HomeMy WebLinkAboutDAQ-2024-010584
Small Source Registration
DAQE-EN121340003-24
{{$d1 }}
Cecil Prewitt
Shriners Children’s
1275 East Fairfax Road
Salt Lake City, UT 84103
cprewitt@shrinenet.org
Dear Cecil Prewitt:
Re: Request for Evaluation of Compliance with Rule R307-401-9, UAC: Small Source Exemption
Project Fee Code: N121340003
On August 22, 2024, the Division of Air Quality (DAQ) received your request for a small source
exemption for Shriners Children's. The source is located at 1275 East Fairfax Road, in Salt Lake City, Salt Lake County. DAQ has determined the small source exemption applies to the source, as long as the
equipment and associated processes operate as specified in the registration request.
The small source exemption does not exempt a source from complying with other applicable federal,
state, and local regulations and the current Utah Administrative Code. Based on the emissions that you
submitted to DAQ with your registration request, Shriners Children's Medical Clinic is not required to
obtain an approval order under R307-401. If you change your operation such that there is an increase in
emissions, we recommend that you notify us, as an approval order may be required.
As authorized by the Utah Legislature, the fee for issuing this small source exemption is a one-time filing
fee in addition to the actual time spent by the review engineer and all other staff on the project. Payment
should be sent to DAQ upon receipt of the invoice.
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144820 • Salt Lake City, UT 84114-4820
Telephone (801) 536-4000 • Fax (801) 536-4099 • T.D.D. (801) 903-3978
www.deq.utah.gov
Printed on 100% recycled paper
State of Utah
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF AIR QUALITY
Bryce C. Bird
Director
2 $ 2 0 1 Û á Û Ù Û Ý
DAQE-EN121340003-24
Page 2
Thank you for registering your source with the DAQ. If you have any additional questions, please contact
Dungan Adams at (385) 290-2474 or dunganadams@utah.gov.
Sincerely,
Bryce C. Bird
Director
{{$s }}
Alan D. Humpherys, Manager
New Source Review Section
BCB:ADH:DA:jg
{{#d1=date1_es_:signer1:date:format(date, "mmmm d, yyyy")}} {{#s=Sig_es_:signer1:signature}}
DAQC-035-22
Site ID 12134 (B1)
MEMORANDUM
TO: FILE — SHRINERS HOSPITAL FOR CHILDREN
THROUGH: Rik Ombach, Minor Source Compliance Section Manager 6:7)
FROM: Irene Tucker, Environmental Scientist
DATE: January 5, 2022
SUBJECT: Full Compliance Evaluation, Minor, Salt Lake County
INSPECTION DATE: November 30, 2021
SOURCE LOCATION: 1275 East Fairfax Road, Salt Lake City, UT 84103
SOURCE CONTACT(S): Cecil Prewitt, Maintenance/Engineering, 801-536-3803,
cprewitt@shrinenet.org
OPERATING STATUS: Boiler #1 was in operation during this inspection.
PROCESS DESCRIPTION: Shriners is a Pediatric Special Care Hospital and currently operates as a
Clinic. The boilers are used to provide comfort heat, and steam to the
facility. Boiler #3 is out of service. Boilers #1 and #2 operate alternately
each month; only one boiler runs at a time for a month, while the other
serves as backup and undergoes testing and maintenance for one hour for
that month. Three water heaters provide hot water to the facility.
The Emergency Generator is used for emergency purposes only and in
the event of a power outage.
APPLICABLE
REGULATIONS: Approval Order DAQE-649-98, dated October 1, 1998
UAC R307-210-1 incorporating:
40 CFR 60 Subparts A General Provisions
40 CFR Part 60 Subpart Dc Standards of Performance for Small
Industrial-Commercial-Institutional Steam Generating Units
UAC R307-214-2 incorporating:
40 CFR Part 63 Subpart A General Provisions
40 CFR Part 63 Subpart ZZZZ — National Emission Standards for
Hazardous Air Pollutants for Stationary Reciprocating Internal
Combustion Engines
SOURCE EVALUATION:
General Conditions:
1. This AO applies to the following company:
1
DAQ-2022-000246
Facility Office
Shriner Hospitals for Children
Fairfax Avenue & Virginia Street
Salt Lake City, Utah 84103
Phone Number
Fax Number
(801) 536-3500
(801) 536-3782
The equipment listed below in this AO shall be operated at the following location:
PLANT LOCATION:
Fairfax Avenue & Virginia Street, Salt Lake City, Salt Lake County, Utah
Universal Transverse Mercator (UTM) Coordinate System:
4,514.2 kilometers Northing; 428.26 kilometers Easting; Zone 12
Status: In compliance. The above source location information is correct
2. Definitions of terms, abbreviations, and references used in this AO conform to those used in the Utah
Administrative Code Rule 307 (UAC R307), and Series 40 of the Code of Federal Regulations (40
CFR). These definitions take precedence, unless specifically defined otherwise herein.
Status: This is not a compliance issue.
3. Shriners Hospitals for Children shall install and operate three natural gas and diesel fuel fired boilers,
two rated at 8.4 x 106 Btu/hr, and one at 6.3 x 106 Btu/hr, and shall operate one diesel fired backup
generator rated at 1332 bhp according to the terms and conditions of this AO as requested in the
Notice of Intent dated and additional information submitted to the executive secretary dated April 13,
1998.
Status: In compliance. Boiler #3 is currently out of service. Boilers #1 and #2 operate alternately each
month; only one boiler runs at a time for a month, while the other serves as backup and
undergoes testing and maintenance for one hour for that month.
4. At least once per calendar year, all employees who operate equipment (operator) that produces and/or
controls emissions to the air shall receive proper training as to their responsibilities in operating that
equipment according to all relevant conditions of this AO. The training for each operator shall be for
all equipment that operator operates. The equipment shall include all of the equipment listed below in
Condition #5. Within 60 days of every time this AO is modified or reissued, those employees who
operate equipment that produces and/or controls emissions to the air that is affected by the AO
changes shall receive proper training as to their responsibilities in operating equipment according to
all relevant conditions of this AO. Within 60 days of a new operator being employed or assigned
with the job responsibility to operate any of the equipment that produces and/or controls emissions to
the air, the new operator shall receive proper training as to their responsibilities in operating the
equipment according to all relevant conditions of this AO. Records of operator training shall be made
available to the executive secretary or executive secretary's representative upon request and the
records shall include the two-year period prior to he date of the request. This AO shall be made
available to all employees who operate the equip ent listed in this AO.
Status: In compliance. Shriners Hospital train all employees who operate the boilers and the
emergency generator. During this inspection, Mr. Prewitt was the only one trained to operate
the boilers and the emergency generator.
5. The approved installations shall consist of the following equipment or equivalent*:
A. Two (2) Natural Gas Fired Boilers
Manufacturer: Superior Boiler Works*
Model No: 8-5-1000
Serial No: 12404, 12403
Heating Capacity: 8.4 x 106 BTU/hr-each
Back-up fuel: #2 diesel fuel
B. One (1) Natural Gas Fired Boiler
Manufacturer: Superior Boiler Works*
Model No: 8-5-750
Serial No: 12402
Maximum rating: 6.3 x 106 BTU/hr per burner
Back-up fuel: #2 diesel fuel
C. One Diesel Fired Emergency Generator
Manufacturer: Caterpillar *
Model No: 3500
Rated at: 930 kW/1332 bhp
Fuel: #2 diesel fuel
Status: In compliance. The dual-fueled Boilers #1 and #2 are rated 8.03 MMBTU, were manufactured
in 1994. Boiler #3 in AO Condition 5B is currently out of service. The diesel-fueled Cat 3508
Emergency Generator is rated at 800 kW and was manufactured in 1995.
6. The executive secretary shall be notified in writing upon start-up of the installation, as an initial
compliance inspection is required. Eighteen months from the date of this AO the executive secretary
shall be notified in writing of the status of construction/installation if construction/installation is not
completed. At that time, the executive secretary shall require documentation of the continuous
construction/installation of the operation and may revoke the AO in accordance with R307-1-3.1.5,
UAC. If construction is complete and operation has commenced, a notice is not required on the status
of the construction/installation.
Status: In compliance. According to the records in the DAQ files, the initial inspection was conducted
in August 2000.
7. Visible emissions from the following emission points shall not exceed the following values:
A. Visible emissions from the boiler stacks shall not exceed a 10% opacity limit when using natural
gas as a fuel.
B. Visible emissions from the boiler stacks shall not exceed a 20% opacity limit when using diesel
fuel.
C. Visible emissions from the emergency generator stack shall not exceed a 20% opacity limit.
3
Opacity observations of emissions from stationary sources shall be conducted according to 40 CFR
60, Appendix A, Method 9. Visible emissions from mobile sources and intermittent sources shall use
procedures similar to Method 9, but the requirement for observations to be made at 15-second
intervals over a six-minute period shall not apply. Any time-interval with no visible emissions shall
not be included.
Status: In compliance. There were no visible emissions observed from the Boiler # 1 during this
inspection. The Emergency Generator was not in operation during this inspection. See the
attachment for additional information.
8. The following production and/or consumption limits shall not be exceeded without prior approval in
accordance with R307-1-3.1, UAC:
A. 62 x 106 standard cubic feet of natural gas per year (all boilers combined) per rolling 12-month
period
B. Operation (including periods for testing/maintenance) shall not exceed 100 hours per boiler per
rolling 12-month period when operated on the diesel fuel #2
C. Emergency generator operation (including periods for testing/maintenance) shall not exceed 300
hours per rolling 12-month period
Compliance with the annual limitations shall be determined on a rolling 12-month total. The
owner/operator shall calculate a new 12-month total based on the first day of each month using data
from the previous 12 months. Records of consumption/operation (utility bills, purchase receipts,
hours of operation from hour meters or operation logs) shall be kept for all periods when the plant is
in operation. Records of consumption/operation, including rolling 12-month totals shall be made
available to the executive secretary or executive secretaries representative upon request and shall
include a period of two years ending with the date of the request. Consumption shall be determined
by company records or billing statements.
Status: In compliance. The rolling 12-month consumption totals/hours of operation from January to
December 2021 included the following.
A. 7.8 x 106 standard cubic feet of natural gas (all boilers combined);
B. 12 hours of operation for testing/maintenance of Boilers #1 and #2 on #2 diesel fuel;
C. 12.32 hours of operation for testing/maintenance emergency generator. .
The Emergency Generator is tested on Fridays for ten minutes with a one hour load test the
second Friday of each month.
See the attachment for additional information.
Fuels
9. The owner/operator shall use only natural gas as a primary fuel and #2 diesel fuel as a backup fuel in
the boilers. The owner/operator shall use only #2 diesel fuel in the diesel generators. If any other
fuel is to be used, an AO shall be required in accordance with R307-1-3.1, UAC.
Status: In compliance. Shriners Hospital uses natural gas as primary fuel and #2 diesel fuel as
backup for the boilers; and #2 diesel fuel in the emergency generator.
4
10. The sulfur content of any fuel oil or diesel burned shall not exceed 0.5 percent by weight. Sulfur
content shall be decided by ASTM Method D-4294-89, or approved equivalent. The sulfur content
shall be tested if directed by the executive secretary.
Status: In compliance. According to Sevier Valley Oil, the diesel is classified as Ultra Low Sulfur with
a sulfur content less than 0.0015 sulfur by weight. See the attachment for additional
information.
Records & Miscellaneous
11. All installations and facilities authorized by this AO shall be adequately and properly maintained. All
pollution control vendor-recommended equipment shall be installed, maintained, and operated.
Instructions from the vendor or established maintenance practices that maximize pollution control
shall be used. All maintenance performed on equipment authorized by this AO shall be recorded, and
the records shall be maintained for a period of two years. All necessary equipment control and
operating devices, such as pressure gauges, amp meters, volt meters, flow-rate indicators, temperature
gauges, CEMS, etc., shall be installed and operated properly and easily accessible to compliance
inspectors. A copy of all the manufacturers' and company's own subsequent operating instructions
for pollution control equipment and pollution emitting equipment shall be kept on site. These
instructions shall be available to all employees who operate the equipment and shall be made
available to compliance inspectors upon their request. Maintenance records shall be made available
to the executive secretary or executive secretary's representative upon request and the records shall
include the two-year period prior to the date of the request.
Status: In compliance. Shriners Hospital maintains records of maintenance activities conducted on
approved equipment for a minimum of two years.
12. The owner/operator shall comply with R307-1-4.7, UAC. This rule addresses unavoidable
breakdown reporting requirements. Any breakdown lasting longer than two hours shall be reported to
the executive secretary within three hours of the breakdown if reasonable, but in no case longer than
18 hours after the beginning of the breakdown. During times other than normal office hours,
breakdowns for any period longer than two hours shall be initially reported to the Environmental
Health Emergency Response Coordinator. Within seven calendar days of the beginning of any
breakdown lasting longer than two hours, a written report shall be submitted to the executive
secretary. The owner/operator shall calculate/estimate the excess emissions (amount above AO
limits) whenever a breakdown occurs. The total of excess emissions per calendar year shall be
reported to the executive secretary with the inventory submittal, as directed by the executive
secretary. The owner or operator of an installation suffering an unavoidable breakdown shall assure
that emission limitations and visible emission limitations are exceeded for only as short a period of
time as reasonable. The owner or operator shall take all reasonable measures which may include but
are not limited to the immediate curtailment of production, operations, or activities at all installations
of the source if necessary to limit the total aggregate emissions from the source to no greater than the
aggregate allowable emissions averaged over the periods provided in the source's approval order.
Status: In compliance. There were no reportable breakdowns at Shriners Hospital since the last
inspection.
FEDERAL REQUIREMENTS
In addition to the requirements of this AO, and applicable Area Source Rules, the following federal
programs have been found to apply to the following equipment at this facility.
5
40 CFR Part 60 Subpart Dc Standards of Performance for Small Industrial-Commercial-Institutional
Steam Generating Units
In compliance. Shriners Hospital operates two dual-fueled Boilers #1 and #2 are rated 8.03 NIMBTU,
were manufactured in 1994. Boiler #3 in AO Condition 5B is currently out of service. The rolling 12-
month consumption totals of natural gas from January to December 2021 indicated 7.8 x 106 standard
cubic feet. The diesel usage indicated 67 gallons for Boiler #1 and 70 gallons for Boiler #2.
40 CFR Part 63 Subpart ZZZZ — National Emission Standards for Hazardous Air Pollutants for Stationary
Reciprocating Internal Combustion Engines.
In compliance. Shriners Hospital operates a diesel-fiteled Emergency Generator, Caterpillar 3508
rated at 1,332 hp, and equipped with a non-resettable meter. This Emergency Generator qualifies as
an existing Stationary Engine >500 HP Located at Area Sources of HAP, constructed before June 12,
2006, and consequently, no notification, no initial compliance test, no operating limitations, and no
performance tests required. The rolling 12-month operation hours from January-December 2021,
indicated 12.32 hours. According to Sevier Valley Oil, the diesel is classified as Ultra Low Sulfur with
a sulfur content less than 0.0015 sulfur by weight. See the attachment for additional information.
R307 SOURCE RULES EVALUATION
UAC R307-203. Emission Standards: Sulfur Content of Fuels
In compliance. According to Sevier Valley Oil, the diesel is classified as Ultra Low Sulfur with a
sugar content less than 0.0015 sulfur by weight. See the attachment for additional information.
EMISSION INVENTORY: Shriners Hospital is currently not required to submit an emissions
inventory. The potentials to emit from the AO are (Pollutant, Tons/yr):
PM10, 0.49; SO2, 2.12; NO, 6.66; CO, 0.91; VOCs, 0.30
PREVIOUS
ENFORCEMENT ACTIONS: No enforcement actions within the past five years.
COMPLIANCE STATUS &
RECOMMENDATIONS: Shriners Hospital is in compliance with the conditions of Approval Order
DAQE-649-98 dated October 1, 1998.
RECOMMENDATION FOR
NEXT INSPECTION: Inspect as usual.
ATTACHMENTS: Visible Emissions Observation Form, Rolling 12-month Natural
Gas/Diesel Consumption for Boilers, Rolling 12-month Emergency
Generator Usage, Fuel Certification
6
Sun flY Wind Emission
Observer Position X
int with Plume Cy-1
Observer's Signature:
Page of STATE OF UTAH, DEPARTMENT OF ENVIRONMENTAL QUALITY
DIVISION OF AIR QUALITY
EPA METHOD 9 — VISIBLE EMISSION OBSERVATION FORM
OBSERVATION DATE:
Start time:
Site ID:
Facility:
Equipment/Process:
Control Equipment:
Emission Point:
Sky Conditions: Clear [)c%, Partly Cloudy [ ] Overcast [ ]
Precipitation: No 1)1\ Yes [ ]
Wind: Direction: Speed: mph
Ambient Temp: oF RH:
Height Relative to Observer:
Distance From Observer:
Condensed Water Vapor Present: No [ 1 Yes [ ]
Attached [ ] Detached [ ]
Length of Condensed Water Vapor Plume:
Background:
Sketch process unit: indicate observer position relative to
source; indicate potential emission points and/or actual
emission points.
Distrib: white-file; canary-inspector; pink-owner/operator
secec 0 15 30 45
1
( Oa) 2
3
4
5 \ 1 \\\
7 \\
9V
10 NO
11
12
COMMENTS:
I have received a copy of these observations:
SIGNATURE:
Printed Name:
Title:
- Q. MOM .17 NM f6. 10161 ilatin 2021 23.6 2046 26.7 1880 21.2 25.5 1306 1405 19.2
rap, y Fe b u AVM 2402 MAMA WirMattzi 2020
2021 re r tAitil resAIWY-1014101C4 ViVitelli 11 0 12 0 12 0 11 0 10
4%411 egrA17.1e .1 Fatili111 Mt j174 Witil $34,60,t, s 2021 0 12 i 0 10 0 12 0 12 0
iti 2021 - f WAWA 0:111 In -
, WW-1.. 6.1;:iy,6-6(;:. NI*K. ApOl':. Vay,, kijie:-.1.ii. iiiiig6W SWeembe-r- '
2021 27 28 31 27 29 31 35 28 30
0.42 1.5 1.58 1.92 0.58 0.53 1.05 1.5 1.17
OctblAn Riikgbit
1058
DAWN. Octob WAWA
0 11 0
OctolYi0 00,1601411
da6garl -..4
12 0 12
OffibAYA - - o
OCt4 . - ,.•
29 29 31
1.02 0.52 0.53
running total 7811.2
running total 24.7
Total 7835.9
gallons 67
gallons 70 iirot":71,0 cm. • 0 a 0 '3- 0 I. 1,4
Out of Service 0
Gallons 355
hours 12.32 4C.P1 i - u.157 19-1-:,,;:h !t _,„
tin.f.ROPti
24.7
Lott/ 5o I la/ (ct-r/04
Sevier Valley Oil Co., rtc.
SINCE 1949
1890 South Industrial Park Rd.
Richfield, Utah 84701
(435) 896-4405 • Fax (435) 896-4551
October 27, 2015
To Whom It May Concern:
Shriner's Hospital, located at Fairfax Road at Virginia Street,
Salt Lake City, Utah, has only been receiving UltraLow Sulfur
diesel products from our company. The Ultra Low Sulfur diesel is
less than .0015% sulfur by weight.
Any questions can be directed to Sevier Valley Oil Co. at
435-896-4406.
1
CLL)
Rachelle Ogden
Accounting
Petroleuni Marketing - Gasoline, Diesel - Intermountain States
Thank you!
Response Summary:
To be eligible businesses shall not do any of the follow:
1) Emit more than 5 tons per year of each of the following pollutants: Sulfur Dioxide (SO2), Carbon Monoxide (CO),
Nitrogen Oxides (NOx), Particulate Matter (PM10), Ozone (O3), or Volatile Organic Compounds (VOCs).
2) Emit more than 500 lbs/yr of any single Hazardous Air Pollutant (HAP), and emit more than 2000 lbs/yr of any
combination of HAPs
3) Emit more than 500 lbs/yr of any combination of air contaminants not listed in 1 or 2
A copy of this registration notice and worksheets are required on site to verify permit exemption status.
Please be aware a the Small Source Exemption ONLY exempts the site from the air permitting requirements of R307-
401-5 thru R307-401-8 of the Utah Administrative Code, all other air quality regulations still apply.
Q4.
Please fill out the following contact information:
Site Contact Site Owner
Name Cecil Prewitt Shriners Children's Shriners Children's
Mailing Address 1275 E. Fairfax Rd 1275 E. Fairfax Rd 1275 E. Fairfax Rd
Mailing Address 2 n/a n/a n/a
City Salt Lake City Salt Lake City Salt Lake City
State UT ut UT
Zip Code 84103 84103 84103
Phone 8015363803 8015363500 8015363500
Fax 8015393736 8015393736 8015393736
Email cprewitt@shrinenet.org cprewitt@shrinenet.org cprewitt@shrinenet.org
Q5. County the Site is located in:
Salt Lake County
Q6. Briefly describe the process including the end products, raw materials, and process equipment used.
boiler runs 5 minutes per hour during operational hours and 3 minutes per hour during non-operational hours, looking at
around 100 minutes of boiler operation per 24 hours and around 600 total hours of boiler operation per year.
Q7. List emission units
8 MMBtu/hour
Q8. List any pollution control equipment
N/A
Q9. Please include Annual Emission Rates calculation spreadsheet.
[Click here]
Q11. Contact Information: (person filling out form - signature will be required)
Name Cecil Prewitt
Title Manager Plant and Facilities
Phone 8015363803
Date 8/22/2024
Q10. By signing below, I hereby certify that the information and data submitted in this notice fully describes
this site and ONLY this site. The information provide is true, accurate, and complete to the best of my
knowledge. I understand that I am responsible for determining whether the site remain eligible for this
exemption before making operational or process changes in the future, and agree to notify the Division of
Air Quality when this site is not longer eligible for this exemption. (Signature of Owner/Manager)
[Click here]
Embedded Data:
N/A
Dungan Adams <dunganadams@utah.gov>
Fwd: Small Source Exemption
2 messages
Alan Humpherys <ahumpherys@utah.gov>Fri, Aug 23, 2024 at 11:02 AM
To: Dungan Adams <dunganadams@utah.gov>
Dungan,
Here is a SSE for the AO revocation that I just sent you.
Site ID: 12134
Peer: Christine
Thanks,
Alan
---------- Forwarded message ---------
From: <noreply@qemailserver.com>
Date: Thu, Aug 22, 2024 at 5:12 PM
Subject: Small Source Exemption
To: <ahumpherys@utah.gov>
The following small source exemeption was submitted, please go into qualtrics and print off the PDF and forward to Alan.
Recipient Data:
Time Finished: 2024-08-22 17:12:10 MDT
IP: 74.203.131.11
ResponseID: R_3fHUAwcMfoD3hU1
Link to View Results: Click Here
URL to View Results: https://utahgov.iad1.qualtrics.com/apps/single-response-reports/reports/ri%2EF6XJTvwvsL6eCdx-
jKDV9VoXxZEtn7rKi4IP1w3dgz9udKnvvi9QUo6Kh4SkXYxleqs4HWrPVzxS1ZxuqKr7rQ6OHBjkSsHOzq2b%
2EQPcVWgvz4O6lDDSoTwnh4xJnlUyAvSmBf%2EZ5p5PDwCzuGKN6yWBM-QE5Bf53-
gWWbVmlX7kGe5PDr6e38w63YPnwce41hKHKzPAVBpKT-nh9KevMfBcr1wUf%2EAm5CQxjwILmHJfXkh5V01Rzk-
Mmlvcg-9%2EcpGr9k9k-xIPnyFrR6f96XsT5m4WdPLlLREcIlb4Blx-tTdfOihE9qxehvv127HIPQC7ocCx7YzXn%2EjEYhQ
Response Summary:
Please fill out the following contact information:
Name
Site Contact Cecil Prewitt
Site Shriners Children's
Owner Shriners Children's
Mailing Address
Site Contact 1275 E. Fairfax Rd
Site 1275 E. Fairfax Rd
Owner 1275 E. Fairfax Rd
Mailing Address 2
Site Contact n/a
Site n/a
Owner n/a
City
Site Contact Salt Lake City
Site Salt Lake City
Owner Salt Lake City
State
8/23/24, 11:51 AM State of Utah Mail - Fwd: Small Source Exemption
https://mail.google.com/mail/u/0/?ik=c52f18613a&view=pt&search=all&permthid=thread-f:1808198602225608698&simpl=msg-f:180819860222560869…1/3
Site Contact UT
Site ut
Owner UT
Zip Code
Site Contact 84103
Site 84103
Owner 84103
Phone
Site Contact 8015363803
Site 8015363500
Owner 8015363500
Fax
Site Contact 8015393736
Site 8015393736
Owner 8015393736
Email
Site Contact cprewitt@shrinenet.org
Site cprewitt@shrinenet.org
Owner cprewitt@shrinenet.org
County the Site is located in:
Salt Lake County
Briefly describe the process including the end products, raw materials, and process equipment used.
boiler runs 5 minutes per hour during operational hours and 3 minutes per hour during non-operational hours, looking at
around 100 minutes of boiler operation per 24 hours and around 600 total hours of boiler operation per year.
List emission units
8 MMBtu/hour
List any pollution control equipment
N/A
Please include Annual Emission Rates calculation spreadsheet.
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_2QgEfnfipv5DzCV
Contact Information: (person filling out form - signature will be required)
Name Cecil Prewitt
Title Manager Plant and Facilities
Phone 8015363803
Date 8/22/2024
By signing below, I hereby certify that the information and data submitted in this notice fully d...
https://utahgov.co1.qualtrics.com/WRQualtricsControlPanel/File.php?F=F_Ry2lxeTp16H8FmF
--
Alan Humpherys
Manager | Minor NSR Section
P: (385) 306-6520
F: (801) 536-4099
airquality.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
8/23/24, 11:51 AM State of Utah Mail - Fwd: Small Source Exemption
https://mail.google.com/mail/u/0/?ik=c52f18613a&view=pt&search=all&permthid=thread-f:1808198602225608698&simpl=msg-f:180819860222560869…2/3
Shriners_Children_s_Emission_Calculations.pdf
177K
Dungan Adams <dunganadams@utah.gov>Fri, Aug 23, 2024 at 11:03 AM
To: Alan Humpherys <ahumpherys@utah.gov>
Awesome. Thanks!
-Dungan
[Quoted text hidden]
--
Dungan Adams
Environmental Engineer | Minor NSR Section
M: (385) 290-2474
airquality.utah.gov