;lv /L.~o;"of 18.~.d If-mo£. .1 I /iZS I .x-c6 vo /'1-' I 30 , Cell 2 RECLAMATION OF CELL 2 Obtain Permits for Clay Borrow Site -Section 16 Resource Description Units Cost/Unit Task Units Task Cost Permits &Licenses \-ea----.....-----:$-1-0,-0-00-.-00--r1-----5--r1---,.$-5-0,-00~ol Total Obtain Permits for Clay Borrow Site -Section 16 $50,000 Place Remainder of Bridging (Platform)Lift Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 0 $0 Cat 627F Scraper hrs $201.83 0 $0 Cat 815C Compactor hrs $94.88 0 $0 Cat D8N Dozer With Ripper hrs $94.08 0 $0 Cat D7 Dozer hrs $79.39 0 $0 Cat 651 Waterwagon hrs $108.06 0 $0 Cat 14G Motorgrader hrs $65.19 0 $0 Equipment Maintenance (Butler)hrs $21.15 0 $0 Total Place Remainder of Bridging (Platform)Lift Place Lower Random Fill (12") Resource Description Units Cost/Unit Task Units $0 Task Cost Equipment Operators hrs $18.43 902 $16,628 Cat 637 Scraper hrs $201.83 402 $81,137 Cat 825 Compactor hrs $94.88 100 $9,488 Cat D8N Dozer With Ripper hrs $94.08 100 $9,408 Cat D7 Dozer hrs $79.39 100 $7,939 Cat 651 Waterwagon hrs $108.06 100 $10,806 Cat 14G Motorgrader hrs $65.19 100 $6,519 Equipment Maintenance (Butler)hrs $21.15 902 $19,078 Total Place Lower Random Fill (12") Clay Layer Resource Description Units Cost/Unit Task Units $161,004 Task Cost Equipment Operators hrs $18.43 1,720 $31,707 Cat 825 Compactor hrs $94.88 325 $30,835 Cat D8N Dozer With Ripper hrs $94.08 300 $28,225 Cat D7 Dozer hrs $79.39 0 $0 Cat 651 Waterwagon hrs $108.06 300 $32,419 Cat 14G Motorgrader hrs $65.19 320 $20,860 Cat 980 Loader hrs $98.73 300 $29,619 5000 Gallon Water Truck hrs $61.90 175 $10,833 Highway Trucks hrs $63.77 2,400 $153,048 Truck Drivers hrs $16.23 2,400 $38,952 Equipment Maintenance (Butler)hrs $21.15 1,720 $36,379 Total Place Clay Layer 3/3/2009 -8:32 AM -WMM Rec Plan Est February 2009.xls $412,879 Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 2 Upper Random Fill Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,990 $36,685 Cat 637 Scraper hrs $201.83 796 $160,659 Cat 825 Compactor hrs $94.88 199 $18,881 Cat D8N Dozer With Ripper hrs $94.08 199 $18,723 Cat 07 Dozer hrs $79.39 199 $15,799 Cat 651 Waterwagon hrs $108.06 199 $21,505 Cat 14G Motorgrader hrs $65.19 199 $12,973 5000 Gallon Water Truck hrs $61.90 199 $12,319 Equipment Maintenance (Butler)hrs $21.15 1,990 $42,090 Total Place Upper Random Fill Rock Armor Resource Description Units Cost/Unit Task Units $339,633 Task Cost Equipment Operators hrs $18.43 825 $15,209 Cat 07 Dozer hrs $79.39 275 $21,833 Cat 651 Waterwagon hrs $108.06 275 $29,718 Cat 14G Motorgrader hrs $65.19 275 $17,927 Rock Cost Delivered CY $4.98 66,200 $329,926 Equipment Maintenance (Butler)hrs $21.15 825 $17,449 Units Total Place Rock Armor Quality Control Resource Description Quality Control Contractor Total Quality Control TOTAL RECLAMATION OF CELL 2 3/3/2009 -8:32 AM -WMM Rec Plan Est February 2009.xls $432,062 Cost/Unit Task Units Task Cost l_hr_s ....L...-_--:..$_62_.0_01 1.:......,0_5°...l.I__$~6__..:5,_10_..l0I $65,100 $1,460,6781 Denison Mines (USA)Corp. White Mesa Mill Volume Calculation -Cell 2 ? 1)Area of Cell 2 -2,986,660 sq ft =68.56 acres Reviewed 02/16/09 I~ 2)Area of Cell 2 still open as of February 21,2008 (see Figure A) Area totally covered 3)Assumptions Use sq ft 0.0 acres -Bridging layer is placed using random fill from piles west of Cell 2 -Cell will be graded to Design elevation utilizing finer materials in random fill stockpiles and from "clay"stockpiles. -Clay will be mined,blended,and hauled from borrow site location in Section 16 - four miles south of the mill area,using belly dump trucks,clay layer on top of Cell only, except on south slope common to Cell 3. -The upper 1 foot of random fill will be placed utilizing the fine random fill and clay stockpiles -Rock for side armor,top armor and toe aprons will come from an off-site gravel source one (1)mile north of Blanding.Rock will be produced through screening,stockpiled and trucked to the site at the time of use.Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 4)Bridging Layer (Platform Fill)Remaining to be placed sq ft X 3 ft./27 cubic feet per cubic yard = 5)Bring Platform Fill up to Design elevation (Lower Random) Assume full area of Cell X one (1)foot thick 2,986,660 sq ft X 1 ft./27 cubic feet per cubic yard = 6)Placement of Clay Layer (One (1)foot thick on top of Cell only) Assume full area of Cell X one (1)foot thick 2,986,660 sq ft X 1 ft./27 cubic feet per cubic yard = cubic yards Use 1L.....;;c;.;::u::::;b;.;;ic..lY;.;::a;;.;rd;;;s;.... 110,617 cubic yards Use I 110,700 cubic yards 110,617 cubic yards Use I 110,700 cubic yards Volume Calculation -Cell 2 (con't)page 2 7)Upper Random Fill Volume -Top of Cell area Assume full area of Cell X one (2)foot thick 2,986,660 sq ft X 2 ft.1 27 cubic feet per cubic yard = 8)Armor Protection -Top of Cell Assume full area of Cell X one-half (0.5)foot thick 221,234 cubic yards Use I 221,300 cubic yards 2,986,660 sq ft X 0.5 ft.1 27 cubic feet per cubic yard =55,309 cubic yards Use I 55,400 cubic yards 9)Cell 2 North Slope (Slope #1 )common with Cell 1-1 Average height 12 feet Length 2600 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [12 X 12 X 5)/2 -(12 X 12 X 3)/2]X 2600 =374,400 cubic feet/27 =13,867 cubic yards Use I 13,900 cubic yards Remaining Random Fill [15X15X5)/2 -(12X12X5)/2]X2600 =526,500 cubic feetl 27 =19,500 cubic yards Use I 19,500 cubic yards Total Random Fill North Slope 33,400 cubic yards b)Rock Armor 8"thick -0.67 feet [15.67 X 15.67 X 5)/2 -(15 X 15 X 5)/2]X 2600 =133,568 cubic feet/27 =4,947 cubic yards Use 1__5-.,0_0_0_cu_b_ic""""-ya_r_ds...... c)Toe Apron Total Rock Armor Cell 2 north Slope 2 X 7 X 2600 127 =1,348 cubic yards Use 1:-_1-.,4..;,0.;.0~cu;,;"b_ic""",,-ya...r...ds........ 6,400 cubic yards Volume Calculation -Cell 2 (con't)page 3 10)North Slope common with Mill yard (Slope #2 ) Average height Length 1 feet 900 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [1 X 1 X 5)/2 -(1 X 1 X 3)/2]X 900 900 cubic feet!27 = Remaining Random Fill [4 X 4 X 5)/2 -(1 X 1 X 5)/2]X 900 =33,750 cubic feet!27 = Total Random Fill North Slope 33 cubic yards Use 1......_~1_0.;"0_c.;,,u;;.;b_ic_y;l.;a_r_ds;....,j 1,250 cubic yards Use 1......_1_,3_0_0_C_u_b_ic_y;l",a_r_ds~ 1,400 cubic yards b)Rock Armor 8"thick -0.67 feet [4.67 X 4.67 X 5)/2 -(5 X 5 X 5)/2]X 900 =13,070 cubic feet!27 =484 cubic yards Use 1...__5_0_0_c_u_b_ic_y;l",a_r_ds~ c)No Toe Apron on fill common with Mill Yard Total Rock Armor on slope commmon to Mill Yard 11)Cell 2 West Dike (Slope #3 ) 500 cubic yards l Average height Length 2 feet 500 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [2 X 2 X 5)/2 -(2 X 2 X 3)/2]X 500 =2,000 cubic feet!27 =74 cubic yards Use 1...__1_0_0_cu_b_ic-,-ya_r_ds_ Volume Calculation -Cell 2 (can't)page 4 Remaining Random Fill [2 X 2 X 5)/2 -(2 X 2 X 3)/2]X 500 Total Random Fill North Slope =2,000 cubic feet!27 =74 cubic yards Use 11-__1...;0..;0.....;C,;",u..bi..;,c"'y.;.a..;,rd..;s~ 200 cubic yards I b)Rock Armor 8"thick -0.67 feet [5.67 X 5.67 X 5)/2 -(5 X 5 X 5)/2]X 500 =8,936 cubic feet!27 =331 cubic yards Use 11-__4...;0..;0.....;c,;",u..bi_c"'y.;.a..;,rd...;s~ c)Toe Apron Not required for slope 10 feet long -Drainage from Cell goes south to Cell 3 and then off of south slope of Cell 3 Total Rock Armor Cell 2 north Slope 12)Cell 2 East Dike (Slope #4 ) 400 cubic yards I Average height Length a)Random Fill Wedge from #10 1 feet 1250 feet 1 cubic foot per linear foot X 1250 46 cubic yards Use 1 1_00_c_u_b_ic_y""a_rd_s_ b)Remaining Random Fill from #10 37.5 cubic foot per linear foot X 1250/27 Total Random Slope #4 1,736 cubic yards Use 1_~1':.;,8.;.0..0 _c;;.;u;;;;b...;ic;..y~a.;;.rd_s~ 1,900 cubic yards I c)Rock Armor 8"thick -0.67 feet from #10 14.52 cubic feet per linear foot of dike 14.52 cubic foot per linear foot X 1250 127 c)Toe Apron Not required =672 cubic feetl 27 =672 cubic yards Use 1__.;.7.;.0..0_c;;.;u;;;;b...;ic;..y~a.;;.rd_s~ Total Rock Armor Cell 2 north Slope 700 cubic yards I Volume Calculation -Cell 2 (con't)page 5 13)South Slope Cell 2 com mom with Cell 3 (Slope #5 ) Average height Length 3 feet 3500 feet a)Random fill to reduce slope from 3:1 to 5:1 Random Fill [3 X 3 X 5)/2 -(3 X 3 X 3)/2]X 3500 =31,500 cubic feet!27 =1,167 cubic yards Use l 1,200 cubic yards Random Fill Upper [6 X 6 X 5)/2 -(4 X 4 X 5)/2]X 3500 =175,000 cubic feet!27 =6,481 cubic yards Use I 6,500 cubic yards b)Clay Layer [4 X 4 X 5)/2 -(3 X 3 X 5)/2]X 3500 61,250 cubic feet!27 =2,269 cubic yards Use I 2,300 cubic yards c)Rock Armor 8"thick -0.67 feet [6.67 X 6.67 X 5)/2 -(6 X 6 X 5)/2]X 3500 74,278 cubic feet!27 =2,751 cubic yards Use I 2,800 cubic yards No Toe Apron Total Rock Armor on slope Cell 2 Slope commmon to Cell 3 2,800 cubic yards l \; .....:.~~l.......~.....-.y-.•...... + CELL 1+:1 ++ Cell 2 Volume Calculations Scale I"=300 feet + -- Section A -A (not to scale) Showing Cover Rock Annor (6"Top) Typical Section through Exterior Dike RandomFil1 Clay Random Fill Tailings Dike 3:1 A BottomofCell I-I After crystal and Liner Removal A' Area Modified for Cell 1-1 Disposal Area Toe Apron Top of Cell North (Slope #1 ) North (Slope #2 ) West (Slope #3) East (Slope #4 ) South (Slope #5 ) Totals Volume Summary •Cell 2 Lower Upper Rock Bridqinq Laver Random Clav Random Armor -110,700 110,700 221,300 55,400 13,900 19,500 6,400 100 1,300 500 100 100 400 100 1,800 700 1,200 2,300 6,500 2,800 -126,100 113,000 250,500 66,200 Cell 2 Reclamation Cat637Resource Requirements Volume Route Yds/hr %Equip.Hr. Cell 2 Bridging Lift Tailings Surface -5 296 100%0.0 Cell 2 Lower Random Fill Tailings Surface 110,700 5 296 67%250.6 Tailings Surface 110,700 4 368 33%99.3 Slope 1 13,900 5 296 100%47.0 Slope 2 100 4 368 100%0.3 Slope 3 100 5 296 100%0.3 Slope 4 100 4 368 100%0.3 Slope 5 1,200 5 296 100%4.1 Total 401.7 Cell 2 Lower Random Fill Tailings Surface 221,300 5 296 67%500.9 Tailings Surface 221,300 4 368 33%198.4 Slope 1 19,500 5 296 100%65.9 Slope 2 1,300 4 368 100%3.5 Slope 3 100 5 296 100%0.3 Slope 4 1,800 4 368 100%4.9 Slope 5 6,500 5 296 100%22.0 Total 796.0 Cell 2 Rock Armor --use Highway Trucks Clay Volume == == Trucking Clay Production Cell 2 (use same assumptions as Cell 3 ) 113,000 Bank Cubic Yards (BCY) 0.8 Swell Factor 141,250 Loose Cubic Yards (LCY) 475 LCY/hr 8 trucks plus one (1)Loader 150,000 LCY I 475 LCY/hr = use 297 hours 300 hours 980 Loader D8N wi ripper Cat 651 WW Cat 825 Compo 14G Patrol 5000 gal WW 300 X 8 Trucks ==2400 hours Hours 300 300 300 325 325 175 Rock Armor Production Cell 2 66,200 cubic yards (cy) 38 cy per hour times 8 trucks 304 cy per hour delivered Assume 25%extra time for spreading,loading and screen wait 304 11.25 243.2 cy per hour 272 Hours I INTERNA TJONAL URANIUIo4 (USA)CORP. COST ESTIIdA TE ~.~~F"1.-ch)<.J~r.ov /~ )/~'-/1:-0 ~k ;F/'f.:M1 ~/t:, ~5c:~".,Cl~L(;N 1"1-t,.--.~t:"~ J •2000'~U IIIl1'lltl 2 /6dO'/IX............"'....3 I 1,6Z.........4200::l::t::t11I11I11I 4-s~oo ,().5%oClO11I00-N .s S70(),}·4% ...N"iI'~5200 1 0.8%..,q>'"-po-I ••.2f-".sao .IMC'lNNC'lC'l @ 4d..?>?~77Z.~&'_e.:J ~2 ""It...e:>,£:olIN";"J.7(..J~ U'7 ~.281.1;,%,.(.....~o. /,~""M~-h:.~..w K 8 'T~==-;-2 h>''-vu4J ~ C)tck k 1&r>->;"'....,Ir;,+"....,,MI~~r L~.c::.~f;"tP .ff:::L5; C:,oo m ,/I'?,,.,f .t,,5 S"fO /fA I.tf h1N ;fYI,'.v l:z.iOO m /.'f "'-"N /'2.,.." ;,,",oom /.,IM,4 1.5""".1 Ii/om /.75MIIII /,(,7 <?>_ ).5(,;:,(J)«?J•.5 ,."".,;/."H ~ C/.tJSJ">7I',y 7,-1-3- /~,+B,.,~;'" FiJt'IJ:t)~*:;-lc~J-~. .j'ti?/'7,y .8Jar.""I 3~0;..1 7b •5 M~/"7.~='iis'~,;...,"l 'P/'/"'Y -uP'7 j,0 .tJ."Y..s-~C:........::. .'\ /"-.. 4.,:4 -h--"'U'=J8 ""/-..."'1:-..</:rl'f.~ So ........-wwl•.4....::::Z.7 c~~ ._~..'...-:.-~..'...~...'. 22 c.Y/<7...t...-(7.7'7k;4r Kg!. .="~y/hr. 2 t=..-.:....::'{'..Ips'La-er -+h.-u.l'+-2>.z.e.e._"...c-_·-V~R..,.buy/kIs"?,,) :kj ~i:;Z"'"(r.~)$r",,;,~~~",r..,'£'£"F'-' '"~J:.~It:;)#U"M7.__"_~~~. ~:;:,t;;t~,::-:.Jt~:.~~:_...7.:~:,,~~.:~:~~~,,~-~';...~~~t ),L~-:~_ .~V:'t.~:..:~r "~;::."~O<l.~#~ke 70 ST'1o'"()8 t.~l9fJ('.lk'¢'L.K:...~'.....~~~.2·')'1,·~:.iCO ~'9-r .;23l!.·:r I::Z.ff1.A-;J.,7'..:.'~rl>..z" .!IIM .u~¥t ''C..?'1-C1~2"'U1 SN "._..~~(......',""'"_.....J~....ooze .,.. ..",. 22 . Z7 .......:......~--_....-'-_.'-'-- •....,.;!:;. INTERNATIONAL URANIUM (USA)CORP. COST 'ESTIMA TE ~...E.C.T ~~~_~~bv·······..···.····..·~eet ~. ~y ~~ON ~'T'~ ~O,..,J 16~w~- d.Cl..,At'~Cl""C"OfV e .u.4,~w.~"'!.4£.12,~~·~e.ce'@"$e:..-noN ICe, e b "A'~~~~()~"'Bm.ut,M I"'BAS/~e..l=Qs~'"l.€ ~GAl''\JANC>~~.._ H ~~~MI"'"v~e;,.t"fl 0 e:'<::'(..A'r'~<GP0i!:J0 F+/~ Oil WITH ~!JoW«-I!II!Im DlIl I!II!Im :I1'llll-azIA-Il30mIJ'IIl)»>~--.~IJ'lili":tIE1=lEi!i 13l/l)-fl.,. Ri!i 1'W>--Ilfl'I'--A -lCIiIolI£. i!-~ 60 ~()M ~JJ,~I 'tie aT ~~A-J$Lg ~ ~b-T"~zsc;)~T'IHouL 1.J.,)1~.AN ~H-I!:a~" f 5OO~/~J t!W~w.u-~~M«~T ~u,.T"is,UTlLI~~~ OF ~,.~Cvc:T'lCU ~2,-e1'PPI~~b a&'Ca,~~~I rb:~Q.~. Cell 3 RECLAMATION OF CELL 3 RECLAMATION OF CELL 3 Dewatering of Cell 3 Resource Description Dewatering of Cell 3 Total Dewatering of Cell 3 Place Remainder of Bridging (Platform)Lift Resource Description Ihrs Units Units Cost/Unit $0.481 Cost/Unit Task Units 62,4001 Task Units Task Cost $30,0001 $30,000 Task Cost Equipment Operators hrs $18.43 1,402 $25,841 Cat 637 Scraper hrs $201.83 623 $125,742 Cat 825 Compactor hrs $94.88 156 $14,777 Cat D8N Dozer With Ripper hrs $94.08 156 $14,654 Cat D7 Dozer hrs $79.39 156 $12,366 Cat 651 Waterwagon hrs $108.06 156 $16,831 Cat 14G Motorgrader hrs $65.19 156 $10,153 Equipment Maintenance (Butler)hrs $21.15 1,402 $29,648 Total Place Remainder of Bridging (Platform)Lift Place Lower Random Fill (12") Resource Description Units Cost/Unit Task Units $250,011 Task Cost Equipment Operators hrs $18.43 1,422 $26,214 Cat 637 Scraper hrs $201.83 452 $91,228 Cat 825 Compactor hrs $94.88 194 $18,406 Cat D8N Dozer With Ripper hrs $94.08 194 $18,252 Cat D7 Dozer hrs $79.39 194 $15,403 Cat 651 Waterwagon hrs $108.06 194 $20,965 Cat 14G Motorgrader hrs $65.19 194 $12,647 Equipment Maintenance (Butler)hrs $21.15 1,422 $30,076 Total Place Lower Random Fill (12") Clay Layer Resource Description Units Cost/Unit Task Units $233,191 Task Cost Equipment Operators hrs $18.43 1,835 $33,827 Cat 637 Scraper hrs $201.83 0 $0 Cat 825 Compactor hrs $94.88 350 $33,207 Cat D8N Dozer With Ripper hrs $94.08 320 $30,107 Cat D7 Dozer hrs $79.39 0 $0 Cat 651 Waterwagon hrs $108.06 320 $34,581 Cat 14G Motorgrader hrs $65.19 350 $22,816 Cat 980 Loader hrs $98.73 320 $31,594 5000 Gallon Water Truck hrs $61.90 175 $10,833 Highway Trucks hrs $63.77 2,560 $163,251 Truck Drivers hrs $16.23 2,560 $41,549 Equipment Maintenance (Butler)hrs $21.15 1,835 $38,812 Total Place Clay Layer 3/3/2009 -8:32 AM -WMM Rec Plan Est February 2009.xls $440,577 Denison Mines (USA)Corp. White Mesa Mill RECLAMATION OF CELL 3 Upper Random Fill Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 2,364 $43,570 Cat 637 Scraper hrs $201.83 868 $175,191 Cat 825 Compactor hrs $94.88 249 $23,648 Cat D8N Dozer With Ripper hrs $94.08 249 $23,451 Cat 07 Dozer hrs $79.39 249 $19,789 Cat 651 Waterwagon hrs $108.06 249 $26,935 Cat 14G Motorgrader hrs $65.19 249 $16,248 5000 Gallon Water Truck hrs $61.90 249 $15,430 Equipment Maintenance (Butler)hrs $21.15 2,364 $49,990 Total Place Upper Random Fill Rock Armor Resource Description Units Cost/Unit Task Units $394,251 Task Cost Equipment Operators hrs $18.43 819 $15,098 Cat 07 Dozer hrs $79.39 273 $21,675 Cat 651 Waterwagon hrs $108.06 273 $29,502 Cat 14G Motorgrader hrs $65.19 273 $17,796 Rock Cost Delivered CY $4.98 66,380 $330,823 Equipment Maintenance (Butler)hrs $21.15 819 $17,322 Total Place Rock Armor Quality Control Resource Description Quality Control Contractor Total Quality Control TOTAL RECLAMATION OF CELL 3 3/3/2009 -8:32 AM -WMM Rec Plan Est February 2009.xls Units $432,217 $74,400 $1,854,6471 Denison Mines (USA)Corp. White Mesa Mill Volume Calculation -Cell 3 IUpdated 02/26/09 1)Area of Cell 3 -3,234,252 sq It 74.25 acres /W8e 2)Area of Cell 3 still open as of February 21,2008 (see Figure A) 900 It X 1725 It =1,552,500 3)Assumptions Use 1,552,500 sq It 35.6 acres -Bridging layer is placed using random fill from piles east and west of Cell 3 -Cell will be graded to Design elevation utilizing finer materials in random fill stockpiles and from "clay"stockpiles. -Clay will be mined,blended,and hauled from borrow site location in Section 16 - four miles south of the mill area,using belly dump trucks,clay layer on top of Cell only. -The upper 1foot of random fill will be placed utilizing the fine random fill and clay stockpiles -Rock for side armor,top armor and toe aprons will come from an off-site gravel source one (1)mile north of Blanding.Rock will be produced through screening,stockpiled and trucked to the site at the time of use.Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 4)Bridging Layer (Platform Fill)Remaining to be placed 1,552,500 sq It X 3 ft./27 cubic feet per cubic yard =172,500 cubic yards Use I 172,500 cubic yards 5)Bring Platform Fill up to Design elevation (Lower Random) Assume full area of Cell X one (1)foot thick 3,234,252 sq It X 1 ft./27 cubic feet per cubic yard =119,787 cubic yards Use I 120,000 cubic yards 6)Placement of Clay Layer (One (1)foot thick on top of Cell only) Assume full area of Cell X one (1)foot thick 3,234,252 sq It X 1 ft./27 cubic feet per cubic yard =119,787 cubic yards Use I 120,000 cubic yards Volume Calculation -Cell 3 (can't)page 2 7)Upper Random Fill Volume -Top of Cell area Assume full area of Cell X one (2)foot thick 3,234,252 sq ft X 2 ft./27 cubic feet per cubic yard = 8)Armor Protection -Top of Cell Assume full area of Cell X one-half (0.5)foot thick 239,574 cubic yards Use I 240,000 cubic yards 3,234,252 sq ft X 0.5 ft./27 cubic feet per cubic yard =59,894 cubic yards Use I 60,000 cubic yards 9)Cell 3 North Slope (Slope #6)common with Cell 2 Average height Length 2 feet 1100 feet No clay on slopes.Toe apron only at base of long slope or where drainage is directed. a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [2 X 2 X 5)/2]X 1100 11,000 cubic feet!27 = Remaining Random Fill [5 X 5 X 5)/2 -(2 X 2 X 5)/2]X 1100 57,750 cubic feet!27 = Total Random Fill North Slope 407 cubic yards Use 1 41_0_c_ub_i_co:.ya_r_ds_ 2,139 cubic yards Use 1__2;;;,:,,;;;,20;,,,;0;.....,;c..;.ub;,,,;i..;.c,,-ya;,;;.r..;.ds;;..... 2,610 cubic yards b)Rock Armor 8"thick -0.67 feet [5.67 X 5.67 X 5)/2 -(5 X 5 X 5)/2]X 1100 19,659 cubic feet!27 =728 cubic yards Use 1 73_0_c_ub_i_co:.ya_r_ds_ c)Toe Apron No rock required Total Rock Armor Cell 3 north Slope 730 cubic yards I Volume Calculation -Cell 3 (con't)page 3 10)Cell 3 South Dike,west end (Slope #7 ) Average height Length 16 feet 1750 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [16 X 16 X 5)/2 -(16 X 16 X 3)/2]X 1750 448,000 cubic feet!27 = Remaining Random Fill [19 X 19 X 5)/2 -(16 X 16 X 5)/2]X 1750 459,375 cubic feet!27 = Total Random Fill North Slope 16,593 cubic yards Use I 16,600 cubic yards 17,014 cubic yards Use I 17,100 cubic yards 33,700 cubic yards b)Rock Armor 8"thick -0.67 feet [19.67 X 19.67 X 5)/2 -(19 X 19 X 5)/2]X 1750 113,351 cubic feet!27 =4,198 cubic yards Use 1..._..;.4,:;;;2.;;.00~c;;.;u;;.;b.;.;ic...y.,;;a;;..rd;;.;s~ c)Rock Apron at toe of slope Total Rock Armor Slope #7 [2ft X 7ft wide X 1750 long]/27 =907 Use 1...__1,.,;;0.;;.00~c;;.;u..;.b..;.ic...y.,;;a;;..rd..;.s~ 5,200 cubic yards 11)Cell 3 South Dike (Slope #8 )VOLUME DELETED.AREA FILLED WITH CELL 4A TAILINGS Average height 0 feet Length 0 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge cubic yards Use I cubic yards Volume Calculation -Cell 3 (can't)page 4 Remaining Random Fill cubic yards Use II-c_u_b_ic....y:...a_rd_s_ Total Random Fill North Slope cubic yards I b)Rock Armor 8"thick -0.67 feet cubic yards Use I cubic yards c)Rock Apron at toe of slope Use I --.,;;c.;;.ub;;.;ic~ya;;.;r.;;.ds;;......l Total Rock Armor Cell 3 South Dike 12)Cell 3 East Slope (Slope #9 ) cubic yards I Average height Length a)Random Fill No existing Dike Total Random Slope #4 4 feet 800 feet [(4 X4 X 5)/2]X 800 /27 =1185 cubic yards Use 1__1.;.:.,;;.20;.;0;.....;.c.;;.ub;;.;ic~ya;;.;r.;;.ds;;..- 1,200 cubic yards I b)Rock Armor 8"thick -0.67 feet 14.52 cubic feet per linear foot of dike 14.52 cubic foot per linear foot X 800 /27 c)Toe Apron Not required Total Rock Armor Cell 3 East Slope 430 cubic feet!27 =430 cubic yards Use 1'--__45._0_C_u_bi_C""ya_r_ds..;..... 450 cubic yards I Volume Summary -Cell 3 Top of Cell West (Slope #6 ) South (Slope #7 ) South (Slope #8 ) East (Slope #9 ) Totals Lower Upper Rock Bridging Layer Random Clay Random Armor 172,500 120,000 120,000 240,000 60,000 410 2,200 730 16,600 17,100 5,200 --- 1,200 450 172,500 137,010 120,000 260,500 66,380 Cell 3 Reclamation Cat 637Resource Requirements Volume Route Yds/hr %Equip.Hr. Cell 3 Bridging Lift Tailings Surface 172,500 6 277 100%622.7 Cell 3 Lower Random Fill Tailings Surface 120,000 5 296 100%405.4 Slope 6 410 5 296 100%1.4 Slope 7 16,600 4 368 100%45.1 Slope 8 -5 296 100%0.0 Slope 9 -4 296 100%0.0 Total 451.9 Cell 3 Lower Random Fill Tailings Surface 240,000 4 296 100%810.8 Slope 6 2,200 4 296 100%7.4 Slope 7 17,100 5 368 100%46.5 Slope 8 -4 296 100%0.0 Slope 9 1,200 5 368 100%3.3 Total 868.0 Cell 3 Rock Armor --use Highway Trucks Clay Volume = Clay Production Cell 3 (use same assumptions as Cell 2 ) 120,000 Bank Cubic Yards (BCY) 0.8 Swell Factor 150,000 Loose Cubic Yards (LCY) Trucking 475 LCY/hr 150,000 LCY I 475 LCY/hr = use 8 trucks plus one (1)Loader 316 hours 320 hours 980 Loader D8N wi ripper Cat 651 WW Cat 825 Compo 14G Patrol 5000 gal WW 320 X 8 Trucks =2560 hours Hours 320 320 320 350 350 175 Rock Armor Production Cell 3 66,380 cubic yards (cy) 38 cy per hour times 8 trucks 304 cy per hour delivered Assume 25%extra time for spreading,loading and screen wait 304 11.25 243.2 cy per hour 273 Hours Cell4A RECLAMATION OF CELL 4A -Total Units Dewatering of Cell 4A Resource Description Dewatering of Cell 4A Total Dewatering of Cell 4A Cost/Unit Task Units Task Cost l-hr-s---I $0.481 62,4001 $30,0001 $30,000 Place Bridging (Platform)Lift Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $201.83 689 $139,101 Cat 637 Scraper Operators hrs $17.24 689 $11,885 Cat 825 Compactor hrs $94.88 172 $16,347 Cat 825 Compactor Operator hrs $12.74 172 $2,195 Cat D8N Dozer With Ripper hrs $94.08 172 $16,211 Cat D8N Dozer Operator hrs $12.74 172 $2,195 Cat 07 Dozer hrs $79.39 172 $13,679 Cat 07 Dozer Operator hrs $12.74 172 $2,195 Cat 651 Waterwagon hrs $108.06 172 $18,619 Cat 651 Waterwagon Operator hrs $16.23 172 $2,796 Cat 14G Motorgrader hrs $65.19 172 $11,232 Cat 14G Motorgrader Operator hrs $18.41 172 $3,172 Equipment Maintenance (Butler)hrs $21.15 2,929 $61,952 Total Place Bridging (Platform)Lift Place Lower Random Fill Resource Description Units $301,579 Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,122 $20,682 Cat 637 Scraper hrs $201.83 499 $100,641 Cat 825 Compactor hrs $94.88 125 $11,827 Cat D8N Dozer With Ripper hrs $94.08 125 $11,728 Cat 07 Dozer hrs $79.39 125 $9,897 Cat 651 Waterwagon hrs $108.06 125 $13,471 Cat 14G Motorgrader hrs $65.19 125 $8,126 Equipment Maintenance (Butler)hrs $21.15 1,122 $23,730 Total Place Lower Random Fill $200,103 Clay Layer Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,020 $18,803 Cat 637 Scraper hrs $201.83 0 $0 Cat 825 Compactor hrs $94.88 180 $17,078 Cat D8N Dozer With Ripper hrs $94.08 180 $16,935 Cat D7 Dozer hrs $79.39 0 $0 Cat 651 Waterwagon hrs $108.06 180 $19,452 Cat 14G Motorgrader hrs $65.19 180 $11,734 Cat 980 Loader hrs $98.73 150 $14,810 5000 Gallon Water Truck hrs $61.90 150 $9,286 Highway Trucks hrs $38.77 1,600 $62,032 Truck Drivers hrs $16.23 1,600 $25,968 Equipment Maintenance (Butler)hrs $21.15 2,620 $55,415 Total Place Clay Layer Upper Random Fill Resource Description Units $251,512 Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 1,360 $25,062 Cat 637 Scraper hrs $201.83 544 $109,758 Cat 825 Compactor hrs $94.88 136 $12,899 Cat D8N Dozer With Ripper hrs $94.08 136 $12,791 Cat D7 Dozer hrs $79.39 136 $10,794 Cat 651 Waterwagon hrs $108.06 136 $14,692 Cat 14G Motorgrader hrs $65.19 136 $8,863 5000 Gallon Water Truck hrs $61.90 136 $8,416 Equipment Maintenance (Butler)hrs $21.15 1,360 $28,755 Total Place Upper Random Fill $232,029 Rock Armor Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 597 $11,005 Cat D7 Dozer hrs $79.39 199 $15,799 Cat 651 Waterwagon hrs $108.06 199 $21,505 Cat 14G Motorgrader hrs $65.19 199 $12,973 Rock Cost Delivered CY $4.98 48,450 $241,464 Equipment Maintenance (Butler)hrs $21.15 597 $12,627 Total Place Rock Armor $315,374 Quality Control Resource Description Units Cost/Unit Task Units Task Cost~Q~u-a':":"'lit-y""=C-o-nt-ro"":"'l""=C-o-nt-ra-c-to-r--------r:-Ih-rs----...I-7'"$6-=-=2=-.0=-=-01 1,0451 $64,7901 Total Quality Control TOTAL RECLAMATION OF CELL 4A $64,790 1 $1,395,3861 Volume Calculation -Cell 4 IUpdated 02/27/09 1)Area of Cell4A - 2)Assumptions 1,829,520 sq ft =42.00 acres //I&e -Bridging layer is placed using random fill from piles east of Cell 4A -Cell will be graded to Design elevation utilizing finer materials in random fill stockpiles and from "clay"stockpiles. -Clay will be mined,blended,and hauled from borrow site location in Section 16 - four miles south of the mill area,using belly dump trucks,clay layer on top of Cell only. -The upper 1 foot of random fill will be placed utilizing the fine random fill and clay stockpiles -Rock for side armor,top armor and toe aprons will come from an off-site gravel source one (1)mile north of Blanding.Rock will be produced through screening,stockpiled and trucked to the site at the time of use.Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 3)Bridging Layer (Platform Fill)Remaining to be placed 1,829,520 sq ft X 3 ft./27 cubic feet per cubic yard =203,280 cubic yards Use I 204,000 cubic yards 4)Bring Platform Fill up to Design elevation (Lower Random) Assume full area of Cell X one (1)foot thick 1,829,520 sq ft X 1 ft./27 cubic feet per cubic yard =67,760 cubic yards Use I 68,000 cubic yards 5)Placement of Clay Layer (One (1)foot thick on top of Cell only) Assume full area of Cell X one (1)foot thick 1,829,520 sq ft X 1 ft./27 cubic feet per cubic yard =67,760 cubic yards Use I 68,000 cubic yards Volume Calculation -Cell 4A (can't)page 2 6)Upper Random Fill Volume -Top of Cell area Assume full area of Cell X one (2)foot thick 1,829,520 sq ft X 2 ft./27 cubic feet per cubic yard = 7)Armor Protection -Top of Cell Assume full area of Cell X one-half (0.5)foot thick 135,520 cubic yards Use 1 136,000 cubic yards 1,829,520 sq ft X 0.5 ft./27 cubic feet per cubic yard =33,880 cubic yards Use 1 34,000 cubic yards 8)Cell 4A South Dike,(Slope #1 ) Average height Length 36 feet 1600 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [36 X 36 X 5)/2 -(36 X 36 X 3)/2]X 1600 =2,073,600 cubic feet/27 = Remaining Random Fill [39 X 39 X 5)/2 -(36 X 36 X 5)/2]X 1600 900,000 cubic feet/27 = Total Random Fill South Slope 76,800 cubic yards Use I 77,000 cubic yards 33,333 cubic yards Use I 34,000 cubic yards 111,000 cubic yards b)Rock Armor 8"thick -0.67 feet [39.67 X 39.67 X 5)/2 -(39 X 39 X 5)/2]X 1600 =210,836 cubic feet/27 =7,809 cubic yards Use 11.._.;.7.:.;;,8;.;;0.;;,0...;.;cu;;.;;b;.;.ic;..y~a;;.;.r.;;,ds;;.... c)Rock Apron at toe of slope Total Rock Armor South Slope [2ft X 7ft wide X 1600 long]/27 =830 Use 11.._.....;;8;.;;5.;;,0_C;;;,;u;;.;;b;.;.ic;..y~a;;;.r.;;,ds;;.... 8,650 cubic yards I Volume Calculation -Cell 4A (can't)page 3 9)Cell4A West Dike (Slope #2) Average height Length 26 feet 1200 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [26 X 26 X 5)/2 -(26 X 26 X 3)/2]X 1200 =811,200 cubic feet!27 = Remaining Random Fill [29 X 29 X 5)/2 -(26 X 26 X 5)/2]X 1200 495,000 cubic feet!27 = Total Random Fill North Slope 30,044 cubic yards Use I 30,000 cubic yards 18,333 cubic yards Use I 19,000 cubic yards 49,000 cubic yards b)Rock Armor 8"thick -0.67 feet [29.67 X 29.67 X 5)/2 -(29 X 29 X 5)/2]X 1200 117,927 cubic feet/27 =4,368 cubic yards Use 1L.._..;.4.:.;;;,5;,;;0,;;;,0....;;,;CU:;.;b;.;,;ic;;.,.L,;ya;;;,r.;;;,ds:... c)Rock Apron at toe of slope [2ft X 7ft wide X 1200 long]/27 =622 Use 1L..-_...;6...;5.;;.0.....;;.CU;;;,;b;.;.ic;;..:.;ya;;.;.r.;;.ds;;.... Total Rock Armor Cell 4A South Dike 10)Cell 4A East Slope (Slope #3 ) 5.150 cubic yards I Average height Length 8 feet 1200 feet a)Random fill to reduce slope from 3:1 to 5:1 First Wedge [8 X 8 X 5)/2 -(8 X 8 X 3)/2]X 1200 =76,800 cubic feet/27 =1185 cubic yards Use 1L.._..;.1.:.;;;.2;.;;0,;;;,0....;;,;cu:;.;b;.;,;ic;;.,.L,;ya;;;,r.;;;,ds:... Volume Calculation -Cell 4A (con't)page 4 Remaining Random Fill [11 X 11 X 5)/2 -(8 X 8 X 5)/2]X 1200 =171,000 cubic feet!27 = Total Random Slope #3 6,333 cubic yards Use 1L-...::;6.:.;;,5;.;:0,;:,0...:;.;cu::.;b;;.:;ic::...L,;ya::.:r,;;;,ds:;;.... 7,700 cubic yards b)Rock Armor 8"thick -0.67 feet 14.52 cubic feet per linear foot of dike 14.52 cubic foot per linear foot X 1200 /27 c)Toe Apron Not required Total Rock Armor Cell4A East Slope 645 cubic feet!27 =645 cubic yards Use 1L-_..:6;.;:5,;:,0...:;.;cu::.;b;;.:;ic::...L,;ya::.:r,;;;,ds:;;.... 650 cubic yards ~ Volume Summary •Cell 4A Top of Cell South (Slope #1 ) West (Slope #2 ) East (Slope #3 ) Totals Lower Upper Rock Bridqinq Layer Random Clay Random Armor 204,000 68,000 68,000 136,000 34,000 77,000 34,000 8,650 30,000 19,000 5,150 1,200 6,500 650 204,000 176,200 68,000 195,500 48,450 Cell 4A Reclamation Cat 637Resource Requirements Volume Calculation -Cell 4A (can't)page 5 Volume Route Yds/hr %Equip.Hr. Cell 4A Bridging Lift Tailings Surface 204,000 4 296 100%689.2 Cell 4A Lower Random Fill Tailings Surface 68,000 5 368 100%184.8 Slope 1 77,000 5 368 100%209.2 Slope 2 30,000 4 296 100%101.4 Slope 3 1,200 5 368 100%3.3 Total 498.6 Cell 4A Upper Random Fill Tailings Surface 136,000 5 368 100%369.6 Slope 1 34,000 5 368 100%92.4 Slope 2 19,000 4 296 100%64.2 Slope 3 6,500 5 368 100%17.7 Total 543.8 Cell 3 Rock Armor --use Highway Trucks Clay Volume = = Clay Production Cell 4A (use same assumptions as Cell 2 ) 68,000 Bank Cubic Yards (BCY) 0.8 Swell Factor 85,000 Loose Cubic Yards (LCY) Trucking 475 LCY/hr 150,000 LCY I 475 LCY/hr = use 8 trucks plus one (1)Loader 179 hours 320 hours 980 Loader D8N wi ripper Cat 651 WW Cat 825 Compo 14G Patrol 5000 gal WW 320 X 8 Trucks =2560 hours Hours 320 320 320 350 350 175 Rock Armor Production Cell 4A 48,450 cubic yards (cy) 38 cy per hour times 8 trucks 304 cy per hour delivered Assume 25%extra time for spreading,loading and screen wait 304 11.25 243.2 cy per hour 199 Hours Miscellaneous MISCELLANEOUS ITEMS MISCELLANEOUS ITEMS Equipment Mobilization Resource Description Units Cost/Unit Task Units Task Cost Butler Machinery Mobilization LS $272,6001 1 $272,600 Other Equipment Mobilization LS $1,1001 1 $1,100 Cranes LS $2,700 2 $5,400 Total Equipment Mobilization $279,100 Task CostTaskUnitsCost/UnitUnits Office Facilities Resource Description Install New Powerline LS $15,000 1 $15,000 Utilities for Offices months $1,000 36 $36,000 Temporary Office Trailer months $1,500 3 $4,500 Temporary Office Trailer,mob,demob &setup LS $3,000 1 $3,000 Total Office Facilities $58,500 Decontamination Pad Resource Description Units Cost/Unit Task Units Task Cost Laborers Construct Wheel Wash Facility hrs $12 LS $180,000 8,320 $101,275 $180,000 Total Wheel Wash Facility Facilities constructed in 2000 &2008 ($180,000) $101,275 MANAGEMENVSUPPORT Resource Description Units Cost/Unit Task Units Task Cost Manager/Engineer hrs $54.88 6,240 $342,482 Radiation Safety Officer hrs $42.88 6,240 $267,593 Secretary hrs $17.34 6,240 $108,224 Clerk hrs $14.27 4,866 $69,438 Environmental Technician (Part time,4.5 years)hrs $24.15 4,866 $117,511 Maintenance Foreman hrs $31.47 6,240 $196,356 Chemist hrs $25.25 2,080 $52,514 Security hrs $9.29 18,720 $173,981 Safety Engineer hrs $24.15 4,160 $100,461 Misc.Materials &Supplies hrs $36.45 6,240 $227,448 Health Physics Costs hrs $64.81 2,080 $134,800 Environmental Monitoring Costs,Laboratory years $71,620.00 4.5 $322,290 Total Management/Support $2,113,100 TOTAL MISCELLANEOUS ITEMS ,$2,551 ,975~ 3/3/2009 -8:54 AM -WMM Ree Plan Est February2009.xls Denison Mines (USA)Corp. White Mesa Mill Rock Production ROCK PRODUCTION COST Assumptions: Rock is obtained from gravel source north of Blanding,Utah.BLM Public pit Rock is processed by screening only,no crushing is required,1.25 CY of feed for 1 CY of product Rock is produced and stockpiled at the site Site is 7 road miles from the mill;6 miles of which is paved public highway Rock will be hauled in 22 CY bellydump trucks,contract haulers ($80.00/hr) Rock will be dumped in windrows on Tailings Cells by trucks,spread by grader,and spread by 07 Dozer Trucks can average 30 MPH (1.75 rounds/hr) Material fed to plant PRODUCTION OF RIPRAP Product Material Feed Required (CY)Reject Factor to Plant (CY) 146,000 25.0%182,500 Plant Throughput (CY/hr) 122 Plant Operating Hours 1,500 Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.43 2,340 $43,137 Laborer hrs $12.17 1,500 $18,259 Cat D8N Dozer With Ripper hrs $94.08 365 $34,341 Cat 980 Loader hrs $98.73 1,975 $194,994 Screening Plant w/conveyors*hrs $55.61 1,500 $83,409 Contract Highway Trucks -Bellydumps**hrs $80.00 3,800 $304,000 Equipment Maintenance (Butler)hrs $21.15 2,340 $49,493 Total Production of RipRap RIPRAP COST PER CUBIC YARD DELIVERED *Cost Quoted from Power Motive Corporation,Denver,Colorado updated February 24,2009 $7,000 plus $2,200 for conveyors,176 hours per month for one month, Mob and Demob -$5,000.00 $727,632 $4.98~ **Cost quoted from Dennis Cosby,Cosby Trucking,Inc.,Blanding,Utah,Updated February 16,2009 (includes ownership expense,fuel,maintanence and operator) 3/3/2009 -10:17 AM -WMM Rec Plan Est February 2009.xls International Uranium (USA)Corp. White Mesa Mill Amy Bushman From: Sent: To: Cc: Subject: Attachments: Dear Amy, Brad Neptune [bneptune@powermotivecorp.com] Tuesday,February 24,2009 9:33 AM Amy Bushman Mike Norris 2512KT Screen FNG_2512kL2512k.pdf;FT_271 K_291 K.pdf Thank you for the opportunity to quote a rental screen to Denison Mines. Last year,per the February 22,2008 quote,we quoted our 271 K plant and our 2512KT plant.I'm attaching spec sheets on each so you can see what each screen and plant looks like. The 271 K plant does NOT have anyon-plant stackers,but does have a 4'x 10'two deck screen.You would need to rent off plant hydraulic stackers to stack out two products.It is also a rubber tired plant. The 2512KT is a Track Mounted plant that DOES have on-plant stackers and can stack out three products right off of the plant.You do not need additional conveyors. Rental rates are the same as quoted last year. 271K Screen 2512KT Screen 36"x60'Hyd Stacker 30"x 80'Hyd Stacker $7,0001 mo $12,8001 mo $1,5001 mo $2,2001 mo The 271 K Screen is presently tied up on a rental.The 2512KT plant is sitting idle in Colorado Springs.I'd estimate delivery from C Spgs to Blanding to be approximately $2,500.The present purchase price we have on the 2512KT is $135,000,thus you may want to consider purchasing the plant as opposed to renting it for $12,800 per month. Screen cloth and installation of screen cloth will run about $2,000 total. Please feel free to email or call with any additional questions. Sincerely, Brad Neptune 970-985-5875 SCREENSMOBILE III AST•The Fold 'n Go 2512KT is amobile track screening plant that features a Kolberg@ double deck screen for processing sand & gravel,topsoil,slag,crushed stone and recycled materials.This plant offers astandard inlet hopper chute for inline processing feed from crushing plant or feed conveyor,As with all Fold 'n Go@ mobile screening plants,this plant provides easy to reach engine controls and grease points for routine service. For material producers that prefer wheels and need more site to site mobility,the Fold 'n Go 2512K is available.Both plants provide simple- to-use hydraulic leveling gears,hydraulic plant controls and screen angle adjustment. Fold 'n Go 2512KT/2512K SCREEN: Koiberglil2512K double deck screen:5'x12'screen top and bottom deck driven by 1200RPM vibrating mechanism mounted on screen;Variable eccenlTic shaft with five (5) force amplitude settings on adjustable slip countel\'leights; Rubber Isolatorblocks;Hydraulic conlrols for variable angle operation.Top and bottom discharge chutes,aggregate spreader,and fixed access ladder with wrap-around walkway foreasy screen access.Standard material separations range from 3'to 10M depanding on application. POWER SYSTEM: 125 HP(100 HP for 25121<)Tier II John Deere waler- cooled diesel engine to power all plantfunctions and three on-beard stacking conveyors;12 voltbatlery. Engine mounted pumps tooperate all ptantftlnctions. NEMA4 rated instrument panel,tachometer,hour meter.voltmeter.oil pressure gauge,oil temperature gauge and emergency stop.Auxiliary power for lJp to 30 HP off-plant conveyors. PLANT CAPACITY: Screening plantcan process tip to350 TPH or more of feed materia!.Actual tonnageswill vary depending on application requirements:feed material size,material seperations.type of screens used,weight of product and other material considerations. CONVEYOR SYSTEM: 2512KT:Delivery Conveyor-28'x42'conveyorwith hydraulic drive (350 FPM);Full-length skirt boards. SideConveyors--Two (2)27'x24'swing out conveyOfS with hydraulic variable speed drive (0-350 FPM); Fines Conveyor-20'x48"conveyor with hydraUlic drive (350 FPM);All conveyors have 220 PIW,118 x1/16 cover belting,belt cleaners and fold for transport. 2512K:Delivery Conveyor-38'x36"conveyor with hydraulic drive (350 FPM).Side Conveyors--Two (2)27'x24'swing out conveyors v~th hydraulic variable speed drive (0-350 FPM);Fine..Conveyor.-23'x 42' conveyorwith hydraulic drive (350 FPM);All conveyors have 220 PIW,1/8x1/16 cover belting.beltcleaners and fold for transport. FEEDER SYSTEM: 12cubic yard heaped capacity hopper wilh 6'x 13'top opening;Heavy-dtlty 25'sloped grizzly with 6'nominal opening;Hydraulic dump with patented scissor aclion for easy cleaning;Adjtlstable gate;14'x42"belt feederwith hydraulic variable speed drive (O-BO FPM); Belting is 330 PIW,3/16 x 1/16 cover. CHASSIS: 2512KT:24'I-beam;HydraUliC landing gear forleveling of plant;Inter-Trac FL6 tracks with wireless remote control for easy jobsite movement. 2512K:21"I-beam with king pin type hitch;Hydraulic landing gear for leveling of plan;Tandem axleassembrf with eight (8)11 R22.5 tires and mud flaps;Leaf spring type suspension.airbrakes,rear taillights and side marker lights. SERVICE CAPACITY: FueL "140 gal Hydratllic Tank 100 gal (150 gal for25121<) TRANSPORTATION:2512KT 2512K Weight..61 ,000 Ibs 54,600 Ibs Height.. .13'11'(on lowboy)13'0' Length .....49'8"62'2" Width....11'11'11'11" Axles....N/A Tandem OPTIONS: Bulkhead--Assists in ramping forloader feed to food hopper. Remote ControlGrlzzly-Assisls in dwnping oversize material off feed hopperfrom loader. Wings-Assists in funneling food matlJJia!onto feed hopper grizzly. Hammermill Shredder--Helps break feed material apart for improved processing.Hydratltic controls can retract shredder up and away from drop zone of feed conveyor to delivery conveyor for material bypass ofshredder. Screen Cloth ©2006Astoo MJbi~SCfeens-Aa riftltsrc:seNed, Specificationsare subjecttochange. I!I .... Record of Telephone Call Page-Lof...L. IJ Phone No: Call to:----lL"-0~e,v~,(/~t.s~'---lG"'-'<::..t.s~j!::7,L.';?'_ Company:_~G~s~i:';V!:--...£../:-4-4~k!:1..L..(.~Ic=-.!./",,:,:N~,(._r IT (~~:t)6 r&-2890 Date:0 L ~/G -oct Subject: Notes:200 7 fJa4._.If 130,00/)o~.<. «h~/~t-V~<"I j11cu:....le-v,4.<.?ce-\d.r(,.[~J Ir Comments: 2006 Equipment Costs EQUIPMENT COSTS WHITE MESA MILL RECLAMATION COST HOURLY EQUIPMENT COSTS 2008 DOLLARS Actual equipment rates quoted from North Central Rental &Leasing.LLC.12 month rental period February 18,2008 637E Scraper D8R Dozer D7R Dozer 825G Compactor 980 G Loader 988 G Loader 770 Haul Truck 365BL Excavator 651 WaterWagon 5000 gal Water Truck 14H/Ripper Motor Grader 16H/Ripper Motor Grader Units 4 1 1 1 1 1 4 1 1 1 1 1 I RATE I MTCE I FUEL I FUEL@ TOTAL Mob/Demob I Mob/Demob IOperatinQ Hrs I I MONTHLY I HOURLY I EXPENDABLES I USAGE I $2.107 COST per machine I Totals I per Month I 25,400 144.32 8.00 23.5 49.51 $201.83 $21.200 $84.800 704 12.650 71.88 4.30 8.5 17.91 $94.08 $14.100 $14.100 176 10.700 60.80 3.85 7.0 14.75 $79.39 $12,450 $12,450 176 11,200 63.64 3.85 13.0 27.39 $94.88 $13.000 $13.000 176 13,300 75.57 4.20 9.0 18.96 $98.73 $12.800 $12.800 176 17,500 99.43 5.45 11.0 23.18 $128.06 $15,450 $15,450 176 11,500 65.34 6.20 8.5 17.91 $89.45 $13,250 $53,000 704 16.500 93.75 6.40 13.0 27.39 $127.54 $24,000 $24,000 176 11.800 67.05 5.20 17.0 35.82 $108.06 $14,300 $14,300 176 6,650 37.78 3.05 10.0 21.07 $61.90 $6,450 $6,450 176 8,800 50.00 3.60 5.5 11.59 $65.19 $10.150 $10.150 176 12,650 71.88 4.35 8.5 17.91 $94.13 $12.100 $12.100 176 $272.6001 3,168 Equipment Rental Rate Quoted by WorldWide Rental Services (02/25/2009)for PC 300 Excavator with Demo-Pro 900 Shear Cat 330 wi Shear Small tools allocation -Demolition - $1.30/mechanic labor hour for oxygen/acetylene.expendables Butler Equipment Maintenance Cost Crane Rental Rates 65 ton Hydraulic Crane 30 ton Hydraulic Crane 22,500.00 127.84 17.99 12.5 26.341 $172.171 0 Maintenance Monthly Planned Cost per Maintenance Operating Availability Operating Flat Rate Hours/month Factor Hour $62.315.00 3.168 0.931 $21.151 I RATE I MTCE I FUEL I FUEL@ TOTAL I MONTHLY I HOURLY I EXPENDABLES I USAGE I $2.107 COST 11.100 63.07 2.15 15.0 31.61 $96.82 6,400 36.36 2.15 10.0 21.07 $59.58 Mob/Demob $2,000 $700 Rental Rates updated from Honnen Equipment,02/25/09 3/3/2009 -8:54AM -WMMRec Plan Est February 2009.xls International Uranium (USA)Corp. White MesaMill lNLTH ;~~TRAL RENTAL &LEASING LLC A Subsidiary of ButlerMachineryCo. 3401 33"1 Street Southwest Po Box 9559 Fargo,ND 58106-9559 Phone (701)232-0033 Fax (701)298-1717 February 2,2009 Denison Mines Attn:Harold Roberts E-Mailedto:hroberts@denisonmines.com Dear Harold: Thank you for the invitation to quote Denison Mines (Denison)the equipment needed for their mining project in Blanding,Utah.North Central Rental &Leasing,(NCRL) respectfully submits our proposal for a maintained fleet of Caterpillar machines. Listed on Attachment A,you will find the models,quantities,monthly rental rates,hours allowed per month,excess hour charge,guaranteed number of months rates are based upon,total freight charges and the maintenance rate per hour for materials only. All rates shown on Attachment A do not include any state,local,property or any other taxes that may be applicable. Rates are based upon electric hour meter readings that are attached to the dash of each machine.Rates are based on 176 hours of use each month.Excess hour charges,ifany, will be calculated and invoiced at the end of the project.There would be no credit issued for any hours under the allowed during the term of this proposal.IfDenison elects to double shift machines,then NCRL would invoice those hours at the end of each month.(To figure the double shift rates,take the excess hour rate shown on Attachment A times the number of hours). Rates are based upon a minimum guarantee of 12 months and a package deal.This quote is valid for 90 days. Maintenance and Repairs: Maintenance:The maintenance rates per hour listed on Attachment A includes the material part items only,such as air,oil,and fuel filters,lubricant oils,grease,anti-freeze, batteries,fan belts,lights and make-up oils.NCRL would invoice Denison actual hours used on machines at the end of each month.Our monthly maintenance charge would be $62,315 which includes our labor,specialized lube trucks,support vehicles and equipment, specialized tooling,scheduled oil sampling,parts trailers and inventories,mileage and travel expense. February 2,2009 Denison Mines Page 2 Maintenance (cont.):NCRL will provide two (2)full-time maintenance technicians on site fifty (50)hours per week on a schedule to be determined,Monday through Friday. Denison would have to schedule the machines available for a time frame yet to be determined adequate for NCRL maintenance personnel to perform the required maintenance.NCRL would invoice Denison for the monthly maintenance charge at the end ofeach month. Repairs:NCRL would be responsible for all repairs including parts and labor on our machines other than failures caused by damages or mis-use.Repairs include items as minor as starters, alternators,water pumps,hydraulic hoses,etc.to the major items such as engines,transmissions, differentials,brakes,hydraulic pumps and cylinders,etc.Iftime permits and Denison requests NCRL's technician to perform repairs or maintenance on their machines,our hourly charge would be $95.00 per hour for standard time,$122.00 per hour for overtime and $140.00 per hour for Sundays and holidays plus materials. Mobilization,Freight and Assembly Charges: Mobilization:The mobilization charge of $30,820 includes the moving expense of our support personnel,set up the job site,and transportation costs of our vehicles,parts and tooling inventory to the job site.NCRL would charge the same amount to demobilize at the end of the project. Freight and Assembly Charges:The freight and assembly charges listed on Attachment A are based upon all machines shipped by truck to the job site. Denison would be responsible for demobilization including disassembly and return freight on all machines.Parts,vehicles and equipment,at the end,or at time during the rental period to Rapid City,SD NCRL would be responsible for freight to the job site for all stock order parts shipments, emergency repair parts,maintenance parts,and G.E.T.and bulk oil shipments. Once the equipment has been delivered and assembled,an inspection would take place.During the inspection,a representative of NCRL and a representative ofDenison will verify on the Acceptance Report the condition of the equipment. Denison's Responsibilities Include: Operators:Provide the operators as needed to operate machines as stated in Caterpillar's operating guide.NCRL will provide,at no expense to Denison,qualified training instructors for the purposes of training operators.This training would take place on the jobsite at the initial start up of the job and would include classroom,walk around,and in iron demonstrations. February 2,2009 Denison Mines Page 3 Fuel:Supply and fill all fuel for equipment including NCRL's service vehicles. Damages:This includes glass breakage,bent handrails,stepladders,fenders,etc.NCRL's normal policy for repairing damages to rental machines is to repair them when the rental period is completed,however,if the damaged item is of a safety concern,we would repair the damages as soon as possible after they occurred.An itemized list of the parts and labor required would be provided to Denison prior to starting the repair,and invoiced at current list prices plus freight upon completion. Undercarriage and Tires:Denison would be responsible for all tire wear including tire damages on the machines with an asterisk listed on Attachment A.Equipment would have to be returned with same brand and model tires as when delivered,or prorated accordingly by percentage of tire wear and condition at termination of rental period. Upon delivery of machines,a representative of NCRLIBMC,a representative ofDenison and a representative from an independent tire dealer or manufacturer would jointly verify in writing the condition,percentage of wear,and tire value.Upon termination of rental,we would again have the representatives mentioned above determine the condition,percentage of wear,and tire values.Any differences noted,would then be charged or credited to Denison including both materials and labor. Undercarriage wear on all track type machines would be NCRL's expense. Ground Engaging Tools:Denison would be responsible for all parts relating to ground engaging tools (G.E.T.),i.e.cutting edges,ripper tips and protectors,bucket tips and adapters,edges between adapters,wear plates on bottom of buckets and all mounting hardware.NCRL would install these items on an as needed basis at the current Caterpillar list price plus freight at no additional labor costs.All machines would be delivered with new G.E.T.items and are to be returned with new. We wish to thank Denison and you for giving us the opportunity to present our proposal and for all the consideration we receive. Sincerely yours, North Central Rental &Leasing Butler Machinery Company Oscar fj).Swenson Rental Fleet Marketing Manager ODS:Imc Attachment cc:Joel Nikle,Rental Fleet Manager Joyce Wittkopp,Asst.Rental Fleet Manager Attachment A Denison Mine Equipment Package Quote:Blanding,Utah February 2,2009 MINIMUM GUARANTEED TOTAL** MONTHLY HOURS EXCESS NUMBER OF FREIGHT MAINTENANCE RENTAL ALLOWED HOUR J MONTHS RATE CHARGES RATE MODEL QTY RATE PER MONTH CHARGE I BASED UPON TO &FROM PER HOUR *637G 4 $25,400 EA.176 EA.$73 EA.12 EA.$21,200 EA.$8.00 EA. I D9RfT RIPPER 1 i 15,450 176 44 12 15,550 4.85, I D8RfT RIPPER 1 i 12,650 176 36 12 14,100 4.30 D7R/RIPPER 1 10,700 176 31 12 12,450 3.85 I 825H 1 11,200 176 32 12 13,000 3.85 I 980H 1 11,300 176 32 12 12,800 4.20 I *988H 1 17,500 176 50 12 15,450 5.45 I II *770 4 11,500 EA.i 176 EA.I 33 EA.12 EA.13,250 EA.I 6.20 EA.I I II 365B II 1 16,500 I 176 47 12 24,000 I 6.40 iI 10,000 GAL.Water Wagon 1 11,800 176 34 12 14,300 5.20 5,000 GAL.Water Wagon 1 6,650 176 19 12 6,450 3.05 14H/M RIPPER 1 8,800 176 25 12 10,150 3.60 I 16H/M RIPPER 1 12,650 I 176 36 12 12,100 4.35 *PLUS TIRE WEAR **INCLUDES ASSEMBLY AND DISASSEMBLY I I I The charge for two service technician's working fifty (50)hours per week,maintenance and lube trucks,parts and service trailers,and overhead would be $62,315 per month to be invoiced at the end of each month. Maintenance rates per hour would be invoiced at the end of each month based upon actual hours. Delivery and receivinq mobilization charqe is $30,820 each wav. WORLDWIDE RENTAL SERVICES 1125 Legacy View St Salt Lake City,UT 84104 TEL:(801)978-3300 FAX:(801)978-3777 TOLL FREE:1-877-997-7752 WO LDWIDE RENTAL SERVICES RENTAL RATE QUOTE We are pleased to offer the following rates for your review.Quoted rates are good for 30 days. Name:Dennison Mines Address:Blanding,DT Phone #435-678-2221 Fax #435-678-2224 Contact:Amy E-mail:abushman@denisonmines.com Project Name: Est.Start Date: Description ofEquipment Equipment Value S.t<riaLNo.Minimum Term Dailv Rate W~Rate Monthly Rate PC300 excavator with 22500.00shear--~.-- -- i------.-- -1----------- --'--- GENERAL TERMS AND CONDITIONS OF RENTAL 1.Machine month is detlned as cost ofone machine per month.Ifmultiple units are required,multiply the base rate times the number ofunits required. 2.Credit approval will be determined by credit information supplied by the contractor to Worldwide prior tojob mobilization. 3.Monthly rate is based on 28 days and 200 hours ofusage.Overtime will be billed at 70%the hourly rate. 4.Payment terms are net 30. 5.All equipment is subject to availablility. 6.Excessive tire wear and ground engaging tool wear to be billed at end ofcontract. 7.Customer must supply insurance binder covering value ofequipment We look forward to supplying your equipment requirements.Please let me know ifyou have any questions or ifthere is anything else you need! Kelly Kloberdanz Branch Manager,WRS-SLC 801.978.3300 office 801.978.3777 fax 801.330.3485 cell HONNEN EQUIPMENT February 25,2009 Amy Bushman Denison Mines USA 6425 S.Hwy 191 Blanding,UT 84511 Dear Amy: We are pleased to quote rental rates on the following: 1.Grove RT530E (30 ton)Crane $6,400.00/Month 2.Grove R1760E (60 ton)Crane $1l,100.00jMonth 3.Grove RT875E (75 ton)Crane $14,600.00/Month We currently do not have a 75 ton available. Freight will be $700.00 for the 30 ton and $1000.00 for the 60 ton at start and again at end of rental period. ~W1ffTGEtJGROU"'-i./ We believe the equipment as quoted will exceed your expectations.On behalf of Hannen Equipment Co.,thank you for the opportunity to quote Grove Lifting machinery.Please call if you have any questions or comments. Sincerely, Shane Frazee Territory Manager 970-270-2070 cell 800-746-6636 office This proposal subject to the following conditions: 1)Quote valid for 30 days. 2)Specific quoted units subject to avaifability. 5055 E 72'lJ Avenue Commerce Cily,CO 80022 303-287-7506 23581-70 Frontage Road GrandJunction,CO 81505 970-243-7090 16 Girard Street PO Box 27 Durango,CO 81303 970-247-4460 150 Salt Creek Highway POBox 1180 Mills,WY 82644 307-266-4474 5217$,Highway 59 Gillette,WY 82718 307-685-4288 October 2008 to January 2009 -Fuel Cost Calculation Producer Price Index -Commodities #2 Diesel October November December January 2009 282.3 * 224.9 * 171.5 * 164.1 *842.8 $2.107 per Gallon off road use *4 month Average Bureau ofLabor Statistics Data www.bls.gov Search:IAll BLS.gov i:]for: Page 1 of 1 -;;BUREAU OF LABOR STATISTICS Newsroom I Tutorials I ReleaseCalendar iillJl Home Subject Areas Databases &Tables Publications Economic Releases AM Z Index I About BlS._-----------_._-- Q_~~~!?<.l:~~~,_I~!?!~~~_~_~!~l:l!<.l:tg~~__!?X?~!?j.~~.~._ Change OutputOptions:From,11999 i'J To 12009iJ ~ I include graphs NEW! Data extracted on:March 2,2009 (12:28:39 PM) Producer Price Index-Commodities Series rd:WPU057303 Not Seasonally Adjusted Group:Fuels and related products and power Item:No.2 diesel fuel Base Date:198200 More Formatting Options...... FONT SIZE, Year Jan Feb'Mar 1Apr Mav Jun Jul Aug Sep Oct Nov Dec Annual 1999.40.2 38.1 .43.2 53.1 53.0 53.5 59.8 65.6 68.8 67.5 72.7 57.3 2000'76.1 86.1 '90.084.1 82.8 85.7 89.5 92.1 110.8110.0 110.4 101.6 93.3 200196.7 92.483.5 86.4 93.1 90.2 81.6 82.0 91.6 75.9 .3 56.2 83.4 200258.9 60.0 :69.7 76.9 74.7 73.3 77.6 80.4 92.398.7 85.586.8 77.9 200397.6 123.8'129.4102.387.9 .89.8 92.7 96.6 9Ll :lOLl 95.998.1 100.5 2004109.3 103.7109.7'119.9121.0 114.2123.0 135.1140.9166.6 159.7 135.3 128.2 2005141.1 149.5173.3175.4170.8'187.2'189.8200.6212.6264.1 206.2 198.5 189,1 2006'197.1 196.2 206.5230.4239.6'246.9 237.5 250.2 201.3197.5 197.2 203.0 216.9 2007,180.9 193,5220.2'238.0226.5227.6243.5231.2246.2249.6 296.7 271.9 235.5 20081278.2 287,5353.7365.1398.2,421.0.431.9346.7'342.3.282.3(p)'224.9(p),171.5(p)325.3(p) 2009164.1(p)1 1 1 1 1 1 1 1 '1 '1 '1 p :Preliminary.All indexes are subject to revision four months after original publication. Quick Links Tools At a Glance Tables Economic News Reieases Databases &Tabies Maps Calculators Inflation Location Quotient Injury And Illness Help Help &Tutorials A to Z Index FAQs Glossary About BLS Contact Us Info What's New Careers @ BLS Find It'DOL Join our Mailing Lists Privacy &Security :J Linking &Copyright Information Frequently Asked Questions I Freedom ofInformation Act I CustomerSurvey U.S.Bureau of Labor Statistics 2 Massachusetts Avenue,NE Washington,DC 20212-0001 www.bls.gov ITelephone:(202)691-5200 I Do you have a Data question? http://data.bls.gov/PDQ/servlet/SurveyOutputServlet;jsessionid=f030403891615$3F$3F$ blS.gov 3/2/2009 Labor Costs LABOR COSTS 2009 Estimated Labor Rates'* Specified Wages Heavy Construction Labor Classification Base Rate Mandated Fringe 13.97% Labor Burden (FICA,SUI, FUI,etc. 21.28% Company Benefits (medical,life insure,etc)Fringe Costs Labor CostlHR Boiler Makers Millwrights Ironworkers Carpenters Cement Masons Electricians Ironworkers -Reinforcing Laborers (including pipelayers) Pipefitters POWER EQUIPMENT OPERATORS Backhoes Cranes Dozers Graders Loaders Scrapers Trackhoes Tractors Truck Drivers $25.22 $18.76 $3.52 no added cost $22.28 $47.50 $20.82 $4.28 $2.91 $0.15 $7.34 $28.16 $21.84 $9.92 $3.05 no added cost $12.97 $34.81 $14.75 $3.03 $2.06 $0.11 $5.20 $19.95 $14.00 $0.56 $1.96 $2.42 $4.94 $18.94 $14.52 $2.71 $2.03 $0.38 $5.12 $19.64 $14.00 $1.96 $2.98 $4.94 $18.94 $9.00 $0.00 $1.26 $1.92 $3.17 $12.17 $12.60 $1.76 $2.68 $4.44 $17.04 $10.00 $1.40 $2.13 $3.53 $13.53 $10.43 $1.46 $2.22 $3.68 $14.11 $13.63 $1.90 $2.90 $4.80 $18.43 $13.61 $1.90 $2.90 $4.80 $18.41 $11.38 $1.59 $2.42 $4.01 $15.39 $12.75 $1.78 $2.71 $4.49 $17.24 $13.63 $1.90 $2.90 $4.80 $18.43 $9.42 $1.32 $2.00 $3.32 $12.74 $12.00 $1.68 $2.55 $4.23 $16.23 Note:base rates do not includeFICA,worker comp,unemployment,orcompany benefits which increase the cost per hour **State of Utah -General Decision -Current Update UT20080073,4 pages,10/19/2008 2/16/2009 -1:05 PM -WMM Rec Plan Est February2009.xls Denison Mines (USA)Corp. WhiteMesa Mill Nonspecified Wages Base Rate*** LABOR COSTS Labor Burden (FICA.SUI, Mandated Fringe FUI,etc. Company Benefits (medical,life insure,etc)Fringe Costs Labor CostlHR Survey Crew Member Sample Crew Member Mechanic (Demolition) Manager/Engineer Radiation Safety Officer Secretary Clerk Engineer Environmental Technician Safety Engineer Maintenance Foreman Security Personnel Chemist $11.09 $0.00 $1.55 $2.36 $3.91 $15.00 $11.09 $0.00 $1.55 $2.36 $3.91 $15.00 $11.52 $0.00 $1.61 $2.45 $4.06 $15.59 $40.58 $0.00 $5.67 $8.64 $14.30 $54.88 $31.71 $0.00 $4.43 $6.75 $11.18 $42.88 $12.82 $0.00 $1.79 $2.73 $4.52 $17.34 $10.55 $0.00 $1.47 $2.25 $3.72 $14.27 $31.71 $0.00 $4.43 $6.75 $11.18 $42.88 $17.86 $0.00 $2.49 $3.80 $6.29 $24.15 $17.86 $0.00 $2.49 $3.80 $6.29 $24.15 $23.27 $0.00 $3.25 $4.95 $8.20 $31.47 $6.87 $0.00 $0.96 $1.46 $2.42 $9.29 $18.67 $0.00 $2.61 $3.97 $6.58 $25.25 ***Reflects 0.0%cost of living raise for 2009 2/16/2009 -1:05 PM -WMM Ree Plan Est February 2009.xls Denison Mines (USA)Corp. While Mesa Mill Page 1 of4 GENERAL DECISION:UT20080073 10/10/2008 UT73 Date:October 10,2008 General Decision Number:UT20080073 10/10/2008 State:Utah Construction Type:Heavy County:San Juan County in Utah. Including Natural Gas Pipeline Construction Modification Number o ENGI0003-047 07/01/2008 Publication Date 10/10/2008 Excluding Natural Gas Pipeline Construction Rates POWER EQUIPMENT OPERATOR (3)Backhoe $24.53 ENGI0003-054 11/01/2007 Natural Gas Pipeline Construction Only Rates POWER EQUIPMENT OPERATOR Backhoe/Excavator/Trackhoe, Blade/Grader,Boom, Bulldozer,Crane, Mechanic,Trencher $30.25 Oiler $17.66 LAB00295-018 11/01/2007 Natural Gas Pipeline Construction Only Rates LABORER Chain Saw and Power Drill ...$18.86 Common or General,Nail gun,Pipelayer,Pot Tender ..$17.61 Formworker $18.61 Powderman $19.36 Sandblaster $18.36 SUUT2008-028 08/19/2008 Rates CARPENTER,Including Form Work (Excluding Natural Gas Pipeline Construction Form Fringes 12.71 Fringes 13 .14 9.64 Fringes 4.94 4.94 4.94 4.94 4.94 Fringes http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/16/2009 Work)$14.75 CEMENT MASON/CONCRETE FINISHER ...$14.00 LABORER:Mason Tender - Cement/Concrete $9.00 LABORER:Common or General (Excluding Natural Gas Pipeline Construction)$12.00 LABORER:Pipelayer (Excluding Natural Gas Pipeline Construction)$9.00 OPERATOR:Roller (Dirt and Grade Compaction)$10.89 OPERATOR:Blade/Grader (Excluding Natural Gas Pipeline Construction)$13.61 OPERATOR:Excavator (Excluding Natural Gas Pipeline Construction)$12.75 OPERATOR:Front End Loader $11.38 OPERATOR:Trackhoe (Excluding Natural Gas Pipeline Construction)$13.63 TRUCK DRIVER (Excluding Natural Gas Pipeline Construction)$12.00 TEAM0222-020 11/01/2007 NATURAL GAS PIPELINE CONSTRUCTION ONLY Rates TRUCK DRIVER Group 1: Articulated End Dump,Low Boy,Rollagon or Similar type Equipment,Truck Mechanic $27.14 Group 2: A-Frame,Challenger(For transportation purposes), Forklift,Fuel Truck,Gin Pole,Rubber-Tired Tractor,Tandem Float (4 &5 Axle),Track Truck/All-Track Dumper Equipment,Vacuum Truck, Winch Truck $26.68 Group 3: Ambulance,Bus,Dump 3.03 0.56 0.36 0.00 0.00 ,,- 0.00 0.00 y 0.00 ~ 0.00 ,/ 0.00 .", o.00 ~ Fringes 8.74 8.74 Page 2 of 4 http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/16/2009 Truck (2 and 3 axle), Flatbed Truck (2 and 3 axle),Grease Truck,Hot Pass Truck (3 axle), Jeep,Pick-up,Single Axle Float (3 axle),Skid Truck (2 and 3 axle), Station Wagon,Stringer Bead &Hot Pass (2 axle), Swamp Buggy/Marsh Buggy, or similar type equipment,Team Driver, Water Truck (2 and 3 axle).$26.39 Premium Pay: 8.74 Page 3 of 4 Add $1.25 to the above Rate for the following classifications Group 1:Low Boy and Truck Mechanic Group 2:Stringer Truck WELDERS -Receive rate prescribed for craft performing operation to which welding is incidental. Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29 CFR 5.5 (a)(1)(ii)). In the listing above,the "sun designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates.Other designations indicate unions whose rates have been determined to be prevailing. WAGE DETERMINATION APPEALS PROCESS 1.)Has there been an initial decision in he matter?This can be: *an existing published wage determination *a survey underlying a wage determination *a Wage and Hour Division letter setting forth a position on a wage determination matter *a conformance (additional classification and rate)ruling On survey related matters,initial contact,including requests for summaries http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...211612009 Page 4 of4 of surveys,should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program.If the response from this initial contact is not satisfactory,then the process described in 2.)and 3.)should be followed. with regard to any other matter not yet ripe for the formal process described here,initial contact should be with the Branch of Construction Wage Determinations.Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S.Department of Labor 200 Constitution Avenue,N.W. Washington,DC 20210 2.)If the answer to the question in 1.)is yes,then an interested party (those affected by the action)can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator U.S.Department of Labor 200 Constitution Avenue,N.W. Washington,DC 20210 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description,area practice material,etc.)that the requestor considers relevant to the issue. 3.)If the decision of the Administrator is not favorable,an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board).Write to: Administrative Review Board U.S.Department of Labor 200 Constitution Avenue,N.W. Washington,DC 20210 4.)All decisions by the Administrative Review Board are final. END OF GENERAL DECISION http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT2008...2/1612009 Long Term Care LONG TERM CARE CALCULATION February 2009 Base Amount (Starting in Dec.1978) CPI-U December,1978 CPI-U December 2008 $250,000 67.7 210.2 Adjusted Long Term Care =$250,000 x (CPI-U most recent /CPI-U Dec.,1978) Adjusted Long Term Care 2/16/2009 -12:36 PM -WMM Ree Plan Est February 2009.xls $776,322 Denison Mines (USA)Corp. White Mesa Mill tlureau ot Labor Statistics Data www.bls.gov Search:IAll BLS.gov ::±]for: Page 1 of 1 -};BUREAU OF LABOR STATISTICS Newsroom I Tutorials I Release Calendar @illl Home Subject Areas Databases &Tables Publications Economic Releases A - ZIndex I About BLS Change OutputOptions:From:11998iJ To:12008:.£1 FONT SIZE: r include graphs NEW! Data extracted on:February 16,2009 (1:32:15 PM) Consumer Price Index -All Urban Consumers Series rd:CUUROOOOSAO,CUUSOOOOSAO Not Seasonally Adjusted Area:U.S.city average Item:All items Base Period:1982-84=100 More Formatting Options ~ Year Jan Feb Sep HALF2 1998·161.6 163.6 163.9 163.7 1999:164.3 164.5 167.9 168.3 167.8 2000'168.8 169,8 173.7 174.0 173.6 2001175.1 175.8 178.3 176,7 177.5 2002177,1 177.8 181.0 180.9 180,9 2003181.7 183.1 185,2 184.3 184,6 2004185.2 186.2 189,9 190.3 190.2 2005190.7 191.8 198.8 196.8 197.4 2006198,3 198.7 199.8 201.5 202.5 202.9 203.5 203,9 202.9 201.8 201.5 201.8 201.6 200.6 202.6 2007202.416203.499.205,352 206,686,207.949.208.352'208.299 207.917208.490 208,936210.177 210.036207.342205.709,208.976 2008"211.080,211.693 "213.528.214.823 '216.632 ·218.815'219.964.219.086'218.783 216,573 212.425 210,228'215.303.214.429'216,177 Quick Links Tools At a Glance Tables Economic News Reieases Databases &Tables Maps Calculators Inflation Location Quotient Injury And Iilness Help Help &Tutorials A to Z Index FAQs Glossary About BLS Contact Us Info What's New Careers @ BLS Find Itl DOL Join our Mailing Lists Privacy &Security Linking &Copyright Information Frequently Asked Questions I Freedom of Information Act I Customer Survey U.S.Bureau of Labor Statistics 2 t>1assachusetts Avenue,NE Washington,DC 20212-0001 www.bls.gov ITelephone:(202)691-5200 I Do you have a Data question7 http://data.b1s.gov/PDQ/servlet/SurveyOutputServlet;jsessionid=f030a14d5fOd$3F$3FR$ bls.gov 2/1612009