HomeMy WebLinkAboutDWQ-2025-001293Appendix H Permit # UGW350010
Operations & Maintenance Manual East Waste Rock Extension Water Collection System
Operations & Maintenance Manual
Rio Tinto Kennecott Utah Copper
East Waste Rock Extension
Water Collection System
December 2016
III
Contents
Section Page
1.0 Context and Purpose ........................................................................................................... 1-1
1.1 Context ............................................................................................................................. 1-1
1.2 Purpose ............................................................................................................................ 1-1
1.3 Disclaimer ........................................................................................................................ 1-1
2.0 Design and Operation ......................................................................................................... 2-1
2.1 Overview of EWRE Water Collection System................................................................... 2-1
2.2 Typical Component Designs for the EWRE Water Collection System .............................. 2-2
2.2.1 Toe Drains ........................................................................................................... 2-2
2.2.2 Storm Water Detention Basins ........................................................................... 2-5
2.2.3 Cut-Off Walls ....................................................................................................... 2-5
2.2.4 Weir boxes .......................................................................................................... 2-7
2.2.5 Storm Water Weir/Flume and Lower Concrete Lined Canal ............................ 2-10
2.2.6 Branch Connection Vault and WCRW Main Line .............................................. 2-10
2.2.7 Settling Basin .................................................................................................... 2-11
2.3 Atypical Designs of the EWRE Water Collection System ............................................... 2-14
2.3.1 Copper 4 ............................................................................................................ 2-15
2.3.2 Copper 3 ............................................................................................................ 2-15
2.3.3 Copper 2 ............................................................................................................ 2-16
2.3.4 Copper 1 ............................................................................................................ 2-17
2.3.5 Lost Creek and Keystone ................................................................................... 2-17
2.3.6 North Keystone ................................................................................................. 2-19
2.3.7 South Crapo ...................................................................................................... 2-21
2.3.8 Crapo ................................................................................................................. 2-21
2.3.9 South Congor and Midas .................................................................................. 2-21
2.3.10 WRCW Branch Vault Diversion Box (Station 2134+00) .................................... 2-23
2.3.11 South Area Dumps (SAD) Box ........................................................................... 2-23
2.3.12 Storm Water Inlet Structure at Canal ............................................................... 2-24
2.3.13 Lower Concrete Lined Canal ............................................................................. 2-25
3.0 Inspection and Maintenance ............................................................................................... 3-1
3.1 Overview .......................................................................................................................... 3-1
3.2 Guidance for Inspection ................................................................................................... 3-1
3.2.1 Dump Face .......................................................................................................... 3-1
3.2.2 Down Drains ........................................................................................................ 3-1
3.2.3 Toe Drain ............................................................................................................. 3-2
3.2.4 Storm Water Detention Basin ............................................................................. 3-3
3.2.5 Cut-off Wall ......................................................................................................... 3-6
3.2.6 Weir Box .............................................................................................................. 3-7
3.2.7 Branch Connection Vault .................................................................................... 3-9
3.2.8 Storm Water Vault, Lower Concrete Lined Canal and Datalogger Station ......... 3-9
3.2.9 Old Bingham Tunnel ......................................................................................... 3-11
3.2.10 Settling Basin .................................................................................................... 3-12
3.2.11 Lower Concrete Lined Canal ............................................................................. 3-14
3.2.12 WRCW Branch Vault Diversion Box (WRCW Vault Station 2134+00) ............... 3-14
3.2.13 South Area Dumps (SAD) Box ........................................................................... 3-15
iii
CONTENTS (CONTINUED)
3.2.14 Storm Water Inlet Structure at Lower concrete lined Canal ............................ 3-15
3.3 Compliance Sampling Locations and Frequency ........................................................... 3-16
4.0 Training .............................................................................................................................. 4-1
4.1 General Requirements ..................................................................................................... 4-1
5.0 Reference Information ........................................................................................................ 5-1
5.1 UDWQ Construction Permit ............................................................................................. 5-1
5.2 Dam Safety Permit ........................................................................................................... 5-1
5.3 Groundwater Discharge Permit ....................................................................................... 5-1
5.4 Project Contacts ............................................................................................................... 5-1
5.5 Project Quality Assurance and Quality Control ............................................................... 5-2
5.6 Revision History ............................................................................................................... 5-2
Appendices
A EWRE Geology, Seeps, and Springs Map
B Drainage Basin Photographic Logs
C South Area Water Services East Side Collection System – East Waste Rock Extension
Groundwater Discharge Permit Inspection and Supplemental Inspection Forms
D Drainage Basin As-Built Drawings
E XML Terrain Files and AutoCAD Design Files
F Redline Design Drawings
G Survey Monument Documentation
H EWRE Compliance Monitoring Transition Documentation
I State Inspection Reports
J Quality Assurance and Quality Control Documentation
K Operations and Maintenance Manual Microsoft Word Document File
L CH2M HILL Hydrology Report
Tables
1-1 Applicable operating permits related to groundwater and surface water management
2-1 Storm water detention basin dimensions
2-2 East Waste Rock Extension water collection system conveyance description and size
2-3 Atypical designs of the EWRE water collection system
3-1 Inspection frequency and guidance
5-1 EWRE project contact information
Figures
1-1. Rio Tinto Kennecott Utah Copper facilities map.
1-2. Copper area structures overview.
1-3. Keystone area structures overview.
1-4. Crapo area structures overview.
2-1. EWRE water collection system schematic (typical).
2-2. EWRE water collection system flow diagram.
2-3. Type 1 and Type 2 toe drain details.
2-4. Type 3 toe drain detail.
iv
CONTENTS (CONTINUED)
2-5. Typical toe drain showing clean-outs, rip-rap ditch and the access road.
2-6. Typical toe drain under construction.
2-7. Typical cut-off wall.
2-8. (A) WRCW by-pass valve located in each cut-off wall; (B) manipulated with valve tool; (C) valve
tool attaches to valve stem for manipulation.
2-9. (A) Space frame with baffle and v-notch; (B) weir box with space frame and B.
2-10. Lost Creek-Keystone weir box and carrier pipe leak detection.
2-11. Photograph of a newly constructed weir box and auxiliary components.
2-12. Typical datalogger display showing real-time flow rate through the weir V-notch.
2-13. Photograph of a newly constructed WRCW branch connection vault.
2-14. The WRCW Mainline terminates in the settling basin; from the settling basin, WRCW is conveyed
to the Midas Pump Station.
2-15. Mine water drainage process and instrumentation diagram.
2-16. Storm water in the Copper 3 drainage connects to the lower concrete lined canal through a pre-
existing storm water flume.
2-17. Copper 2 and Copper 1 storm water branch canal.
2-18. Lost Creek drainage directional boring outlet.
2-19. Keystone drainage directional boring outlet.
2-20. Keystone detention basin straddling the Bingham Tunnel.
2-21. Photograph showing the 14-inch-diameter HPDE pipe conveying WRCW under the Mine Access
Road in the North Keystone drainage basin. The coarse quartzite finger drain directs WRCW flow
toward the North Keystone segment of toe drain.
2-22. The North Keystone storm water conveyance pipe will eventually be covered by waste rock and will require prope
2-23. Photograph showing the Crapo storm water branch line connection to a pre-existing branch canal.
2-24. Photograph showing tunnel discharge from the Old Bingham Tunnel (OBT). The tunnel discharge
from the OBT is conveyed to the combined South Congor and Midas weir box, but enters below
the V-notch flow measuring point.
2-25. WCRW branch vault (Station 2134+00) can divert water into the lower concrete lined canal
when maintenance is required at the Settling Basin.
2-26. South Area Dump (SAD) box.
2-27. Storm water inlet structure by Copper 3.
3-1. Photographic overview of EWRE water collection system components.
3-2. Photograph of a newly constructed segment of the toe drain; toe drain features include the
clean outs, rip rap ditch and access road.
3-3. Photograph of a newly constructed storm water detention basin; features include desilting area,
check dam, storm water detention basin, outlet box, spillway and silt fences.
3-4. Photograph of a newly constructed spillway. The spillway connects the storm water detention
pond to the cut-off wall.
3-5. Photograph of a newly constructed cut-off wall. The spillway connects the storm water
detention pond to the cut-off wall; the cut-off wall includes a storm water inlet grate and a valve
vault.
3-6. Photograph of a newly constructed cut-off wall. The valve port allows access to manipulate the
WRCW flow valves.
3-7. Photograph of a newly constructed weir box and auxiliary components.
3-8. Photograph of a newly constructed WRCW branch connection vault.
3-9. Photograph of a newly constructed storm water vault, level indicator and lower concrete lined
canal.
3-10. Photo of the Old Bingham Tunnel (OBT) entrance.
3-11. Settling Basin isometric projection and cross sectional view.
3-12. Section of the lower concrete lined canal.
v
CONTENTS (CONTINUED)
3-13. (A) WRCW branch vault diversion box (Station 2134+00); (B) diversion gate valve.
3-14. Compliance monitoring well and sampling location map.
3-15. Seeps, springs and geology map.
vi
SECTION 1
1.0 Context and Purpose
1.1 Context
Rio Tinto Kennecott Copper (RTKC) and its Bingham Canyon Mine are required to effectively manage
waste rock contact water (WRCW) and the discharge to groundwater, surface water, sediment and
debris associated with the waste rock dumps on property. These requirements are outlined in Section 5
under the applicable permits associate with the operation. The agencies and permits are listed in
Table 1.
Table 1-1. Applicable operating permits related to groundwater and surface water management
Agency Permit
Utah Department of Environmental Quality - Division
of Water Quality
Groundwater Discharge Permit No. UGW350010 Bingham Canyon
Mine and Water Collection System
Utah Department of Environmental Quality - Division
of Water Quality
UPDES Permit No. UT0000051 Storm Water Pollution
Prevention Plan
Utah Department of Natural Resources - Division of
Oil, Gas and Mining
Permit No. M/035/0002 Mining and Reclamation Plan
In order to best meet obligations to the public and regulatory agencies specifically related to the East
Waste Rock Extension (EWRE) (Figure 1-1), an integrated system of toe drains, detention basins, cut-off
walls and conveyance lines were constructed throughout 2015 and 2016 (Figures 1-2, 1-3, 1-4). The
effort was completed to accommodate continuation of mining and waste rock placement while carefully
managing the surface and groundwater capture and conveyance.
1.2 Purpose
This Operations and Maintenance (O&M) manual is designed to provide the operator with clear
instructions and reference material for the proper care and upkeep of the EWRE project groundwater
and surface water control infrastructure.
1.3 Disclaimer
This operation and maintenance manual was created to (1) fulfill the construction permit condition for
the EWRE project which requires an O&M manual in order to operate the system, and (2) provide
general guidance to the South Area Water Services (SAWS) operators and maintenance staff as part of
the handover of the newly constructed capture system. This manual is applicable only to the
infrastructure associated with the EWRE project.
1-1
SECTION 2
2.0 Design and Operation
2.1 Overview of EWRE Water Collection System
The EWRE water collection system affectively captures WRCW through a toe drain system on top of
low-permeable bedrock and directly at the toe of the relaxed waste rock slope. The WRCW is moved by
gravity through HDPE pipes and lined concrete structures. Secondary containment of all WRCW
conveyance is in place down gradient of the cut-off walls to minimize the potential for a release of
WRCW to the environment. The system is also designed to capture surface water (up to a 100 year-
24-hour event) off of the face of the waste rock dump.
Key features of the EWRE water collection system include the following:
• The system captures surface and alluvial water (groundwater) up gradient of the cut-off walls;
WRCW reporting to the toe of the waste rock is collected in
subsurface toe drains filled with coarse quartzite, keyed into
bedrock, and conveyed in a system of HDPE pipes (double
contained down gradient of the cut-off wall) separate from
surface water.
• The toe drain is the primary collection point for WRCW and the
cut-off wall acts as the secondary collection point in the event
the toe drain under performs.
• WRCW from the toe drains and all drainages from Copper 4 to
Midas is transported via gravity to the Midas Pump
Station (MPS), and then pumped to the existing ACC plant for
copper recovery.
• The cut-off wall locations permit gravity flow from the cut-off
wall collection piping via the down gradient collection
system piping.
• Secondary containment and leak detection exists for all WRCW piping and structures down gradient
of the cut-off walls.
• Storm water is collected in detention basins and released slowly to the storm water piping system so
as not to overwhelm the associated piping and concrete lined canal.
• WRCW and storm water flows are recorded on data loggers using weirs, flumes and level indicators.
• WRCW water samples can be collected at the weir boxes.
The collection system is described from top to bottom.
A conceptual
representation of
the EWRE water
collection system
design is shown
in Figure 2-1.
2-1
SECTION 2 DESIGN AND OPERATION
Figure 2-1. EWRE water collection system schematic (typical).
2.2 Typical Component Designs for the EWRE Water
Collection System
The photographic representation of the typical water capture system components for the EWRE are
shown on Figure 2-2. Specific details of the typical EWRE water collection system components are
presented below.
2.2.1 Toe Drains
The toe drains are designed to intercept waste rock contact water (WRCW) moving along the bedrock
contact as it reports directly from the toe of the waste rock. The toe drains are composed of two
parallel, 12-inch-diameter perforated corrugated HDPE pipes placed along the lower permeability layer
at the bedrock contact. There are three types of toe drains:
• Type 1 is a more robust design, clay down on the down gradient side of the toe drain is 8 feet thick,
and was used primarily at drainage bottoms in the collection system where flow reporting from the
waste rock is anticipated to be greatest and in cases where slope parallel with the toe drain is < 1%
(Figure 2-3).
• Type 2 was used throughout the majority of the collection system and where flow from waste rock
is anticipated to be less active and/or significantly diminished or slopes are ≥ 1%. Clay down gradient
of the toe drain is 2 feet thick (Figure 2-3).
2-2
SECTION 2 DESIGN AND OPERATION
• Type 3 was used on steep slopes greater than 45 degrees and incorporated no imported clay. Type 3
was used where constructability of Type 2 toe drains was not achievable (Figure 2-4).
Figure 2-3. Type 1 and Type 2 toe drain details.
Figure 2-4. Type 3 toe drain detail.
Note: This toe drain
detail is applicable to
ground slopes greater
than 1:1 (45°), such as
the south slope of the
Lost Creek drainage
and the south
slope of the
Keystone drainage.
2-3
SECTION 2 DESIGN AND OPERATION
Within each drainage basin, the perforated 8” toe drain piping connects to a solid wall 14-inch-diameter
HDPE conveyance pipeline. This piping extends down gradient from the toe drain through the cut-off
wall and reports to a collection weir box. Two oblique angled 14-inch-diameter capped HDPE pipe
cleanouts are located approximately every 500-feet of toe drain, in addition to the cleanouts at branch
connection. Photographs of the completed and ‘in construction’ toe drain are shown in Figures 2-5 and
2-6, respectively.
Figure 2-5. Typical toe drain showing clean-outs, rip-rap surface water ditch and the access road.
Figure 2-6. Typical toe drain under construction. Upstream of the toe drain are finger drains built with coarse non-acidic (non-reactive) rock (quartzite)
drainage (NARD) material. In most cases, the coarse quartizte fingers drains were keyed into bedrock;
however, in a few locations, the finger drains were placed in drainage lows once all soils were removed
to bedrock. The locations of the coarse quartzite finger drains are illustrated on the EWRE Geology,
Seeps and Springs Map (Appendix A).
Clean outs
Rip rap ditch
Access Road
Bedrock keyway
Perforated toe drain pipe
Coarse quartzite
Geotextile fabric Clay backfill
2-4
SECTION 2 DESIGN AND OPERATION
2.2.2 Storm Water Detention Basins
Storm water detention basins are located in all drainages associated with EWRE. The size of each
detention basin was determined based on the modeled peak storm water flow rates reporting from the
waste rock face. Basic design criteria used is based on a 100-year, 24-hour storm event and the planned,
reclaimed waste rock and site topography. At a minimum, the storage provided in each detention basin
will be sufficient to detain the estimated peak storm volume (Table 2-1).
The detention basins are designed to drain to a topographic low point, and are bounded at the inlet by a
pervious rock embankment approximately 6 feet tall designed to capture sediment and debris. A
primary outlet box is located at the basin’s topographic low point. The detention basin is designed to
drain in a 24-hour period. The primary outlet box is generally 4 feet tall, and includes a variably-sized
inlet orifice (Table 2-1), a fiberglass top grate, and a 24-inch-diameter HDPE outlet pipe. The primary
outlet box directs storm water into a 24-inch-diameter HDPE outlet pipe through the cut-off wall storm
water collection vault and ultimately the canal. In the event the outlet box fails or cannot keep up with a
given storm event, the detention basin embankment contains an emergency overflow (between 4 and 9
feet above the basin floor), which directs storm water via a pervious rip rap rock spillway to a second
grated inlet on the wet-side of the cut-off wall.
The detention basins are slightly oversized to accommodate sediment buildup, and include a staff gauge
near the topographic low to visually monitor sediment accumulation.
Table 2-1. Storm water detention basin dimensions
Basin
Basin
Volume
(acre-feet)
Average
Basin Depth
(feet)
Basin Floor
Elevation
(feet)
Outlet Box
Top Elevation
(feet)
Emergency
Overflow Weir
Elevation (feet)
Berm Top
Elevation
(feet)
Copper 4 6.3 6.7 5,635 5,642 5,644 5,645
Copper 3 1.9 3.3 5,635 5,639 5,640 5,641
Copper 2 2.8 5.7 5,610 5,617 5,618 5,620
Copper 1 2.3 4.3 5,603 5,607 5,608 5,610
Lost Creek 1.9 5.4 5,578 5,585 5,686 5,588
Keystone Upper 0.9 5.1 5,554 5,563 5,564 5,566
Keystone Lower 2.6 5.8 5,534 5,541 5,542 5,544
North Keystone 5.6 3.8 5,560 5,565 5,566 5,568
South Crapo 4.1 3.8 5,549 5,553 5,554 5,556
Crapo 1.9 4.4 5,525 5,532 5,533 5,535
South Congor 3.4 4.2 5,530 5,534 5,535 5,538
Midas 7.4 3.7 5,540 5,544 5,545 5,547
2.2.3 Cut-Off Walls
The cut-off walls are designed to serve as a secondary capture system for alluvial groundwater, with the
toe drains functioning as the primary capture system. Figure 2-7 shows a typical cut-off wall in
cross section.
2-5
SECTION 2 DESIGN AND OPERATION
Figure 2-7. Typical cut-off wall.
Cut-off walls are located in each of the major drainages (Figures 1-2, 1-3, 1-4), and are keyed into
bedrock for structural support and to enhance capture effectiveness. Additionally, the upgradient wet-
side of the cut-off walls are protected from WRCW by a HDPE liner.
Three pipes pass through each cut-off wall:
1. A French drain with a perforated 8-inch-diameter HDPE pipe runs parallel to the base of each cut-off
wall, along the surface of the bedrock. This French drain captures WRCW originating between the
toe drain and the cut-off wall or WRCW in the event the toe drain under performs. The 8-inch-
diameter HDPE pipe, passes through the valve vault at the cut-off wall, becomes double contained
inside a 12-inch-diameter HDPE pipe at the cut-off wall and gravity drains to the weir box.
2. The 14-inch-diameter HDPE pipe from the toe drain, passes through the valve vault at the cut-off
wall, becomes double contained inside a 24-inch-diameter HDPE pipe at the cut-off wall and gravity
drains to the weir box.
3. The 24-inch-diameter HDPE pipe from the storm water detention basin outlet structure enters the
cut-off wall storm water vault, passes through the storm water vault to exit via another 24-inch-
diameter HDPE pipe, and gravity drains to the lower concrete lined canal. The water can be diverted
to the storm water line in the event the 14-inch-diameter WRCW line requires repair (Figure 2-8).
Storm water arriving at the cut-off wall via the spillway overflows into the storm water vault, and is then
carried through the cut-off wall and downgradient to the lower concrete lined canal via a 24-inch
diameter HDPE pipe. Before storm water enters the canal, it passes through either a weir box or flume
where flow is measured.
2-6
SECTION 2 DESIGN AND OPERATION
Figure 2-8. (A) WRCW by-pass valve located in each cut-off wall; (B) manipulated with valve tool; (C) valve tool
attaches to valve stem for manipulation.
2.2.4 Weir Boxes
Waste rock contact water from the toe drain and the cut-off wall are comingled in weir boxes. A weir
box is an HDPE lined concrete structure that includes a baffle for stilling the water, a V-notch weir
(Figure 2-9) and level indicator for flow measurement, leak detection, and a data logger.
On the upgradient side of the weir box, WRCW reports from the 14-inch-diameter HDPE pipe from the
toe drain (double contained within a 20-inch-diameter HDPE pipe) and the 8-inch-diameter HDPE pipe
from the base of the cut-off wall (double contained within a 12-inch-diameter HDPE pipe). On the
downgradient side of the weir box, a 14-inch-diameter HDPE pipe (double contained in a
20-inch-diameter HDPE pipe) of combine WRCW gravity drains to the WRCW main line.
(A)
(B) (C)
2-7
SECTION 2 DESIGN AND OPERATION
Leak detection is located outside of the weir box in three (visible) vertical 18-inch-diameter HDPE pipes
(Figures 2-10 and 2-11). The three 18-inch-diameter leak detection inspection pipes are connected to
the secondary WRCW pipes and concrete weir box via 3-inch HDPE pipes. Signage in the field indicates
which leak detection 18-inch-diameter HDPE pipe correlates to which respective pathway.
The real-time flow datalogger collects flow data at the V-notch weir or flume. The datalogger and digital
station are powered by a solar panel (Figure 2-11). Data acquisition is acquired manually at the data
logger (Figure 2-12).
Figure 2-9. (A) Space frame with baffle and V-notch; (B) weir Box with space frame.
Figure 2-10. Lost Creek-Keystone weir box and carrier pipe leak detection.
Baffle
V-notch
weir Baffle
V-notch weir
Inlet
Outlet
Weir Box
Leak detection
Toe drain WRCW Cut-off wall WRCW
(A) (B)
Leak detection
piping
2-8
SECTION 2 DESIGN AND OPERATION
Figure 2-11. Photograph of a newly constructed weir box and auxiliary components.
Weir box
Leak detection
Solar panel
Datalogger
Battery
Level indicator
Bolt penetrations through the weir liner are problematic to seal. A space
frame (Figure 2-9A) was used to eliminate the need to penetrate the liner in
order to mount the baffle and v-notch plates.
If water is found in the leak detection sumps, test water quality to
determine if it matches WRCW characteristics and to rule out
malfunctioning leak detection piping as displayed in Figures 2-10 and 2-11.
2-9
SECTION 2 DESIGN AND OPERATION
Figure 2-12. Typical datalogger display showing real-time flow rate through the weir V-notch.
2.2.5 Storm Water Weir/Flume and Lower Concrete Lined Canal
Water reporting from storm water detention basin outlet boxes is conveyed via 24-inch-diameter HDPE
pipe through the cut-off walls to the lower concrete lined canal, which ultimately conveys flow to Zone 2
of the Large Reservoir. Storm water weirs and flumes with level indicators are present where the
24-inch-diameter HDPE pipe connects to the lower concrete lined canal. In some instances, the new
system used historic existing branch canals. The lower concrete lined canal originates in the Copper 3
drainage (Figure 1-2). The EWRE system ties into the south dumps at the South Area Drainage (SAD) box.
Storm water exits the SAD box via a 36-inch-diameter HDPE storm water overflow line. The line
increases in diameter to a 42-inch line at the Copper 4 drainage. The Copper 4 drainage does not have a
means of flow measurement and is connected via hard pipe at the Copper 4 deep branch connection.
Water from south dumps and the Copper 4 drainage enter the lower concrete lined canal at an outlet
box at the head of the canal. The canal is sized to manage storm water from all EWRE basin
simultaneously during a 24-hour 100-year event.
2.2.6 Branch Connection Vault and WCRW Main Line
The WRCW branch connection vaults are situated parallel to the storm water main line and lower
concrete lined canal, and receive WRCW from the dual contained 14-inch-diameter HDPE branch line(s)
(Figure 2-13). The branch lines tie into the 16-inch-diameter
HDPE WRCW main line pipe (double contained within a
24-inch-diameter HDPE pipe). This 16-inch-diameter HDPE
pipe diameter increases in diameter to 24-inch at the Crapo
branch connection vault.
A typical branch connection vault is accessible via a metal
hatch (Figure 2-13). Dual containment of the WRCW main line
Real-time flow rate
Opening the hatch and exposing
the opening in the lid of the box
will require fall protection.
Entering the vault will require
conformance with confined space
entry protocol.
2-10
SECTION 2 DESIGN AND OPERATION
and the weir box branch connection drain directly into the branch connection vault; thus, water flowing
into the branch connection vault is indicative of a leak in the respective conveyance piping.
Many branch connection vaults contain automated leak detection sensor that are connected to strobe
lights on the associated weir box datalogger station for the respective drainage basin. In the case of
branch connection vaults that are located in close proximity to one another, such as Crapo and South
Crapo, only one leak detection strobe is used per datalogger. A leak from a secondary pipe will enter the
vault triggering the strobe once water comes in contact with the sensor. Water will continue down the
secondary pipe associated with the outlet triggering each downstream probe as the water accumulates.
The main line pipe conveys WRCW from the EWRE water collection system, as well as flows from the
existing system south of Copper 4, to the Midas Pump Station (MPS). The WRCW main line pipe is
buried, and is located parallel to and adjacent to the existing lower concrete lined canal (Figures 1-2, 1-
3, and 1-4).
Figure 2-13. Photograph of a newly constructed WRCW branch connection vault.
2.2.7 Settling Basin
The WRCW Mainline terminates in the settling basin (Figure 2-14). The settling basin also receives inflow
directly from the comingled flows of South Congor, Midas and the Old Bingham Tunnel (OBT). From the
settling basin, the WRCW is conveyed to the MPS. In the event the MPS cannot receive additional
Branch connection vault Air backflow
Access hatch for
leak detection
Lower concrete lined canal
2-11
SECTION 2 DESIGN AND OPERATION
WRCW, WRCW in the settling basin can be diverted directly to the lower concrete lined canal. The
settling basin also has a fail-safe overflow pipe that directs water to the lower concrete lined canal in the
event the outlets of the settling basin are plugged or malfunctioning, thus preventing WRCW spills
to ground. The settling basin is also equipped with leak detection for the HDPE liner, as well as the
WRCW piping reporting to the settling basin.
Sediment accumulation in the settling basin is estimated to be considerable in the first one to two years
of operation as the WRCW collection system (e.g., finger drains, toe drain, piping,) rinses free of fine
sediment. Further guidance is provided in Section 3.2.10.
Figure 2-14. The WRCW Mainline terminates in the settling basin; from the settling basin, WRCW is conveyed to the
Midas Pump Station.
Piping for specific components of the EWRE water collection system are detailed in Table 2-2. The table
describes the function of each pipe, as well as the pipe diameter and dual lining diameter (if applicable).
Figure 2-15 is a design drawing detailing the typical and atypical components of the EWRE water
collection system.
2-12
SECTION 2 DESIGN AND OPERATION
Table 2-2. East Waste Rock Extension water collection system conveyance description and size
EWRE Water Collection Piping Description of Piping Pipe Diameter (inches) DR Rating Dual Lining Diameter (inches) DR Rating
Toe Drain Pipe Two parallel perforated HDPE
pipes; union at tow drain
branch connection
12 17 None None
Toe Drain Clean Out Pipes Two oblique capped HDPE pipes; each attached to single toe drain pipe
12 17 None None
Toe Drain Branch
Connection Pipe
Solid wall HDPE pipe;
transitions at cut-off wall
14 26 None None
Storm Water Outlet Box Inlet Orifice Upgradient penetrating port through concrete See Table 2-1 N/A None None
Storm Water Outlet
Box Outlet Pipe
Downgradient penetrating pipe
through concrete; terminates at
storm water vault and lower
concrete lined canal
24 26 None None
Cut-off Wall French Drain Pipe Perforated HDPE pipe; transitions at cut-off wall 8 26 None None
Toe Drain WRCW
from Cut-off Wall
to Weir Box
Solid wall HDPE pipe;
terminates at weir box
14 26 20 32.5
Cut-off Wall WRCW
to Weir Box
Solid wall HDPE pipe;
terminates at weir box
8 26 12 32.5
Weir Box Outlet
Pipe
Solid wall HDPE pipe;
terminates at branch
connection vault
14 26 20 32.5
Branch Connection
Vault Inlet from
Weir Box
Solid wall HDPE pipe 14 26 20 32.5
Branch Connection
Vault Outlet
(WRCW main line
upgradient of
Crapo)
Solid wall HDPE pipe;
terminates at settling basin
16 26 24 32.5
Branch Connection
Vault Outlet
(WRCW main line
downgradient of
Crapo)
Solid wall HDPE pipe;
terminates at settling basin
24 26 36 32.5
Storm water main line from SAD box to Copper 4
Solid wall HDPE pipe 36 17 None None
Storm water
mainline from
Copper 4 to lower
concrete lined
canal
Solid wall HDPE pipe 42 26 None None
2-13
SECTION 2 DESIGN AND OPERATION
2.3 Atypical Designs of the EWRE Water Collection System
While the majority of the components present in each drainage are constructed identically, there are a
few distinct differences within the drainages. These atypical design components are summarized in
Table 2-3, and described in subsequent sections below.
Table 2-3. Atypical designs of the EWRE water collection system
Drainage Unique Feature
Copper 4
(Section 2.3.1)
Storm water branch line ties into storm water mainline at storm water branch connection; no weir is
present.
Copper 3
(Section 2.3.2)
Storm water branch line ties into canal at head of canal through pre-existing flume.
Copper 2
(Section 2.3.3)
1. Two toe drain branch lines report to the cut-off wall.
2. Storm water branch line ties into pre-existing branch canal and comingles with Copper 1 storm
water flow; flow measured at pre-existing flume.
3. Branch vault leak detection light located on the Copper 1 datalogger station
Copper 1
(Section 2.3.4)
Storm water branch line ties into pre-existing branch canal and comingles with Copper 2 storm water flow; flow measured at pre-existing flume.
Lost Creek
(Section 2.3.5)
1. WRCW branch lines comingle at Lost Creek/Keystone weir for one combined flow.
2. Storm water passes under Mine Access Road via HDPE pipe to storm water detention basin.
3. Commingled Lost Creek-Keystone storm water enters at pre-existing flume
Keystone
(Section 2.3.5)
1. WRCW branch lines comingle at Lost Creek/Keystone weir for one combined flow.
2. Storm water passes under Mine Access Road via HDPE pipe to storm water detention basin.
3. Commingled Lost Creek-Keystone storm water enters at pre-existing flume
4. There are two detention basins in the drainage straddling the Bingham Tunnel
North Keystone
(Section 2.3.6)
1. Finger drain of NARD material located west of Mine Access Road collects WRCW; this finger drain
leads to HDPE pipe that passes under the Mine Access Road. The HDPE pipe under Mine Access Road
opens into another NARD drain east of the Mine Access Road; this NARD drain leads to the toe drain.
2. Surface water from the Mine access road is captured in a rip rap basin and routed under the road,
past the toe drain and reports to the detention basin. Care to properly abandon this pipe will be
required before the waste rock is placed in this location to prevent the transport of WRCW across the
toe drain.
South Crapo
(Section 2.3.7)
None
Crapo
(Section 2.3.8)
1. Storm water branch line ties into pre-existing branch canal; flow measured through
pre-existing flume.
2. Storm water routed under the toe drain road via culvert.
3. The WRCW main line increases in pipe diameter from 16-inch-diameter to 24-inch-diameter
4. At branch connection diversion located downgradient of the Crapo branch connection vault permits WRCW to be segregated from the WCRW main line into the lower concrete lined canal.
2-14
SECTION 2 DESIGN AND OPERATION
South Congor
(Section 2.3.9)
1. WRCW branch lines comingle at South Congor/Midas weir for one combined flow, which also
includes flow from Old Bingham Tunnel. The flow from the Old Bingham Tunnel enters the weir below the V-Notch. No leak detection for flow from the Old Bingham Tunnel.
2. Combine WRCW flow goes direct to Settling Basin and not WRCW Mainline.
3. Storm water combined for South Congor and Midas; flows combine at weir.
Midas
(Section 2.3.9)
1. WRCW branch lines comingle at the South Congor/Midas weir for one combined flow.
2. WRCW flow out of the weir box includes flow from the Old Bingham Tunnel (OBT). The OBT flow is
not accounted for in the combined South Congor/Midas flow as OBT flow enters the weir box below
the V-Notch. There is no leak detection for the OBT conveyance pipe.
3. Combine WRCW flow goes direct to Settling Basin and not WRCW Mainline.
4. Storm water combined for South Congor and Midas; flows combine at weir.
Structure Unique Feature
WRCW Branch Vault
(Station 2134+00)
(Section 2.3.10)
1. Valve to divert WRCW to lower concrete lined canal.
South Area Dumps
(SAD) Box
(Section 2.3.11)
1. 16-inch-diameter pipe with 6-inch-diameter orifice accepts base flow (approximately 100 gallons
per minute) water from the South Area Dumps.
2. Portal to access 32-inch-diameter HDPE WRCW pipe and insert “pig.”
Storm Water Inlet
Structure at Canal
(Section 2.3.12)
1. Energy dissipation structure that directs water from the 42-inch-diameter storm water pipe into
the canal in the Copper 3 drainage.
Lower concrete
lined canal
(Section 2.3.13)
1. Curbing to extend top of canal near Copper 1 and Copper 2, where a flat grade of less than 1%.
2.3.1 Copper 4
Appendix B provides a photo log documenting the construction process of the Copper 4 drainage.
The one unique feature of the Copper 4 drainage basin is the following:
1. There is no storm water weir in the Copper 4 drainage; rather, the 24-inch-diameter HDPE storm
water branch line ties directly into the 42-inch-diameter storm water mainline via a branch
connection.
2.3.2 Copper 3
Appendix B provides a photo log documenting the construction process of the Copper 3 drainage.
The one unique feature of the Copper 3 drainage basin is the following:
1. Storm water in the Copper 3 drainage connects to the lower concrete lined canal through a pre-
existing storm water flume, shown in Figure 2-16.
2-15
SECTION 2 DESIGN AND OPERATION
Figure 2-16. Storm water in the Copper 3 drainage connects to the lower concrete lined canal through a pre-existing
storm water flume.
2.3.3 Copper 2
Appendix B provides a photo log documenting the construction process of the Copper 2 drainage.
The two unique features of the Copper 2 drainage basin are the following:
1. The Copper 2 cut-off wall is unique in that two branch lines from the toe drain report to the cut-off
wall. This is due to two low-elevation sections in the toe drain above the Copper 2 drainage basin.
The two toe drain branch lines comingle below the wall in a single branch connection to the
Copper 2 weir box.
2. The Copper 2 storm water branch line and the Copper 1 storm water branch line connect in a storm
water vault upgradient of a pre-existing branch canal (Figure 2-17) to the lower concrete lined canal.
The comingled flow of Copper 2 and Copper 1 storm water flow is measured with a data logger
installed in a pre-existing flume.
2-16
SECTION 2 DESIGN AND OPERATION
Figure 2-17. Copper 2 and Copper 1 storm water branch canal.
2.3.4 Copper 1
Appendix B provides a photo log documenting the construction process of the Copper 1 drainage.
The one unique feature of the Copper 1 drainage basin is the following:
1. The Copper 1 storm water branch line and the Copper 2 storm water branch line connect in a storm
water vault upgradient of a pre-existing branch canal (Figure 2-17) to the lower concrete lined canal.
The comingled flow of Copper 1 and Copper 2 storm water flow is measured with a datalogger
installed in a pre-existing flume.
2.3.5 Lost Creek and Keystone
Appendix B provides photo logs documenting the construction process of the Lost Creek and Keystone
drainages.
The Lost Creek and Keystone drainages basins are steeply incised drainages separated by a relatively
narrow ridge. As such, the drainage basins are near to each other, and share three atypical design
features. The three unique features of the Lost Creek and Keystone drainage basins are the following:
1. The WRCW branch lines from each respective cut-off wall comingle at a shared Lost Creek and
Keystone weir box. As such, there are four dual-contained input pipes in the stilling portion of the
weir box, five leak detection pipe surrounding the shared weir box, and the datalogger measures
combined Lost Creek and Keystone WRCW flow through the V-notch.
2. Storm water and WRCW from upgradient portions of each respective drainage basin is conveyed
under the Mine Access Road through a 24-inch-diameter HDPE pipe, and a 14-inch-diameter HDPE
pipe, respectively. The 24-inch-diameter HDPE pipes drain into energy dissipation channels
immediately upgradient of each respective storm water detention basin (Figures 2-18 and 2-19), and
Copper 1 storm water inflow
Copper 2
storm water inflow
Branch Canal
2-17
SECTION 2 DESIGN AND OPERATION
the WRCW 14-inch-diameter HDPE pipe continues to the cut-off wall. The conveyance pipes under
the MAR were installed through directional drilling boreholes.
3. The combined flow of the Lost Creek and Keystone storm water branch lines is measured with a
datalogger installed in the pre-existing Lower Keystone flume that drains to the lower concrete lined
canal.
Figure 2-18. Lost Creek drainage directional boring outlet.
Storm water outlet
WRCW clean out
Mine Access Road
Storm water outlet
WRCW clean out
2-18
SECTION 2 DESIGN AND OPERATION
Figure 2-19. Keystone drainage directional boring outlet.
4. Two detention basins were constructed in the Keystone drainage in an effort to avoid construction
and impounding water atop the Bingham Tunnel (Figure 2-20). As a result, additional concrete inlet
and outlet structures are incorporated into the surface water conveyance structures which are not
typical of other EWRE detention basins.
Figure 2-20. Keystone detention basins straddling the Bingham Tunnel.
2.3.6 North Keystone
Appendix B provides a photo log documenting the construction process of the North Keystone drainage.
The one unique feature of the North Keystone drainage basin is the following:
1. West of the Mine Access Road, in the upgradient portion of the North Keystone drainage basin, a
coarse quartzite finger drain was installed to collect WRCW. This finger drain leads to a
14-inch-diameter HDPE pipe, which conveys the WRCW under the Mine Access Road. The
14-inch-diameter HDPE pipe opens into another coarse quartzite finger drain east of the Mine
Access Road (Figure 2-21), which directs WRCW flow toward the North Keystone segment of toe
drain.
2. The surface water drain moves water off the Mine Access Road, past the toe drain and into the
North Keystone detention basin. The surface water conveyance pipe (Figure 2-22) will be covered by
waste rock as part of the EWRE dump footprint, at which time the pipe will act as WRCW
conveyance.
Storm water inlet
Bingham Tunnel
Storm water inlet
Storm water outlet
Storm water outlet
2-19
SECTION 2 DESIGN AND OPERATION
Figure 2-21. Photograph showing the 14-inch-diameter HPDE pipe conveying WRCW under the Mine Access Road in
the North Keystone drainage basin. The coarse quartzite finger drain directs WRCW flow toward the North Keystone
segment of toe drain.
Figure 2-22. The North Keystone storm water conveyance pipe will eventually be covered by waste rock and will
require proper abandonment to ensure effective WRCW capture.
IMPORTANT
The North Keystone storm water
conveyance pipe must be properly
abandoned in order to ensure WRCW
is not conveyed across the toe drain
and water collection system.
Toe drain
Coarse quartzite
finger drain North Keystone
WRCW
conveyance pipe
North Keystone storm
water conveyance line
2-20
SECTION 2 DESIGN AND OPERATION
2.3.7 South Crapo
Appendix B provides a photo log documenting the construction process of the South Crapo drainage.
No atypical water collection system design features are present in the South Crapo drainage basin.
2.3.8 Crapo
Appendix B provides a photo log documenting the construction process of the Crapo drainage.
There are four atypical features of the EWRE water collection system in the Crapo drainage basin. The
four unique aspects are the following:
1. Storm water generated in upgradient areas of the Crapo drainage basin is routed under the toe
drain road via culvert toward the Crapo storm water detention basin.
2. The Crapo storm water branch line ties into a pre-existing branch canal (Figure 2-23), where flow is
measured with a datalogger installed in a pre-existing flume.
3. At the Crapo WRCW branch connection vault, the WCRW main line increases in pipe diameter from
16-inch-diameter to 24-inch-diameter. The WCRW main line remains 24-inch-diameter HDPE pipe to
the settling basin.
4. At branch connection diversion located downgradient of the Crapo branch connection vault
(Station 2134+00) permits WRCW to be segregated from the WCRW main line into the lower
concrete lined canal (see Section 2.3.10). This feature will be used when repairs are necessary to the
settling basin.
Figure 2-23. Photograph showing the Crapo storm water branch line connection to a pre-existing branch canal.
2.3.9 South Congor and Midas
Appendix B provides photo logs documenting the construction process of the South Congor and Midas
drainages.
Branch canal
Storm water branch line
l
Concrete slab
2-21
SECTION 2 DESIGN AND OPERATION
The South Congor and Midas drainages basins are steeply incised drainages separated by a relatively
narrow ridge. As such, the drainage basins are near to each other, and share four atypical design
features. The four unique features of the South Congor and Midas drainage basins are the following:
1. The WRCW branch lines from each respective cut-off wall comingle at a shared South Congor and
Midas weir box. As such, there are four dual-contained input pipes in the stilling portion of the weir
box, five leak detection pipe surrounding the shared weir box, and the datalogger measures
combined South Congor and Midas WRCW flow through the V-notch.
2. The WRCW flow out of the weir box includes tunnel discharge from the Old Bingham Tunnel (OBT)
(Figure 2-24). The OBT flow is not accounted for in the combined South Congor and Midas flow, as
the OBT flow enters the weir box below the V-Notch. Additionally, no leak detection for the OBT
conveyance pipe was installed.
3. The combine South Congor, Midas, and OBT WRCW is conveyed directly to the settling basin, by-
passing the WRCW Mainline.
4. Storm water generated in the South Congor and Midas drainage basins is combined in a storm water
weir; the combined South Congor and Midas storm water flow is discharged to the lower concrete
lined canal.
Figure 2-24. Photograph showing tunnel discharge from the Old Bingham Tunnel (OBT). The tunnel discharge from
the OBT is conveyed to the combined South Congor and Midas weir box, but enters below the V-notch
flow measuring point.
Tunnel discharge
Old Bingham Tunnel Entrance
2-22
SECTION 2 DESIGN AND OPERATION
2.3.10 WRCW Branch Vault Diversion Box (Station 2134+00)
This WRCW branch vault behaves similarly to all other WRCW vaults but in addition contains a gate
valve that, once closed, will divert water into the lower concrete lined canal. The necessity of this
feature became apparent during EWRE construction when repairs, modifications or maintenance was
required at the Settling Basin. Access to the valve is inside the vault and requires a confined space entry.
Figure 2-25. WCRW branch vault (Station 2134+00) can divert water into the lower concrete lined canal when
maintenance is required at the Settling Basin.
2.3.11 South Area Dumps (SAD) Box
The South Area Dump (SAD) box accepts water from the south dump drainages (Yosemite to Queen) via
a 36-inch-diameter HDPE pipe (Figure 2-26). Base flow from the south dumps is typically less than 100
gallons per minute (gpm) and is accepted through the WRCW outlet line. The WRCW outlet is a 16-inch-
diameter dual lined HDPE pipe with an 8-inch-diameter orifice. Should a storm event exceed the 100
gpm flow threshold into the SAD box, the comingled flow will rout through a 36-inch-diameter overflow
pipe. The SAD box has an HDPE liner but does not have leak detection due to the chemical nature of the
contact water. Contact water from the south dump drainages is of better water quality compared to
contact water north of Copper 4 drainage.
Additionally, a port was installed upgradient of the connection box for pigging the line and temporarily
stopping the flow for repairs or cleaning (Figure 2-26).
WRCW diversion to lower concrete lined canal
Station 2134+00
Diversion valve
2-23
SECTION 2 DESIGN AND OPERATION
Figure 2-26. South Area Dump (SAD) box.
2.3.12 Storm Water Inlet Structure at Canal
The storm water inlet box (Figure 2-27) receives water from the south area dumps (Yosemite to Queen
Drainages) via a 36-inch-diameter HDPE pipe and dissipates the energy of the water as it is introduced to
the canal. The HDPE pipe is 36-inch-diameter from the SAD box to the Copper 4 branch line, at which
time the HDPE pipe becomes 42-inch-diameter. A gate valve at the outlet structure allows for the
drainage of standing water behind the structures energy dissipation baffle.
Figure 2-27. Storm water inlet structure by Copper 3.
SAD Box
“Pig” port
Standing water outlet
Energy dissipation baffle
2-24
SECTION 2 DESIGN AND OPERATION
2.3.13 Lower Concrete Lined Canal
The lower concrete lined canal was originally constructed in the 1990’s and is permitted under
groundwater discharge permit #UGW350010 to convey both storm water and process water under
upset conditions. The lower concrete lined canal, while still functional, was refurbished as part of the
EWRE project and modified in sections to accommodate the capacity needed under the modeled 100-
year 24-hour storm event. Surface water reports to the lower concrete lined canal from the detention
basins via HDPE pipe and/or sections of pre-existing branch canal. Water flow can be measured through
pre-existing flumes or newly constructed weirs. Flow is recorded at the same data loggers that capture
WRCW flow in the weir boxes.
2-25
SECTION 3
3.0 Inspection and Maintenance
3.1 Overview
Inspection frequency is guided by groundwater discharge permit # UGW350010. The groundwater
discharge permit specifically requires quarterly inspection; however, best practice recommends
inspection following large rain events. Table 3-1 provides inspection guidance and frequency.
Table 3-1. Inspection frequency and guidance
Inspection Type Frequency Guidance
UDWQ Groundwater Discharge Permit
#UGW350010 1 Quarterly Groundwater Discharge Permit # UGW350010
Significant precipitation event 2 As Needed Rainfall period ≥10 year-24 hour as indicated
by the Copper drainage rain gage
Other As Needed
Examples for inspection may include a Health
and Safety incident, Dump/Slope movement,
or at the request of regulatory agency
Notes: 1 Required by the groundwater discharge permit
2 Not required by the groundwater discharge permit. Refer UPDES Permit (0000051) Statement of Basis (p. 21)
and Part I.E as well as 40 CFR 440.131(c) for guidance.
3.2 Guidance for Inspection
Inspection checklists for evaluating the primary and auxiliary components of the EWRE water
collection system are provided in Appendix C. Final as-built drawings of each drainage basin the
respective water collection system components are provided in Appendix D. The following sections are
descriptions of what to assess and evaluate during the inspection process, conditions that may result in
a need for maintenance, and potential mitigation and repair recommendations.
3.2.1 Dump Face
A visual inspection of the dump face (Figure 3-1) is required for each respective drainage basin.
Examples of potential issues with the dump face may include the following:
• Erosional gullies and/or debris flows developing
• Seeps or wet spots observed
• Settling, bulging or slumping observed
• Horizontal or vertical cracks developing
3.2.2 Down Drains
Visual inspection of the down drains is required for each respective drainage basin. Examples of
potential issues with the down drains may include the
following:
• Erosion and channel development along the sides of
the down drain
If evidence of any of these items is observed on the
dump face, document the findings in the inspection
checklist, photograph, and notify RTKC Mine
operations for support and resolution.
If evidence of any of these items is observed
on the down drains, document the findings in
the inspection checklist, photograph, and
notify RTKC Mine operations for servicing.
3-1
SECTION 3 INSPECTION AND MAINTENANCE
• Disturbed rip-rap channels altering drainage
Figure 3-1. Photographic overview of EWRE water collection system components.
3.2.3 Toe Drain
3.2.3.1 Access Road
Inspection of the toe drain access road (Figure 3-2) is required for each respective drainage basin.
Examples of potential issues with the access road may include the following:
• Rutting related to weather and driving in wet conditions
• Channeling related to running water and erosion
• Maintenance of the surface water rip rap ditch adjacent to the
access road
3.2.3.2 Toe Drain Clean Outs
Inspection of the toe drain clean outs (Figure 3-2) is required for each respective drainage basin.
Examples of potential issues with the clean outs may include the
following:
• Access to the clean out port has changed due to rock, debris or
erosion
Dump face
Check dam
Stormwater detention basin
Outlet box
Toe drain
Spillway
Cut-off wall
Weir box
Mitigation may include
redirecting surface water
through engineered structures
and/or regrading the access
road.
Mitigation may include repair,
removal of rock/debris,
construction of a protective berm,
and/or regrading the area around
the clean out.
Silt fence
3-2
SECTION 3 INSPECTION AND MAINTENANCE
• The clean out cover or pipe is damaged (e.g., struck by debris or equipment)
3.2.3.3 Rip Rap Ditch and Energy Dissipation
Inspection of the rip rap ditch (Figure 3-2) and energy dissipation system (not installed as of
October 31, 2016) are required for each respective drainage basin. Examples of potential issues with
these components may include the following:
• Erosion along the sides of the rip rap channel
• Rip rap channel full of sediment and debris
• Rock in the rip rap channel has moved or is missing
• A significant volume of water is ponded in the rip rap channel
Figure 3-2. Photograph of a newly constructed segment of the toe drain; toe drain features include the clean outs, rip
rap ditch and access road.
3.2.4 Storm Water Detention Basin
3.2.4.1 Check Dam Integrity
Inspection of the check dam (Figure 3-3) is required for each respective drainage basin. Examples of
potential issues with the check dam may include the following:
• Erosion in upgradient portions of the drainage basin
have caused excessive silting
• Check dam embankment material has moved or is
missing
• The silt fence is damaged and/or full of sediment
Access road
Rip rap ditch
Clean outs
Toe drain
For design and maintenance
support, contact the Facility
Environmental Engineer
Silt fence is advised to prevent silt
plugging the desilting basin and
outlet structure while vegetation
becomes established.
3-3
SECTION 3 INSPECTION AND MAINTENANCE
3.2.4.2 Storm Water Detention Basin
Inspection of the storm water detention basin (Figure 3-3)
is required for each respective drainage basin. Excess silt,
sediment and debris can decrease basin capacity or lead to
system failure (i.e., plugged outlets). A staff gauge is
included in each basin to easily conduct visual observations.
In addition, as built drawings (Appendix D), XML terrain files
and AutoCAD design files (Appendix E), redline design
drawings (Appendix F), and documentation of cut-off wall
survey monuments (Appendix G) are all available for
reconstruction of the detention basin to original design
schematics. Examples of potential issues with the storm
water detention basin may include the following:
• The storm water detention basin is not draining
• The storm water detention basin has excessive silt
3.2.4.3 Outlet Box
Inspection of the outlet box (Figure 3-3) is required for each respective drainage basin. Examples of
potential issues with the outlet box may include the following:
• The low flow orifice is blocked by sediment, vegetation
or debris
• The silt fence is damaged and/or full of sediment
3.2.4.4 Embankments and Spillway
Inspection of the embankments (Figure 3-3) and spillway (Figure 3-4) are required for each respective
drainage basin. Examples of potential issues with these components may include the following:
• Displacement or movement of spillway or embankment
material
• Embankment instability, potentially caused by
burrowing animals/tunneling
• Erosion along the edges of the spillway or through the
embankments
If the low flow orifice to the outlet box is
blocked greater than 10 percent of the
diameter, then the orifice requires
cleanout maintenance.
The storm water detention basin may not
be draining due to a blocked overflow
structure, or it may be draining, but a
seep/spring has developed in the basin. If
a seep is identified, estimate the flow rate
and report the finding to the Facility
Environmental Engineer (Table 5-1).
If sediment is greater than 1.5 feet at the
staff gauge, the storm water detention
basin should be scheduled for sediment
removal and clean out.
Potential maintenance to embankments
and spillways may include
removal/replacement of embankment
and spillway material, especially if
erosion along the edge of the rip-rap
channel begins to develop.
3-4
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-3. Photograph of a newly constructed storm water detention basin; features include desilting area, check
dam, storm water detention basin, outlet box, spillway and silt fences.
Outlet box
Silt fence
Storm water detention basin
Check dam
Desilting area
Silt fence Embankment Spillway
3-5
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-4. Photograph of a newly constructed spillway. The spillway connects the storm water detention basin to the
cut-off wall.
3.2.5 Cut-off Wall
Inspection of the cut-off walls (Figures 3-5 and 3-6) are required for each respective drainage basin.
Examples of potential issues with the cut-off walls may include the following:
• Cracks have developed and/or are enlarging in the cut-off wall concrete
• The cut-off wall has been damaged (i.e., equipment strikes or storm debris)
• Sediment has built-up behind the wall
• Associated cut-off wall piping is plugged, damaged or broken (evidence of a problem will not likely
be visible at the cut-off wall proper, but rather in other areas along the storm water or WRCW
flow paths)
• The storm water inlet grate is damage or clogged by vegetation or debris
• Associated cut-off wall pipe valves are stiff, leaking or damaged
Storm water inlet grate
Spillway
Cut-off wall
3-6
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-5. Photograph of a newly constructed cut-off wall. The spillway connects the storm water detention pond to
the cut-off wall; the cut-off wall includes a storm water inlet grate and a valve vault.
3.2.6 Weir Box
3.2.6.1 Weir Box Integrity
Inspection of the weir box (Figure 3-7) is required for each respective drainage basin. Examples of
potential issues with the weir box may include the following:
• The above ground concrete weir box curbing
and/or surface grating is damage
• Weir box signage is missing or damaged
• Scale, debris, or sediment (at quantities that
potentially may disrupt flow measurement) has
accumulated in the weir box
• The weir box piping, liner, V-notch, and/or baffle is
damaged
• The weir box piping has developed scale (at
quantities that potentially may disrupt
flow measurement)
Spillway
Valves
Storm water inlet grate
Cut-off wall
Embankment
In order to maintain accurate flow
readings, it is recommended that level
indicators be calibrated approximately
every six months. In addition, the v-
notch may begin to scale and require
cleaning in order to accurately represent
water level. Scale removal from the v-
notch and calibration of the level
indicator should be done in conjunction.
3-7
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-6. Photograph of a newly constructed cut-off wall. The valve port allows access to manipulate the WRCW flow
valves.
Figure 3-7. Photograph of a newly constructed weir box and auxiliary components.
Valve access port
Spillway Storm water vault
Cut-off wall
Weir box
Leak detection
Solar panel
Datalogger
Battery
Level indicator
3-8
SECTION 3 INSPECTION AND MAINTENANCE
3.2.6.2 Data Logger
Inspection of the data logger stations (Figure 3-7) is required. Visually inspect the components of the
data logger station to identify wear and tear, broken or missing parts, and to confirm all display
components are functional. During the inspection, examine the solar panel for damage and clean off
dust. If the data logger is not functioning, operational troubleshooting may be required. See the
Reference Links in Section 5 for guidance on the operation of the datalogger and service
contact information.
3.2.6.3 Leak Detection Sump
Inspection of the leak detection sumps (Figure 3-7) should be performed quarterly, or if there is
suspected pipe damage along the WRCW flow path. If water is detected in any of the leak detection
sumps, notify the facility environmental engineer (Table 5-1) as sample collection will likely be required.
3.2.7 Branch Connection Vault
Inspection of the branch connection vault (Figure 3-8) is required for each respective drainage basin.
Examples of potential issues with the branch connection vault may include the following:
• Presence of standing water inside the vault
• Presence of sediment inside the vault
• Damage to the metal hatch, vent pipe or bollards
• Leak detection sensor malfunction
Potential maintenance to the branch connection vault may include
determining the source(s) of standing water and/or sediment,
draining/cleaning the branch connection vault, and repair of any
damaged components. If flowing water is observed in the branch
connection vault, there is a break in the pipe upstream that will
require immediate repair. Notify the facility environmental engineer
(Table 5-1) if flowing water is observed.
3.2.8 Storm Water Vault, Lower Concrete Lined Canal and Datalogger Station
Inspection of the storm water vault, lower concrete lined canal, and datalogger station (if applicable)
(Figure 3-9) is required for each respective drainage basin. Examples of potential issues with the storm
water vault and lower concrete lined canal may include the following:
• Damage to or
development of
cracks in the
concrete vault
or canal
• Accumulation of
sediment or debris
• Datalogger
malfunction
The leak detection sensor
should be tested annually to
confirm functionality; in order
to test the sensor and
datalogger station strobe, the
sensor must be submerged in
water. A confined space
permit is required to enter the
branch connection vault.
Potential maintenance to the storm water vault and lower concrete lined
canal may include concrete repair and debris/sediment clean out.
Inspect the components of the data logger station to identify wear and tear,
broken or missing parts, and to confirm all display components are functional.
Examine the solar panel for damage and clean off dust.
Calibration of the storm water level indicators is recommended annually in
order to maintain accurate measurements.
If the data logger is not functioning, operational troubleshooting may be
required (see reference links in Section 5 for service contact information).
3-9
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-8. Photograph of a newly constructed WRCW branch connection vault.
Branch connection vault Air backflow
Access hatch for
leak detection
Bollard
Lower concrete lined canal
3-10
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-9. Photograph of a newly constructed storm water vault, level indicator and lower concrete lined canal.
3.2.9 Old Bingham Tunnel
Inspection of the Old Bingham Tunnel (OBT) is required. Examples of potential issues with the OBT may
include the following:
• Collapse or failure of the tunnel entrance
• Accumulation of rock or debris in the tunnel discharge area
• Plugging of the tunnel discharge orifice
Lower concrete lined canal
Storm water vault
and level indicator
Datalogger
Solar panel
Potential maintenance to the OBT may include tunnel
entrance repairs, excavation of rock and/or debris, and
removing accumulated sediment from the discharge and
drainage area.
Battery
3-11
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-10. Photo of the Old Bingham Tunnel (OBT) entrance.
3.2.10 Settling Basin
The Settling Basin (Figure 3-11) should be drained and inspected on a quarterly basis for two years
starting 4Q2016 to establish a performance baseline. In order to perform the inspection, the following
steps need to be taken:
• Place the WRCW into bypass by closing the valve at the WRCW Branch Vault diversion (Station
2134+00). Cross reference section 2.3.10 for additional details.
• Pump down the Settling Basin in manual to low shut-off.
• Remove the remaining water; use of a vacuum truck is strongly recommended due to the likely
presence of silt.
• Remove the excess silt and water with a vacuum truck. Consult with the facility environmental
engineer for proper disposal of sediment and water.
• IMPORTANT. When vacuuming, always keep separation between the hose intake and the liner so
as not to damage the liner. The corner welds are stronger and better anchored than the center
liner; vacuuming should be preferentially focused in these areas. In order to maintain space
between the hose tip and the liner, incorporate a basket or similar implement.
Tunnel discharge
Old Bingham Tunnel entrance
3-12
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-11. Settling Basin isometric projection and cross sectional view.
Examples of potential issues, other than accumulated sediment, occurring in the Settling Basin may
include the following:
• The concrete Settling Basin curbing and/or surface grating is damage
• Signage is missing or damaged
• Scale or debris (at quantities that potentially may disrupt flow measurement) has accumulated in
the Settling Basin
• The piping is damaged
• The piping has developed scale (at quantities that potentially may disrupt flow measurement)
When vacuuming
always keep
separation between
the hose intake and
the liner so as not to
damage the liner.
3-13
SECTION 3 INSPECTION AND MAINTENANCE
3.2.11 Lower Concrete Lined Canal
The lower concrete lined canal (Figure 3-12) should be inspected for accumulation of sediment and
debris and the elimination of sources (i.e., eroded embankments). Sediment and debris should be
removed regularly in order to maintain design capacity and best performance. Should vegetation
develop, remove in order to maintain best performance. Quarterly inspection should include
observations for settling and cracking of the lower concrete lined canal sections. Minor cracks will not
hinder performance but should be addressed in order to prevent deterioration of the structure and
costlier repairs in the future.
Figure 3-12. Section of the lower concrete lined canal.
3.2.12 WRCW Branch Vault Diversion Box (WRCW Vault Station 2134+00)
The inspection of the branch vault diversion box (Station 2134+00) is similar to the inspection of typical
WRCW vaults (See Section 3.2.7), and can be done in conjunction with the settling basin inspection since
this is where the basin bypass is accomplished. This vault does not contain a leak detection sensor and
associated strobe. In addition to criteria outlined in section 3.2.7, the valve requires exercise and
associated bypass piping requires inspection for leaks or damage.
Lower concrete lined canal
3-14
SECTION 3 INSPECTION AND MAINTENANCE
Figure 3-13. (A) WRCW branch vault diversion box (Station 2134+00); (B) diversion gate valve.
3.2.13 South Area Dumps (SAD) Box
The South Area Dump (SAD) Box does not have leak detection due to the relatively clean nature of the
WRCW as compared to the WRCW reporting from the Copper drainages north. The important aspects to
inspect in order to ensure proper function of the structure are:
• If sediment and debris are present in the box they should be removed immediately.
• Check for damage of the liner and pipe inlets/outlets due to sediment and debris.
• If scale is present it should be removed in order to preserve capacity.
IMPORTANT. When vacuuming always keep separation between the hose intake and the liner so as
not to damage the liner.
3.2.14 Storm Water Inlet Structure at Lower Concrete Lined Canal
The storm water inlet structure at the lower concrete lined canal should require limited maintenance.
Inspect for sediment and debris that could hinder capacity and full function of the structure. Large
intense rain events will be of particular interest since this is about the only time the structure will have
become active. Sediment and debris will need to be removed in order to maintain full functionality.
Station 2134+00
WRCW diversion flow
Diversion gate valve
(A)
(B)
3-15
SECTION 3 INSPECTION AND MAINTENANCE
3.3 Compliance Sampling Locations and Frequency
Compliance points such as cut-off walls, weir boxes, seeps and tunnels are associated with the Bingham
Canyon Mine Groundwater Discharge Permit #UGW350010, and are required to be sampled on various
frequencies for water quality and flow rate (Figure 3-14). The installation of the cut-off walls and toe
drain associated with the EWRE required updating many of these sample points, as the legacy system
was replaced and the new collection system was installed.
Appendix H details the transition from the legacy east side collection system to the newly
installed EWRE water collection system. The operational sample identification numbers (i.e. cut-off
walls) were kept the same at the new weir boxes in cases where the legacy flow was traced to the
corresponding new toe drain section, branch line and weir box. In cases where new drainages were
intercepted not corresponding to the legacy system, a new identification number was assigned.
Incorporated into the new system is capture of WRCW primarily at the toe drain and secondarily at the
cut-off wall. Both sources for a particular drainage are collected at a shared weir box. The sample
reporting from the toe drain has an “A” designation while the sample from the cut-off wall has a “B”
designation. During construction, water quality from the A and B sources was typically different, in that
toe drain water was more characteristic of waste rock contact water, and cut-off wall water was more
characteristic of fresh water. Based upon this information, the following guidance is derived:
• When the two water qualities mix in the weir box, and are introduced to an open environment with
increased oxygen, water chemistry will change and increased mineral precipitation (i.e. scale) can be
expected.
• If water quality is to suddenly diminish in the “B” sample reporting from the cut-off wall, toe drain
functionality could be in question, although all potential sources need to be considered
and investigated.
Typically, each weir represents a single drainage; however, flow from the Lost Creek-Keystone drainages
merge into a single weir box, and flow from the South Congor-Midas drainages merge into a single weir
box. Discharge water from the Old Bingham tunnel also enters the South Congor-Midas weir box, but
can still be sampled at the tunnel opening. In all cases the curb is labeled with the sample identification
number for easy identification, and a sample port grate allows for sample collection access.
A number of seeps were identified during the EWRE project. The locations of these seeps, as well as the
geology, are shown on Figure 3-15. This seeps, springs and area geology map was constructed to provide
documentation of the EWRE site prior to waste rock coverage.
3-16
SECTION 4
4.0 Training
4.1 General Requirements
Training for the operation of the basins consists of the following components:
• A complete read of the O&M and thorough review of the materials provided in the appendices;
• A site tour with a member of the construction team and/or operations team familiar with the basins
and structures.
If, in the future, a knowledge gap is identified, contact a member of the RTKC Water Quality team
(Table 5-1) and arrange for training support should knowledgeable members of the construction team or
operations team not be available.
4-1
SECTION 5
5.0 Reference Information
5.1 UDWQ Construction Permit
The collection system design and specifications were reviewed and approved by Mr. Woodrow
Campbell, P.E. of the Utah Department of Environmental Quality – Division of Water Quality. Eight
periodic field visits were conducted during the construction activities, including a final inspection on
October 25, 2016. The State inspection reports are included in Appendix I.
5.2 Dam Safety Permit
The embankments associated with the detention basins were reviewed and approved through the Utah
Department of Natural Resources – Water Rights – Dam Safety. Under the advisement of the Assistant
State Engineer, the basins were lumped together by drainage and issued a permit number accordingly.
The combined basins per drainage are classified as a small dam – low hazard with cumulative capacities
by drainage of less than 20 acre-feet.
5.3 Groundwater Discharge Permit
The EWRE collection system components are associated with the Bingham Canyon Mine and Water
Collection System Groundwater Discharge Permit # UGW350010, under the sections Part 1.D.3 and
Part 1.D.2.
5.4 Project Contacts
Should questions arise in the future that are not covered in this document, RTKC contacts are
provided below.
Table 5-1. EWRE project contact information
Name Title Contact Information
Tom Gibson Construction Manager 970-946-0641
Steve Ferris Project Manager 385-246-6938
Rob Watson Construction Superintendent 801-824-1146
Scott Bird Manager – HSEC & Quality 801-699-8337
Jason Hill Quality and Engineering 435-841-9413
Zeb Kenyon Environmental Compliance and Quality 801-913-2356
Jason Doyle Operations Manager - Tailings 801-652-0028
Guillermo Salcedo Operations Supervisor - SAWS 801-232-1297
Brian Vinton Principal Advisor – Water Quality 801-712-4597
5-1
SECTION 5 REFERENCE INFORMATION
Reference
Links:
Datalogger Flow Monitoring Reference Material
The Pulsar Ultra Twin UL Instruction Manual (June 2011) is available at:
https://www.pulsar-
pm.com/LinkClick.aspx?fileticket=BoFap_kwCtI%3d&tabid=771&portalid=0&mid=1111&language=en-
GB
The Pulsar datalogger software is Ultra Log 5.1, and is available at:
https://www.pulsar-pm.com/support/downloads/software.aspx
Midas Pump Station Reference Material
The installation, operation and maintenance manual for the Goulds Pumps Model
3196 i-FRAME at the Midas Pump Station is available at:
https://www.gouldspumps.com/ittgp/medialibrary/goulds/website/Products/3196-i-
FRAME/InstallationOperationMaintenance_3196_i_FRAME.pdf
5.5 Project Quality Assurance and Quality Control
Documentation of project quality assurance and quality control is provided in Appendix J. Quality
Control was performed by Amec Foster Wheeler Environment and Infrastructure, Inc., and discrepancies
were satisfactorily reported and corrected.
5.6 Revision History
To assist in future updates and revisions to the EWRE O&M Manual, the native Microsoft Word file is
included in Appendix K.
Rev # Description of Changes Prepared by Date
0 Original release of O&M to comply with
UDWQ Permit #UGW350010
Permit to Construct, Condition #2
Zeb Kenyon, RT G&I December 2016
5-2
DWQ-2020-015202
Appendix A
EWRE Geology, Seeps, and
Springs Map
Appendix B
Drainage Basin Photographic Logs
Appendix C
South Area Water Services East Side
Collection System – East Waste Rock
Extension Groundwater Discharge
Permit Inspection and Supplemental
Inspection Forms
Appendix D
Drainage Basin As-Built Drawings
Appendix E
XML Terrain Files and AutoCAD
Design Files
Appendix F
Redline Design Drawings
Appendix G
Survey Monument Documentation
Appendix H
EWRE Compliance Monitoring
Transition Documentation
Appendix I
State Inspection Reports
Appendix J
Quality Assurance and Quality Control
Documentation
Appendix K
Operations and Maintenance Manual
Microsoft Word Document File
Appendix L
CH2M HILL Hydrology Report