Loading...
HomeMy WebLinkAboutDRC-2025-002555Deq submit <dwmrcsubmit@utah.gov> Fwd: Schedule Update 12AUG25 - ES PH3E Liner Construction 1 message LLRW DWMRC <llrw@utah.gov>Tue, Aug 12, 2025 at 8:57 AM To: Deq submit <dwmrcsubmit@utah.gov> drc ---------- Forwarded message --------- From: Shauna L. Watkins <slwatkins@energysolutions.com> Date: Tue, Aug 12, 2025 at 7:10 AM Subject: Schedule Update 12AUG25 - ES PH3E Liner Construction To: carlo Romano (cromano@utah.gov) <cromano@utah.gov>, LLrw@utah.gov <LLrw@utah.gov> Cc: Garrett Q. Dutson <gqdutson@energysolutions.com>, James M. Cason <jmcason@energysolutions.com>, Marissa R. Sotelo <mrsotelo@energysolutions.com>, Todd L. Stewart <tlstewart@energysolutions.com> SHAUNA WATKINS Quality Assurance Specialist II   ENERGYSOLUTIONS LLC 2235 S Saltbush Rd Grantsville, Ut 84029 O: 801-649-2072 C: 435-882-7841 slwatkins@energysolutions.com From: dcummings@brokenarrowusa.com <dcummings@brokenarrowusa.com> Sent: Tuesday, August 12, 2025 7:03 AM To: Garrett Q. Dutson <gqdutson@energysolutions.com>; Shauna L. Watkins <slwatkins@energysolutions.com> Cc: Dave Booth <dbooth@energysolutions.com>; 'Jared Bunn' <jbunn@brokenarrowusa.com>; kcummings@brokenarrowusa.com; shanemartin39@yahoo.com Subject: [EXTERNAL] Schedule Update 12AUG25 - ES PH3E Liner Construction 8/12/25, 12:11 PM State of Utah Mail - Fwd: Schedule Update 12AUG25 - ES PH3E Liner Construction https://mail.google.com/mail/b/AEoRXRQTka32rGZnuzYRfdmzd691fK8v7WlQAUDUNG1ideOWdXfh/u/0/?ik=adf9d5e615&view=pt&search=all&permt…1/3 EXTERNAL: This message is from a NON-EnergySolutions sender, please ensure it is from a legitimate source. DO NOT click links or open attachments if sender is unknown or the message seems suspicious in any way. Good Morning All, Please find attached the updated and final schedule for the subject project. All Broken Arrow contract items were completed as of Friday August 08,2025. Thank you everyone for your support and contributions to this successful and well done clay liner expansion! Regards, Dave David Cummings | SR. Vice President | Broken Arrow Inc. 8960 Clinton Landing Road | Lake Point | Utah | 84074 O: (801) 355-0527 | F: (801) 252-7501 | M: (435) 241-0010   From: dcummings@brokenarrowusa.com <dcummings@brokenarrowusa.com> Sent: Monday, August 4, 2025 3:06 PM To: 'Garrett Q. Dutson' <gqdutson@energysolutions.com>; 'Shauna L. Watkins' <slwatkins@energysolutions.com> Cc: 'Dave Booth' <dbooth@energysolutions.com>; 'Jared Bunn' <jbunn@brokenarrowusa.com>; 'kcummings@brokenarrowusa.com' <kcummings@brokenarrowusa.com>; 'shanemartin39@yahoo.com' <shanemartin39@yahoo.com> Subject: Schedule Update 04AUG25 - ES PH3E Liner Construction 8/12/25, 12:11 PM State of Utah Mail - Fwd: Schedule Update 12AUG25 - ES PH3E Liner Construction https://mail.google.com/mail/b/AEoRXRQTka32rGZnuzYRfdmzd691fK8v7WlQAUDUNG1ideOWdXfh/u/0/?ik=adf9d5e615&view=pt&search=all&permt…2/3 Good Afternoon, Please find the updated schedule for the subject project attached. Regards, Dave David Cummings | SR. Vice President | Broken Arrow Inc. 8960 Clinton Landing Road | Lake Point | Utah | 84074 O: (801) 355-0527 | F: (801) 252-7501 | M: (435) 241-0010   ES PH3E Liner Schedule 12AUG2025.pdf 73K 8/12/25, 12:11 PM State of Utah Mail - Fwd: Schedule Update 12AUG25 - ES PH3E Liner Construction https://mail.google.com/mail/b/AEoRXRQTka32rGZnuzYRfdmzd691fK8v7WlQAUDUNG1ideOWdXfh/u/0/?ik=adf9d5e615&view=pt&search=all&permt…3/3 Energy Solutions / 2025 ES PH3E Liner Schedule Act ID Activity Description Orig Dur Rem Dur Early Start Early Finish % 02 JUN 2025 09 JUL 16 AUG 23 SEP 30 07 14 21 28 04 11 18 25 01 08 15 10 Total Calendar Days 59 *0 *10JUN25 A 08AUG25 A 100 20 Pre-Construction Meeting 0 0 09JUN25 A 100 30 Mobilization Project Support Equipment 4 0 10JUN25 A 16JUN25 A 100 40 Mine and Prepare Clay Liner Material 10 0 16JUN25 A 27JUN25 A 100 50 Establish Foundation Surface 3 0 30JUN25 A 03JUL25 A 100 60 Install Lysimeter Components 12 0 08JUL25 A 28JUL25 A 100 70 Clay Liner Load, Haul, Place and Compact 16 0 16JUL25 A 06AUG25 A 100 80 Clay Liner Finish Grading 2 0 06AUG25 A 07AUG25 A 100 90 Berm Construction 2 0 07AUG25 A 08AUG25 A 100 100 Project Completed & Accepted 0 0 08AUG25 A 100 Total Calendar Days Pre-Construction Meeting Mobilization Project Support Equipment Mine and Prepare Clay Liner Material Establish Foundation Surface Install Lysimeter Components Clay Liner Load, Haul, Place and Compact Clay Liner Finish Grading Berm Construction Project Completed & Accepted Early start point Early finish pointEarly barProgress bar Critical barSummary barProgress point Critical pointSummary pointStart milestone point Finish milestone point Project Owner - Energy Solutions Contractor - Broken Arrow Inc. Date Revision Checked Approved 12AUG25 D.Cummings KC/SM DC 04AUG25 D.Cummings KC/SM DC 29JUL25 D.Cummings KC/SM DC 23JUL25 D.Cummings KC/SM DC Start date 02JUN25 Finish date 12AUG25 Data date 12AUG25 Run date 12AUG25 Page number 1A © Primavera Systems, Inc.