HomeMy WebLinkAboutDAQ-2025-0020701
DAQC-367-25
Site ID 12495 (B5)
MEMORANDUM
TO: CEM FILE – WEST VALLEY POWER
THROUGH: Harold Burge, Major Source Compliance Section Manager
FROM: Rob Leishman, Environmental Scientist
DATE: April 10, 2025
SUBJECT: Source: Units 1, 2, 3, 4, and 5 (GE LM600 Natural Gas Turbines)
Contact: Jerame Blevins – 801-967-1200 x232
Location: 5935 West 4700 South, WVC, Salt Lake County, UT
Test Contractor: Alliance Technical Group
FRS ID#: UT0000004903500527
Permit/AO#: Title V operating permit 3500527005, dated July 8, 2024
Subject: Review of RA/PST Protocol dated March 24, 2025
On March 28, 2025, Utah Division of Air Quality (DAQ) received a protocol for a RA/PST (relative
accuracy/performance specification test) of the West Valley Power electrical generation facility in West
Valley City, Utah. Testing will be performed on June 16-20, 2025, to determine the relative accuracy of
the O2, CO2, NOX, and CO monitoring systems.
PROTOCOL CONDITIONS:
1. RM 1 used to determine sample velocity traverses: OK
2. RM 3A used to determine dry molecular weight of the gas stream: OK
3. RM 7E used to determine NOX concentrations of emissions: OK
4. RM 10 used to determine CO concentrations of emissions: OK
5. RM 19 used to determine volumetric flow: OK
6. RM 205 used to validate gas dilution systems for field instrument calibration: OK
DEVIATIONS: No deviations were noted.
CONCLUSION: The protocol appears to be acceptable.
RECOMMENDATION: Send attached protocol review and test date confirmation notice.
1 8 2
wrsr vertEy PowER
March 24,2025
Director
State of Utah
Department of Environmental Quality - Division of Air Quality
195 North 1950 West Temple
Salt Lake City, UT 84116-3100
USEPA, Region Vlll
Office of Enforcement, Compliance and Environmental Justice
(Mail Code 8ENF)
1595 Wynkoop Street
Denver, CO 8O202-LL29
DEPARTMENT OF
EiIIVIRONMENTAL Ot AUIY
MAR 2 8 2025
DMSlot{ OF AtR OUAUW
Reference: West Valley Power Plant (Permit #3500527005)
2025 Relative Accuracy Test Audit (RATA) Protocol Submittal and Test Notification
Dear Director:
Utah Municipal Power Agency has contracted Alliance Source Testing to conduct Relative Accuracy Test
Audits (RATAs) on the continuous emissions monitoring systems (CEMS) for five natural gas combustion
turbines located at the West Valley Power Plant (Permit #3500527005).
ln accordance with UAC R307.170-7(2) notice is being given that testing is scheduled to be conducted
during the week beginning June 16, 2025.
For your review, please find enclosed a copy of the Source Emissions Test Protocol for conducting
testing to determine the relative accuracy of the oxygen(Oz), nitrogen oxides (NOx) and carbon
monoxide (CO) CEMS installed on each of five General Electric 1M5000 PC Sprint natural gas fired
combustion turbine generators (Units 1 - 5).
Should you have any questions or need additional information regarding this submittal, please contact
Jerame Blevins at (801) 967-L2OO ext 232.
Sincerelv.TrarhBalL
Travis Ball
Responsible Official
West Valley Power Plant
Enclosu re
CC: J. Blevins, Chris Cook & West Valley Compliance File
Trinity Consultants: Melissa Armer
Site Specific Test Plan
Utah Municipal Power Agency
West Valley Power
5935 West 4700 South
West Valley City, UT 841l8
Sources to be Tested: Units l-5
Proposed Test Dates: June 16 - 20,2025
Project No. AST-2025- 1292
Prepared By
Alliance Technical Group, LLC
3683 W 2270 S, Suite E
West Valley City, UT 84120
i,fAR 2 B 2t:5
DMS]ON OF AIR OUAUTY
=talEE)AI Site Specific Test Plan
Test Program Summary
Regulatory Information
Permit No.
Regulatory Citations
Source Information
Title V Operating Permit 3500527005
40 CFR 60, Appendix B, Performance Specifications 2, 3 and 4
40 CFR 75. Appendices A & B
Source Name
(5) General Electric Model LM600
PC Sprint, Natural Gas-Fired
Simple Cycle Combustion Turbine
Generators
Contact Information
Source lD
Unit I
Unit 2
Unit 3
Unit 4
Unit 5
Target Parameters
O:, NOx. CO
O:, NOx. CO
O:, NOx. CO
Ou, NOx, CO
O:, NOx. CO
Test Location
Utah Municipal Power Agency
West Valley Power
5935 West 4700 South
West Valley Ciry, UT 841 l8
Jerame Blevins
jerame@umpa.energy
(80r) e67-r200
Test Company
Alliance Technical Group, LLC
3683 W 2270 S, Suite E
West Valley City, UT 84120
Project Manager
Charles Horton
charles.horton@al I iancetg.com
(3s2) 663-7s68
Field Manager
Ryan Lyons
ryan. lyons@all iancetg.com
(708) 2 l4-4850
(subject to change)
QA/QC Manager
Kathleen Shonk
katie.shonk@all iancetg.com
(812) 452-4785
Test Plar/Report Coordinator
Delaine Spangler
delaine.spangler@all iancetg.com
AST-202s-t292 West Valley Power - West Valley Ciq. UT
Site Specrfic Test Plan
Table ofContents
TABLE OF CONTENTS
2.0 Summary of Test Program ............ 2- I
2.2 Process/Control System Parameters to be Monitored and Recorded............... .....................2-l
3.1 U.S. EPA Reference Test Method I - Sample Point Determination............ .........................3-l
3.2 U.S. EPA Re ference Test Method 34 - Oxygen/Carbon Dioxide......... ......... 3- I
3.3 U.S. EPA Reference Test Method 7E - Nitrogen Oxides ......... 3-l
3.4 U.S. EPA Re ference Test Method l0 - Carbon Monoxide..... ........................ 3-2
3.5 U.S. EPA Reference Test Method 19 - Mass Emission Factors .....................3-2
3.6 Quality AssuranceiQuality Control - U.S. EPA Reference Test Methods 3A.78 and 10..........................3-2
LIST OF TABLES
Table 2-l: Program Outline and Tentative Test Schedule ......................2-2
Table 2-2: Relative Accuracy Requirements and Limits ........................ 2-3
LIST OF APPENDICES
AppendixA MethodlData
Appendix B Example Field Data Sheets
AST-202s- l 292 West Valley Power - West Valley Cit),. L.lT Page ii
Sire Specrf c Test Plan
lnlroductton
1.0 lntroduction
Alliance Technical Croup, LLC (Alliance) was retained by Utah Municipal Power Agency to conduct performance
specification (PS) testing at the West Valley Power plant in West Valley City, Utah. Portions of the facility are
subject to provisions of 40 CFR 60, Appendix B. PS 2,3 and 4 and 40 CFR 75, Appendices A & B. The facility
operates under the Utah Department of Environmental Quality. Division of Air Quality (UDAQ) Title V Operating
Permit No. 3500527005. Testing will include conducting a relative accuracy test audit (RATA) to determine the
relative accuracy (RA) of the oxygen (O:), nitrogen oxides (NOx) and carbon monoxide (CO) continuous emissions
rnonitoring systems (CEMS) installed on five (5) General Electric Natural Gas-Fired Combustion Turbine
Generators designated as Units l-5.
This site-specific test plan (SSTP) has been prepared to address the notification and testing requirements of the
UDAQ Title V permit.
l.l Facility Descriptions
West Valley Power operates five (5) Ceneral Electric Model LM600
Conrbustion Turbine Generators at the West Valley Generating Station
1.2 CEMS Descriptions
Unit I
Pollutant
NOx
Thermo
42iQLS
t200696549
Low:0-lOOppnr
High: 0-500ppnr
Pollutant
NOx
Thermo
42iQLS
I 200696550
Low:0-lOOppnr
High:0-500ppm
Pollutant
NOx
Thermo
42iQLS
r 2006955 r
Low:0-lO0ppnr
High:0-500ppm
PC Spring, Natural Gas-Fired, Simple Cycle
The generators are designated as Units l-5.
Parameter:
Make:
Model:
Serial No.:
Span:
Unit 2
Parameter:
Make:
Model:
Serial No.:
Span:
Llnit 3
Parameter:
Make:
Model:
Serial No.:
Span:
Pollutant
co/o:
Thermo
48iQ
1200696554
CO:0-10,000ppm
O::0-259/o
Pollutant
CO/O:
Thermo
48iQ
I 200696555
CO:0-10,000ppm
O::0-25oh
Pollutant
co/o:
Thenno
48iQ
I 200696556
CO:0-10,000ppm
Ot 0-25o/o
AST-2025- I 292 West Valley Power - West Valley Cib., UT Page l-l
=IAAI
f..ri
Site Specif c Tcst Plan
lntroduction
tlnit I
Parameter:
Make:
Model:
Serial No.:
Span:
Unit 5
Parameter:
Make:
Model:
Serial No.:
Span:
Pollutant
NOx
Thermo
42iQLS
t200696s52
Low:0-l00ppm
High: 0-500ppm
Pollutant
NOx
Thermo
42iQLS
r 200696553
Low:0-l00ppm
High:0-500ppm
Pollutant
CO/Oz
Thermo
48iQ
t200696557
CO: 0-10,000ppm
O::0-25o/o
Pollutant
co/o:
Thermo
48iQ
r 200696s58
CO:0-10,000ppm
Ot 0-25o/o
1.3 Project Team
Personnel planned to be involved in this project are identified in the following table.
Table l-l: Project Team
1.4 Safety Requirements
Testing personnel will undergo site-specific safety training for all applicable areas upon arrival at the site. Alliance
personnel will have current OSHA or MSHA safety training and be equipped with hard hats, safety glasses with side
shields. steel-toed safefy shoes, hearing protection, fire resistant clothing, and fall protection (including shock
corded lanyards and full-body harnesses). Alliance personnel will conduct themselves in a manner consistent with
Client and Alliance's safety policies.
A Job Safety Analysis (JSA) will be completed daily by the Alliance Field Team Leader.
West Valley Power Personnel Jerame Blevins
Regulatory Agency UDAQ
Alliance Personnel Ryan Lyons
other field personnel assigned at time of testing event
AST-2025- l 292 West Valley Power - West Valley Cit). UT Page l-2
AI Site Specific Test Plan
Summary ofTest Programs
2.0 Summary of Test Program
To satis! the requirements of the UDAQ Title V permit, the facility will conduct a performance test program to
determine the compliance status of Units I -5.
2.1 General Description
All testing will be performed in accordance with specifications stipulated in U.S. EPA Reference Test Methods l,
34, 7E, 10, and 19. Table 2-l presents an outline and tentative schedule for the emissions testing program. The
following is a summary of the test objectives.
Testing will be perfomred to demonstrate compliance with the UDAQ Title V permit, 40 CFR 60,
Appendix B, PS 2, 3 and 4. and 40 CFR 75, Appendices A & B.
Emissions testing will be conducted on the exhaust of Units l-5.
Performance testing will be conducted at more than 50 percent of the normal load.
Each of the l2 test runs will be approximately 2l minutes in duration.
2.2 Process/Control System Parameters to be Monitored and Recorded
Plant personnel will collect operational and parametric data at least once every l5 minutes during the testing. The
following list identifies the measurements, observations and records that will be collected during the testing
program:
Production rate - KW
Gas Flow Rate - scfh
CEMS Data
2.3 Proposed Test Schedule
Table 2- I presents an outline and tentative schedule for the emissions testing program.
-IA
, i ..,
a
a
a
a
O
a
AST-2025-t292 West Valley Power - WesI Valley Cit)'. UT Page 2-l
put6rpe
TECI]NICAL GROUP Site Specifc Test Plan
Summary ofTest Programs
Table 2-1: Program Outline and Tentative Test Schedule
DAY I -lune16,2025
Equipment Setup & Pretest QA/QC Checks
l0 hr
Unit I
Oz 3A
t2 2l minNOx7E
CO l0
VFR / lbiMMBtu l9
DAY2-June17,2025
Unit 2
Oz 3A
t2 2l min
l0 hr
NOx 7E
CO l0
VFR / Ib/IvIMBtu l9
DAY 3 -June 18,2025
Unit 3
Oz 3A
t2 2l min
l0 hr
NOx 7E
CO l0
VFR / lb/\,IMBtu l9
DAY4-June 19,2025
Unit 4
o:3A
t2 2l min l0 hr
NOx 7E
CO l0
VFR / Ib/TT4MBIU ls
DAY 5 -June20,2025
Unit 5
Ou 3A
t2 2l mrn
l0 hr
NOx 7E
CO l0
VFR / Ib,A4MBtU l9
AST-2025-t292 West Valley Power - West Valley City, UT Page2-2
pill6rpe
Site Spectfic Test Plan
Summary ofTest Programstl
2.4 Emission Limits
Emission limits for each pollutant are below.
Table 2-2: Relative Accuracy Requirements and Limits
2.5 Test Report
The final test report must be submitted within 60 days of the completion of the performance test and will include the
following information.
t lnlroduction-Brief discussion ofproject scope ofwork and activities.
o Results and Discussion - A summary of test results and process/control system operational data with
comparison to regulatory requirements or vendor guarantees along with a description of process conditions
and/or testing deviations that may have affected the testing results.
o lVlethodologt - A description of the sampling and analytical methodologies.
o Sample Calculations - Example calculations for each target parameter.
o Field Dala - Copies of actual handwriuen or electronic field data sheets.
o Qualily Conlrol Data - Copies of all instrument calibration data and/or calibration gas certificates.
c Process Operating/Control System Data- Process operating and control system data (as provided by West
Valley Power) to support the test results.
ffi:[-1i]tF3ry..r,"r'}ae- l:t; lt lr,i fl!
Units l-5
o:%o vd
S20 % (RM) or t I o/o O2 60, Appendix B. PS 3
S7.5% (RM) or d<0.7ohO:.T5,AppendixA&B
NOx
ppmvd @15%Oz
lb/MMBtu
lb/hr
<20 % (RM) or <10 % (AS)
100 ppmvd
@l5oh02-7.4lblhr
60, Appendix B, PS 2
57.5% (RM) or d 5 0.015
lb/h4MBtu T5,AppendixA&B
CO ppmvd @l5o/o 02
lb/hr
Sl0 % (RM) or <5 o/o (AS) or
dS5ppm(d+CC)
l0 ppmvd
@l5Yo Ot,
8.75 lb/hr
60, Appendix B, PS 4
AST-2025- l 292 West Valley Power- West Valley Citi,. UT Page 2-3
Sire Specific Test Plan
Tesring Merhodology
3.0 Testing Methodology
This section provides a description of the sampling and analytical procedures for each test method that will be
employed during the test program. All equipment. procedures and quality assurance measures necessary for the
cornpletionofthetestprogrammeetorexceedthespecificationsofeachrelevanttestmethod. Theemissiontesting
program will be conducted in accordance with the test methods listed in Table 3-1.
Table 3-l: Source Testing Methodology
All stack diameters, depths, widths, upstream and downstream disturbance distances and nipple lengths will be
measured on site with an EPA Method I verification measurement provided by the Field Team Leader. These
measurements will be included in the test report.
3.1 U.S. EPA Reference Test Method I - Sample Point Determination
The sampling location will be evaluated in accordance with U.S. EPA Reference Test Method l. The upstream and
downstream distances will be measured and equated to equivalent diameters to confirm compliance with U.S. EPA
Reference Test Method l.
3.2 U.S. EPA Reference Test Method 3A - Oxygen
The oxygen (O2) testing will be conducted in accordance with U.S. EPA Reference Test Method 3A. Data will be
collected online and reported in one-minute averages. The sampling system will consist of a stainless steel probe,
Teflon sample Iine(s), gas conditioning system and the identified gas analyzer. The gas conditioning system will be
a non-contact condenser used to remove moisture from the stack gas. lf an unheated Teflon sample line is used,
then a portable non-contact condenser will be placed in the system directly after the probe. Otherwise, a heated
Teflon sample line will be used. The quality control measures are described in Section 3.6.
The relative accuracy of the O:CEMS will be determined based on procedures found in 40 CFR 75, Appendices A
& B and 40 CFR 60, Appendix B, Performance Specification 3.
3.3 U.S. EPA Reference Test Method 7E - Nitrogen Oxides
The nitrogen oxides (NOx) testing will be conducted in accordance with U.S. EPA Reference Test Method 7E. Data
will be collected online and reported in one-minute averages. Tlre sampling system will consist of a stainless steel
probe, Teflon sample line(s), gas conditioning system and the identified gas analyzer. The gas conditioning system
will be a non-contact condenser used to remove moisture from the stack gas. If an unheated Teflon sample line is
used, then a portable non-contact condenser will be placed in the system directly after the probe. Otherwise, a
heated Teflon sample line will be used. The quality control measures are described in Section 3.6.
AST-2025- I 292 West Valley Power - West Valley Citr'. LIT Page 3- I
Site Spectfic Test Plan
'lesting Methodoloxl
The relative accuracy of the NOx CEMS will be deternrined based on procedures found in 40 CFR 75, Appendices
A & B and 40 CFR 60. Appendix B. Performance Specification 2.
3.4 U.S. EPA Reference Test Method l0 - Carbon Monoxide
The carbon monoxide (CO) testing will be conducted in accordance with U.S. EPA Reference Test Method 10.
Data will be collected online and reported in one-minute averages. The sampling system will consist of a stainless
steel probe. Teflon sample line(s). gas conditioning system, and the identified gas analyzer. The gas conditioning
system will be a non-contact condenser used to remove moisture from the gas. If an unheated Teflon sample line is
used, then a portable non-contact condenser rvill be placed in the systenr directly after the probe. Otherwise, a
heated Teflon sample line will be used. The quality control measures are described in Section 3.6.
The relative accuracy of the CO CEMS will be deternrined based on procedures found in 40 CFR 60, Appendix B,
Performance Specifi cation 4.
3.5 U.S. EPA Reference Test Method 19 - Volumetric Flow Rate / Mass Emission Factors
The gas volumetric flow rate will be detennined in accordance with U.S. EPA Reference Test Method l9 using the
measured oxygen concentration, the published fuel factor, a calibrated gas meter and the fuel heating value.
The pollutant concentrations will be converted to mass emission factors (lbiMMBtu) using procedures outlined in
U.S. EPA Reference Test Method 19. The published dry 01 based fuel factor (F-Factor) of 8,7 l0 dscf/MMBtu for
natural gas will be used in the calculations.
3.6 Quality Assurance/Quality Control - tl.S. EPA Reference Test Methods 3A, 7E and l0
Cylinder calibration gases will meet EPA Protocol I (+l- 2oh) standards. Copies of all calibration gas certificates
will be included in the Quality Assurance/Quality Control Appendix of the report.
Low Level gas will be introduced directly to the analyzer. After adjusting the analyzer to the Low-Level gas
concentration and once the analyzer reading is stable. the analyzer value rvill be recorded. This process will be
repeated for the High-Level gas. For the Calibration Error Test, Low. Mid, and High-Level calibration gases will be
sequentially introduced directly to the analyzer. The Calibration Error for each gas must be within 2.0 percent of the
Calibration Span or 0.5 ppmvl%o absolute difference.
High or Mid-Level gas (whichever is closer to the stack gas concentration) will be introduced at the probe and the
time required for the analyzer reading to reach 95 percent or 0.5 ppm/% (whichever was less restrictive) of the gas
concentration will be recorded. The analyzer reading rvill be observed until it reaches a stable value, and this value
rvill be recorded. Next. Low-Level gas will be introduced at the probe and the time required for the analyzer reading
to decrease to a value within 5.0 percent or 0.5 pprn/% (whichever was less restrictive) will be recorded. lf the Low-
Level gas is zero gas, the acceptable response must be 5.0 percent of the upscale gas concentration or 0.5 ppml9/o
(whichever was less restrictive). The analyzer reading will be observed until it reaches a stable value, and this value
will be recorded. The measurement system response time and initial system bias will be determined from these data.
The Systern Bias for each gas must be within 5.0 percent of the Calibration Span or 0.5 ppmv/%o absolute difference.
High or Mid-Level gas (whichever is closer to the stack gas concentration) will be introduced at the probe. After the
analyzer response is stable, the value will be recorded. Next, Low-Level gas will be introduced at the probe, and the
analyzer value will be recorded once it reaches a stable response. The System Bias for each gas must be within 5.0
AST-2025- I 292 West Vallei l)owcr- West Valley Citl
Sire Specific Test Plan
Testing Methodology
percent of the Calibration Span or 0.5 ppmv/7o absolute difference or the data is invalidated, and the Calibration
Error Test and System Bias must be repeated.
The Drift between pre- and post-run Systern Bias must be within 3 percent of the Calibration Span or 0.5 ppmvi%
absolute difference or the Calibration Error Test and System Bias must be repeated.
To determine the nurnber of sampling points, a gas stratification check will be conducted prior to initiating testing.
The pollutant concentrations will be measured at fwelve traverse points (as described in Method l) or three points
(16.7,50.0 and 83.3 percent of the measurement line). Each traverse point will be sampled for a minimum of twice
the systern response time.
lf the polf utant concentration at each traverse point does not differ more than 5oh or 0.5 ppml}.3oh (whichever is less
restrictive) of the average pollutant concentration, then single point sampling will be conducted during the test runs.
If the pollutant concentration does not meet these specifications but differs less than l07o or 1.0 ppm/0.5% from the
average concentration, then three (3) point sampling will be conducted (stacks less than 7.8 feet in diameter - 16.7,
50.0 and 83.3 percent of the measurement line; stacks greater than 7.8 feet in diameter- 0.4, 1.0, and 2.0 meters
from the stack wall). If the pollutant concentration differs by more than l0% or 1.0 ppm/0.5%o from the average
concenffation, then sampling will be conducted at a minimum of fwelve (12) traverse points. Copies of stratification
check data will be included in the Quality Assurance/Quality Control Appendix of the report.
An NO:- NO converter check will be performed on the analyzer prior to initiating testing. Mid-level nitrogen oxide
protocol I calibration gas will be mixed at a l:l ratio with span [evel protocol I oxygen calibration gas in a Tedlar
sample bag to form NO2 gas. The NOz gas will be delivered to the nitrogen oxides analyze( directly from a Tedlar
sample bag. The response of the analyzer must be stable for the 30-minute duration of the test with the variation
less than 2.0o/o at the end of the test from the nraximum value of the test.
A Data Acquisition System with banery backup will be used to record the instrument response in one (l) minute
averages. Thedatawill becontinuouslystoredasa*.CSVfileinExcel fonnatontheharddriveofacomputer. At
the completion of testing, the data will also be saved to the Alliance seryer. All data will be reviewed by the Field
Team Leader before leaving the facility. Once arriving at Alliance's office, all written and electronic data will be
relinquished to the report coordinator and then a final review will be performed by the Project Manager.
AST-202s-t292 West Valley Power - Wcst Valley Cit),. UT Page 3-3
AI Site Specific Test Plan
Oualin, Assurance P rogram
4.0 Quality Assurance Program
Alliance follows the procedures outlined in the Quality Assurance/Quality Control Management Plan to ensure the
continuous production of useful and valid data throughout the course of this test program. The QC checks and
procedures described in this section represent an integral part of the overall sampling and analytical scheme.
Adherence to prescribed procedures is quite often the most applicable QC check.
4.1 Equipment
Field test equipment is assigned a unique, pennanent identification number. Prior to mobilizing for the test
program, equipment is inspected before being packed to detect equipment problems prior to arriving on site. This
minimizes lost time on the job site due to equipment failure. Occasional equipment failure in the field is
unavoidable despite the most rigorous inspection and maintenance procedures. Therefore, replacements for critical
equipment or components are brought to the job site. Equipment returning from the field is inspected before it is
returned to storage. During the course of these inspections. items are cleaned, repaired, reconditioned and
recal ibrated where necessary.
Calibrations are conducted in a manner, and at a frequency, which meets or exceeds U.S. EPA specifications. The
calibration procedures outlined in the U.S. EPA Methods, and those recommended within the Quality Assurance
Handbook for Air Pollution Measurement Systems: Volume III (EPA-600/R-94/038c, September 1994) are utilized.
When these methods are inapplicable, methods such as those prescribed by the American Society for Testing and
Materials (ASTM) or other nationally recognized agency may be used. Data obtained during calibrations is checked
for completeness and accuracy. Copies of calibration forms are included in the report.
The following sections elaborate on the calibration procedures followed by Alliance for these items of equipment.
r Barometer. The barometric pressure is obtained from a nationally recognized agency or a calibrated
barometer. Calibrated barometers are checked prior to each field trip against a mercury barometer. The
barometer is acceptable if the values agree within + 2 percent absolute. Barometers not meeting this
requirement are adjusted or taken out ofservice.
o Other Equinment. A mass flow controller calibration is conducted on each Environics system annually
following the procedures in the Manufacturer's Operation manual. A methane/ethane penetration factor
check is conducted on the total hydrocarbon analyzers equipped with non-methane cutters every six (6)
months following the procedures in 40 CFR 60, Subpan JJJJ. Other equipment such as probes, umbilical
lines, cold boxes, etc. are routinely maintained and inspected to ensure that they are in good working order.
They are repaired or replaced as needed.
4.2 Field Sampling
Field sampling will be done in accordance with the Standard Operating Procedures (SOP) for the applicable test
method(s). General QC measures for the test program include:
r The sampling port will be sealed to prevent air from leaking from the port.
o All raw data will be maintained in an organized manner.
o All raw data will be reviewed on a daily basis for completeness and acceptability.
r
TA
AST-2025- r r92 West Valley Power - West Valley Citi,, UT Page 4-1
#r6rce Method I Data
tddioD Utlh
Souna Unil I
DirtmctmmPrrWrllroOurtid.ofPod: 15575 in
NtppL L.nnh: I L75 iil
Dcpth of DBi: l.l4.oo in
Cm$ Serlonrl Aftr o, DEr: I lJl0 ft:
No. ofTalt Pon!: J
Dlile. A: 7.0 lt
Diitm. A lhrct Di.mL6r 06 (mst b. > 0.5)
Ditrft. B: 61 0 n
Diduc. B DEt Dimtcnl 53 (mut be > 2)
Adul NuEbar ofTrrreFc Pointr: 3
LOCATION OT TRAVERSE DOINTS
Nuilbq oft^,.rs. NinB on o diomd.t
t
3
I
s
6
1
8
9
l0|ll:
J I 7 fl 9 to tl It
14.6 t6.7 67
85 .l 50.0 25.0
- rl.l 75.0_:'1'
4.1
l{ 6
2.).6
701
85.{
32
t0 5
t9l
12l
6?7
806
89.J,:,
8l
l{.6
22(
.l{ 2
6J lt
71.4
854
9l t
2t
ll r
171
25.0
156
(A.4
7!0
823
llt.2
9ll
'lerccil of stak ilnn.tet frw nsnlc Nall to tracne qMt
Tr$'ana
Polil
./. ol
Dirm€r
Dlttm.
ron iilidr
Bell
frem
ouliide o,
I
3
I
5
6
1
tl
9
l0
u
t2
t6.7
50.0
*1',
24 05
72 00
I lq9,
35.80
83.75
l3 L70
SucL Diagdn
A=7n.
B=63fi
Dcplh of Ducr = l.l] in.
Crcs Seliml AEa
Upiraam
Diaturbancc
{Erce Method 1 Data
Solre Unit ,
DBt Orlcnhtior: Vdiul
lhd llcrittr: Circulu
IlbtG. tmn Prr Wdl to Ourld.of Pon: 155 75 in
Nitltk Lngh: l l 75 ir
o.prhof DB: l{4.00 inCffi Sc(hnd Aci of Ihmr I I l lo ftr
No.ofTd Pont: {
Dilre A: 7.0 lt
Dirtu. A lhrl Dimt B: 0.6 (n6t bc > 0-q)
Dt r*. B,---Tii-fi
Diilmc. B lha Diimrcn: 5.3 (msr be > 2)
Adul Nurt.r of Tn cnr Foint: -T-
LOCATION OF TUVELSE PO1NTS
Nu&bu oI bovcre poiats M a dhil&r
I
3
.l
3
6
1
E
9
l0
ll
3 l 5 6 7 8 9 lo ll t2
14.6 t6.7 67
85 .t 50.0 2J.0
- E3.l 75.t1
91.3
t.t.6
29.6
70.+
E5..1
,:u
:
3.2
t0 5
19.{
32.3
67.7
E0.(,
Itg 5
:,
2.6
8.2
1.1.6
:2.6
34.2
65E
n.4
E5.4
91.8
2.1
I t.8
t7.7
2J.(!
356
64.4
7! t)
821
s.2
931
tPctcn, olit$k deilct.t ftM nild. eull to tt6,.ty Nnt.
TrtvcBa
Polnt
'/. ol
Dlrmlar
Oi!tea
'mm lnridr
wrll
frem
ou&id. ol
!
3
J
s
6
7
I
9
l0
lt
t2
50.0
E3.3
72 00
I t9.95
83.75
t3 t.70
Sbcl DilgM
A= 7n
B=61n.
DcpthofDucl = 14{ in.
Cr6! Sdbml AM
t p.r..m
Dhurh.m.
AEEe Method I Data
SouBa Unil 3
DBt Oricnlrtim: Vcniol
om o-tgn'--a;G-
Dirte.fomFrrWdltoOdrid.ofPod: 15575 in
NlppL lrn$h: I Lr in
Dcplh of lhrt: 14{.00 in
CEr! Sdiotrd Arcr o( Ihrr I I ll o ft:
No.ofTail Pon!: 4
Dirt[ca A: 7.0 ft
Dirruc A DBI Dirffi.n: ffi (mBt be > 0-S)
lrltt[ca B: 63.0 ll
Diilu.. B Dxt Ditrcn: 53 (hur bc > 2)
Actud Nunbcr oaTrrvcm Point.: 3
'&*.r+b-._
EJE&,
-Hr+
Trlr'eBe
Point
Vo otDlrmer
Dlltmca
frcfr lBld€
*all outid€ of
I
{
5
6
1
8
9
t0
ll
l7
t6.7
50.0
'1'
24.05
72.00
I 19.95
3J.80
83.7J
l3L?0
LOCATION OF TRAVERSE FOINTS
Nufrb.t of frawrs. points on o diaild.,
I
3
{
5
6
I
9
l0
It
J t 5 6 1 8 9 lo !t l,
t4.6 t6.7 61 - 4.{ - 1.2 - 26 - 2.1851 50.0 25.O - t{6 - l0.t - 8.2 - 6.1
- r3l 75.0 - 29.6 - l9.f - t{6 - ll.ri
.:tir,.ll
'Percant of tti-* dtffictet ftffi nsrlc N'all to ud,erft g\nt
Strcl Diagm
A= 7n.
A=6ln
DcprhofDu.l= 11{rn.
Cr6s S€riml k
Upfra.m
Di.rurb.nc.
A!6rce
SOUFCE TESTINC Method I Data
l^daion Ut.t - wdt Vdlcy
Soure Unll {
D(t Orianarlkmr Vdi6l
IXe! lrcrio: Circulu
Dirlm. lmd F.r W.ll ro Ourid. of Pon: 15J.75 in
Nlppk trnBh: I 1.75 lnDctihofD*r: li{.00 in
Cm.!Serirn.lArcrofD&t: llll0 frr
No. ofTail Pont: .l
DhrEC. A: 7.0 Il
Dirta. A lhs Dimkn: 06 (nut bc > 0-()
IrirtMC B: 61.0 ftDige. I Dlr DimlcE: 5J (mut bc > 2)
A$ul Numbar ofT[rara Polnlt: 3
LOCATION OF TRAVERSE POINTS
Nanba oI ttv..s. PirE il o fiM,
I
3
{
5
5
1
t
9
IOll
l2
7 I I 1 t to It t1
14.6 161 67
85 { 50.0 25.0
- r.l I ?5.0
93.3
1..1
l{.6
2t) 6
701
851'l'
_
3.:
10.5
19l
il.i
67.7
E0.(,
E95
%.8
2.6
82
l{.6
22.6
ll.2
6t.E
Tt.4
854
9t.8
2.t
(t.7
I t.8
111
250
356
64.4
75.0
82.3
EE.2
933
tPetc.il of \td* dt@cttt kM nsttL Nall to travry wnt
Trf,ratu
Pdnr '/. ol
Difficr
DirIac
rcfr t6ldrr!ll
lrcm
oufl& o,
I
3
I
s
6
7
I
I
l0ll
t2
t6.7
50.0,1'
:
24.05
72.00
I t9.95
35.E0
83.7J
ll L70
Stscl Dilgnm
A= 7n
B=63n
Dcprh ofDucr = l{{ in.
Cr6s Scti@l Arcs
UPatra.mil.rrtuM.
Al6rce
SOURCE TESTING Method I Data
ldriion Ulrh
D[tOri.ntrti(E: Vcnrol
ort nc.ign,-Tiiiiil
Di.t.mc frcm Frr wrll lo Outrid. of Pon: 155 75 in
Nlrnlc Lcngth: I I 75 in
DeDthofDBr: 144.m in
Crcri Setionrl AM of Dwt: I ll lo fr:
No.ofTcil Ponr: .1
DlrleccAi 70 fl
Dillffi. A DBI O.m.n: ft (m6t bc > 0-l)
Ditrucc B: 63 o ft
Dilrmcc B IrBl Diml.ni 5-1 (mul lrc > 2)
Actu{l NumberofTrrrcrrc Points: 3
LOCATION OF TRAVERSE FOINTS
Numb.t ofiowr$ ?oints oil o dlamcta
I
2
3I
s
6
1
t
9
t0
t!
3 J s 6 I 9 l0 ll l2
t46
85{
t67 61
500 150
r33 750: '1',
{l
ll (r
296
70 .t
E5 1
ll
t0 5
t9 .l
123
671
806
8t. J,:*
26
8l
l{6
22.6
1.1.2
65.8
?1 4
rJ4
9t t
,?1
2t
67
I 1.8
177
2J.0
lJ.6
(a4
75 r)
82i
s2.)l -l
'l'cricnt ol'na!* lrudetet lntn nshlc rilll to tt^.^c potnt
Trlr'ada
Polni
./6 oI
Diml€r
Dirtucc
fmm iaide
wrll
frem
outlida of
I
J
a
3
6
1
I
9
t0ll
16.7
50.0*:,
24 {t5
72 00
I 1995
35 80
83.75
ll L70
Strcl Di.gM
A=7n
B=63n
Dcpth of Duct = I {-l in.
Cr6s Scctioml Arca
Uprtraam
Driurbama
02 Summary
Locetion:
Source:
Project No.:
Run
No.Date Time Reference Method
()z Concentration
o/" dru
CEMS
Or Concentration
o/o drv
Average
Difference
o/o d,mStrrtEnd
I
2
J
.+
5
6
'7
8
9
l0
ll
l2
2/
2/
2/
2/
2/
2t
2/
2/
2/
2t
2l
2t
3t24
3/24
3t24
3/24
3/24
3t24
3t24
3t24
3t24
3t24
3t24
3t24
Averasr
Standard Deviation (Sd
Applicable Source Standard (AS
Confidence Coefllcient (CC
Relative Accuracy (RA
Perlbrmance Required - Mean Rel'erence Methoc RA s 20%
Pcrlormance Soecrfi cation Methoc PS3
Confi dence Coeffi cient, CC
cc=lff,sal
where.
lo l15
n
Sd
CC
d
c'c
RM
RA
#N/A_-=-=-(r-
degrees of fieedorn value
number of runs selected lirr calculating the RA
standard deviation oldiliercnce
confldence coeflicrent
: average drl'lerence of Rel'erence Method and CEMS
= conlldence coelllcient
= ret'erence rnethod. To dry
= relative accuracr'- 7o
Relative Accuracl', RA
na = fffi,.roo
where,
NOx Summary
Location: -- - --
Source: --
Project No.: --
Run
No.Drte Time Reference lllethod
NOx Concentration
nnmvd
CEMS
NOr Concentration
nnmvd
Average
Diffcrence
onmvdStartEnd
I
2
-1
1
5
6
'7
8
9
l0
lt
t2
2t
2/
2/
2t
2t
2/
2t
2/
2/
2l
)t
3t24
3/24
3/24
3t24
3t24
3t24
3t24
3t24
3t24
3t24
3t24
3t24
A verap.(
Standard Deviation (Sd
Applrcable Source Shndard (AS
Confi dence Coeffi cient (CC
Bias Adiustment Reouired (BA No
Bias Adtustment Factor (BAF r 000
Relative Accuracy (RA) - Hide Row
Relative Accuracy (RA
Perliirmance Required - Mean Rel'erence Methoc RA:20%
S('AQMD RECLAI M CRITERIA:
Does source Qualily as L.orv Emitter'l RM average < 5 ppmv<No
Altemative Criteria for [-orv Emitter per R2012-Chapter 2, Eq. 9c ls ldl+lccl < I ppmv'#VALTIE:
ldl+lcc #VALTiE:
Performance Specifi cat ion Methoc PS2
CVALLJEI
Conlidence Coefficient. CC
cc = lto=t, sallVn I
where.
turr,1f\!]!_: degrees of thedom value
n 0 : number olruns selected lbr calculating the RA
Sd-: standard deviation of ditterence
CC
-:
conlilence coelficient
Relative Accuracy, RA
ldl+lcclRA = 'x 100AS or RM
where.
d-= average dtf'lbrence of Reference Method and CEMS
CC _= confidence coefficient
RM_= rel'erence rnelhod. ppmvd
RA : relative accuracv. To
CO Summaty
l,ocation: -- - --
Source: -
Project No.: -
Run
No.Date Time Reference Method
CC) Concentration
nnmvd
CEMS
CO Concentration
nnmvd
Average
Difference
onmvdStartEnd
I
2
3
.l
5
6
'7
8
9
t0
II
t2
2/
il
2t
2l
2t
2t
2t
2t
2t
2t
2t
)/
3t24
3t24
3t24
3t24
3/24
3t24
3t24
3t24
3t24
3t24
3t24
3t24
Averaur
Standard Deviation (Sd
Applicable Source Standard (AS
Confidence Coefllcient (CC
Bias Adiustment Required ( BA No
Bias Adlustment Factor (BAF I 000
Relative Accuracv (RA) - t{ide Row
Relative,{ccuracv (RA
Pert'ormance Required - Mean Ret-erence Method RA s l0%
Perforrnance Specr frcation Method PS 4A
Alternative Relative Accuracv (R{#VALUEI
Altemative Perlirnnance Required (d + CC <5oom
Performance Speci fi cation Method PS 4A
#vALUEl
(lonfidence Coefficient, CC
cc = lto'gt , sallVn I
where,
t,,rzi_{}|11!= degrees of freedom value
n 0 = number ofruns selccled for calculating the RA
s,t-= stunrlar.l deviatron of rlifferencc
CC
-:
conlidence coellicrent
Relative Accuracy, RA
ldl+lcclRA - 'x 100AS or RM
where.
d .: average difference of Reference Method and CEMS
CC
-
: contldence coeflicient
,aM
-=
rcrcrcncc metn()d- ppmvo
RA
-=
relatn e accuracr', 7o
pJ/ta
t-
Runl-RMDatalGe
, i ji
Lcstion: - - -
Sourcc: -Projecl No.: -Date:
Time
tjnit
Strtus
Or - Outlct
6/. dry
COr - Outlet
lo dry
CO - Outlct
ppmvd
NOr - Outlct
ppwd
Unco.rectcd Run Avcrr8e (C"L)
C.l Grs Co.ccntrelion (Crr^)
Prctcit Sysiem Zero Rdponle
Posit6a System Zero Rsponse
Avcru8c Zero Responsc (('o)
Prel$t Sysrcm Csl R6pon!.
Posltest Systcm Csl R6ponse
Averegc Cal RdpoNG (C\t)
#N/A4N/_{
QA Data
Location -- - --
Source --
Project No. -
Parameter Oz - Outlet COz - Outlet CO - Outlet NOx - Outlet
Make
Model
S/N
Ooeratins Ranse
Cylinder ID
Z*ro
Low
Mid
Hish
NA
)1
NA
t1
NA
t1
NA
)1
Cylinder Certifed Values
Zero
Low
Mid
Hish
NA
l1
NA
Y
NA
Y
NA
r1
Cylinder Expiration Date
Zero
Low
Mid
Hish
NA
i1
NA
i1
NA
i1
NA
i1
Tvne of Samole Line
Calibration Data
Project No.: --
Date: 2ll3l24
Parameter Oz - Outlet COu - Outlet CO - Outlet NOx - Outlet
Exoected Average Concentration
Span Between
Low
High
Desired Span
Low Range Gas
Low
Hish
NA
NA
NA
NA
NA
NA
NA
NA
Mid Range Gas
Low
Hieh
High Range Gas
Low
Hish
NA
NA
NA
NA
NA
NA
NA
NA
Actual Concentration (7o or ppm)
7,ero
Low
Mid
Hish
0.00
NA
0.00
i1
0.00
i1
0.00
i1
Response Time (seconds)
Upscale Calibration Gas (C-^)
lnstrument Response (7o or ppm)
7*ro
Low
Mid
Hieh
NA NA NA NA
Performance (o/o of Span or Cal. Gas Conc.)
Zero
Low
Mid
Hish
NA NA NA NA
Status
7*ro
Low
Mid
Hioh
NA NA NA NA
Bias/D rift Determinations
Location:
Source:
Project No.:
Parameter O: - Outlet COr - Outlet CO - Outlet NOx - Outlet
Run I Date 2ll3l21
Span Value
I nitial Instrunrent Zero Cal Response
Initial Instrument Upscale Cal Response
Pretest System Zero Response
Posttest System Zero Response
Pretest System Upscale Response
Posftest System Upscale Response
#N/A #N/A #N/A #N/A
Bias (%)
Pretest Zero
Posttest Zero
Pretest Span
Posttest SDan
)rift (%)
lero
\4id
Run 2 Date 2ll3l24
Span Value
lnstrument Zero Cal Response
lnstrument Upscale Cal Response
Pretest System Zero Response
Posttest System Zero Response
Pretest System [Jpscale Response
Posttest System UDscale Resoonse
#N/A #N/A #N/A #N/A
Bias (%)
Pretest Zero
Posftest Zero
Pretest Span
Posttest Snan
Drift (%)
Zero
Mid
Run 3 Date 2ll3l21
Span Value
lnstrument Zero Cal Response
Instrument Upscale Cal Response
Pretest System Zero Response
Posttest System Zero Response
Pretest System Upscale Response
Posttest System Upscale Response
#N/A #N/A #N/A #N/A
Bias (%)
Pretest Zero
Posttest Zero
Pretest Span
Posttest Snan
Drili (%)
Zero
Mid
putErlpe
Location: -- - --
Project No.: --
NO2 Converter Check - Outlet
Analyzer Make
Analyzer Model
Serial Number
Cylinder ID Number
Cylinder Exp. Date
Cvlinder Concentration. DDm
Pre-Test Date Time
Pre-Test Concentration, ppm
Pre-Test Efficiencv. 7o
Post-Test Date Time
Post-Test Concentration, ppm
Post-Test Effi ciencv. 7o
*Elliciency is > 90 %.
pul6rpe
It-..I l: lr.. .,tl
Location: -- - --
tl
Source: --
Project No.: --
Run No. /Method Run I / Method 34
Oz - Outlet Concentration (Co,), Vo dry
Co,: (Cou,-Co)x ( ft;)
Cob,
co
average analyzer value during test, % dry
Co average ofpretest & posttest zero responses,o/o dryCMA-FfF= actual concentration of calibration gas, % dry
C,T=averageofpretest&posttestcalibrationresponses,%odry
Co,T= oz Concentration, % dry
where,
pJ/t6
Source: --
Project No.: --
Run No. /Method Run I / Method l0
CO - Outlet Concentration (Cco), ppmvd
Cco: (Co6,-Cs)x ( $-.r-;)
where,Cob, average analyzer value during test, ppmvd
CoT=averageofpretest&posttestzeroreSponSes,ppmvdCMA-FfF= actual concentration of calibration gas, ppmvd
C*T=averageofpretest&posttestcalibrationresponSes'ppmvdC.oT= Co Concentration, ppmvd
pul6rpe
t't l'i" )-. i,l'iLLocation: -- - --
Source: --
Project No.: --
Run No. /tlethod Run I / Method 7E
NOx - Outlet Concentration (Cno,), ppmvd
Cr.,o*: ( Cop,-C6 ) x t aa,Iia. I
where,
= average analyzer value during test, ppmvd
CoT=averageofpreteSt&posttestzeroresponses,ppmvdCMA-FfF: actual concentration of calibration gas, ppmvd
CM
Cno,
= average ofpretest & posttest calibration responses, ppmvd: NOx Concentration, ppmvd
DEPARTMENT OF
ENVIRONMENTAL OUAUTY
MAR 2 8 2025
DIVISION OF AIR OI,IAUW