HomeMy WebLinkAboutDERR-2025-004763
SITE VISIT REPORT
DATE: 05/20/2025
SITE: Schovaers Electronics VCP
SITE ADDRESS: 22 South Jeremy Street, SLC, UT
PREPARED BY: Allison Stanley
Utah Department of Environmental Quality
Division of Environmental Response and Remediation
195 North 1950 West
Salt Lake City, UT 84116
ATTENDEES: Allison Stanley (DERR), Steve Maliszeski (Terracon)
ARRIVAL TIME: 1350 - DEPARTURE TIME: 1530
Split Samples Collected: NA
Is the work being performed in a manner consistent with the accepted workplan? Yes
SUMMARY:
DERR met with Terracon on-site to oversee the implementation of the Sampling and Analysis
Plan. Upon DERR's arrival, drillers were completing the installation of the final two groundwater
wells at the Site, and Terracon was logging the soil cores. Terracon reported no signs of staining
or odor, and PID readings were taken approximately every foot. Terracon was also finalizing the
installation of the last remaining vapor pin inside the building. Decontamination procedures were
observed.
PHOTO LOG:
Photo 1: Monitoring well installation.
Photo 2: Logging of soil cores.
Photo 3: Decontamination procedures observed.