HomeMy WebLinkAboutDERR-2025-003520Utah Department of Environmental Quality - UST Release Detection
TANK OWNERSHIP
Name GREEN VALLEY GAS
Address 280 N MAIN
MONROE, UT 84754
Contact GREEN VALLEY GAS
Phone
Email GREENVALLEYGASINC@GMAIL.COM
TANK LOCATION
Name GREEN VALLEY GAS
Address 280 N MAIN ST
MONROE, UT 84754
A Operator None
Phone None
B Operator SAME
Phone SAME
Facility ID: 2000097 Inspection Date: 05/01/2025
DISPENSER DETAILS
DISP
ID/ALT
ID
SUBSTANCE UDC PIPE FLEX LOC
INSTALL
DATE
UDC
INSTALL
DATE
FIRE
VALVE
SAT
PRESENT
UDC
TEST
DISP
FLEX
CP
TEST
1 - 1/2 Yes Steel Flex in Sump Jan. 1,
1992
None Yes No None None
TANK DETAILS
Tank ID/Alt ID 3 / 3A
E-Gen/AST No / Yes
Siphon/Compart No / Yes
Tank Status Currently In Use
Installed/Cap/Loc Jan. 1, 1992 / 4000 /
Substance
Stored Gasoline / Regular
Tank Material-
Mod
Asphalt Coated or Bare Steel-
None
ATG /
LTT Test None
LLD Test None
Pipe Material-Mod Not Listed / None
Pipe type/STP Cont Pressurized / No
STP Flex Connectors
LLD Model
Spill/Overfill/Sm
Delivery 5 gal. Spill Bucket / / No
PST Fund/Other
Type No / None
Tank/Pipe Rel Det TankLDNotListed
PipeLineTightness
CP Tank Test None
CP Pipe Test None
Tank ID/Alt ID 4 / 4B
E-Gen/AST No / Yes
Siphon/Compart No / Yes
Tank Status Currently In Use
Installed/Cap/Loc Jan. 1, 1992 / 2000 /
Substance
Stored Gasoline / Non-Ethanol
Tank Material-
Mod
Asphalt Coated or Bare Steel-
None
ATG /
LTT Test None
LLD Test None
Pipe Material-Mod Not Listed / None
Pipe type/STP Cont Pressurized / No
STP Flex Connectors
LLD Model
Spill/Overfill/Sm
Delivery 5 gal. Spill Bucket / / No
PST Fund/Other
Type No / None
Tank/Pipe Rel Det TankLDNotListed
PipeLineTightness
CP Tank Test None
CP Pipe Test None
2025-05-01 Page 1 of 4
Tank ID/Alt ID 5 / 5
E-Gen/AST No / Yes
Siphon/Compart No / No
Tank Status Currently In Use
Installed/Cap/Loc Jan. 1, 1910 / 900 /
Substance Stored Diesel / Diesel #2 (U.L.S.)
Tank Material-Mod Asphalt Coated or Bare Steel-
ATG /
LTT Test None
LLD Test None
Pipe Material-Mod None / None
Pipe type/STP Cont / No
STP Flex Connectors
LLD Model
Spill/Overfill/Sm
Delivery / / No
PST Fund/Other
Type No / None
Tank/Pipe Rel Det TankLDNotListed
PipeLineTightness
CP Tank Test None
CP Pipe Test None
INSPECTION COMMENTS
None
2025-05-01 Page 2 of 4
FACILITY RESPONSES
The above accurately represents the
facility's release detection records Yes
Financial Responsibility
Financial responsibility method is ok?No
TANK RESPONSES
Tank 3A Pressure Piping Leak Detection
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
No
Tank 4B Pressure Piping Leak Detection
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
No
Tank 3A Spill/Overfill
Tank has a spill prevention device?No
Tank 4B Spill/Overfill
Tank has a spill prevention device?No
Tank 5 Spill/Overfill
Tank has a spill prevention device?No
DISPENSER RESPONSES
Dispenser 1/2
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
MONTHLY LEAK DETECTION MONITORING
May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25 Apr '25
Tank 3 Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Tank 4 Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Tank 5 Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
NON-COMPLIANCE ITEMS
TANK 3A
No Photos
Question:Tank has a spill prevention device?
Comments:None
TANK 3A
No Photos
Question:Does the pressurized piping system have a valid annual line tightness test or valid monthly
monitoring?
Comments:None
TANK 4B
No Photos
Question:Tank has a spill prevention device?
Comments:None
TANK 4B
No Photos
2025-05-01 Page 3 of 4
Prepared by fueloperator.com
Question:Does the pressurized piping system have a valid annual line tightness test or valid monthly
monitoring?
Comments:None
TANK 5
No Photos
Question:Tank has a spill prevention device?
Comments:None
FACILITY
No Photos
Question:Financial responsibility method is ok?
Comments:None
Inspection Information
Inspector:Warner, Sean
Record Created:May 1, 2025, 2:06 p.m.
Inspection Date:May 1, 2025
2025-05-01 Page 4 of 4