HomeMy WebLinkAboutDERR-2025-005380Utah Department of Environmental Quality - UST Release Detection
TANK OWNERSHIP
Name UTAH STATE FUEL NETWORK
Address 4315 S 2700 W
SALT LAKE CITY, UT 84129
Contact UTAH STATE FUEL NETWORK
Phone
Email brettgurney@utah.gov
TANK LOCATION
Name CLEARFIELD CITY SHOPS
Address 497 S MAIN ST
CLEARFIELD, UT 84015
A Operator None
Phone None
B Operator SAME
Phone SAME
Facility ID: 3000303 Inspection Date: 07/23/2025
DISPENSER DETAILS
DISP
ID/ALT
ID
SUBSTANCE UDC PIPE FLEX LOC
INSTALL
DATE
UDC
INSTALL
DATE
FIRE
VALVE
SAT
PRESENT
UDC
TEST
DISP
FLEX
CP
TEST
1 - 1 Gasoline Yes Steel Flex in Sump None None Yes No None None
2 - 2 Diesel Yes Steel Flex in Sump None None Yes No None None
TANK DETAILS
Tank ID/Alt ID 5 / 5
E-Gen/AST No / Yes
Siphon/Compart No / No
Tank Status Currently In Use
Installed/Cap/Loc Oct. 14, 2015 / 6000 /
Substance
Stored Diesel /
Tank Material-
Mod
Asphalt Coated or Bare Steel-
Double-Walled
ATG Veeder Root / TLS-300 CSLD No
Manifold
LTT Test None
LLD Test None
Pipe Material-
Mod Flexible Plastic / Double-Walled
Pipe type/STP
Cont Pressurized / No
STP Flex
Connectors
LLD Model
Spill/Overfill/Sm
Delivery
5 gal. Per Prod. APST Cont. Sump
/ Automatic shutoff / No
PST Fund/Other
Type Yes / None
Tank/Pipe Rel
Det TankTightness PipeLineTightness
CP Tank Test None
CP Pipe Test None
Tank ID/Alt ID 6 / 6
E-Gen/AST No / Yes
Siphon/Compart No / No
Tank Status Currently In Use
Installed/Cap/Loc Oct. 14, 2015 / 12000 /
Substance
Stored Gasoline / Regular
Tank Material-
Mod
Asphalt Coated or Bare Steel-
Double-Walled
ATG Veeder Root / TLS-300 CSLD No
Manifold
LTT Test None
LLD Test None
Pipe Material-
Mod
Fiberglass Reinforced Plastic /
Double-Walled
Pipe type/STP
Cont Pressurized / No
STP Flex
Connectors
LLD Model
Spill/Overfill/Sm
Delivery
5 gal. Per Prod. APST Cont. Sump
/ Automatic shutoff / No
PST Fund/Other
Type Yes / None
Tank/Pipe Rel
Det TankTightness PipeLineTightness
CP Tank Test None
CP Pipe Test None
INSPECTION COMMENTS
None
2025-07-23 Page 1 of 3
FACILITY RESPONSES
Financial Responsibility
Financial responsibility method is ok?Yes
The above accurately represents the
facility's release detection records Yes
TANK RESPONSES
Tank 5 Pressure Piping Leak Detection
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
Yes
Tank 6 Spill/Overfill
Tank has a spill prevention device?Yes
Are you able to visually inspect the spill
containment bucket(s) for functionality?
(i.e. are the buckets clean enough to
see cracks, etc?)
Yes
Is the spill containment bucket intact?Yes
Is the spill containment bucket(s) able
to contain a spill? (i.e. is there water,
product, debris, etc in the spill bucket
to prevent it from containing a spill?)
Yes
Tank 6 Spill/Overfill
Does the spill bucket have a valid 3-
year test, valid monthly monitoring for
DW buckets, or the tank is exempt?
Yes
Tank 5 Spill/Overfill
Tank has a spill prevention device?Yes
Are you able to visually inspect the spill
containment bucket(s) for functionality?
(i.e. are the buckets clean enough to
see cracks, etc?)
Yes
Is the spill containment bucket intact?Yes
Is the spill containment bucket(s) able
to contain a spill? (i.e. is there water,
product, debris, etc in the spill bucket
to prevent it from containing a spill?)
Yes
Tank 5 Spill/Overfill
Does the spill bucket have a valid 3-
year test, valid monthly monitoring for
DW buckets, or the tank is exempt?
Yes
Tank 6 Pressure Piping Leak Detection
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
Yes
DISPENSER RESPONSES
Dispenser 2
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
Dispenser 1
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
MONTHLY LEAK DETECTION MONITORING
Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25 May '25 Jun '25
Tank 5 Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Tank 6 Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
NON-COMPLIANCE ITEMS
All items are in compliance.
2025-07-23 Page 2 of 3
Prepared by fueloperator.com
Inspection Information
Inspector:Harris, Gary
Record Created:July 23, 2025, 12:40
p.m.
Inspection Date:July 23, 2025
2025-07-23 Page 3 of 3