HomeMy WebLinkAboutDERR-2025-003997005
Stormwater catch basin and manhole access. Stormwater curbing. Looks low but they checked 2 or 3 times.
theCollaborative 4350
4350 S 900 East,
Millcreek, Utah 84124
Report number: 005
Date: November 18, 2024 10:00
Site Conditions: Temperature - 48 degrees and sunny
Field Report - 4350 S 900 East
Project Status
Met with Juan & Duane (LL&L) regarding the excavation. As they progress with building A and B footing excavation they have not
found questionable soils or concerns for further inspections.
Met with RMP thinks we should have boxes and transformers onsite this week by 11/21.
Met with JCorp to discuss completion of and responsibility of horizontals between both groups and timing.
Site Observations
● All soils are being retained onsite as excavation continues from West to East.
● Clearing up a little confusion between Public Utilities and their engineers. RMP and Lumens is close to being removed from the
site.
Stormwater curbing. Looks low but they checked 2 or 3 times. Conduit to power Matt Strong's project being completed.
Manhole at southwest corner of site.