HomeMy WebLinkAboutDDW-2024-007295
Snowbasin Resort
Trappers Loop Water Improvement District
Legend Well House
Waterline Utility Specifications
April 2024
TABLE OF CONTENTS
The following is a list of 2017 APWA Standard Specifications that are expected to be referenced;
however, additional specification may be referenced as needed:
DIVISION 22 PLUMBING
Mechanical General Requirements
22 05 00 Mechanical General Requirements
Plumbing Piping and Pumps
22 11 13 Facility Water Distribution Piping
22 13 33 Submersible Pump
DIVISION 33 UTILITIES
Utilities General
33 05 02 Concrete Pipe and Culvert
33 05 05 Ductile Iron Pipe
33 05 09 Steel Pipe – Lined and Coated
33 05 20 Backfilling Trenches
33 08 00 Commissioning of Water Utilities
Water Utilities
33 11 00 Water Distribution and Transmission
33 12 16 Water Valves
33 13 00 Disinfection
Snowbasin Resort Legend Well House Specifications
SECTION 22 05 00
MECHANICAL GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 SECTION INCLUDES
A. General requirements for mechanical systems.
B. General requirements for submittals, labeling, and servicing mechanical systems.
C. Locating equipment and test run mechanical systems.
1.2 SUBMITTALS
A. General: Submittals must indicate proper arrangements to suit installation and
maintenance requirements such as but not limited to motor location, access door
openings, filter removal, piping connections. Clearly mark equipment submittal sheets
indicating equipment symbol and exact selection of proposed equipment.
B. Shop Drawings: Submit complete, bound, indexed, loose leaf binder large enough for all items, including:
1. Equipment schedule items.
2. Vibration elimination devices.
3. Valves.
4. Insulation.
5. Registers and grilles.
6. Automatic temperature controls.
7. Certificates of guarantee.
C. Pipe Tests: If requested, submit a report of tests performed by pipe manufacturer and the date each test was completed.
1.3 LABELING
A. Identify all critical items of equipment with permanently etched, laminated plastic
labels indicating function or relationship of each piece of equipment to system
involved. Secure all labels in place in a clearly visible location with appropriate self-
tapping screws.
B. Mark pipe continuously to identify such information as nominal size, pressure rating, industry standards designation number, etc.
1.4 SERVICE
A. Provide emergency service for mechanical systems.
B. In the event of a system Failure, OWNER shall be able to telephone a single request
for complete service call by using a number furnished under the contract. The service
organization shall dispatch in the time specified by the ENGINEER a person to the site
who shall be able to analyze the systems and locate the malfunction. If work should
berequired out of the normal trade definition, it shall be the responsibility of this service
organization to contact the CONTRACTOR or any other specialty involved, and take the
responsibility of completing the repairs and putting the system into operation.
C. Service shall be provided by a service business, established and experienced in this
Snowbasin Resort Legend Well House Specifications
work. Complete information in regard to this service organization, showing the
personnel, equipment, location, experience, etc., shall be submitted for review along
with other items of the system.
D. This service shall be provided starting at the date of Substantial Completion, and
for the duration of the CONTRACTOR's guarantee period.
1.5 SUBSTITUTIONS
A. Section 01 25 00.
B. Resolve any conflict arising from use of substituted equipment.
C. Pay all costs required to make equipment comply with intent of Contract Documents. All approvals shall be obtained in writing.
1.6 COORDINATION
A. Section 01 31 13.
B. Plan all work to proceed with a minimum of interference with other trades.
C. Inform affected trades of all openings for mechanical work.
D. Furnish all special frames and sleeves as indicated in other Sections.
1.7 PRODUCT HANDLING
A. Section 01 65 00.
B. Deliver all materials to the job bearing manufacturer's name and trade name and UL label in every case where a standard has been established for that particular material.
C. Store product in original containers, protect from elements, and make readily accessible for inspection until ready for installation.
1.8 PROJECT CONDITIONS
A. Notify ENGINEER if a discrepancy occurs between the equipment supplied and the intent or function of the equipment, catalog numbers, discontinued products, Drawings, Specifications, etc.
B. Failure to report any conflict does not relieve CONTRACTOR from meeting the
intent of the Contract Documents nor shall it change the contract cost.
C. Perform all required digging, cutting, incidental work, and make required repairs.
D. Do not cut into any structural element without ENGINEER’s knowledge.
PART 2 PRODUCTS
2.1 EQUIPMENT
A. Where two (2) or more units of the same class of new equipment are required, provide units of single manufacturer.
B. Use standard products of the manufacturer unless indicated otherwise.
PART 3 EXECUTION
Snowbasin Resort Legend Well House Specifications
3.1 ROUGH IN REQUIREMENTS
A. Refer to architectural, structural, mechanical, civil and electrical Drawings.
B. Verify that equipment dimensions meet space requirements with sufficient clearances as may be required by equipment used and as indicated.
C. Check building and equipment dimensions for exact placement of sleeves, conduit and equipment.
D. Determine requirements and dimensions relating to manufacturer's Shop Drawings.
E. Make changes required due to lack of coordination at no additional cost to OWNER.
3.2 ACCESSIBILITY FOR MAINTENANCE
A. Coordinate location of equipment such as valves, dampers, fixtures, motors, fans, controls, etc. to allow accessibility for maintenance.
B. Ensure access for service or maintenance for proper operation and function.
C. To facilitate function, coordinate mechanical work of all other trades to avoid concealing equipment.
D. Refer any critical location or assembly conflicts to ENGINEER.
3.3 TEST RUN
A. Perform preliminary operation of all mechanical systems in cooperation with all trades involved.
B. Arrange time of test run.
C. Make operating test by a team consisting of manufacturer's representative, CONTRACTOR's representative and ENGINEER.
D. Complete test run in one (1) working day including possible different date identification and recheck of significant items under different working conditions.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 22 11 13
FACILITY WATER DISTRIBUTION PIPING
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Installation of building water piping, drain piping, and related work.
B. Installation of pipe hangers, sleeves, supports, brackets, and related items.
C. Testing of piping systems and correction of any problems found to exist.
1.2 REFERENCES
A. ASME Standards:
B31.1: Power Piping.
1.3 PIPING SYSTEM LAYOUTS
A. Piping system Drawings are diagrammatic and are intended to show approximate
location of equipment and piping. Verify dimensions, whether in figures or scaled, in
the field. CONTRACTOR is responsible for the installation of complete and
workable systems whether completely detailed on the plans or not.
B. Ascertain locations of apparatus, fixtures, equipment, and piping in the field, and
layout work accordingly. ENGINEER reserves the right to make minor changes in
location of piping and equipment up to the time of installation without additional
cost to OWNER.
1.4 REQUIREMENTS OF REGULATORY AGENCIES
A. Install work per applicable provisions of codes, rules, regulations, statutes,
and ordinances of authorities having jurisdiction.
PART 2 PRODUCTS
2.1 PIPE
A. Provide size, type, and class of pipe for various uses as follows:
1. Steel pipe lined and coated, Section 33 05 09.
2. Ductile iron pipe, Section 33 05 05.
3. Copper pipe, Section 33 05 03.
4. PVC pipe, Section 33 05 07.
5. ABS pipe, Section 33 05 01.
6. PP pipe, Section 33 05 11.
B. Do not substitute different pipe unless approved in writing before
Substitutions. To request Substitution, refer to Section 01 25 00.
2.2 PIPE HANGERS AND SUPPORTS
A. Properly support, suspend, or anchor all piping and fittings to prevent sagging,
Snowbasin Resort Legend Well House Specifications
overstressing, or longitudinal movement, and to prevent thrust or loads on or against
other equipment.
B. Support horizontal piping on adjustable split steel ring or clevis hangers. The following
schedule shows minimum spacing:
1. Steel and Copper:
a. 1-1/4" and smaller 6'-0" on center b. 1-1/2" to 3"
8'-0" on center
c. 4" and larger 12'-0" on center
2. PVC, CPVC, and ABS:
a. 1" and smaller 4'-0" on center
b. 1-1/4" to 2" 5'-0" on center
c. 2-1/2" to 4" 6'-0" on center
d. 5" and larger 8'-0" on center
C. Support insulated piping with pipe saddles and hangers that fit on outside of insulation.
Do not compress or damage pipe insulation with hangers or supports.
D. Provide all rigid hangers with a means of vertical adjustment after erection.
E. Use copper or copper plated hangers for supporting uninsulated copper pipe.
F. Use one of the following means of supporting horizontal piping from a wall.
1. Steel J-Hook for pipe located close to wall, up to three (3) inches pipe.
2. For hanger suspension with 750 lbs. maximum loading, use light welded steel
bracket with hole for one rod, 3/4 inch diameter.
3. For pipe-roll stand support use welded-steel bracket.
G. For vertical piping supports for all pipe except copper:
1. Support vertical piping with wrought steel riser clamps. Make adequate provision
for expansion, contraction, and lateral stability.
2. Use steel extension pipe clamps for vertical pipe supports. Refer to
manufacturer's rated maximum loading for each size pipe. Bolt clamp securely to
pipe rest, clamp end extension on building structure.
3. Where pipe sleeves extend above floor, place pipe clamps at ceiling below,
support clamp end extension from inserts.
H. For uninsulated vertical copper tubing lines, furnish copper tube straps.
I. Use beam clamps that are of malleable iron for 3/8 inch hanger rods; forged steel
beam clamp for hanger rod up to 1-1/2 inches.
2.3 INSERTS
A. Furnish and set inserts in concrete forms; provide reinforcing rods for pipe sizes
over three (3) inches or equivalent.
B. Furnish concrete inserts as follows: Black, malleable iron, universal type for
threaded connections with lateral adjustment.
2.4 SHIELDS
A. Provide shields to protect insulation in all areas.
Snowbasin Resort Legend Well House Specifications
B. Provide approved galvanized form shields to protect insulation at areas of contact
with hangers and supports.
C. Furnish low compressive insulation protector shields. Size per shield
manufacturer's recommendations.
2.5 SLEEVES
A. Where pipes pass through floors, footings, foundations, walls, or ceilings, furnish and
install pipe sleeves. Sleeves for concealed piping shall be of galvanized iron, and for
exposed piping on I.P.S. black steel pipe installed so as to be completely covered by
escutcheons. Extend sleeves through floors 1/2 inch above finish floor.
2.6 ESCUTCHEONS
A. Fit pipe passing through walls, floors, or ceilings with escutcheons with set screws.
B. Use prime painted escutcheons where surface is to receive a paint finish; otherwise,
use escutcheons that are nickel or chromium plated.
C. Where piping is insulated, use escutcheon outside the insulation.
2.7 JOINTS
A. For screwed pipe make ends with sharp, clean tapered threads using pipe compound
on male thread only. Do not use mill cut threads. Ream cut pipe to full inside diameter.
B. Welding may be done by either arc or acetylene process, ASME B31.1.
C. For solder joints use fittings specifically made for soldering. Clean all burrs and
roughen pipe to clean. Solder complete around joint.
D. For grooved pipe jointing systems use mechanical pipe couplings and fittings.
E. For no-hub cast iron pipe use double screw joint neoprene coupler.
2.8 UNIONS
A. Furnish and install unions necessary for installation and necessary to permit
removal of equipment.
B. For unions in steel pipe 1-1/2 inches and smaller use malleable iron ground joint
unions with brass to iron seat, galvanized or black as required.
C. For larger unions in steel pipe use standard weight, cast iron flange unions with
1/16 inch thick gaskets, galvanized or black as required.
PART 3 EXECUTION
3.1 PREPARATION
A. Before installation of piping, verify that it will not interfere with clearances required
for the erection and finish of structural members, architectural members, electrical,
sprinkler, or mechanical items.
B. Hang or support piping materials from roof support system whenever possible.
C. Do not cut any structural members for installation of piping.
Snowbasin Resort Legend Well House Specifications
3.2 INSERTS
A. Use inserts for suspending hangers from reinforced concrete slabs and sides of
reinforced concrete beams wherever practicable.
B. Set inserts in position in advance of concrete work. Provide reinforcement rod in
concrete for inserts carrying pipe over four (4) inches in diameter.
C. Where concrete slabs form finished ceiling, finish inserts flush with slab surface.
D. Where inserts are omitted, drill through concrete slab from below and provide rod
with recessed square steel plate and nut above slab.
3.3 SLEEVES
A. Set sleeves in position in advance of concrete work. Provide suitable reinforcing
around sleeves.
B. Extend sleeves through potentially wet floors 1 inch above finished floor level. Caulk
sleeves full depth and provide floor plate.
C. Where piping passes through floor, ceiling, or wall, close-off space between pipe and
construction with noncombustible insulation. Provide tight-fitting metal caps on both
sides and caulk.
3.4 PIPE HANGERS AND SUPPORTS
A. Support all piping and make adequate provisions for expansion, contraction,
slope, and anchorage.
B. The use of pipe hooks, chains, or perforated metal for pipe support will not be
permitted.
C. Suspend all piping in the building as indicated.
D. Install hangers to provide minimum 1/2 inch clear space between finished
covering and adjacent work.
E. Place a hanger within 1 foot of each horizontal elbow.
F. Use hangers that are vertically adjustable 1-1/2 inches minimum after piping is
erected.
G. Support horizontal soil pipe near each hub, with five (5) feet maximum spacing
between hangers.
H. Support vertical piping at every other floor. Support vertical soil pipe at each floor and
at hub.
I. Where several pipes can be installed in parallel and at same elevation, provide
multiple or trapeze hangers.
J. Where practical, support riser piping independently of connected horizontal
piping.
3.5 PIPING INSTALLATION
A. Cut piping accurately for fabrication to measurements established at the construction
site and work into place without springing or forcing.
B. Remove burrs and cutting slag from pipe by reaming or other approved cleaning
Snowbasin Resort Legend Well House Specifications
methods.
C. Make changes in direction with proper fittings.
D. Arrange piping so as not to interfere with the removal of other equipment, ducts, or
devices. Do not block doors, windows, or access openings. Provide unions in the
piping at connections to all equipment. Unions must be accessible.
E. Make connections of dissimilar metals (such as copper and steel) with insulating
couplings suitable for at least 175 psig working pressure at 250 deg F
F. Cap or plug open ends of pipes and equipment with PVC caps or expanding
neoprene plugs to keep dirt and other foreign materials out of the system. Plugs of
rags, wool, cotton, waste, or similar materials are not acceptable.
G. Install all piping systems so they can easily be drained. Provide hose bibs at low
point of water lines.
H. Slope all soil and waste lines within the building at 1/4 inch per foot fall in the direction
of flow unless indicated otherwise.
3.6 PRIMING AND COATING
A. Prime coat exposed steel hangers and supports and hangers and supports located in
crawl spaces, pipe shafts, and suspended ceiling spaces.
B. Color Code, Section 09 91 00.
3.7 DISINFECTION AND TESTING
A. Disinfect culinary water piping, Section 33 13 00.
B. Performance testing culinary water piping, Section 33 08 00.
C. Repair defects that develop under tests promptly and repeat tests. No caulking of
screwed joints, cracks, or holes will be permitted. Replace pipe or fitting or both with
new material when repairing leaks in screwed joints.
D. Repair leaks in copper tubing by melting out joint, thoroughly cleaning both tubing
and fitting, and resoldering.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 22 13 33
SUBMERSIBLE PUMP
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Submersible pump with controls and components.
B. Coordinate installation with work of separate trades.
1.2 DESIGN REQUIREMENTS
A. Statically and dynamically balance rotating parts.
B. Pumps to operate under continuous submergence at a minimum depth of 35 feet
without loss of watertight integrity.
C. Capable of handling storm water, sanitary sewerage, and wastewater.
D. Pump to operate at 1750 rpm unless indicated otherwise.
E. Design to permit complete servicing without breaking piping or motor connections.
F. Motor temperature rise to conform to latest NEMA standards for submersible
pumps.
1.3 SUBMITTALS
A. Substitutions: Section 01 25 00.
B. Shop Drawings: Section 01 33 00 for pumps, electrical connections and controls.
C. Pump Curves: Certified pump performance characteristics with pump and system
operating point plotted. Include net positive suction head (NPSH) curve.
D. Motor and Cable Insulation Test: For moisture content or insulation defects.
E. Pump manufacturer's certificate that installation is correct and the pump(s)
function properly relative to flow, speed, vibration and amperage draw.
1.4 HANDLING AND STORAGE
A. Protect against damage and dirt during shipping and storage.
PART 2 PRODUCTS
2.1 MAJOR PUMP COMPONENTS
A. Gray case iron, Class 30 casing, with smooth surfaces devoid of blow holes and
other irregularities.
B. Stainless steel exposed bolts and nuts, Section 05 05 23.
Snowbasin Resort Legend Well House Specifications
C. Waterproof exterior. Manufacturer select exterior spray with PVC epoxy primer
chloric rubber paint finish.
2.2 DISCHARGE CONNECTION ELBOW
A. Installed in the wet well.
B. Make connection of pump to discharge connection elbow automatic when pump is
lowered into place in a simple downward motion.
C. Provide sliding guide bracket and guide bar(s) as part of the discharge connection
elbow.
D. Guarantee sealing of the discharge interface.
2.3 MATING SURFACES
A. Seal all mating surfaces. Do not use secondary sealing compounds, gaskets,
grease, or other devices.
2.4 CABLE ENTRY
A. Watertight and submersible seal for cable entry into pump.
B. Isolate cable entry junction chamber and motor from each other so foreign material
entering through the pump top (if any) shall not have access to the motor.
C. Do not use epoxies, silicones, or other secondary sealing systems.
2.5 PUMP MOTOR
A. Squirrel-cage, induction, shell type design, housed in an air-filled, watertight chamber,
NEMA design B type with stator winding and stator leads insulated against moisture
and temperatures less than 311 deg F
B. Design for continuous duty, capable of sustaining a minimum of 10 starts per
hour.
C. Capable of continuous operation at totally, partially or non-submerged conditions.
2.6 JUNCTION CHAMBER
A. Junction chamber to contain the terminal board.
B. Connection Between Cable and Stator Leads: Perfectly leak-proof.
2.7 COOLING SYSTEM
A. Provide an adequately designed cooling system for the pump(s).
B. Provide provision for external cooling and flushing.
2.8 THERMAL SENSORS
A. Use thermal sensors to monitor stator temperatures that are wired to the control
panel.
2.9 PUMP SHAFT SEAL
A. Carbon steel shaft completely isolated from the pumped liquid by a mechanical
rotating shaft seal system. Seals require neither maintenance nor adjustment, which
Snowbasin Resort Legend Well House Specifications
can be easily inspected and replaced.
B. Do not use a pressure differential consisting of a single or double spring action
between upper and lower sealing units to offset external pressure and to effect shaft
sealing.
C. Use oil as seal lubricant. Provide drain and inspection plug, with a positive anti-
leak seal that is easily accessible from the outside.
2.10 SHAFT BEARINGS
A. Permanently lubricated bearings capable of five (5) years continuous operation.
B. Use bearings capable of operating for short periods of time with the discharge
valve closed.
2.11 IMPELLER
A. Dynamically balanced, double shrouded, nonclogging design having a long thrulet
without acute turns capable of handling solids, fibrous materials, heavy sludge and
other similar materials.
B. Fit the impeller and the shaft by sliding and using a key to lock.
2.12 VOLUTE
A. Designed with smooth fluid passages large enough at all points to pass any size
solid which can pass through the impeller.
B. Install a wear ring system to provide efficient sealing between the volute and impeller.
2.13 PUMP MOTOR CABLE
A. Use pump motor cable suitable for submersible pump application. Conform
cable sizing to NEC specifications for pump motors.
B. Seal pump cable end with a high quality protective covering to make it impervious to
moisture or water seepage before electrical installation.
C. Provide 1 foot extra length of cable for each 50 feet of depth.
D. Provide 10 feet of extra cable beyond surface plate.
E. Provide corrosion resistant shield where cable passes pump volute.
2.14 ACCESS FRAME, GUIDES AND DOOR
A. Provide access frame to the discharge connection elbows complete with hinges and
flush locking mechanism, upper guide holder and level sensor(s) cable holder.
Provide frame with sliding nut rails to attach the accessories required. Lower guide
bar holder(s) shall be integral with the discharge connection elbow.
B. Provide guide bars of the size necessary to lift and lower the pump(s) without
bending, binding, or vibration. Do not support any portion of the weight of the pump
of the guide bars.
C. Provide surface plate with adequate rigidity to support the system, but with
sufficient openings to allow free access to cable, vent and water.
D. Access doors of skid proof design.
Snowbasin Resort Legend Well House Specifications
E. All components galvanized or zinc coated, Section 05 05 10.
2.15 CONDUIT SYSTEMS
A. Section 26 05 33.
B. Do not use flexible conduit.
2.16 CONTROL PANEL
A. Solid state logic circuitry operational in temperature range of -40 deg F and +120
deg F and waterproof, designed for outdoor use, lockable and containing line
voltage pump power circuit and lower voltage pilot control circuit or approved
equivalent. The pilot control circuit takes power from the same terminal board.
Perform the following functions:
1. Start and stop pumps at required water levels.
2. Alternate the sequence of starting via manual or automatic selection.
3. Start progressively more pumps if water level in sump continues to rise.
4. Instant disconnect from power source in the event of major electrical fault.
B. Equip the panel with all protective devices for motors as disconnects, relays,
hand-auto-off switches designed for three phase 480/277 volt power system to
control the pumps via the operation of the liquid sensors.
C. On/off pump running lights in the control panel for each pump.
D. Adjustable thermostat heater.
2.17 STRAINER
A. Strainer with net inlet area three (3) times (if not indicated) the net inlet area of
impeller.
2.18 TIMERS
A. Provide timers such that the operating time of each pump can be continuously
monitored. Fit each timer with a reset capability to restart timing cycle.
PART 3 EXECUTION
3.1 INSTALLATION
A. Check impeller, motor rating, and electrical connections for compliance with
manufacturer's recommendations.
B. Secure pumps as indicated and per the manufacturer's recommendations.
3.2 PUMP TESTING AND START-UP - FIELD
A. Qualified millwright to check, align, and certify pumps before start-up.
B. Before submergence, run the pump dry to establish correct rotation and mechanical
integrity.
Snowbasin Resort Legend Well House Specifications
C. Run the pump for a minimum of 30 minutes submerged, under six (6) feet of water
minimum. Retest motor and cable insulation.
D. Ensure pumps operate at specified system fluid temperatures without vapor binding
and cavitation, are non overloading in parallel or individual operation, operate within
25 percent of midpoint of published maximum efficiency curve.
E. System Testing: Run a complete operating test of the pumps and associated
equipment after installed in the field:
1. Dry Test: Turn on the power to all equipment. With the pump station dry, activate
the number 1 pump liquid level sensor. Then activate the number two (2) pump
and the number three (3) pump liquid level sensors, etc. Check the "pumps
running" lights on the control panel to see that they are operating properly.
Deactivate all sensors. Pump systems should turn off and the number 1 pump
should switch to become the lag pump with the number two (2) pump becoming
the lead pump, etc. Repeat the above process to verify that the pumps have
transferred the lead.
2. Wet Test: Provide a source of water adequate for this test. Conduct this test
identically to the Dry Test. All equipment must pass these tests. Repair or replace
any equipment failing to operate properly at no additional cost to OWNER.
F. Start-up: Instruct OWNER's personnel, Section 01 78 23.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 05 02
CONCRETE PIPE AND CULVERT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Reinforced and non-reinforced concrete pipe and culvert, fittings and joint materials.
1.2 REFERENCES
A. AASHTO Standards:
HB-17 Highway Bridges.
LRFD Bridge Design Specifications, Customary U.S. Units. M198 Joints
for Concrete Pipe, Manholes, and Precast Box
Sections using Preformed Flexible Joint Sealants.
B. ASTM Standards:
C14 Concrete Sewer, Storm Drain, Culvert Pipe.
C76 Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe.
C118 Concrete Pipe for Irrigation or Drainage. C150 Portland
Cement.
C361 Reinforced Concrete Low-Head Pressure Pipe. C412
Concrete Drain Tile.
C443 Joints for Circular Concrete Sewer and Culvert Pipe, Using Rubber Gaskets.
C444 Perforated Concrete Pipe.
C497 Testing Concrete Pipe, Sections, or Tile.
C505 Non-Reinforced Concrete Irrigation Pipe with Rubber Gasket Joints.
C507 Reinforced Concrete Elliptical Culvert, Storm Drain, and Sewer Pipe.
C654 Porous Concrete Pipe.
C655 Reinforced Concrete D-Load Culvert, Storm Drain and Sewer Pipe.
C985 Non-reinforced Concrete Specified Strength Culvert, Storm Drain, and Sewer Pipe.
C1433 Precast Reinforced Concrete Monolithic Box Sections for Culverts, Storm Drains, and Sewers. (Designed according to AASHTO BH-17).
C1479 Installation of Precast Concrete Sewer, Storm Drain, andCulvert Pipe
Using Standard Installations.
C1504 Precast Reinforced Concrete 3 Sided Structures for Culverts and Storm Drains.
C1577 Precast Reinforced Concrete Monolithic Box Sections for Culverts, Storm Drains, and Sewer (Designed according to AASHTO LRFD).
Snowbasin Resort Legend Well House Specifications
C. AWWA Standards:
C302 Reinforced Concrete Pressure Pipe, Non-cylinder Type, for Water and Other Liquids.
1.3 SUBMITTALS
A. Precast box culvert design summary.
B. Manufacturer’s proof of certification.
1.4 QUALITY ASSURANCE
A. Manufacturer and Transporter: Certified per Section 03 34 00.
B. Pipe:
1. Remove and replace pipe that show exposed reinforcing steel, honeycomb or open texture.
2. Repair or replace reinforced concrete pipe if cracks are greater than
0.10 inch.
PART 2 PRODUCTS
2.1 PIPE AND FITTINGS
A. Provide type, class, strength and size of pipe and fittings required.
B. Concrete:
1. Use ASTM C150 or C1157 cement unless required otherwise.
2. Admixtures and pozzolans may be used only with approval.
C. Gravity Pipe System:
1. Reinforced Concrete Pipe: ASTM C76 or ASTM C655.
2. Non-reinforced Pipe: ASTM C14 in sizes up to 36" diameter and ASTM C985 for pipe up to 60" diameter.
3. Irrigation or Drainage Pipe: ASTM C118 or ASTM C505.
4. Drainage Tile: ASTM C412.
5. Perforated Pipe: ASTM C14 Type 1 Class 2 or ASTM C444.
6. Elliptical Pipe: ASTM C507.
7. Porous Concrete Pipe: ASTM C654.
8. Perforated Concrete Pipe: ASTM C444.
9. Precast Box Section Bridge: ASTM C1433 or ASTM C1577 as applicable.
10. Three Sided Culvert: ASTM C1504.
D. Low Head Pressure Pipe Systems: ASTM C361 or AWWA C302.
2.2 JOINTS
A. Use ASTM C443 rubber gasket bell and spigot type joints.
B. For box sections use tongue and groove joints with bituminous mastic joint sealant.
C. For elliptical sections use tongue and groove joints with bituminous mastic joint sealant, AASHTO M198.
D. Mortar: Portland cement, Section 04 05 16.
Snowbasin Resort Legend Well House Specifications
2.3 SOURCE QUALITY CONTROL
A. Pipe and tile, ASTM C497.
B. Box sections, ASTM C1433.
C. Three sided culverts, ASTM C1504.
PART 3 EXECUTION
3.1 FACTORY FITTINGS
A. Fit all service tees and other miscellaneous fittings with an expanding plug.
B. Grout all fittings to provide a smooth interior and exterior surface.
C. When providing pipe or box sections specifically manufactured with branch
connections, carefully shape and fit adjoining pieces to facilitate grouting. Grout all
fittings to provide a smooth interior and exterior surface. Lateral pipe or sections
shall not project beyond the inner surface of pipe.
D. Use epoxy adhesive grout, Section 03 61 00 as interface between new and existing concrete and piping materials.
3.2 INSTALLATION - PIPE AND FITTINGS
A. Assembly: Abide by manufacturer's instructions, ASTM C1479, and the following. Use the more stringent provisions if there are any conflicts.
1. Pressurized Systems:
a. Water distribution and transmission, Section 33 11 00.
b. Underground irrigation, Section 32 84 23.
2. Gravity Systems:
a. Sanitary sewers, Section 33 31 00.
b. Under drains and storm drains, Section 33 41 00.
B. Burial: Comply with Section 33 05 20 and the following.
1. Place circular concrete pipe that contains elliptical reinforcing so that the
reference lines designating the top of the pipes will not be more than five (5)
degrees from the vertical plane through the longitudinal axis of the pipe.
3.3 INSTALLATION - BOX SECTIONS
A. Assembly: Abide by manufacturer's instructions, and Section 33 41 00 for under
drains and storm drain systems. Use the more stringent provisions if there are any
conflicts.
1. Install per manufacturer’s instructions.
2. Provide a leveling course under box section. Use Sewer Rock unless specified otherwise.
3. Pull sections together using internal winches or tugger. Do not push box section together. Pushing causes joint misalignment.
4. Limit joint gap to maximum specified by manufacturer. Remove excess
bituminous mastic joint sealant from interior box wall, floor, and ceiling.
B. Burial: Comply with Section 33 05 20.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 05 05
DUCTILE IRON PIPE
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Ductile iron pipe, couplings, fittings, and joint materials.
1.2 REFERENCES
A. AWWA Standards:
C104 Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water.
C110 Ductile-Iron and Gray Iron Fittings, 3 In. Through 48 In., for Water and Other Liquids.
C111 Rubber-Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and Fittings.
C115 Flanged Ductile-Iron and Gray Iron Pipe with Threaded Flanges.
C151 Ductile-Iron Pipe, Centrifugally Cast in Metal Molds or Sand-Lined Molds, for Water or Other Liquids.
C600 Installation of Ductile-Iron Water Mains and Their Appurtenances.
1.3 QUALITY ASSURANCE
A. Repair damaged delaminated, or scaled coating on pipe.
PART 2 PRODUCTS
2.1 PIPE AND FITTINGS
A. Buried Applications:
1. Class 52 or pressure class 350 psi ductile iron pipe, AWWA C151 with push-on joints, AWWA C111.
2. Cement lining for all pipe and fittings, AWWA C104.
3. Class 250 fittings with AWWA C110 joints.
4. Coupler with mechanical joint fittings, AWWA C104, C110, and C111.
5. Rubber gasket slip-on pipe joints, AWWA C111 with gasket lubricant.
6. Bronze wedges with current capacity of 400 amps each for each joint as follows:
Pipe No. of
Diameter Wedges
less than 10” 2
10” 3
12” 4
greater than 12” 6
B. Above Ground Applications: As buried applications, except use bolted flanged fittings, AWWA C104, C110, and C115.
2.2 COVERINGS
A. Buried Mechanical Joints: Grease and eight (8) mil vinyl wrap plastic cover.
Snowbasin Resort Legend Well House Specifications
PART 3 EXECUTION
3.1 INSTALLATION
A. Assembly: Abide by manufacturer’s instructions, AWWA C600, and the following. Use the more stringent provisions if there are any conflicts.
1. Pressurized Systems:
a. Water distribution and transmission, Section 33 11 00.
b. Underground irrigation, Section 32 84 23.
2. Gravity Systems:
a. Sanitary sewers, Section 33 31 00.
b. Under drains and storm drains, Section 33 41 00.
B. Burial: Comply with Section 33 05 20.
1. Protect ferrous materials with polyethylene sheet that is at least six
(6) mil thick. Tape wrap the sheet around the pipe.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 05 09
STEEL PIPE - LINED AND COATED
PART 1 GENERAL
1.1. SECTION INCLUDES
A. Cement mortar lined and coated steel pipe, couplings, fittings, and joint materials in
sizes four (4) inches through 120 inches.
1.2 REFERENCES
A. ASTM Standards:
A82 Steel Wire, Plain, for Concrete Reinforcement. A283 Low and
Intermediate Tensile Strength Carbon Steel
Plates.
A370 Mechanical Testing of Steel Products.
A569 Steel, Carbon (0.15 Maximum, Percent), Hot-Rolled Sheet and Strip,
Commercial Quality.
A570 Steel, Sheet and Strip, Carbon, Hot-Rolled, Structural Quality.
C33 Concrete Aggregates. C150 Portland
Cement.
B. AWWA Standards:
C200 Steel Water Pipe 6 In. and Larger.
C205 Cement-Mortar Protective Lining and Coating for Steel Water Pipe - 4
In. and Larger - Shop Applied.
C208 Fabricated Steel Water Pipe Fittings.
C303 Reinforced Concrete Pressure Pipe, Steel Cylinder Type, Pre-
Tensioned, for Water and Other Liquids.
1.3 SUBMITTALS
A. Design Summary: Before any fabrication, submit a design summary for each size and
class of pipe and line layout drawings or line schedules that show the location of each
section of pipe and each special fitting to be furnished.
B. Shop Drawings of special fitting and outlets.
1.4 QUALITY ASSURANCE
A. Perform quality assurance tests required by AWWA C303.
1.5 DELIVERY, STORAGE AND HANDLING
A. Attach end covers to pipe stored either in the yard or in the field to prevent drying
out of concrete.
B. Stalls: Remain in place during storage.
C. Gaskets: Store in a cool, well ventilated place and protect from direct sunlight.
PART 2 PRODUCTS
2.1 STEEL CYLINDERS
A. Fabricated from either:
Snowbasin Resort Legend Well House Specifications
1. Hot-rolled Carbon Steel Sheets: Conform to ASTM A570, Grades B, C, D, or E,
or ASTM A569 except that the maximum carbon content may be 0.25 percent
and a minimum yield strength of 33,000 psi.
2. Plates: Conform to ASTM A283, Grade C or D.
B. Seams: Fabricate sheets or plates into cylinders with longitudinal seams. Produce
welds with a tensile strength at least equal to the specified minimum tensile strength
of the sheet or plate. Cut test specimens from the cylinder and test per ASTM A370
when specified.
C. Specified Diameter: The inside diameter of the concrete section.
D. Circumference of Steel Cylinders: Not to deviate from the design value by more than
+3/16 inch for pipe sizes 16 inches and smaller or more than +1/4 inch for larger
sizes.
E. Test Steel Cylinders: Test hydrostatically to a minimum hydrostatic pressure which
develops a fiber stress equal to 75 percent of the specified minimum yield strength of
the steel. Reweld cylinders that show any leakage under test at the points of leakage
and subject them to another hydrostatic test. Continue procedure until completely
watertight under the required test pressure.
2.2 JOINTS
A. General: As indicated using one of the following procedures.
B. Bell and Spigot for Rubber Gasket: Fabricate the bell and spigot ends by either
forming integrally with the steel cylinder or welding steel joint rings to the cylinder.
Make the bell and spigot ends circular in shape and fabricated so that when the pipe
is laid the joint will be self centering with a gasket of sufficient size and cross-section
to seal the joint. The difference in circumferential measurement between the outside
circumference of the spigot and the inside circumference of the bell must not exceed
0.200 inch.
C. Belled Ends for Welding: Form a bell on the cylinder to accommodate the spigot.
Make the spigot stub approximately 1-1/2 inches. Remove weld beads on the
outside of the spigot and the inside of the bell to permit easy entry.
D. Plain Ends for Welding: Make both ends of pipe section plain and remove edge
burrs.
E. Ends for Mechanical Couplings: Make ends of pipe section plain, grooved, or banded.
Grind any weld beads on exterior of pipe flush with the pipe for a sufficient distance
from the ends of the pipe to accommodate the coupling. Prepare grooved or banded
ends to fit the type of mechanical coupling to be used.
2.3 CEMENT MORTAR
A. Cement: Type I or II, ASTM C150.
B. Sand: "Fine aggregate", ASTM C33, except the gradation may be modified to
provide a lining of optimum density.
C. Cement-Mortar Mix: One part cement to not more that three (3) parts of sand by
weight. Control water content to obtain dense, workable, durable mortar. Rebound
may be reclaimed and used as aggregate.
2.4 RUBBER GASKETS
A. Shape: Circular cross-section.
B. Gasket Compounds: Conform to the requirements of AWWA C200 consisting of first-
Snowbasin Resort Legend Well House Specifications
grade natural rubber, synthetic rubber, or a suitable combination thereof. Form and
cure to be dense and homogenous with a smooth surface free from blisters, pits, and
other imperfections.
2.5 INTERIOR LINING
A. Use gage rings at the ends of the pipe to control the spinning thickness. Spin the
lining in the cylinder to obtain nominal thickness as follows:
1. 5/16 inch for pipe sizes four (4) inches through 12 inches.
2. 3/8 inch for pipe sizes 14 inches through 18 inches.
3. 1/2 inch for 20 inches and larger.
4. Other lining thickness, as specified in AWWA C205 or indicated.
B. After mortar has been placed in the cylinder, revolve at a speed that causes the
cement-mortar to level out to a uniform thickness throughout the cylinder. Continue
the spinning until the lining is thoroughly compacted and surplus water removed, and
the finished lining is smooth and uniform throughout.
C. Lining Thickness Tolerance: Not more than 1 percent less or 25 percent more than
the specified nominal thickness.
2.6 EXTERIOR COATING
A. Apply cement mortar exterior coating by mechanical means producing a dense,
uniform finished coating adhering tightly to the pipe. Additional coating thickness
may be specified to resist excessive external loads. Provide a minimum nominal
coating applied over the cylinder as follows.
1. 1/2 inch for pipe sizes four (4) inches through 12 inches.
2. 5/8 inch for pipe sizes 14 inches pipe through 18 inches.
3. 3/4 inch for pipe sizes 20 inches and over.
B. Cement Slurry Coating: One bag of cement to not more than 10 gallons of water
applied concurrent with the coating application to coat the steel assembly surface and
the mortar-coating leading edge.
C. Steel Reinforcement: 14 gage cold-drawn steel wire conforming to ASTM A82,
helically wound and embedded in middle third of the coating.
D. Suitably support the pipe during handing and curing to prevent damage to the lining
coating.
2.7 CURING
A. Moist cure the lining for a minimum period of 24 hours after spinning. This may be
accomplished by tightly sealing the ends of the cylinder with a waterproof membrane
to retain the moisture in the mortar. Steam curing may be used in lieu of or in
combination with moist curing on a time ratio basis of one (1) hour steam curing to
four (4) hours moist curing.
B. Moist cure the completed pipe for six (6) days minimum. Steam curing may be used
in lieu of moist curing.
C. Protect the mortar lining from temperatures below 40 deg F during the application
and curing.
2.8 PIPE LENGTHS
A. 40 feet except where shorter lengths are required for fittings, curves, or closures.
2.9 BENDS AND SPECIFIC FITTINGS
A. Fabricate short radius bends or special fittings such as wyes, tees and crosses from
Snowbasin Resort Legend Well House Specifications
previously tested steel cylinders, AWWA C208. Fabricate bends or special fittings at
least equal in strength to the abutting pipe sections and line and coat with the same
material as the pipeline. Obtain approval of design before fabrication.
B. Test all seams of bends or special fittings, except those seams previously tested as
cylinders. Test seams by the air soap method or by the
dye-check method. Repair any leaks by welding and retest the seam and recoat if
required.
2.10 OUTLETS
A. Build outlets into the wall of the pipe, before testing, for blow-offs, branches, air
valves, access manholes, etc. Provide cast or fabricated steel fittings of suitable
design and securely weld to the cylinder before
being coated. Reinforce the pipe cylinder, as necessary, for the required opening.
Obtain approval of the design of such outlets before fabrication.
PART 3 EXECUTION
3.1 INSTALLATION
A. Assembly: Abide by manufacturer's instructions and Section 33 11 00
requirements for water distribution and transmission. Use the more stringent
provisions if there are any conflicts.
1. Provide a maximum joint deflection on curved alignment by means of
unsymmetrical closure of spigot into bell as per manufacturer's
recommendation but not greater than the following:
a. 3/4 inch for pipes 12 inches through 24 inches.
b. 1 inch for pipes 27 inches through 72 inches.
2. Joints to be grouted inside and outside as per manufacturer's
requirements.
B. Burial: Comply with Section 33 05 20.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 05 20
BACKFILLING TRENCHES
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Backfill materials in trenches and backfilling requirements.
1.2 REFERENCES
A. APWA (Utah) Standards:
Plan 381Trench backfill
Plan 382 Pipe zone backfill
B. ASTM Standards:
D698 Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3
(600 kN-m/m3)).
D1557 Laboratory Compaction Characteristics of Soil using Modified Effort (56,000 ft-lbf/ft3
(2,700 kN-m/m3)).
D2922 Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth).
D4832 Preparation and Testing of Soil-Cement Slurry Test Cylinders.
1.3 DEFINITIONS
A. Bedding: That surface of the excavation or portion of the Pipe Zone below the pipe.
B. Pipe Zone: That zone in a backfilling operation which supports, and surrounds the pipe
barrel, and extends to 1 foot above the top of the pipe barrel.
1.4 SUBMITTALS
A. Submit maximum laboratory dry density and optimum laboratory moisture content for:
1. Subgrade material, and
2. Each type of fill to be used.
B. Submit aggregate batch delivery tickets showing name of material source, serial
number of ticket, date and truck number, name of Supplier, job name and location,
volume or weight. And aggregate classification or Supplier’s identification code.
1.5 QUALITY ASSURANCE
A. Do not change material sources, or aggregate without ENGINEER's knowledge.
B. Reject backfill material that does not comply with requirements in this Section.
C. If requested, submit a quality control inspections and testing report describing source
and field quality control activities performed by CONTRACTOR and Suppliers.
1.6 STORAGE
A. Safely stockpile backfill materials.
Snowbasin Resort Legend Well House Specifications
B. Separate differing materials, prevent mixing, and maintain optimum moisture content of
backfill materials.
1.7 SITE CONDITIONS
A. Do not place, spread, or roll any backfill material over material that is damaged by
water. Remove and replace damaged material at no additional cost to OWNER.
B. Control traffic and erosion. Keep area free of trash and debris. Repair settled, eroded,
and rutted areas.
C. Reshape and compact damaged structural section to required density.
D. Restore any damaged structure to its original strength and condition.
E. Replace contaminated backfill at no additional cost to OWNER.
1.8 SEQUENCING
A. Coordinate backfilling operation with pipeline commissioning, Section 33 08 00.
1.9 ACCEPTANCE
A. General: Native material may be wasted if there is no additional cost to substitute
material acceptable to ENGINEER.
B. Material: For material acceptance refer to:
1. Common fill, Section 31 05 13.
2. Aggregate base course, Section 32 11 23.
3. Cement treated fill, Section 31 05 15.
C. Lift Thickness: One test per lot.
D. Compaction: One test per lot. Verify density using nuclear tests, ASTM D2922.
Compaction standard and Lot sizes as follows:
Table 1: Compaction Standard and Lot Size
Material Proctor Lot Size
Subgrade Standard 200 linear feet
Common Fill Standard 200 linear feet per lift
25 square feet of footing area per lift
Aggregate
base course Modified 200 linear feet per lift
25 square feet of footing area per lift
NOTES
(a) Standard proctor, ASTM D698.
(b) Modified proctor, ASTM D1557.
(c) Lift thickness above pipe zone before compaction, 8 inches.
E. Flowable Fill Strength: Lot size is one (1) day production with sub-lots of 50 cubic
yards or part thereof. Verify strength using cylinders, ASTM D4832.
F. Grade, Cross Slope: Measured at random locations.
Snowbasin Resort Legend Well House Specifications
1.10 WARRANTY
A. Correct any settlement of Trench backfill or structures built over Trench backfill at no
cost to OWNER.
B. Restore structures damaged by settlement at no additional cost to OWNER.
PART 2 PRODUCTS
2.1 BACKFILL MATERIALS
A. Common fill, Section 31 05 13. Granular material, CONTRACTOR’s choice.
B. Aggregate base course, Section 32 11 23. Untreated base course.
C. Cement treated fill, Section 31 05 15. Use a flowable fill so vibration is not required.
D. Slag or bitumen bearing material NOT ALLOWED in trench.
2.2 WATER
A. Make arrangements for sources of water during construction and make arrangements
for delivery of water to site.
B. Comply with local Laws and Regulations at no additional cost to OWNER when
securing water from water utility company.
2.3 GEOTEXTILE FABRIC
A. Section 31 05 19. Use woven or non-woven stabilization-separation fabric. Select
either moderate MARV or high MARV as needed.
2.4 IDENTIFICATION TAPE
A. Permanent, bright colored, continuous printed magnetic plastic tape, intended for
direct burial service; not less than six (6) inches wide by four (4) mils thick. Tape shall
read "CAUTION: BURIED INSTALLATION BELOW". Color as follows.
Red Electric power lines, cables, conduit and lighting cables
Yellow Gas, oil, steam, petroleum or gaseous materials
Orange Communications, alarm, signal, cables or conduits
Blue Potable water
Purple Reclaimed water, irrigation and slurry lines
Green Sewer and storm drain lines
PART 3 EXECUTION
PREPARATION
A. Implement traffic control plan requirements, Section 01 55 26.
B. Identify required line, levels, contours, and datum.
Snowbasin Resort Legend Well House Specifications
C. Stake and flag locations of underground utilities.
D. Verify:
1. Backfill material meets gradation requirements.
2. Foundation walls are braced to support surcharge forces imposed by backfilling
operations, areas to be backfilled are free of debris, snow, ice or water.
3. Trench bottom is not frozen.
E. If ground water is in the intended backfill zone, dewater.
3.2 SUBGRADE
A. Protect subgrade from desiccation, flooding, and freezing.
B. Before backfilling over Subgrade, get ENGINEER’s review of Subgrade surface
preparations.
C. If Subgrade is not readily compactable, get ENGINEER’s permission to stabilize the
subgrade:
1. Excavation for Subgrade stabilization is incidental work, Section 31 23 16.
2. Place geotextile fabric. Place acceptable fill in lifts. Compact.
3.3 PROTECTION
A. During installation or repair, plug end of pipe or fitting except when installing next
section of pipe or fitting.
B. Movement of construction machinery over Work at any stage of construction is solely at
CONTRACTOR’s risk.
3.4 GENERAL BACKFILLING REQUIREMENTS
A. Avoid injuring and displacement of conduit, pipe and structures while compacting soil or
operating equipment next to pipeline.
B. Place geotextile fabrics; Section 31 05 19.
C. Do not damage corrosion protection on pipe.
D. Repair or replace damaged pipe at no additional cost to OWNER.Withdraw sheathing,
shoring, piles, and similar supports as backfilling progresses. Backfill and compact all
holes left by removals.
E. Provide sufficient water quality facilities to protect downstream fish and wildlife, and to
meet State water quality requirements.
F. Water settling of trench backfill is not permitted. "Jetting" of trench backfill is prohibited.
3.5 PIPE ZONE
A. Follow APWA Plan 382 requirements.
B. Maintain uniform foundation along barrel of pipe with sufficient relief for joint
connections.
C. Use backfill materials meeting pipe manufacturer's recommendations. Maximum
backfill particle size is 3/4 inch for plastic pipe.
D. Do not permit free fall of backfill material that may damage pipe, pipe finish, or pipe
alignment.
Snowbasin Resort Legend Well House Specifications
E. Except where piping must remain exposed for tests, fill pipe zone as soon as possible.
3.6 TRENCH ABOVE PIPE ZONE.
A. Follow APWA Plan 381 requirements.
B. Maximum lift thickness before compaction is eight (8) inches.
C. Fill unauthorized excavations with material acceptable to ENGINEER at no additional
cost to OWNER.
D. Do not damage adjacent structures or service lines.
E. Install continuous identification tape directly over buried lines 18 inches below finished
grade.
3.7 MODIFIED BACKFILL LAYER METHOD
A. At discretion of CONTRACTOR, backfill may be placed in thicker layers than indicated
above subject to the following provisions:
1. CONTRACTOR proves the ability of proposed method to achieve specified average
compaction density.
2. ENGINEER, on the basis of test results, approves the system in writing.
B. Should CONTRACTOR find it necessary to change the method or any part of it,
including the source of material, or the rate of placing the material, obtain approval of
ENGINEER, who may require a further trial area.
C. If testing shows a previously approved system is no longer producing the required
degree of compaction, make changes to comply.
D. Where vibration effects are creating environmental problems, make changes to
eliminate problems.
3.8 TOLERANCES
A. Compaction: Ninety-five (95) percent or greater relative to a standard or modified
proctor density, Section 31 23 26.
B. Lift Thickness (before compaction):
1. Eight (8) inches when using riding compaction equipment.
2. Six (6) inches when using hand held compaction equipment.
3. As proven in the modified backfill layer method.
C. Cement Treated Fill: Compressive strength targets are 60 psi in 28 days and 90 psi
maximum in 28 days.
3.9 FIELD QUALITY CONTROL
A. Test trench backfilling until a compaction pattern acceptable to CONTRACTOR and
ENGINEER is achieved. Continue random quality control compaction testing.
3.10 SURFACE FINISHING
A. Provide temporary paved surfaces where trenches pass through roadways, driveway
approaches or sidewalks.
B. Restore paved surfaces, Section 33 05 25.
Snowbasin Resort Legend Well House Specifications
C. Landscapes: Restore landscaping as indicated and as follows where applicable.
1. Section 32 92 00 for turf and grasses.
2. Section 32 93 13 for other ground cover.
D. Repair public and private facilities damaged by CONTRACTOR.
3.11 CLEANING
A. Remove stockpiles from site when work is complete. Grade site to prevent free
standing surface water.
B. Leave borrow areas clean and neat.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 08 00
COMMISSIONING OF WATER UTILITIES
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Tests to be performed for commissioning pressurized and non- pressurized water piping systems.
B. Warning: DO NOT use hydrostatic pressures for air-pressure testing.
1.2 REFERENCES
A. ASTM Standards.
C497 Testing Concrete Pipe, Sections, or Tile
C969 Infiltration and Exfiltration Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines
C1103 Joint Acceptance Testing of Installed Precast Concrete Pipe Sewer Lines
C1214 Test Method for Concrete Pipe Sewerlines by Negative Air Pressure (Vacuum)
F1417 Installation Acceptance of Plastic Non-pressure Sewer Lines Using Low-Pressure Air
F2497 Infiltration and Exfiltration Acceptance Testing of Installed Corrugated High Density Polyethylene Pipelines
B. NASSCO Standards.
PACP Pipe Condition Assessment Using CCTV.
1.3 DEFINITIONS
A. CCTV: Acronym for closed-circuit television.
B. Leakage: The quantity of water required to maintain specified hydrostatic test
pressure after pipeline has been filled with water and air expelled.
C. Non-rigid Pipe: Any pipe that requires bedding and pipe zone backfill material for
sturctural support to prevent distortion that may be caused by dditional backfill
placement.
D. PACP: Acronym for pipeline assessment certification program. This program is
provided by the National Association of Sewer Service Companies (NASSCO).
1.4 SUBMITTALS
A. CCTV Report: Include the following.
1. CCTV personnel are NASSCO PACP certified.
2. NASSCO PACP certified database and electronic worksheets accompany
Snowbasin Resort Legend Well House Specifications
all progress inspection work.
3. All ENGINEER and NASSCO PACP required header information must be
fully and accurately entered on all CCTV reports.
4. Corrections to punch list items are submitted in report form prior to final payment.
B. Commissioning Test Report: Use the commissioning test schedule (Table 3
this section) which identifies tests to be performed for commissioning potable
and non-potable water piping systems. For each test performed, submit the
following information as applicable.
1. Type of test.
2. Project number and date of the report.
3. Size, type, location and length of pipe in test section.
4. Test pressure and time.
5. Written and still image documentation of locations where deflection
deviations, joint gaps, pipe damage, and any other deficiencies are
observed.
6. Statement of whether mandrel was or was not able to pass.
7. Amount of leakage versus allowable.
8. Date of test approval.
9. Signature of test supervisor.
10. Signature of Resident Project Representative witnessing the test.
1.5 PROJECT CONDITIONS
A. CCTV: Run water through subject test system prior to video inspection. Conduct
inspection prior to installation of paved surfaces. ENGINEER to be present during
video inspection.
1. Record vertical and horizontal deviations, joint gaps, cracks, and pipe damage.
2. Video the entire circumference at each joint. Zoom where necessary.
3. Video image must be clear, continuously illuminated, focused, free from roll, static, or other image distortion qualities.
4. Identify the date, pipe reach, slope, upstream and downstream manhole numbers, and manhole to manhole footage.
5. Provide video inspection log as a computerized data report with a map of the
system inspected with appropriate identification labels and still images of
defects discovered in the video.
6. Repeat unsatisfactory inspections at no additional cost to OWNER.
B. Manual inspections are to be done by ENGINEER.
1.6 WARRANTY
A. At the end of the one year correction period repeat any test requested by ENGINEER to verify warranty of pipeline performance.
Snowbasin Resort Legend Well House Specifications
B. OWNER will pay for the cost of additional test inspections if pipe tests meet criteria in this section.
PART 2 PRODUCTS
2.1 TESTING MATERIALS
A. Medium: Water, air.
PART 3 EXECUTION
3.1 CONSTRUCTION EQUIPMENT
A. Leakage Recording Equipment:
1. Supply all equipment and power to perform leakage testing.
2. Secure approval of pressure and vacuum gages.
3. Locate all gages and recording equipment away from affect of sunshine or unsuitable weather conditions.
4. Place, vents, taps and drains for the test. Repair pipeline at completion of test at no additional cost to OWNER.
B. CCTV:
1. Video operator is currently NASSCO PACP certified.
2. Camera is to be crawler mounted meeting the following.
a. Head is in the pipe diameter center with lighting sufficient to produce a clear picture of the entire periphery of the pipe.
b. Pan and tilt to a 90 degree angle with the axis of the pipe.
c. Rotate 360 degrees.
d. Crawl at a speed no greater than 30 feet per minute.
3. For pipe lateral replacements constructed by bursting, operate video camera in presence of Project Representative.
C. Mandrel:
1. Diameter whether it is fixed or variable size must be verified with a proving ring or other method according to manufacturer's guideline.
2. Contains at least nine equally spaced runners.
3. Length not less than the diameter.
4. Pulled (not pushed) through pipe.
5. Recommend an alternate method of measurement if mandrel testing would cause damage to internal pipe coating.
3.2 PREPARATION
A. Notify ENGINEER 48 hours in advance of test.
B. Carry out selected tests as pipeline construction progresses to ensure
Snowbasin Resort Legend Well House Specifications
construction methods are producing satisfactory results.
C. Remove debris, sediment and other material from installed pipe before testing.
Do not discharge or flush sand, gravel, concrete, debris or other foreign material
into any existing pipeline system. Flushing with clean water only will be allowed
but with minimal flows to eliminate exceeding capacities of receiving systems.
Flushing into existing pressurized water systems is NOT ALLOWED.
3.3 GRADE AND ALIGNMENT TEST
A. Tolerances for pipe placement are as follows.
Table 1 - Grade and Alignment
Design Grade Tolerances
Grade (a) Alignment
Greater than 1% 1/2 inch in 10 feet 1" from true line
0.5 to 1% 1/4 inch in 10 feet 1" from true line
Less than 0.5% 1/4 inch in 100 feet 1" from true line
NOTES
(a) Grade does not result in a level or reverse sloping invert. Standing water is evidence of non-compliance.
(b) For culverts, increase tolerances by 50 percent.
3.4 JOINT TESTS
A. Gap: Evaluate each pipe joint with a gap exceeding allowance in the following table. Recommend appropriate corrective action according to manufacturer's recommendations.
Table 2 - Joint Gap
Pipe Diameter, inches Allowance, maximum
Less than 12 (a)
12 - 36 0.75 inch
42 - 48 1.00 inch
54 - 90 1.25 inches
96 - 144 1.75 inches
NOTES
(a) In pipes less than 12 inches diameter, allowable separation is equal to or less than amount permitted by manufacturer.
B. Invert Elevation: Variation in invert elevation where pipe sections join shall not exceed 1/64 inch per inch of pipe diameter, or 1/4 inch maximum.
Snowbasin Resort Legend Well House Specifications
3.5 INFILTRATION TEST
A. Tolerance: 200 gallons per inch, per mile, per day maximum (EPA's standard for
sanitary sewers is specified). If ground water table is less than two (2) feet above
the crown of the pipe the infiltration test is not required.
B. Concrete Pipe: ASTM C969.
C. Plastic Pipe: ASTM F2497.
3.6 EXFILTRATION TEST
A. Preparation: Air test or hydrostatic test is CONTRACTOR's choice.
B. Air Test:
1. Plastic Pipe: ASTM F1417.
a. For pipe up to 30 inches diameter, pressure drop is 0.5 psi.
b. For pipe larger than 30 inches diameter, isolated joint test is
3.5 psi. Maximum pressure drop is 1.0 psi in 5 seconds.
2. Concrete Pipe:
a. ASTM C1214 for concrete pipe 4" to 24" diameter.
b. ASTM C1103 for concrete pipe 27" and larger.
C. Hydrostatic Test: Provide air release taps at pipeline’s highest elevations and
expel all air before the test. Insert permanent plugs after test has been completed.
1. Plastic Pipe: ASTM F2497.
2. Concrete Pipe: ASTM C497. Abide by Section 3 and Section 16 in the ASTM standard and applicable recommendations of manufacturer.
C. Locate and repair leakage and retest until leakage rate is less than allowable.
D. Repair any noticeable leakage even if total leakage is less than allowable.
3.7 DISTORTION TEST
A. Concrete Pipe: Maximum crack width is 0.1 inch. Provide photographs of all cracks for possible mitigation or monitoring purposes.
1. Record location of cracks smaller than 0.1 inch. ENGINEER will evaluate crack at end of one year correction period.
2. For cracks exceeding 0.01 inch, measure crack width and provide
photographs for monitoring purposes during subsequent inspections.
B. Plastic and Other Pipe: Maximum internal diameter reduction in any plane
measured full length of installation prior to pavement placement, and at the end of
the correction period is as follows.
1. Polyvinyl chloride pipe, 7.5 percent.
2. High density polyethylene pipe, 5 percent.
3. Polypropylene pipe, 5 percent.
4. Ductile iron pipe, 3 percent.
5. Corrugated metal pipe, 7.5 percent.
Snowbasin Resort Legend Well House Specifications
3.8 OBSTRUCTION TEST
A. Maximum protuberance is 1 inch.
3.9 TRACER WIRE CONTINUITY TEST
A. Test all tracer wire sections for continuity.
3.10 COMMISSIONING TEST SCHEDULE
A. The following table identifies required commissioning tests.
Table 3 - Commissioning Test Schedule
Ali
gnment
Gr
ade
Jo
int
Inf
f
i
l
t
rati
o
n Exfi
l
t
ratio
n Distorti
on
Obstructi
o
n Disin
f
ec
ti
o
n Trace
r
Wi
re
Gravity Irrigation
Landscaping
(a) ●
Pressure Irrigation
Landscaping
(a,b,c) ● ●
Sanitary Sewers (b,c) ● ● ● ● ● ● ●
Sub-drains ● ● ●
Storm Drains (c,d) ● ● ● ● ● ● ●
Potable Water (c,d,e) ● ● ● ●
Non-potable water (d) ● ● ●
NOTES
(a) All lateral pipes drain.
(b) Operational testing: Landscaping systems.
• Perform operational testing after hydrostatic
test is complete, backfill is in place, and
sprinkler heads are adjusted to final
coverage.
• Demonstrate system meets coverage requirements and automatic controls function properly.
• Coverage requirements are based on operation
of one (1) circuit at a time.
(c) Exfiltration test for pressure pipeline systems.
(d) Exfiltration when requested by ENGINEER or
specified elsewhere.
(e) Legally dispose disinfection and flushing water and ensure no damage to the environment.
3.11 REPAIR
A. Repair pipeline system at no additional cost to OWNER until it passes commissioning tests.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 11 00
WATER DISTRIBUTION AND TRANSMISSION
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Installation of a pressurized water pipe system.
B. Refer to Section 33 31 00 if the system is a non-pressure sanitary sewer.
C. Refer to Section 33 41 00 if the system is a non-pressure storm drain, sub-drain,
irrigation system, etc.
1.2 REFERENCES
A. American Concrete Pipe Association (ACPA) Publications: Concrete
Pipe Handbook.
B. APWA (Utah) Standards:
Plan 255 Bituminous pavement T-patch.
Plan 256 Concrete pavement patch.
Plan 381 Trench backfill.
Plan 382 Pipe zone backfill.
Plan 521 3/4” and 1” meter.
Plan 522 1-1/2” and 2” meter.
Plan 541 Water service line.
Plan 542 Water service line loop.
Plan 543 Watermain loop.
Plan 551 3/4” and 1” service taps.
Plan 552 1-1/2” and 2” service taps.
Plan 561 Direct bearing thrust block.
Plan 562 Tie-down trust restraints.
Plan 574 Cover collar for water valve boxes.
C. AWWA Standards:
C600 Installation of Ductile-Iron Water Mains and Their Appurtenances.
C605 Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe
and Fittings for Water.
C800 Underground Service Line Valves and Fittings. C901
Polyethylene (PE) Pressure Pipe and Tubing, 1/2 in.
Through 3 in., for Water Service.
M11 Manual for Steel Pipe - Design and Installation.
D. Copper Development Association (CDA) Standards.
E. Applicable water company requirements standards.
Snowbasin Resort Legend Well House Specifications
1.3 PERFORMANCE REQUIREMENTS
A. Depth of Cover:
1. Minimum as indicated in local building code from top of pipe to ground surface.
72 inches maximum unless ENGINEER authorizes otherwise.
2. If less cover, provide additional protection to withstand frost and external
loads.
B. Remove any section of pipe already placed that is found to be defective or
damaged. Relay or replace without additional cost to OWNER.
1.4 SUBMITTALS
A. Product data: Submit manufacturer’s technical product data and installation
instructions.
B. Commissioning: Provide Section 33 08 00 submittals.
C. Record Documents, Section 01 78 39: Include details of underground structures,
connections, thrust blocks and anchors. Show interface and spatial relationship
between piping and adjacent structures.
D. Operating and Maintenance: Submit data, Section 01 78 23. Include maintenance
data, parts list, product data and Shop drawings.
1.5 SITE CONDITIONS
A. Minimize neighborhood traffic interruptions. Barricade stockpiles.
B. Secure acceptance of pipeline lateral tie-in work.
C. Repair public and private facilities damaged by CONTRACTOR.
D. Do not operate any currently active water valve until its owner and water company's
permission is secured.
1.6 ACCEPTANCE
A. Each component in the distribution and transmission system must pass applicable
commissioning requirements in Section 33 08 00.
PART 2 PRODUCTS
2.1 PIPES AND FITTINGS
A. Provide piping materials and factory fabricated piping products of sizes, types,
pressure ratings, and capacities indicated. Use only NSF approved products in
drinking water systems. All such products shall be appropriately stamped with the
NSF logo.
B. Where not indicated, provide proper selection as determined by installer and
acceptable to ENGINEER to comply with installation requirements.
C. Provide sizes and types of equipment connections for fittings of material that
matches pipe material used in the piping system. Where more than one type of
material or product Option is indicated, selection is installer's choice.
D. Provide pipe fittings and accessories of same material and weight or class as
pipe, with joining method indicated or recommended by manufacturer.
Snowbasin Resort Legend Well House Specifications
2.2 VALVES
A. Section 33 12 16.
2.3 VALVE BOX
A. Buried Valves in Traffic Areas: Cast iron two (2) piece slip sleeve type, 5-1/4 inch
shaft, with a drop lid.
B. Buried Valves in Non-Traffic Areas: Cast iron two (2) piece screw adjustable
sleeve of height required for installation.
C. Markings: Cast appropriate utility lettering on cover.
2.4 VALVE CHAMBER
A. Basin: Class 4000 concrete floor and walls.
B. Steps: Plastic, cast into sidewalls greater than four (4) feet deep.
C. Top: Flat slab class 4000 concrete.
D. Frame and Cover: Scoriated asphalt coated, heavy duty ductile iron conforming to
Section 05 56 00 with flat top design and appropriate utility lettering. Shape and
size required.
2.5 MORTAR, GROUT, AND CONCRETE
A. Mortar: Portland cement, Section 04 05 16.
B. Grout: Portland cement, Section 03 61 00.
C. Concrete:
1. Cast-in-place: Class 4000, Section 03 30 04.
2. Precast: Class 5000, Section 03 40 00.
2.6 TAPPING SADDLES
A. Bronze alloy or stainless steel saddles with stainless steel straps (double straps on
pipes over 12 inches diameter).
B. Straight threads. Tappered threads not allowed.
C. Rated working pressure, 300 psi minimum.
D. Neoprene Buna N gaskets.
2.7 SERVICE CONNECTION
A. Taps: Saddle clamp or direct type. Provide plastic spacers or nipples to separate
non-similar metals.
B. Service Line:
1. Copper Pipe: Type K, Section 33 05 03 with 200 psi compression fittings
according to AWWA C800.
2. Polyethylene Pipe: AWWA C901 with 200 psi compression fittings, and
ratings according to AWWA C800.
Snowbasin Resort Legend Well House Specifications
2.8 ACCESSORIES
A. Bolts, Nuts, Washers: Steel, Section 05 05 23.
B. Anchorages: Provide anchorages for tees, wyes, crosses, plugs, caps, bends, valves,
and hydrants. After installation, apply full coat of asphalt or other acceptable
corrosion-retarding material to surfaces of ferrous anchorages.
C. Corporation Stops: All bronze, straight threads, full port, ball valve.
D. Hydrant and Valve: Dry barrel, Section 33 12 19.
E. Water Meter and Valve: Section 33 12 19.
F. Grease: Non-oxide food grade required where in contact with potable water. Non-
oxide poly-fm for all exposed buried metal surfaces for bolts, nuts, washers,
restraints, etc.
G. Polyethylene Sheet: Six (6) mil thick minimum.
H. Joint Restraints: Acceptable to ENGINEER prior to installation.
PART 3 EXECUTION
3.1 EXAMINATION
A. Verify trench excavation is ready to receive work, and dimensions, and elevations
are as required.
B. Commencing installation means acceptance of existing conditions.
3.2 PREPARATION
A. Excavation, Section 31 23 16. Hand trim to required elevations. Correct over
excavations.
B. Remove stones or other hard matter that manufacturer stipulates may damage pipe
during embedment or impede backfilling or compaction.
C. Examine areas and conditions under which materials and products are to be installed.
Do not proceed with system installation until unsatisfactory conditions have been
corrected in manner acceptable to system installer.
D. Clearly identify and promptly set aside defective or damaged pipe.
E. Use pipe cutting tool acceptable to pipe manufacturer.
3.3 LAYOUT
A. Comply with Utah administrative rules R309-550. As a minimum locate potable water
pipe at least 18 inches vertical and 10 feet horizontal edge to edge between water
and sewer lines. Place water lines above sewer line.
B. Where potable water pipe crosses under gravity-flow sewer lines, fully encase sewer
pipe in concrete for a distance at least 10 feet each side of the crossing:
1. Do not locate any joint in the water line within 36 inches of the crossing.
2. Encase water line if it is within 24 inches of a sewer force main or a sewer
inverted syphon.
3. Encase sewer main joints in concrete if joints are horizontally closer than 36
inches to the water line.
C. Do not put potable water lines in the same trench with sewer lines, storm drains or
Snowbasin Resort Legend Well House Specifications
electric wires.
3.4 INSTALLATION - PIPE AND FITTING
A. General:
1. Seal each open end of pipeline at end of day’s work.
2. Grease all bolts and nuts then apply polyethylene sheet and tape wrap.
B. Steel Pipe: AWWA M11.
C. Ductile Iron Pipe: AWWA C600.
D. Copper Tube: CDA "Copper Tube Handbook".
E. Polyethylene Pipe: For three (3) inches and smaller pipe follow AWWA C901. Install
all other sizes per manufacturer's installation instructions.
F. Polyvinyl Chloride Pipe: AWWA C605.
G. Concrete Pipe: ACPA "Concrete Pipe Handbook".
H. Wedges: Install metal wedges on metal pipe systems. Grease and plastic wrap
exposed metal wedges.
3.5 INSTALLATION – CONCRETE THRUST BLOCK
A. APWA Plan 561 or 562.
B. Do not make hydrostatic tests of Section 33 08 00 until thrust block concrete has
cured for at least five (5) days.
C. Provide thrust blocks on all plugs, caps, tees, hydrants and vertical or horizontal
elbows.
D. Provide stainless steel or epoxy coated steel tie rods and clamps or shackles to
restrain thrust.
E. Unless indicated otherwise or directed by ENGINEER, place base and bearing sides
of thrust blocking directly against undisturbed earth.
F. Sides of thrust blocking not subject to thrust may be placed against forms. Place
thrust blocking so joint fittings will be accessible for repair.
3.6 INSTALLATION - VALVE AND VALVE BOX
A. Valves:
1. Ensure all parts are in working order.
2. Set location of valves outside of sidewalk limits, driveway approach and other
pedestrian or vehicular interference.
3. Install plumb with stem pointing up.
4. Grease all exposed bolts and nuts then apply polyethylene sheet and tape wrap.
B. Air Relief Valves:
1. At high points in water mains where air can accumulate, air may be removed by
means of hydrants or air relief valves.
2. DO NOT use automatic air relief valves where flooding may occur.
C. Valve Box:
1. Set over valve nut so operator's key is plumb with clearance in valve box when
Snowbasin Resort Legend Well House Specifications
opening and closing the valve. Riser must NOT rest on valve or pipe system.
2. Adjust riser to finish grade and clean all dirt or foreign material out of riser.
3. Install concrete cover collar in bituminous paved surface APWA Plan 574.
3.7 INSTALLATION – JOINT RESTRAINTS
A. Without Thrust Blocks: Install joint restraints with all valves for the distance
acceptable to the ENGINEER.
B. With Thrust Blocks: Install joint restraints for the distance approved by the
ENGINEER where concrete block design exceeds three (3) cubic yards, for vertical
bends, where soil is disturbed, or where undisturbed soil bearing capacity is less than
1000 pounds per square foot.
3.8 INSTALLATION – TAPS
A. APWA Plan 551 or 552.
B. Apply for and pay for applicable permits from water company for size and location of
tap to water main. Comply with all connection requirements of water company.
C. Make service taps with a tapping machine acceptable to water company. Use teflon
tape on all taps unless indicated otherwise.
D. Minimum distance between taps is 24 inches, with a five (5) degree stagger. Do not
make service taps within 24 inches of the end of pipe. Install taps at 60 degrees
from vertical, or authorized by ENGINEER.
E. Service saddles are required on all taps except, 3/4 inch or 1 inch taps to new ductile
iron pipe
F. Grease all exposed bolts and nuts then apply six (6) mil thick polyethylene
sheet and tape wrap.
3.9 INSTALLATION – SERVICE LINE
A. Replacing Existing Water Service Line: APWA Plan 541.
1. Follow AWWA C800, Utah drinking water Rules and Regulations and
International Building Code requirements.
2. When replacing water service lines, replace non-copper pipe with:
a. Type K copper pipe, Section 33 05 03, or
b. Polyethylene pipe, AWWA C901
3. Minimum pipe diameter 3/4 inch, maximum 3 inches.
4. Distance from nearest joint or existing tap is 24 inches minimum unless a greater
distance is required by pipe manufacturer.
B. Looping Existing Water Service: APWA Plan 542.
1. Minimum pipe diameter is one (1) inch.
2. Use liquid nitrogen to spot freeze active service lines. Pinching tools used to
close active service lines may be used only if allowed in writing by ENGINEER.
3. Soldered joints or connections not allowed.
4. For copper to iron connections use a brass pack joint compression coupling
with joint locking device.
Snowbasin Resort Legend Well House Specifications
5. For copper-to-copper connections use a brass compression fittings. Flared
end fittings are not allowed.
C. Meter box: APWA Plan 521 or 522. Install meter box back of curb, outside of
sidewalk, outside of driveway approaches, or other vehicular or pedestrian
interference.
3.10 INSTALLATION – WATER MAIN LOOP (SYPHON)
A. APWA Plan 543.
B. Existing water mains may not match standard size. Excavate to obtain actual
pipe diameter and match size.
C. Do not shutdown pipeline until couplings and fittings are on site. Coordinate
shutdown with water company.
D. Connections to steel or transite pipe require transition couplings or sleeves
with transition gaskets.
E. Grease all exposed bolts and nuts then apply six (6) mil thick
polyethylene sheet and tape wrap.
F. Provide thrust blocks except where joints are welded. Follow details shown on
drawings.
3.11 DISINFECTION
A. Section 33 13 00.
B. After disinfection, legally dispose of disinfection water.
3.12 BACKFILLING
A. Before backfilling secure ENGINEER’s acceptance of brass wedge
installations and concrete thrust block installations.
B. Trenches and Pot-holes: Follow requirements in Section 33 05 20 and the
following Standard Plans.
1. APWA Plan 382 for the pipe zone.
2. APWA Plan 381 for the trench backfill.
C. Landscapes and Structural Backfill: Follow Section 31 23 23
requirements.
3.13 COMMISSIONING
A. Before surface finishing, commission pipeline per Section 33 08 00. Provide sizes
and types of equipment connections and fittings that match pipe materials when
pressure testing system.
B. If paved surfaces must be kept open prior to commissioning, provide temporary
paved surfaces.
3.14 SURFACE FINISHING
A. Roadway Trenches and Patches: Follow requirements in Section 33 05 25 and in
the following Standard Plans:
1. APWA Plan 255 for bituminous concrete T-patch.
Snowbasin Resort Legend Well House Specifications
2. APWA Plan 256 for concrete pavement patch.
B. Landscapes: Restore landscaping as indicated and as follows where
applicable.
1. Section 32 92 00 for turf and grasses.
2. Section 32 93 13 for other ground cover.
C. Repair public and private facilities damaged by CONTRACTOR.
3.15 CLEANING
A, Remove debris, concrete, or other extraneous material that accumulates in
existing piping or structures.
B. Clean all pipelines after testing. Do not flush sand, gravel, concrete, debris or other
materials into existing piping systems.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 12 16
WATER VALVES
PART 1 GENERAL
1.1. SECTION INCLUDES
A. Gate, butterfly, plug, check, pressure reducing, pressure relief, control valves and their installation.
1.2 REFERENCES
A. AWWA Standards:
C111 Rubber-Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and Fittings.
C504 Rubber-Seated Butterfly Valves.
C508 Swing-Check Valves for Waterworks Service, 2 In.
Through 24 In. NPS.
C509 Resilient-Seated Gate Valves for Water and Sewerage Systems.
C550 Protective Interior Coatings for Valves and Hydrants. C600
Installation of Ductile-Iron Water Mains and Their Appurtenances.
1.3 SUBMITTALS
A. Provide technical information for evaluating quality of valve. As a minimum include
dimensions, weights, materials lists and operation charts.
PART 2 PRODUCTS
2.1 VALVES - GENERAL
A. Underground:
1. Less than three (3) inches: Screwed ends.
2. 3 inches and larger: Flanged or mechanical joint ends. Non-rising stem. Two
inches square operating nut. Low alloy steel bolts, AWWA C111.
B. Submerged or Above Sewage or Water:
1. Valve body bolts per manufacturer’s recommendations.
2. For joining valve to piping system use stainless steel nuts and bolts, Section 05 05 23.
C. Below an Operating Deck: Provide shaft extension from the valve to deck level.
D. Above Ground: Non-rising stems equipped with a hand wheel.
E. Manually Operated Valves Over six (6) feet Above Operating Level: Provide chain operated handles.
F. Clearance: Install so handles clear all obstruction when moved from open to closed.
G. Rated Working Pressure: 150 psi if not indicated.
H. Coating: Interior, AWWA C550. Exterior per manufacturer’s recommendation.
Snowbasin Resort Legend Well House Specifications
2.2 GATE VALVES
A. AWWA C509.
B. 3 inches through 48 inches, cast iron body, bronze mounted, non-rising stem with "O" ring seals.
C. Open counterclockwise.
2.3 BUTTERFLY VALVES
A. AWWA C504.
B. 3 inches through 48 inches, cast iron body, bronze mounted.
C. Short body if disc will not interfere with adjacent fittings or long body at CONTRACTOR's option.
D. Wafer Valves: Subject to ENGINEER’s approval.
2.4 ECCENTRIC PLUG VALVES
A. Material: Cast iron body, bronze mounted, non-lubricated, eccentric, quarter-turn type with resilient face plugs, ductile iron discs with upper and lower shafts integral.
B. Markings: Indicate open and close position.
C. Port Areas: At least 82 percent of full pipe area.
D. Resilient Seat Seals: Buna N, field replaceable.
2.5 CHECK VALVES
A. AWWA C508.
B. Less than three (3) inches: Y-pattern, bronze, regrinding, swing check valve, 200 psi working pressure.
C. 3 inches and larger: Iron body, bronze mounted, swing valves with stainless steel
hinge pins and outside weight and lever if not indicated otherwise.
2.6 PRESSURE REDUCING VALVES - SERVICE LINE
A. Operation: Capable of reducing a varying higher upstream pressure to an adjustable constant lower downstream pressure.
B. Spring and nylon reinforced diaphragm type construction.
C. Equip with Y-strainer upstream of valve.
2.7 PRESSURE REDUCING VALVES - MAIN LINE
A. Operation: Capable of maintaining an adjustable constant downstream pressure regardless of upstream pressure.
B. Type: Hydraulically operated using a direct-acting, spring-loaded, normally open, pilot valve controlled diaphragm:
1. Single removable seat and a resilient disc. No "O" ring type discs permitted. No
external packing glands permitted. No pistons operating main valve or pilot
controls permitted.
2. Y-strainers on pilot controls, variable closing and opening speed controls and a valve position indicator.
C. Rating: 250 psi working pressure.
D. Connection: Flanged.
E. Pressure Gage: Upstream and downstream of valve capable of accurately
Snowbasin Resort Legend Well House Specifications
measuring system pressures.
2.8 PRESSURE RELIEF VALVES
A. Operation: Maintain a constant upstream pressure by passing or relieving excess pressure.
B. Closed Valves: Drip-tight.
C. Type: Hydraulically operated, pilot control using a diaphragm with a single removable seat and resilient disc.
D. Pilot Controls: Direct acting, adjustable between 20 and 200 psi, spring- loaded diaphragm valve.
E. Rating: 250 psi working pressure.
F. Connection: Flanged.
2.9 CONTROL VALVE
A. Globe: Diaphragm actuated, single seated, composition disc, hydraulically operated.
B. Pilot Controls: Externally mounted, four-way, solenoid pilot valve with self cleaning strainers and diaphragm type check valves:
1. Equipped with a limit switch for pump control.
2. Equipped with a built-in lift check valve to prevent flow reversal.
E. Rating: 250 psi working pressure.
F. Connection: Flanged.
G. Solenoids and Limit Switch: Supplied with operating voltage indicated.
PART 3 EXECUTION
3.1 INSTALLATION
A. Flush all lines before valve installation.
B. In ductile iron water mains, AWWA C600.
C. Install butterfly valve shafts vertical in vault boxes and horizontal otherwise.
END OF SECTION
Snowbasin Resort Legend Well House Specifications
SECTION 33 13 00
DISINFECTION
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Disinfection of potable water system.
B. Test and report results.
1.2 REFERENCES
A. AWWA Standards:
A100 Water Wells. B300 Hypochlorites.
B301 Liquid Chlorine.
C651 Disinfecting Water Mains.
C652 Disinfection of Water-Storage Facilities.
B. State of Utah Standards:
Public Drinking Water Regulations, Part 2, Section 12.
1.3 DEFINITIONS
A. Disinfectant Residual: The quantity of disinfectant in treated water.
B. ppm: Parts per million.
1.4 SUBMITTALS
A. CONTRACTOR's evidence of experience in disinfection.
B. Bacteriological laboratory's certification.
C. Disinfection Report: Three (3) copies containing:
1. Date issued.
2. Project name and location.
3. Treatment contractor's name, address and phone number.
4. Type and form of disinfectant used.
5. Time and date of disinfectant injection started.
6. Time and date of disinfectant injection completed.
7. Test locations.
8. Initial and follow-up disinfectant residuals in ppm for each outlet tested.
9. Time and date of flushing start.
10. Time and date of flushing completion.
11. Disinfectant residual after flushing in ppm for each outlet tested.
12. Flush water disposal location and acceptance by local agency.
Snowbasin Resort Legend Well House Specifications
D. Bacteriological Report: Three (3) copies including:
1. Date issued.
2. Project name and location.
3. Laboratory's name, certification number, address, and phone number.
4. Time and date of water sample collection.
5. Name of person collecting samples.
6. Test locations.
7. Time and date of laboratory test start.
8. Coliform bacteria test results for each outlet tested.
9. Certification that water conforms or fails to conform to bacterial standards of State of Utah public drinking water regulations.
10. Bacteriologist's signature.
1.5 QUALITY ASSURANCE
A. Bacteriological Laboratory: Certified by State of Utah if laboratory is other than OWNER's laboratory.
1.6 PRODUCT HANDLING
A. Store and protect disinfectant in accordance with manufacturer's recommendations
to protect against damage or contamination. Do not use unsuitable disinfectant.
B. Follow all instruction labeling for safe handling and storage of disinfectant materials.
1.7 REGULATORY REQUIREMENTS
A. Conform to State of Utah public drinking water regulations.
PART 2 PRODUCTS
2.1 DISINFECTANT
A. AWWA B301. Liquid chlorine 99.5 percent pure by volume.
B. AWWA B300. Sodium hypochlorite not less than 100 grams per liter available chlorine.
C. AWWA B300. Calcium hypochlorite 65 to 70 percent available chlorine by weight in granular form.
D. Powder, tablet, or gas according to manufacturer's specification.
2.2 ALKALI
A. Caustic soda or soda ash.
2.3 ACID
A. Hydrochloric (muriatic).
Snowbasin Resort Legend Well House Specifications
PART 3 EXECUTION
3.1 PREPARATION
A. Provide necessary signs, barricades, and notices to prevent accidental exposure to disinfecting materials, consuming disinfecting water, or disturbing system being disinfected.
B. Make sure potable water system is complete, clean, and that the system to be disinfected is not connected to an existing system.
3.2 DISINFECTION OF WATER LINES
A. Use one method defined under AWWA C651 that is acceptable to ENGINEER.
B. After pressure testing per Section 33 08 00, flush system through hydrants or if a hydrant does not exist, install a tap of sufficient size to provide 2.5 feet per second flushing velocity in the line.
C. Starting at outlet closest to water source, bleed water from each outlet until chlorine
residual reaches outlet. Repeat process at each outlet throughout system.
D. Collect a bacteriological water sample at end of line to be tested. If sample fails
bacteriological test, flush system and retest. Continue flushing and retesting until
a good sample is obtained.
E. If flushing does not produce a passing bacteriological test disperse disinfectant throughout system to obtain 10 to 25 ppm of free chlorine residual.
F. Flush the chlorinated water from the main until chlorine measurements show
concentration in the water leaving the main is no higher than that generally prevailing
in the system or is acceptable for domestic use.
G. After a passing bacteriological test sample is obtained, let the system relax for 24
hours. Flush and collect a subsequent bacteriological sample for testing. If the
subsequent test passes then water line is acceptable.
3.3 DISINFECTION OF CULINARY WELLS
A. Use one method defined under AWWA A100 that is acceptable to ENGINEER.
B. Do not start disinfection until well is thoroughly cleaned.
C. Use a disinfecting solution containing a minimum of 50 ppm residual chlorine.
D. Flush system after disinfection.
3.4 DISINFECTION OF WATER STORAGE RESERVOIRS
A. Use one method defined under AWWA C652 that is acceptable to ENGINEER.
B. Do not start disinfection until water storage tank is thoroughly cleaned.
C. Provide and use necessary safety equipment for workers in contact with disinfectant or gasses.
D. Flush system after disinfection.
3.5 FIELD QUALITY CONTROL
A. Bacteriological Test:
1. Collect samples for testing no sooner than 16 hours after system flushing.
2. Analyze water samples per State of Utah requirements.
3. If bacteriological test proves water quality to be unacceptable, repeat system treatment.
Snowbasin Resort Legend Well House Specifications
4. Do not place water systems into service until a passing bacteriological test is
made. Provide a copy of the passing test to ENGINEER.
B. Disposal of Disinfectant:
1. Legally dispose of disinfecting water and ensure no chlorine buildup or damage to the environment.
END OF SECTION