HomeMy WebLinkAboutDDW-2025-009485Sanitary Survey - Deficiency Report
PWS Number:UTAH05017 Deficiency Points:65 Survey Date:09/16/2025
Survey Name:GREENDALE AND BOOTLEG
CAMPGROUNDS
Surveyor:Hunter Payne
Sanitary Survey Category: FW
SDWIS Severity Code: Significant Deficiency
Storage Tanks | ST001 | STORAGE FACILITY ST001
76C. Access opening lid properly gasketed
Rule: R309-545-14(2)Rule requires the access opening to a tank to be furnished with a gasket between the lid
and frame. This significant deficiency must be corrected within 120 days of notification
or have a corrective action plan approved by DDW.
Notes:Tank lid not completely sealed with gasket. Recommend installing new gasket for a complete
seal.
Deficiency Points: 25
Days until points become effective on IPS: 120
SDWIS Deficiency Description: V009 STORAGE TANK LID LACKS A FUNCTIONING GASKET BETWEEN THE LID AND
FRAME
Sanitary Survey Category: FW
SDWIS Severity Code: Significant Deficiency
Storage Tanks | ST002 | STORAGE FACILITY ST002
96A. Overflow line discharges at least 12 inches above ground or the flood rim of receiving basin?
Rule: R309-545-13 Rule requires all water storage tanks to be provided with an overflow that discharges at
an elevation between 12 and 24 inches above the ground surface or the rim of the
receiving basin.
Notes:The overflow discharge is overgrown and sediment has built up beneath it to the degree that
it no longer has an adequate air gap. Recommend digging out the air gap beneath the
overflow.
Deficiency Points: 25
Days until points become effective on IPS: 120
SDWIS Deficiency Description: V011 END OF STORAGE TANK OVERFLOW LACKS A CLEARANCE OF BETWEEN 12
AND 24 INCHES FROM GROUND SURFACE
Sanitary Survey Category: TR
SDWIS Severity Code: Minor Deficiency
Treatment - Chlorination General | TP001 | GREENDALE WTP
141. Solution tanks and tank refilling line entry points are properly labeled to identify the chemicals
Rule: R309-525-11(8)(c)(vii)Rule requires tanks to be properly labeled to designate the chemical contained.
Notes:Solution tanks were not labeled.
Deficiency Points: 15
Days until points become effective on IPS: 0
SDWIS Deficiency Description: TG03 SOLUTION TANKS AND CHEMICAL REFILL LINES NOT LABELED