DAQC-466-25
Site 11042 (B1)
Site 13140 (B1)
Grant Ensign
Geneva Rock Products, Inc.
730 North 1500 West
Orem, Utah 84057
Dear Mr. Ensign:
Re: Geneva Rock Products, Inc. – Temporary Relocation/Operation, Notice of Intent – Utah
County
Your Notice of Intent dated April 18, 2025, to relocate portable concrete batch plant equipment to
the temporary project for Geneva Rock Products’ Payson Concrete Batch Plant located at 1600
North Main Street, Payson, Utah, was received by the Utah Division of Air Quality (DAQ) and
has been reviewed.
The following equipment has been approved for operation for this temporary project:
Cemco 125 cubic yard per hour mobile concrete batch plant
Wisperwatt 70 KVA diesel generator
The State of Utah has permitted portable equipment for Geneva Rock Products on the Approval
Order (AO) DAQE-AN110420003-21 dated March 17, 2021. This location is a permanent
permitted facility with established production limits. All equipment operating at this site must be
in accordance with the current AO DAQE-AN131400004-18 dated January 31, 2018. The total
production of concrete from all temporary projects when combined with the permanent
equipment’s production cannot exceed the 12-month rolling limits as per Condition II.B.1.c of this
AO. As per Condition II.B.3.c of your portable equipment AO, the equipment shall operate only
between 6:00 am and 10:00 pm each day. The hours of operation may be altered upon approval of
the director; however, any request for a change in these hours shall include modeling showing that
all National Ambient Air Quality Standards (NAAQS) are met.
6 Û Ù Û Ù Û Þ
DAQC-466-25
Page 2
Approval is granted to relocate and operate this equipment at the new location for a period not to
exceed 180 operational days. As per Utah Administrative Code (UAC) R307-401-17, the
operation of equipment at this temporary site may be for up to 180 working days in any calendar
year not to exceed 365 consecutive days, starting from the initial relocation date. Approval is
subject to the conditions of the dust control plan submitted for this location and the applicable
conditions of the above referenced portable AO. Hours of operation shall be held to 16 hours each
day. The maximum production rate shall be held to the requested 125 cubic yards per hour.
The owner/operator shall maintain records of the actual operation hours, days, and production
rate, of the above referenced equipment at this relocation site and have the ability to submit the
information to the DAQ upon the request of representatives of the director. Please make certain
that the plant operator is aware of all the location specific requirements for this site and the
conditions of the aforementioned AO.
Utah Division of Water Quality Storm Water Permits and regulations may apply to this temporary
project. Please refer to https://secure.utah.gov/deq-dashboard/index.html for additional
information.
This approval for relocation in no way releases the owner or operator from any liability for
compliance with all other applicable federal, state, and local regulations including the UAC.
If you have any questions regarding this relocation authorization or the temporary relocation
process please contact Susan Weisenberg at (385) 306-6512.
Sincerely,
Jay P. Morris
Assistant Director
JPM:SW:rh
Enclosure: Submitted Temporary Relocation Form
cc: Utah County Health Department
4 * - - $ . — 4 @ H v A ? A D ? H w D B ˜
Susan Weisenberg <sweisenberg@utah.gov>
Portable/Temporary Relocation Form
1 message
noreply@qemailserver.com <noreply@qemailserver.com>Fri, Apr 18, 2025 at 2:31 PM
Reply-To: trigger@qemailserver.com
To: sweisenberg@utah.gov
Susan/Chad:
Site # -- Geneva Rock Products has requested a Temporary Relocation. Please see the information below. Any
attachments can be access by clicking on the links.
Recipient Data:
Time Finished: 2025-04-18 14:31:30 MDT
IP: 205.197.217.202
ResponseID: R_1EFLMKeYvfCR3K0
Link to View Results: Click Here
URL to View Results: https://utahgov.iad1.qualtrics.com/apps/single-response-reports/reports/
cMYu2wzCkmN6xaTtULVLwSxnNKpRUH71tENun0BUhvPATSOWK7DE9B6mWL0j
mdxSo62DCYGw9VK35ZhypWHo7Rb3pr0ab7GP3BmPNkoR0ttthGJ_5flsqfpyPEsY3DaHOEobZd0ZdF9yIt
cT1aRpzJmw1RA-Jhgl0rliheE83ZAGIDxXOLBhwHQ9ovbv40HvBsnq2S9o224HfZPTI448tML8EH_
adMEQn8ih6kEKw2pm1gv7qKZCv0kUcesZrnDEDYCkhiwo2jHQXQQLxT3-InNrpCmokYiKv6tldgDXbpkcXurkUV
JLNJ6XWWcgfVJSNs1Z9hgE-o4QjZ82Fk-47A
Response Summary:
Please fill out the information below:
Contact Person: Grant Ensign
Company Name: Geneva Rock Products
Mailing Address: 730 N 1500 West
City: Orem
Zip: 84057
Phone Number: 8018026954
Email: gensign@clydeinc.com
Is the site located within a PM2.5 non-attainment and maintenance plan areas on cleared land grea...
Yes
All temporary relocation projects are required to submit a Fugitive Dust Control Plan (FDCP). Lo...
10519
Briefly give directions to the site and/or physical address:
1325 N. Main Street, Payson, UT
Proposed Relocation Information:
Closest City Payson
County Utah
UTM X Coordinates 40.061428
UTM Y Coordinates -111.733420
Approximate distance to the nearest house/business 400 feet
UTM X Coordinates to nearest house/business 40.061465
UTM Y Coordinates to nearest house/business -111.731884
Does this site currently have a permit with DAQ?
4/21/25, 10:47 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1829773817950858797%7Cmsg-f:1829773817950858797&s…1/2
Yes
If yes, what is the Permit (DAQ-AN) # ?
DAQE-AN131400004-18
If yes, what is the Permit Holder's Name?
Geneva Rock Products, Inc.
Please provide the permit ID for the equipment? (DAQE-XXXXXXXXX-XX)
DAQE-AN110420003-21
Please list all the Equipment on Site:Note: It is important to identify ALL diesel powered engine...
1
Equipment Type Mobile Concrete Batch Plant
Make/Model Cemco 220
Design Capacity 125 CY/hr
2
Equipment Type Diesel Generator
Make/Model Wisperwatt 70KVA
Serial or ID# 7359212
Manufactured Date 2024
3
Equipment Type Associated conveyors/belts
Have any other state or local regulatory agencies issued any other "Conditional Use Permits" for...
No
Operational Information: (Please note: Operating time over 16 hours in a 24 hour period will re...
Total Hours of operation per 24 hr period 24
Starting time of operation (am/pm) 12 AM
Ending time of operation (am/pm) 12 AM
Maximum hourly production rate for project 125 CY/hr
Expected startup date 05/01/2025
Expected completion date 05/01/2026
What type of application is this for?
New Application
In accordance with the fee schedule approved by the Utah State Legislature, the Division of Air Q...
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_1FLoXFqWXmpOHkQ
Owner/Operator Representative:
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_32Sev348aP9KaZe
4/21/25, 10:47 AM State of Utah Mail - Portable/Temporary Relocation Form
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1829773817950858797%7Cmsg-f:1829773817950858797&s…2/2
Susan Weisenberg <sweisenberg@utah.gov>
TRP: Geneva Rock - Payson: Concrete Batch Plant
1 message
Grant Ensign <gensign@clydeinc.com>Wed, May 14, 2025 at 10:20 AM
To: Susan Weisenberg <sweisenberg@utah.gov>
Hi Susan,
A few weeks ago, I submi ed a TRP for a mobile concrete batch plant for Geneva Rock in Payson, UT. This is the
project we're hoping to get approved for 24-hour opera on.
We’re currently modeling the plant to determine whether it exceeds the Significant Impact Level (SIL), but it will likely
take a few more weeks to finalize. In the mean me, would you be able to issue the TRP with the standard restricted
opera ng hours of 6:00 AM to 10:00 PM? This would allow us to begin produc on while we complete the modeling.
Once we’re able to demonstrate that the plant is below the SIL, we’ll submit a request for 24-hour opera on.
Thanks so much!
Grant Ensign
ENVIRONMENTAL ENGINEER
O (801) 802-6954
C (801) 633-7830
WWW.CLYDEINC.COM
5/14/25, 11:17 AM State of Utah Mail - TRP: Geneva Rock - Payson: Concrete Batch Plant
https://mail.google.com/mail/u/0/?ik=bffac613d3&view=pt&search=all&permthid=thread-f:1832113514768570369%7Cmsg-f:1832113514768570369&s…1/1