HomeMy WebLinkAboutDSHW-2025-001312Deq submit <dwmrcsubmit@utah.gov>
UDEQ Spill Report Follow-up (19516)
1 message
Ken McQueen <ken.mcqueen@coolskyenergy.com>Thu, Mar 6, 2025 at 9:33 AM
To: "dwmrcsubmit@utah.gov" <dwmrcsubmit@utah.gov>
Daniella,
Apologies, I thought we sent this last week.
Please let me know if you need anything else.
--
Daniella Leeber
Environmental Scientist | Hazardous Waste
Office: (385) 499-0283
Office Hours: MTW 7:00am-
5:00pm
Main Line: (801) 536-0200
Email: dleeber@utah.gov
Electronic Document
Submittal
Portal: dwmrcsubmit@utah.gov
wasteandradiation.utah.gov
Emails to and from this email address may be considered public records and thus
subject to Utah GRAMA requirements.
3/6/25, 3:11 PM State of Utah Mail - UDEQ Spill Report Follow-up (19516)
https://mail.google.com/mail/b/AEoRXRSYroS_jWomOT_fUNQIMOVeut6Gw1kG5gOeBlwHP3ZDzkrC/u/0/?ik=adf9d5e615&view=pt&search=all&perm…1/2
Statements made in this email do not constitute the official position of the Director of
the Division of Waste Management and Radiation Control. If you desire a statement of
the Division Director's position, please submit a written request to the
Director, including copies of documents relevant to your request.
<Incident Report 19516 - Unitah_ Co Produced Water_ ARB Energy Utah 2025-02-24 (1).pdf>
<2025.26.03_ARBEnergy_MainCanyonFederal11-10-15-23_SpillRemediation.docx>
2025.26.03_ARBEnergy_MainCanyonFederal11-10-15-23_SpillRemediation.docx
2232K
3/6/25, 3:11 PM State of Utah Mail - UDEQ Spill Report Follow-up (19516)
https://mail.google.com/mail/b/AEoRXRSYroS_jWomOT_fUNQIMOVeut6Gw1kG5gOeBlwHP3ZDzkrC/u/0/?ik=adf9d5e615&view=pt&search=all&perm…2/2
Spill Remediation
For the
Main Canyon Federal 11-10-15-23
February 2025
ARB Energy Utah, LLC
23501 Cinco Ranch Blvd.
Suite B244
Katy, TX 77494
Consultants to ARB Energy
Coolsky Energy, LLC
310 E. Broadway
Prosper, TX 75078
CONTENTS
1 Project Description 2
2 Background 2
3 Notifications:2
4 Volume reported spilled:2
5 Spill Area 2
6 Initial Site Photo of Spill 3
7 Remediation 3
1 Project Description
Operator ARB Energy Utah, LLC
API Number 43-047-30639
Well Location Name Main Canyon Federal 11-10-15-23
Legal Location 39.528475, -109.33269722222222
Spill/Release Area ~1157 square feet
Total Initial Remediation Area ~1300 Square Feet
This document describes the spill, the extent of the spill, and the cleanup that occurred.
2 Background
The release was discovered on February 3, 2025, and was the result of check valve failure and pipeline freeze and
break. The release made its way down gradient across the site approximately 50 feet. There were no injuries as a result
of the release. The hazards to the environment were resolved with the removal of the affected soil.
3 Notifications:
The initial spill notification was sent to Mike Zucker at UDEC on February 13, 2025.
4 Volume reported spilled:
As per Pumper Jonathon Denniston, approximately 5-10 barrels of produced water was spilled.
5 Spill Area
Estimate of spill area is approximately 1157 sq feet.
6 Initial Site Photo of Spill
7 Remediation
Area of remediation was approximately 1300 square feet. Stubbs and Stubs excavated two dump loads (approximately
20 yards) of material and brought in two dump loads of fresh material. Impacted soil was removed from location and
disposed of at DHI Companies, Dalbo, INC & RN Industries – PO Box 1168 Vernal Utah. Office: 435-722-2800 Email:
DHI-AR@Dalboholdings.com.