HomeMy WebLinkAboutDERR-2024-006202
Page | 1
April 16, 2024
Mr. Brett Gurney
Utah Department of Government Operations
Division of Fleet Operations, State of Utah Fuel Network
447 West 13800 South
Draper, Utah 84020
Mr. Kevin Beery
Utah Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, UT 84114
Re: Work Plan and Budget OFU-04 for Corrective Action Plan
Utah State Prison Uintah Maximum Security Generator
14400 South Pony Express Road, Draper, Utah
Facility Identification No. 4002081, Release OFU
Dear Mr. Gurney and Mr. Beery:
WSP USA Environment & Infrastructure, Inc. (WSP) is pleased to present this Work Plan and Budget (WP&B) for preparation
of a Corrective Action Plan (CAP) for the Utah State Prison Uintah Generator, located at 14400 South Pony Express Road,
Draper, Utah (Site), facility ID No. 4002081. The DERR assigned the facility Release OFU. This WP&B was prepared in
response to request from the Division of Environmental Response and Remediation (DERR) in email communications on
February 2, 2024 and April 9, 2024.
The Site is the location of a former underground storage tank (UST) that was closed by removal in October 2022. Findings of
subsurface investigations conducted by WSP at the Site were summarized in a report submitted to the DERR (WSP, 2024)1.
Based on the findings, it was recommended that a CAP for limited source removal will be prepared for the Site.
A CAP meeting was held via video conferencing on January 30, 2024, with participants from the DERR, the Utah Division of
Fleet - State Fuel Network (SFN), which is the Responsible Party (RP) for the Site, the Division of Facilities and Construction
Management (DFCM), and WSP as the certified UST consultant for the RP. The CAP Meeting Summary Letter is attached as
Attachment A. A Public Notice for the proposed CAP was published on March 18, 2024 at the following locations:
DERR Public Notices page at https://documents.deq.utah.gov/environmental-response-and-
remediation/laserfiche/DERR-2024-004878.pdf
Draper public library at 1136 Pioneer Rd, Draper, UT 84020
Riverton public library at 12877 S 1830 W, Riverton, UT 84065
Former State Prison site entrances on 14400 South Pony Express Road, and on 13800 South Street.
No comments were received during the public comments period (March 18 – April 8, 2024).
1 WSP, 2024. Additional Subsurface Investigation Report, Utah State Prison Uintah Generator, Facility ID 4002081 Release OFU, 14400
South Pony Express Road, Draper, Utah WSP USA Environment & Infrastructure Inc., January 12, 2024
10876 South River Front
Parkway
Suite 250
South Jordan, Utah 84095
+1 801-999-2002
wsp.com
Page | 2
The tasks for preparation of the CAP are described in the following paragraphs and include:
Task 1 – Work plan and budget preparation
Task 2 – Health and Safety, communication, and project management
Task 3 – Developing the CAP document, construction design, bidding documents, and cost estimates.
Task 1 – Work Plan and Budget Preparation
Task 1 includes the preparation of this WP&B.
Task 2 – Health and Safety, and Project Administration
Task 2 includes updating of the Site-Specific Health and Safety Plan (HASP) for the field activities, preparation, and submittal
of the Petroleum Storage Tank (PST) Fund request for payment vouchers for cost reimbursements,
Task 2 also includes project management, communicating and coordinating with the client and DERR about the CAP
development and acceptance, and tracking the budget and invoicing in accordance with WSP’s Terms and Conditions.
Task 3 –CAP Preparation
Task 3 includes the preparation of the CAP documents including detailed site background, detailed evaluation of remedial
alternatives, preparation of excavation plan, sampling and analysis plan, and development and distribution of bid
documents for subcontractor. WSP anticipates that the following subcontracts will be required for the CAP implementation:
Soil excavation, transportation, and disposal.
Site survey for excavation area, excavation as built, and confirmation sample locations.
Analytical laboratory.
Task 3 will also include development of detailed cost estimate for the CAP implementation.
The total estimated cost for this WP&B is $9,150. Estimated cost details are provided in Table 1. Labor rates are based on
the DERR Cost Guidelines for Utah Underground Storage Tank Sites, as updated January 2023. The work described above
will be performed on a time and materials basis, and no activities will be performed outside the proposed SOW and budget
without prior approval from the DERR. WSP will prepare and submit the CAP to the DERR within 20 business days of
receiving DERR and SFN approval for the WP&B.
Please contact Ehud Ardon at ehud.ardon@wsp.com or if you have questions or comments regarding this WP&B.
Respectfully submitted,
WSP USA Environment & Infrastructure Inc.
Submitted By: Reviewed By:
Ehud Ardon Bryan Morse
Senior Environmental Scientist Environmental Remediation Lead
Certified UST Consultant # CC-279
Attachments:
Table 1: Cost Estimate
PST Trust Fund Work Plan Approval Application and Agreement
Activity Cost
Senior Project Manager (P101) - Documents and WP&B Review 3 hours $152.00 hour 456.00$
Project Manager (P103) -SOW & Cost Estimate 6 hours $118.00 hour 708.00$
1,164.00$
Project Manager (P101) - Communication, voucher/HASP Review 4 hours $152.00 hour 608.00$
Field Scientist (P104) - HASP 2 hours $101.00 hour 202.00$
Administrative Assistant (P109) 3 hours $62.00 hour 186.00$
PST Claim Specialist (P108) 3 hours $78.00 hour 234.00$
1,230.00$
Senior Project Manager (P101) - Prep/Review 6 hours $152.00 hour 912.00$
Proffesional Geologist (P102) -CAP, design specs., review RFPs 12 hours $138.00 hour 1,656.00$
Project Manager (P103) -CAP document, cost estimates 20 hours $118.00 hour 2,360.00$
Field Scientist (P104) - RFPs, SAP 12 hours $101.00 hour 1,212.00$
Drafter (P107) - Site plans 8 hours $77.00 hour 616.00$
6,756.00$
9,150.00$
Hours or Units Hourly or Unit Rate
WP&B Total
Task 3 - CAP Preperation
Task 3 Subtotal:
Task 1 - WP&B Preparation
Task 1 Subtotal:
Task 2 -Health and Safety, Project Administration
Task 2 Subtotal:
Table 1: Cost Estimate
Utah State Prison Uintah Maximum Security Generator
14400 South Pony Express Road, Draper, Utah
Facility Id No. 4002081, Release OFU
WP&B OFU-04
OFU-04
Utah State Prison Uintah Maximum Security Generator
14400 South Pony Express Road, Draper, Utah
4002081
OFU
Utah State Fuel Network
WSP USA E&I Inc./Ehud Ardon
OFU-04
OFU
Corey Buchanan, Bryan Morse, Ehud Ardon, Rylie Burke
Contract requirements with WSP USA Environment & Infrastructure Inc. (Formerly
Wood Environment & Infrastructure Solutions, Inc.)
Brett Gurney Fuel Network Program Manager 04/09/2024
Ehud Ardon