---------- Forwarded message ---------
From: Nick Clarke <nmclarke@energysolutions.com>
Date: Thu, Aug 3, 2023 at 4:20 PM
Subject: IUF South Bay BAT Inspection
To: llrw@utah.gov <llrw@utah.gov>, Charles Bishop <charlesbishop@utah.gov>, Brandon Davis <bbdavis@utah.gov>
Cc: Robert W. Sobocinski <rwsobocinski@energysolutions.com>, Steve D. Gurr <sdgurr@energysolutions.com>, Vern C.
Rogers <vcrogers@energysolutions.com>, Garrett Q. Dutson <gqdutson@energysolutions.com>, Otis Willoughby III
<owilloughby@utah.gov>, Brennon Dick <bdick@energysolutions.com>
Good Afternoon,
This morning on 8/03/2023 EnergySolutions performed the pre-inspection of the south bay, post clean up from the south
dividing wall removal. Deficiencies were identified and pictures were taken. The repairs were made throughout the day
and a post-inspection was performed this afternoon. All of the repairs identified were corrected with satisfactory results.
Pictures were taken of all of the repairs and are saved on file.
The south bay of the Intermodal Unloading Facility (IUF) will be placed back on-line tomorrow 8/04/2023 and will resume
operations.
Please let me know if you have any questions.
Thank you,
Nick Clarke