Report number: 003
Date: August 5, 2024 12:00
Site Conditions: Temperature - 94 degrees and sunny
Field Report - 4350 S 900 East
Project Status
Clearing and grubbing is complete. All existing fencing has been removed and construction fencing has been placed.
Excavation has begun on StormTek system. The excavator LL&L has provided proof of their Osha Hazwoper certificate#240837. They
understand they must carefully monitor the soils and notify us and Wasatch Enviromental if contaminated soils are found.
Site Observations
● All remaining debris has been removed from site.
● Track-out pad has been installed and gate has been moved. All BMPs have been placed.
Temp fencing has been placed throughout. Excavation has begun on southwest corner.
StormTek is being dug. StormTek is being dug.
Stockpiling dirt on site from excavation. Lot has been completely cleared of debris.
Trackout pad has been installed. Lot is clean and ready for new construction.
Trackout pad installed using city rocks. Trackout pad installed using city rocks.
StormTek is being dug. Site has been surveyed and stakes have been placed.
Only a small amount of metal remains onsite for removal. Jobsite looks clean and ready for new construction.