HomeMy WebLinkAboutDAQ-2025-002524Chad Gilgen <cgilgen@utah.gov>
Hawley Rock
Chad Gilgen <cgilgen@utah.gov>Fri, May 23, 2025 at 9:32 AM
To: Bryant Bunnell <bwbunnell@hotmail.com>
Hello Bryant,
Thanks for that additional information and your planned suggestions for Hawley Rock. I think that sounds good and
covers everything for now. I'll make a note here for future inspections to confirm the status of this generator engine to
ensure compliance with the Approval Order.
Thanks,
Chad
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
On Fri, May 23, 2025 at 7:36 AM Bryant Bunnell <bwbunnell@hotmail.com> wrote:
Hi Chad,
It's my understanding that the generator hasn't been operated since the issuance of the new Approval Order. While
the generator remains on-site, I will advise them to consider its removal. Currently, no lockout devices are installed,
however if they opt to retain the generator, I will recommend them adding a lockout mechanism. I'll also
recommend adding clear signage to indicate its inoperable status and documen ng these measures in the
maintenance records.
Let me know if you require addi onal details or specific ac ons to verify compliance. I'll make sure to pass this
informa on along.
Thanks,
Bryant
From: Chad Gilgen <cgilgen@utah.gov>
Sent: Thursday, May 22, 2025 11:45 AM
To: Bryant Bunnell <bwbunnell@hotmail.com>
Subject: Re: Hawley Rock
Hello Bryant,
Thanks for the update. Has this generator engine been removed from the source location? If not, are there plans to
remove it or permanently lock it out so it cannot be used? Was it ever used after the new Approval Order was issued?
It would probably be best for Hawley Rock to remove this engine from their Approval Order at some point in the future
when modifying the AO for other purposes (adding new equipment, increasing production limits, etc.) but, if it's not in
5/23/25, 9:32 AM State of Utah Mail - Hawley Rock
https://mail.google.com/mail/u/0/?ik=36f4379b4d&view=pt&search=all&permmsgid=msg-a:r3114453573269354344&dsqt=1&simpl=msg-a:r311445357…1/4
REVIEWED
Initials: CG Date: 5-23-25
Compliance Status: II.A.26 Engine Status Correspondence
File # 12066 (B1)
use and will not be used going forward, then it's probably alright for now.
Thanks,
Chad
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
On Thu, May 8, 2025 at 9:19 AM Bryant Bunnell <bwbunnell@hotmail.com> wrote:
Hey Chad,
I've been working with Hawley Rock on this stack test requirement, and they've ul mately decided to not use the
400 kW/500 HP (II.A.26 of Approval Order DAQE-AN120660006-24) generator for their opera on. They've been
on the fence the past few months but un mately decided to exclude it. I'm not sure what the path forward is
regarding this? Does this no fica on to you suffice? Or do we need to modify their permit?
As always thanks for your help,
Bryant
From: Chad Gilgen <cgilgen@utah.gov>
Sent: Friday, March 7, 2025 12:58 PM
To: Bryant Bunnell <bwbunnell@hotmail.com>
Subject: Re: Hawley Rock
Hi Bryant,
That sounds great. Thanks for the update.
Chad
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
On Wed, Mar 5, 2025 at 1:53 PM Bryant Bunnell <bwbunnell@hotmail.com> wrote:
Hey Chad,
Thanks for the follow up. The company we were going to use has filled in their schedule for the next few months.
I've been looking for another option without any luck. I'll try and solidify a testing date this week and get back to
you.
Thanks,
5/23/25, 9:32 AM State of Utah Mail - Hawley Rock
https://mail.google.com/mail/u/0/?ik=36f4379b4d&view=pt&search=all&permmsgid=msg-a:r3114453573269354344&dsqt=1&simpl=msg-a:r311445357…2/4
Bryant
Sent from my Verizon, Samsung Galaxy smartphone
Get Outlook for Android
From: Chad Gilgen <cgilgen@utah.gov>
Sent: Thursday, February 27, 2025 4:13:07 PM
To: Bryant Bunnell <bwbunnell@hotmail.com>
Subject: Re: Hawley Rock
Hello Bryant,
Any update on the stack test at Hawley Rock?
Thanks,
Chad
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
On Tue, Feb 11, 2025 at 2:30 PM Bryant Bunnell <bwbunnell@hotmail.com> wrote:
Hey Chad,
No worries, I need to follow up with the tes ng company we're working with and ask about the 30-day
no fica on and see if they s ll have us on their schedule.
I will give you an update shortly.
Thanks,
Bryant
From: Chad Gilgen <cgilgen@utah.gov>
Sent: Tuesday, February 11, 2025 12:23 PM
To: Bryant Bunnell <bwbunnell@hotmail.com>
Subject: Re: Hawley Rock
Hello Bryant,
Sorry for taking a while to get back to you. Jared did not have any other notes regarding the inspection. The
only open issue is the stack test. Your previous email indicated testing was being scheduled for February. What
is the status of that planned stack test?
For reference, all stack tests require notification to the Utah Division of Air Quality at least 30 days prior to the
test. The pretest protocol for the test needs to be submitted via the online portal at https://deq.utah.gov/air-
quality/stationary-source-compliance and choosing the "Submit Minor Stack Test Protocol/Report" tab in the
middle of the page. Results are to be submitted within 60 days of testing using the same process.
Thanks and please let me know if you have any additional questions.
Chad
5/23/25, 9:32 AM State of Utah Mail - Hawley Rock
https://mail.google.com/mail/u/0/?ik=36f4379b4d&view=pt&search=all&permmsgid=msg-a:r3114453573269354344&dsqt=1&simpl=msg-a:r311445357…3/4
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
On Mon, Jan 13, 2025 at 6:44 AM Bryant Bunnell <bwbunnell@hotmail.com> wrote:
Hi Chad,
I apologize for the delayed response. Your email was inadvertently missed, but I came across it while
looking to reach out to Jared. Thank you for the update.
We had scheduled a company to perform a stack test on the generator. However, they have postponed
their tes ng several mes, and the current schedule is now set for February. I have reached out to several
other companies to see if we can expedite the tes ng and I'm wai ng to hear back.
Does Jared have any addi onal notes on other outstanding ac ons concerning that inspec on? I want to
make sure we get all the info you need. Feel free to call my cell (below) if necessary.
Thanks,
Bryant
435-201-3366
From: Chad Gilgen <cgilgen@utah.gov>
Sent: Thursday, December 19, 2024 3:45 PM
To: bwbunnell@hotmail.com <bwbunnell@hotmail.com>
Subject: Hawley Rock
Hello Bryant,
I am reaching out to you regarding Hawley Rock in Elsinore, Utah. See the attached Approval Order for this
site.
Previously, you have corresponded with Jared James regarding an inspection that was conducted here in
August 2024. Jared is no longer with the Minor Source group and I wanted to check in on the status of stack
testing for the 400 kW/500 HP (II.A.26 of Approval Order DAQE-AN120660006-24) generator engine? Jared
indicated in his memo that this was being scheduled with you.
Thanks,
Chad
Chad Gilgen | Manager | Minor Source Compliance
385-306-6500 (cell)
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA requirements.
5/23/25, 9:32 AM State of Utah Mail - Hawley Rock
https://mail.google.com/mail/u/0/?ik=36f4379b4d&view=pt&search=all&permmsgid=msg-a:r3114453573269354344&dsqt=1&simpl=msg-a:r311445357…4/4