HomeMy WebLinkAboutDERR-2025-002531Utah Department of Environmental Quality - UST Release Detection
TANK OWNERSHIP
Name BROTHER & SON LLC / SID SAFI
Address 802 S 900 W
SALT LAKE CITY, UT 84105
Contact BROTHER & SON LLC / SID SAFI
Phone
Email naseerlee@msn.com
TANK LOCATION
Name SHOP & SAVE
Address 1302 S STATE ST
SALT LAKE CITY, UT 84115
A Operator GHULAM SEDDIQUE SAFI
Phone (801) 652-2332
B Operator SAME
Phone SAME
Facility ID: 4001248 Inspection Date: 04/03/2025
DISPENSER DETAILS
DISP
ID/ALT
ID
SUBSTANCE UDC PIPE FLEX LOC
INSTALL
DATE
UDC
INSTALL
DATE
FIRE
VALVE
SAT
PRESENT
UDC
TEST
DISP
FLEX
CP
TEST
1 - 1/2 Gasoline No Booted Steel Flex None None Yes No None None
2 - 3/4 Gasoline No Booted Steel Flex None None Yes No None None
3 - 5/6 Gasoline No Booted Steel Flex None None Yes No None None
4 - 7/8 Gasoline No Booted Steel Flex None None Yes No None None
TANK DETAILS
Tank ID/Alt ID 1 / 1A
E-Gen/AST No / No
Siphon/Compart No / Yes
Tank Status Currently In Use
Installed/Cap/Loc June 1, 1990 / 10000 / West
Substance
Stored Gasoline / Regular
Tank Material-
Mod Composite (Steel w/ FRP)-None
ATG Veeder Root / TLS-350 CSLD No
Manifold
LTT Test Dec. 19, 2024
LLD Test Dec. 19, 2024
Pipe Material-
Mod
Fiberglass Reinforced Plastic /
None
Pipe type/STP
Cont Pressurized / No
STP Flex
Connectors Booted Steel Flex
LLD Model Red Jacket / VR FX1V
Spill/Overfill/Sm
Delivery
5 gal. Spill Bucket / Automatic
shutoff / No
PST Fund/Other
Type Yes / None
Tank/Pipe Rel
Det
TankATG
PipeAutoLineLeakDetection /
PipeLineTightness
CP Tank Test None
CP Pipe Test None
Tank ID/Alt ID 6 / 1B
E-Gen/AST No / No
Siphon/Compart No / Yes
Tank Status Currently In Use
Installed/Cap/Loc June 1, 1990 / 5000 / Center
Substance
Stored Gasoline / Premium
Tank Material-
Mod Composite (Steel w/ FRP)-None
ATG Veeder Root / TLS-350 CSLD No
Manifold
LTT Test Dec. 19, 2024
LLD Test Dec. 19, 2024
Pipe Material-
Mod
Fiberglass Reinforced Plastic /
None
Pipe type/STP
Cont Pressurized / No
STP Flex
Connectors Booted Steel Flex
LLD Model Red Jacket / VR FX1V
Spill/Overfill/Sm
Delivery
5 gal. Spill Bucket / Automatic
shutoff / No
PST Fund/Other
Type Yes / None
Tank/Pipe Rel
Det
TankATG
PipeAutoLineLeakDetection /
PipeLineTightness
CP Tank Test None
CP Pipe Test None
2025-04-03 Page 1 of 7
Tank ID/Alt ID 7 / 1C
E-Gen/AST No / No
Siphon/Compart No / Yes
Tank Status Currently In Use
Installed/Cap/Loc June 1, 1990 / 5000 / East
Substance
Stored Gasoline / Premium
Tank Material-
Mod Composite (Steel w/ FRP)-None
ATG Veeder Root / TLS-350 CSLD No
Manifold
LTT Test Dec. 19, 2024
LLD Test Dec. 19, 2024
Pipe Material-
Mod
Fiberglass Reinforced Plastic /
None
Pipe type/STP
Cont Pressurized / No
STP Flex
Connectors Booted Steel Flex
LLD Model Vaporless LD2000
Spill/Overfill/Sm
Delivery
5 gal. Spill Bucket / Automatic
shutoff / No
PST Fund/Other
Type Yes / None
Tank/Pipe Rel
Det
TankATG
PipeAutoLineLeakDetection /
PipeLineTightness
CP Tank Test None
CP Pipe Test None
INSPECTION COMMENTS
None
2025-04-03 Page 2 of 7
FACILITY RESPONSES
Financial Responsibility
Financial responsibility method is ok?Yes
The above accurately represents the
facility's release detection records Yes
Operator Training
A Operator current?Yes
B Operator current?Yes
Monthly checklist available and
complete?Yes
Is the site unmanned?No
C Operators trained?Yes
TANK RESPONSES
Tank 1A Spill/Overfill
Tank has a spill prevention device?Yes
Are you able to visually inspect the spill
containment bucket(s) for functionality?
(i.e. are the buckets clean enough to
see cracks, etc?)
Yes
Is the spill containment bucket intact?Yes
Does the Spill Prevention device have a
potential to release product into the
environment?
Yes
Is the spill containment bucket(s) able
to contain a spill? (i.e. is there water,
product, debris, etc in the spill bucket
to prevent it from containing a spill?)
Yes
Tank has an overfill device?Yes
Tank 1A ATG/IM
ATG/IM - Records on site document that
the system is properly installed,
calibrated, operated, and maintained
(system and tank setup reports,
maintenance records)? Written
documentation of calibration,
maintenance, and repair is kept for at
least one year after work is completed?
Yes
ATG/IM - ATG console or other
equipment used to take readings and
perform tests is adequate, accessible,
and operational?
Yes
ATG/IM - Documentation of valid testing
or monitoring is available (must have
records for the two most recent months
and 10 of last 12 months)? Show results
in the RD tab.
Yes
ATG - The tank was filled to at least the
minimum level required to ensure a
valid leak test, and the tank size is
within the allowed upper and lower size
limits?
Yes
Tank 1A Cathodic Protection
Tanks are protected from corrosion?Yes
Piping is protected from corrosion?Yes
Flex connectors at the tank sub-pumps
are protected from corrosion?Yes
Tank 1A Pressure Piping Leak Detection
Does the pressurized piping system
have a line leak detector?Yes
Does the pressurized piping system
have a valid line leak detector test?Yes
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
Yes
Tank 1A Spill/Overfill
Does the spill bucket have a valid 3-
year test, valid monthly monitoring for
DW buckets, or the tank is exempt?
Yes
Does the overfill device have a valid 3-
year test or the tank is exempt?Yes
Tank 1B Cathodic Protection
Tanks are protected from corrosion?Yes
Piping is protected from corrosion?Yes
Flex connectors at the tank sub-pumps
are protected from corrosion?Yes
Tank 1B Pressure Piping Leak Detection
Does the pressurized piping system
have a line leak detector?Yes
Does the pressurized piping system
have a valid line leak detector test?Yes
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
Yes
2025-04-03 Page 3 of 7
Tank 1A ATG/IM
Does the ATG system have a valid
annual test?Yes
Tank 1B Spill/Overfill
Tank has a spill prevention device?Yes
Are you able to visually inspect the spill
containment bucket(s) for functionality?
(i.e. are the buckets clean enough to
see cracks, etc?)
Yes
Is the spill containment bucket intact?No
Does the Spill Prevention device have a
potential to release product into the
environment?
Yes
Is the spill containment bucket(s) able
to contain a spill? (i.e. is there water,
product, debris, etc in the spill bucket
to prevent it from containing a spill?)
Yes
Tank has an overfill device?Yes
Tank 1B ATG/IM
ATG/IM - Records on site document that
the system is properly installed,
calibrated, operated, and maintained
(system and tank setup reports,
maintenance records)? Written
documentation of calibration,
maintenance, and repair is kept for at
least one year after work is completed?
Yes
ATG/IM - ATG console or other
equipment used to take readings and
perform tests is adequate, accessible,
and operational?
Yes
ATG/IM - Documentation of valid testing
or monitoring is available (must have
records for the two most recent months
and 10 of last 12 months)? Show results
in the RD tab.
Yes
ATG - The tank was filled to at least the
minimum level required to ensure a
valid leak test, and the tank size is
within the allowed upper and lower size
limits?
Yes
Tank 1B ATG/IM
Does the ATG system have a valid
annual test?Yes
Tank 1C Spill/Overfill
Tank has a spill prevention device?Yes
Are you able to visually inspect the spill
containment bucket(s) for functionality?
(i.e. are the buckets clean enough to
see cracks, etc?)
Yes
Is the spill containment bucket intact?Yes
Is the spill containment bucket(s) able
to contain a spill? (i.e. is there water,
product, debris, etc in the spill bucket
to prevent it from containing a spill?)
Yes
Tank has an overfill device?Yes
Tank 1B Spill/Overfill
Does the spill bucket have a valid 3-
year test, valid monthly monitoring for
DW buckets, or the tank is exempt?
Yes
Does the overfill device have a valid 3-
year test or the tank is exempt?Yes
Tank 1C Cathodic Protection
Tanks are protected from corrosion?Yes
Piping is protected from corrosion?Yes
Flex connectors at the tank sub-pumps
are protected from corrosion?Yes
Tank 1C Pressure Piping Leak Detection
Does the pressurized piping system
have a line leak detector?Yes
Does the pressurized piping system
have a valid line leak detector test?Yes
Does the pressurized piping system
have a valid annual line tightness test
or valid monthly monitoring?
Yes
Tank 1C Spill/Overfill
Does the spill bucket have a valid 3-
year test, valid monthly monitoring for
DW buckets, or the tank is exempt?
Yes
Does the overfill device have a valid 3-
year test or the tank is exempt?Yes
2025-04-03 Page 4 of 7
Tank 1C ATG/IM
ATG/IM - Records on site document that
the system is properly installed,
calibrated, operated, and maintained
(system and tank setup reports,
maintenance records)? Written
documentation of calibration,
maintenance, and repair is kept for at
least one year after work is completed?
Yes
ATG/IM - ATG console or other
equipment used to take readings and
perform tests is adequate, accessible,
and operational?
Yes
ATG/IM - Documentation of valid testing
or monitoring is available (must have
records for the two most recent months
and 10 of last 12 months)? Show results
in the RD tab.
Yes
ATG - The tank was filled to at least the
minimum level required to ensure a
valid leak test, and the tank size is
within the allowed upper and lower size
limits?
Yes
Tank 1C ATG/IM
Does the ATG system have a valid
annual test?Yes
DISPENSER RESPONSES
Dispenser 3/4
Flex connectors at the dispensers are
protected from corrosion?Yes
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
Dispenser 7/8
Flex connectors at the dispensers are
protected from corrosion?Yes
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
Dispenser 1/2
Flex connectors at the dispensers are
protected from corrosion?Yes
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
Dispenser 5/6
Flex connectors at the dispensers are
protected from corrosion?Yes
Fire valve is anchored properly?Yes
Does the line tightness test port on the
fire valve have the manufacturers plug
installed in it? (no ball valves)
Yes
Is the fire valve located properly below
grade?Yes
Is the fire valve's fuseable link intact?Yes
2025-04-03 Page 5 of 7
MONTHLY LEAK DETECTION MONITORING
Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25 Feb '25 Mar '25
Tank 1 Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Tank 6 Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
Tank 7 Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass Pass
Line Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl Not Appl
NON-COMPLIANCE ITEMS
TANK 1B
Question:Is the spill containment bucket intact?
Comments:liquid in the interstice
2025-04-03 Page 6 of 7
Prepared by fueloperator.com
Inspection Information
Inspector:Warner, Sean
Record Created:April 3, 2025, 9:22 a.m.
Inspection Date:April 3, 2025
2025-04-03 Page 7 of 7