HomeMy WebLinkAboutDRC-2025-002812Energy Solutions / 2025 Evaporation Pond Schedule Act ID Activity Description Orig Dur Rem Dur Early Start Early Finish % 07 JUL 2025 14 AUG 21 SEP 28 OCT 04 NOV 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 10 Total Calendar Days 64 *43 *05AUG25 A 07OCT25 33 100 Pre-Construction Meeting 0 0 05AUG25 A 100 110 Mobilization Project Support Equipment 2 0 04AUG25 A 06AUG25 A 100 120 Site Safety Training 1 0 06AUG25 A 06AUG25 A 100 130 Clearing and Grubbing 1 0 05AUG25 A 11AUG25 A 100 140 Excavation - Approx 43,000 CY 18 8 13AUG25 A 04SEP25 54 150 Berm Construction 2 2 04SEP25 05SEP25 0 160 Foundation Finish Grading 2 2 04SEP25 05SEP25 0 170 Clay Liner Placement - Approx 4,800 CY 5 5 15SEP25 A 12SEP25 0 180 Anchor Trench Construction 2 2 12SEP25 15SEP25 0 190 Clay Liner Finish Grading 3 3 16SEP25 18SEP25 0 200 Sump Construction / Leak Detection System 10 10 19SEP25 02OCT25 0 210 HDPE Liner Installation 7 7 22SEP25 30SEP25 0 220 Spillway and Off-Loading Concrete Work 10 10 22SEP25 03OCT25 0 230 Project Cleanup & Demobilization 2 2 06OCT25 07OCT25 0 240 Project Completed & Accepted 0 0 07OCT25 0 Total Calendar Days Pre-Construction Meeting Mobilization Project Support Equipment Site Safety Training Clearing and Grubbing Excavation - Approx 43,000 CY Berm Construction Foundation Finish Grading Clay Liner Placement - Approx 4,800 CY Anchor Trench Construction Clay Liner Finish Grading Sump Construction / Leak Detection System HDPE Liner Installation Spillway and Off-Loading Concrete Work Project Cleanup & Demobilization Project Completed & Accepted Early start point Early finish point Early barProgress bar Critical bar Summary bar Progress pointCritical point Summary point Start milestone pointFinish milestone point Project Owner - Energy Solutions Contractor - Broken Arrow Inc. Date Revision Checked Approved 26AUG25 D.Cummings KC/SM DC 19AUG25 D.Cummings KC/SM DC 12AUG25 D.Cummings KC/SM DC 04AUG25 D.Cummings KC/SM DC Start date 18JUN25 Finish date 07OCT25 Data date 26AUG25 Run date 26AUG25 Page number 1A © Primavera Systems, Inc.