Loading...
HomeMy WebLinkAboutDERR-2025-003633VCP/Brownfields Section - Site Visit Report SITE NAME: Airport West / North Temple Landfill SITE LOCATION: Salt Lake City DATE OF SITE VISIT: 8 May 2025 PURPOSE OF SITE VISIT: DERR (David Bird) oversight of field activities at the Airport West VCP site. FIELD OBSERVATIONS: At ~1:30 pm, the DERR met with Stantec (Shauna and David Cline) at the western site boundary. Stantec was in the process of collecting groundwater samples from the P3-S well. The sampling was proceeding according to the accepted SAP. At ~2:15 pm, the DERR met with Stantec (Casey) at piezometer P8. Sampling appeared to be going well. At ~ 3 pm, the DERR met UIPA’s contractor, Ninigret (Gary McEntee & Eric Rice) at the site to discuss how preparations for beginning remediation of Phase I at the site is coming along. Mobilization of the excavation contractor is expected to begin the week of May 12th. Construction of the WAIV unit at the leachate processing ponds is progressing, with a framework for the evaporation sails mostly complete. The WAIV system for evaporation of leachate is expected to be operational by the end of May 2025. The piles of crushed concrete (roadbase) in the southwest portion of the site have grown, and are reported to total approximately 160,000 tons. The processing is expected to be complete by the end of May 2025, with an expected total of 220,000 tons. Ninigret and the DERR discussed the schedule for the excavation of material from the waste cells of the landfill in Phase I. This is expected to commence near the end of May 2025, with excavation of the 25 foot buffer zone and dewatering of landfill cells in the footprint of the future repository to be among the first actions. The DERR left the site at ~4:00 pm. SPLIT SAMPLES COLLECTED: No IS THE WORK BEING PERFORMED IN A MANNER CONSISTENT WITH THE ACCEPTED WORKPLAN? Yes Looking east at piezometer P8 on an area to the west of the Airport West site. Sample collection was underway. Looking southwest at the leachate pond where the WAIV (evaporation) unit is to be installed. The walkway is mostly complete and the framework for the evaporation sails is under construction. Looking southwest at a secondary pile of crushed concrete. This pile is estimated at 80,000 tons, and the original pile to the east is estimated at 80,000 tons.