Loading...
HomeMy WebLinkAboutDRC-2011-007451_6 - 0901a0688027e864ATTACHMENT C COST ESTIMATES FOR RECLAMATION OF WHITE MESA FACILITY IN BLANDING, UTAH Cost Summary WHITE MESA MILL RECLAMATION COST ESTIMATE September 2011 Revision 5.0 Mill Decommissioning $1,973,302 Cell 1 $1,565,949 Cell 2 $1,266,066 Cell 3 $1,334,075 Cell 4A $1,499,804 Cell 4B $1,343,529 Miscellaneous $3,637,667 Subtotal Direct Costs $12,620,391 Profit Allowance 10.00% $1,262,039 Contingency 15.00% $1,893,059 Licensing & Bonding 2.00% $252,408 UDEQ Contract Administration 4.00% $504,816 Contractors Equipment Floater $82,250 Automobile and General Liability Insurance $284,600 Long Term Care Fund $809,376 Total Reclamation $17,708,939 Revised Bond Amount $17,708,939 9/28/2011 - 8:38 AM - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Mill Decommissioning MILL DECOMMISSIONING MILL DECOMMISSIONING Mill Building Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 640 $10,736 Laborers hrs $12.51 320 $4,002 Small Tools hrs $1.35 960 $1,296 Cat 770 Haul Truck hrs $95.11 640 $60,872 Truck Drivers hrs $18.16 640 $11,623 Cat 988 Loader hrs $134.11 160 $21,458 Cat 988 Loader Operator hrs $17.21 160 $2,754 Cat 365 Excavator hrs $130.25 160 $20,840 Cat 365 Excavator Operator hrs $20.65 160 $3,304 PC 300 w/metal Shears hrs $147.18 160 $23,548 PC 300 Operator hrs $20.65 160 $3,304 60 Ton Crane hrs $103.61 160 $16,577 60 Ton Crane Operator hrs $15.76 160 $2,522 30 Ton Crane hrs $65.24 80 $5,219 30 Ton Crane Operator hrs $15.76 80 $1,261 Equipment Maintenance (Butler) hrs $18.46 1,360 $25,102 Concrete Removal sf $3.30 37,500 $123,750 Total Mill Building Demolition $338,170 Ore Feed Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 64 $1,074 Laborers hrs $12.51 32 $400 Small Tools hrs $1.35 96 $130 Cat 770 Haul Truck hrs $95.11 64 $6,087 Truck Drivers hrs $18.16 64 $1,162 Cat 988 Loader hrs $134.11 16 $2,146 Cat 988 Loader Operator hrs $17.21 16 $275 Cat 365 Excavator hrs $130.25 16 $2,084 Cat 365 Excavator Operator hrs $20.65 16 $330 PC 300 w/metal Shears hrs $147.18 16 $2,355 PC 300 Operator hrs $20.65 16 $330 30 Ton Crane hrs $65.24 0 $0 30 Ton Crane Operator hrs $15.76 0 $0 Equipment Maintenance (Butler) hrs $18.46 112 $2,067 Total Ore Feed Demolition $18,441 SX Building Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 320 $5,368 Laborers hrs $12.51 160 $2,001 Small Tools hrs $1.35 480 $648 Cat 770 Haul Truck hrs $95.11 320 $30,436 Truck Drivers hrs $18.16 320 $5,812 Cat 988 Loader hrs $134.11 80 $10,729 Cat 988 Loader Operator hrs $17.21 80 $1,377 Cat 365 Excavator hrs $130.25 80 $10,420 Cat 365 Excavator Operator hrs $20.65 80 $1,652 PC 300 w/metal Shears hrs $147.18 80 $11,774 PC 300 Operator hrs $20.65 80 $1,652 60 Ton Crane hrs $103.61 0 $0 60 Ton Crane Operator hrs $15.76 0 $0 30 Ton Crane hrs $65.24 0 $0 30 Ton Crane Operator hrs $15.76 0 $0 Equipment Maintenance (Butler) hrs $18.46 560 $10,336 Concrete Removal sf $3.30 55,970 $184,701 Total SX Building Demolition $276,906 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING CCD Circuit Removal Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 120 $2,013 Laborers hrs $12.51 60 $750 Small Tools hrs $1.35 180 $243 Cat 770 Haul Truck hrs $95.11 120 $11,414 Truck Drivers hrs $18.16 120 $2,179 Cat 988 Loader hrs $134.11 30 $4,023 Cat 988 Loader Operator hrs $17.21 30 $516 Cat 365 Excavator hrs $130.25 30 $3,908 Cat 365 Excavator Operator hrs $20.65 30 $620 PC 300 w/metal Shears hrs $147.18 30 $4,415 PC 300 Operator hrs $20.65 30 $620 60 Ton Crane hrs $103.61 30 $3,108 60 Ton Crane Operator hrs $15.76 30 $473 30 Ton Crane hrs $65.24 15 $979 30 Ton Crane Operator hrs $15.76 15 $236 Equipment Maintenance (Butler) hrs $18.46 255 $4,707 Concrete Removal sf $3.30 15,000 $49,500 Total CCD Circuit Removal $89,704 Sample Plant Removal Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 32 $537 Laborers hrs $12.51 16 $200 Small Tools hrs $1.35 48 $65 Cat 770 Haul Truck hrs $95.11 32 $3,044 Truck Drivers hrs $18.16 32 $581 Cat 988 Loader hrs $134.11 8 $1,073 Cat 988 Loader Operator hrs $17.21 8 $138 Cat 365 Excavator hrs $130.25 8 $1,042 Cat 365 Excavator Operator hrs $20.65 8 $165 PC 300 w/metal Shears hrs $147.18 8 $1,177 PC 300 Operator hrs $20.65 8 $165 30 Ton Crane hrs $65.24 0 $0 30 Ton Crane Operator hrs $15.76 0 $0 Equipment Maintenance (Butler) hrs $18.46 56 $1,034 Concrete Removal sf $3.30 4,200 $13,860 Total Sample Plant Removal $23,081 Temporary Storage Building Removal Resource Description Units Cost/Unit Task Units Task Cost Laborers hrs $12.51 8 $100 Small Tools hrs $1.35 8 $11 Cat 770 Haul Truck hrs $95.11 2 $190 Truck Drivers hrs $18.16 2 $36 Cat 988 Loader hrs $134.11 2 $268 Cat 988 Loader Operator hrs $17.21 2 $34 Equipment Maintenance (Butler) hrs $18.46 4 $74 Concrete Removal sf $3.30 600 $1,980 Total Temporary Storage Building Removal $2,694 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING Truck Shop Removal Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 32 $537 Laborers hrs $12.51 16 $200 Small Tools hrs $1.35 48 $65 Cat 770 Haul Truck hrs $95.11 24 $2,283 Truck Drivers hrs $18.16 24 $436 Cat 988 Loader hrs $134.11 8 $1,073 Cat 988 Loader Operator hrs $17.21 8 $138 Cat 365 Excavator hrs $130.25 8 $1,042 Cat 365 Excavator Operator hrs $20.65 8 $165 PC 300 w/metal Shears hrs $147.18 8 $1,177 PC 300 Operator hrs $20.65 8 $165 30 Ton Crane hrs $134.11 0 $0 30 Ton Crane Operator hrs $17.21 0 $0 Equipment Maintenance (Butler) hrs $18.46 48 $886 Concrete Removal sf $3.30 4,200 $13,860 Total Truck Shop Removal $22,027 Boiler Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 160 $2,684 Laborers hrs $12.51 80 $1,000 Small Tools hrs $1.35 240 $324 Cat 770 Haul Truck hrs $95.11 160 $15,218 Truck Drivers hrs $18.16 160 $2,906 Cat 988 Loader hrs $134.11 40 $5,364 Cat 988 Loader Operator hrs $17.21 40 $689 Cat 365 Excavator hrs $130.25 40 $5,210 Cat 365 Excavator Operator hrs $20.65 40 $826 PC 300 w/metal Shears hrs $147.18 40 $5,887 PC 300 Operator hrs $20.65 40 $826 60 Ton Crane hrs $103.61 0 $0 60 Ton Crane Operator hrs $15.76 0 $0 30 Ton Crane hrs $65.24 0 $0 30 Ton Crane Operator hrs $15.76 0 $0 Equipment Maintenance (Butler) hrs $18.46 280 $5,168 Concrete Removal sf $3.30 2,900 $9,570 Total Boiler Demolition $55,673 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING Vanadium Oxidation Circuit Removal Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 64 $1,074 Laborers hrs $12.51 32 $400 Small Tools hrs $1.35 96 $130 Cat 770 Haul Truck hrs $95.11 64 $6,087 Truck Drivers hrs $18.16 64 $1,162 Cat 988 Loader hrs $134.11 16 $2,146 Cat 988 Loader Operator hrs $17.21 16 $275 Cat 365 Excavator hrs $130.25 16 $2,084 Cat 365 Excavator Operator hrs $20.65 16 $330 PC 300 w/metal Shears hrs $147.18 16 $2,355 PC 300 Operator hrs $20.65 16 $330 60 Ton Crane hrs $103.61 0 $0 60 Ton Crane Operator hrs $15.76 0 $0 30 Ton Crane hrs $65.24 0 $0 30 Ton Crane Operator hrs $15.76 0 $0 Equipment Maintenance (Butler) hrs $18.46 112 $2,067 Concrete Removal sf $3.30 1,200 $3,960 Total Vanadium Oxidation Circuit Removal $22,401 Main Shop/Warehouse Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 128 $2,147 Laborers hrs $12.51 64 $800 Small Tools hrs $1.35 192 $259 Cat 770 Haul Truck hrs $95.11 128 $12,174 Truck Drivers hrs $18.16 128 $2,325 Cat 988 Loader hrs $134.11 32 $4,292 Cat 988 Loader Operator hrs $17.21 32 $551 Cat 365 Excavator hrs $130.25 32 $4,168 Cat 365 Excavator Operator hrs $20.65 32 $661 PC 300 w/metal Shears hrs $147.18 32 $4,710 PC 300 Operator hrs $20.65 32 $661 Equipment Maintenance (Butler) hrs $18.46 224 $4,134 Concrete Removal sf $3.30 19,300 $63,690 Total Main Shop/Warehouse Demolition $100,572 Decon Pads (2) Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 64 $1,074 Laborers hrs $12.51 32 $400 Small Tools hrs $1.35 96 $130 Cat 770 Haul Truck hrs $95.11 64 $6,087 Truck Drivers hrs $18.16 64 $1,162 Cat 988 Loader hrs $134.11 16 $2,146 Cat 988 Loader Operator hrs $17.21 16 $275 Cat 365 Excavator hrs $130.25 16 $2,084 Cat 365 Excavator Operator hrs $20.65 16 $330 PC 300 w/metal Shears hrs $147.18 16 $2,355 PC 300 Operator hrs $20.65 16 $330 Equipment Maintenance (Butler) hrs $18.46 112 $2,067 Concrete Removal sf $3.30 1,350 $4,455 Total Decon Pads (2) Demolition $22,896 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING Office Building Demolition Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 96 $1,610 Laborers hrs $12.51 48 $600 Small Tools hrs $1.35 144 $194 Cat 770 Haul Truck hrs $95.11 96 $9,131 Truck Drivers hrs $18.16 96 $1,743 Cat 988 Loader hrs $134.11 24 $3,219 Cat 988 Loader Operator hrs $17.21 24 $413 Cat 365 Excavator hrs $130.25 24 $3,126 Cat 365 Excavator Operator hrs $20.65 24 $496 PC 300 w/metal Shears hrs $147.18 24 $3,532 PC 300 Operator hrs $20.65 24 $496 Equipment Maintenance (Butler) hrs $18.46 168 $3,101 Concrete Removal sf $1.25 12,100 $15,125 Total Office Building Demolition $42,787 Septic Tanks and Drain Fields Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 0 $0 Laborers hrs $12.51 16 $200 Small Tools hrs $1.35 32 $43 Cat 770 Haul Truck hrs $95.11 16 $1,522 Truck Drivers hrs $18.16 16 $291 Cat 988 Loader hrs $134.11 8 $1,073 Cat 988 Loader Operator hrs $17.21 8 $138 Cat 365 Excavator hrs $130.25 8 $1,042 Cat 365 Excavator Operator hrs $20.65 8 $165 PC 300 w/metal Shears hrs $147.18 0 $0 PC 300 Operator hrs $20.65 0 $0 Equipment Maintenance (Butler) hrs $18.46 32 $591 Total Septic Tanks and Drain Fields $5,064 Misc. Tankage & Spare Parts Removal Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 48 $805 Laborers hrs $12.51 24 $300 Small Tools hrs $1.35 72 $97 Cat 770 Haul Truck hrs $95.11 48 $4,565 Truck Drivers hrs $18.16 48 $872 Cat 988 Loader hrs $134.11 12 $1,609 Cat 988 Loader Operator hrs $17.21 12 $207 Cat 365 Excavator hrs $130.25 12 $1,563 Cat 365 Excavator Operator hrs $20.65 12 $248 PC 300 w/metal Shears hrs $147.18 12 $1,766 PC 300 Operator hrs $20.65 12 $248 Equipment Maintenance (Butler) hrs $18.46 84 $1,550 Total Misc. Tankage & Spare Parts Removal $13,831 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING Alternate Feed Circuit and Reagent Storage Building Resource Description Units Cost/Unit Task Units Task Cost Mechanics hrs $16.77 50 $839 Laborers hrs $12.51 50 $625 Small Tools hrs $1.35 96 $130 Cat 770 Haul Truck hrs $95.11 50 $4,756 Truck Drivers hrs $18.16 50 $908 Cat 988 Loader hrs $134.11 34 $4,560 Cat 988 Loader Operator hrs $17.21 34 $585 Cat 365 Excavator hrs $130.25 34 $4,429 Cat 365 Excavator Operator hrs $20.65 34 $702 PC 300 w/metal Shears hrs $147.18 52 $7,653 PC 300 Operator hrs $20.65 52 $1,074 Equipment Maintenance (Butler) hrs $18.46 170 $3,138 Concrete Removal sf $3.30 3,500 $11,550 Total Alternate Feed Circuit and Reagent Storage Building $40,948 Mill Yard Decontamination Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 238 $50,064 Cat 637 Scraper Operator hrs $19.31 238 $4,595 Cat 988 Loader hrs $134.11 60 $8,047 Cat 988 Loader Operator hrs $17.21 60 $1,033 Cat D8N Dozer With Ripper hrs $95.82 60 $5,749 Cat D8N Dozer Operator hrs $20.65 60 $1,239 Cat D7 Dozer hrs $81.27 60 $4,876 Cat D7 Dozer Operator hrs $20.65 60 $1,239 Cat 651 Waterwagon hrs $113.30 60 $6,798 Cat 651 Waterwagon Operator hrs $18.16 60 $1,090 Cat 14G Motorgrader hrs $71.34 60 $4,280 Cat 14G Motorgrader Operator hrs $20.62 60 $1,237 Equipment Maintenance (Butler) hrs $18.46 538 $9,930 Total Mill Yard Decontamination $100,177 Ore Storage Pad Decontamination Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 142 $29,870 Cat 637 Scraper Operator hrs $19.31 142 $2,742 Cat 988 Loader hrs $134.11 36 $4,828 Cat 988 Loader Operator hrs $17.21 36 $620 Cat D8N Dozer With Ripper hrs $95.82 36 $3,449 Cat D8N Dozer Operator hrs $20.65 36 $743 Cat D7 Dozer hrs $81.27 36 $2,926 Cat D7 Dozer Operator hrs $20.65 36 $743 Cat 651 Waterwagon hrs $113.30 36 $4,079 Cat 651 Waterwagon Operator hrs $18.16 36 $654 Cat 14G Motorgrader hrs $71.34 36 $2,568 Cat 14G Motorgrader Operator hrs $20.62 36 $742 Equipment Maintenance (Butler) hrs $18.46 322 $5,943 Total Ore Storage Pad Decontamination $59,908 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING Equipment Storage Area Cleanup Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 47 $9,887 Cat 637 Scraper Operator hrs $19.31 47 $907 Cat 988 Loader hrs $134.11 12 $1,609 Cat 988 Loader Operator hrs $17.21 12 $207 Cat D8N Dozer With Ripper hrs $95.82 12 $1,150 Cat D8N Dozer Operator hrs $20.65 12 $248 Cat D7 Dozer hrs $81.27 12 $975 Cat D7 Dozer Operator hrs $20.65 12 $248 Cat 651 Waterwagon hrs $113.30 12 $1,360 Cat 651 Waterwagon Operator hrs $18.16 12 $218 Cat 14G Motorgrader hrs $71.34 12 $856 Cat 14G Motorgrader Operator hrs $20.62 12 $247 Equipment Maintenance (Butler) hrs $18.46 107 $1,975 Total Equipment Storage Area Cleanup $19,887 Revegetate Mill Yard & Ore Pad Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 195 $41,019 Cat 637 Scraper Operator hrs $19.31 195 $3,765 Cat 988 Loader hrs $134.11 0 $0 Cat 988 Loader Operator hrs $17.21 0 $0 Cat D8N Dozer With Ripper hrs $95.82 49 $4,695 Cat D8N Dozer Operator hrs $20.65 49 $1,012 Cat D7 Dozer hrs $81.27 49 $3,982 Cat D7 Dozer Operator hrs $20.65 49 $1,012 Cat 651 Waterwagon hrs $113.30 49 $5,552 Cat 651 Waterwagon Operator hrs $18.16 49 $890 Cat 14G Motorgrader hrs $71.34 49 $3,495 Cat 14G Motorgrader Operator hrs $20.62 49 $1,010 Seed Mix Acre $322.50 50 $16,125 Equipment Maintenance (Butler) hrs $18.46 391 $7,217 Total Revegetate Mill Yard & Ore Pad $89,774 Total Demolition and Decontamination $1,344,939 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING CLEANUP OF WINDBLOWN CONTAMINATION Scoping Survey Resource Description Units Cost/Unit Task Units Task Cost Soil Samples each $50.00 100 $5,000 Survey Crew hrs $16.14 752 $12,140 Sample Crew hrs $16.14 1,312 $21,181 Total Scoping Survey $38,322 Characterization Survey Resource Description Units Cost/Unit Task Units Task Cost Soil Samples each $50.00 472 $23,600 Sample Crew hrs $16.14 1,136 $18,340 Total Characterization Survey $41,940 Final Status Survey Resource Description Units Cost/Unit Task Units Task Cost Soil Samples each $50.00 300 $15,000 Sample Crew hrs $16.14 3,552 $57,344 Total Final Status Survey $72,344 Windblown Cleanup Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 680 $143,039 Cat 637 Scraper Operator hrs $19.31 680 $13,129 Cat D8N Dozer With Ripper hrs $95.82 170 $16,289 Cat D8N Dozer Operator hrs $20.65 170 $3,511 Cat D7 Dozer hrs $81.27 170 $13,817 Cat D7 Dozer Operator hrs $20.65 170 $3,511 Cat 14G Motorgrader hrs $71.34 170 $12,127 Cat 14G Motorgrader Operator hrs $20.62 170 $3,506 Soil Samples each $50.00 500 $25,000 Survey Crew hrs $16.14 163 $2,632 Sample Crew hrs $16.14 83 $1,340 Equipment Maintenance (Butler) hrs $18.46 1,190 $21,964 Total Windblown Cleanup $259,864 Quality Control Resource Description Units Cost/Unit Task Units Task Cost Quality Control Contractor hrs $62.00 2,080 $128,960 Total Quality Control $128,960 Total Cleanup Windblown Contamination $541,430 Conventional Ore Disposal Resource Description Units Cost/Unit Task Units Task Cost Cat 770 Haul Truck (3) hrs $95.11 117 $11,143 Truck Drivers (3) hrs $18.16 117 $2,128 Cat 988 Loader hrs $134.11 39 $5,237 Cat 988 Loader Operator hrs $17.21 39 $672 Cat 651 Waterwagon hrs $113.30 39 $4,425 Cat 651 Waterwagon Operator hrs $18.16 39 $709 Cat 14G Motorgrader hrs $71.34 25 $1,783 Cat 14G Motorgrader Operator hrs $20.62 25 $516 Equipment Maintenance (Butler) hrs $18.46 220 $4,065 Total Conventional Ore Disposal $30,679 Total Quantity 22,963 Cubic Yards* 196 Cubic Yards per Truck per hour 117 Truck Hours * 31,000 tons maximum projected for December 2011 Loose (in-truck)material unit weight assumed to be 100 lb/cubic foot 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill MILL DECOMMISSIONING Alternate Feed Disposal Cabot and FMRI Material Resource Description Units Cost/Unit Task Units Task Cost Cat 770 Haul Truck (3) hrs $95.11 67 $6,406 Truck Drivers (3) hrs $18.16 67 $1,223 Cat 988 Loader hrs $134.11 22 $3,011 Cat 988 Loader Operator hrs $17.21 22 $386 Cat 651 Waterwagon hrs $113.30 22 $2,544 Cat 651 Waterwagon Operator hrs $18.16 22 $408 Cat 14G Motorgrader hrs $71.34 10 $713 Cat 14G Motorgrader Operator hrs $20.62 10 $206 Equipment Maintenance (Butler) hrs $18.46 122 $2,257 Total Cabot & FMRI Material $17,155 Total Quantity 13,201 Cubic Yards* (as of 01/31/2011) 196 Cubic Yards per Truck per hour 67 Truck Hours * Includes Linde, Cabot and FMRI Cameco Barrels and Honeywell Barrels Resource Description Units Cost/Unit Task Units Task Cost Equipment Operators hrs $18.16 306 $5,564 Flat Bed Trailer and Tractor* hrs $55.00 306 $16,851 Fork Lift (2)hrs $18.00 613 $11,030 Equipment Maintenance (Butler) hrs $18.46 306 $5,655 Total Cameco and honeywell Barrels $39,100 * includes operator 30,638 Barrels (as of 01/31/2011) 40 Barrels per load 0.4 Hours per load 306 Truck Hours Tons lbs. per barrel No. Drums CaF2 1,083 727 2,978 Calcined 2,622 320 16,388 Regen 337 406 1,660 KF 1,484 309 9,605 UF4 2 547 7 5,528 30,638 Sub-Total Alternate Feed Disposal $56,254 TOTAL MILL DECOMMISSIONING $1,973,302 9/28/2011WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Mill Decommissioning Reviewed 09/22/11 1) Removal of contaminated material from Mill Yard Assume: -- 18 inches (1.5 feet) will have to be removed -- Area (from CAD takeoff) = 1,643,453 sq. feet 37.7 acres 91,303 cubic yards Use 92,000 cubic yards 388 cubic yards per hour (92,000 CY / 388 CY/hour) = 238 machine hours 2) Removal of contaminated material from Ore Pad Assume: -- 18 inches (1.5 feet) will have to be removed -- Area (from CAD takeoff) = 976,780 sq. feet 22.4 acres 54,266 cubic yards Use 55,000 cubic yards 388 cubic yards per hour (55,000 CY / 388 CY/hour) = 142 machine hours 3) Removal of contaminated material Equipment Storage Area Assume: -- 18 inches (1.5 feet) will have to be removed -- Area assumed = 314,500 sq. feet 7.2 acres 17,472 cubic yards Use 18,000 cubic yards 388 cubic yards per hour (18,000 CY / 388 CY/hour) = 47 machine hours Use Haul Route 14 = (1,643,453 square feet X 1.5 feet) / 27 = (967,780 square feet X 1.5 feet) / 27 = Use Haul Route 14 = (314,500 square feet X 1.5 feet) / 27 = Use Haul Route 14 = Mill Decommissioning Volumes Rev 5.0.xls Mill Decommissioning (con't)page 2 4) Demolition Equipment -- Kamatsu PL400 (or Cat equivalent) with LaBounty Sheers (hydraulic) -- Cat 365 Trackhoe with Grapples -- Cat 769 Rock Trucks (4 each) -- Cat 988 Loader (1 each) 5) Demolition Crew -- Heavy Equipment Operators - PC400, Cat 365, Cat 988 -- Dust Control - 2 Laborers -- Mechanics - Cut debris to reduce/avoid oversize and voids - 4 each -- Truck Drivers - 4 each Mill Decommissioning Volumes Rev 5.0.xls Mill Decommissioning (con't)page 3 6) Tool and Expendable Allowance, covering the following items: -- Safety gear and supplies -- Hand tools -- Bottled Gases and Torches -- Allow $1.30 per man-hour for all but Heavy Equipment Operators and Truck Drivers 7) Demolition Time Estimates -- Mill Building 20 Days -- Ore Bin 2 Days -- SX Building 10 Days -- CCD, Pre-Leach, Claricone 5 Days -- Sample Plant 1 Day -- Boiler House 5 Days -- Vanadium EMF/Ox 2 Days -- Shop/Warehouse 4 Days -- Office/Lab Building 3 Days -- Misc. & Bone Yard 4 Days -- Decon Pads (2) 2 Days 8) Foundation Demolition -- Assume area of structure times $3.30 per square foot -- Areas by building as follows: Area, sq ft $ Cost Mill Building 37,500 123,750$ SX Building 55,970 184,701$ CCD, Pre-Leach, Claricone 15,000 49,500$ Shop/Warehouse 19,300 63,690$ Office* 12,100 15,125$ Sample Plant 4,200 13,860$ Vanadium EMF/Ox 1,200 3,960$ Boiler house 2,900 9,570$ Decon Pads 1,350 4,455$ -- Labor at $2.75, Equipment at $0.55 -- * Labor at $0.70, Equipment at $0.55 Mill Decommissioning Volumes Rev 5.0.xls Mill Decommissioning (con't)page 4 9) Revegetation Assume: -- Mill Yard Area sq. feet -- Ore Pad Area sq. feet -- Equipment Storage Area sq. feet Total: sq. feet -- Place 6 inches of Topsoil -- Cat 637 Scraper, Haul Route #4 [ 2,934,733 ] sq.feet x 0.5 feet] / [27 cubic feet / cubic Yard] 54,347 cu yds Use 54,400 cu yds Use Haul Route 15 279 CY/hour 54,400 / 279 cu yds per hour = 195 Scraper hours 1,643,453 976,780 314,500 2,934,733 Mill Decommissioning Volumes Rev 5.0.xls • COST ESTIMATE . J;.Jiil~<.. S"PAVI/!'7 C#•tc. 6e: a.-.rc.l'uc?'C'"' 0~\/ &{ c;;-,;--4 ,..-~ b6 c/:-hr_,P"./, f:,_.-r ..;;.,. 7"-,4..;, ~~lt-.r~ r/ /f pi~,/;.No./ ~ :;_., Ci#!'EA1 ~r.,.;r;...,.-n"",u b; h ' ):;£1""./ ...... ~-*rr /ooo A--c:-7' (JIA 7 S7~ £ c~/ A. ~JTfll crC>--' //'1~ ,i!?..Ju.v.:Jr.- 7h,~ ir ~""' .rr..., V*?'"'-'~ .:r;,.,t:_e_ ~~"'" ~/u_,,., c:;-.J-1..-.-~r/•-.l Jv""' t./ HI~ .. ./. /;bz h .h\J,...,d Pow-v tvhvct o-:1' /JC.. .rr.ro .,~ ?J~.u ~ .,....., ~ C.:~.;./ _·,:rt!' o../ -lAo yc;,,_,/,..,-a£C..:;> ~Art~ · To~c. ~ ~ "fA Ct!ll ..3 CQII 2 Ct!>ll I /Y}.It..L Y.oA.O 01'!.~ $To-9~~ ~~ .381 72.6 1 OtJO HZ... I 1 '7o'i 1 croo ..fi -z 3 I 2 3-T I Quo II z 2 1 9871 ooo/JZ L J 57(.. 1 60(.) liZ. J,,43 1 ooa.fl' ~11 1 oou .ff'- • L/:Sfclqz~ ;=Lou n?6"117' oF" :::5'-r,.,.,.oJ()/UJ /v'/Zc:/E/A /0 x 10 mt.l.r {ji?d (;o ~ A:SS VAl<-.::SC.o~J/ S:vru7 Cu-~foh~ .67 S e-..;,.,,.v...J Wr7"# Jfl' /11~./e,­ J-1./cl tJ,.,,s~ -;-c J.rc v,.._t:/ £vh,4 ._/,-.-,.u/"7 d../-::t:-tP. S ,/11'1/Jcc. .;fJJ j?~Y 6vd.,-vc.• .1-"' /f./st.Gs"G-5'4-f-9. ~ 5/ -40 21 0 00 ../I .2. ;:;- /1>7~ -4 2 ~ .3,1.&.00 hi~ 7'J S"oo ,Po,...,~.~ /j)117 .2PJ~n X 8.-{r.s ;< -7'7 ~~f -} 75",? Plif.N ./.r..r { -ScM<ICJ , -··· ..... -··· ·-.. .. . .. COST ESTIWA TE i ~.:S'~o./h":~ ..30 rn6 ~,... f:b;-, •• : -r.::.,.. -<.:.....::~ /O ~· /...;> Cif"'.r-sil !:C ..;;"' J.c,-/0 ,-:~ o..t, .,p~.~.,../.~ A~"~C.J? ( ;OC"l. /\/u~ 58"14 ~ .:. Z3, "-00 G' v1 D .s ""' b 2 J>,7 7D ~.-.11~~ .ln.trMt. 31:34 ~YJt>.r /c"l 6 2 ~ 7.: X z_, e.n >< & ~r.z .:= I n :2. /n,,.; ,l;r .. s 7 a"'l A:s:s-"',-?f~ /??A~ ~~fo)&1~C...'7/PN + ~~ ~~-h~ ~h .::s-c~,..J,..,,"'J C'~.....J ~ #IIQ;t:J,:;~"T.ft,.,./11"91-2o r;,.?:S 7Q c::;_,~/e~ ,:20 .D.n 7 .s X' 2 .no Q"" x .5/,...(,.s-/~7 -=: f 3"20 "".-; ~..s- 7Q..,..._.,. ::r,c.,,.,.-./~Aij' /)")t/W' hr.r #' { /..3 12 ) .. S<:--c>-!"J,..,l ~rvry (.A./I// rL.JV./~ /00 a;J ...(,._, ,_,;.-~'? ~.1~ s:;-yL' e:r ~<-.,'. .::;, ~ / ~ ;I :50-tr~ / c,c.K ( V,-r,.l..;. ,G. zz'=>) s~'Yk_, ~ -J J6 -1 ... ~ e;..,~ ;;._ -1>-c. ~.:1 .::rc.~...,,·:; --1,~ ~"".4~- ...2) ~,~c..7t:"ll'&.t'2'-'7-" ,..,/ .::fv-tv~ - ..Sr..tt9 "'7 ~ a;'C"f1.S idll_,..,(.f:/ ~ a./~ T<:rCI 'r&"Q.E. ~,7 _=r'""<,_,, ~~ J0 ~"'? .J4. ;$ s "'.n-1. 6 . ' • .2c% "./ ..4'~ "' .. nTI ro;tNtre-~v· +..,.,#-f. c:;,..,_. J..::.; • Pro> .J -'IV..J Will /;. v..r~ / -;£ ;:;r• tt.. .. .. ~ ~ri.O (&~I ·o:.-- • Sow<.. s-.....,/#.J w.i/ .be.. ro;v.tred ~.r/ /0/o ,T 6'-!~ JJ.,~ • s~~ (..v.l/ be L,. v,.,~--r II!. tu C.,...,/ /.r~ .:~~'0 (L.-eJ 25,~ ~02/ 000 .#'__ /0 7• .f'.J :§o.o X • Z ::: • , 4-~ C..,.; Gvc-r er~ c-.; ~~ /t;O ~y~~~ /t~J• 7 ~I'Q,jJIVJ ,.u' S"1' ~~ /tJ~l '?rc}../,v./ /ol::e::> f-7z Z. C ,~· ::=: /OO v-:-/~ 47 >( z. X 6 :: /75Z h~.S I COST ESTIMATE , .; ~ /;; ~' ~:: ..,f~ I d{: /r.,-;,;"' ,;Pr-.:ov'.p r--77(,,../ -T-J...-r.-._;o .?:=-.o~.<c-7/ ~-.I -r(.J~ p~~~,.,._J.I' :;-~n7 _. 5~~'"'x s~~-)FdTrso ( r------1 / /~'-,.., -..~ A r' .s j • IN o~ '1b ~•w l=O~ t"e 04..t5, 1,.\.1\u.,. ~ .. llt .. .f£ 4 t:""'/611.4~AA a,...,~ ~ ~ iJ:O ~ "2. £:.~c ~AU I ~ "T'i-1€ ~"Tcr) AE'Q. (~ 1J ~ ) ~ -zac:> ~CI>tl ~-"'-~i)~~~ L..JIU,.. ~ ~ ~~ ~ J.>~~ ~ (Eel."b~) • \ •. /!u., '2c;QurQ.e 100 (b..w:.twA~ ~01~ ~ T"WC !~"FWO ~ 1 . 25,402. + f01b f+"'oo-2 :: · "23)""7 C-rl:. ;o! ·•Q~~ d.Ji'Z.1 ~·"Os h~p 13, f.sOI x. O·'ZO 4, 7Z.I "" 4 .c~ :: = ~~ ~·'lie.~ ~,.. tee.e, ~~~~ • C2e..J (..., T~ ts. ~·4. ~~I~ ~ .:. [ 200 • UIO] ~ ~S· INiEANATIONAL URANIUM (USA) CORP. COST ESTIMATE ~T ........ -......................................... .oa. ........................ ~ ~ .......................................... ~elt ........ ol. ·- MI\..L ~~~,.,) ,r-,Q \.J,uo~AJ CbN~'.uA'TTO"--' (~-t) '\ 5) ·c.~ -UP. • ~~ ZcL Dl" A~ ~t.v~ Acn~ • ~· 0 ~ Sell'-~u.. ~ ~"11t&"C .. '2 I ?40, o«:'J -R!' ~~~ttd' ( ,..1 \00'1d!\ • fls IT tS ~« ~~ ~ \o.)H~1z~ ~.J•-t a.-('~~'tN.tt~ 6~~~ 'Tl-9e 'us.e ori-t-"31 · ~ ~.,. •" ~ k (Dr~ • 8£rl>.!tiC: t:JC:. ~ ~.64..-~ 'Uer,•......C.. ~ 't'I~U;A.Ja.J~ ~~ ~~ ~~t... k ~T sc.t. ~· e.a.u~ ID'f1 £:pi.C~ .. ~ 2.-rt ~ l/tsr -. o.SO = . ~~ ~ ... klO ~' ~ ~~~3,4v-: (,81 ~~ ~~(.a> ~:J WMM Inventory AccoUJlting Summary 1 2011 d.!!I!!!!X f!l!!!!!!x c:.!xll 488 caF4 Caldned Ptoi)JCI-Canwco 21'3 F-..t...,JJFMRI t<F Product-Cemtco 29 Regeo PtodUCI· Cameco 13 WMM ALTERNATE FEED RECEIPTS FOR THE MONTH ENDING January st. 2011 Dry Tons Recell/ed June ~ 21'3 29 13 UF4MM~~----~~-----------------------------------------------------------------------------------------------------------i.~ 803 803 CtrJN Butt&-cameco Mcstena Smith Ranch-Cameco South Texas Mining Ven!Ure 65 WMM 11e2 Material Receipts FOR THE MONTH ENDiNG January 31, 2011 65 ~----~----------------------------------------------------------------------------------------------~ WMM ALTEJU(ATE FEED Ending Inventory FOR THE MONTH ENDING J/HJuary 31, 2011 ZD11 B!!(Jlnn1!!9 2011 vro ~ 2011 En111nq Mmri&l ~ Roc•lv!S Ions Fe<! Adl,;;t;;;nt! ~ Cabal &,157 488 5,645 CaFZ·Honeywell 1,083 1,083 CaJdned Produa· Cemeeo 2.349 273 2,521 F~MRI 11,177 11.177 KF Pn>du=-Came<» 1.455 29 1,"85 Regen Produc:I-Cemeco 324 13 337 UF4 Maternti·Cemec:o---:=-i-2;---:.:,,.---....:...-------''------::=i2;-2:2.5oe7 SOl 2J~50 AwraaBU308 ~ 0.3-0.6% content 0,5 -3.0% canton! 4.5%con!cn\ 0.2!Kl.S'l<o <Xln11!nt 1%eonturrt 7~.0% content OS.~ ClCI\lenl ( f•f-~Hf~R1 FEH.-i:. r-tJ BCJ>: ~ r ['':-.'''[. C.RE n, C (, t C.: 7C· ) SOLD TO: ~r·nuu1 ~ -;-, -'"~"''' ~"': 1...,. t , ,_ • ... ..... SEEf·: lt~C ~-"l -•• -. /• ... , -....... ~ ['f'\\!ISO!! M]HES (l.!~n) 1050 171H ~lREEl ~-UJ'lE ~~·C· L:E:·-!VE'F; . (I). ITEM NUMBER'~ DESCRIPTION (\ :,· "': '"}'; .. cs:r.:: •-t:J/• l.....:.. ·-I \.f •-.... • ~~E.£~· I~ ~l .'· -J ~ UC~--C:•."lO ~-f-1f: I Gl-! 1 .. "' .· 't.L1f![:; .Y r;]/·JE ~-U1·1i:! t•' ·-" ~--~--- '/~ ( I ..--;:/ II -· --L" OUAt./TITY 1J4 . !. ~,~ .J ~\ -) v'"' \(__):.•_ INVOICE NUMBER II~VOIOE DATE SALESPERSON NO. DUE DATE DISCOUNT Dt.TE PAGE i .. Iii!' ' . ! l; 1 .• ' I PRICE txTENSION ~;ij . -; '-;-(s~ --,'J\:.1 ~ ........ J (\·;~-• '\J .,.. L;<; . 7 s J'. f!.C -, L ,...; V'-..\f\.J...../ SUBTOT.AL SALEs "!.(X IINOICE rOTAL AMOUNT P/.10 { BALANCE CHANGE DUE 2!.:.3(~.83 .. ........ DENISON MINES (USA) CORP. Vendor 10 I Name CAR004 I Carhart Feed and Seed Our Voucher Number !Date I 311190 311687 3/3012009 4ni2009 -J1 '':!(' p-.. ----- J Payment Number 1ooooooooooooo94s1 AmQuritJ $2,430.83 $9.47 $2,440.30 · .. An\Qiit:ttf'ald $2,430.83 $9.47 $2,440.30 REORDER FROM YOUR LOCAL SAFEGUAIID lltSTRIBUTOII.II' UNKNOWN. CA1L 800.0U.2AU ., t! ~":"! ,~, p": ----- 372 C~queOale I:Docul1)ent Nuin~r 4/1712009 1 oo37238 Olscount·J · $0.00 $0.00 $0.00 Ne~~9unf~~lCI $2,430.83 $9.47 $2,440.30 -· 38 - 1 Harold Roberts From: Sent: To: Subject: Christy Woodward Thursday, June 25, 2009 3:45 PM Harold Roberts Seed On average, we have been paying $21 per pound of seed and apply it at $15 lbs per acre (also an average). Christy Woodward Envir011mental Coordinator t (303) 389-4136 1 c: (303) 549-97221 f: (303) 389-41l5 1050 17th Street, Suite 950, Denver. CO 80265 DENISON MINES (USA) CORP www.denisonmines.com Tills e·maflls intended for exclusive use the person(s) menlioned as the reclpient(s). This message and any attached files wtth it are confidential and may contain plivlieged or proprietary Information. If you are not the Intended rec;lplent(s) please delete this message and notify lhe sender. You may not use. distribute print or copy tills message II you are not the Intended recJplent(s). 1 Cell 1 RECLAMATION OF CELL 1 RECLAMATION OF CELL 1 Dewatering of Cell 1 Resource Description Units Cost/Unit Task Units Task Cost Dewatering of Cell 1 hrs $0.48 62,400 $30,000 Total Dewatering of Cell 1 $30,000 Crystal Removal Resource Description Units Cost/Unit Task Units Task Cost Cat 770 Truck hrs $95.11 2,157 $205,159 Truck Drivers hrs $16.67 2,157 $35,966 Cat 988 Loader hrs $134.11 539 $72,286 Cat 988 Loader Operator hrs $17.21 539 $9,278 Cat D8N Dozer With Ripper hrs $95.82 539 $51,646 Cat D8N Dozer Operator hrs $20.65 539 $11,132 Cat 365 Excavator hrs $130.25 539 $70,206 Cat 365 Excavator Operator hrs $20.65 539 $11,132 Cat 651 Waterwagon hrs $113.30 539 $61,068 Cat 651 Waterwagon Operator hrs $18.16 539 $9,789 Cat 14G Motorgrader hrs $71.34 539 $38,450 Cat 14G Motorgrader Operator hrs $20.62 539 $11,115 Equipment Maintenance (Butler) hrs $18.46 4,852 $89,554 Total Crystal Removal $676,779 Contaminated Materials Removal Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 386 $81,196 Cat 637 Scraper Operator hrs $19.31 386 $7,453 Cat D8N Dozer With Ripper hrs $95.82 97 $9,294 Cat D8N Dozer Operator hrs $20.65 97 $2,003 Cat 825C Compactor hrs $97.64 97 $9,471 Cat 825C Compactor Operator hrs $14.22 97 $1,379 Cat 651 Waterwagon hrs $113.30 97 $10,990 Cat 651 Waterwagon Operator hrs $18.16 97 $1,762 Cat 14G Motorgrader hrs $71.34 97 $6,920 Cat 14G Motorgrader Operator hrs $20.62 97 $2,000 Equipment Maintenance (Butler) hrs $18.46 774 $14,286 Total Contaminated Materials Removal $146,754 Topsoil Application Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 82 $17,249 Cat 637 Scraper Operator hrs $19.31 82 $1,583 Cat D8N Dozer With Ripper hrs $95.82 40 $3,833 Cat D8N Dozer Operator hrs $20.65 40 $826 Cat 651 Waterwagon hrs $113.30 40 $4,532 Cat 651 Waterwagon Operator hrs $18.16 40 $726 Cat 14G Motorgrader hrs $71.34 40 $2,853 Cat 14G Motorgrader Operator hrs $20.62 40 $825 Equipment Maintenance (Butler) hrs $18.46 202 $3,728 Total Topsoil Application $36,156 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 1 Construct Channel Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 8 $1,683 Cat 637 Scraper Operator hrs $19.31 8 $154 Cat 770 Truck hrs $95.11 148 $14,051 Truck Drivers hrs $16.67 148 $2,463 Cat 988 Loader hrs $134.11 37 $4,953 Cat 988 Loader Operator hrs $17.21 37 $636 Drilling & Blasting Contractor BCY $2.69 13,000 $34,950 Cat 14G Motorgrader hrs $71.34 37 $2,635 Cat 14G Motorgrader Operator hrs $20.62 37 $762 Cat D8N Dozer With Ripper hrs $95.82 39 $3,730 Cat D8N Dozer Operator hrs $20.65 39 $804 Equipment Maintenance (Butler) hrs $18.46 269 $4,956 Total Construct Channel $71,777 Place Clay Liner Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 0 $0 Cat 637 Scraper Operators hrs $19.31 0 $0 Cat 825 Compactor hrs $97.64 60 $5,859 Cat 825 Compactor Operator hrs $14.22 60 $853 Cat D8N Dozer With Ripper hrs $95.82 60 $5,749 Cat D8N Dozer Operator hrs $20.65 60 $1,239 Cat D7 Dozer hrs $81.27 0 $0 Cat D7 Dozer Operator hrs $20.65 0 $0 Cat 651 Waterwagon hrs $113.30 60 $6,798 Cat 651 Waterwagon Operator hrs $18.16 60 $1,090 Cat 980 Loader hrs $93.97 60 $5,638 Cat 980 Loader Operator hrs $17.21 60 $1,033 5000 Gallon Water Truck hrs $65.95 30 $1,978 5000 Gallon Water Truck Operator hrs $18.16 30 $545 Highway Trucks hrs $83.33 435 $36,247 Truck Drivers hrs $16.67 435 $7,253 Cat 14G Motorgrader hrs $71.34 85 $6,063 Cat 14G Motorgrader Operator hrs $20.62 85 $1,753 Equipment Maintenance (Butler) hrs $18.46 355 $6,552 Total Place Clay Liner $88,650 Place Radon Attenuation and Grading Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 150 $31,553 Cat 637 Scraper Operators hrs $19.31 150 $2,896 Cat D8N Dozer With Ripper hrs $81.27 38 $3,088 Cat D8N Dozer Operator hrs $20.65 38 $785 Cat D7 Dozer hrs $71.34 38 $2,711 Cat D7 Dozer Operator hrs $20.65 38 $785 Cat 14G Motorgrader hrs $71.34 38 $2,711 Cat 14G Motorgrader Operator hrs $20.62 38 $784 Equipment Maintenance (Butler) hrs $18.46 264 $4,873 Total Place Radon Attenuation and Grading Layer $50,185 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 1 Place Compacted Radon Attenuation Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 176 $37,022 Cat 637 Scraper Operators hrs $19.31 176 $3,398 Cat 825 Compactor hrs $97.64 44 $4,296 Cat 825 Compactor Operator hrs $14.22 44 $626 Cat D8N Dozer With Ripper hrs $95.82 44 $4,216 Cat D8N Dozer Operator hrs $20.65 44 $909 Cat D7 Dozer hrs $81.27 44 $3,576 Cat D7 Dozer Operator hrs $20.65 44 $909 Cat 651 Waterwagon hrs $113.30 44 $4,985 Cat 651 Waterwagon Operator hrs $18.16 44 $799 Cat 14G Motorgrader hrs $71.34 44 $3,139 Cat 14G Motorgrader Operator hrs $20.62 44 $907 Equipment Maintenance (Butler) hrs $18.46 396 $7,309 Total Place Compacted Radon Attenuation Layer $72,091 Place Water Storage Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 172 $36,181 Cat 637 Scraper Operators hrs $19.31 172 $3,321 Cat D8N Dozer With Ripper hrs $95.82 43 $4,120 Cat D8N Dozer Operator hrs $20.65 43 $888 Cat D7 Dozer hrs $81.27 43 $3,495 Cat D7 Dozer Operator hrs $20.65 43 $888 Cat 14G Motorgrader hrs $71.34 43 $3,067 Cat 14G Motorgrader Operator hrs $20.62 43 $887 Equipment Maintenance (Butler) hrs $18.46 301 $5,556 Total Place Water Storage Layer $58,402 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 1 Place Erosion Protection Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 15 $3,155 Cat 637 Scraper Operators hrs $19.31 15 $290 Cat D8N Dozer With Ripper hrs $95.82 5 $479 Cat D8N Dozer Operator hrs $20.65 5 $103 Cat D7 Dozer hrs $81.27 5 $406 Cat D7 Dozer Operator hrs $20.65 5 $103 Cat 14G Motorgrader hrs $71.34 15 $1,070 Cat 14G Motorgrader Operator hrs $20.62 15 $309 Rock Mulch Cost Delivered CY $12.77 2,000 $25,532 Equipment Maintenance (Butler) hrs $18.46 40 $738 Total Place Erosion Protection Layer $32,186 Place Compacted Outslope Fill Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 86 $18,090 Cat 637 Scraper Operators hrs $19.31 86 $1,660 Cat 825 Compactor hrs $97.64 22 $2,148 Cat 825 Compactor Operator hrs $14.22 22 $313 Cat D8N Dozer With Ripper hrs $81.27 22 $1,788 Cat D8N Dozer Operator hrs $20.65 22 $454 Cat D7 Dozer hrs $81.27 22 $1,788 Cat D7 Dozer Operator hrs $20.65 22 $454 Cat 651 Waterwagon hrs $113.30 22 $2,493 Cat 651 Waterwagon Operator hrs $18.16 22 $400 Cat 14G Motorgrader hrs $71.34 22 $1,569 Cat 14G Motorgrader Operator hrs $20.62 22 $454 Equipment Maintenance (Butler) hrs $18.46 196 $3,618 Total Place Compacted Outslope Fill $35,229 Rock Armor and Rip Rap Bedding Layer Resource Description Units Cost/Unit Task Units Task Cost Cat D7 Dozer hrs $81.27 70 $5,689 Cat D7 Dozer Operator hrs $20.65 70 $1,446 Cat 651 Waterwagon hrs $113.30 70 $7,931 Cat 651 Waterwagon Operator hrs $18.16 70 $1,271 Cat 14G Motorgrader hrs $71.34 70 $4,993 Cat 14G Motorgrader Operator hrs $20.62 70 $1,444 Rock Cost Delivered CY $12.77 15,000 $191,489 Equipment Maintenance (Butler) hrs $18.46 210 $3,876 Total Place Rock Armor and Rip Rap Bedding Layer $218,139 Quality Control Resource Description Units Cost/Unit Task Units Task Cost Quality Control Contractor hrs $62.00 800 $49,600 Total Quality Control $49,600 TOTAL RECLAMATION OF CELL 1 $1,565,949 Notes and Assumptions: - Assume trucks can haul rock away at 4 round trips per hour, 22 CY per trip - Quality control contractor is assumed to be necessary for duration of material placement plus 20% for reporting. - To blend topsoil and rock mulch in the Erosion Protection Layer, it is assumed that materials will be windrowed and "bladed" three times by motograder. 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Volume Calculation - Cell 1 Updated 09/23/11 1) Area of Cell 1 - 656,664 sq ft = 15.07 acres 2) Assumptions - All volumes are presented in bank cubic yards (BCY) unless otherwise noted * Indicates volume is presented as in-place (compacted) volume - Rock for rip rap armor, rip rap bedding layer and rock mulch will come from an off-site gravel source one (1) mile north of Blanding. Rock will be produced through screening, stockpiled and trucked to the site at the time of use. Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. - Assume rock swell factor of 1.5 - Assume rock is hauled away in highway rucks 3) Radon Attenuation and Grading Layer remaining to be placed Random fill placed at 80% relative compaction =57,226 cubic yards Use 58,000 cubic yards 4) Compacted Radon Attenuation Layer Random fill placed at 95% relative compaction =67,955 cubic yards Use 68,000 cubic yards 5) Water Storage/Biointrusion/Frost Protection/Radon Attenuation Layer Random fill placed at 85% relative compaction =85,123 cubic yards Use 86,000 cubic yards Volume Calculation Cell 1 Rev 5.0.xls Volume Calculation - Cell 1 (con't) page 2 6) Erosion Protection Layer Topsoil mixed with 25% gravel placed at 85% relative compaction = 7,927 cubic yards Use 8,000 cubic yards 7) Cell 1 North Outslope Average height 18 feet Length 2,450 feet A) Random Fill Placed at 95% relative compaction 324 square feet (324 square feet X 2,450 linear feet) = 793,800 cubic feet/ 27 = 32,859 cubic yards Use 32,900 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 45 square feet (65 square feet X 2,450 linear feet) = 110,250 cubic feet/ 27 = 4,083 cubic yards * Use 4,100 cubic yards * b) Rip Rap Armor 12" thick 82 square feet (118 square feet X 2,450 linear feet) = 200,900 cubic feet/ 27 = 7,441 cubic yards * Use 7,500 cubic yards * C) Rip Rap Apron at toe of slope Rip Rap Apron wraps around perimerter of Cell 1. Length = 2,910 feet Width = 10 feet a) Rip Rap Armor Thickness = 2 feet 58,200 cubic feet/ 27 = 2,156 cubic yards * Use 2,200 cubic yards * Total North Outslope Rip Rap Bedding Layer 4,100 cubic yards * Total North Outslope Rip Rap Armor 9,700 cubic yards * (2 ft X 10 ft X 2,910 ft) = Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 1 Rev 5.0.xls Volume Calculation - Cell 1 (con't) page 3 8) Removal of Contaminated Material Volume as determined in hand calculations 95,500 cubic yards Volume Summary - Cell 1 Radon Attenuation and Grading Layer (CY) Compacted Radon Attenuation Layer (CY) Water Storage Layer (CY) Compacted Outslope Fill (CY) Total Random Fill (CY) Erosion Protection Layer (CY) * Rip Rap Bedding Layer (CY) * Rip Rap Armor (CY) * Contaminated Material (CY) Top of Cell 58,000 68,000 86,000 0 212,000 8,000 0 0 North Outslope 0 0 0 32,900 32,900 0 4,100 9,700 Other 0 0 0 0 0 0 0 0 95,500 Totals 58,000 68,000 86,000 33,000 245,000 8,000 5,000 10,000 96,000 Cell 1 Reclamation Cat 637 Resource Requirements Volume Route CY/hr % Equip. Hr. (CY) Radon Attenuation and Grading Layer Tailings Surface 58,000 7 388 100% 150 Compacted Radon Attenuation Layer Tailings Surface 68,000 7 388 100% 176 Water Storage Layer Tailings Surface 86,000 7 388 100% 222 Compacted Outslope Fill Outslopes 33,000 7 388 100% 86 Erosion Protection Layer 1 Tailings Surface 6,000 13 410 100% 15 Contaminated Material Removal Cell 1 96,000 16 249 100% 386 1 Volume includes topsoil only (does not include rock mulch) 2 Rock mulch, rip rap armor, and rip rap bedding layer will be hauled using highway trucks Volume Calculation Cell 1 Rev 5.0.xls Volume Calculation - Cell 1 (con't) page 4 17,000 cubic yards (CY) 38 CY per hour times 8 trucks 304 CY per hour delivered Assume 25% extra time for spreading, loading and screen wait 304 / 1.25 243.2 CY per hour 70 Hours Cell 1 Discharge Channel 2,080 BCY = 2,210 LCY Use 3,000 cubic yards 8,540 BCY = 12,810 LCY Use 13,000 cubic yards Volume Route CY/hr % Equip. Hr. (CY) 3,000 7 388 100% 8 Rock to be Removed: Soil to be Removed: Rock Mulch, Rip Rap Armor, and Rip Rap Bedding Layer Production Cell 1 Soil to be Removed: Volume Calculation Cell 1 Rev 5.0.xls I I _~ I ~ .J U'lU'lU'l ..... E i :1::1 ::: U'lU'lU'l ' ... CCC W)CC -f'4 ... ...-. "'t·· ---. . . 1'11'11'1 C"'C'41'1 ~ l I- I I l. 1) ., '· .5) INTERNATIONAL URANIUM (USA) CORP. + COST ESTIMATE + c. F(.J... .1 -.r -EriAPOI"V:"riC>I'J + + + + + f'or..~, ',t::~.u;tA == 5#:J I I Ac;A.t;:; ( l"'t:~•~r; z,,,c.t!::o+ ~ .... c:;.J '· • ~"?..S ?"4t-'C/-~<!'";SS .6~~15-tf' PN h1-1 ;~r&.CA"-~.o7"Kro/ i7r -r.J,.. -' .;IC ~-;-,._ ~7-lrl' --.,JQ Aa.~"' -'»'¥,'?? -:-~v~ 3 ./i. ~,u.c.. .21 s.7~1 7oa .:/).z. x (e#ocLJ-s-.f.l..):::: 4 .2t!f;2h:3l 2-i .{f'l/t.7 ___,.. r;;, 1 Soo ~y ·\ oC I''"/·~.~ ,/ -1~ e.~,4_'A ILl J./1 ... / u~I.,.I'V.a-r"' ,....""'*../ ~~ r6,_.~RT./ 4~-~,t,"'(! ,/.....,.qj( k l!>l.k~ &·JI 71.KI~ ~,..,,,t:!":J 7b A .... (; 'Xyl.r +-~ t:/v.t:"r.:. A·~J'fl~~"') ~ ~PJ r;.,C +-7b9 TnM-~ J a 127_,5'(.. .. 7~"'~~ i ?t!-6 l .. cu·~,.,., r:J-5.s'"""' f. ku.'-~h ,#. i. ~"' p~dv-c..r~o~,J (1'11 cy jl,,} "Pk!c~ Jj,. ) ·~ ---------------- TOPSOIL CELL 1 (EVAPORATION) 29.5647 Acres 2.5402 Ac-re-s..a---A REA OF CELL DAKOTA TO BE BREACHED SANDSTONE By .<SAM Date 9/?6/ 1i Client '[:)'"""'·''"! Sheet __.____,of __,2:.____ Chkd. By ______ Description "(._.: ,;,~ L£-'··c-'-i'---'C:...='·IccA""/j._._~'-'111:"'L~'-...\.o(';l;:c,,.,A"''·'-''T--''"-.,.-'"----"f;;"'···""'· T..1.'' 1'1>1 "'-A'lu'''"'" :.,_, --~Job No. _,1.,-C0"'9'-'1'-'4,_o,___ I At. L"-Gfx~~hN "i.,-~;lD r-..J '\l:),~ P TIL ~ b l"'f I IH ~ow. ! . . . . A .. · ~\'1\14+ 'f(): cL.-r>nr o,;:_ 'R9""' !£-JcMA'r~u :c [. C:.:1-1~~~~t<l D i!<>t.··,l :-, 'l:>t:'l . I 'V I . . ··~ , ., .. "! D""'"-" ..• ?., ~,.., y ·~~-· •1.~ " ,,.,. ". "'' ..... , r1 r £,.,-A C).• oo c.~<>!>"-. C 1(o,;·,$.v:~'f"<O<·Ih.l. At" (.S6oL): 0 C11.o•.:'.· $.u.·n<>t4A L A Rf-"' ( P,oc~): I, ~~-r ~r--r----T-~-=- -' . I . _-. "'* S-rA. 4, + r~ C.1<0S~ . r'<.-r'•O>I ' ' -~--· ,_ ,,-;-z 9 f'T z. · A;,:e,,,nL~/ ~~---''·--+----'-----+-------:------·--' -. . (.O"l'f'AG-r . 47 1 F''i~ 0 r--r'- w] 0 'i:'4 1D w = "' $ ro 0 e :I: 5: :! ~ "" 0 z .0 0 ~ L,· ' ~ .Q 15. "5 ~ w 0 ~ "' -o ~ 6 !--~----··· 1 -:'S-t-A 41-10: (g~·So:cno"'>'U. Aru:A.: 4l1 FT2 (~~·'") SeA 2Y~6 ; &oss · Scc.-r'""'-~"'-A-..c.;.. '. 471 er-t. . (Ro"lt.\ f-----:Sr.A-D.J:.D.o....:....Lz.o.ss..o...,S,a.=.,.c.>MAJ~ ... ~-J.002> f'<2 (Ro.~--------- v~L..c>M~: f:.--rA0'6:J to2•3s: Ro"~=-.(i,oo8~'".,.~~41-'+F.,. .. r:(2<>sFT}·(·Iyd') __ 6,46Z.S"yd' . _ 2 . . · z:"?n"S ----~~=s~~C)~---------- --------;;,..Az+ ~s_ 1-o tJ no: 'Roc..~<. -::. ~11 "_,.z. t o ~-r"'-) .6c~_s_ "'_,.)·( ____ 1'i ___ ·ds ...... _._)·····_-_·_-= z,ois.£3 yd 3 . . -z __ -• 21;::-rS . . . ~ \l)oolg•-Dn>ftfng\CIIonto-A-H\,DENISCH IINES\001-Wtulol•g Dtuwlogo\STEI£\100Q740 BCRAOW CELL 1 NORTHERN OUTSLOPE TYPICAL CROSS-SECTION TOP OF ET COVER RANDOM FILL CROSS-SECTIONAL AREA: 324SF RIP RAP CROSS-SECTIONAL AREA: 82 SF 5 RIP RAP BEDDING CROSS-SECTIONAL AREA: 45SF AVG. HEIGHT: 18FT. PROJ OENISOJ)~~ r.mTTTl£.,-------w-HI_TE_ME_SA_M_ILL_RE_cLAMA_T_Io_N _ ___, • MW H MINES Denison Mines (USA) Corp SLOPE AREA CALCULATIONS CELL 1 I».TE SEP 2011 FlU: NANE 1009740 BORROW Franklin Drilling & Blasting, Inc. P .0. Box 2246 Durango, CO 81392 Phone: 970-259-5620 Fax: 970-259-1304 Mobile: 970-259-4167 Email: office@franklinblasting.com Ms. Dawn Gagon Denison Mines PO Box809 Blanding, UT 84511 February 18, 2011 Re: Spillway Blasting in Blanding, Utah . We received your e-mail request for cost of drilling and blasting a spillway at your Mine site in Blanding, Utah. The information we now have is an area of approximately 150' wide by 1200' long with an average depth of about 10', generating in the neighborhood of 67,000 cubic yards in place. If this is correct, with a 9 feet by 9 feet pattern our price would be $2.25 per in-bank cubic yard for dry conditions. If water infiltrates into the bore holes and requires wet hole product, we will charge an additional fee. The fee will be the invoice cost of wet hole product delivered, plus 25% mark up to cover additional labor. This price reflects higher fuel and nitrogen prices today. We do not know how long these prices will remain at these levels, so we will qualify our bid. This bid will be good to October 1, 2011. · Our mobilization for 2 drills and supplies will be $7000. Payable when we mob in and start. Production rates of about 2000 cubic yards per drill/per day can be expected. With two drills drilling, and a 90% availability rate, that will be about 3600 cubic yards drilled per day. This should amount to about 25 working days. Please call if you have any further questions. Regards, Jeff Franklin/President/Owner 1 Cell 2 RECLAMATION OF CELL 2 RECLAMATION OF CELL 2 Place Radon Attenuation and Grading Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 879 $184,899 Cat 637 Scraper Operators hrs $19.31 879 $16,972 Cat D8N Dozer With Ripper hrs $95.82 220 $21,080 Cat D8N Dozer Operator hrs $20.65 220 $4,544 Cat D7 Dozer hrs $81.27 220 $17,880 Cat D7 Dozer Operator hrs $20.65 220 $4,544 Cat 14G Motorgrader hrs $71.34 220 $15,694 Cat 14G Motorgrader Operator hrs $20.62 220 $4,537 Equipment Maintenance (Butler) hrs $18.46 1,539 $28,405 Total Place Radon Attenuation and Grading Layer $298,554 Place Compacted Radon Attenuation Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 217 $45,646 Cat 637 Scraper Operators hrs $19.31 217 $4,190 Cat 825 Compactor hrs $97.64 55 $5,370 Cat 825 Compactor Operator hrs $14.22 55 $782 Cat D8N Dozer With Ripper hrs $95.82 55 $5,270 Cat D8N Dozer Operator hrs $20.65 55 $1,136 Cat D7 Dozer hrs $81.27 55 $4,470 Cat D7 Dozer Operator hrs $20.65 55 $1,136 Cat 651 Waterwagon hrs $113.30 55 $6,231 Cat 651 Waterwagon Operator hrs $18.16 55 $999 Cat 14G Motorgrader hrs $71.34 55 $3,923 Cat 14G Motorgrader Operator hrs $20.62 55 $1,134 Equipment Maintenance (Butler) hrs $18.46 492 $9,081 Total Place Compacted Radon Attenuation Layer $89,369 Place Water Storage Layer (42") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 1,572 $330,673 Cat 637 Scraper Operators hrs $19.31 1,572 $30,352 Cat D8N Dozer With Ripper hrs $95.82 393 $37,656 Cat D8N Dozer Operator hrs $20.65 393 $8,117 Cat D7 Dozer hrs $81.27 393 $31,941 Cat D7 Dozer Operator hrs $20.65 393 $8,117 Cat 14G Motorgrader hrs $71.34 393 $28,035 Cat 14G Motorgrader Operator hrs $20.62 393 $8,105 Equipment Maintenance (Butler) hrs $18.46 2,751 $50,775 Total Place Water Storage Layer (42")$533,770 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 2 Erosion Protection Layer (6") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 213 $44,805 Cat 637 Scraper Operators hrs $19.31 213 $4,113 Cat D8N Dozer With Ripper hrs $81.27 59 $4,795 Cat D8N Dozer Operator hrs $20.65 59 $1,219 Cat D7 Dozer hrs $81.27 59 $4,795 Cat D7 Dozer Operator hrs $20.65 59 $1,219 Cat 14G Motorgrader hrs $71.34 115 $8,204 Cat 14G Motorgrader Operator hrs $20.62 115 $2,372 Rock Mulch Cost Delivered CY $12.77 5,000 $63,830 Equipment Maintenance (Butler) hrs $18.46 446 $8,232 Total Place Upper Random Fill $143,581 Place Compacted Outslope Fill Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 37 $7,783 Cat 637 Scraper Operators hrs $19.31 37 $714 Cat 825 Compactor hrs $97.64 10 $976 Cat 825 Compactor Operator hrs $14.22 10 $142 Cat D8N Dozer With Ripper hrs $81.27 10 $813 Cat D8N Dozer Operator hrs $20.65 10 $207 Cat D7 Dozer hrs $81.27 10 $813 Cat D7 Dozer Operator hrs $20.65 10 $207 Cat 651 Waterwagon hrs $113.30 10 $1,133 Cat 651 Waterwagon Operator hrs $18.16 10 $182 Cat 14G Motorgrader hrs $71.34 10 $713 Cat 14G Motorgrader Operator hrs $20.62 10 $206 Equipment Maintenance (Butler) hrs $18.46 87 $1,606 Total Place Compacted Outslope Fill $15,494 Rock Armor and Rip Rap Filter Resource Description Units Cost/Unit Task Units Task Cost Cat D7 Dozer hrs $81.27 53 $4,308 Cat D7 Dozer Operator hrs $20.65 53 $1,095 Cat 651 Waterwagon hrs $113.30 53 $6,005 Cat 651 Waterwagon Operator hrs $18.16 53 $963 Cat 14G Motorgrader hrs $71.34 53 $3,781 Cat 14G Motorgrader Operator hrs $20.62 53 $1,093 Rock Cost Delivered CY $12.77 8,000 $102,127 Equipment Maintenance (Butler) hrs $18.46 159 $2,935 Total Place Rock Armor and Rip Rap Filter $122,305 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 2 Quality Control Resource Description Units Cost/Unit Task Units Task Cost Quality Control Contractor hrs $62.00 1,016 $62,992 Total Quality Control $62,992 TOTAL RECLAMATION OF CELL 2 $1,266,066 Notes and Assumptions: - Quality control contractor is assumed to be necessary for duration of material placement plus 20% for reporting. - To blend topsoil and rock mulch in the Erosion Protection Layer, it is assumed that materials will be windrowed and "bladed" three times by motograder. 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Volume Calculation - Cell 2 Updated 09/15/11 1) Area of Cell 2 - 3,021,700 sq ft = 69.37 acres 2) Assumptions - All volumes are presented in bank cubic yards (BCY) unless otherwise noted * Indicates volume is presented as in-place volume - Rock for rip rap armor, rip rap bedding layer and rock mulch will come from an off-site gravel source one (1) mile north of Blanding. Rock will be produced through screening, stockpiled and trucked to the site at the time of use. Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 3) Radon Attenuation and Grading Layer remaining to be placed Random fill placed at 80% relative compaction =230,748 cubic yards Use 231,000 cubic yards 4) Compacted Radon Attenuation Layer Random fill placed at 95% relative compaction =56,032 cubic yards Use 57,000 cubic yards 5) Water Storage/Biointrusion/Frost Protection/Radon Attenuation Layer Random fill placed at 85% relative compaction =391,703 cubic yards Use 392,000 cubic yards Volume Calculation Cell 2 Rev 5.0.xls Volume Calculation - Cell 2 (con't) page 2 6) Erosion Protection Layer A) Topsoil mixed with 25% gravel placed at 85% relative compaction = 19,429 cubic yards Use 20,000 cubic yards B) Topsoil placed at 85% relative compaction = 36,529 Use 37,000 cubic yards 7) Cell 2 West Exterior Slope ( Slope #3 ) Average height 6 feet Length 460 feet A) Random Fill Placed at 95% relative compaction 90 square feet (90 square feet X 460 linear feet) = 41,400 cubic feet/ 27 = 1,714 cubic yards Use 1,800 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 15 square feet (15 square feet X 460 linear feet) = 6,900 cubic feet/ 27 = 256 cubic yards * Use 300 cubic yards * b) Rip Rap Armor 12" thick 28 square feet (28 square feet X 460 linear feet) = 12,880 cubic feet/ 27 = 477 cubic yards * Use 500 cubic yards * C) Rip Rap Apron at toe of slope Length = 460 feet Width = 10 feet a) Rip Rap Armor Thickness = 2 feet 9,200 cubic feet/ 27 = 341 cubic yards * Use 400 cubic yards * Total West Slope Rip Rap Bedding Layer 300 cubic yards * Total West Slope Rip Rap Armor 900 cubic yards * 8) Cell 2 East Exterior Slope ( Slope #4 ) Average height 5 feet Length 1,300 feet A) Random Fill Placed at 95% relative compaction 63 square feet (63 square feet X 1,300 linear feet) = 81,900 cubic feet/ 27 = 3,390 cubic yards Use 3,400 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 13 square feet (13 square feet X 1,300 linear feet) = 16,900 cubic feet/ 27 = 626 cubic yards * Use 700 cubic yards * Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = (2 ft X 10 ft X 460 ft) = Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 2 Rev 5.0.xls Volume Calculation - Cell 2 (con't) page 3 b) Rip Rap Armor 12" thick 23 square feet (23 square feet X 1,300 linear feet) = 29,900 cubic feet/ 27 = 1,107 cubic yards * Use 1,200 cubic yards * C) Rip Rap Apron at toe of slope Length = 1,300 feet Width = 10 feet a) Rip Rap Armor Thickness = 2 feet 26,000 cubic feet/ 27 = 963 cubic yards * Use 1,000 cubic yards * Total East Slope Rip Rap Bedding Layer 700 cubic yards * Total East Slope Rip Rap Armor 2,200 cubic yards * 9) Cell 2 North Exterior Slope ( Slope #2 ) Common with Mill Yard Average height 5 feet Length 1,000 feet A) Random Fill Placed at 95% relative compaction 63 square feet (63 square feet X 1,000 linear feet) = 63,000 cubic feet/ 27 = 2,608 cubic yards Use 2,700 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 13 square feet (13 square feet X 1,000 linear feet) = 13,000 cubic feet/ 27 = 481 cubic yards * Use 500 cubic yards * b) Rip Rap Armor 12" thick 23 square feet Cross-Sectional Area = (2 ft X 10 ft X 1,300 ft) = Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 2 Rev 5.0.xls Volume Calculation - Cell 2 (con't) page 4 (23 square feet X 1,000 linear feet) = 23,000 cubic feet/ 27 = 852 cubic yards * Use 900 cubic yards * C) Rip Rap Apron at toe of slope Length = 1,000 feet Width = 10 feet a) Rip Rap Armor Thickness = 2 feet 20,000 cubic feet/ 27 = 741 cubic yards * Use 800 cubic yards * Total North Exterior Slope Rip Rap Bedding Layer 500 cubic yards * Total North Exterior Slope Rip Rap Armor 1,700 cubic yards * 10) Cell 2 North Interior Slope ( Slope #1 ) Common with Cell #1 Average height 3 feet Length 860 feet A) Random Fill - Already Included in Top Surface Quantity Estimates B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 9 square feet (9 square feet X 860 linear feet) = 7,740 cubic feet/ 27 = 287 cubic yards * Use 300 cubic yards * b) Rip Rap Armor 12" thick 14 square feet (14 square feet X 860 linear feet) = 12,040 cubic feet/ 27 = 446 cubic yards * Use 500 cubic yards * Cross-Sectional Area = Cross-Sectional Area = (2 ft X 10 ft X 1,000 ft) = Volume Calculation Cell 2 Rev 5.0.xls Volume Calculation - Cell 2 (con't) page 5 Total North Interior Slope Rip Rap Bedding Layer 300 cubic yards * Total North Interior Slope Rip Rap Armor 500 cubic yards * Volume Summary - Cell 2 Radon Attenuation and Grading Layer (CY) Compacted Radon Attenuation Layer (CY) Water Storage Layer (CY) Compacted Outslope Fill (CY) Total Random Fill (CY) Erosion Protection Layer (CY) * Rip Rap Bedding Layer (CY) * Rip Rap Armor (CY) * Top of Cell 231,000 57,000 392,000 0 680,000 57,000 0 0 North ( Slope #1 ) 0 0 0 0 0 0 300 500 North ( Slope #2 ) 0 0 0 2,700 2,700 0 500 1,700 West ( Slope #3 ) 0 0 0 1,800 1,800 0 300 900 East ( Slope #4 ) 0 0 0 3,400 3,400 0 700 2,200 Totals 231,000 57,000 392,000 8,000 688,000 57,000 2,000 6,000 Volume Calculation Cell 2 Rev 5.0.xls Volume Calculation - Cell 2 (con't) page 6 Cell 2 Reclamation Cat 637 Resource Requirements Volume Route CY/hr % Equip. Hr. (CY) Radon Attenuation and Grading Layer Tailings Surface 231,000 5 263 100% 879 Compacted Radon Attenuation Layer Tailings Surface 57,000 5 263 100% 217 Water Storage Layer Tailings Surface 103,000 5 263 26% 392 Tailings Surface 289,000 6 245 74% 1,180 Compacted Outslope Fill Outslopes 8,000 6 245 100% 33 Erosion Protection Layer 1 Tailings Surface 52,000 6 245 100% 213 1 Volume includes topsoil only (does not include rock mulch) 2 Rock mulch, rip rap armor, and rip rap bedding layer will be hauled using highway trucks 13,000 cubic yards (CY) 38 CY per hour times 8 trucks 304 CY per hour delivered Assume 25% extra time for spreading, loading and screen wait 304 / 1.25 243.2 CY per hour 53 Hours Rock Mulch, Rip Rap Armor, and Rip Rap Bedding Layer Production Cell 2 Volume Calculation Cell 2 Rev 5.0.xls CELL 2 EASTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION RIP RAP BEDDING CROSS-SECTIONAL AREA: 13 SF _j GROUND SURFACE CELL 2 NORTHEASTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION CELL 2 WESTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION RIP RAP BEDDIN(l...t CROSS-SECTIONAL AREA: 15SF RAP CROSS-SECTIONAL AREA: 28SF _j CELL 2 NORTH INTERIOR SLOPE COMMON WITH CELL #1 TYPICAL CROSS-SECTION RIP RAP CROSS-SECTIONAL AREA: 14SF GROUND SURFACE TOP OF ET COVER TOP OF ET COVER RIP RAP BEDDINC;...t CROSS-SECTIONAL AREA: 13SF _j GROUND SURFACE OENISOJ)~~ MINES RIP RAP BEDDING CROSS-SECTIONAL AREA:9SF PROJECT 1T11..E Denison Mines (USA) Corp WHITE MESA MILL RECLAMATION SLOPE AREA CALCULATIONS CELL2 TOP OF ET COVER <I>MWH DATE SEP 2011 FlL£ NAWE 10119740 BORROW Cell 3 RECLAMATION OF CELL 3 RECLAMATION OF CELL 3 Dewatering of Cell 3 Resource Description Units Cost/Unit Task Units Task Cost Dewatering of Cell 3 hrs $0.48 62,400 $30,000 Total Dewatering of Cell 3 $30,000 Place Radon Attenuation and Grading Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 1,821 $383,051 Cat 637 Scraper Operators hrs $19.31 1,821 $35,159 Cat D8N Dozer With Ripper hrs $95.82 456 $43,693 Cat D8N Dozer Operator hrs $20.65 456 $9,418 Cat D7 Dozer hrs $81.27 456 $37,061 Cat D7 Dozer Operator hrs $20.65 456 $9,418 Cat 14G Motorgrader hrs $71.34 456 $32,529 Cat 14G Motorgrader Operator hrs $20.62 456 $9,404 Equipment Maintenance (Butler) hrs $18.46 3,189 $58,860 Total Place Radon Attenuation and Grading Layer $618,592 Place Compacted Radon Attenuation Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 179 $37,653 Cat 637 Scraper Operators hrs $19.31 179 $3,456 Cat 825 Compactor hrs $97.64 45 $4,394 Cat 825 Compactor Operator hrs $14.22 45 $640 Cat D8N Dozer With Ripper hrs $95.82 45 $4,312 Cat D8N Dozer Operator hrs $20.65 45 $929 Cat D7 Dozer hrs $81.27 45 $3,657 Cat D7 Dozer Operator hrs $20.65 45 $929 Cat 651 Waterwagon hrs $113.30 45 $5,098 Cat 651 Waterwagon Operator hrs $18.16 45 $817 Cat 14G Motorgrader hrs $71.34 45 $3,210 Cat 14G Motorgrader Operator hrs $20.62 45 $928 Equipment Maintenance (Butler) hrs $18.46 404 $7,457 Total Place Compacted Radon Attenuation Layer $73,481 Place Water Storage Layer (42") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 1,143 $240,432 Cat 637 Scraper Operators hrs $19.31 1,143 $22,069 Cat D8N Dozer With Ripper hrs $95.82 286 $27,404 Cat D8N Dozer Operator hrs $20.65 286 $5,907 Cat D7 Dozer hrs $81.27 286 $23,244 Cat D7 Dozer Operator hrs $20.65 286 $5,907 Cat 14G Motorgrader hrs $71.34 286 $20,402 Cat 14G Motorgrader Operator hrs $20.62 286 $5,898 Equipment Maintenance (Butler) hrs $18.46 2,001 $36,933 Total Place Water Storage Layer (42")$388,195 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 3 Erosion Protection Layer (6") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 193 $40,598 Cat 637 Scraper Operators hrs $19.31 193 $3,726 Cat D8N Dozer With Ripper hrs $81.27 49 $3,982 Cat D8N Dozer Operator hrs $20.65 49 $1,012 Cat D7 Dozer hrs $81.27 49 $3,982 Cat D7 Dozer Operator hrs $20.65 49 $1,012 Cat 14G Motorgrader hrs $71.34 49 $3,495 Cat 14G Motorgrader Operator hrs $20.62 49 $1,010 Equipment Maintenance (Butler) hrs $18.46 340 $6,275 Total Place Upper Random Fill $65,094 Place Compacted Outslope Fill Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 20 $4,207 Cat 637 Scraper Operators hrs $19.31 20 $386 Cat 825 Compactor hrs $97.64 5 $488 Cat 825 Compactor Operator hrs $14.22 5 $71 Cat D8N Dozer With Ripper hrs $81.27 5 $406 Cat D8N Dozer Operator hrs $20.65 5 $103 Cat D7 Dozer hrs $81.27 5 $406 Cat D7 Dozer Operator hrs $20.65 5 $103 Cat 651 Waterwagon hrs $113.30 5 $566 Cat 651 Waterwagon Operator hrs $18.16 5 $91 Cat 14G Motorgrader hrs $71.34 5 $357 Cat 14G Motorgrader Operator hrs $20.62 5 $103 Equipment Maintenance (Butler) hrs $18.46 45 $831 Total Place Compacted Outslope Fill $8,119 Rock Armor and Rip Rap Filter Resource Description Units Cost/Unit Task Units Task Cost Cat D7 Dozer hrs $81.27 25 $2,032 Cat D7 Dozer Operator hrs $20.65 25 $516 Cat 651 Waterwagon hrs $113.30 25 $2,832 Cat 651 Waterwagon Operator hrs $18.16 25 $454 Cat 14G Motorgrader hrs $71.34 25 $1,783 Cat 14G Motorgrader Operator hrs $20.62 25 $516 Rock Cost Delivered CY $12.77 6,000 $76,595 Equipment Maintenance (Butler) hrs $18.46 75 $1,384 Total Place Rock Armor and Rip Rap Filter $86,113 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 3 Quality Control Resource Description Units Cost/Unit Task Units Task Cost Quality Control Contractor hrs $62.00 1,040 $64,480 Total Quality Control $64,480 TOTAL RECLAMATION OF CELL 3 $1,334,075 Notes and Assumptions: - Quality control contractor is assumed to be necessary for duration of material placement plus 20% for reporting. - Erosion Protection Layer for Cell 3 does not require rock mulch. 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Volume Calculation - Cell 3 Updated 09/15/11 1) Area of Cell 4A - 3,150,200 sq ft = 72.32 acres 2) Assumptions - All volumes are presented in bank cubic yards (BCY) unless otherwise noted * Indicates volume is presented as in-place volume - Rock for rip rap armor, rip rap bedding layer and rock mulch will come from an off-site gravel source one (1) mile north of Blanding. Rock will be produced through screening, stockpiled and trucked to the site at the time of use. Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 3) Radon Attenuation and Grading Layer remaining to be placed Random fill placed at 80% relative compaction =543,007 cubic yards Use 544,000 cubic yards 4) Compacted Radon Attenuation Layer Random fill placed at 95% relative compaction =63,517 cubic yards Use 64,000 cubic yards 5) Water Storage/Biointrusion/Frost Protection/Radon Attenuation Layer Random fill placed at 85% relative compaction =408,356 cubic yards Use 409,000 cubic yards Volume Calculation Cell 3 Rev 5.0.xls Volume Calculation - Cell 3 (con't) page 2 6) Erosion Protection Layer Topsoil placed at 85% relative compaction = 58,337 cubic yards Use 59,000 cubic yards 7) Cell 3 North Slope ( Slope #8 ) common with Cell 2 Internal transition slope armored with rip rap and bedding layer. Average height 3 feet Length 950 feet A) Random Fill - none necessary B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 8 square feet (8 square feet X 950 linear feet) =7,600 cubic feet/ 27 =281 cubic yards * Use 300 cubic yards * b) Rip Rap Armor 12" thick 15 square feet (15 square feet X 950 linear feet) =14,250 cubic feet/ 27 =528 cubic yards * Use 600 cubic yards * 8) Cell 3 West Exterior Slope ( Slope #6 ) Average height 7 feet Length 1,150 feet A) Random Fill Placed at 95% relative compaction 123 square feet (123 square feet X 1,150 linear feet) =141,450 cubic feet/ 27 =5,855 cubic yards Use 5,900 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 17 square feet (17 square feet X 1,150 linear feet) =19,550 cubic feet/ 27 =724 cubic yards * Use 800 cubic yards * Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 3 Rev 5.0.xls Volume Calculation - Cell 3 (con't) page 3 b) Rip Rap Armor 12" thick 32 square feet (32 square feet X 1,150 linear feet) =36,800 cubic feet/ 27 =1,363 cubic yards * Use 1,400 cubic yards * C) Rip Rap Apron at toe of slope Length = 1,150 feet Width = 10 feet a) Rip Rap Bedding Layer 6" thick 5 square feet (5 square feet X 1,150 linear feet) =5,750 cubic feet/ 27 =213 cubic yards * Use 300 cubic yards * b) Rip Rap Armor Thickness = 2 feet 23,000 cubic feet/ 27 =852 cubic yards * Use 900 cubic yards * Total West Slope Rip Rap Bedding Layer 1,100 cubic yards * Total West Slope Rip Rap Armor 2,300 cubic yards * 8) Cell 3 East Exterior Slope ( Slope #9 ) Average height 3.5 feet Length 540 feet A) Random Fill Placed at 95% relative compaction 31 square feet (31 square feet X 540 linear feet) =16,740 cubic feet/ 27 =693 cubic yards Use 700 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 9 square feet (9 square feet X 540 linear feet) =4,860 cubic feet/ 27 =180 cubic yards * Use 200 cubic yards * b) Rip Rap Armor 12" thick 18 square feet (18 square feet X 540 linear feet) =9,720 cubic feet/ 27 =360 cubic yards * Use 400 cubic yards * 0.5 ft X 10 ft = Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = (2 ft X 10 ft X 1,150 ft) = Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 3 Rev 5.0.xls Volume Calculation - Cell 3 (con't) page 4 C) Rip Rap Apron at toe of slope Length = 540 feet Width = 10 feet a) Rip Rap Bedding Layer 6" thick 5 square feet (5 square feet X 540 linear feet) =2,700 cubic feet/ 27 =100 cubic yards * Use 100 cubic yards * b) Rip Rap Armor Thickness = 2 feet 10,800 cubic feet/ 27 =400 cubic yards * Use 400 cubic yards * Total East Slope Rip Rap Bedding Layer 300 cubic yards * Total East Slope Rip Rap Armor 800 cubic yards * Volume Calculation - Cell 3 (con't) page 5 Volume Summary - Cell 3 Radon Attenuation and Grading Layer (CY) Compacted Radon Attenuation Layer (CY) Water Storage Layer (CY) Compacted Outslope Fill (CY) Total Random Fill (CY) Erosion Protection Layer (CY) * Rip Rap Bedding Layer (CY) * Rip Rap Armor (CY) * Top of Cell 544,000 64,000 409,000 0 1,017,000 59,000 0 0 West ( Slope #6 ) 0 0 0 5,900 5,900 0 1,100 2,300 North ( Slope #8 ) 0 0 0 0 0 0 300 600 East ( Slope #9 ) 0 0 0 700 700 0 300 800 Totals 544,000 64,000 409,000 7,000 1,024,000 59,000 2,000 4,000 (2 ft X 10 ft X 540 ft) = Cross-Sectional Area = 0.5 ft X 10 ft = Volume Calculation Cell 3 Rev 5.0.xls Volume Calculation - Cell 3 (con't) page 5 Cell 3 Reclamation Cat 637 Resource Requirements Volume Route CY/hr % Equip. Hr. (CY) Radon Attenuation and Grading Layer Tailings Surface 420,000 3 285 77% 1,474 Tailings Surface 124,000 4 358 23% 347 Compacted Radon Attenuation Layer Tailings Surface 64,000 4 358 100% 179 Water Storage Layer Tailings Surface 409,000 4 358 100% 1,143 Compacted Outslope Fill Outslopes 7,000 4 358 100% 20 Erosion Protection Layer 1 Tailings Surface 39,000 9 291 66% 134 Tailings Surface 20,000 10 340 34%59 1 Erosion Protection Layer for Cell 3 does not require rock mulch 2 Rip rap armor and rip rap bedding layer will be hauled using highway trucks 6,000 cubic yards (CY) 38 CY per hour times 8 trucks 304 CY per hour delivered Assume 25% extra time for spreading, loading and screen wait 304 / 1.25 243.2 CY per hour 25 Hours Rip Rap Armor and Rip Rap Bedding Layer Production Cell 3 Volume Calculation Cell 3 Rev 5.0.xls TOP OF ET COVER CELL 3 NORTHERN SLOPE COMMON WITH CELL 2 TYPICAL CROSS-SECTION RIP RAP BEDDING CROSS-5ECTIONAL AREA: 8SF RIP RAP CROSS-5ECTIONAL AREA: 15SF TOP OF ET COVER CELL 3 EASTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION RIP RAP CROSS-SECTIONAL AREA: 18SF RIP RAP BEDDING \------:--..1.....-~r7":!~~:---CROSS-SECTIONAL I ,-,..-._-~...,1 AREA: 9 SF RANDOM FILL CROSS-SECTIONAL AREA: 31 SF SURFACE CELL 3 WESTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION TOP OF ET COVER RANDOM FILL CROSS-SECTIONAL AREA: 123SF RIP RAP BEDDING CROSS-SECTIONAL AREA: 17SF PROJECr _j OENISOJ)~~ WHITE MESA MILL RECLAMATION MINES GROUND SURFACE ((D) MWH Denison Mines (USA) Corp SLOPE AREA CALCULATIONS CELL3 DATE SEP2011 m.E NIWE 1009740 BORROW Cell 4A RECLAMATION OF CELL 4A RECLAMATION OF CELL 4A Dewatering of Cell 4A Resource Description Units Cost/Unit Task Units Task Cost Dewatering of Cell 4A hrs $0.48 62,400 $30,000 Total Dewatering of Cell 4A $30,000 Place Radon Attenuation and Grading Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 522 $109,804 Cat 637 Scraper Operators hrs $19.31 522 $10,079 Cat D8N Dozer With Ripper hrs $95.82 131 $12,552 Cat D8N Dozer Operator hrs $20.65 131 $2,706 Cat D7 Dozer hrs $81.27 131 $10,647 Cat D7 Dozer Operator hrs $20.65 131 $2,706 Cat 14G Motorgrader hrs $71.34 131 $9,345 Cat 14G Motorgrader Operator hrs $20.62 131 $2,702 Equipment Maintenance (Butler) hrs $18.46 915 $16,888 Total Place Radon Attenuation and Grading Layer $177,427 Place Compacted Radon Attenuation Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 634 $133,363 Cat 637 Scraper Operators hrs $19.31 634 $12,241 Cat 825 Compactor hrs $97.64 159 $15,525 Cat 825 Compactor Operator hrs $14.22 159 $2,261 Cat D8N Dozer With Ripper hrs $95.82 159 $15,235 Cat D8N Dozer Operator hrs $20.65 159 $3,284 Cat D7 Dozer hrs $81.27 159 $12,923 Cat D7 Dozer Operator hrs $20.65 159 $3,284 Cat 651 Waterwagon hrs $113.30 159 $18,014 Cat 651 Waterwagon Operator hrs $18.16 159 $2,888 Cat 14G Motorgrader hrs $71.34 159 $11,342 Cat 14G Motorgrader Operator hrs $20.62 159 $3,279 Equipment Maintenance (Butler) hrs $18.46 1,429 $26,375 Total Place Compacted Radon Attenuation Layer $260,014 Place Water Storage Layer (42") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 796 $167,440 Cat 637 Scraper Operators hrs $19.31 796 $15,369 Cat D8N Dozer With Ripper hrs $95.82 199 $19,068 Cat D8N Dozer Operator hrs $20.65 199 $4,110 Cat D7 Dozer hrs $81.27 199 $16,174 Cat D7 Dozer Operator hrs $20.65 199 $4,110 Cat 14G Motorgrader hrs $71.34 199 $14,196 Cat 14G Motorgrader Operator hrs $20.62 199 $4,104 Equipment Maintenance (Butler) hrs $18.46 1,393 $25,711 Total Place Water Storage Layer (42")$270,280 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 4A Erosion Protection Layer (6") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 86 $18,090 Cat 637 Scraper Operators hrs $19.31 86 $1,660 Cat D8N Dozer With Ripper hrs $81.27 29 $2,357 Cat D8N Dozer Operator hrs $20.65 29 $599 Cat D7 Dozer hrs $81.27 29 $2,357 Cat D7 Dozer Operator hrs $20.65 29 $599 Cat 14G Motorgrader hrs $71.34 86 $6,135 Cat 14G Motorgrader Operator hrs $20.62 86 $1,774 Rock Mulch Cost Delivered CY $12.77 9,000 $114,893 Equipment Maintenance (Butler) hrs $18.46 230 $4,245 Total Place Upper Random Fill $152,709 Place Compacted Outslope Fill Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 364 $76,568 Cat 637 Scraper Operators hrs $19.31 364 $7,028 Cat 825 Compactor hrs $97.64 91 $8,886 Cat 825 Compactor Operator hrs $14.22 91 $1,294 Cat D8N Dozer With Ripper hrs $81.27 91 $7,396 Cat D8N Dozer Operator hrs $20.65 91 $1,879 Cat D7 Dozer hrs $81.27 91 $7,396 Cat D7 Dozer Operator hrs $20.65 91 $1,879 Cat 651 Waterwagon hrs $113.30 91 $10,310 Cat 651 Waterwagon Operator hrs $18.16 91 $1,653 Cat 14G Motorgrader hrs $71.34 91 $6,491 Cat 14G Motorgrader Operator hrs $20.62 91 $1,877 Equipment Maintenance (Butler) hrs $18.46 819 $15,116 Total Place Compacted Outslope Fill $147,774 Rock Armor and Rip Rap Filter Resource Description Units Cost/Unit Task Units Task Cost Cat D7 Dozer hrs $81.27 148 $12,029 Cat D7 Dozer Operator hrs $20.65 148 $3,057 Cat 651 Waterwagon hrs $113.30 148 $16,768 Cat 651 Waterwagon Operator hrs $18.16 148 $2,688 Cat 14G Motorgrader hrs $71.34 148 $10,558 Cat 14G Motorgrader Operator hrs $20.62 148 $3,052 Rock Cost Delivered CY $12.77 27,000 $344,680 Equipment Maintenance (Butler) hrs $18.46 444 $8,195 Total Place Rock Armor and Rip Rap Filter $401,026 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 4A Quality Control Resource Description Units Cost/Unit Task Units Task Cost Quality Control Contractor hrs $62.00 977 $60,574 Total Quality Control $60,574 TOTAL RECLAMATION OF CELL 4A $1,499,804 Notes and Assumptions: - Quality control contractor is assumed to be necessary for duration of material placement plus 20% for reporting. - To blend topsoil and rock mulch in the Erosion Protection Layer, it is assumed that materials will be windrowed and "bladed" three times by motograder. 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Volume Calculation - Cell 4A Updated 09/13/11 1) Area of Cell 4A - 1,857,300 sq ft = 42.64 acres 2) Assumptions - All volumes are presented in bank cubic yards (BCY) unless otherwise noted * Indicates volume is presented as in-place volume - Rock for rip rap armor, rip rap bedding layer and rock mulch will come from an off-site gravel source one (1) mile north of Blanding. Rock will be produced through screening, stockpiled and trucked to the site at the time of use. Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 3) Radon Attenuation and Grading Layer remaining to be placed Random fill placed at 80% relative compaction =157,384 cubic yards Use 158,000 cubic yards 4) Compacted Radon Attenuation Layer Random fill placed at 95% relative compaction =191,494 cubic yards Use 192,000 cubic yards 5) Water Storage/Biointrusion/Frost Protection/Radon Attenuation Layer Random fill placed at 85% relative compaction =240,761 cubic yards Use 241,000 cubic yards Volume Calculation Cell 4A Rev 5.0.xls Volume Calculation - Cell 4A (con't) page 2 6) Erosion Protection Layer Topsoil mixed with 25% gravel placed at 85% relative compaction = 34,394 cubic yards Use 35,000 cubic yards 7) Cell 4A South Dike, ( Slope #1 ) Average height 33 feet Length 1,400 feet A) Random Fill Placed at 95% relative compaction 1,703 square feet (1,703 square feet X 1,400 linear feet) = 2,384,200 cubic feet/ 27 = 98,692 cubic yards Use 98,700 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 82 square feet (82 square feet X 1,400 linear feet) = 114,800 cubic feet/ 27 = 4,252 cubic yards * Use 4,300 cubic yards * Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 4A Rev 5.0.xls Volume Calculation - Cell 4A (con't) page 3 b) Rip Rap Armor 12" thick 150 square feet (150 square feet X 1,400 linear feet) = 210,000 cubic feet/ 27 = 7,778 cubic yards * Use 7,800 cubic yards * C) Rip Rap Apron at toe of slope Does not run straight and parallel to slope. Length = 1,600 feet Width = 19 feet a) Rip Rap Armor Thickness = 3.75 feet 114,000 cubic feet/ 27 = 4,222 cubic yards * Use 4,300 cubic yards * Total South Dike Rip Rap Bedding Layer 4,300 cubic yards * Total South Dike Rip Rap Armor 12,100 cubic yards * 8) Cell 4A East Slope ( Slope #2 ) Average height 17 feet Length 1,300 feet A) Random Fill Placed at 95% relative compaction 560 square feet (560 square feet X 1,300 linear feet) = 728,000 cubic feet/ 27 = 30,135 cubic yards Use 30,200 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 42 square feet (42 square feet X 1,300 linear feet) = 54,600 cubic feet/ 27 = 2,022 cubic yards Use 2,100 cubic yards * b) Rip Rap Armor 12" thick 78 square feet (78 square feet X 1,300 linear feet) = 101,400 cubic feet/ 27 = 3,756 cubic yards * Use 3,800 cubic yards * C) Rip Rap Apron at toe of slope Length = 1,300 feet Width = 19 feet a) Rip Rap Armor Thickness = 3.75 feet 92,625 cubic feet/ 27 = 3,431 cubic yards * Use 3,500 cubic yards * Total East Slope Rip Rap Bedding Layer 2,100 cubic yards * Total East Slope Rip Rap Armor 7,300 cubic yards * (3.75 ft X 19 ft X 1,600 ft) = (3.75 ft X 19 ft X 1,300 ft) = Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = Volume Calculation Cell 4A Rev 5.0.xls Volume Calculation - Cell 4A (con't) page 4 Volume Summary - Cell 4A Radon Attenuation and Grading Layer (CY) Compacted Radon Attenuation Layer (CY) Water Storage Layer (CY) Compacted Outslope Fill (CY) Total Random Fill (CY) Erosion Protection Layer (CY) * Rip Rap Bedding Layer (CY) * Rip Rap Armor (CY) * Top of Cell 158,000 192,000 241,000 0 591,000 35,000 0 0 South ( Slope #1 )0 0 0 98,700 98,700 0 4,300 12,100 East ( Slope #2 )0 0 0 30,200 30,200 0 2,100 7,300 Totals 158,000 192,000 241,000 129,000 720,000 35,000 7,000 20,000 Volume Calculation Cell 4A Rev 5.0.xls Volume Calculation - Cell 4A (con't) page 5 Cell 4A Reclamation Cat 637 Resource Requirements Volume Route CY/hr % Equip. Hr. (CY) Radon Attenuation and Grading Layer Tailings Surface 158,000 2 303 100% 522 Compacted Radon Attenuation Layer Tailings Surface 192,000 2 303 100% 634 Water Storage Layer Tailings Surface 241,000 2 303 100% 796 Compacted Outslope Fill Outslopes 129,000 1 358 100% 361 Erosion Protection Layer 1 Tailings Surface 27,000 8 317 100% 86 1 Volume includes topsoil only (does not include rock mulch) 2 Rock mulch, rip rap armor, and rip rap bedding layer will be hauled using highway trucks 36,000 cubic yards (CY) 38 CY per hour times 8 trucks 304 CY per hour delivered Assume 25% extra time for spreading, loading and screen wait 304 / 1.25 243.2 CY per hour 148 Hours Rock Mulch, Rip Rap Armor, and Rip Rap Bedding Layer Production Cell 4A Volume Calculation Cell 4A Rev 5.0.xls TOPOFET CELL 4A SOUTHERN EXTERIOR SLOPE TYPICAL CROSS-SECTION CELL 48 SOUTHERN EXTERIOR SLOPE TYPICAL CROSS-SECTION RAP BEIJOING CROss..BECllONAL AREA:UIF TOPOP: OENISOJ)~~ MINES Denison Mines (USA) Corp CELL 4A EASTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION .17FT. RAPEEDDING CROBS-8ECT10Nolll. AREA: 428F CELL 48 WESTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION WHITE MESA MILL RECLAMATION SLOPE AREA CALCULATIONS CELLS 4A AND 48 <I>MWH Cell 4B RECLAMATION OF CELL 4B RECLAMATION OF CELL 4B Dewatering of Cell 4B Resource Description Units Cost/Unit Task Units Task Cost Dewatering of Cell 4B hrs $0.48 62,400 $30,000 Total Dewatering of Cell 4B $30,000 Place Radon Attenuation and Grading Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 525 $110,435 Cat 637 Scraper Operators hrs $19.31 525 $10,137 Cat D8N Dozer With Ripper hrs $95.82 132 $12,648 Cat D8N Dozer Operator hrs $20.65 132 $2,726 Cat D7 Dozer hrs $81.27 132 $10,728 Cat D7 Dozer Operator hrs $20.65 132 $2,726 Cat 14G Motorgrader hrs $71.34 132 $9,416 Cat 14G Motorgrader Operator hrs $20.62 132 $2,722 Equipment Maintenance (Butler) hrs $18.46 921 $16,999 Total Place Radon Attenuation and Grading Layer $178,537 Place Compacted Radon Attenuation Layer Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 651 $136,939 Cat 637 Scraper Operators hrs $19.31 651 $12,569 Cat 825 Compactor hrs $97.64 163 $15,916 Cat 825 Compactor Operator hrs $14.22 163 $2,318 Cat D8N Dozer With Ripper hrs $95.82 163 $15,618 Cat D8N Dozer Operator hrs $20.65 163 $3,366 Cat D7 Dozer hrs $81.27 163 $13,248 Cat D7 Dozer Operator hrs $20.65 163 $3,366 Cat 651 Waterwagon hrs $113.30 163 $18,468 Cat 651 Waterwagon Operator hrs $18.16 163 $2,960 Cat 14G Motorgrader hrs $71.34 163 $11,628 Cat 14G Motorgrader Operator hrs $20.62 163 $3,361 Equipment Maintenance (Butler) hrs $18.46 1,466 $27,058 Total Place Compacted Radon Attenuation Layer $266,816 Place Water Storage Layer (42") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 812 $170,806 Cat 637 Scraper Operators hrs $19.31 812 $15,678 Cat D8N Dozer With Ripper hrs $95.82 203 $19,451 Cat D8N Dozer Operator hrs $20.65 203 $4,193 Cat D7 Dozer hrs $81.27 203 $16,499 Cat D7 Dozer Operator hrs $20.65 203 $4,193 Cat 14G Motorgrader hrs $71.34 203 $14,481 Cat 14G Motorgrader Operator hrs $20.62 203 $4,186 Equipment Maintenance (Butler) hrs $18.46 1,421 $26,227 Total Place Water Storage Layer (42")$275,713 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 4B Erosion Protection Layer (6") Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 86 $18,090 Cat 637 Scraper Operators hrs $19.31 86 $1,660 Cat D8N Dozer With Ripper hrs $81.27 29 $2,357 Cat D8N Dozer Operator hrs $20.65 29 $599 Cat D7 Dozer hrs $81.27 29 $2,357 Cat D7 Dozer Operator hrs $20.65 29 $599 Cat 14G Motorgrader hrs $71.34 86 $6,135 Cat 14G Motorgrader Operator hrs $20.62 86 $1,774 Rock Mulch Cost Delivered CY $12.77 9,000 $114,893 Equipment Maintenance (Butler) hrs $18.46 230 $4,245 Total Place Upper Random Fill $152,709 Place Compacted Outslope Fill Resource Description Units Cost/Unit Task Units Task Cost Cat 637 Scraper hrs $210.35 238 $50,064 Cat 637 Scraper Operators hrs $19.31 238 $4,595 Cat 825 Compactor hrs $97.64 60 $5,859 Cat 825 Compactor Operator hrs $14.22 60 $853 Cat D8N Dozer With Ripper hrs $81.27 60 $4,876 Cat D8N Dozer Operator hrs $20.65 60 $1,239 Cat D7 Dozer hrs $81.27 60 $4,876 Cat D7 Dozer Operator hrs $20.65 60 $1,239 Cat 651 Waterwagon hrs $113.30 60 $6,798 Cat 651 Waterwagon Operator hrs $18.16 60 $1,090 Cat 14G Motorgrader hrs $71.34 60 $4,280 Cat 14G Motorgrader Operator hrs $20.62 60 $1,237 Equipment Maintenance (Butler) hrs $18.46 538 $9,930 Total Place Compacted Outslope Fill $96,937 Rock Armor and Rip Rap Filter Resource Description Units Cost/Unit Task Units Task Cost Cat D7 Dozer hrs $81.27 115 $9,347 Cat D7 Dozer Operator hrs $20.65 115 $2,375 Cat 651 Waterwagon hrs $113.30 115 $13,029 Cat 651 Waterwagon Operator hrs $18.16 115 $2,089 Cat 14G Motorgrader hrs $71.34 115 $8,204 Cat 14G Motorgrader Operator hrs $20.62 115 $2,372 Rock Cost Delivered CY $12.77 19,000 $242,552 Equipment Maintenance (Butler) hrs $18.46 345 $6,368 Total Place Rock Armor and Rip Rap Filter $286,335 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill RECLAMATION OF CELL 4B Quality Control Resource Description Units Cost/Unit Task Units Task Cost Quality Control Contractor hrs $62.00 911 $56,482 Total Quality Control $56,482 TOTAL RECLAMATION OF CELL 4B $1,343,529 Notes and Assumptions: - Quality control contractor is assumed to be necessary for duration of material placement plus 20% for reporting. - To blend topsoil and rock mulch in the Erosion Protection Layer, it is assumed that materials will be windrowed and "bladed" three times by motograder. 9/28/2011 - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Volume Calculation - Cell 4B Updated 09/15/11 1) Area of Cell 4A -1,895,700 sq ft = 43.52 acres 2) Assumptions - All volumes are presented in bank cubic yards (BCY) unless otherwise noted * Indicates volume is presented as in-place volume - Rock for rip rap armor, rip rap bedding layer and rock mulch will come from an off-site gravel source one (1) mile north of Blanding. Rock will be produced through screening, stockpiled and trucked to the site at the time of use. Belly dump trucks will dump gravel in windrows on the top and sides of the Cell. 3) Radon Attenuation and Grading Layer remaining to be placed Random fill placed at 80% relative compaction =158,146 cubic yards Use 159,000 cubic yards 4) Compacted Radon Attenuation Layer Random fill placed at 95% relative compaction =196,530 cubic yards Use 197,000 cubic yards 5) Water Storage/Biointrusion/Frost Protection/Radon Attenuation Layer Random fill placed at 85% relative compaction =245,741 cubic yards Use 246,000 cubic yards Volume Calculation Cell 4B Rev 5.0.xls Volume Calculation - Cell 4B (con't) page 2 6) Erosion Protection Layer Topsoil mixed with 25% gravel placed at 85% relative compaction = 35,106 cubic yards Use 36,000 cubic yards 7) Cell 4B South Dike, ( Slope #1 ) Average height 28 feet Length 1,400 feet A) Random Fill Placed at 95% relative compaction 1,291 square feet (1,291 square feet X 1,400 linear feet) =1,807,400 cubic feet/ 27 =74,816 cubic yards Use 74,900 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 70 square feet (70 square feet X 1,400 linear feet) =98,000 cubic feet/ 27 =3,630 cubic yards * Use 3,700 cubic yards * b) Rip Rap Armor 12" thick 127 square feet (127 square feet X 1,400 linear feet) =177,800 cubic feet/ 27 =6,585 cubic yards * Use 6,600 cubic yards * C) Rip Rap Apron at toe of slope Length = 1,400 feet Width = 19 feet a) Rip Rap Armor Thickness = 3.75 feet 99,750 cubic feet/ 27 =3,694 cubic yards * Use 3,700 cubic yards * Total South Dike Rip Rap Bedding Layer 3,700 cubic yards * Total South Dike Rip Rap Armor 10,300 cubic yards * Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = (3.75 ft X 19 ft X 1,400 ft) = Volume Calculation Cell 4B Rev 5.0.xls Volume Calculation - Cell 4B (con't) page 3 8) Cell 4B West Slope ( Slope #3 ) Average height 9 feet Length 1,300 feet A) Random Fill Placed at 95% relative compaction 180 square feet (180 square feet X 1,300 linear feet) =234,000 cubic feet/ 27 =9,686 cubic yards Use 9,700 cubic yards B) Outslope Armoring a) Rip Rap Bedding Layer 6" thick 22 square feet (22 square feet X 1,300 linear feet) =28,600 cubic feet/ 27 =1,059 cubic yards * Use 1,100 cubic yards * b) Rip Rap Armor 12" thick 41 square feet (41 square feet X 1,300 linear feet) =53,300 cubic feet/ 27 =1,974 cubic yards * Use 2,000 cubic yards * C) Rip Rap Apron at toe of slope Length = 1,300 feet Width = 10 feet a) Rip Rap Armor Thickness = 2 feet 26,000 cubic feet/ 27 =963 cubic yards * Use 1,000 cubic yards * Total West Slope Rip Rap Bedding Layer 1,100 cubic yards * Total West Slope Rip Rap Armor 3,000 cubic yards * Volume Summary - Cell 4B Radon Attenuation and Grading Layer (CY) Compacted Radon Attenuation Layer (CY) Water Storage Layer (CY) Compacted Outslope Fill (CY) Total Random Fill (CY) Erosion Protection Layer (CY) * Rip Rap Bedding Layer (CY) * Rip Rap Armor (CY) * Top of Cell 159,000 197,000 246,000 0 602,000 36,000 0 0 South ( Slope #1 ) 0 0 0 74,900 74,900 0 3,700 10,300 West ( Slope #3 ) 0 0 0 9,700 9,700 0 1,100 3,000 Totals 159,000 197,000 246,000 85,000 687,000 36,000 5,000 14,000 Cross-Sectional Area = Cross-Sectional Area = Cross-Sectional Area = (2 ft X 10 ft X 1,300 ft) = Volume Calculation Cell 4B Rev 5.0.xls Volume Calculation - Cell 4B (con't) page 4 Cell 4B Reclamation Cat 637 Resource Requirements Volume Route CY/hr % Equip. Hr. (CY) Radon Attenuation and Grading Layer Tailings Surface 159,000 2 303 100% 525 Compacted Radon Attenuation Layer Tailings Surface 197,000 2 303 100% 651 Water Storage Layer Tailings Surface 246,000 2 303 100% 812 Compacted Outslope Fill Outslopes 85,000 1 358 100% 238 Erosion Protection Layer 1 Tailings Surface 27,000 8 317 100%86 1 Volume includes topsoil only (does not include rock mulch) 2 Rock mulch, rip rap armor, and rip rap bedding layer will be hauled using highway trucks 28,000 cubic yards (CY) 38 CY per hour times 8 trucks 304 CY per hour delivered Assume 25% extra time for spreading, loading and screen wait 304 / 1.25 243.2 CY per hour 115 Hours Rock Mulch, Rip Rap Armor, and Rip Rap Bedding Layer Production Cell 4B Volume Calculation Cell 4B Rev 5.0.xls TOPOFET CELL 4A SOUTHERN EXTERIOR SLOPE TYPICAL CROSS-SECTION CELL 48 SOUTHERN EXTERIOR SLOPE TYPICAL CROSS-SECTION RAP BEIJOING CROss..BECllONAL AREA:UIF TOPOP: OENISOJ)~~ MINES Denison Mines (USA) Corp CELL 4A EASTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION .17FT. RAPEEDDING CROBS-8ECT10Nolll. AREA: 428F CELL 48 WESTERN EXTERIOR SLOPE TYPICAL CROSS-SECTION WHITE MESA MILL RECLAMATION SLOPE AREA CALCULATIONS CELLS 4A AND 48 <I>MWH Miscellaneous MISCELLANEOUS ITEMS MISCELLANEOUS ITEMS Equipment Mobilization Resource Description Units Cost/Unit Task Units Task Cost Butler Machinery Mobilization LS $386,600 1 $386,600 Other Equipment Mobilization LS $4,550 1 $4,550 Cranes LS $2,700 2 $5,400 Total Equipment Mobilization $396,550 Office Facilities Resource Description Units Cost/Unit Task Units Task Cost Install New Powerline LS $15,000 1 $15,000 Utilities for Offices months $1,000 36 $36,000 Temporary Office Trailer months $1,500 3 $4,500 Temporary Office Trailer, mob, demob & setup LS $3,000 1 $3,000 Total Office Facilities $58,500 Decontamination Pad Resource Description Units Cost/Unit Task Units Task Cost Laborers hrs $13 8,320 $104,046 Construct Wheel Wash Facility LS $180,000 1 $180,000 Facilities constructed in 2000 & 2008 ($180,000) Total Decontamination Facilities $104,046 Plug and Abandon WW2 Resource Description Units Cost/Unit Task Units Task Cost Laborers hrs $0 8,320 $0 Contract Services LS $20,000 1 $20,000 Total Plug and Abandon WW2 $20,000 Slimes Drain Evaporation Pond Resource Description Units Cost/Unit Task Units Task Cost 60 mil HDPE Liner sq. ft. $0.58 960,000 $556,800 Cat 637 Scraper hrs $210.35 100 $21,035 Cat 637 Scraper Operator hrs $19.31 100 $1,931 Cat 825 Compactor hrs $97.64 25 $2,441 Cat 825 Compactor Operator hrs $14.22 25 $355 Cat D7 Dozer hrs $81.27 25 $2,032 Cat D7 Dozer Operator hrs $20.65 25 $516 Cat 651 Waterwagon hrs $113.30 25 $2,832 Cat 651 Waterwagon Operator hrs $18.16 25 $454 Cat 14G Motorgrader hrs $71.34 25 $1,783 Cat 14G Motorgrader Operator hrs $20.62 25 $516 Equipment Maintenance (Butler) hrs $18.46 200 $3,691 Total Slimes Drain Evaporation Pond $594,388 MANAGEMENT/SUPPORT Resource Description Units Cost/Unit Task Units Task Cost Manager/Engineer hrs $59.06 6,240 $368,561 Radiation Safety Officer hrs $46.15 6,240 $287,969 Secretary hrs $18.66 6,240 $116,465 Clerk hrs $15.36 4,866 $74,726 Environmental Technician ( Part time, 4.5 years) hrs $25.99 7,300 $189,714 Maintenance Foreman hrs $33.86 6,240 $211,308 Chemist hrs $27.17 2,080 $56,513 Security hrs $10.00 18,720 $187,229 Safety Engineer hrs $25.99 4,160 $108,111 Misc. Materials & Supplies hrs $36.45 6,240 $227,448 Health Physics Costs hrs $64.81 2,080 $134,800 Environmental Monitoring Costs, Laboratory years $71,620.00 7.0 $501,340 Total Management/Support $2,464,184 TOTAL MISCELLANEOUS ITEMS $3,637,667 9/28/2011 - 8:42 AM - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Phone Call Summary From: Steve McManus (MWH Americas, Inc.) To: Kit Hawkins (Northwest Linings and Geotextile Products, Inc.) Phone #: (800) 729-6954 Date: September 26, 2011 12:35pm (MDT) Conversation: Steve inquired about a unit rate estimate for an evaporation pond liner (installed). 900,000- 1,000,000 square feet of liner, 4:1 side slopes, 60-mil smooth HDPE, public wages. Kit Hawkins estimated $0.55 – 0.58 per square foot of liner (installed). Rock Production ROCK PRODUCTION COST Assumptions: Rock is obtained from gravel source north of Blanding, Utah. BLM Public Pit Rip rap rock is processed by screening only, no crushing is required, 1.25 CY of feed for 1 CY of product Rip rap bedding and rock mulch are produced from rip rap reject Rock is produced and stockpiled at the site Site is 7 road miles from the mill; 6 miles of which is paved public highway Rock will be hauled in 22 CY bellydump trucks, contract haulers ($100.00/hr) Rock will be dumped in windrows on Tailings Cells by trucks, spread by grader, and spread by D7 Dozer Trucks can average 30 MPH and unloading/unloading take 5min each: 14miles / 30mph X 60min/hr + (2 X 5min) = 38min round trip Work hours are 50min long: 50min / 38min round trip = 1.3 round trips per hour Product Required (CY) Reject Factor Material Feed to Plant (CY) Plant Throughput (CY/hr) Plant Operating Hours Rip rap material fed to plant 54,000 25.0% 67,500 122 600 Rip rap bedding material fed to plant 21,000 10.0% 23,100 122 200 Rock mulch fed to plant 25,000 10.0% 27,500 122 300 100,000 1,100 PRODUCTION OF RIPRAP Resource Description Units Cost/Unit Task Units Task Cost Laborer hrs $12.51 1,100 $13,756 Cat D8N Dozer With Ripper hrs $95.82 367 $35,133 Cat D8N Dozer Operator hrs $20.65 367 $7,573 Cat 980 Loader hrs $93.97 1,100 $103,367 Cat 980 Loader Operator hrs $17.21 1,100 $18,935 Screening Plant w/conveyors* hrs $60.80 1,100 $66,875 BLM Usage Fee CY $0.60 100,000 $60,000 Contract Highway Trucks - Bellydumps** hrs $100.00 3,497 $349,650 Equipment Maintenance (Butler) hrs $18.46 1,467 $27,070 Mob/Demob and Screen Setup LS $7,000.00 1 $7,000 Total Production of Rip Rap $689,359 RIPRAP COST PER CUBIC YARD DELIVERED $12.77 * Cost Quoted from Power Motive Corporation, Denver, Colorado updated February 21, 2011 $7,000 plus $3,700 for conveyors, 176 hours per month for one month, plus screen set up at $2,000. Mob and Demob - 5,000.00$ ** Cost quoted from Dennis Cosby, Cosby Trucking, Inc., Blanding, Utah, Updated February 25, 2011 (includes ownership expense, fuel, maintanence and operator) 9/28/2011 - 8:42 AM - WMM Rec Plan Est Rev 5.0.xls International Uranium (USA) Corp. White Mesa Mill Dawn Gagon From: Sent: To: Subject: Jim Schmitt [jschmitt@powermotivecorp.com) Tuesday, February 22, 2011 6:20AM Dawn Gagan RE: Annual Request for Quote Good morning Dawn, 1 was trying to find the email that I sent you last year, but 1 couldn't. However, the rental rates are still the same as last year for 20 II Thanks, Jim Schmitt Area Manager Power Motive Corp. Mobile (719) 492-7378 jschmitt@powermotivecorp.com P~Cilol'r~IJU<ISuppnrii'...,Pir POWER MOTIVE CORPORATION From: Dawn Gagon fmailto:dgaqon@denisonmines.coml Sent: Monday, February 21, 201111:16 AM To: Jim Schmitt Subject: FW: Annual Request for Quote Importance: High DawnGagon t: 435-678-2221 x106 I f: 435-678-2224 6425 S. Highway 191, PO Box 809, Blanding, UT 84511 DENISON MINES (USA) CORP www.den.isonmines.com This e-mail is intended for the exclusive use of the person(s) mentioned as the recipienl(s). This message and any attached fi les with it are confidential and may contain privileged or proprietary information. lf you are not the intended recipient(s) please delete this message and notify the sender. You may not use. distribute print or copy this message if you are not the jntended recipient(s). 1 Amy Bushman From: Sent: To; Cc: Subject: Attachments: Deer Arrry, Brad Neptune (bneplune@powermoUvecorp.comj Tuesday, February24, 2009 9:33AM Amy Bushman Mike Norris 2512KT Saeen FNG_2512kt_2512k.pdf; FT _271 K_291 K pdf Thank you for the opponunity to quote a rental screen to OeniS<ln Mines. Lest year, per lhe February 22, 2008 quote, we quoted our 271 K plant and our 2512KT plant. I'm allaching spec sheets on each so you c!lfl aee what each scsaen and plant looks like. The 271 K plant does NOT have any on-plant stackers, but doss have a 4' x 10' two deck screen. You would need to rent ott plant hydraulic stackers to stack oul two products. It is also a 1\Jbber llred plant. The 2512KT is a Track Mounted plant that OOES have orrplanl stackers and can stack out three products right off of the plant. You do not need additional conveyors. Rental rates are the same as quoted last year. 271K Screen $ 7,000 r mo 25t 2KT Screen $12,800 /mo 36'' x 60' Hyd Stacker $ 1,500/mo 30" x 60' Hyd Slacker $ 2,200/mo 1he 271K Screen Is presently !led up on a rental. The 2512KT plant is sllllng 1dle In Cof()(ado Springs. I'd estimate delivery from C Spgs to Blanding to be approximately $2,500 Tho prl)sent purchase price we have on the 2512KT is $135,000, thus you may want to consider purchasing the J')tRrlt a!J OJ)posed to rentu'lg lt for $12,600 per month. Scteen cloth and installation of screen cloth will run about $2,000 total Please feel free to email or call with any additional questions Sincerely, Brad Neptune 97Q..9BS..5875 ASTEC MOBILE SCREENS The Fold ·n Go 2512KT is a mobile track screening plant that features a Kolberg® double deck screen for processing sand & gravel, topsoil, slag, crushed stone and recycled materials. This plant offers a standard inlet hopper chute for inline processing feed from crushing plant or feed conveyor. As with all Fold • n GI:P mobile screening plants, this plant provides easy to reach engine controls and grease points for routine service. For material producers that prefer wheels and need more site to site mobility, the Fold ·n Go 2512K is available. Both plants provide simple-- to-use hydraulic leveling gears, hydraulic plant controls and screen angle adjustment. Fold 'n Go 2512KT/2512K SCREEN: Kolbeqf 2512K double deck &ereen: 5' X 12' a.;reen lop and bottom deck driven t:lf 1200 RPM vibrating 11'111Cha1ism moun lad on screen; Variable eccef1lric shaft wi1l1 fNe (5) fon;e ~lilude setlngs on aOJIIStable slip C01111181vftlighls; Rub.ber isolalor bloclcs; Hydraufic conflols for variaOie illlge operatioo Top a'ld bottom discharge chutes, a~te ~pread&-,cr~d fixed eccess ladder will ~nd walkway for 00'.1'/ saeen acces!i.Standard material separaijoos 11111ge from 3" to 10M depending on application. PO 'MER SYSTEM: 125 HP (100 HP !Of 25121<) r~e~ II John Oeero waler- cooled diesel oo!#ne lo power eO plant functions aod ltlree on-board stac!Ung convayon; 12 voll bal!e!y. Engine mouniBd pulf1ls to operate all plant fllnctioos. NEMA-4 rated miniment p~el. tacllometer, hour meter. voltrne4er, oi1 Pleasure gauge, oo lemperab.Jra gauge aod lll1lfll9!lOOI s1op. Auxirla!Y powel for up 1o 30 HP off-plant conveyors. PLAHT CAPACITY: Seteening plant can p!tlC8S1 up 10 350 TPH a more of feed material. Actual tonnages wiU Vf!r'( depentfng a'l application ~irements: feed material silll, material separetion,, t)'pe cl S<:fEiellS used, weight af product ami othef matecial coosidenltioos. !)2006Aaooi.We Saans-AI ,;qns- Spadf'cotions • .., "'bjoct lo cllonoe. CONVEYOR SYSTEM: 2512KT: Delivery Conveyor-28' X 42" COfro/ByOf wi1h hydrao6c <iivo (350 FPM); FIA-lengijl skirt beads. Side Conveyor.-Two (2) 11' x 24" ~9 out cooveyors wi1h hydrnollc variable &peed~ (()..350 FPM); Flnft ~nveya-2f1 x 48" coovaya wi1l1 hydreulic drive (350 FPM); All coovayors have 220 PIW, 1/8x 1116 CJ:Nec be/1ing, belt cfeanels md lold for bansport. 25121<: Del Ivory ConveyOf-38" x 36" cooveyor wilh hydrau!H: Give (350 FPM) Side ~nveyors-Two (2) 27' x 24" swing out conveyors wi1l1 hydralllicvariable speed drive (().350 FPM): A"" ~oveyor-23'x 42' CO!WfYtor wilh hydraulic drive (350 FPM); AJJ conveyiXS have 220 PfW, 1/8 x 1116 r;mf!l belting, belt clean9f9 and fold for lrensport FEEDER SYSTEM: 12 cubic yard heaped capacily hopper wiltl f; x 13' lOp opening; Hesvy.(!uty 25' sloped grizzly with 6"norrinal opaoing; Hydraulic ~wit! patented scissOf actioo fot easy cleaning; Adjus!BIJje gate; 14' x 42' belt feeder with hydraotic Yllllial*! speed drive (()..6() FPM); Belling is 330 PfW, 3116 X 1116 rntee. CHASSIS: 2512KT: 24"1-beem; Hydraulic landing gear lot leve!fng of plant; lnler-Trac FL6IJ'IIcb wilh ~s remote coolrol for eaey jobsil9 ll10'o"'ll1llll 25121<: 21"1-beem wilt1 king pin type hitdl; Hydraulic laming gear for lweling cl plan; T oodem axle IIS'S~ with eight (8) 11 R22.5 tlres and mud flaps; Leaf spring type SUSp!lllsion, air braJ\Il", 18« llilli!111s 81ld Side maJI<ef tights. SERVIC£ CAPAaTY: Fuel... ................... 140 gal HydtaUiic T<!nk ......... 100 gal (150 g;l lor2512K) TRANSPORTATION: 2512KT 25121< Weigh! .................. 61,000 lbs 54,600 bs Haight ........... _. __ ,13' 11' (oolowboy) 13' 0" Lenglh ................. .49' 8" 62' 2' Widlh ........... _ ......... 11'11" 11' 11" Axles............ .. ........... NJA T endern OPTIONS: BulkhiNid-Assists in lllflllinQ for loader feed txl feed hopper. Remo• Control Grizzly-Assists in dumping C7<'mize material oil feed hopper from loadef: Wln~ists in fUnneling feed maOl!ial onto feed hopper grizzly. Hamm .. mill stredd .. -Helps break feed malerialapart 1\)r improYed processing. Hydrauiic controls C8ll ranct shl9dder up and 1WRf from !top zone of feed COfflByOf 10 delivery COOV9'(0f for malllriaf t:lf~ of shredder. Screen Cloth JT··· J_ .,·.r . ~ ~ ,. I !I ..... ~llt1Mfi WlJJ Jl. rr1il1 ~ g ~ 1-~ ~-1 l jL~ H IHllll l ~ ·-'-' ~ w T il OpefiJ'~ Powlo ~&SlOe . I n--·· .:_· ;. S TE ASTEC MOBILE SCREENS .,, Ast ec tndustrecs comp<~ny '-· .. -~ 270-1 WEST LEFEVRE RD ·STERLING. ll61081 • 800 5·15 2125 FAX 815 626 ~3.0 • <15-'>:cr-<lt 1')S.Cree~s ccm Record of Telephone Call /J /) / /?-/)--=-Pa-ge....---;_L..-o-=-f -_~_.--11 Project: /)/IJ/!1 -ICe(, Pftt.v [et!. 4.S by: /W'Q'C Call to: !Je.v~ 1 s Gs6y 7 Company: Lo.s £'? 74u"G.,,.;, f / Phone No: ( '135 ) 6 '79 -Z99o Date: (')2-Z5-ZOI/ Notes: Comments: 7 2006 Call to: 7i;/ u?c /)q~ Company: rJ. S. /5Ltr/ -JdiV!J~~ t>/ftc<- Phone No: {.'Bf) S87-ISI~ Date : -::54/--? /l . Z~ 2 / I Subject: !fi~t'Afs Cui . BLtrl R.tic. P,·b ' Notes: TeJ 1s eornwt~J..r : -!fla/e/ltJ t.i so/J ow ~ ~,;,., tf'l~~e/ Vlf~e. JrlJIJ. -~tttte""'-1 fltt;-c.-ts .;f {), ScJ /{'4, t~~o ... /c. y~d £emo~J -7h.t~e (J) ott-~~.e. { ~) ;()/r.._.I-1J $"t1t.(lfc~.r c /;sc: 4 Ifill I -~tlvwAJ Cfi.~oA/ -e~Ji dl dt / 1 -J e,(.ls Dte~.v ... IJ,MJi o.f l3/.+J:"'f -<j'S' 1 I(Jwp.n.l k...,; Pcwt,/c,. tee"'/4,ee w~..rl -~f:ek die -~a,,f/;~ ·~I dJ a.vle.o A.Jew a~e~ df'!'AJJ Comments: U~c, # tJ, (pO fe~t--f3C-r 1~ (?J hm~ I.e j;'d. rMa fe/lJ Co.rl ~ tt/Jv·.f;,;~~ cfellA,.f.N£i! "f ,1cce>.r lfst.teJ. 2006 Equipment Costs EQUIPMENT COSTS WHITE MESA MILL RECLAMATION COST HOURLY EQUIPMENT COSTS 2011 DOLLARS Actual equipment rates quoted from North Central Rental & Leasing, LLC, 12 month rental period February 16, 2011 RATE MTCE FUEL FUEL @ Tires and GET TOTAL Mob/Demob Mob/Demob Operating Hrs Replacement Cost Units MONTHLY HOURLY Excess Hours 50 Hour Weeks EXPENDABLES USAGE $2.332 COST per machine Totals per Month 637E Scraper 4 27,500 156.25 79.00 140.80 9.50 23.5 54.80 5.25 $210.35 $25,600 $102,400 880 1,940,000$ D8R Dozer 1 13,650 77.56 39.00 69.85 5.10 8.5 19.82 1.05 $95.82 $17,050 $17,050 220 650,000$ D7R Dozer 1 11,550 65.63 34.00 59.30 4.60 7.0 16.32 1.05 $81.27 $15,100 $15,100 220 550,000$ 825H Compactor 1 12,150 69.03 35.00 62.23 4.60 13.0 30.32 0.50 $97.64 $15,750 $15,750 220 250,000$ 980 H Loader 1 12,250 69.60 35.00 62.68 5.05 9.0 20.99 5.25 $93.97 $15,500 $15,500 220 300,000$ 988 H Loader 1 18,900 107.39 54.00 96.71 6.50 11.0 25.65 5.25 $134.11 $18,700 $18,700 220 345,000$ 770 Haul Truck 4 12,450 70.74 36.00 63.79 7.40 8.5 19.82 4.10 $95.11 $16,100 $64,400 880 2,000,000$ 365BL Excavator 1 17,850 101.42 51.00 91.34 7.55 13.0 30.32 1.05 $130.25 $29,050 $29,050 220 425,000$ 651 Water Wagon 1 12,750 72.44 37.00 65.35 6.20 17.0 39.64 2.10 $113.30 $17,350 $17,350 220 250,000$ 5000 gal Water Truck 1 7,200 40.91 21.00 36.93 3.60 10.0 23.32 2.10 $65.95 $7,800 $7,800 220 175,000$ 14H/Ripper Motor Grader 1 9,550 54.26 28.00 49.01 4.25 5.5 12.83 5.25 $71.34 $12,300 $12,300 220 265,000$ $315,400 3,740 Equipment Rental Rate Quoted by WorldWide Rental Services (02/19/2011) for PC 300 Excavator with Shear Mob/Demob PC 300 w/ Shear 19,500.00 110.80 57.00 100.04 17.99 12.5 29.15 $147.18 $4,550 450,000$ Small tools allocation - Demolition - $1.35/mechanic labor hour for oxygen/acetylene, expendables $1.35 Monthly Maintenance Flat Rate Butler Maintained Equipment Planned Operating Hours/month Planned Operating hours/month (other equipment Total Operating hours per month Fuel Usage per day, gal, Fuel Cost per month, 21 days Maintenance Cost per Operating Hour Mob/Demob Butler Equipment Maintenance Cost $68,050 3,740 570 4,310 20 979.44$ $18.46 71,200$ RATE MTCE FUEL FUEL @ TOTAL Crane Rental Rates MONTHLY HOURLY EXPENDABLES USAGE $2.332 COST Mob/Demob 60 ton Hydraulic Crane 11,700 66.48 2.15 15.0 34.98 $103.61 2,000$ 250,000$ 30 ton Hydraulic Crane 7,000 39.77 2.15 10.0 23.32 $65.24 700$ 175,000$ Rental Rates updated from Honnen Equipment, 02/14/2011 Power Motive - Screen deck and conveyors 200,000$ 8,225,000$ 82,250$ 9/28/2011 - 8:43 AM - WMM Rec Plan Est Rev 5.0.xls International Uranium (USA) Corp.White Mesa Mill ~RTH J) ~TRA L RENTAL & LEASING LLC A Subsidiary of Butler Machinery Co. February 16, 2011 Denison Mines Attn: Harold Roberts E-Mailed to: hroberts@dcnison.mines.com Dear Harold: 3401 33r Street Southwest Po Box 9559 Fargo, ND 58106-9559 Phone (701) 232-0033 Fax (701) 298-1717 Thank you for the invitation to quote Denison Mines (Denison) the equipment needed for their mining project in Blanding, Utah. North Central Rental & Leasing, (NCRL) respectfully submits our proposal for a maintained fleet of Caterpillar machines. Listed on Attachment A, you will find the models, quantities, monthly rental rates, hours allowed per month, excess hour charge, guaranteed number of months rates are based upon, total freight charges and the maintenance rate per hour for materials only. All rates shown on Attachment A do not include any state, local, property or any other taxes that may be applicable. Rates are based upon electric hour meter readings that are attached to the dash of each machine. Rates are based on 176 hours of use each month. Excess hour charges, if any, will be calculated and invoiced at the end of the project. There would be no credit issued for any hours under the allowed during the term of this proposal. If Denison elects to double shift machines, then NCRL would invoice those hours at the end of each month. (To figure the double shift rates, take the excess hour rate shown on Attachment A times the number of hours). Rates are based upon a minimum guarantee of 12 months and a package deal. This quote is valid for 90 days. Maintenance and Repairs: Maintenance: The maintenance rates per hour listed on Attachment A includes the material part items only, such as oil filters, lubricant oils, grease, anti-freeze, batteries, fan belts, lights and make-up oils. NCRL would invoice Denison actual hours used on machines at the end of each month. Our monthly maintenance charge would be $68,050 which includes our labor, specialized lube trucks, support vehicles and equipment, specialized tooling, scheduled oil sampling, parts trailers and inventories, mileage and travel expense. February 16, 2011 Denison Mines Page2 Maintenance (cont.): NCRL will provide two (2) full-time maintenance technicians on site fifty (50) hours per week on a schedule to be determined, Monday through Friday. Denison would have to schedule the machines available for a time frame yet to be determined adequate for NCRL maintenance personnel to perform the required maintenance. NCRL would invoice Denison for the monthly maintenance charge at the end of each month. Repairs: NCRL would be responsible for all repairs including parts and labor on our machines other than failures caused by damages or mis-use. Repairs include items as minor as starters, alternators, water pumps, hydraulic hoses, etc. to the major items such as engines, transmissions, differentials, brakes, hydraulic pumps and cylinders, etc. If time permits and Denison requests NCRL's technician to perform repairs or maintenance on their machines, our hourly charge would be $99.00 per hour for standard time, $127.00 per hour for overtime and $146.00 per hour for Sundays and holidays plus materials. Mobilization, Freight and Assembly Charges: Mobilization: The mobilization charge of $35,600.00 includes the moving expense of our support personnel, set up the job site, and transportation costs of our vehicles, parts and tooling inventory to the job site. NCRL would charge the same amount to demobilize at the end of the project. Freight and Assembly Charges: The freight and assembly charges listed on Attachment A are based upon all machines shipped by truck to the job site. Denison would be responsible for demobilization including disassembly and return freight on all machines. Parts, vehicles and equipment, at the end, or at time during the rental period to Rapid City, SD NCRL would be responsible for freight to the job site for all stock order parts shipments, emergency repair parts, maintenance parts, and G.E.T. and bulk oil shipments. Once the equipment has been delivered and assembled, an inspection would take place. During the inspection, a representative of NCRL and a representative of Denison will verify on the Acceptance Report the condition of the equipment. Denison's Responsibilities Include: Operators: Provide the operators as needed to operate machines as stated in Caterpillar's operating guide. NCRL will provide, at no expense to Denison, qualified training instructors for the purposes of training operators. This training would take place on the jobsite at the initial start up of the job and would include classroom, walk around, and in iron demonstrations. February 16, 2011 Denison Mines Page3 Fuel: Supply and fill all fuel for equipment including NCRL's service vehicles. Damages: This includes glass breakage, bent handrails, stepladders, fenders, etc. NCRL's normal policy for repairing damages to rental machines is to repair them when the rental period is completed, however, if the damaged item is of a safety concern, we would repair the damages as soon as possible after they occurred. An itemized list of the parts and labor required would be provided to Denison prior to starting the repair, and invoiced at current list prices plus freight upon completion. Undercarriage and Tires: Denison would be responsible for all tire wear including tire damages on the machines with an asterisk listed on Attachment A. Equipment would have to be returned with same brand and model tires as when delivered, or prorated accordingly by percentage of tire wear and condition at termination of rental period. Upon delivery of machines, a representative ofNCRL/BMC, a representative ofDenison and a representative from an independent tire dealer or manufacturer would jointly verify in writing the condition, percentage of wear, and tire value. Upon termination of rental, we would again have the representatives mentioned above determine the condition, percentage of wear, and tire values. Any differences noted, would then be charged or credited to Denison including both materials and labor. Undercarriage wear on all track type machines would be NCRL's expense. Ground Engaging Tools: Denison would be responsible for all parts relating to ground engaging tools (G.E.T.), i.e. cutting edges, ripper tips and protectors, bucket tips and adapters, edges between adapters, wear plates on bottom of buckets and all mounting hardware. NCRL would install these items on an as needed basis at the current Caterpillar list price plus freight at no additional labor costs. All machines would be delivered with new G.E.T. items and are to be returned with new. We wish to thank Denison and you for giving us the opportunity to present our proposal and for all the consideration we receive. Sincerely yours, North Central Rental & Leasing Butler Machinery Company Oscar(]). Swenson Rental Fleet Marketing Manager ODS: lmc Attachment cc: Joel Nikle, RentaJ Fleet Manager Joyce Wittkopp, Asst. Rental Fleet Manager Attachment A Denison Mine Equipment Package Quote: Blanding, Utah February 16, 2011 MINIMUM GUARANTEED TOTAL** MONTHLY HOURS EXCESS NUMBER OF FREIGHT MAINTENANCE RENTAL ALLOWED HOUR MONTHS RATE CHARGES RATE MODEL QTY RATE PER MONTH CHARGE BASED UPON TO & FROM PER HOUR *637G 4 $27,500 EA. 176 EA. $79 EA. 12 EA. $25,600 EA. $9.50 EA. D9R!T RIPPER 1 16,700 176 48 12 18,800 5.80 D8RfT RIPPER 1 13,650 176 39 12 17,050 5.10 D7RJRIPPER 1 11,550 176 34 12 15,100 4.60 825H 1 12,150 176 35 12 15,750 4.60 980H 1 12,250 176 35 12 15,500 5.05 *988H 1 18,900 176 54 12 18,700 6.50 *770 4 12,450 I 176 EA. 36 EA. 12 EA. 16,100 EA. 7.40 EA. 3658 II 1 17,850 176 51 12 29,050 7.55 10,000 GAL Water Wagon 1 12,750 I 176 37 12 17,350 6.20 I 5,000 GAL. Water Wagon 1 I 7,200 176 21 12 7,800 3.60 14H/M RIPPER 1 9,550 176 28 12 12,300 4.25 16H/M RIPPER 1 13,650 176 39 12 14,650 5.20 *PLUS TIRE WEAR ** INCLUDES ASSEMBLY AND DISASSEMBLY The charge for two service technician's working fifty (50) hours per week, maintenance and lube trucks, parts and service trailers, and overhead would be $68,050 per month to be invoiced at the end of each month. Maintenance rates per hour would be invoiced at the end of each month based upon actual hours. Deliveryand receiving mobilization charge is $35,600 each way. Dawn Gagon From: Sent: Sam Loughman [Samloughman@honnen.com] Monday, February 14, 2011 11:52 AM To: Dawn Gagan Cc: Randy DeFosse Subject: Crane annual quote Good Morning Dawn, The following rates are based on 176 usage hours per month, above that overtime hourly rates apply. The rates do NOT Include transport to your location. Please contact me for current availability and estimated transport cost. Grove RT530E {30ton) Crane: $7,000 per month Grove RT760E {60Ton) Crane: $11,700 per month Grove RT875E {75 ton) Crane: $14,500 per month tii('~HONNEN ~EQUIPMENT Sam Loughman Territory Manager samloughman@honnen.com (970}403-9985 Cell (970}247-4460 Office (970)247-4463 Fax 1 Dawn Gagon From: Sent: To: Subjec~: Dawn, BBryson@wwmach com Friday, February 19, 2010 9·23 AM Dawn Gagen Denison Mines Rental Quote# 870 for Jobsite Blending, UT Here is the updated quote. Please let me know if you have any questions or if there Is anything else you need. Thanks Brian RENTAL QUOTE Client Dawn Gagon Denison Mines Phone: (435)678-2221 Fax: (435)678-2224 Email:: , .. ~.. ·•l' ·' Job site Blanding,UT Date 02/19/2010 Quote t1 870 Expiration Date 03/21/2010 Estimated start We are pleased to offer the following quote. Do not hesitate to contact us with any question or concerns Qty. EqUJponent Frc1ghl (one-way)· PC300 Excavator w/ shear $2,275 • Representative • Brian Bryson Email: · · •: '· ''~ '., Mobile : (801)879-6702 Monthly rata • $19,500 • All Rates ate per Machine. Special use and Sales tax are not included in above rates. Terms and Conditions 1.-All equipment is subject to availabifily. Weekly rate • $6,500 ---, 2.-Monthly rate (28 day billing cycle} Is based on 200 hours usage Overtime will be billed at 70% of the hourly rate. 3 -Payment terms are due upon receipt, unless otherwise specified 4.-Credit approval will be determined by credit information supplied by the contractor to Wortdwide, prior to job mobilization. 5.-Ground engaging toot wear to be billed at the end of the contract. 6.· Machine month is defined as cost of one machine per 28 day month. If multiple units are required, multiply the base rate limes the number of units required January 2010 to December 2010 -Fuel Cost Calculation Producer Price Index -Commodities #2 Diesel January 2010 February March April May June July August September October November December 229.4 206.9 225.5 240.0 235.8 221.8 218.5 231.1 227.6 243.9 255.7 261.7 Fuel Cost Calculation Rev 4.5 March 2011.xls 2797.9 $ 2.332 per Gallon "12 month Average off road use Bureau of Labor Statistics Data Page 1 of2 A to Z Index I Site Map I FAQs I About BLS I Contact Us Subscribe to E-mail Updates liliJ tf ~®J!Lrox+m~m~ Home I Subject Areas I Databases & Tools I Publications I What's New I Release Calendar Economic Releases I Beta Search BLS.gov Databases, Tables & Calculators by Subj ect 1 FONT SIZE: (==; !.fJ Change Output From: 2000 . Options: To: 2010 D include graphs ~ More Formatting Options _. Data extracted on: February 11, 2011 (3:17:35 PM) Producer Price Index-Commodities Series Id: WP0057303 Not Seasonally Adjusted Group: Fuels and related products and power Item: No . 2 Qiesel fuel Base Date: 198200 Download: 'MJ .xis ,- Year Jan Feb Mar Apr May lun lui Aug r--:: 2000 76.1 f-86.1 90.0 84.1 82.8 85.7 89.5 92.1 2001 96.7 92.4 83.5 86.4 93.1 90.2 81.6 82.0 2002 58.9 60.0 69.7 76.9 74.7 73.3 77.6 80.4 r-2003 97.6 123.8 129.4 102.3 87.9 89.8 92.7 96.6 Sep Oct Nov ---110.8 110.0 110.4 91.6 75.9 71.3 92.3 98.7 85.5 91.1 101.1 95.9 ·--Dec Annual --101.6 93.3 56.2 83.4 86.8 1~~:~ 98.1 I------2004 109.3 103.7 109.7 119.9 121.0 114.2 123.0 135.1 140.9 166.6 159.7 135.3 128.2 --f---2005 141.1 149.5 173.3 175.4 170.8 187.2 189.8 200.6 .212.6 264.1 206.2 198.5 189.1 2006 197.1 196.2 206.5 230.4 239.6 246.9 237.5 250.2 201.3 197.5 197.2 203.0 216.9 2007 180.9 193.5 220.2 238.0 226.5 227.6 243.5 231.2 246.2 249.6 296.7 271.9 235.5 -:----2008 278.2 287.5 353.7 365.1 398.2 421.0 431.9 346.7 342.3 281.8 224.1 168.0 324.9 2009 161.6 147.2 139.2 167.4 166.4 191.1 172.8 204.1 193.2 202.8 215.7 205.1 180.6 2010 229.4 206.9 225.5 240.0 235.8 221.8 --218.5 231.1 227.6(P) 243.9(P) 255.7(P) 261.7(P) 233.2(P) P: Preliminary. All indexes are subject to revision four months after origin~ublication. TOOLS CALCULATORS HELP INFO Areas at a Glance Inflation Help & Tutorials What's New Industries at a Glance Location Quotient FAQs Careers @ BLS Economic Releases Injury And Illness Glossary Find It! DOL Databases & Tables About BLS Join our Mailing Lists http:/ I data. bls.gov /pdq/SurveyOutputServ let 2/11/2011 Labor Costs LABOR COSTS Specified Wages Heavy Construction 2011 Estimated Labor Rates**17.67% 21.28%17.07% Labor Classification Base Rate Mandated Fringe Labor Burden (FICA, SUI, FUI, etc. Company Benefits (medical, life insure, etc)Fringe Costs Labor Cost/HR Fringe Costs - on Overtime hours Labor Cost/HR - Overtime Labor Cost/HR - 50 hour week % of employee pay Boiler Makers $25.22 $18.76 $4.46 no added cost $23.22 $48.44 $22.62 $71.75 $53.10 Payroll Taxes 7.65 WC 9.42 Millwrights $20.82 $4.28 $3.68 $0.15 $8.11 $28.93 $7.51 $42.49 $31.64 UI 0.60 Ironworkers $21.84 $9.92 $3.86 no added cost $13.78 $35.62 $13.18 $52.53 $39.00 17.67 Cement Masons $14.00 $0.56 $2.47 $2.42 $5.45 $19.45 $4.85 $28.28 $21.22 Electricians $14.52 $2.71 $2.57 $0.38 $5.66 $20.18 $5.06 $29.36 $22.01 Ironworkers - Reinforcing $14.00 $2.47 $2.98 $5.45 $19.45 $4.85 $28.28 $21.22 Laborers (including pipelayers) $9.00 $0.00 $1.59 $1.92 $3.51 $12.51 $2.91 $17.86 $13.58 Pipefitters $12.60 $2.23 $2.68 $4.91 $17.51 $4.31 $25.36 $19.08 POWER EQUIPMENT OPERATORS Backhoes $10.00 $1.77 $2.13 $3.90 $13.90 $3.30 $19.94 $15.10 Cranes $10.43 $1.84 $2.22 $4.06 $14.49 $3.46 $20.84 $15.76 Dozers $13.63 $2.41 $2.90 $5.31 $18.94 $4.71 $27.51 $20.65 Graders $13.61 $2.40 $2.90 $5.30 $18.91 $4.70 $27.47 $20.62 Loaders $11.38 $2.01 $2.42 $4.43 $15.81 $3.83 $22.82 $17.21 Scrapers $12.75 $2.25 $2.71 $4.97 $17.72 $4.37 $25.67 $19.31 Trackhoes $13.63 $2.41 $2.90 $5.31 $18.94 $4.71 $27.51 $20.65 Tractors $9.42 $1.66 $2.00 $3.67 $13.09 $3.07 $18.73 $14.22 Truck Drivers $12.00 $2.12 $2.55 $4.67 $16.67 $4.07 $24.11 $18.16 Note: base rates do not include FICA, worker comp, unemployment, or company benefits which increase the cost per hour ** State of Utah - General Decision - Current Update UT20100073, 4 pages, 07/09/2010 9/28/2011 - 8:43 AM - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill LABOR COSTS Nonspecified Wages Base Rate*** Mandated Fringe Labor Burden (FICA, SUI, FUI, etc. Company Benefits (medical, life insure, etc)Fringe Costs Labor Cost/HR Fringe Costs - on Overtime hours Labor Cost/HR - Overtime Labor Cost/HR - 50 hour week Survey Crew Member $11.62 $0.00 $2.05 $2.47 $4.53 $16.14 $3.93 $23.32 $17.58 Sample Crew Member $11.62 $0.00 $2.05 $2.47 $4.53 $16.14 $3.93 $23.32 $17.58 Mechanic (Demolition) $12.07 $0.00 $2.13 $2.57 $4.70 $16.77 $4.10 $24.26 $18.27 Manager/Engineer $42.51 $0.00 $7.51 $9.05 $16.56 $59.06 $15.96 $87.70 $64.79 Radiation Safety Officer $33.21 $0.00 $5.87 $7.07 $12.94 $46.15 $12.34 $68.32 $50.58 Secretary $13.43 $0.00 $2.37 $2.86 $5.23 $18.66 $4.63 $27.10 $20.35 Clerk $11.05 $0.00 $1.95 $2.35 $4.30 $15.36 $3.70 $22.14 $16.71 Engineer $33.21 $0.00 $5.87 $7.07 $12.94 $46.15 $12.34 $68.32 $50.58 Environmental Technician $18.70 $0.00 $3.30 $3.98 $7.28 $25.99 $6.68 $38.08 $28.41 Safety Engineer $18.70 $0.00 $3.30 $3.98 $7.28 $25.99 $6.68 $38.08 $28.41 Maintenance Foreman $24.37 $0.00 $4.31 $5.19 $9.49 $33.86 $8.89 $49.90 $37.07 Security Personnel $7.20 $0.00 $1.27 $1.53 $2.80 $10.00 $2.20 $14.10 $10.82 Chemist $19.55 $0.00 $3.46 $4.16 $7.62 $27.17 $7.02 $39.85 $29.71 *** Reflects ------% cost of living raise for 2011 9/28/2011 - 8:43 AM - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill GENERAL DECISION : UT20100073 07/09/2010 UT73 Date : July 9, 2010 General Decision Number : UT20100073 07/09/2010 Superseded General Decision Number : UT20080073 .state: Utah Construction Type: Heavy County: San Juan County in Utah . Including Natural Gas Pipeline Construction Modification Number 0 1 Publication Date 03/12./2010 07/09/2010 * ENGT0003.-047 07/01/2010 Excluding Natural Gas Pipeline Construction Rates OPERATOR : Power 8quipment (3) Backhoe .................. $ 24 .93 * ENGIOOOl-054 02/02/2010 Natural Gas PipeliFie Construction Only OPERATOR : Power Equipment &ackhoe/Excavator/Tr ackhoe, Blade/Grader, Boom, Bulldozer, Crane, Rates Mechanic, Trencher .......... $ 35 .10 Oiler ....................... $ 20 . 62 LAB00295-018 11/01/2007 Natural Gas Pipeline Constructi.on On·ly Rates LABORER Chain Saw and Power Drill ... $ 18.86 Common or General, Nail gun, Pipelayer, Pot Tender .. $ 17.61 Fonnworker .................. $ 18.61 Powderman ................... $ 19. 36 Sandblaster ................. ~ 18.36 SOUT2008-028 08/19/2008 Rates Fringes 13.26 Fringes 12 .49 9 .37 fringes 4. 94 4 . 94 4 . 94 4 . 94 4 . 94 Fringes Page 1 of4 http:/ /frwebgate.access.gpo.gov/cgi-bjnfgetdoc.cgi?dbname:::;:Davis-Bacon&docid=UT20 100... 2/4/201 J CARPENTER, Including form Work (Excluding Natural Gas Pipeline Construction Form Work) ............................ $ 14.75 CEMENT MASON/CONCRETE FINISHER ... $ 14 .00 LABORER: Mason Tender - Cement/Concrete .................. $ 9.00 LABORER: Common or General (Excluding Natural Gas Pipeline Construction) ........... $ 12.00 LABORER : Pipelayer (Excluding Natural Gas Pipeline Construction) .................... $ 9 .00 OPERATOR: Roller (Dirt and Grade Compaction) ................ $ 10 .89 OPERATOR : Trackhoe (Excluding Natural Gas Pipeline Construction) ........... $ 13.63 OPERATOR : Blade/Grader (Excluding Natural Gas Pipeline Construction) ........... $ 13 .61 OPERATOR : Excavator (Excluding Natural Gas Pipeline Construction) ........... $ 12 .75 OPERATOR: Front End Loader ....... $ 11 .38 TRUCK DRIVER (Excluding Natural Gas Pipeline Construction) .................... $ 12. 00 TEAM0222-020 11/01/2007 NATURAL GAS PIPELINE CONSTRUCTION ONLY TRUCK DRIVER Group 1 : Articulated End Dump , Low Boy, Rollagon or Similar type Equipment, Truck Rates Mechanic ................... $ 27 .14 Group 2 : A-Frame, Challenger(For transportation purposes), Forklift, Fuel Truck, Gin Pole, Rubber-Tired Tractor, Tandem Float (4 & 5 Axle), Track Truck/Al l-Track Dumper Equipment , Vacuum Truck, Page 2 of4 3 .03 0 .56 0 .36 0 .00 0.00 0.00 0 .00 0 .00 0 .00 0 .00 0 .00 Fringes 8 .74 http:/ /frwebgate.access.gpo.gov/cgi-bin/geldoc.cgi?dbname= Davis-Bacon&docid=UT20 1 00... 2/4/20 I I Winch Truck ................ $ 26 .68 Group 3 : Ambulance , Bus, Dump Truck (2 and 3 axle), Flatbed Truck (2 and 3 axle), Grease Truck, Hot Pass Truck (3 axle), Jeep, Pick-up, Single Axle Float (3 axle), Skid Truck (2 and 3 axle), Station Wagon, Stringer Bead & Hot Pass (2 axle), Swamp Buggy/ Marsh Buggy, or similar type equipment, Team Driver, Water Truck (2 and 3 axle).$ 26.39 Pr emium Pay: 8 .74 8 .74 Add $1 .25 to the above Rate for the following classifica·tions Group 1: Low Boy and Truck Mechanic Group 2: Stringer Truck WELDERS -Receive rate prescribed for craft performing operation to which welding is incident al . Unlisted cl assifications needed for work not included within the scope of the classifications list ed may be added after award only as provided in the labor standards contract clauses (29 CFR 5 .5(a) (1) (ii)). In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collecti vely bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevaili ng. WAGE DETERMINATION APPEALS PROCESS 1 .) Has there been an initial decision in he matter? This can be : * an existing published wage determination * a survey underlying a wage determination * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification a nd rate) ruling Page 3 of 4 http://fiwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=UT201 00... 2/4/2011 Long Term Care LONG TERM CARE CALCULATION March 2011 Base Amount (Starting in Dec. 1978) $250,000 CPI-U December, 1978 67.7 CPI-U December 2010 219.179 Adjusted Long Term Care = $250,000 x (CPI-U most recent / CPI-U Dec., 1978) Adjusted Long Term Care $809,376 9/28/2011 - 8:43 AM - WMM Rec Plan Est Rev 5.0.xls Denison Mines (USA) Corp. White Mesa Mill Bureau of Labor Statistics Data Page 1 of 1 A to Z Index I Site Map I FAQs I About BLS I Contact Us Subscribe to E-mail Updates EEl TATISTIGS What's New I Release Calendar Home I Subject Areas I Databases & Tools I Publications I Economic Releases I Beta Databases, Tables & Calculators by Subject Change Output Options: From: 2000 · To: 2010 · ~ D nclude graphs More Formatting Options .. Data extracted on: February 11, 2011 (3:15:40 PM) Consumer Price Index -All Urban Consumers Series Id: CUUROOOOSAO Not Seasonally Adjusted Area: u.s. city average Item: All items Base Period: 1982-84=100 Download: ®.xis Year Jan Feb Mar Apr May Jun lui A_!!_!L Sep Oct 2000 168.8 ~~~:: 171.2 171.3 171.5 172.4 172.8 172.8 173.7 174.0 2001 175.1 176.2 176.9 177.7 178.0 177.5 177.5 178.3 177.7 2002 177.1 177.8 178.8 179.8 179.8 179.9 l1Q:1 180.7 181.0 181.3 --2003 181.7 183.1 184.2 183.8 183.5 183.7 183.9 184.6 185.2 185.0 ----2004 185.2 1~ f-187.4 ,_!88.0 189.1 189.7 189.4 189.5 189.9 190.9 2005 190.7 191.8 193.3 194.6 194.4 194.5 195.4 196.4 198.8 199.2 2006 198.3 198.7 199.8 201.5 202.5 202.9 203.5 203.9 202.9 201.8 2007 2o2.4i6 203.499 205.352 206.686 207.949 208.352 ~~-299 207.917 208.490 208.936 2008 211.080 211.693 213.528 214.823 216.632 218.815 219.964 219.086 218.783 216.573 Nov 174.1 177.4 181.3 184.5 19~ 197.6 201.5 210.177 212.425 Search BLS.gov FONT SIZE: 8 :tJ J -~-Dec Annua! HAl!!_ J!ALF2 174.0 172.2 170.8 173.6 176.7 177.1 176.6 177.5 180.9 179.9 178.9 180.9 --184.3 184.0 183.3 184.6 190.3 188.9 187.6 190.2 196.8 195.3 193.2 197;! 201.8 201.6 200.6 202.6 210.036 207.342 205.709 208.976 -210.228 215.303 214.429 216.177 2009 211.143 212.193 212.709 213.240 213.856 215.693 215.351 215.834 215.969 216.177 216.330 215.949 214.537 2~ 2~ ~10 216.687 216.741 217.631 218.009 218.178 217.965 218.011 218.312 218.439 218.711 218.803 219.179 218.056 217.535 218.576 -L. ··-C-- -_..;._ TOOLS CALCULATORS HELP INFO Areas at a Glance Inflation Help & Tutorials WhaYsNew Industries at a Glance Location Quotient FAQs Careers@ BLS Economic Releases Injury And Illness Glossary Find It! DOL Databases & Tables About BLS Join our Mailing lists Maps Contact Us linking & Copyright Info Freedom of Information Act I Privacy & Security Statement I Disclaimers I Customer Survey I Important Web Site Notices U.S. Bureau of Labor Statistics 1 Postal Square Building, 2 Massachusetts Avenue, NE Washington, DC 20212·0001 www.bls.gov l Telephone: 1·202-691-5200 I TDD: 1-800-877·8339 I Contact Us http://data.bls.gov/pdq/SurveyOutputServlet --- 2/11120 11 General Liability & Auto Insurance General Liability and Auto Insurance Project Life 7 years GL Insurance per full year 35,000$ Auto 1,200$ 12,000$ Vehicles Vehicle Ins. GL Insurance Year 1 5 6,000$ 20,000$ Year 2 10 12,000$ 35,000$ Year 3 10 12,000$ 35,000$ Year 4 10 12,000$ 35,000$ Year 5 10 12,000$ 35,000$ Year 6 10 12,000$ 35,000$ Year 7 3 3,600$ 20,000$ 69,600$ 215,000$ Project Cost 284,600$ 9/28/2011 WMM Rec Plan Est Rev 5.0.xls Harold Roberts From: Sent: To: Cc: Subject: Hi, Thomas.McBeath@aon.ca Friday, February 04, 2011 2:41 PM Jim Anderson Harold Roberts Re: FW: Denison Mines Our estimate of costs remains unchanged, as the insurance market place pricing remains constant and general criteria for the work is also unchanged. That is: a) General Liability: $35,000 per year b) Automobile: $1 ,200 per vehicle per year. Thus, $12,000 for 10 vehicles. Best Regards, Thomas McBeath, P.Eng. I Aon Reed Stenhouse Inc. Vice President 1 Risk Management Practice 20 Bay Street, Toronto, ON M5J 2N9 Tel: 416.868.24491 Fax: 416.868.5580 thomas.mcbeath@aon.ca www.aon.ca Jim Anderson <JAnderson@denlsonmines.com> Feb/04/2011 03:38 PM EST Tom, can you provide this? Jim Anderson Executive Vice President & Chief Financial Officer t: 416-979-1991 x372 1 f: 416-979-5893 595 Bay Street, Suite 402, Toronto, ON M5G 2C2 To Thomas McBeath/ARS/CNAON cc Harold Roberts <HRoberts@denisonmines.com> Subject FW: Denison Mines DENISON MINES CORP www.denisonmines.com This e-mail Is Intended for the exclusive use of the person(s) mentioned as the reciplent(s). This message and any attached files with it are confidential and may contain privileged or proprietary information. If you are not the intended recipient( a) please delete this message and notify the sender. You may not use, distribute print or copy this message if you are not the intended recipient(s). From: Harold Roberts Sent: February 4, 2011 3:36PM 1 To: Jim Anderson Subject: RE: Denison Mines Jim: I need to get an update on this insurance number. A statement that it hasn't changed or an update on the costs. Thanks, Harold Roberts Executive Vice President, US Operations DENISON MINES (USA) CORP 1: (303) 389-4160 J f: (303) 389-4125 www.denisonmines.com 1050 17th Street. Suite 950, Denver, CO 80265 This e-mail is intended for the exclusive use of the person(s) mentioned as the recipient(s). This message and any attached files with it are confidential and may contain privileged or proprietary information. If you are not the intended recipient(s) please delete this message and notify the sender. You may not use, distribute print or copy this message if you are not the Intended recipient(s). From: Jim Anderson Sent: Thursday, July 29, 2010 7:16AM To: Harold Roberts Subject: FW: Denison Mines Harold, is Tom's assumption correct? Jim Anderson Executive Vice Prestdenl & Chief Financtal Officer t: 416-979-1991 x372 J f: 416-979-5893 595 Bay Street, Suite 402, Toronto, ON M5G 2C2 DENISON MINES CORP www.denisonmines.com This e-mail is Intended for exclusive use the person(s) mentioned as the reciplent(s). This message and any attached files with it are confidential and may contain privileged or proprietary information. If you are not the intended recipient(s) please delete this message and notify the sender. You may not use, distribute print or copy this message if you are not the intended recipient(s). 2 From: Thomas.McBeath@aon.ca [mallto:Thomas.McBeath@aon.ca] Sent: July 29, 2010 8:07AM To: Jim Anderson Subject: Re: Denison Mines Jim, Would it be correct to assume that the $16mil reclaimation project would be done over several years? The letter hints at this with 5 years of monitoring, and 6.5yrs of pumping. I have used that assumption and recommend the following premiums: a) General Liability: $35,000 per year b) Automobile: $1 ,200 per vehicle per year. Thus, $12,000 for 10 vehicles. Trust this meets your needs. Feel free to call if questions. Sincerely, Tom Thomas McBeath, P.Eng. J Aon Reed Stenhouse Inc. Vice President 1 Risk Management Practice 20 Bay Street. Toronto, ON M5J 2N9 Tel: 416.866.24491 Fax: 416.668,5580 thomas.mcbeath@aon.ca www.aon.ca Jim Anderson <JAnderson@denisonmlnes.com> Jul/23/201 0 02:29 PM AST To 'Thomas.McBeath@aon.ca" <Thomas.McBeath@aon.ca> cc Subject Denison Mines Tom, we are re-estimating our reclamation liability for the White Mesa mill in the US . The attached letter outlines some additional information required by the State. On page two in t he paragraph marked they require some specific estimates on insurance. Once you have had a chance to review, could you give me a call to discuss how best to address this? Jim Anderson Executive Vice President & Chi ef Financial Officer t : 416-979-1991 x372 I f : 416-979-5893 595 Bay Street, Suite 402, Toronto, ON MSG 2C2 DENISON MINES CORP http ://www .denisonmines .com/ 3 Haul Routes Haul Route Travel Time (min) Fixed Time (min) Total Cycle Time (min) Trips per Work Hour 1 Bank Cubic Yards per Hour 1 2.7 1.2 3.9 12.8 358 2 3.4 1.2 4.6 10.9 303 3 3.7 1.2 4.9 10.2 285 4 2.7 1.2 3.9 12.8 358 5 4.1 1.2 5.3 9.4 263 6 4.5 1.2 5.7 8.8 245 7 2.4 1.2 3.6 13.9 388 8 3.2 1.2 4.4 11.4 317 9 3.6 1.2 4.8 10.4 291 10 2.9 1.2 4.1 12.2 340 11 4.5 1.2 5.7 8.8 245 12 3.5 1.2 4.7 10.6 297 13 2.2 1.2 3.4 14.7 410 14 2.4 1.2 3.6 13.9 388 15 3.8 1.2 5 10.0 279 16 4.4 1.2 5.6 8.9 249 1 50 minute work hour (83.3% efficiency) HAUL ROUTE SUMMARY Haul Route Material Source Material Destination In-Stockpile Quantity (cy) 1 E8 and W9 Outslopes of Cells 4A and 4B 243,000 2 W7, W8, and W9 Tailings Surface of Cells 4A and 4B 1,194,000 3 E2, E3, E4, E5, E6, E7 Cell 3 Tailings Surface and Outslopes 420,000 4 W7, W5 Cell 3 Tailings Surface and Outslopes 603,000 5 W5 Cell 2 Tailings Surface and Outslopes 391,000 6 W2 Cell 2 Tailings Surface and Outslopes 298,000 7 W2 Cell 1 235,000 8 W6 Tailings Surface of Cells 4A and 4B 54,000 9 W6 Cell 3 Tailings Surface 39,000 10 W4 Cell 3 Tailings Surface 20,000 11 E1 Cell 2 Tailings Surface 15,900 12 W4 Cell 2 Tailings Surface 36,100 13 W4 Cell 1 10,500 14 Mill Site (Contaminated Soils)Cell 1 N/A 15 W3 Mill Site 54,400 54,400 cy (64%) of Stockpile W3 16 Cell 1 Contaminated Material Cell 4B N/A HAUL ROUTE DESCRIPTIONS 36,100 cy (40%) of W4 10,500 cy (12%) of W4 Notes 235,000 cy (40%) from W2 54,000 cy (58%) of W6 39,000 cy (42%) of W6 20,000 cy (22%) of W4 15,900 cy (all) of E1 900,000 cy (all) from W8, 284,000 cy (95%) from W9 and 10,000 cy (25%) from W7 227,000 cy (all) from E8 and 16,000 cy (5%) from W9 All of stockpiles E2-E7 29,000 cy (75%) from W7 and 574,000 cy (60%) from W5 391,000 cy (40%) from W5 298,000 cy (51%) from W2 Length (ft)GR TR (%) Travel Time (min) Length (ft)GR TR (%) Travel Time (min) Length (ft)GR TR (%) Travel Time (min) 1 420 -7% -2% 0.3 1,590 0% 5% 1.1 2 760 -1% 4% 0.6 1,810 0% 5% 1.2 3 810 0% 5% 0.8 1,870 0% 5% 1.3 4 2,470 0% 5% 1.7 5 800 1% 6% 0.9 2,320 0% 5% 1.5 6 1,310 -1% 4% 0.8 2,180 0% 5% 1.4 7 570 0% 5% 0.5 1,340 -1% 4% 0.8 8 550 2% 7% 0.6 1,810 0% 5% 1.2 9 1,070 1% 6% 0.9 1,650 0% 5% 1.2 10 680 -1% 4% 0.5 1,620 0% 5% 1.1 11 1,370 -1% 4% 0.9 1,110 0% 5% 0.8 710 0% 5% 0.6 12 680 -1% 4% 0.5 2,180 0% 5% 1.4 13 1,440 0% 5% 1 14 2,030 -1% 4% 1.1 15 1,695 -2% 3% 0.9 1,695 2% 7% 1.4 16 1,980 0%5%1.3 1,620 -1%4%1 Length (ft)GR TR (%) Travel Time (min) Length (ft)GR TR (%) Travel Time (min) Length (ft)GR TR (%) Travel Time (min) Total Travel Time (min) Load Time (min) 1 Maneuver and Spread Time (min) Total Cycle Time (min) 1 1,590 0% 5% 0.9 420 7% 12% 0.4 2.7 0.6 0.6 3.9 2 1,810 0% 5% 1.1 760 1% 6% 0.5 3.4 0.6 0.6 4.6 3 1,870 0% 5% 1.1 810 0% 5% 0.5 3.7 0.6 0.6 4.9 4 2,470 0% 5% 1 2.7 0.6 0.6 3.9 5 2,320 0% 5% 1.2 800 -1% 4% 0.5 4.1 0.6 0.6 5.3 6 2,180 0% 5% 1.2 1,310 1% 6% 1.1 4.5 0.6 0.6 5.7 7 1,340 1% 6% 0.8 570 0% 5% 0.3 2.4 0.6 0.6 3.6 8 1,810 0% 5% 1.1 550 -2% 3% 0.3 3.2 0.6 0.6 4.4 9 1,650 0% 5% 1 1,070 -1% 4% 0.5 3.6 0.6 0.6 4.8 10 1,620 0% 5% 0.9 680 1% 6% 0.4 2.9 0.6 0.6 4.1 11 710 0% 5% 0.4 1,110 0% 5% 0.6 1,370 1% 6% 1.2 4.5 0.6 0.6 5.7 12 2,180 0% 5% 1.2 680 1% 6% 0.4 3.5 0.6 0.6 4.7 13 1,440 0% 5% 1.2 2.2 0.6 0.6 3.4 14 2,030 1% 6% 1.3 2.4 0.6 0.6 3.6 15 1,695 -2% 3% 0.6 1,695 2% 7% 0.9 3.8 0.6 0.6 5 16 1,620 1%6%1 1,980 0%5%1.1 4.4 0.6 0.6 5.6 1 Loaded using 1 D8 LOADED TRAVEL TIMES Haul Route EMPTY Haul Route TOTAL Segment B Segment C Segment D Segment E Segment F Segment A Length (ft)Initial El.Final El.Grade (%)Length (ft)Initial El.Final El.Grade (%)Length (ft)Initial El.Final El.Grade (%) 1 420 5,610 5,581 -6.9%1,590 5,581 5,581 0.0% 2 760 5,624 5,617 -0.9%1,810 5,617 5,613 -0.2% 3 810 5,620 5,619 -0.1%1,870 5,619 5,620 0.1% 3a 1,430 5,640 5,619 -1.5%1,870 5,619 5,620 0.1% 3b 1,030 5,629 5,619 -1.0%1,870 5,619 5,620 0.1% 3c 840 5,628 5,619 -1.1%1,870 5,619 5,620 0.1% 3d 560 5,616 5,619 0.5%1,870 5,619 5,620 0.1% 3e 480 5,607 5,619 2.5%1,870 5,619 5,620 0.1% 3f 600 5,606 5,619 2.2%1,870 5,619 5,620 0.1% 4 2,470 5,612 5,620 0.3% 5 800 5,612 5,620 1.0%2,320 5,620 5,625 0.2% 6 1,310 5,625 5,616 -0.7%2,180 5,616 5,625 0.4% 7 570 5,625 5,627 0.4%1,340 5,627 5,620 -0.5% 8 550 5,608 5,617 1.6%1,810 5,617 5,613 -0.2% 9 1,070 5,608 5,620 1.1%1,650 5,620 5,620 0.0% 10 680 5,624 5,616 -1.2%1,620 5,616 5,620 0.2% 11 1,370 5,634 5,622 -0.9%1,110 5,622 5,622 0.0%710 5,622 5,625 0.4% 12 680 5,624 5,616 -1.2%2,180 5,616 5,625 0.4% 13 1,440 5,624 5,620 -0.3% 14 2,030 5,637 5,622 -0.7% 15 1,695 5,640 5,610 -1.8%1,695 5,610 5,637 1.6% 16 1,980 5,610 5,616 0.3%1,620 5,616 5,605 -0.7% Length (ft)Initial El.Final El.Grade (%)Length (ft)Initial El.Final El.Grade (%)Length (ft)Initial El.Final El.Grade (%) 1 1,590 5,581 5,581 0.0%420 5,581 5,610 6.9% 2 1,810 5,613 5,617 0.2%760 5,617 5,624 0.9% 3 1,870 5,620 5,619 -0.1%810 5,619 5,620 0.1% 3a 1,870 5,620 5,619 -0.1%1,430 5,619 5,640 1.5% 3b 1,870 5,620 5,619 -0.1%1,030 5,619 5,629 1.0% 3c 1,870 5,620 5,619 -0.1%840 5,619 5,628 1.1% 3d 1,870 5,620 5,619 -0.1%560 5,619 5,616 -0.5% 3e 1,870 5,620 5,619 -0.1%480 5,619 5,607 -2.5% 3f 1,870 5,620 5,619 -0.1%600 5,619 5,606 -2.2% 4 2,470 5,620 5,612 -0.3% 5 2,320 5,625 5,620 -0.2%800 5,620 5,612 -1.0% 6 2,180 5,625 5,616 -0.4%1,310 5,616 5,625 0.7% 7 1,340 5,620 5,627 0.5%570 5,627 5,625 -0.4% 8 1,810 5,613 5,617 0.2%550 5,617 5,608 -1.6% 9 1,650 5,620 5,620 0.0%1,070 5,620 5,608 -1.1% 10 1,620 5,620 5,616 -0.2%680 5,616 5,624 1.2% 11 710 5,625 5,622 -0.4%1,110 5,622 5,622 0.0%1,370 5,622 5,634 0.9% 12 2,180 5,625 5,616 -0.4%680 5,616 5,624 1.2% 13 1,440 5,620 5,624 0.3% 14 2,030 5,622 5,637 0.7% 15 1,695 5,637 5,610 -1.6%1,695 5,610 5,640 1.8% 1,620 5,605 5,616 0.7%1,980 5,616 5,610 -0.3% Haul Route Haul Route Segment F HAUL ROUTE DISTANCES AND GRADES (LOADED) HAUL ROUTE DISTANCES AND GRADES (EMPTY) Segment A Segment B Segment C Segment D Segment E Estimated Load (LCY) Load Factor Payload (BCY) Cat 637G 31 0.9 27.9 3,200 lb 114,744 lb 89,280 lb 204,024 lb 49% 59% Usable Pull = Traction Factor * Weight on Driving Wheels 0.5 page 27-2 49,986 lb 33,849 lb Altitude Deration Factor @ 5,600 ft amsl = 1 page 27-8 5% page 27-1 Percentage of Weight on Driving Wheels (Loaded) = Assume 1 BCY = Machine Weight (Empty) = Payload = Machine Weight (Loaded) = Calculate Usable Pull (Traction Limitation) Traction Factor (med. firm earth) = Usable Pull (Loaded) = Usable Pull (Empty) = Percentage of Weight on Driving Wheels (Empty)= Rolling Resistance (rutted/flexing dirt roadway w/ little maintenance and no water) = Cell Radon Attenuation and Grading Layer Compacted Radon Attenuation Layer Water Storage Layer Erosion Protection Layer Topsoil Rock Mulch Compacted Outslope Fill Rip Rap Bedding Layer Rip Rap Armor Random Fill Subtotal (cy) 1 58,000 68,000 86,000 8,000 6,000 2,000 33,000 5,000 10,000 245,000 2 231,000 57,000 392,000 57,000 52,000 5,000 9,000 2,000 6,000 689,000 3 544,000 64,000 409,000 59,000 59,000 0 7,000 2,000 4,000 1,024,000 4a 158,000 192,000 241,000 35,000 27,000 9,000 130,000 7,000 20,000 721,000 4b 159,000 197,000 246,000 36,000 27,000 9,000 85,000 5,000 14,000 687,000 Mill 0 0 0 0 55,000 0 0 0 0 0 Subtotal: 1,150,000 578,000 1,374,000 195,000 226,000 25,000 264,000 21,000 54,000 3,366,000 TOTAL:3,366,000 Cell Radon Attenuation and Grading Layer Compacted Radon Attenuation Layer Water Storage Layer Erosion Protection Layer Topsoil Rock Mulch Compacted Outslope Fill Rip Rap Bedding Layer Rip Rap Armor Random Fill Subtotal (cy) 1 54,588 76,000 86,000 8,000 6,000 N/A 36,882 N/A N/A 253,471 2 217,412 63,706 392,000 57,000 52,000 N/A 10,059 N/A N/A 683,176 3 512,000 71,529 409,000 59,000 59,000 N/A 7,824 N/A N/A 1,000,353 4a 148,706 214,588 241,000 35,000 27,000 N/A 145,294 N/A N/A 749,588 4b 149,647 220,176 246,000 36,000 27,000 N/A 95,000 N/A N/A 710,824 Mill 55,000 Subtotal: 1,082,353 646,000 1,374,000 195,000 226,000 0 295,059 0 0 3,397,412 TOTAL:3,398,000 85%Relative Compaction in Stockpiles: IN-PLACE VOLUMES IN-STOCKPILE VOLUMES CELL 1 (EVAPORATION) 0 r <I>MWH ----HAUL ROUTE 1 ----HAUL ROUTE 2 ----HAUL ROUTE 5 ----HAUL ROUTE 6 WHITE MESA MILL RECLAMATION 1T11..E Denison Mines (USA) Corp DATE SEP 2011 HAUL ROUTES 1 - 7 - - -HAU ROLITE 3 ----HAUL ROUTE 4 ----HAUL ROUTE 7 FlL£ NAWE 10119740 BORROW ---HAUL ROUTE 8 ---HAUL ROUTE 9 HAUL ROUTE 10 HAUL ROUTE 11 - - -HAUL ROUTE 12 ---HAU L ROUTE 13 ---HAU L ROUTE 16 CFI L 1 JEVAPORA TION) OENISOJ)~~ WHITE MESA MILL RECLAMATION MINES Denison Mines (USA) Corp HAUL ROUTES 8-16