HomeMy WebLinkAboutDDW-2025-004923Danielle Zebelean <dzebelean@utah.gov>
IPP - Potable Water Plan Approval
1 message
Logan.Green <Logan.Green@kiewit.com>Thu, Oct 19, 2023 at 12:30 PM
To: "dzebelean@utah.gov" <dzebelean@utah.gov>, "jchartier@utah.gov" <jchartier@utah.gov>
Cc: "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Amanda.Sobek"
<Amanda.Sobek@kiewit.com>
Danielle and John,
This is in reference to attached Plan Approval.
It has come to our attention regarding a sanitary line size change required for the IPP Renewed facility. The originally-
sized sanitary lines (6”) have already been already installed underground and backfilled. As Kiewit has evaluated the
revised line sizing (3”) and routing, the desired path forward is to abandon-in-place these already installed lines (but not
before disconnecting them from their respective source/destination at either end to preclude sanitary waste from entering
the pipe) and install new sanitary lines. With this design, there will be a portion where the sanitary line is routed above
potable water pipe in a crossing instance. Kiewit has reviewed Utah Administrative Rule R309-550-7 where it offers
guidance on protection of potable water lines routed beneath sanitary lines, but in this design instance the sanitary pipe
would cross above the potable water pipe.
Kiewit would like to review for acceptance the following proposed design for the instances in which the new underground
sanitary line is routed above the previously installed potable line.
Proposal: In the instances where a sanitary line is routed above the previously installed potable water line, Kiewit would
install a 6” PVC sleeve over the 3” sanitary pipe (HDPE SDR 11) which shall extent no less than 10 feet beyond either
side of the point of crossing. Our preference would be to use a PVC sleeve for the installation for these lines, with a
secondary option being a 6” HDPE SDR 21 sleeve. The sanitary line will be a pressurized pipe as it is being pumped from
a lift station and the potable water pipe is a pressurized line from the facility booster pump.
This is a high priority to review and discuss in order to minimize the construction impacts. If you have any direct
questions, please let Paul Novogoratz or myself know. Additionally, Kiewit would be available for a call this week or early
next week to answer any questions. I have attached the instances where this revised sanitary routing would be required to
be routed over an existing installed potable water line as well as a diagram of the 10ft sleeve extending in each direction
from where a sanitary and potable water cross would occur.
Thank you,
LOGAN GREEN
Process Engineer, Water
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Water Plan Approval
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1780209694244048465&simpl=msg-f:1780209694244048465 1/2
KIEWIT ENGINEERING GROUP INC.
8900 Renner Blvd, Lenexa, KS 66219
Mailstop: K4.2.C.06
913-928-7355 direct
www.kiewit.com
2 attachments
DDW-2023-008445.pdf
282K
IPP Sanitary and Potable Routing.pdf
1346K
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Water Plan Approval
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1780209694244048465&simpl=msg-f:1780209694244048465 2/2
Danielle Zebelean <dzebelean@utah.gov>
IPP - Potable Operating Permit Question
6 messages
Logan.Green <Logan.Green@kiewit.com>Fri, Apr 5, 2024 at 10:21 AM
To: "jchartier@utah.gov" <jchartier@utah.gov>, "dzebelean@utah.gov" <dzebelean@utah.gov>
Cc: "lucas.davis" <lucas.davis@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>
John or Dani,
For the Certification of Rule Conformance (checklist item #1) for the Potable Water Operating Permit, can you confirm if
the Utah DDW has a preferred form for Kiewit to fill out, or if it is typical to just use a standard company letter head for this
Certification of Rule Conformance?
Thank you,
LOGAN GREEN
Process Engineer, Water
KIEWIT ENGINEERING GROUP INC.
8900 Renner Blvd, Lenexa, KS 66219
Mailstop: K4.2.C.06
913-928-7355 direct
www.kiewit.com
Danielle Zebelean <dzebelean@utah.gov>Mon, Apr 8, 2024 at 7:15 AM
To: "Logan.Green" <Logan.Green@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "lucas.davis" <lucas.davis@kiewit.com>, "Paul.Novogoratz"
<Paul.Novogoratz@kiewit.com>
Hi Logan,
We do not have a form and you are correct that it is typically a standard company letterhead. It's preferred that any major
redlines to the project after plan approval was received are called out in the letter.
Please also note the four sets of water quality data that is required as well with the operating permit. Further, I would like
to conduct a final inspection of the facility before issuing an operating permit. John will probably also like to join. If you are
at the point where a final inspection is possible let us know and we can start coordinating.
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Operating Permit Question
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1795512427750551710&simpl=msg-f:179551242775055171…1/5
Please let me know if you have any questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Logan.Green <Logan.Green@kiewit.com>Thu, Apr 11, 2024 at 10:22 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "lucas.davis" <lucas.davis@kiewit.com>, "Paul.Novogoratz"
<Paul.Novogoratz@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-
PTR@ticus.com>
Dani,
Construction is still on-going, so I would recommend potentially mid/end-May is realistic for the final inspection walkdown
for the potable water treatment process. Over the next month our team will continue to stay in touch as it gets closer to
submitting the paperwork for the Operating Permit. The on-site contacts will be Brittany James
(brittany.james@kiewit.com) and Lance Batts (lance.batts-ptr@ticus.com). Lance will be the primary contact for the onsite
final inspection while Brittany will be the primary contact who will be submitting the formal documentation for the
Operating Permit.
Regarding your note the four sets of water quality samples, can you confirm your expectation on this? Is it the same
potable sample location taken four different days, or are you expecting the same day but four different locations at the
facility?
Thank you,
LOGAN GREEN
913-928-7355 direct
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, April 8, 2024 8:15 AM
To: Logan.Green <Logan.Green@kiewit.com>
Cc: jchartier@utah.gov; lucas.davis <lucas.davis@kiewit.com>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>
Subject: [External]Re: IPP - Potable Operating Permit Question
Hi Logan,
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Operating Permit Question
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1795512427750551710&simpl=msg-f:179551242775055171…2/5
We do not have a form and you are correct that it is typically a standard company letterhead. It's preferred that any major
redlines to the project after plan approval was received are called out in the letter.
Please also note the four sets of water quality data that is required as well with the operating permit. Further, I would like
to conduct a final inspection of the facility before issuing an operating permit. John will probably also like to join. If you are
at the point where a final inspection is possible let us know and we can start coordinating.
Please let me know if you have any questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Thu, Apr 11, 2024 at 10:45 AM
To: "Logan.Green" <Logan.Green@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "lucas.davis" <lucas.davis@kiewit.com>, "Paul.Novogoratz"
<Paul.Novogoratz@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-
PTR@ticus.com>
Hi Logan,
For the four sets here is the language that was included in the operating permit checklist at the very end of the plan
approval letter: Four sets of raw and treated water samples will be analyzed for arsenic, pH. Additionally, the chlorine
residual of the treated water will be measured. Each of the sets will be collected on separate calendar days.
And sounds good. I will look for future emails.
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Operating Permit Question
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1795512427750551710&simpl=msg-f:179551242775055171…3/5
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Paul.Novogoratz <Paul.Novogoratz@kiewit.com>Mon, May 13, 2024 at 9:11 AM
To: Danielle Zebelean <dzebelean@utah.gov>, "Logan.Green" <Logan.Green@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "lucas.davis" <lucas.davis@kiewit.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>
Hi, Dani;
Would you mind performing a quick sanity check for the attached draft for the Certification of Rule Conformance? Is this
generally what the DDW is expecting?
Thanks,
Paul
PAUL NOVOGORATZ, P.E.
Mechanical Engineer
KIEWIT ENGINEERING GROUP INC.
8880 Penrose Lane., Lenexa, KS 66219
913-928-7000 Ext. 7443
[Quoted text hidden]
Potable Water -Certification of Rule Conformance.docx
35K
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Operating Permit Question
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1795512427750551710&simpl=msg-f:179551242775055171…4/5
Danielle Zebelean <dzebelean@utah.gov>Tue, May 14, 2024 at 1:31 PM
To: "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>
Cc: "Logan.Green" <Logan.Green@kiewit.com>, "jchartier@utah.gov" <jchartier@utah.gov>, "lucas.davis"
<lucas.davis@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-
PTR@ticus.com>
Hi Paul,
Yes that is sufficient for the certification of rule conformance.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
5/29/25, 11:53 AM State of Utah Mail - IPP - Potable Operating Permit Question
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1795512427750551710&simpl=msg-f:179551242775055171…5/5
Danielle Zebelean <dzebelean@utah.gov>
IPP Renewed Potable Water System
17 messages
Harrison.Stinson <Harrison.Stinson@kiewit.com>Wed, Jul 17, 2024 at 11:28 AM
To: "dzebelean@utah.gov" <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>
Dani,
I'm currently on site at IPP Renewed in Delta, Utah, and will be your primary point of contact for the Potable Water
Opera ng Permit. I wanted to provide you with an update on the scheduled flushing dates. See below with what we
have currently planned:
Initial flushing - 8.26
Chlorination flush - 9.2
Prior to issuing the permit, would you like to conduct a final inspec on of the facility? If so, please let me know when
you prefer to conduct the inspec on before the chlorina on flush.
I will be in touch as the September 2nd date approaches with any further updates.
If you have any ques ons or concerns, please do not hesitate to reach out.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
Danielle Zebelean <dzebelean@utah.gov>Thu, Jul 18, 2024 at 6:44 AM
To: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>
Hi Harrison,
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…1/23
Thank you for the update. I would like to come conduct a final inspection on the facility. Right now I have availability
August 12, 13, 19, 20, 21, and 22. I would be able to make it to the plant around 11 am or later any of those days.
Do you have a timeframe for collecting the raw and finished water samples for the operating permit request? Will that be
after the chlorination flush?
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Harrison.Stinson <Harrison.Stinson@kiewit.com>Fri, Jul 26, 2024 at 11:19 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>
Danielle,
Sorry for just now ge ng back to you. A er ge ng with my team, we can have you on site 8.22, 1pm would be the
preferable me.
For the water samples, we planned on collec ng the samples a er the chlorina on flush to then send to the lab for
tes ng.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Thursday, July 18, 2024 6:44 AM
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…2/23
To: Harrison.S nson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Ba s-PTR <Lance.Batts-PTR@ticus.com>;
Bri any.James <Brittany.James@kiewit.com>
Subject: [External]Re: IPP Renewed Potable Water System
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Mon, Jul 29, 2024 at 3:53 PM
To: John Chartier <jchartier@utah.gov>
Does Aug 22 around 1 pm work for you? Would you like to come on the final inspection?
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
John Chartier <jchartier@utah.gov>Mon, Jul 29, 2024 at 4:11 PM
To: Danielle Zebelean <dzebelean@utah.gov>
I am interested in seeing the final product there, and that day and time should work for me. I'll
plan on it, if you don't mind me tagging along.
Thanks!
John L. Chartier, P.E.
Central District Engineer| DEQ
M: (435) 559-1969
P: (435) 896-5451 ext. 314
70 Westview Drive Richfield, UT 84701
deq.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Mon, Jul 29, 2024 at 4:15 PM
To: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…3/23
Great! Thank you Harrison! I've added this to my calendar. Our district engineer, John Chartier, is also planning on
coming. I've also notified the Central Utah Health Department if they would like to join.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Harrison.Stinson <Harrison.Stinson@kiewit.com>Mon, Aug 19, 2024 at 8:49 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>
Dani,
As we prepare for your visit this week, is there anything specific you want out of this system walk or anything you
want prepared prior to your visit? Iso's, P&ID's, etc.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, July 29, 2024 4:15 PM
To: Harrison.S nson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Ba s-PTR <Lance.Batts-PTR@ticus.com>;
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…4/23
Bri any.James <Brittany.James@kiewit.com>
Subject: Re: [External]Re: IPP Renewed Potable Water System
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Tue, Aug 20, 2024 at 9:00 AM
To: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>
Hi Harrison,
I will be focusing on the new treatment plant and storage tank to verify they will pass a Sanitary Survey Inspection. I've
attached the question set below. Not everything will be applicable since some questions are about ongoing operation and
maintenance.
Please let me know if you have any further questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
13356 Questions.pdf
142K
Harrison.Stinson <Harrison.Stinson@kiewit.com>Tue, Aug 20, 2024 at 1:26 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>
Dani,
Following up on our phone call. We will be best prepared to have you and John on site the week of Sept. 30th to
conduct a final walkdown of the system.
I will keep you posted if anything changes.
Best,
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…5/23
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Tuesday, August 20, 2024 9:00 AM
To: Harrison.S nson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Ba s-PTR <Lance.Batts-PTR@ticus.com>;
Bri any.James <Brittany.James@kiewit.com>
[Quoted text hidden]
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Tue, Aug 20, 2024 at 1:28 PM
To: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>
Great!
I have availability September 30 to October 2. I can plan on October 1 around 1 pm?
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Wed, Sep 25, 2024 at 11:50 AM
To: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>, David Heaton <dheaton@centralutahhealth.org>, Eric Larsen <elarsen@centralutahhealth.org>
Hi Harrison,
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…6/23
Following up on this thread. I still have it on my calendar that potentially October 1 I would be coming down for the final
inspection. Is the project still on track for that?
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Harrison.Stinson <Harrison.Stinson@kiewit.com>Wed, Sep 25, 2024 at 1:10 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>, "Kylie.Alejos" <Kylie.Alejos@ticus.com>, David Heaton <dheaton@centralutahhealth.org>, Eric
Larsen <elarsen@centralutahhealth.org>
Dani,
Thanks for taking my call. As discussed, today is my last day on IPP and Kylie Alejos, cc'd, will be your new point of
contact for site related items. October 1st will be somewhat early as we want to let you walk down the system as
close to comple on as possible. We are holding October 14th for the chlorina on flush, so the week of October
7th would be best for you to walk the system. You men oned having previous commitments on the 7th and 8th so
Kylie will work with you on the exact date of your walk.
Please direct any further ques ons to Kylie.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…7/23
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Wednesday, September 25, 2024 11:50 AM
To: Harrison.S nson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Ba s-PTR <Lance.Batts-PTR@ticus.com>;
Bri any.James <Brittany.James@kiewit.com>; Don.Smith-PTR <Don.Smith@ipsc.com>; Andrew.Dutson-PTR
<Andrew.Dutson@ipsc.com>; David Heaton <dheaton@centralutahhealth.org>; Eric Larsen
<elarsen@centralutahhealth.org>
[Quoted text hidden]
[Quoted text hidden]
Kylie.Alejos <Kylie.Alejos@ticus.com>Wed, Sep 25, 2024 at 1:11 PM
To: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>, Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>, David Heaton <dheaton@centralutahhealth.org>, Eric Larsen <elarsen@centralutahhealth.org>
Dani,
Are you able to come out to site 10/9 or 10/10?
Kylie Alejos
269-235-0206
From: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Sent: Wednesday, September 25, 2024 1:10 PM
To: Danielle Zebelean <dzebelean@utah.gov>
[Quoted text hidden]
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Wed, Sep 25, 2024 at 2:07 PM
To: "Kylie.Alejos" <Kylie.Alejos@ticus.com>
Cc: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>, "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz"
<Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR"
<Lance.Batts-PTR@ticus.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>,
"Andrew.Dutson-PTR" <Andrew.Dutson@ipsc.com>, David Heaton <dheaton@centralutahhealth.org>, Eric Larsen
<elarsen@centralutahhealth.org>
Hi Kylie,
I can make it down 10/9 or 10/10 in the afternoon around 3:30pm, I have meetings in the morning both days.
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…8/23
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Kylie.Alejos <Kylie.Alejos@ticus.com>Wed, Sep 25, 2024 at 2:18 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "Harrison.Stinson" <Harrison.Stinson@kiewit.com>, "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz"
<Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR"
<Lance.Batts-PTR@ticus.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>,
"Andrew.Dutson-PTR" <Andrew.Dutson@ipsc.com>, David Heaton <dheaton@centralutahhealth.org>, Eric Larsen
<elarsen@centralutahhealth.org>, "Natalee.Brake" <Natalee.Brake@ticus.com>
Dani –
10/10 sounds great. Either myself, or our Field Engineer Natalee Brake will walk with you.
Thanks,
Kylie Alejos
269-235-0206
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Wednesday, September 25, 2024 2:07 PM
To: Kylie.Alejos <Kylie.Alejos@ticus.com>
Cc: Harrison.Stinson <Harrison.Stinson@kiewit.com>; jchartier@utah.gov; Paul.Novogoratz
<Paul.Novogoratz@kiewit.com>; Dustin.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR
<Lance.Batts-PTR@ticus.com>; Brittany.James <Brittany.James@kiewit.com>; Don.Smith-PTR <Don.Smith@ipsc.com>;
Andrew.Dutson-PTR <Andrew.Dutson@ipsc.com>; David Heaton <dheaton@centralutahhealth.org>; Eric Larsen
<elarsen@centralutahhealth.org>
Subject: Re: [External]Re: IPP Renewed Potable Water System
Hi Kylie,
I can make it down 10/9 or 10/10 in the afternoon around 3:30pm, I have meetings in the morning both days.
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:18048481438407989…9/23
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
[Quoted text hidden]
[Quoted text hidden]
[Quoted text hidden]
[Quoted text hidden]
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…10/23
On Tue, Aug 20, 2024 at 1:28 PM Danielle Zebelean <dzebelean@utah.gov> wrote:
Great!
I have availability September 30 to October 2. I can plan on October 1 around 1 pm?
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Tue, Aug 20, 2024 at 1:26 PM Harrison.Stinson <Harrison.Stinson@kiewit.com> wrote:
Dani,
Following up on our phone call. We will be best prepared to have you and John on site the week of Sept. 30th to
conduct a final walkdown of the system.
I will keep you posted if anything changes.
Best,
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…11/23
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Tuesday, August 20, 2024 9:00 AM
To: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>; Dustin.Delozier-
PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR <Lance.Batts-PTR@ticus.com>; Brittany.James
<Brittany.James@kiewit.com>
Subject: Re: [External]Re: IPP Renewed Potable Water System
Hi Harrison,
I will be focusing on the new treatment plant and storage tank to verify they will pass a Sanitary Survey
Inspection. I've attached the question set below. Not everything will be applicable since some questions are about
ongoing operation and maintenance.
Please let me know if you have any further questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…12/23
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Aug 19, 2024 at 8:49 PM Harrison.Stinson <Harrison.Stinson@kiewit.com> wrote:
Dani,
As we prepare for your visit this week, is there anything specific you want out of this system walk or anything
you want prepared prior to your visit? Iso's, P&ID's, etc.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, July 29, 2024 4:15 PM
To: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dustin.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR <Lance.Batts-PTR@ticus.com>;
Brittany.James <Brittany.James@kiewit.com>
Subject: Re: [External]Re: IPP Renewed Potable Water System
Great! Thank you Harrison! I've added this to my calendar. Our district engineer, John Chartier, is also planning
on coming. I've also notified the Central Utah Health Department if they would like to join.
Thanks!
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…13/23
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jul 26, 2024 at 11:19 AM Harrison.Stinson <Harrison.Stinson@kiewit.com> wrote:
Danielle,
Sorry for just now getting back to you. After getting with my team, we can have you on site 8.22, 1pm would
be the preferable time.
For the water samples, we planned on collecting the samples after the chlorination flush to then send to the
lab for testing.
Best,
Harrison Stinson
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…14/23
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Thursday, July 18, 2024 6:44 AM
To: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dustin.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR <Lance.Batts-
PTR@ticus.com>; Brittany.James <Brittany.James@kiewit.com>
Subject: [External]Re: IPP Renewed Potable Water System
Hi Harrison,
Thank you for the update. I would like to come conduct a final inspection on the facility. Right now I have
availability August 12, 13, 19, 20, 21, and 22. I would be able to make it to the plant around 11 am or later
any of those days.
Do you have a timeframe for collecting the raw and finished water samples for the operating permit request?
Will that be after the chlorination flush?
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…15/23
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Kylie.Alejos <Kylie.Alejos@ticus.com>Tue, Oct 8, 2024 at 1:43 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>, David Heaton <dheaton@centralutahhealth.org>, Eric Larsen <elarsen@centralutahhealth.org>
Hello Dani,
Can you please give me a call when you have a chance? I have a few questions I would like to ask you before your visit
Thursday. I left you a voicemail this morning.
Kylie Alejos
269-235-0206
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Wednesday, September 25, 2024 2:07 PM
To: Kylie.Alejos <Kylie.Alejos@ticus.com>
Cc: Harrison.Stinson <Harrison.Stinson@kiewit.com>; jchartier@utah.gov; Paul.Novogoratz
<Paul.Novogoratz@kiewit.com>; Dustin.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR
<Lance.Batts-PTR@ticus.com>; Brittany.James <Brittany.James@kiewit.com>; Don.Smith-PTR <Don.Smith@ipsc.com>;
Andrew.Dutson-PTR <Andrew.Dutson@ipsc.com>; David Heaton <dheaton@centralutahhealth.org>; Eric Larsen
<elarsen@centralutahhealth.org>
Subject: Re: [External]Re: IPP Renewed Potable Water System
Hi Kylie,
I can make it down 10/9 or 10/10 in the afternoon around 3:30pm, I have meetings in the morning both days.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…16/23
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
[Quoted text hidden]
[Quoted text hidden]
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Tue, Aug 20, 2024 at 1:28 PM Danielle Zebelean <dzebelean@utah.gov> wrote:
Great!
I have availability September 30 to October 2. I can plan on October 1 around 1 pm?
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…17/23
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Tue, Aug 20, 2024 at 1:26 PM Harrison.Stinson <Harrison.Stinson@kiewit.com> wrote:
Dani,
Following up on our phone call. We will be best prepared to have you and John on site the week of Sept. 30th to
conduct a final walkdown of the system.
I will keep you posted if anything changes.
Best,
Harrison Stinson
Start Up Lead Field Engineer
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…18/23
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Tuesday, August 20, 2024 9:00 AM
To: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>; Dustin.Delozier-
PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR <Lance.Batts-PTR@ticus.com>; Brittany.James
<Brittany.James@kiewit.com>
Subject: Re: [External]Re: IPP Renewed Potable Water System
Hi Harrison,
I will be focusing on the new treatment plant and storage tank to verify they will pass a Sanitary Survey
Inspection. I've attached the question set below. Not everything will be applicable since some questions are about
ongoing operation and maintenance.
Please let me know if you have any further questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…19/23
On Mon, Aug 19, 2024 at 8:49 PM Harrison.Stinson <Harrison.Stinson@kiewit.com> wrote:
Dani,
As we prepare for your visit this week, is there anything specific you want out of this system walk or anything
you want prepared prior to your visit? Iso's, P&ID's, etc.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, July 29, 2024 4:15 PM
To: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dustin.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR <Lance.Batts-PTR@ticus.com>;
Brittany.James <Brittany.James@kiewit.com>
Subject: Re: [External]Re: IPP Renewed Potable Water System
Great! Thank you Harrison! I've added this to my calendar. Our district engineer, John Chartier, is also planning
on coming. I've also notified the Central Utah Health Department if they would like to join.
Thanks!
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…20/23
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jul 26, 2024 at 11:19 AM Harrison.Stinson <Harrison.Stinson@kiewit.com> wrote:
Danielle,
Sorry for just now getting back to you. After getting with my team, we can have you on site 8.22, 1pm would
be the preferable time.
For the water samples, we planned on collecting the samples after the chlorination flush to then send to the
lab for testing.
Best,
Harrison Stinson
Start Up Lead Field Engineer
TIC – The Industrial Company
(913)329-4223
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…21/23
Harrison.Stinson@ticus.com
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Thursday, July 18, 2024 6:44 AM
To: Harrison.Stinson <Harrison.Stinson@kiewit.com>
Cc: jchartier@utah.gov <jchartier@utah.gov>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Dustin.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Batts-PTR <Lance.Batts-
PTR@ticus.com>; Brittany.James <Brittany.James@kiewit.com>
Subject: [External]Re: IPP Renewed Potable Water System
Hi Harrison,
Thank you for the update. I would like to come conduct a final inspection on the facility. Right now I have
availability August 12, 13, 19, 20, 21, and 22. I would be able to make it to the plant around 11 am or later
any of those days.
Do you have a timeframe for collecting the raw and finished water samples for the operating permit request?
Will that be after the chlorination flush?
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…22/23
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Tue, Oct 8, 2024 at 1:52 PM
To: "Kylie.Alejos" <Kylie.Alejos@ticus.com>
Cc: "jchartier@utah.gov" <jchartier@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Dustin.Delozier-PTR"
<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "Brittany.James"
<Brittany.James@kiewit.com>, "Don.Smith-PTR" <Don.Smith@ipsc.com>, "Andrew.Dutson-PTR"
<Andrew.Dutson@ipsc.com>, David Heaton <dheaton@centralutahhealth.org>, Eric Larsen <elarsen@centralutahhealth.org>
Hi Kylie,
Apologies I am out on a survey today and haven’t listened to your voicemail yet. I can give you a call when I head back
this afternoon or evening.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
5/29/25, 11:54 AM State of Utah Mail - IPP Renewed Potable Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1804848143840798988&simpl=msg-f:1804848143840798…23/23
Danielle Zebelean <dzebelean@utah.gov>
Intermountain Power New Arsenic Treatment Plant OP Inspection
3 messages
Danielle Zebelean <dzebelean@utah.gov>Mon, Jul 29, 2024 at 4:15 PM
To: elarsen@centralutahhealth.org
Cc: John Chartier <jchartier@utah.gov>
Hi Eric,
I will be doing a final inspection of Intermountain Power's new arsenic treatment plant on August 22 at 1 pm if you would
like to join for that. No worries if not.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
Eric Larsen <elarsen@centralutahhealth.org>Mon, Aug 5, 2024 at 4:24 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: David Heaton <dheaton@centralutahhealth.org>, John Chartier <jchartier@utah.gov>
Hi Dani,
Thank you for the heads up! I will not be able to make it myself, but I have CC'd my EH Scientist for the area, David
Heaton, in case he is available and interested. I'll let him coordinate directly with you if he is interested.
Again, thank you for reaching out!
Eric Larsen, M.P.H., M.H.A., L.E.H.S.
Director of Environmental Health
Central Utah Health Department
70 Westview Drive, Richfield, UT 84701
435/896-5451 ext. 315
CentralUtahPublicHealth.org
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Tue, Aug 20, 2024 at 11:54 AM
5/29/25, 11:54 AM State of Utah Mail - Intermountain Power New Arsenic Treatment Plant OP Inspection
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-a:r-3705798155534338196&simpl=msg-a:r549966123279856…1/2
To: David Heaton <dheaton@centralutahhealth.org>, John Chartier <jchartier@utah.gov>
Cc: Eric Larsen <elarsen@centralutahhealth.org>
Hi David and John,
Just got off the phone with the consultant for the expansion at intermountain power. They are behind schedule and will not
be ready for a final inspection on Thursday. Harrison will let me know sometime next week when we can reschedule it to.
Thank you for your understanidng. Be in touch soon!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
5/29/25, 11:54 AM State of Utah Mail - Intermountain Power New Arsenic Treatment Plant OP Inspection
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-a:r-3705798155534338196&simpl=msg-a:r549966123279856…2/2
Danielle Zebelean <dzebelean@utah.gov>
IPP New Water System
12 messages
Trevor Johnson <Trevor.Johnson@ipsc.com>Thu, Oct 10, 2024 at 5:21 PM
To: "dzebelean@utah.gov" <dzebelean@utah.gov>
Hi Dani,
Thank you for coming down and inspecting the system this afternoon. I want to make sure I remember all the items that TIC needs to fix. The only things I wrote down were a screen onthe potable water tank air vent, and create and air gap on the tank drain and the UF system discharge line. Is there anything I forgot?
Thank You,
Trevor Johnson
Environmental Technical Analyst
INTERMOUNTAIN POWER SERVICE CORP.
A: 850 West Brush Wellman Road Delta, UT 84624
P: 435-864-6493
E: Trevor.Johnson@ipsc.com
IPSC CONFIDENTIALITY NOTICE
This e-mail transmission, and any documents, files or previous e-mail messages attached to it may contain information that is confidential or legally privileged. If you are not the intended
recipient, or a person responsible for delivering it to the intended recipient, you are hereby notified that you must not read this transmission and that any disclosure, copying, printing,distribution or use of any of the information contained in or attached to this transmission is STRICTLY PROHIBITED. If you have received this transmission in error, please immediately
notify the sender by telephone or return e-mail and delete the original transmission and its attachments without reading or saving in any manner. Thank you.
Danielle Zebelean <dzebelean@utah.gov>Thu, Oct 10, 2024 at 5:41 PMTo: Trevor Johnson <Trevor.Johnson@ipsc.com>
Hello!
Yes I also need to double check the approved plans on the finished water tank to see if it has an internal overflow or else that will need an exception as well. Also if the tank was originallysupposed to be inside there may be an issue with the exception for the hatch.
I’ll be able to look into that hopefully tomorrow or next week.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Fri, Oct 11, 2024 at 10:32 AMTo: Trevor Johnson <Trevor.Johnson@ipsc.com>
Cc: "Kylie.Alejos" <kylie.alejos@ticus.com>
Hi Trevor,
So from the drawings (pg. 723 of submittal) I assume one of the internal standpipes is the overflow. Whichever line coming out of the tank is the overflow line will also need the 12-inches
of clearance and a #4 screen. It looks like there is no access hatch on top so the exception for the shoebox style lid would still be valid. Can you confirm that there is not a hatch on top ofthe tank?
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…1/10
Please let me know if you have any follow up questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Fri, Oct 11, 2024 at 4:43 PMTo: Trevor Johnson <Trevor.Johnson@ipsc.com>
Also, sorry for forgetting to send with my other email earlier. David Kruse is the person who is overseeing inorganic monitoring. His email is dbkruse@utah.gov
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Kylie.Alejos <kylie.alejos@ticus.com>To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-P
Hello Dani,
Our team is looking to coordinate the final permitting of the water system. Based on your initial inspection I believe there were only a few minor actions required before we can obtain the permmade a note on page 615 of the Potable Water Permit Submittal (yellow highlight in snap below) regarding the <12” of separation for the overflow. This is not possible due to the overflow and
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…2/10
In your image below, the overflow is nozzle D2 (near the top of the tank), however, the design changed slightly since the application was submitted. The drawing for the final tank design is atta
internal riser). Additionally, I can confirm there is not a hatch on the top of the tank. Please confirm that this item is complete.
We are working on confirming the bird screens and will send over photos once we are able.
Kylie Alejos
269-235-0206
From: Danielle Zebelean <dzebelean@utah.gov>Sent: Friday, October 11, 2024 10:33 AM
To: Trevor Johnson <Trevor.Johnson@ipsc.com>Cc: Kylie.Alejos <kylie.alejos@ticus.com>
Subject: [External]Re: IPP New Water System
Hi Trevor,
So from the drawings (pg. 723 of submittal) I assume one of the internal standpipes is the overflow. Whichever line coming out of the tank is the overflow line will also need the 12-inches of clso the exception for the shoebox style lid would still be valid. Can you confirm that there is not a hatch on top of the tank?
Please let me know if you have any follow up questions.
Thanks!
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…3/10
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Thu, Oct 10, 2024 at 5:41 PM Danielle Zebelean <dzebelean@utah.gov> wrote:
Hello!
Yes I also need to double check the approved plans on the finished water tank to see if it has an internal overflow or else that will need an exception as well. Also if the tank was originally s
hatch.
I’ll be able to look into that hopefully tomorrow or next week.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Thu, Oct 10, 2024 at 5:21 PM Trevor Johnson <Trevor.Johnson@ipsc.com> wrote:
Hi Dani,
Thank you for coming down and inspecting the system this afternoon. I want to make sure I remember all the items that TIC needs to fix. The only things I wrote down were a screen on tdrain and the UF system discharge line. Is there anything I forgot?
Thank You,
Trevor Johnson
Environmental Technical Analyst
INTERMOUNTAIN POWER SERVICE CORP.
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…4/10
A: 850 West Brush Wellman Road Delta, UT 84624
P: 435-864-6493
E: Trevor.Johnson@ipsc.com
[Quoted text hidden]
20024113-94.03.72-000114.03.VDR.03.01 (3).pdf207K
Danielle Zebelean <dzebelean@utah.gov>To: "Kylie.Alejos" <kylie.alejos@ticus.com>
Cc: "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-P
Hi Kylie,
Sorry I must have also misunderstood Patrick's response to my review comment back in May 2023.
This will also require an exception that we can issue with the operating permit so that they do not get deficiencies during surveys. Please follow the process here to request an exception to thewater/exceptions-to-rule-requirements. The rules to reference are R309-545-13 and R309-545-10(d)
Also yes I confirm my comments about the hatch exception are complete.
Have a happy holiday!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
State of Utah Mail - IPP Renewed - Potable Water Permit.pdf449K
Paul.Novogoratz <Paul.Novogoratz@kiewit.com>To: Danielle Zebelean <dzebelean@utah.gov>, "ddwpnf@utah.gov" <ddwpnf@utah.gov>
Cc: "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-P
Dani,
Please see attached letter requesting the exception. I have also included ddwpnf@utah.gov on the “To” line as instructed in the link in your email below.
Please advise if anything else is needed.
Thanks,
Paul
PAUL NOVOGORATZ, P.E.
Mechanical Engineer
KIEWIT ENGINEERING GROUP INC.
8880 Penrose Lane., Lenexa, KS 66219
913-928-7000 Ext. 7443
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…5/10
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Friday, December 20, 2024 2:11 PMTo: Kylie.Alejos <kylie.alejos@ticus.com>
Cc: Paul.Novogoratz <Paul.Novogoratz@kiewit.com>; Cory.McCleary <Cory.McCleary@kiewit.com>; Logan.Green <Logan.Green@kiewit.com>; Dustin.Delozier-PTR <Dustin.Delozier-PTR@Subject: Re: [External]Re: IPP New Water System
Hi Kylie,
Sorry I must have also misunderstood Patrick's response to my review comment back in May 2023.
[Quoted text hidden]
[Quoted text hidden]
overflow_and_drain_exception_letter.pdf1001K
Paul.Novogoratz <Paul.Novogoratz@kiewit.com>To: Danielle Zebelean <dzebelean@utah.gov>, "ddwpnf@utah.gov" <ddwpnf@utah.gov>
Cc: "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-P
Dani,
Please see attached letter requesting the exception. I have also included ddwpnf@utah.gov on the “To” line as instructed in the link in your email below.
Please advise if anything else is needed.
Thanks,
Paul
PAUL NOVOGORATZ, P.E.
Mechanical Engineer
KIEWIT ENGINEERING GROUP INC.
8880 Penrose Lane., Lenexa, KS 66219
913-928-7000 Ext. 7443
From: Danielle Zebelean <dzebelean@utah.gov>Sent: Friday, December 20, 2024 2:11 PM
To: Kylie.Alejos <kylie.alejos@ticus.com>Cc: Paul.Novogoratz <Paul.Novogoratz@kiewit.com>; Cory.McCleary <Cory.McCleary@kiewit.com>; Logan.Green <Logan.Green@kiewit.com>; Dustin.Delozier-PTR <Dustin.Delozier-PTR@
Subject: Re: [External]Re: IPP New Water System
Hi Kylie,
Sorry I must have also misunderstood Patrick's response to my review comment back in May 2023.
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…6/10
[Quoted text hidden]
[Quoted text hidden]
drain_and_overflow_exception_letter.pdf1001K
Paul.Novogoratz <Paul.Novogoratz@kiewit.com>Fri, Jan 3, 2025 at 4:10 PMTo: DDW PNF <ddwpnf@utah.gov>, Danielle Zebelean <dzebelean@utah.gov>
Hello.
This is for the new potable water storage tank, tag number 9WSD-TNK-0001.
Thanks,
Paul
From: mnewberry@utah.gov <mnewberry@utah.gov> On Behalf Of DDW PNF
Sent: Friday, January 3, 2025 4:54 PMTo: Paul.Novogoratz <Paul.Novogoratz@kiewit.com>
Subject: Re: [External]Re: IPP New Water System
Paul, can you please verify which storage tank this exception request if for?
Thanks,
DDW PNF Team
Division of Drinking Water
Phone: (801) 536-4200
Fax: (801) 536-4211
drinkingwater.utah.gov
[Quoted text hidden]
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Mon, Jan 6, 2025 at 10:26 AMTo: "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Kylie.Alejos" <kylie.alejos@ticus.com>
Cc: "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR"<Lance.Batts-PTR@ticus.com>, John Chartier <jchartier@utah.gov>
Thank you Paul!
I will issue the exception with the operating permit. Is there an anticipated timeline for operating permit request?
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…7/10
On Fri, Jan 3, 2025 at 2:35 PM Paul.Novogoratz <Paul.Novogoratz@kiewit.com> wrote:
[Quoted text hidden]
Kylie.Alejos <kylie.alejos@ticus.com>To: Danielle Zebelean <dzebelean@utah.gov>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>
Cc: "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-P<Brittany.James@kiewit.com>, "Natalee.Brake" <Natalee.Brake@ticus.com>
Dani,
To follow up on both bullet points 2 & 3 listed on the Checklist for Issuing Operating Permits, please be advised there are no as-built changes to the system drawings thatyou require additional documentation or if we can progress forward with these two requirements satisfied.
Additionally, during your site walk we discussed the need to clarify that the overflow and drain for the Potable Water Tank had a bird screens installed. Please see the attasufficient.
Finally, to answer your previous question on timeline, we intend to chlorinate the system, perform required testing, and submit final documentation for the operating perm
Please let me know if you have any questions or if you require additional documentation.
Kylie Alejos
269-235-0206
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, January 6, 2025 10:27 AM
To: Paul.Novogoratz <Paul.Novogoratz@kiewit.com>; Kylie.Alejos <kylie.alejos@ticus.com>
Cc: Cory.McCleary <Cory.McCleary@kiewit.com>; Logan.Green <Logan.Green@kiewit.com>; Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Lance.Ba s-PTR <Lance.
Subject: Re: [External]Re: IPP New Water System
Thank you Paul!
I will issue the exception with the operating permit. Is there an anticipated timeline for operating permit request?
Dani Zebelean, P.E.
Environmental Engineer III | Division of DrinkingWater
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jan 3, 2025 at 2:35 PM Paul.Novogoratz <Paul.Novogoratz@kiewit.com> wrote:
Dani,
Please see attached letter requesting the exception. I have also included ddwpnf@utah.gov on the “To” line as instructed in the link in your email below.
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…8/10
Please advise if anything else is needed.
Thanks,
Paul
PAUL NOVOGORATZ, P.E.
Mechanical Engineer
KIEWIT ENGINEERING GROUP INC.
8880 Penrose Lane., Lenexa, KS 66219
913-928-7000 Ext. 7443
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Friday, December 20, 2024 2:11 PMTo: Kylie.Alejos <kylie.alejos@ticus.com>
Cc: Paul.Novogoratz <Paul.Novogoratz@kiewit.com>; Cory.McCleary <Cory.McCleary@kiewit.com>; Logan.Green <Logan.Green@kiewit.com>; Dustin.Delozier-PTR <Dustin.Delozier-PTSubject: Re: [External]Re: IPP New Water System
Hi Kylie,
Sorry I must have also misunderstood Patrick's response to my review comment back in May 2023.
This will also require an exception that we can issue with the operating permit so that they do not get deficiencies during surveys. Please follow the process here to request an exception to water/exceptions-to-rule-requirements. The rules to reference are R309-545-13 and R309-545-10(d)
Also yes I confirm my comments about the hatch exception are complete.
Have a happy holiday!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
[Quoted text hidden]
[Quoted text hidden]
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:18125710593502622…9/10
2 attachments
IMG_0880.jpg1382K
IMG_2435.jpg
2120K
Danielle Zebelean <dzebelean@utah.gov>Fri, Jan 31, 2025 at 12:05 PMTo: "Kylie.Alejos" <kylie.alejos@ticus.com>
Cc: "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>, "Cory.McCleary" <Cory.McCleary@kiewit.com>, "Logan.Green" <Logan.Green@kiewit.com>, "Dustin.Delozier-PTR"<Dustin.Delozier-PTR@kiewit.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, John Chartier <jchartier@utah.gov>, "Brittany.James" <Brittany.James@kiewit.com>,
"Natalee.Brake" <Natalee.Brake@ticus.com>
Thank you Kylie,
The pictures attached are sufficient to show those are taken care of.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
5/29/25, 11:55 AM State of Utah Mail - IPP New Water System
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1812571059350262242&simpl=msg-f:1812571059350262…10/10
Danielle Zebelean <dzebelean@utah.gov>
IPP Renewed New Water System - Water Quality Data & Chlorination
8 messages
Kylie.Alejos <Kylie.Alejos@ticus.com>Thu, Apr 17, 2025 at 3:21 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>,
"Scott.Blair" <Scott.Blair@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Natalee.Brake"
<Natalee.Brake@ticus.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "jchartier@utah.gov" <jchartier@utah.gov>,
"Cory.McCleary" <Cory.McCleary@kiewit.com>
Dani,
Please see the attached Water Quality Data and Sample Reporting for the chlorination and testing of the new potable
water system at the IPP Renewed Power Project.
Our understanding is that this should be the final portion of the operating permit submittal for the system. Just a reminder,
TIC is the General Contractor for the project and has placed the system in service. However, IPP is the end user, and the
operating permit will only belong to them.
Let me know if there is anything else that you need from us at this time.
Thanks,
Kylie Alejos
Startup Lead Field Engineer
IPP Renewed
TIC – The Industrial Company
Cell: (269) 235-0206
IPP Potable Water Operating Permit Sample Results.pdf
6483K
Danielle Zebelean <dzebelean@utah.gov>Thu, Apr 17, 2025 at 3:27 PM
To: David Kruse <dbkruse@utah.gov>
5/29/25, 11:55 AM State of Utah Mail - IPP Renewed New Water System - Water Quality Data & Chlorination
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1829686351481044038&simpl=msg-f:182968635148104403…1/6
See attached analysis results for the IPP (#14050) new arsenic removal treatment plant. Let me know if you have any
questions!
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
IPP Potable Water Operating Permit Sample Results.pdf
6483K
Danielle Zebelean <dzebelean@utah.gov>Mon, Apr 21, 2025 at 8:49 PM
To: "Kylie.Alejos" <Kylie.Alejos@ticus.com>
Cc: "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>,
"Scott.Blair" <Scott.Blair@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Natalee.Brake"
<Natalee.Brake@ticus.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "jchartier@utah.gov" <jchartier@utah.gov>,
"Cory.McCleary" <Cory.McCleary@kiewit.com>
Thank you Kylie,
I am waiting on our source inorganics manager to confirm the arsenic sampling results. Another thing to note, we’ve
changed our exception request process since the request was sent in. I will fill out the form with the information provided
previously and send to IPP for approval.
I am in St. George for the WEAU conference and sanitary surveys this week but I believe I’ll have time to get that handled
in between.
Please let me know if you have any questions.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Cory.McCleary <Cory.McCleary@kiewit.com>Fri, May 2, 2025 at 8:00 AM
To: Danielle Zebelean <dzebelean@utah.gov>
5/29/25, 11:55 AM State of Utah Mail - IPP Renewed New Water System - Water Quality Data & Chlorination
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1829686351481044038&simpl=msg-f:182968635148104403…2/6
You don't often get email from dzebelean@utah.gov. Learn why this is important
Cc: "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>,
"Scott.Blair" <Scott.Blair@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Natalee.Brake"
<Natalee.Brake@ticus.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "jchartier@utah.gov" <jchartier@utah.gov>
Good morning Dani,
Kylie has been assigned to a new project and I will be supporting the efforts of getting the potable water
permit from this point forward.
Has there been further progression on the permit, and/or do you need anything else from me or my team to
ensure this permit is completed?
Thanks,
Cory McCleary
Resident Mechanical Engineer
IPP Renewed
Work: 913-928-7660
Cell: 402-676-1683
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, April 21, 2025 8:50 PM
To: Kylie.Alejos <Kylie.Alejos@ticus.com>
Cc: Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Sco .Blair <Scott.Blair@kiewit.com>; Bri any.James <Brittany.James@kiewit.com>; Natalee.Brake
<Natalee.Brake@ticus.com>; Lance.Ba s-PTR <Lance.Batts-PTR@ticus.com>; jchartier@utah.gov;
Cory.McCleary <Cory.McCleary@kiewit.com>
Subject: [External]Re: IPP Renewed New Water System - Water Quality Data & Chlorina on
Thank you Kylie,
I am waiting on our source inorganics manager to confirm the arsenic sampling results. Another thing to note, we’ve
changed our exception request process since the request was sent in. I will fill out the form with the information provided
previously and send to IPP for approval.
I am in St. George for the WEAU conference and sanitary surveys this week but I believe I’ll have time to get that handled
in between.
Please let me know if you have any questions.
Thanks!
5/29/25, 11:55 AM State of Utah Mail - IPP Renewed New Water System - Water Quality Data & Chlorination
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1829686351481044038&simpl=msg-f:182968635148104403…3/6
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking
Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Fri, May 2, 2025 at 4:19 PM
To: "Cory.McCleary" <Cory.McCleary@kiewit.com>
Cc: "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>,
"Scott.Blair" <Scott.Blair@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Natalee.Brake"
<Natalee.Brake@ticus.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "jchartier@utah.gov" <jchartier@utah.gov>
Hi Cory!
Sorry it’s been a busy two weeks for me. I need to fill out a new exception request form then send that to IPP to sign.
Kylie has gotten me everything needed I believe for the operating permit.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Mon, May 5, 2025 at 8:55 AM
To: David Kruse <dbkruse@utah.gov>
Here you go! Back to the top!
[Quoted text hidden]
5/29/25, 11:55 AM State of Utah Mail - IPP Renewed New Water System - Water Quality Data & Chlorination
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1829686351481044038&simpl=msg-f:182968635148104403…4/6
You don't often get email from dzebelean@utah.gov. Learn why this is important
IPP Potable Water Operating Permit Sample Results.pdf
6483K
Cory.McCleary <Cory.McCleary@kiewit.com>Wed, May 7, 2025 at 11:38 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>,
"Scott.Blair" <Scott.Blair@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Natalee.Brake"
<Natalee.Brake@ticus.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "jchartier@utah.gov" <jchartier@utah.gov>
Good morning Dani,
I hope you're doing well! I just wanted to follow up to see if you’ve had a chance to submit the exception
request form. Please don’t hesitate to reach out if there’s anything I can do to support the process.
We do have some pending work that depends on the permit being finalized, so I appreciate any updates
you can share.
Thank you again for your help!
Cory McCleary
Resident Mechanical Engineer
IPP Renewed
Work: 913-928-7660
Cell: 402-676-1683
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Friday, May 2, 2025 4:19 PM
To: Cory.McCleary <Cory.McCleary@kiewit.com>
Cc: Dus n.Delozier-PTR <Dustin.Delozier-PTR@kiewit.com>; Paul.Novogoratz <Paul.Novogoratz@kiewit.com>;
Sco .Blair <Scott.Blair@kiewit.com>; Bri any.James <Brittany.James@kiewit.com>; Natalee.Brake
<Natalee.Brake@ticus.com>; Lance.Ba s-PTR <Lance.Batts-PTR@ticus.com>; jchartier@utah.gov
Subject: Re: [External]Re: IPP Renewed New Water System - Water Quality Data & Chlorina on
Hi Cory!
Sorry it’s been a busy two weeks for me. I need to fill out a new exception request form then send that to IPP to sign.
Kylie has gotten me everything needed I believe for the operating permit.
5/29/25, 11:55 AM State of Utah Mail - IPP Renewed New Water System - Water Quality Data & Chlorination
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1829686351481044038&simpl=msg-f:182968635148104403…5/6
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking
Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
[Quoted text hidden]
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Wed, May 7, 2025 at 11:51 AM
To: "Cory.McCleary" <Cory.McCleary@kiewit.com>
Cc: "Dustin.Delozier-PTR" <Dustin.Delozier-PTR@kiewit.com>, "Paul.Novogoratz" <Paul.Novogoratz@kiewit.com>,
"Scott.Blair" <Scott.Blair@kiewit.com>, "Brittany.James" <Brittany.James@kiewit.com>, "Natalee.Brake"
<Natalee.Brake@ticus.com>, "Lance.Batts-PTR" <Lance.Batts-PTR@ticus.com>, "jchartier@utah.gov" <jchartier@utah.gov>
Hi Cory,
I sent the form to Trevor yesterday to be signed. Our inorganics manager also let me know yesterday that the arsenic
samples were acceptable.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
5/29/25, 11:55 AM State of Utah Mail - IPP Renewed New Water System - Water Quality Data & Chlorination
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1829686351481044038&simpl=msg-f:182968635148104403…6/6
Danielle Zebelean <dzebelean@utah.gov>
New Exception Form for Renewed Units 3&4 Storage
4 messages
Danielle Zebelean <dzebelean@utah.gov>Tue, May 6, 2025 at 4:27 PM
To: Trevor Johnson <Trevor.Johnson@ipsc.com>
Cc: John Chartier <jchartier@utah.gov>
Hi Trevor,
Can you or whoever else needs to sign this exception request do so and send it back to me? This is for the request that
was submitted back in January but we were waiting on the operating permit to issue it. Unfortunately, since then we
changed our exception process. I've filled out the form using the information in the letter, feel free to change it as needed.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
2 attachments
Exception Request R309-545-13.pdf
1001K
13556 Exception Request R309-545-13 R309-545-10(1)(d).pdf
1320K
Trevor Johnson <Trevor.Johnson@ipsc.com>Tue, May 6, 2025 at 4:41 PM
To: Danielle Zebelean <dzebelean@utah.gov>
I’m out of the office today Dani, but I’ll try getting it signed by someone and get it back to you tomorrow.
Trevor Johnson
Sent from my iPhone
On May 6, 2025, at 4:30 PM, Danielle Zebelean <dzebelean@utah.gov> wrote:
[Quoted text hidden]
<Exception Request R309-545-13.pdf>
<13556 Exception Request R309-545-13 R309-545-10(1)(d).pdf>
IPSC CONFIDENTIALITY NOTICE
5/29/25, 11:55 AM State of Utah Mail - New Exception Form for Renewed Units 3&4 Storage
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-a:r-6130884693377870705&simpl=msg-a:r641970184856953…1/3
This e-mail transmission, and any documents, files or previous e-mail messages attached to it may contain information
that is confidential or legally privileged. If you are not the intended recipient, or a person responsible for delivering it to the
intended recipient, you are hereby notified that you must not read this transmission and that any disclosure, copying,
printing, distribution or use of any of the information contained in or attached to this transmission is STRICTLY
PROHIBITED. If you have received this transmission in error, please immediately notify the sender by telephone or return
e-mail and delete the original transmission and its attachments without reading or saving in any manner. Thank you.
Trevor Johnson <Trevor.Johnson@ipsc.com>Thu, May 8, 2025 at 4:07 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: John Chartier <jchartier@utah.gov>
Hi Dani,
TIC is looking into adding an airgap, so this may be a non-issue. As of right now we are not going to be signing this. Let
me know if you have any other questions or concerns.
Thank You,
Trevor Johnson
Environmental Supervisor
INTERMOUNTAIN POWER SERVICE CORP.
A: 850 West Brush Wellman Road Delta, UT 84624
P: 435-864-6493
E: Trevor.Johnson@ipsc.com
[Quoted text hidden]
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Thu, May 8, 2025 at 4:16 PM
To: Trevor Johnson <Trevor.Johnson@ipsc.com>
Cc: John Chartier <jchartier@utah.gov>
Thank you Trevor,
However, I can't issue the operating permit unless this exception goes through. I am ok to wait on it if you want to add to
an air gap before the operating permit. The other option is to sign it, get the operating permit, then we can resolve the
exception once the air gap is there.
Let me know what you want to do.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
5/29/25, 11:55 AM State of Utah Mail - New Exception Form for Renewed Units 3&4 Storage
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-a:r-6130884693377870705&simpl=msg-a:r641970184856953…2/3
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
5/29/25, 11:55 AM State of Utah Mail - New Exception Form for Renewed Units 3&4 Storage
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-a:r-6130884693377870705&simpl=msg-a:r641970184856953…3/3
Danielle Zebelean <dzebelean@utah.gov>
IPSC Drinking Water permit
2 messages
Trevor Johnson <Trevor.Johnson@ipsc.com>
To: Danielle Zebelean <dzebelean@utah.gov>
Hi Dani, here are the pictures of the air gap and the screen on the pipe. Let me know if you need anything else. Thank you for all your help.
Thank You,
Trevor Johnson
Environmental Supervisor
INTERMOUNTAIN POWER SERVICE CORP.
A: 850 West Brush Wellman Road Delta, UT 84624
P: 435-864-6493
E: Trevor.Johnson@ipsc.com
5/29/25, 11:55 AM State of Utah Mail - IPSC Drinking Water permit
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1833397658191226250&simpl=msg-f:183339765819122625…1/3
IPSC CONFIDENTIALITY NOTICE
This e-mail transmission, and any documents, files or previous e-mail messages attached to it may contain information that is confidential or legally privileged. If you are not the intended recip
copying, printing, distribution or use of any of the information contained in or attached to this transmission is STRICTLY PROHIBITED. If you have received this transmission in error, please imyou.
Danielle Zebelean <dzebelean@utah.gov>Wed, May 28, 2025 at 3:12 PM
To: Trevor Johnson <Trevor.Johnson@ipsc.com>Cc: John Chartier <jchartier@utah.gov>
Excellent! Thank you Trevor!
5/29/25, 11:55 AM State of Utah Mail - IPSC Drinking Water permit
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1833397658191226250&simpl=msg-f:183339765819122625…2/3
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]