HomeMy WebLinkAboutDAQ-2024-0073191
DAQC-300-24
Site ID 12495 (B5)
MEMORANDUM
TO: CEM FILE – WEST VALLEY POWER
THROUGH: Harold Burge, Major Source Compliance Section Manager
FROM: Rob Leishman, Environmental Scientist
DATE: March 24, 2024
SUBJECT: Source: Units 1, 2, 3, 4, and 5 (GE LM600 Natural Gas Turbines)
Contact: Jerame Blevins – 801-967-1200 ext.232
Location: 5935 West 4700 South, West Valley City, Salt Lake County, UT
Test Contractor: Alliance Technical Group
FRS ID#: UT0000004903500527
Permit/AO#: Title V operating permit 3500527004, dated July 12, 2019
Subject: Review of RA/PST Protocol dated March 18, 2024
On March 20, 2024, DAQ received a protocol for a RA/PST (relative accuracy/performance specification
test) of the West Valley Power electrical generation facility in West Valley City, UT. Testing will be
performed on June 17-21, 2024, to determine the relative accuracy of the O2, CO2, NOX, and CO
monitoring systems.
PROTOCOL CONDITIONS:
1. RM 1 used to determine sample velocity traverses: OK
2. RM 3A used to determine dry molecular weight of the gas stream: OK
3. RM 7E used to determine NOX concentrations of emissions: OK
4. RM 10 used to determine CO concentrations of emissions: OK
5. RM 19 used to determine volumetric flow: OK
6. RM 205 used to validate gas dilution systems for field instrument calibration: OK
DEVIATIONS: No deviations were noted.
CONCLUSION: The protocol appears to be acceptable.
RECOMMENDATION: Send attached protocol review and test date confirmation notice.
1 8 2
WEST v*U.Uy POWnn
March L8,2024
Director
State of Utah
Department of Environmental Quality * Division of Air Quality
195 North 1950 West Temple
salt Lake city, uT 84116-3100
USEPA, Region Vlll
Office of Enforcement, Compliance and Environmental Justice
(Mail Code 8ENF)
1595 Wynkoop Street
Denver, CO 80202-1129
UTAH DEPARruENT OF
ENVIRONMENTAL OUAIJTY
t'4AR ? O 2|,4
DIVISION OF AIR QUALITY
Reference: West Valley Power Plant (Permit #35@527004)
2024 Relative Accuracy Test Audit (RATA) Protocol Submittal and Test Notification
Dear Director:
Utah Municipal Power Agency has contracted Alliance Source Testing to conduct Relative Accuracy Test
Audits (RATAs) on the continuous emissions monitoring systems (CEMS) for five natural gas combustion
turbines located at the West Valley Power Plant (Permit #3500527004).
ln accordance with UAC R307,170-7(2) notice is being given that testing is scheduled to be conducted
during the week beginning June L7 ,2024.
For your review, please find enclosed a copy of the Source Emissions Test Protocol for conducting
testing to determine the relative accuracy of the oxygen(Oz), nitrogen oxides (NOx) and carbon
monoxide (CO) CEMS installed on each of five General Electric 1M5000 PC Sprint natural gas fired
combustion turbine generators (Units 1 - 5).
Should you have any questions or need additional information regarding this submittal, please contact
Jerame Blevins at (801) 957-7200 ext 232.
Sincerely,
Ku*#afuZ
Kevin G#lick
Responsible Official
West Valley Power Plant
Enclosure
CC: J. Blevins, Chris Cook & West Valley Compliance File
Trinity Consultants: Melissa Armer
At6rre
TECHNICAL GROUP
Site Specific Test PIan
Utah Municipal Power Agency
West Valley Power
5935 West 4700 South
West Valley City, UT 841 18
Sources to be Tested: Units l-5
Proposed Test Dates: June 17-21,2024
Project No. AST-2024-177 8
Prepared By
Alliance Technical Group,
3683 W 2270 S, Sui
West Valley City,
UTAH DEPA,RTMENT OF
ENVIRONMENTAL OUATITY
DIVISION OF AIR QUALITY
NICAL
Informetion
Permit No.
Regulatory Citations
Source Informetion
Sowce Name
(5) General Electric Model LM600
PC Sprin! Natural Gas-Fired
Simple Cycle Combustion Turbine
Generaton
Contect Infometion
Permit 35005274o4.
B, Performance Specifications 2,3 and 4
A&B
Tifle V
40 cFR60,
40 CER75,
ID
1
2
3
4
5
nit
nit
nit
nit
nit
Target Ptaneters
O2,NOx, CO
oz,NOX, CO
O2,NOX, CO
O2,NOx, CO
Ou,N0x, CO
Test Compary
Alliance Technical Group, LLC
3683W 2270 S, Suit€E
West Valley City, UT 84120
Projec'tManager
Charles Horton
chades.horton@alliancetg.com
(3s2) 663-7568
Field Manager
Ryan Lyons
ryan.lyons@allianceQ.com
(708) 21,t4850
(subject to change)
QA/QCManager
Kdrleen Shonk
katie.shonk@alliancetg.com
(812) 452478s
Test Plan/Report Coordinator
Indah Rahmadina
indah.rahmadina@alliancetg.com
Test Location
Utah Municipal Power Agency
West Valley Power
5935 West 4700 South
West Valley City, UT 841l8
Jerame Blevins
jerame@umpa.energy
(801) 967-1200
AST-z,a.+tTt8 Crty, UI
pur6rpe
Site Specific Test Plot
Table ofContentsTECHNICAL GROTJP
TABLE OF CONTENTS
2.0 Summary of Test Program ............ 2-l
2.2 Process/Control System Parameters to be Monitored and Recorded ................. ...................2-l
3.1 U.S. EPA Reference Test Method I - Sample Point Determination........... .......................... 3-l
3.2 U.S. EPA Reference Test Method 3A - Oxygen/Carbon Dioxide........ .......... 3-l
3 .3 U.S. EPA Reference Test Method 7E - Nitrogen Oxides .......... ..................... 3- I
3.4 U.S.EPAReferenceTestMethod l0-CarbonMonoxide..... ........................3-2
3.5 U.S. EPA Reference Test Method 19 - Mass Emission Factors ..................... 3-2
3.6 Quality Assurance/Quality Control - U.S. EPA Reference Test Methods 3A,78 and 10..........................3-2
LIST OF TABLES
Table 2-l: Program Outline and Tentative Test Schedule ......................2-2
Table 2-2: Relative Accuracy Requirements and Limits.... .................... 2-3
LIST OF APPENDICES
AppendixA MethodlData
Appendix B Example Field Data Sheets
AST-2024-1778 West Valley Power - West Valley Crty, Uf Page ii
pur6rpe
TECI-1NICAt. GROI.JP
Sile Specfic Test Plan
Introduction
1.0 Introduction
Alliance Technical Group, LLC (Alliance) was retained by Utah Municipal Power Agency to conduct performance
specification (PS) testing at the West Valley Power plant in West Valley City, Utah. Portions of the facility are
subject to provisions of 40 CFR 60, Appendix B, PS 2, 3 and 4 and 40 CFR 75, Appendices A & B. The facility
operates under the Utah Department of Environmental Quality, Division of Air Quality (UDAQ) Title V Operating
permit No. 3500527004. Testing will include conducting a relative accuracy test audit (RATA) to determine the
relative accuracy (RA) of the oxygen (Oz), nitrogen oxides (NOx) and carbon monoxide (CO) continuous emissions
monitoring systems (CEMS) installed on five (5) General Elechic Natural Gas-Fired Combustion Turbine
Generators designated as Units l-5.
This site-specific test plan (SSTP) has been prepared to address the notification and testing requirements of the
UDAQ Title V permit.
1.1 Facility Descriptions
West Valley Power operates five (5) General Electric Model LM600 PC Spring, Natural Gas-Fired, Simple Cycle
Combustion Turbine Generators at the West Valley Generating Station. The generators are designated as Units l-5.
1.2 CEMS Descriptions
Unit I
Pollutant
NOx
Thermo
42iQLS
1200696549
Low:0-l00ppm
High:0-500ppm
Pollutant
NOx
Thermo
42iQLS
1200696550
Low:0-l00ppm
High:0-500ppm
Pollutant
NOx
Thermo
42iQLS
12006955 I
Low:0-l00ppm
High:0-500ppm
Parameter:
Make:
Model:
Serial No.:
Span:
Unil 2
Parameter:
Make:
Model:
Serial No.:
Span:
Unit 3
Parameter:
Make:
Model:
Serial No.:
Span:
Pollutant
COIOz
Thermo
48iQ
1200696s54
CO:0-10,000ppm
O1.0-25%o
Pollutant
COIOz
Thermo
48iQ
1200696ss5
CO:0-10,000ppm
Oz:0-25%o
P,ollutant
COIOz
Thermo
48iQ
1200696s56
CO: Gl0,000ppm
Oz:.0-25o/o
AST-202+1778 West Valley Power- West Valley City, UT Page l-l
pilt6rpe
TECHNICAI GROT]P Site Specific Test Plot
Introduction
Unit 4
Parameter:
Make:
Model:
Serial No.:
Span:
Unit 5
Parameter:
Make:
Model:
Serial No.:
Span:
Pollutant
NOx
Thermo
42iQLS
1200696552
Low:0-lOOppm
High:0-500ppm
Pollutant
NOx
Thermo
42iQLS
1200696553
Low:0-l00ppm
High:0-500ppm
Pollutant
COIOz
Thermo
48iQ
1200696557
CO:0-10,000ppm
Oz:0-25o/o
Pollutant
COIOz
Thermo
48iQ
1200696558
CO:0-10,000ppm
Oz:.0-25Yo
1.3 Project Team
Personnel planned to be involved in this project are identified in the following table.
Table 1-1: Project Team
1.4 Safety Requirements
Testing personnel will undergo site-specific safety training for all applicable areas upon arrival at the site. Alliance
personnel will have current OSIIA or MSHA safety training and be equipped with hard hats, safety glasses with side
shields, steel-toed safet5r shoes, hearing protection, fire resistant clothing, and fall protection (including shock
corded lanyards and full-body harnesses). Alliance personnel will conduct themselves in a manner consistent with
Client and Alliance's safety policies.
A Job Safety Analysis (JSA) will be completed daily by the Alliance Field Team Leader.
West Valley Power Personnel Jerame Blevins
Regulatory Agency UDAQ
Alliance Personnel Ryan Lyons
other field personnel assigned at time oftesting event
AST-202+1778 West Valley Power - West Valley City, UT Page 1-2
put6rpe
Ti..CllNlCAt GR()tlP Site Specfic Test Plan
Summary ofTest
2.0 Summary of Test Program
To satisfr the requirements of the UDAQ Title V permit, the facility will conduct a performance test program to
determine the compliance status of Units l-5.
2.1 General Description
All testing will be performed in accordance with specifications stipulated in U.S. EPA Reference Test Methods l,
3A, TE, 10, and 19. Table 2-l presents an outline and tentative schedule for the emissions testing program. The
following is a summary of the test objectives.
o Testing will be performed to demonstrate compliance with the UDAQ Title V permit, 40 CFR 60,
Appendix B, PS 2, 3 and 4, and 40 CFR 75, Appendices A & B.
o Emissions testing will be conducted on the exhaust of Units l-5.
o Performance testing will be conducted at more than 50 percent of normal load.
r Each of tho 9-12 test runs will be approximately 2l minutes in duration.
2.2 Process/Control System Parameters to be Monitored rnd Recorded
Plant personnel will collect operational and parametric data at least once every 15 minutes during the testing. The
following list identifies the measurements, observations and records that will be collected during the testing
progftlm:
o Production rate - KW
o Gas Flow Rate - scflt
r CEMS Data
2.3 Proposed Test Schedule
Table 2-l presents an outline and tentative schedule for the emissions testing progrirm.
AST-2024-1'178 West Valley Power - West Valley City, UT PWe2-1
pilt6rpe
TECHNICAL GROUP Stte Wcific Test Plot
&mnry of Test Progrons
Table 2-1: Progrem Outline end Tentetive Test Schedule
DAY I -hne17,2024
Equipment Setup & Pretest QA/QC Checks
l0 hr
Unit I
Oz 3A
9-12 21minNOx7E
CO 10
VFR/ lbAdMBtu 19
DAY2-June 18,2024
Unit 2
Oz 3A
9-12 2l min
l0 hr
NOx 7E
co l0
VFR/lbA,IMBtu l9
DAY3 -Jvne19,2024
Unit 3
Oz 3A
9-12 2l min
l0 hr
NOx 7E
CO l0
\r'FR/IbA{MBtU l9
DAY4 -hllnre20,2024
Unit 4
Oz 3A
9-12 2l min
l0 hr
NOx TE
CO t0
VFR/ lbA4MBtu t9
DAY 5 -hne21,2024
Unit 5
Oz 3A
9-12 2l min
l0 hr
NOx 7E
CO t0
VFR/ IbNVIMBfu t9
AST-202+1778 West Valley Power- West Valley City, LfT Page2-2
AltfuTECHNICAL GROUP
2.4 Emission Limits
Emission limits for each pollutant are below.
Table 2-2: Reletive Requirements and Limits
2.5 Test Report
The final tost report must be submitted within 60
following inform ation.
of the completion of the performance test and will include the
c Introductioz - Brief discussion of project of work and activities.
o Results and Discussion - A summary rpsults and process/control system operational data with
comparison to regulatory requirements or guarantees along with a description of process conditions
and/or testing deviations that may have the testing results.
o Methodologt- A description of the and analytical methodologies.
for each targct parameter.
electronic field data sheets.
c Sample Calculations-Examplecalculati
o Field Dda- Copies of actual handwritten
o Quality Control Data- Copies of all instru
o Process Oryrating/Control System Data-
calibration data and/or calibration gas certificates.
operating and control system data (as provided by West
Valley Power) to support the test results.
60, Appendix B, PS 3or * I o/oOz
Units l-5
or d<0.7o/oOz T5,AppendixA&B
100 ppmvd
@l5o/oOz;
7.41b/hr
60, Appendix B, PS 2or<10 % (AS)
or d < 0.015 T5,AppendixA&B
or <5 Yo (AS) or 10 ppmvd
@l5o/oOz;
8.75lb/hr
West Valle,y - West Valley City, UT Page 2-3
tl B
Site Specific Test Plan
Testing Melhodolog)
3.0 Testing Methodologr
This section provides a description of the sampling and analytical procedures for each test method that will be
employed during the test program. All equipment, procedures and quality assurance measures necessary for the
completion of the test program meet or exceed the specifications of each relevant test method. The emission testing
progr.rm will be conducted in accordance with the test methods listed in Table 3-l.
Table 3-l: Source Testing Methodolory
All stack diameters, depths, widths, upstream and downstream disturbance distances and nipple lengths will be
measured on site with an EPA Method I verification measurement provided by the Field Team Leader. These
measurements will be included in the test report.
3.1 U.S. EPA Reference Test Method I - Sample Point Determination
The sampling location will be evaluated in accordance with U.S. EPA Reference Test Method l. The upstream and
downstream distances will be measured and equated to equivalent diameters to confirm compliance with U.S. EPA
Reference Test Method l.
3.2 U.S. EPA Reference Test Method 3A - Oxygen/Carbon Dioxide
The oxygen (Oz) and carbon dioxide (COz) testing will be conducted in accordance with U.S. EPA Reference Test
Method 3A.. Data will be collected online and reported in one-minute averages. The sampling system will consist
of a stainless steel probe, Teflon sample line(s), gas conditioning system and the identified gas analyzer. The gas
conditioning system will be a non-contact condenser used to remove moisture from the stack gas. If an unheated
Teflon sample line is used, then a portable non-contact condenser will be placed in the system directly after the
probe. Otherwise, a heated Teflon sample line will be used. The quality control measures are described in Section
3.6.
The relative accuracy of the Oz CEMS will be determined based on procedures found in 40 CFR 75, Appendices A
& B and 40 CFR 60, Appendix B, Performance Specification 3.
3.3 U.S. EPA Reference Test Method 7E - Nitrogen Oxides
The nitrogen oxides (NOx) testing will be conducted in accordance with U.S. EPA Reference Test Method 7E. Data
will be collected online and reported in one-minute averages. The sampling system will consist of a stainless steel
probe, Teflon sample line(s), gas conditioning system and the identified gas analyzer. The gas conditioning system
will be a non-contact condenser used to remove moisture from the stack gas. If an unheated Teflon sample line is
used, then a portable non-contact condenser will be placed in the system directly after the probe. Otherwise, a
heated Teflon sample line will be used. The quality control measures are described in Section 3.6.
Orygen / Carbon Dioxide
Volumetric Flow Rate / Mass Emission Factors Fuel Factors / Heat Inputs
AST-202+1778 West Valley Power- West Valley City, UT Page 3-l
put6rpe
Site Specific Test Plan
Testing MethodologtI L L]IINICAi Gti(.)trP
The relative accuracy of the NOx CEMS will be determined based on procedures found in 40 CFR 75, Appendices
A & B and 40 CFR 60, Appendix B, Performance Specification 2.
3.4 U.S. EPA Reference Test Method 10 - Carbon Monoxide
The carbon monoxide (CO) testing will be conducted in accordance with U.S. EPA Reference Test Method 10.
Data will be collected online and reported in one-minute averages. The sampling system will consist of a stainless
steel probe, Teflon sample line(s), gas conditioning system, and the identified gas analyzer. The gas conditioning
system will be a non-contact condenser used to remove moisture from the gas. If an unheated Teflon sample line is
used, then a portable non-contact condenser will be placed in the system directly after the probe. Otherwise, a
heated Teflon sample line will be used. The quality control measures are described in Section 3.6.
The relative accuracy of the CO CEMS will be determined based on procedures found in 40 CFR 60, Appendix B,
Performance Specifi cation 4.
3.5 U.S. EPA Reference Test Method 19 - Volumetric Flow Rate / Mass Emission Factors
The gas volumetric flow rate will be determined in accordance with U.S. EPA Reference Test Method 19 using the
measured oxygen concentration, the published fuel factor, a calibrated gas meter and the fuel heating value.
The pollutant concentrations will be converted to mass emission factors flb[\{MBtu) using procedures outlined in
U.S. EPA Reference Test Method 19. The published dry 02 based fuel factor (F-Factor) of 8,710 dscflMMBtu for
natural gas will be used in the calculations.
3.6 Quality Assurance/Quality Control - U.S. EPA Reference Test Methods 3A, 7E and 10
Cylinder calibration gases will meet EPA Protocol 1 (+l- 2%) standards. Copies of all calibration gas certificates
will be included in the Quality Assurance/Quality Control Appendix of the report.
Low Level gas will be introduced directly to the analyzer. After adjusting the analyzer to the Low-Level gas
concentration and once the analyzer reading is stable, the analyzer value will be recorded. This process will be
repeated for the High-Level gas. For the Calibration Error Test, Low, Mid, and High-Level calibration gases will be
sequentially introduced directly to the analyzer. The Calibration Error for each gas must be within 2.0 percent of the
Calibration Span or 0.5 ppmvlYo absolute difference.
High or Mid-Level gas (whichever is closer to the stack gas concentration) will be introduced at the probe and the
time required for the analyzer reading to reach 95 percent or 0.5 ppm/%o (whichever was less restrictive) of the gas
concentration will be recorded. The analyzer reading will be observed until it reaches a stable value, and this value
will be recorded. Next, Low-Level gas will be introduced at the probe and the time required for the analyzer reading
to decrease to a value within 5.0 percent or 0.5 ppm/% (whichever was less restrictive) will be recorded. If the Low-
Level gas is zero gas, the acceptable response must be 5.0 percent of the upscale gas concentration or 0.5 ppmlYo
(whichever was less restrictive). The analyzer reading will be observed until it reaches a stable value, and this value
will be recorded. The measurement system response time and initial system bias will be determined from these data.
The System Bias for each gas must be within 5.0 percent of the Calibration Span or 0.5 ppmv/% absolute difference.
High or Mid-Level gas (whichever is closer to the stack gas concentration) will be introduced at the probe. After the
analyzer response is stable, the value will be recorded. Next, Low-Level gas will be introduced at the probe, and the
analyzer value will be recorded once it reaches a stable response. The System Bias for each gas must be within 5.0
AST-2024-1778 West Valley Power- West Valle.v City, UT Page3-2
pul6rpEr
IL a-)rll.l ialAi r. [-.] () i i'F-'
Site Specific Test Plan
Testing Methodologt
percent of the Calibration Span or 0.5 ppmv/o/o absolute difference or the data is invalidated, and the Calibration
Error Test and System Bias must be repeated.
The Drift between pre- and post-run System Bias must be within 3 percent of the Calibration Span or 0.5 ppmv/%
absolute difference or the Calibration Error Test and System Bias must be repeated.
To determine the number of sampling points, a gas stratification check will be conducted prior to initiating testing.
The pollutant concentrations will be measured at twelve traverse points (as described in Method 1) or three points
(16.7, 50.0 and 83.3 percent of the measurement line). Each traverse point will be sampled for a minimum of twice
the system response time.
If the pollutant concentration at each traverse point do not differ more than 5% or 0.5 ppmlO.3o/o (whichever is less
restrictive) of the average pollutant concentration, then single point sampling will be conducted during the test runs.
If the pollutant concentration does not meet these specifications but differs less than lDoh or I .0 ppm/O.5% from the
average concenffation, then three (3) point sampling will be conducted (stacks less than 7.8 feet in diameter - 16.7,
50.0 and 83.3 percent of the measurement line; stacks greater than 7.8 feet in diameter- 0.4, 1.0, and 2.0 meters
from the stack wall). If the pollutant concentration differs by more than l0% or 1.0 ppm/O.5%ofrom the average
concentration, then sampling will be conducted at a minimum of twelve (12) traverse points. Copies of stratification
check data will be included in the Quality Assurance/Quality Control Appendix of the report.
An NOz- NO converter check will be performed on the analyzer prior to initiating testing. Mid-level nitrogen oxide
protocol I calibration gas will be mixed at a l:l ratio with span level protocol I oxygen calibration gas in a Tedlar
sample bag to form NOz gas. The NOz gas will be delivered to the nitrogen oxides analyzer directly from a Tedlar
sample bag. The response of the analyzer must be stable for the 30-minute duration of the test with the variation
less than 2.0o/o at the end of the test from the maximum value of the test.
A Data Acquisition System with battery backup will be used to record the instrument response in one (l) minute
averages. The data will be continuously stored as a *.CSV file in Excel format on the hard drive of a computer. At
the completion of testing, the data will also be saved to the Alliance server. All data will be reviewed by the Field
Team Leader before leaving the facility. Once arriving at Alliance's office, all written and electronic data will be
relinquished to the report coordinator and then a final review will be performed by the Project Manager.
AST-2024-1778 West Valley Power* West Valley City, UT Page 3-3
pill6rpe
I Lrt_lllNi(- Ai i_:flt.llti.Site Specific Test Plan
Quality Assurorce P rogram
4.0 Quality Assurance Program
Alliance follows the procedures outlined in the Quality Assurance/Quality Conhol Management Plan to ensure the
continuous production of useful and valid data throughout the course of this test program. The QC checks and
procedures described in this section represent an integral part of the overall sampling and analytical scheme.
Adherence to prescribed procedures is quite often the most applicable QC check.
4.1 Equipment
Field test equipment is assigned a unique, permanent identification number. Prior to mobilizing for the test
program, equipment is inspected before being packed to detect equipment problems prior to arriving on site. This
minimizes lost time on the job site due to equipment failure. Occasional equipment failure in the field is
unavoidable despite the most rigorous inspection and maintenance procedures. Therefore, replacements for critical
equipment or components are brought to the job site. Equipment returning from the field is inspected before it is
returned to storage. During the course of these inspections, items are cleaned, repaired, reconditioned and
recalibrated where necessary.
Calibrations are conducted in a manner, and at a frequency, which meets or exceeds U.S. EPA specifications. The
calibration procedures outlined in the U.S. EPA Methods, and those recommended within the Quality Assurance
Handbook for Air Pollution Measurement Systems: Volume III (EPA-600/R-94/038I, September 1994) are utilized.
When these methods are inapplicable, methods such as those prescribed by the American Society for Testing and
Materials (ASTM) or other nationally recognized agency may be used. Data obtained during calibrations is checked
for completeness and accuracy. Copies of calibration forms are included in the report.
The following sections elaborate on the calibration procedures followed by Alliance for these items of equipment.
Barometer. The barometric pressure is obtained from a nationally recognized agency or a calibrated
barometer. Calibrated barometers are checked prior to each field trip against a mercury barometer. The
barometer is acceptable if the values agree within + 2 percent absolute. Barometers not meeting this
requirement are adjusted or taken out of service.
Other Eguipment. A mass flow controller calibration is conducted on each Environics system annually
following the procedures in the Manufacturer's Operation manual. A methane/ethane penetration factor
check is conducted on the total hydrocarbon analyzers equipped with non-methane cutters every six (6)
months following the procedures in 40 CFR 60, Subpart JJJJ. Other equipment such as probes, umbilical
lines, cold boxes, etc. are routinely maintained and inspected to ensure that they are in good working order.
They are repaired or replaced as needed.
4.2 Field Sampling
Field sampling will be done in accordance with the Standard Operating Procedures (SOP) for the applicable test
method(s). General QC measures for the test program include:
o The sampling port will be sealed to prevent air from leaking from the port.
o All raw data will be maintained in organized manner.
. All raw data will be reviewed on a daily basis for completeness and acceptability.
AST-2024-1778 West Valley Power - West Valley City, UT Pa4e 4-l
A6rr
Iedoo Ut*
soomlrd
Method L Data
lAlrc6
Irrd (H,.aaalr: Vdi..l
Di.llrritr CnEh
Itbh..AoalrrwdloMd.ollolt! l't.f h
I{IDLLqt. ll.?' bDa(rdhr:!!!q_h
Clorlt.dmrf AuolDtd! lf3.r0 If
Nq ol Ld lorr$ _.,:l__Diare* 7.0 lr
D&le A DBr DaElfrr 0.5 (El Dr > 0.5)
D(,e& 633 tt
Dl*& B h D&hD: --jll(@. D. >2)
A.rrlNdsdTilmltfur 3
Lb--
---b
----L
I Dtr(:f
,tudrwpotu6.
Dt tls
htu l*l*EFl+l
I
,
3
a
t
5
1
t,
l0
lt
t,
76(l,llta
t,1.6 16.7 6.7 - 44
t5t 50.0 25.0 - 11.6
- t33 ?10 - D.6,$ 1na
$''
. 95.6 -
.2-2.6-Lt
r.r-t.2-6.1
).{-11.6-ll.tt.t-/t,5-',.7
t,7 - 3a.2 2t.O
).5-6r.!-rr.
t.5 - Tr.t, - a.1
i.t-Et.a-75.o
9t.t - a3::'::g:
vt9 ffi
Pht,
Cror S.diolAH
S..tDi.trr
A- 7t1.
B-63ft.
u- la4ir
A/rfu Method I Data
IftdioD Ui.h
Sorro
D*l Oridlrrionr Vdidl
Dud D$igtr: Circu.l{
NimL langh: 11.75 lo
D.pthofDucr: 144.00 tn
Crc$Sdioo.lAdofDudt 113 10 ft,
No- of T.d Potu: 4
oi*mc,r:---Ji'-t
Dirte A IrrA IX@tc6: 0.6 (mat b. > 0O
Di$uce B: 63.0 ft
Dlilrc B lhd DimtcB: 53 (mut bc > 2)
Acud N@fi.r d TmcE. Poifr: l
LOCATION OT TRAVENSE PIOINTS
Ntilbqoffr$as.poift@afiM
I
3
1
5
6
1
t
9
t0
il
t2
2 {5 6 E 9 l0 lt l2
t4.6 t6.7 6.7 - 4.4 - 3.2 - 2.6 - 2.1
85.4 50.0 25.0 - 14.6 - 10.5 - 8.2 - 6.7
- 83.3 75.0 - 29.6 - 19.4 - 14.5 - ll.8"
: : . [' ri'fi,;i
Trtvana
Poiil
v.6 Di.te@ fDm
Di,mter nrll ouBidc oI
I
3
4
6
1
t
9
l0
il
16,7
50.0
'1',
:
24.05
72.00
I 1995
:
35.80
83.75
I3L70
:
Suct Di!8m
A= 7fl
B=63ft.
Dcpth oflrst = 144 in.
CrGs Sdti@l Asa
Upsalm
Disurb.ne
AFre Method I Data
ndtrndo:_lEE!_
hllcrltf Ciwlr
D.0.loaH: 1,1.1.00 h
cE s.frd Am oaDoar_!!!r!!_f
iGdlsalrl&_ji_
Dtr.e A: 7.0 tr
DIEAIIdDGT! 0.6 (dlE
Dail&f,! 63.0 n
DhethDtrerrg(Ei ba>2)
Adrd N6b6dTm !ert-_L
t,d* vdl b nfirE Polnt,
ffi
6.7
il.t
17.7
2t.0
35.6
a.1
75.0
&.3
rE2
93.3
a2
la.5
t2.6
42
65.t
7r.1
at.4
9t.t
":
3.2
10.5
19.4
32.t
67.7
t0.6
a).5
4.4
14.6
29.6
70.4
ar.4I.
:_
6.7
2t.o
75.0
t6.7
50.0
"j
11.6
15l
Urca..n
Dlort E
Trffi
hh 'A ol
Dlffd
Itaire
hmiltl
ral
n!6
.ddi.C
I
2,
1
t
6
7
I
9
10
1l
16.7
50.0oj
a
u.05
72.00
,t:rt
:
35.4)
t3.?t
o:,
i
A/tfu Method I Data
Ieibn Ulrh
Ihd Orlcotdi@: Vdi.d
Iroci lhritd Circals
DirtefrcnFrWrItoOdid.ofPon: t55.75 tn
Nipplclinsth: 11.75 in
Irrpttoflhd: 144.00 iD
crc$ SdirodAsof ltrd: lt3.l0 d
No.ofTdPoro 4
IrituA: 7.0 ft
Diilre A IhE llirmh: 0.6 (dM b. > 0.O
Di$ae B: 63.0 ft
lridre B lhd lri.dcn: 53 (6url br > 2)
Acul Nmbcr oil Tnvem Poim: 3
LOCATION OT TRAWf,SB FOINTS
Ntilba oJt@dse poi* N a difu
I
2
3
4
5
6
1
E
9
10
11
6345 1 E 9 lo It t2
- 4.4 - 3.2
- 14.6 - 10.5
- 29.6 - 19.4
- 70.4 - 32.3
- 85.4 - 67.7
- 95.6 - 80.6
_ 89.5
....'
14.6 t6.7 6.7
85.4 50.0 25.0
- a3.3 75.0
93.3
2.6
8.2
14.5
22.6
34.2
65.t
7t.4
85.4
91.8
t_,
6.7
u.8
t1.1
25.0
35.6
64.4
75.0
82.3
88.2
93.3
979
ThrtBa
Poiil
o/. ol
Ilirmtcr
IrirtMc.
llmisldr
Brll
lrcm
ouaid. of
I
3
4
5
6
7
8
9
l0
It
l2
t6.7
50.0
1'
u.o5
72.00
I 1995
t3.15
l3 t.70
Diaru
A= 7n.
S=63n.
DepthofD0ct= l,l4in.
CrcsS@ti@lAM
Upftam
Di4urbr@
Method I Data
ld6rUra
8rc
Dr.ad.-& Vcdrl
ED!dr[-.,19!sL
Dlrarc*IbE lrSI a Ma. laftd:J|jllE-f
lqrl.t"qft_!!Lr
D#{aDr.f laa.00 f
Crr.r gccllrJlHCDt.t_l.!l!g-ff
I{e.dlaallrl, a
Dlo..A: ,.0 i
lxrarr.AD!.rudfi 0,5 db>a.O
DhG.lD.tDd.m 53 Fah>A
A.rrdl{*olrm l!h$_j!_
.Pavst d:td. ld'r,.te bffiro&t.
Dhs!. 6r.0 i
80uRCE 1'EEtrNO
l'ffi
hL
*d
Dle
DfuIrHd
ilI
ilo
.dara
I,,
a
3
a
1
t,
la
1l
L6.:'
,0.0
Y
:
21.N
72t0
rr::et
:
:
,r.a
t3.A
I3LM
:
:
5.1
ll.t
t7-7
2:t!
,t.5
4.1
75,0
ta3
It:
3
4.2
tl.6
b.6
v2
66.t
n.1
&r.4
9l.t
":
6.7
25.0
,5.0
?
:
rr.,l ,0.0
- &1.3
Ur.crmd&rt E
pJ/l6rrEE)02 Summary
Location: - - -
Source: --
Project No.: --
Run
No.Date
Time
Rcfcrencc Method
O: Concentration
o/"dw
CEMS
0u Concentration
ohdw
Average
Differcncc
o/" ilrtStartEnd
I
2
3
4
5
6
7
8
9
l0
ll
t2
2fi3/24
2fi3t24
2/13t24
2t13t24
2fi3t24
2t13n4
atln4
2/13t24
2t13t24
2/13124
uttn4
at3D4
Averasr
Standard Deviation (Sd
Applicable Source Standard (AS
Confi dence Coeffi cient (CCl
Relative Accuracy (RAl
Performance Required - Mean Reference Method RA<2U/o
Performance Specifi cation Method PS3
Confidence Coefficient, CC
cc = lto'gt * sallVn I
whcre,
to.rrr-.....sA-
n0sd-
CC
= degrees offreedom value
= number of runs selected for calculating the RA
= standard deviation ofdifhrence
= confidence coefficient
Relative Accurecy, RA
ldl+lcclRA = 7r;ffix1oo
where,
d _= average difference of Refrrence Method and cEMS
CC _: confidence coefficient
RM _ : reference meth od, oh dry
RA = relative accurary, oZ
NOx SummaryIEE)Frcr
j,
AI
Locetion: -- - --
Source: --
Project No.: *
Run
No.Date
Time Reference Method
NOx Concentration
nnmvd
CEMS
NOx Concentration
nnmvd
Average
Difference
nnmvdStartEnd
I
1
j
4
5
6
7
8
9
l0
ll
t2
)t
2l
2/
2/
2t
,t
2t
2/
3/24
3/24
3/24
3/24
3D4
3124
3/24
3124
3/24
3124
3D4
3/24
Averagr
Standard Deviation (Sd
Applicable Source Standard (AS
Confidence Coeffi cient (CC
Bias Adiustment Required (BA No
Bias Adjustment Factor (BAI L000
Relative Accuracy (RA) - Hide Rou
Relative Accuracy (RA
Performance Required - Mean Reference Methor RA < 20%
ICAOMD RECI-AIM CRITERIA:
Does source Qualifr as low Emitter? RM average < 5 ppmv<No
Altemative Criteria for Low Emitter per R2012-Chapter 2, Eq. 9c: Is ldl+lccl < I ppmv #VALUE!
ldl+lcc #VALUE!
Performance Specifi cation Metho<PS2
#vAl-uEl
Confidence Coeflicient CC
cc = lto'zt, sallVn I
where,
to.orr1[= degrees of fieedom value
ng= number of runs selected for calculating the RA
Sd = standard deviation ofdifference
CC
-=
confidence coefficient
Relative Accuracy, RA
ldl+lcclRA = 7s;;;r:x1oo
where,
d = average difference of Reference Method and CEMS
CC
-=
confidence coefficient
RM-= reference method, ppmvd
RA = relative accuracy, o%
pJ/l6r1rce
-4.'il'.1 , :,l- {lF, l-'
CO Summary
Locetion: - - --
Source: -
Project No.: -
Run
No.Datc
Time Rcfcrcncc Mcthod
CO Concentration
nnmvd
CEMS
C0 Concentration
oomvd
Average
Difference
nnmvdStrrlEnd
I
2
3
4
5
6
7
8
9
l0
ll
t2
',I
)l'
)l
2/
)l
1t
2/
1t
3124
3/24
3D4
3t24
3t24
3124
3124
3124
3/24
3t24
3t24
3t24
Averagr
Standard Deviation (Sd
Applicable Source Standard (AS
Confi dence Coefficient (CCl
Bias Adiustnrent Required (BAl No
Bias Adiustment Factor (BAFI I 000
Rclativc Accuracv (RA) - Hide Row
Relative Accurtcy (RAl
Performance Required - Mean Reference Method RA< l0%
Performance Specifi cation Method PS 4A
Alternetive Relative Accuracy (RAl #VALUEI
Altemative Performance Required (d + CC <5ppm
Performance Specrfi cation Method PS 4A'
#VALUEI
Conlidence Coefficien1 CC
cc = lto'It , sallVn I
where,
t0.e75 #N/A = degrees offreedom value
n 0 = number ofruns selected for calculating the RA
sd-: standard deviation of difference
CC = confidence coefficient
Relative Accuracy, RA
ldl+lcclPn = ----. --:-----: x 100
where,
d = average difference of Reference Method and CEMS
cc
-=
confidence coefficient
RM-= reference method, ppmvd
RA = relative accuracy, oZ
pllt6rre
TECHNICAL GROIJP
Sourcc: -
Runl-RMData
Projet Nor -
Ot-OudGt COr-Oudct CO-Outlct
%drV %er ppwd
NOt.Odc{
ppffid
Urcoretid Ru! Avcnge (Cd)
C.l Gu Clmdntio (CMA)
Prctcrt Sy.t6 ro Rcaporl.
Porttort Syrtm Zao lerpre
Avcrrgc Zao Rapre (Co)
Prctst Syltm Cd Rspore
Pottst Syrtm Cd R6porr!
Avcrge Cr! Rarporle (CM)
TECHN
Alrfure Data
ICAL GROUP
Locrtton - - -sourccT-
ProteotNo.F
QA
Prremctcr Or-nflct COh- Ouflct CO-Outu N(lr - ()ufl.{
Mekc
Modcl
s/N
Oocntins Rensc
Cytindcr II)
bro
Low
Mid
IIieh
I
I\
NA
NA
NA
Y
NA
NA
Cylinder Ccr{fed Yelucs
7*ro
Low
Mid
Ifich
I\
l
NA
Y
NA
Y
NA
Y
Cyltndcr Expirafion Dete
7*to
LOW
Mid
TIfuh
I
l
l
\
NA
Y
NA
Y
NA
Y
fvoe of Semnle Linc
rIATEE!
. '_.:. I :r ..i:
AI Calibration Data
Locetion: -- - --
Source: --
Project No.: --
Datez 2ll3l24
Parameter O, - Outlet CO: - Outlet CO - Outlet NOx - Outlet
Exoected Averase Concentration
Span Between
Low
High
Desired Soan
Low Range Gas
Low
Hish
NA
NA
NA
NA
NA
NA
NA
NA
Mid Range Gas
Low
Hioh
High Range Gas
Low
Hish
NA
NA
NA
NA
NA
NA
NA
NA
Actual Concentration (7o or ppm)
7*ro
Low
Mid
Hieh
0.00
r1
0.00
il
0.00
Y
0.00
Y
Response Time (seconds)
Upscale Calibration Gas (Cur)
Instrument Response (7o or ppm)
7*ro
Low
Mid
Hish
NA NA NA NA
Performance (7o of Span or Cal. Gas Conc.)
Zero
Low
Mid
Hish
NA NA NA NA
7*ro
Low
Mid
Hieh
NA NA NA NA
BiaslDrift Determinations
Locetion: -- - --
Source: --
Project No,: -
Parameter Oz - Outlet COz - Outlet CO - Outlet NOx - Outlet
Run I Date 2ll3l24
Span Value
Initial Instrumenl Zero Cal Response
Initial Instrument Upscale Cal Response
Pretest System Zero Response
Posttest System Zero Response
Pretest System Upscale Response
Posttest Svstem Upscale Response
#N/A #N/A #N/A #N/A
Bias (%)
Pretest Zero
Posffest Zero
Pretest Span
Posttest Soan
Drift (7o)
Zero
Mid
Run 2 Date 2ll3l24
Span Value
Instrument Zero Cal Response
lnstrument Upscale Cal Response
Pretest System Zero Response
Posttest System Zero Response
Pretest System Upscale Response
Posttest System Upscale Response
#N/A #N/A #N/A #N/A
Bias (7d
Pretest Zero
Posttest Zero
Pretest Span
Posttest Soan
Drift(%)
Zero
Mid
Run 3 Date 2ll3l24
Span Value
Instrument Zero Cal Response
Instrument Upscale Cal Response
Pretest System Zero Response
Posttest System Zero Response
Pretest System Upscale Response
Posttest System Upscale Response
#N/A #N/A #N/A #N/A
Bias (7o)
Pretest Zero
Posttest Zero
Pretest Span
Posttest Snan
Drift (7o)
Zero
Mid
plll6rpe
:lAI i:[.:i 1-\i]P
Location: -- - --
Project No.: --
NO2 Converter Check - Outlet
Analyzer Make
Analyzer Model
Serial Number
Cylinder ID Number
Cylinder Exp. Date
Cvlinder Concentratiotr, DDrtr
Pre.Test Date Time
PreTestcoo""r,tli-tion,ppm
Pre.TestEfriciencv. To .T
Post-Test Date Time
Post-Test Coo"uoIilffif,.
Post-TestElficiency. To .T
is > 90 ?6'.{.
whcre,
plltfure
TECl-INICAL GROUP
Locrtlon: ---
Sourcc: -
Projcct No: -
Run No lDIGtrodR
Or - Ortlc,tconccntntlon (CoJ, % dry
Co,= (Co,-Co). ( #;)
Co5, - =avcrag€anallzer
c" : = a\r€ragc of pretestcr{,{.-FfF=actual: avcrage ofpretest
= O: ConcenEation,
during tcs! 7o dry
postt€st zero responses, 7o dry
of calibratiou gas, o/o &y
posttcst calibration responso*, o/o dry
dry
C^rT
coh:
pultfure
TECHNICAL GROUP
Locrtion: - - -
Source: -
Proicct No.: -
Run No. /MethodRun I / Method l0
CO - Outlct Concentretion (Cco), ppmvd
cco= (co5o-cs)x 1 ffil)
where'Couo average analyzer value during t€st, ppmvdq:= average of,pretest & postlest zcro responses, ppmvd
C1.1,r.TF[7f = actual concentation of calibrationgrg, ppmvd
CrT= average of protest & posttest calibration rcsponses, ppmvd
c-"o T: Co Concentation, ppmvd
I,TAH DEPAH'TMENT OF
ENVIRONMENTAL OUAUTY
li,lAn 2 0 2nt4
DIVISION OF AIR QUALIT1
Projcct No.:1
Run No. /ltlcthodRrm I /
NOr - Ouflct Conentnfon (Cno,)' ppmvd
cro.= (c05.-cs)x t"lF"rl
wtcrc,
q-= avorage of Prctcst
CM,{ --t[77[-- actual concehtati,
CM--= Oreragc of p'retest
C.r* T = Nox Concentrati<
&ningtest, ppmvd
posttsst zerc rcsponsos, ppmvd
of calibrarim gas, ppmvd
posttest calibrdion rtsponses, ppmvd
ppmvd