HomeMy WebLinkAboutDERR-2025-006523VCP/BROWNFIELDS SECTION – SITE VISIT REPORT
SITE NAME: Murray UTA Lots/Firestation DATE: August 28, 2025
PROJECT MANAGER: Leigh Anderson
PURPOSE OF VISIT: Conduct annual site inspection for the SMP, inspecting repository cap in parking
lot, foundations of buildings, landscaping and cobble slope armor around retention basin, and VMS
risers on roof.
sidewalks, and foundations. Risers also had valves open and meet s
south of retention basin has lost some of the cobble armor and the black geo fabric is exposed in
some locations.
SPLIT SAMPLES COLLECTED?
YES NO COMMENTS:
YES NO COMMENTS:
ATTACHMENTS (PHOTOS, MAPS, ETC.) YES NO
South along Box Elder Street. Southernmost parcel still undeveloped.
Cell tower south of fire station.
Area with thin cobble armoring south of retention basin, some of the geofabric is exposed.