HomeMy WebLinkAboutDRC-2025-00014501" of Waste M2na92:• '"'· 1t
and Radiation Control
JAN O 9 2025
a a ;:::::::-
ENERGYSOLUTIONS
CLASS A WEST EMBANKMENT
CLIVE UTAH
PHASE 6 FINAL COVER
CONSTRUCTION REPORT
&
AS-BUILT DRAWINGS
December 16, 2024
DUPLICATE COPY
TABLE OF CONTENTS
1.0 INTRODUCTION .................................................................................................. 1
1.1 Background ............................................................................................................ 1
1.2 Key Project Staff .................................................................................................... 1
1.3 Project Documentation .......................................................................................... 2
1.3.1
1.3.2
1.3.3
1.3.4
Daily Construction/Activity Reports ....................................................... 2
Construction Quality Assurance/Quality Control Testing &
Monitoring .................................................................................................. 2
Project Photographs ................................................................................ 3
Non-Conformance Reports ....................................................................... 3
1.4 Construction Activities .......................................................................................... 3
2.0 RADON BARRIER PLACEMENT ..................................................................... 3
2.1 Construction Activities ......................................................................................... 3
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
2.1.7
2.1.8
General ........................................................................................................ 3
Clay Borrow .............................................................................................. 4
Clay Stockpiles and Processing ................................................................ 4
Radon Barrier Placement and Compaction ........................................... 4
Radon Barrier Permeability ..................................................................... 5
Lift Bonding ............................................................................................... 5
Radon Barrier Key-In to Construction .................................................... 5
Final Grading ............................................................................................. 6
2.2 Quality Control Support Summary ................................................................... 6
2.3 Corrective Actions ................................................................................................. 6
2.4 Field Changes ......................................................................................................... 6
3.0 COVER ROCK PREPARATION ......................................................................... 7
3.1 Construction Activities .......................................................................................... 7
3.1.1
3.1.2
3.1.3
General ........................................................................................................ 7
Petrographic Examination of Aggregate ................................................. 7
Rock Quality Testing and Gradations ..................................................... 7
3.2 Quality Control Support Summary ..................................................................... 8
3.3 Material Gradation and Permeability Testing .................................................... 8
3.4 Corrective Actions ................................................................................................. 9
3.5 Field Changes ......................................................................................................... 9
4.0 COVER ROCK PLACEMENT ............................................................................. 9
4.1 Construction Activities .......................................................................................... 9
4.1.1
4.1.2
4.1.3
CAW Phase 6 Cover
Construction Report
General ........................................................................................................ 9
Filter Zone and Sacrificial Soil Placement ............................................ 10
Type A and B Riprap Placement ............................................................ 10
DUPLICATE COPY Date: December I 6, 2024
Revision: 0
4.2 Quality Control Support Summary .................................................................. .11
4.3 Corrective Actions ............................................................................................... 11
4.4 Field Changes ....................................................................................................... 11
5.0 COVER TERMINATION FOR FUTURE TIE IN ............................................ 11
5.1 General .................................................................................................................. 11
5.2 Construction Activities ........................................................................................ 11
6.0 DRAIINAGE DITCH BACKFILL AND GRADING ......................................... 12
6.1 Construction Activities ........................................................................................ 12
6.1.1 General ...................................................................................................... 12
6.1.2 Clay Borrow ............................................................................................. 12
6.1.3 Ditch Backfill Placement and Compaction ............................................ 12
6.1.4 Final Grading ........................................................................................... 13
6.2 Quality Control Support Summary ................................................................... 13
6.3 Corrective Actions ............................................................................................... 13
6.4 Field Changes ....................................................................................................... 13
7.0 INSPECTION ROAD ............................................................................................. 14
7.1 Construction Activities ........................................................................................ 14
7.1.1 General ...................................................................................................... 14
7.1.2 Roadbase Material ................................................................................... 14
7.1.3 Subsurface Preparation ........................................................................... 14
7.1.4 Road Base Placement and Compaction ................................................. 14
7.2 Quality Control Support Summary ................................................................... 14
7.3 Corrective Actions ............................................................................................... 14
7.4 Field Changes ....................................................................................................... 14
8.0 SETTLEMENT MONUMENT INSTALLATION ............................................. 15
8.1 General .................................................................................................................. 15
8.2 Construction Activities ........................................................................................ 15
9.0 AS-BUILT DRAWINGS .................................................................................... 15
APPENDICES
APPENDIX A ........................................................................ Select Project Photographs
APPENDIX B ....................................................................................... As-Built Drawings
CAW Phase 6 Cover
Consnuction Report DUPLIC~'TE COPY Date: December 16, 2024
Revision: 0
1.0 INTRODUCTION
EnergySolutions has prepared the following Construction Report and As-Built
Drawings for the Class A West (CAW) Phase 6 Cover Construction work. The
report was prepared by the Project Engineer and was reviewed by the Project
Manager, the Quality Control (QC) Supervisor and Construction Quality
Assurance. This report includes a description of construction activities,
photographs, and As-Built Drawings for all construction activities.
1.1 Background
All construction was performed in compliance with the CAW cover project
construction contract agreement, plans, specifications, and the LLRW and 11 e.(2)
Construction Quality Assurance/Quality Control (CQA/QC) Manual, Revision 28c,
Dated February 12, 2020 (CQA/QC Manual) as approved by the Utah Division of
Waste Management and Radiation Control (UDWMRC).
Construction of the Class A West Phase 6 Cover Construction project was initiated
with the beginning of the excavation, preparation and stockpiling of radon barrier
and screening of rock erosion materials in 2023 ( during Phase V) and 2024 by
Broken Arrow, Inc. Cell construction of the Phase 6 CAW cover (radon barrier
placement) began on August 20, 2024. The CAW cover consisted of completing
the cover construction north and adjacent to the Phase 3 and 4 Cover projects as
shown on the project drawings and in the project photographs. The CQA/QC
Manual required final cover settlement monuments located on the CAW top slopes
be installed during construction atop the completed radon barrier and then carefully
buried within the subsequent rock layers.
Broken Arrow performed gross excavation activities required for clay mining,
preparation, and stockpiling of radon barrier during 2023 and 2024 and
reconditioned that material, as needed, for the Phase 6 work. Broken Arrow
performed all subsequent radon barrier and rock construction activities using the
cover materials produced in 2023 and in 2024 as noted above.
Wiss, Janney, Elstner Associates, Inc. (WJE) and Montgomery Watson Harza
(MHW) performed the Petrographic Studies of Aggregates for the rock cover
sources. EnergySolutions, with limited support from RB&G Engineering,
performed quality control inspections and quality assurance testing of the Type A
and B Filter Zones, Sacrificial Soil, Type A and B Ripraps, Radon Barrier, Ditch
Fill, and Inspection Road. All quality control activities were conducted in
accordance with the CQA/QC Manual and construction drawings.
1.2 Key Project Staff
The following personnel held key positions during the construction of the CAW
cover project.
CAW Phase 6 Cover
Construction Report
December 16, 2024
Revision: 0
EnergySolutions of Utah, LLC.
Project Manager:
Project Engineer:
Quality Control Supervisor:
Quality Assurance Manager:
Quality Assurance Specialist:
Quality Control Technicians:
Todd Stewart
Garrett Q. Dutson, PE
James Cason
Curtis Kirk
Shauna Watkins
Marissa Sotello, Sherlie Gonzales,
John Kenison, and Stewart Ekins
EnergySolutions of Utah, LLC (Temporary Cover)
Manager, Waste Disposal Operations: Brennon Dick
Roger Ekins Project Superintendent:
Broken Arrow (General Construction Contractor)
Project Manager:
Project Superintendent:
WJE (Petrographic Studies of Aggregates)
Associate Principal:
Dave Cummings
Shane Martin
L Brad Shotwell
RB&G Engineering, Inc. (Geotechnical Laboratory and Field support)
Quality Control: Jacob Boone and BrieAnna Osborne
State of Utah Department of Waste Management and Radiation Control
Primary Inspector: Carlo Romano
1.3 Project Documentation
1.3.1 Daily Construction/Activity Reports
Daily Construction Reports, providing specific daily construction activities and QC
inspections, testing and observations were prepared by the EnergySolutions QC
Technicians. The project QC documentation is located on file at EnergySolutions'
Clive Site.
1.3.2 Construction Quality Assurance/Quality Control Testing & Monitoring
Construction quality assurance/quality control (CQA/QC) activities were
performed in accordance with the CQNQC Manual and monitored by the QA. All
CQNQC testing results and monitoring documentation were provided to QA and
were made available to the UDWMRC for inspection and will be maintained as
required.
CAW Phase 6 Cover
Construction Report DUPLI C,~TI: COPY December 16, 2024
Revision: 0
1.3.3 Project Photographs
Project photographs representing the project were taken during construction.
Several representative photographs of the different stages of construction are
provided at Appendix A.
1.3.4 Non-Conformance Reports
No non-conformance reports were issued nor required for this work element.
1.4 Construction Activities
The Class A West Phase 6 Cover construction consisted of six (6) basic
construction elements:
I . Radon Barrier Placement: Excavation, preparation, stockpiling, verification
testing, placement, and testing of radon barrier material. Previously approved
test pad plans (TP-2019-2 and TP-2021-1) were utilized in this phase of
construction.
2. Cover Rock Preparation: Screening, stockpiling, and verification testing of
the cover erosion materials.
3. Cover Rock Placement: Sacrificial Soil & Type A and B Filter Zones: and
Type A and B Riprap placement and inspection and verification testing.
4. Cover Termination Protection: Installation and inspection of geotextile and
sandbags.
5. Drainage Ditch Backfill & Grading: Ditch fill placement, inspection, and
verification testing. Ditch grading, inspection, and survey verification.
6. Inspection Road : placement, inspection and verification testing and surveying
of the Phase 6 haul road.
7. Settlement Monument Installation: placement, inspection, and survey.
2.0 RADON BARRIER PLACEMENT
2.1 Construction Activities
2. 1.1 General
In general, all radon barrier construction and radon barrier clay material stockpiling
activities were observed by EnergySolutions' Quality Control and documented on
daily reports. All required sampling and testing were performed in accordance with
the CQA/QC Manual. Construction activities were also observed by various
EnergySolutions personnel (Project Manager, Project Engineer, QC Supervisor,
QC Technicians, and QA Specialist) and the UDWMRC. Class A West Phase 6
Cover radon barrier construction included placement, testing, and approval of all
CAW Phase 6 Cover
Construction Report DUPLl 0A31E COPY December 16, 2024
Revision: 0
radon barrier lifts as discussed below. Successful final surveys and joint inspections
were held as required.
2.1.2 Clay Borrow
Broken Arrow was approved to excavate clay from an approved location on
EnergySolutions property in Section 5. The approved clay borrow site was cleared
and grubbed as required. Broken Arrow used haul trucks and a track hoe to excavate
clay and deliver to the stockpile processing area.
The clay material used for the CAW cover project met the required soil
Classification, Liquid Limit, Plasticity Index, and Gradation as required by the
specifications and the CQA/QC Manual. In addition, the clay material did not
contain debris, vegetation, or any other deleterious material.
2.1.3 Clay Stockpiles and Processing
It was determined during stockpile construction, from experience and from the test
pads, that Broken Arrow would prepare clay material stockpiles prior to placement
of the clay material in the cells.
Approximately 20,684 cubic yards of lxI0-6 cm/sec and 16,574 cubic yards of
5x I o-8 cm/sec radon barrier materials were prepared and stockpiled in Section 5
( during 2023 and 2024) for cover construction according to a Broken Arrow survey.
Approved Test Pad TP-2019-2 was followed by Broken Arrow for the lxI0-6
cm/sec radon barrier clay material preparation. Approved non-deflocculant 2021
Test Pad TP-2021-1 was followed by Broken Arrow for the 5x 10-8 cm/sec radon
barrier clay material preparation. Broken Arrow used a Soil Recubic
yardscler/Stabilizer to evenly mix the 5xI0-8 cm/sec clay as required by the TP-
2021-01 test plan to ensure that the dry clod size of the material was less than one .
inch.
The total placed radon barrier volume for Phase 6 was approximately 27 ,944 cubic
yards; therefore, a minimum often (10) Proctors at a 3,000 cubic yard lot rate, and
six (6) laboratory classification tests were required at a 5,000 cubic yard lot rate.
Fifteen ( 15) proctors and fifteen (15) classification soil analyses were performed
for the radon barrier clay material pertinent to this Phase. For the CAW cover
project, all proctors and classification testing reports that were completed for use
with the radon barrier density testing were found to conform to the specifications
and the CQA/QC Manual.
2.1.4 Radon Barrier Placement and Compaction
The two test pads, TP-2019-2 and TP-2021-1 were used for the Phase 6 radon
barrier placement. TP-2019-2 is for the placement of lxI0-6 cm/sec clay, and TP-
2021-1 is for the placement of 5x 1 o-s cm/sec clay. Copies of approved test pads
are on file.
CAW Phase 6 Cover
Construction Report DUPLI C,~f1E COPY December 16, 2024
Revision: 0
Several test pad TP-2019-2 and TP-2021-1 equipment equivalencies were
prepared during the Phase 6 project and certified by EnergySolutions' engineering
for equipment that Broken Arrow selected to use on the project and all analyses
were provided to and approval concurrence given by the UDWMRC. In addition,
a Variance to verify the lift thickness using GPS Equipment was prepared by
EnergySolutions and approved by the UDWMRC for CQA/QC Specifications
148 and 184 for Radon Barrier and Ditch ( clay) lift thickness placement during
the Phase 6 Cover project. Copies of these approvals are on file and copies of the
QC documentation showing the lift placement verifications are also on file.
Quality control moisture density tests were required to be performed at a rate of
one test per compacted 500 cubic yards of radon barrier. The radon barrier
volume placed for Phase 6 was approximately 27,944 cubic yards; therefore, a
minimum of fifty-six (56) moisture density tests were required. Seventy-one (71)
passing moisture density tests were performed on compacted radon barrier lifts.
All radon barrier lifts were placed, compacted, tested, and approved in accordance
with the approved test pads and the CQA/QC Manual requirements. Several test
lots initially failed moisture specified requirements and were reworked as needed
and retested until satisfactory results were achieved.
2.1.5 Radon Barrier Permeability
Permeability tests were conducted in-situ on the compacted radon barrier using the
Sealed Single Ring Infiltrometer (SSRI). Permeability tests were required to be
performed at a rate of one test per compacted 2,000 cubic yards of compacted radon
barrier. The radon barrier placed volume was approximated 27,944 cubic yards;
therefore, a minimum of fourteen (14) permeability tests were required. Sixteen
( 16) passing permeability tests were performed on the compacted radon barrier. All
1 x 1 o-6 cm/sec and 5x 1 o-8 cm/sec tests passed.
2.1.6 Lift Bonding
The sheep's foot compactor provided a roughened surface for lift bonding of
subsequent lifts of radon barrier clay. Water was applied to the clay surface and
along the edges as necessary with a water truck prior to placement of the following
lift of radon barrier to help with the clay bonding process and to maintain the
moisture content. Quality Control observed and verified that Broken Arrow
provided a roughened surface of the previously compacted radon barrier lifts as
required.
2.1.7 Radon Barrier Key-In to Construction
Keying-in was required along the western perimeter of the Phase 3 project and
northern perimeter of the Phase 4 project. The previously placed Phase 3 and 4
radon barriers were cleared of non-specification material and debris, cut into
vertical steps where possible (at the most 9 inches in height and at least 18 inches
in width), moisture conditioned and inspected, prior to placement and compaction
CAW Phase 6 Cover
Construction Report DUPLI C,¢.ff1E COPY December 16, 2024
Revision: 0
of new lifts. QC inspections were documented on construction lift approval forms,
which are on file.
2.1.8 Final Grading
The final radon barrier surface was graded to a tolerance of grade to 0.2 feet above
grade and surveyed on a 50-foot grid and at key points as required by the CQA/QC
Manual. The final surface was also rolled with a smooth drum roller. Final survey
measurements for the cells were reviewed and approved as required. The required
48-hour notice was given to the UDWMRC per the CQA/QC Manual requirements.
The completed radon barrier was then inspected by the EnergySolutions'
representative(s) and a UDWMRC representative. The radon barrier surface was
found to be regular (less than one-inch vertical drop over any area), free ofrocks or
other hard objects on the surface that are greater than ½ inch, free of soft spots and
loose soil areas, and free from desiccation cracks that might diminish the integrity
of the radon barrier.
2.2 Quality Control Support Summary
In general, Quality Control performed the following Quality Control activities
during the construction of the radon barrier:
• Verification of the lift thickness prior to radon barrier placement using GPS
or grade stake approved methodologies.
• Verification of proper lift thickness by survey.
• Verification of the removal of any grade stakes, rocks, debris, etc.
• Inspection and sampling of the borrow material placed as radon barrier and
perfonnance of Proctors and soil analysis.
• Observation and documentation of the tilling of the 5x 1 o-8 cm/sec radon
barrier clay stockpiles.
• Observation and inspection of radon barrier placement, compaction, and
performance of in-place moisture/density and permeability tests.
• Verification of survey points.
• Verification that equipment had proper calibrations.
• Verification ofradon barrier drying prevention method (as required per the
latest revision of the CQA/QC Manual.
2.3 Corrective Actions
No corrective actions were required for this work element.
2.4 Field Changes
No field changes to this work element were required.
CAW Phase 6 Cover
Construction Report DUPLl ~~Tf:: COPY December I 6, 2024
Revision: 0
3.0 COVERROCKPREPARATION
3.1 Construction Activities
3.1.1 General
Some of the excess erosion control cover materials, including the Type A Riprap
and some of the Type B Riprap and Type B Filter, were screened and stockpiled by
Broken Arrow during the Phase 5 Cover work in 2023 as reported in the Phase 5
Cover as built report. Through Spring and Summer 2024, Broken Arrow performed
further screening and crushing operations to produce all remaining required Phase
6 Cover rock products including Type B Riprap, Type A and B Filters, and
Sacrificial Soil, and some excess products now remain following the completion of
the Phase 6 Cover project for future cover phases.
As reported in previous cover project phases, the source for the rock materials of
this project are the Graybacks South gravel pit (the former eastern raw material
stockpile on Section 5; now completely processed) and the Graybacks Community
Pit 24 (the now completely processed western raw material stockpile on Section 5).
Incidentally, in early 2024 Broken Arrow mined and delivered approximately
80,000 cubic yards of raw Graybacks Community Pit 24 material stockpiled now
on the northern western portion of Section 5 for future cover materials.
EnergySolutions' Quality Control performed all rock sampling of the various raw
material and screened stockpiles. EnergySolutions and RB&G performed
laboratory testing in accordance with the CQNQC Manual. Construction activities
were also observed by representatives of QA and various EnergySolutions
personnel (Project Manager, Project Engineer, QC Supervisor and QC
Technicians).
3.1.2 Petrographic Examination of Aggregate
As reported with previous construction phases, the Graybacks South gravel pit
samples were sent to Wiss, Janney, Elstner Associates, Inc. (WJE) in Ohio for
performance of the Petrographic Study of the gravel pit rock source that was used
on the Class A West Phase 6 Cover project. The Graybacks rock source was
determined to be "composed of primarily of acidic to intermediate volcanic rocks
that exhibit only minor internal alteration due to weathering". The Graybacks
Community Pit 24 gravel pit was previously evaluated by Montgomery Watson
Harza (MHA) and determined to be composed of the same lithologies as the South
Pit, with generally the same sorting and rounding as that in the South pit, but with
about 80 percent limestone and 20 percent igneous extrusives. Copies of the
Petrographic Examination reports for both gravel pits areas on file.
3.1.3 Rock Quality Testing and Gradations
Quality Control sampled the screened stockpiles in accordance with the CQNQC
Manual. Quality Control then performed the Aggregate Gradation analysis of the
samples for calculation of the required ratios discussed below. As reported in
CAW Phase 6 Cover
Construction Report DUPLI CA7TE COPY December 16, 2024
Revision: 0
previous Cover phase reports, RB&G performed sixteen (16) Rock Quality Tests:
Specific Gravity, Absorption, Sodium Soundness, and L.A. Abrasion from which
each of the Rock Products was scored. Sixteen samples were obtained from the
Community Pit 24 , bank run stockpile. RB&G performed Rock Quality Tests
(Specific Gravity, Absorption, Sodium Soundness, and L.A. Abrasion) for these
samples. All rock products and bank run materials were calculated to have a Rock
Quality score of at least 50 . In like manner and incidentally, RB&G performed
eight (8) Rock Quality tests for the new 80,000 cubic yards stockpile and all scored
at least 50 . All gradation and rock quality test results are on file.
3.2 Quality Control Support Summary
In general, the following Quality Control activities were performed during Rock
Quality testing:
• Observation of rock processing operations.
• Inspection and sampling of the stockpile material for the Rock Quality
testing and analysis.
• Performance of the various Rock Quality Tests and calculation of the Rock
Quality scores.
3.3 Material Gradation and Permeability Testing
The Riprap, Filter Zones and Sacrificial Soil materials were sampled, tested, and
determined to meet the requirements of the CQA/QC Manual. Filter Zone and
Sacrificial Soil gradation testing and ratio calculations were performed by
EnergySolutions' Quality Control group.
Quality control gradation tests were required to be performed at a rate of one test
per 10,000 cubic yards of Type A Filter, Type B Filter, Type A Riprap, Type B
Riprap, and Sacrificial Soil (stockpiled). Permeability testing of the Type B Filter
Zone material was required to be performed at a rate of at least one test per 10,000
cubic yards. Unless otherwise noted, all the following sampling and testing was
performed in 2024 and in 2023 as previously reported in the Phase 5 As-Built
Report.
The total Type B Filter volume processed and stockpiled in 2023 and in 2024 was
approximately 13 ,530 cubic yards and the amount required for placement on the
Phase 6 Cover project was 8,795 cubic yards and therefore, a minimum of one (1)
gradation and permeability test was required for the project. One (1) passing
gradation and permeability test was performed in 2024 in addition to the passing
2023 gradation and permeability tests previously performed. The gradation and
permeability tests were performed by RB&G. The Type B Filter Zone permeability,
and the various material gradations and ratios met the CQA/QC Manual
requirements.
The Sacrificial Soil volume processed and stockpiled in 2024 was approximately
15,361 cubic yards and the amount required for placement on the Phase 6 Cover
CAW Phase 6 Cover
Construction Report DUPLI C~TE COPY December 16, 2024
Revision: 0
project was 12,118 cubic yards. A minimum of two (2) gradation tests was required
and two (2) passing gradation tests were performed in 2024.
Ratio calculations between the Type B Filter and Sacrificial Soil materials
processed in 2024 were performed by comparing the Type B Filter gradation test
results with the Sacrificial Soil gradation test result to calculate the specified
required CQA/QC ratios and two (2) such comparisons were made in 2024 with
each test (lot) combination producing favorable results.
The Type A Filter volume processed and stockpiled in 2024 by Broken Arrow
totaled approximately 7,997 cubic yards and the amount required for placement on
the Phase 6 Cover project was 6,378 cubic yards. A minimum of one (1) gradation
test was required and one (1) passing test was performed in 2024.
The Type A Riprap volume was processed and stockpiled in 2023 by Broken Arrow
and a total of 14,183 cubic yards was available for use. A total of 6,735 cubic yards
was required for Phase 6 Cover placement and therefore, a minimum of one (1)
gradation test was required. One (1) passing gradation test was performed in 2024.
The Type B Riprap volume was processed and stockpiled in 2023 and 2024 by
Broken Arrow totaling approximately 30,547 cubic yards and the amount required
for placement on the Phase 6 Cover project was 18,858 cubic yards. A minimum
of two (2) gradation tests were required and two (2) passing gradation tests were
performed in 2024 in addition to previous passing gradation tests performed in
2023.
Copies of the supporting testing documentation and calibration certificates for the
Quality Control equipment are on file.
3.4 Corrective Actions
No corrective actions were required for this work element.
3.5 Field Changes
No modifications to the plans, specifications or the CQA/QC Manual were
performed for this work element.
4.0 COVER ROCK PLACEMENT
4.1 Construction Activities
4.1.1 General
In general, all Cover Rock Materials construction activities were observed by
Quality Control and documented in daily reports in accordance with the drawings
and the CQA/QC Manual. Construction activities were also observed by
representatives of QA and various EnergySolutions personnel (Project Manager,
Project Engineer, QC Supervisor and QC Technicians) as well as the UDWMRC.
CAW Phase 6 Cover
Construction Report DUPLI CA1"E COPY December 16, 2024
Revision: 0
4.1.2 Filter Zone and Sacrificial Soil Placement
The Type A & B Filter Zones and Sacrificial Soil layers were placed by Broken
Arrow in accordance with the CQA/QC Manual and the construction drawings.
Copies of the support documentation are on file, photographs of material placement
in Appendix A, and the As-Built Drawings in Appendix B.
Type B Filter Zone was placed over the constructed radon barrier at 6 inches thick
on the top slopes and 18 inches thick on the side slopes using Haul Trucks and a
Dozer. Quality Control observed the placement using grade stakes as required. Care
was taken to protect the underlying radon barrier surfaces and the Type B Filter
Zone material was handled in such a manner as to prevent contamination from
waste material and segregation of finer materials. Quality Control observed
placement of the Type B Filter Zone material to ensure that soil fines were not
concentrated in localized areas. There were no instances of concentrated fines in
the Type B Filter Zone placement process.
Sacrificial Soil was placed over the Type B Filter Zone at 12 inches thick using
Haul Trucks and a Dozer. Quality Control observed the placement using grade
stakes as required. The Sacrificial Soil was handled in such a manner as to prevent
contamination from waste material and segregation of finer materials. Quality
Control observed placement of the Sacrificial Soil to ensure that soil fines were not
concentrated in localized areas and no concerns were noted.
Finally, Type A Filter Zone was placed over the constructed Sacrificial Soil in a 6-
inch thickness, including over and up the outside ditch slope, using Haul Trucks
and a Dozer. Quality Control observed the placement using grade stakes as
required. Care was taken to protect the underlying surfaces and the Type A Filter
Zone material was handled in such a manner as to prevent contamination from
waste material and segregation of finer materials. Quality Control observed
placement of the Type A Filter Zone to ensure that soil fines were not concentrated
in localized areas.
4.1.3 Type A and B Riprap Placement
The Type A & B Riprap layers were placed by Broken Arrow in accordance with
the CQA/QC Manual and the construction drawings. Copies of the support
documentation are on file, Photographs of material placement in Appendix A, and
the As-Built Drawings in Appendix B.
Type B Riprap was first placed over the Type A Filter Zone on the top slope at a
24-inch thickness using Haul trucks and a dozer. Quality Control observed the
placement using grade stakes as required. Care was taken to protect the underlying
surfaces and the Type B Riprap material was handled in such a manner as to prevent
contamination from waste material and segregation of finer materials. Quality
Control observed placement of the Type B Riprap material to ensure that soil fines
were not concentrated in localized areas.
CAW Phase 6 Cover
Construction Report DUPLI C~TE COPY December 16, 2024
Revision: 0
Type A Riprap was then placed over the Type A Filter Zone on the side slope in a
24-inch thickness and 18 inches thick up and on the outside ditch slope using Haul
trucks and a dozer. Quality Control observed the placement using grade stakes as
required. Care was taken to protect the underlying surfaces and the Type A Riprap
material was handled in such a manner as to prevent contamination from waste
material and segregation of finer materials. Quality Control observed placement of
the Type A Riprap material to ensure that soil fines were not concentrated in
localized areas.
4.2 Quality Control Support Summary
In general, Quality Control performed the following Quality Control activities
during the processing and placement of the rock cover materials:
• Verification of the lift thickness by grade stake.
• Observation and inspection of material placement.
• Verification that calibrations were performed as required.
4.3 Corrective Actions
No corrective actions were required.
4.4 Field Changes
No modifications to the plans, specifications or the CQA/QC Manual were
performed for this work element.
5.0 COVER TERMINATION FOR FUTURE TIE-IN
5.1 General
Temporary protection along the northern edge of the project was needed to protect
the exposed radon barrier for future cover tie-in. The Cover termination also helps
to simplify tie-in construction to future Class A West Cover phases. The Cover
termination was detailed in the Construction Drawings but was not required by the
CQA/QC Manual.
5.2 Construction Activities
Following Phase 6 cover construction, the new Phase 6 Tie-In geotextile cover was
placed along the northern edge of the project where the subsequent phase (i.e. Phase
7) will not be constructed for several years. The Phase 6 Tie-In cover was
constructed, with 8 oz. nonwoven geotextile laid directly over the exposed Sx 1 o-s
cm/sec radon ban-ier, a portion of the l xl o-6 cm/sec radon barrier (where the future
tie-in will occur), and Type B Filter Rock to keep a clean surface. This geotextile
was anchored in place using sandbags with a 5-year rating. No Quality Control
testing was required but this construction activity was observed by Quality Control
and by the Project Engineer and Project Manager. No corrective actions were
required. The as-built conditions are shown in the As-Built Drawings in Appendix
B.
CAW Phase 6 Cover
Construction Repo11 DUPLI OAT E COPY December I 6, 2024
Revision: 0
6.0 DRAINAGE DITCH BACKFILL AND GRADING
6.1 Construction Activities
6.1.1 General
In general, all backfill activities of the previously excavated areas around the
embankment (ditch backfill) were performed in accordance with the CQA/QC
Manual. Construction activities were also observed by various EnergySolutions
personnel (Project Manager, Project Engineer, QC Supervisor, QC Technicians,
and QA Specialist). Ditch backfill construction included placement, testing, and
approval of all clay lifts as discussed below. Successful final surveys were
performed as required.
6.1.2 Clay Borrow
Clay was excavated from an approved location on EnergySolutions' property in
Section 5. The approved clay borrow site was cleared and grubbed as required. The
clay material used for the CAW cover project met the required soil classification as
required by the CQA/QC Manual. In addition, the clay material did not contain
debris, vegetation, or any other deleterious material. Roughly 5,247 cubic yards of
clay material was placed. Quality control classification tests were required to be
performed at a rate of one test per 5,000 cubic yards: therefore, at least two (2)
classification tests were required, and three (3) passing tests were performed.
Proctors were required at one (1) test per 100,000 square feet and a total of three
(3) proctor tests were performed.
6.1.3 Ditch Backfill Placement and Compaction
All lifts had a loose lift thickness of less than or equal to 9 inches. Quality Control
verified the thickness of each lift ofradon barrier at all key control points by GPS
inspection in accordance with the Variance approved and discussed above in
Section 2.1.4. All lifts were compacted to at least 95 .0 percent of a Standard
Proctor.
Quality control density tests were required to be performed at a rate of one test
per every I 0,000 square feet compacted of a single lift of a specified material
type. The ditch backfill area lift square footage for Phase 6 averaged about 6,000
square feet per lift for 26 lifts and so the required density tests averaged one (1)
test per lift. EnergySolutions assumed a more conservative testing rate than one
test per every 10,000 square feet per lift and performed thirty-four (34) passing
density tests on compacted ditch backfill lifts. All ditch material backfill was
placed, compacted, tested, and approved in accordance with the CQA/QC Manual
requirements, and all density testing results met or exceeded the requirements of
the CQA/QC Manual.
CAW Phase 6 Cover
Construction Report DUPLI C~TE COPY December 16, 2024
Revision: 0
6.1.4 Final Grading
The ditch was graded to a tolerance of grade to 0.1 feet above grade and surveyed
on a 50-foot grid as required by the CQA/QC Manual. During final surveying it
was found that the final Type A Rip Rap and Type A Filter rock layers of the Phase
4 project extended over the Phase 4 ditch tie point and so a measurement at this
ditch grade point location was not available. The next northernmost point of this
tie in point on the 50-foot grid was surveyed and recorded as shown in the Drawing
24001-C02(1). Moreover, to avoid this issue with a future phase to the north of
Phase 6 (i.e. Phase 7) the 50-foot grid was extended north of the design drawing's
ditch point located at the Type A Rip Rap overlap of the ditch centerline to a
location south of the new Phase 6 haul road ramp and north of the rock layer tie
ins for future survey availability. The slope of the Phase 6 ditch was found to be
~0.11 % as per the design and the overall slope from the northern side of the Phase
6 ditch to the Class A West southwestern corner (i.e. Phase 4) was found to be
~0.11 % overall showing that the Phase 6 (and 4) ditch will drain as designed. The
final surface was also rolled with a smooth drum roller.
Final survey measurements for the cells were reviewed and approved by the Project
Manager, Project Engineer, Quality Control Supervisor, and QA Specialist. The
ditch surface was found to be regular and free flowing.
6.2 Quality Control Support Summary
In general, Quality Control performed the following Quality Control activities
during the construction of the radon barrier:
• Verification of the grade using GPS to determine lift thickness placement.
• Verification of proper lift thickness by survey.
• Inspection and sampling of the borrow material placed and performance of
Proctors and soil analysis.
• Observation and inspection of backfill placement, compaction, and
performance of in-place density tests.
• Verification of survey points.
• Verification that equipment has proper calibrations.
6.3 Corrective Actions
No corrective actions were required.
6.4 Field Changes
No field changes were required for Phase 6 construction.
CAW Phase 6 Cover
Construction Report DUPLI C,XTE: COPY December 16, 2024
Revision: 0
7.0 INSPECTION ROAD
7.1 Construction Activities
7 .1.1 General
The Phase 6 road along the western side of the Class A West embankment was
completed.
7.1.2 Road Base Material
Road base material was provided by Broken Arrow and the required laboratory
testing by CMT Technical Services. Approximately 312 cubic yards of road base
was used for the Phase 6 road. Quality control gradation tests and Proctors were
required to be performed at a rate of one test per 3,000 cubic yards: therefore, at
least one (1) gradation test and one (1) Proctor were required. One (1) passing
gradation test and one ( 1) Proctor were performed.
7.1.3 Subsurface Preparation
The road subsurface was the top of the ditch backfill. Therefore, the subsurface did
not require scarification and compaction per the CQNQC Manual specifications
since it was already compacted to at least 95% of a Standard Proctor. Moreover, a
geocomposite (geogrid/nonwoven geotextile, CombiGrid® ) was placed on the
surface prior to the road base.
7.1.4 Road Base Placement and Compaction
The road base material was spread and compacted (to at least 95% of a Standard
Proctor or at least 92% of a Modified Proctor) to within the CQA required final
thickness of 12 inches plus or minus 0.2 feet. Density testing was required at a rate
of one test per every 200 cubic yards compacted. The volume placed was
approximately 312 cubic yards and a total of two (2) passing density tests were
required and successfully performed.
7.2 Quality Control Support Summary
In general, Quality Control performed the following Quality Control activities
during the construction of the radon barrier:
• Verified that the road base produced met gradation, placement, and compaction
specifications.
7 .3 Corrective Actions
No corrective actions were required .
7.4 Field Changes
No field changes were required.
CAW Phase 6 Cover
Construction Report DUPLI C~TE COPY December 16, 2024
Revision: 0
8.0 SETTLEMENT MONUMENT INSTALLATION
8.1 General
Settlement monuments are placed on top of the final approved radon barrier and are
then secured by the rock cover layers as they are built. Each monument was
permanently labeled, flagged, and documented on a reference drawing as directed
by the CQA/QC Manual. The monuments were surveyed on November 8, 2024.
8.2 Construction Activities
Following approval of the final radon barrier surface the new Phase 6 settlement
monuments, constructed per the CQA/QC Manual, were installed at their
specified locations along the top slope of the Phase 6 area, flagged, initially
surveyed, and documented as required. Survey results are on file.
9.0 AS-BUILT DRAWINGS
As-built Drawings have been prepared from the project red-lined drawings and
construction documentation. The attached phase specific As-built Drawings are
found in Appendix B and contain the as-built information for the Class A West
Phase 6 Cover Construction project.
PREPARED BY:
GARRETT Q. DUTSON, PE
CLIVE FACILITY ENGINEER
ENERGY SOLUTIONS
CAW Phase 6 Cover
Construction Repo11 DUPLI C,A5f E COPY December l 6, 2024
Revision: 0
APPENDIX A
PROJECT PHOTOGRAPHS
DUPLICATE COPY
-
Class A West Phase VI Cover
Representative Photographs
08/26/24 -1 x 10·6 cm/sec Radon Barrier Placement.
08/29/24-1 x 10-5 cm/sec Radon Barrier Placement/Compaction.
1
DUPLICATE COPY
t
09/11/24 -Radon Barrier 5 X 10-8 Placement.
~~~Ff!!'~w~; :--~-=.~.' '!:i-<_i ._,. ... ~
;';,. ~-. .. . .. .... ':: --~~
' ~,..; ,.,
09/11/24 -Radon Barrier 5 X 10-8 Placement/Compaction.
2
DUPLICATE COPY
10/07 /24-Completed Radon Barrier and ongoing Ditch work.
10/07 /24-Completed Radon Barrier 5 X 10-8 surface.
3
DUPLICATE COPY
10/08/24 -Ditch material Placement.
10/08/24 -Type B Filter Placement.
4
DUPLICATE COPY
10/14/24-Sacrificial Soil Placement.
10/15/24-Type B Filter and Sacrificial Soil Placement.
5
DUPLICATE COPY
10/15/24-Type A Filter (Ditch line) and Sacrificial Soil Placement.
10/22/24-Sacrificial Soil and Type A Filter Placement on top slope.
6
DUPLICATE COPY
10/23/24-Type A Filter, Sacrificial Soil, and Type B Filter on side slope.
10/24/24 -Type B Rip Rap placement on top slope
7
DUPLICATE COPY
10/31/24-Top slope Rock Cover layers
11/4/24-Type A Rip Rap Placement on side slope.
8
DUPLICATE COPY
11/04/24 -Side slope Rock Cover layers.
11/05/24-Inspection Road placement with CombiGrid and Road Base.
9
DUPLICATE COPY
11/06/24 -Completed Tie In on side slope.
11/07 /24-Completed Tie In on top slope .
10
DUPLICATE COPY
11/08/24 -Completed Phase 6 Cover top slope including tie in.
11/08/24 -Completed Phase 6 Cover side slope including tie in.
11
DUPLICATE COPY
APPENDIXB
AS-BUILT DRAWINGS
DUPLICATE COPY
I
.I{
E
D
C
IB
---7 ---------------------------------1
I -=+ ::----L .. 7
.----~
' i ' I i ' i
~~-----~ ,--------,
~------71" I I
' /I ' / I ' / cu.s's A WEST I y I
I
I
' I/ ,I
.JL--------~
=-:--l=
VITRO
I ' / I I y
I ~w
I I I
I A I
)L ~ _: ~
~
r __ _J
i
I
I I
I
I I
I ~ I ' I
L ______________________________________ J
CLASS A WEST FINAL COVER -PHASE 6
CLASS A WEST
EMBANKMENT
DRAWING NO.
24001-G01
24001-G02
24001-L01
24001 -L02
24001 -C01
24001 -CO2
24001 -C03
24001 -C04
24001 -C05
24001 -C06
24001 -C07
COVER PROJECT AREA
LEGEND
800
ROAD
PROPERTY LINE
RAILROAD
SECTION LINE
PERMITED EMBANKMENTS
ENERGYSOLUTIDNS PROPERTY
0 800 1600
■--'
DUPLICATE COPY
DESCRIPTION
TITLE SHEET
CONSTRUCTION NOTES & SPECIFICATIONS
PROJECT SITE MAP
PHASE INFORMATION MAP
PHASE 6 PROJECT PLAN, 1 OF 2
PHASE 6 PROJECT PLAN, 2 OF 2
SECTIONS AND DETAIL S, 1 OF 3
SECTION S AND DETAILS, 2 OF 3
DETAILS -TIE-IN BETWEEN PHASES
DITCH CONSTRUCTION SEQUENCE DETAILS
SECTIONS & DETAILS, 3 OF 3
ENERGYSOLUTIONS CLIVE F ACIUTY
1-80 EXIT •s
UTAH
VICINITY MAP
C
0TH
I ~ ~ (.)
~ t; t:, I :::, ~ ~ ~
co ~ ~ .., u"' i a: ~
CL e ~
~ ~ «)
~s§~ ~ Q.
"-I
...___' L Q,: I ~a~B~ ~,. u:x::::>
~
(/)...J(/) -z<ww
~
g ~ E~ ::::i I-_J
"
...JI-(.) 0 (/)
S
I:'.?~ ~ < w z (/)
w s
(.)
UTSON
AS NOTED
24001
G01
E
OC)
I-
C
IB
I-
~
I T -z-
CONSTRUCTION NOTES & SPECIFICATIONS
GENERAL:
1. THE CONTRACTOR WILL PERFORM ALL RELEVANT WORK ELEMENTS TO THE
SPECIFICATIONS CONTAINED IN THE "APPROVED LLRW/11a(2) COA/OC MANUAL".
T
A COPY OF THE RELEVANT SECTIONS OF THE MANUAL WILL BE PROVIDED TO THE
CONTRACTOR.
2. THE OWNER WILL PROVIDE ALL QUALITY CONTROL TESTING, UNLESS OTHERWISE
SPECIFIED IN THE CONTRACT SCOPE OF WORK.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR EXAMINING THE PROJECT AREA
AND SITE CONDITIONS AND SHALL NOTIFY THE OWNER'S REPRESENTATIVE OF
CONDITIONS DETRIMENTAL TO THE PROPER AND TIMELY COMPLETION OF THE
WORK.
4. THE CONTRACTOR SHALL IDENTIFY ALL REQUIRED LINES, LEVELS AND DATUM
PRIOR TO CONSTRUCTION.
5. THE CONTRACTOR SHALL PROVIDE ALL SURVEY SUPPORT REQUIRED, AS
DESCRIBED IN THE CONTRACT SCOPE OF WORK. THE OWNER WILL VERIFY AND
APPROVE WORK AS DESCRIBED IN THE "APPROVED LLRW/11e(2) COA/OC
MANUAL".
6. THE OWNER WILL PREPARE AND PROVIDE AUTOCAD CONSTRUCTION SURFACES TO
THE CONTRACTOR. THE CONTRACTOR SHALL COORDINATE WITH THE OWNER TO
FIELD VERIFY THE SURFACE DESIGNS.
7. THE CONTRACTOR SHALL PROTECT EXISTING MONITORING WELLS, LYSIMETER
MANHOLES, PROJECT BOUNDARY FENCES AND OTHER STRUCTURES AS IDENTIFIED
BY THE OWNER. ANY DAMAGE CAUSED BY THE CONTRACTOR SHALL BE
IMMEDIATELY REPORTED TO THE OWNER'S REPRESENTATIVE.
CULVERTS llfHEN SPECIFIED}; &
8. CULVERTS SHALL BE CORRUGATED HOPE N-12, SMOOTH INSIDE WALL, WATER
TIGHT PIPE, UNLESS OTHERWISE APPROVED BY THE OWNER.
9. CULVERTS SHALL BE BEDDED IN GRAVEL, UNLESS OTHERWISE APPROVED BY THE
OWNER.
10. BACKFILL SHALL BE SELECT MATERIAL PLACED IN 9" MAXlt.lUM LOOSE LIFTS AND
COMPACTED TO A MINIMUM OF 95¾ OF THE STANDARD PROCTOR.
11 . A MINIMUM OF 3 FT OF COMPACTED FILL (INCLUDING ANY ROAD BASE) SHALL BE
PLACED OVER CULVERTS PASSING BENEATH ROADS, UNLESS OTHERWISE
APPROVED BY THE OWNER.
HAUL RAMPS:
12. ACCESS HAUL RAMPS SHALL BE CONSTRUCTED USING APPROVED 1x10-a RADON
BARRIER MATERIAL.
13. RAMPS SHALL BE FIELD DETERMINED DEPENDING ON SITE CONDITIONS.
14. RAMPS SHALL MATCH OR EXCEED THE HEIGHT OF ADJACENT RUNOFF CONTROL
BERMS.
15. PLACE AND COMPACT FILL MATERIAL TO t,UNlt.llZE RUTTING AND PROTECT ANY
UNDERLYING EMBANKMENT LINER, RADON BARRIER OR OTHER COVER LAYERS.
16. PLACE SUFFICIENT ROCK COBBLE AT BASE OF RAMP TO CREATE A CONSTRUCTION
ENTRANCE (TO MINIMIZE TRACKING MATERl,t.L ONTO THE EMBANKMENT). OWNER
WILL PROVIDE BUT NOT DELIVER THE ROCK COBBLE.
17. REMOVED RAMP MATERIAL MAY BE REUSED FOR NEW RAMPS OR FOR
CONSTRUCTION OF 1><10-6 RADON BARRIER, BUT ONLY WITH PRIOR APPROVAL
FROM THE OWNER'S REPRESENTATIVE.
18. IF REMOVED RAMP MATERIAL CANNOT BE REUSED, STOCKPILE IT WITHIN THE
CONTROLLED AREA AT A LOCATION PROVIDED BY THE OWNER'S REPRESENTATIVE.
DRAINAGE DITCH Fill· &
19. DRAINAGE DITCH FILL MATERIAL SHALL BE NATIVE CLAY BORROW FROM AN
APPROVED SOURCE.
20. FILL MATERIAL SHALL BE PLACED IN 9" MAXIMUM LOOSE LIFTS AND COMPACTED
TO A t.llNIMUM OF 95" OF THE STANDARD PROCTOR.
21. THE OWNER WILL PROVIDE THE CONTRACTOR UPON REQUEST, CURRENT
TOPOGRAPHICAL SURVEY INFORMATION OF THE SURFACE SURROUNDING THE
EMBANKMENT FOR USE IN VERIFYING FILL QUANTITIES.
1 I 2 I
~ T 4
PROVISIONAL DITCHES;
22. FINAL DITCH AREAS THAT CANNOT BE COMPLETED BETWEEN PHASES SHALL BE
FILLED WITH COMPACTED CLAY MATERIALS AND GRADED TO COLLECT ANO MOVE
RUN Off WITHOUT EXCESSIVE PONDING.
23. FILL MATERIAL, THAT WILL NOT BE REMOVED FOR SUBSEQUENT CONSTRUCTION,
SHALL BE PLACED IN 9" t.lAXIMUM LOOSE LIFTS AND COMPACTED TO A MINIMUM
OF 95¾ OF THE STANDARD PROCTOR.
24. ANY FILL MATERIAL PLACED DIRECTLY ON TOP OF COMPLETED RADON BARRIER
SHALL BE APPROVED RADON BARRIER MATERIAL, EITHER h 10-a OR 5x10-a
DEPENDING ON THE UNDERLYING MATERIAL.
25. THE CONTRACTOR MAY USE WOVEN OR NON-WOVEN GEOTEXTILE AS A
SEPARATION BARRIER BETWEEN COMPLETED COVER LAYERS ANO TEMPORARY FILL
TO FACILITATE FUTURE REMOVAL OF TEMPORARY FILL MATERIALS.
26. FILL AND GRADING SHALL BE FIELD DETERMINED, DEPENDING ON FIELD
CONDITIONS AND EXTENTS OF COMPLETED COVER LAYERS.
INSPECTION/HAUL ROAD (EXCLUDING ON CELL HAUL ROADS\;
27. HAUL ROADS SHAIJ. BE CONSTRUCTED WITH OWNER APPROVED ROAD BASE
MATERIAL.
28. HAUL ROADS SHAIJ. HAVE A MINIMUM WIDTH OF 15 FT.
29. TURNOUTS SHALL BE SIZED, CONSTRUCTED AND LOCATED TO ALLOW THE
SAFE PASSING OF ALL CONSTRUCTION EQUIPMENT USED BY THE
CONTRACTOR.
30. THE CONTRACTOR MAY, lf!TH PRIOR OWNER APPROVAL, "OVER CONSTRUCT"
THE HAUL ROADS AND TURNOUTS AT THE CONTRACTOR'S EXPENSE.
31. THE CONTRACTOR SHALL PERFORM SURFACE GRADING (CUT & FILL) AND
COMPACTION TO CONSTRUCT A FIRM SUBGRADE. SUBGRADE COMPACTION
SHALL BE TO A MINIMUM OF 95,; OF THE STANDARD PROCTOR.
32. ROAD BASE SHALL BE PLACED IN 12" MAXIMUM LOOSE LIFTS AND
COMPACTED TO A MINIMUM OF 95::C: OF THE STANDARD PROCTOR OR
EQUIVALENT MODIFIED PROCTOR.
33. THE HAUL ROAD SHALL BE CROWNED WITH A MINIMUM 2::C: CROSS SLOPE.
34. THE CONTRACTOR SHALL BE RESPONSIBLE TO OPERATE ON THE ROAD SUCH
TO MINIMIZE DAMAGE AND SHALL MAINTAIN AND REPAIR THE HAUL ROAD AS
NEEDED.
35. THE CONTRACTOR SHALL BE RESPONSIBLE TO PROVIDE DUST CONTROL AND
MAY APPLY WETTING AGENTS OR SURFACE TREATMENTS lf!TH PRIOR OWNER
APPROVAL.
RUNOFF CONTROL BERM, REMOVAL fBY OlfNER}:
36. THE OWNER lf!LL EXCAVATE, HAUL AND DISPOSE OF EXCESS MATERIAL AT
THE TOE OF THE EMBANKMENT AND THE RUNOFF CONTROL BERMS IN TWO
STAGES AS DEPICTED ON SHEET COB.
37. THE FIRST PHASE OF REMOVAL WILL BE COMPLETED PRIOR TO THE
CONTRACTOR PLACING RADON BARRIER MATERIAL ON THE SIDE SLOPES.
38. THE SECOND PHASE OF REMOVAL WILL BE COMPLETED AFTER THE FIRST
LIFT OF lXto-• RADON BARRIER MATERIAL IS PLACED OVER THE ENTIRE
PROJECT AREA.
TIE-IN PROTECTION ('WHERE APPLICABLE};
39. GEOSYNTHETIC MATERIALS SHALL BE EITHER 30 MIL LI.PDE GEOMEMBRANE
OR 8 OZ WOVEN GEOTEXTILE, UNLESS OTHERlfISE APPROVED BY THE OWNER.
40. SANDBAGS SHALL BE RED DURABAG8 OR OWNER APPROVED EQUIVALENT.
41. TIE-IN PROTECTION WILL ONLY BE INSTALLED ALONG THE NORTHERN
BOUNDARY OF THE PHASE 6 PROJECT. &
42. SANDBAG SPACING IS ASSUMED TO BE 3 FT BETWEEN BAGS ALONG THE
GEOSYNTHETIC MATERIAL EDGES AND EVERY 5 FT OR AS NEEDED AT GRADE
CHANGES. AN ALTERNATIVE ANCHORING PLAN OR SANDBAG PLACEMENT PLAN
MAY BE IMPLEMENTED WITH THE OWNER'S APPROVAL.
43. TIE-INS ALONG THE WEST BOUNDARIES OF THE PHASES DO NOT REQUIRE
PROTECTION.
~ oup LI CATE <;OPY
T 5 T
I fl I
tf
. ~oiFESSJO,V~ ~ ie
11/lb)_'I ~,
No. 189706 11
7-3
---i'ffd'
6
E
-
D
Cl
t
-
B
-
! ~
>-~ ~ ~ ..., z u -0 ii! u t; "-I Q: :, 0
U> 0 J!: Z < I.. (I) 0
,0 z z Ii:
..,,, Q 8 &: ~ ~ a: ~
CL a: e ~
lfilgl§llii
... ~1·
...... ....................... LI.I ~~ti~ N ... N ~ n...,
~ ~ U) S~~~
VI z 0
~ Cl. "-' I
~~ ~ ;
U 0
r.A:n ~ ~~~
!
GI~
0:: <( w Z VI
w s
u
~ u i.:: u w Bi :c
old~ => VI w . 13w z~ ..J zO
0 5 :::,
0:: Iii z 0 u
~UTSON
5'.'"liooTH ---G. DUTSON
AS NOTED 1'5'2/19/24r~
24001
G02
E
D
C
B
1
' I --__J
t.4AIN SITE
ACCESS
ROAD
COUNTY ROAD
2
NORTH WATER
TOWER
SECURITY OFFICE
(ADt.4IN BUILDING)
3
VITRO
4
□
SOUTH ACCESS GATE
STOCKPILE AREAS TO
Et.4BANKt.4ENT ROUTE
(~2.7 t.4ILES RT)
"--7----
..., 1 PHASE 1
-If) -,(
VI / I i ___ _/_
I
'-. V PHASE 2 /
>---< 1---------1-
/
CLASS/ A WEST ', / ,;,:,,, I / ~"'<, ---7-
/ ~~',' " I / / ~i~ PHASE 4 )'.-------~,~+ -~
CONTRACTOR
FIELD OFFICE
AREA
-_MIXED --;7(
_ WASTE-< I -----~
------
LARW / I ----<
-~ "''
~-------;{ " / I " 11e(2) / I
I '--/ I ~--4. ----
~ -+
CLAY HAUL ROUTE
(~2.4 t.41LES RT)
CLAY
BORROW
SOURCE
10 Ill, .~)~';:;r ~~~K;I~~ ROCK
PROJECT AREA COUNTY ROAD
' JP.~-
SOUTHWEST SITE __/ • LJ S:U;HWEST P:N: ----
ACCESS GATE WATER TOWER
500 0 500 1000 --··--------
DUPLICATE COPY
C
~
5 "" ::, " ~ ~ z i ~ ~ 0 (.) ::, u 5 "-'f ct:: ::::> a ~e;~
:~u~ 1/)"' u z ~ er !:l a. a::: e o
~ ~ ~: S-~ ~ ::c: ~ 0..
"-I ' ~ ~ ~5~:x: ~pg~g r~ !1i -;;j_ ,-u..i
"!"'~~Q~U> t-~ w-::, -, _J
"
....1 1-~U ~ ~~o..
QC < L,J Z VI
L,J s
~u
24001
101
E
D
C
B
PHASE SPECIFIC
ACCESS RAMP
1
LICENSED WASTE
FOOTPRINT
2
I
I
~DESIGN W ~ (TYPICAL) '5TE BREAKS
1 x10-5 RADON BARRIER
PLACEMENT LIMITS (TYPICAL
1/ 1/
/1/
1/
/
/
/
I
A
4
" " " -----.------
' -l
: I I ); I I I I
I I I
I PHASE 5 I I i COMPLETED (2023) / I /
I I I I
I I I I I
: I I I I
I I I I I
I I I I \
I r /; i , ' I 11 1
\f I // : : : ', I I!
I I I / : I I " I I I I / I I " I / / / i / " PHASE 1 / / / PHASE 4 / I PHASE 3 PHASE 2 I '--(COMPLETED 2018) / I / I / / I COMPLETED (2022) / : (COMPLETED 2021) (COMPLETED 2019) : '--I , ,
, , I / I I " I I I I I / I I " I I 11
I / : : " I I I I I I / I I " I I I / : : " I I I
I I / ' ' ' I '\ !:1 ;~----------~------------,-------------L ----------~~,,:
\
/ I I I '( I I // : I : "" I I I / I I I " I I I I I
II / I I I " ii ~ I I I '--
[~----------------' ___ -------' ---=-=r----' __ -----------=-GJ ~ ------------7----------~ --------------.,:;-:VER7 ---------~ ----------....._ -----------
INSPECTION/HAUL ROAD DRAINAGE DITCH
100 0 100 200 -··------
DUPLICATE COPY
.K
Cl
fi
"' (.)
i ~ ~ u
::::, ~ L£. cp g 0
(/)"' z < t; 0
<O ~ ~
"'0"' i 0: ~ n. ~ ~
~ ~ ~i S _, I ~ ll. ll. ..._ I ;i . ....._, w Cl:'. z ::r: ~ ~ ~ ~~ ~.Pu:i~
~
Ul-'°". Z < 0 W
~
2E!z2::: 5 -...J
"
_,1-wU Sl ~ ~ >-~I
~
ffi<ll.
z 1/)
w ~
~u
24001
L02
E
C
l
1x10-1 CM/SEC
RADON BARRIER
N 13,276.5
E 10,348.0
NEW ROAD TURNOUT FIELD
DETERMINE SIZE & LOCATION
(TYPICAL)
RUNOFF CONTROL BERM
REMOVED BY OWNER, (SEE ) 1111 1 I lfiljJ
CONSTRUCTION NOTES) / I
OWNER EXCAVATED AREA
(HATCHED AREA, SEE NOTE 1) 'dJI± j H\IIIH-=---tJ.l>I
MONITORING WELL GW-100
(RETAINED & PROTECTED)
NEW PHASE 6
ISOLATION RUNOFF
~---'--' CONTROL BERM AND
HAUL ROAD RAMP
(SEE NOTE 2)
PHASE 6 PROJECT BOUNDARY
(FENCE OR ROPE, SEE NOTE 3)
20¾ SLOPE
j ,1111111 i 1 x10-CM/SEC
RADON BARRIER
N 12,873.5
10,341 .2
JI
~, it ...J 0 VJ _, VJ
Lu I~~
I
I
I
PHASE 4 ISOLATION
RUNOFF CONTROL BERM
1----' REMOVED AS PLANNED
FOR THE CONSTRUCTION
or PHASE 6
& 50 0 ........... .,
4
4X SLOPE
50 100
I
1 x 1 o-• RADON
BARRIER LIMITS
NOTES_;_ &
1. OWNER EXCAVATED, LOADED, HAULED AND DISPOSED OF
EXISTING RUNOff CONTROL BERM AND SOILS IN THE DITCH
AREA. REFER TO SECTION D, SHEET COG FOR SEQUENCING
DETAILS AND NOTES 36-38 ON SHEET G02.
2. RUNOFF CONTROL BERMS WERE CONSTRUCTED BY THE
OWNER. REFER TO DETAILS 5 AND 6, SHEET C07 roR
ADDITIONAL INFORMATION. CONTRACTOR RETAINED AND
PROTECTED THE PHASE 6 BERMS THROUGHOUT PHASE 5.
3. THE PROJECT (PHASE) BOUNDARY FENCING AND/OR ROPE
WERE INSTALLED BY THE OWNER.
4. TOPOGRAPHY WAS DEVELOPED FROM A SURVEY PERFORMED
ON OCTOBER 2, 2024.
DUPLICATE COPY
J{
&
~ ~ s
~ ~ ~ ~
w <>
.... z i = 0 u :::, F .._ 'f g 0
Ill Ir Z < Iii Q
"'~ !!; w u "' i ~ ~
a. e ~
"' ~ bl
;! 1 5i a..
"--I
L ~ > w ::J > (.) 0 • u
VJ ...J z < 0 Z .:= G: :::::, _, 1---
0 ~ ~ ?:
f5 < z VJ
w ~
(.)
"' "--0 ~~ ~~
a. w
1---~ u__J w (.) ~ a.
24001 COl
E
C
B
1
NEW HAUL ROAD RAMP
(SEE DETAIL 4, SHEET
C07 FOR DETAILS)
NEW ROAD TURNOUT
FIELD DETERMINE
SIZE c!c LOCATION
(TYPICAL)
DITCH INVERT
CENTERLINE
NEW
I I
INSPECTION/HAUL -----------ROAD r:
(RETAINED c!c PROTECTED)~ I MONITORING WELL GW-100 I 1
& I
1
I
I
I
I
I
I
I
I
I
... 0.. 0 .J ti)
::c u I-0
~
0 l
!
1 X 10-• CM/SEC
RADON BARRIER
N 13,276.6
E 10,348.0
·-·-·-·-·-·-· -_:_ ~ ----===
CJ?
--20" SLOPE
1XH,1 CM/SEC
RADON BARRIER
N 12,873.5
E 10,341.2
... I ...
0.. 0.. Oo .J .J ti) ti)
w 0.. !:!o ti) I-
3
... ti) < "":c Oc.. ..... ... z"" -::, I ,-!:!! ::> .........
4
PHASE 6 PROJECT
BOUNDARY
(FENCE OR ROPE)
-·-·-·-·-·-·-·-·-·-·-·-·-·-·-·-·-
_ __:... --t . -----------=--=----=__:..--=-_ __:..-=--=.. ______ _
CJ?
--4¾ SLOPE
PREVIOUSLY CJ?
• -, COMPLETED TIE-IN
DURING PHASE 4 & -..._,,,,---.......__
JECT BOUNDARY
NCE OR ROPE)
ED BY OWNER
·-·-·-·-·-·-·-·-·-· ----==-=----=-== -------
.3
50 0 50
,.__,,..,1.-...
100
I
1x10-1 CM/SEC
RADON BARRIER
N 12,860.2
E 10,993.3 ,.
DUPLICATE COPY
"o. "v.~~ ,<),j:l
~-<"~<".t,,, '"G' ., ov.
,<)-$: Qe. ~)-
'1.r<" '-',i,
.,J
0
J{
&
C!
~
~
.... z I = 0 (.) :::, ,= ... 'l' g 0
"' a: z < t=i Q
CD ~ ~ ... u a: i ~ ~ n. e ~
<D
~ 1 Cl.
I N ..... a:: 0 w :r: N,ct . 1--~:
..... ~ u .J ~ r
~
24001
CO2
'A,
C
I
TYPE A RIPRAP
PERMANENT
COVER SYSTEM
1' THICK
TEMPORARY COVER
1' THICK (MIN)
LINER PROTECTIVE
COVER
2' THICK
CLAY LINER
SACRlflCIAL SOIL
5x10-s RADON BARRIER
1x10-6 RADON BARRIER
WASTE
LINER PROTECTIVE
COVER
CLAY LINER
WASTE LIMIT
(TOE or WASTE)
/[&
DITCH TRANSITION ZONE
(DISTANCE VARIES) -+-----'<~
....,L!..lm• • ·m· • ·rrr • 'ITT' • ·rrr • 'ITT' • 'ITT~1 1
SCALE: 1 "=8' -o•
WASTE
LIMIT
DITCH
CENTERLINE
(INVERT)
4
INSPECTION ROAD
CENTERLINE
20.3' MIN---+--------39.6' MIN------~
-----..........
-/
/
DITCH
TRANSITION
ZONE
~20' MIN
I
I TCH INVERT
i---+------4.7' MIN 1---25' MIN-----<
DITCH Eta? COVER
DETAIL C04
DITCH & ROAD DETAIL TYP.
DITCH INVERT
(ELEVATION VARIES)
TYPE A FILTER MATERIAL
VARY THICKNESS AS NEEDED IN
DITCH TRANSITION ZONE (6" MIN)
COMPACTED
BORROW MATERIAL
(DRAINAGE DITCH FILL)
SCALE: 1"=16'-0"
OWNER TO REMOVE OR REWORK &
LINER PROTECTIVE COVER FOR RADON
BARRIER CONSTRUCTION, FOLLOW LIFT
BONDING SPEClflCATIONS FOR
INTERFACE BETWEEN EXISTING AND
NEW LAYERS
DUPLICATE COPY
INSPECTION ROAD
12" THICK +/-0.2' ROAD BASE
COMPACTED TO 95% STANDARD PROCTOR
OR TO 92% MODIFIED PROCTOR. A
GEOCOMPOSITE WAS PLACED OVER THE
DITCH FILL AND UNDER THE ROAD BASE.
GROUND
ELEVATION
~AX ( ) .r~"~UF.;31F VARIES
_ ;111=111-"
'-NATURAL SOIL
ORROW MATERIAL
(DRAINAGE DITCH FILL)
COMPACTED TO 95%
STANDARD PROCTOR
upoT APPROVED ROAD BASE MATERIAL
SPEClflCAIION·
SIEVE SJZE
1-1/2 INCH
i INCH I INCH ,.
#16
#200
NOTES:
PERCENT PASSING
100
75-95
62-82
35-58
16-36
0-18
1. REFER TO SHEET COS FOR
CONSTRUCTION SEQUENCE AND
DETAILS.
C
~ ~ s
~ ~ ~ ~
z 0 ~ ::, <> ~ 1 ~ ~ ~ u al O t; ~ I o: ::, VI O 0: Z < ... t;; 0
U) z ~ ~
uJ Q u a:: ~ ~ 2s ~ ---. 0
<D
w ~ ~11') :! ::c ~ 0.. ~ u.. I . wl'.k: ~p: > w
:::; i5 <~ Pu w :::>
~ ;,! 0 • ozow
;:: G: ~ ~ 3 t;; (/) 0 Ow Z ~ ~ Q 1f < t; w w z (/) (/)
w 5
u
24001
C03
E
C
1
6" THICK
A FILTER
18" THICK
TYPE B FILTER -----
ZONE
12" THICK
TEMPORARY
COVER (CLAY)
24" THICK TYPE
A RIP RAP
12" THICK
~ SACRIFICIAL
SOIL
12" OF 5x10-8
CM/SEC RADON
BARRIER
12" OF 1x10-6
CM/SEC RADON
BARRIER
DETAIL-SIDE SLOPE
HTS TYPICAL SIDE SLOPE
COVER DETAIL
18" THICK TYPE
A RIP RAP
TYPE A FILTER
ZONE, THICKNESS
VARIES, 6" MIN
NATURAL GROUND OR
IMPORTED DRAINAGE DITCH & BORROW MATERIAL
DETAIL-DITCH OUTER SLOPE
NTS TYPICAL PERIMETER
DITCH COVER DETAIL
6" THICK
A FILTER
6" THICK TYPE
4
TYPE
12" THICK
SACRIFICIAL SOIL
B FILTER ZONE ~-~ 12" OF 5x10-8
CM/SEC RADON
BARRIER
12" THICK
TEMPORARY
COVER (CLAY)
24" THICK TYPE
B RIP RAP
6" THICK TYPE
A FILTER ZONE
6" THICK TYPE B
flLTER ZONE
12" THICK
TEMPORARY
COVER (CLAY)
TOP OF WASTE
EL 4302.6'
~t.:t/,~-~•.;~~~~t:f~(.::.f~{i~~·~,.-f[~~-;i~}~;\~!~~r~~~:;rri._~~
DETAIL-TOP SLOPE
HTS TYPICAL TOP SLOPE
COVER DETAIL
-----~7.2' -----;
12" OF 1x10-6
CM/SEC RADON
BARRIER
TOP OF COVER
EL ~4309.3'
24" THICK TYPE
A RIP RAP
12" THICK
SACRIFICIAL SOIL
._,,_ 18" THICK TYPE B
FILTER ZONE
•• ,_.,, •• "J.:~,~~:'.,:·:;.':.,;•,,;.·;.,;:-:.;:~ ...... ,, .. ,
24" OF RADON
BARRIER
~ DETAIL-SHOULDER
1•=•·
DUPLICATE COPY
COVER MATERIAL GRADATIONS (ASTM C-136)
TYPE A RIP RAP
D 100<= 16 INCH
Dgo <= 12 INCH
D50 >= 4-1/2 INCH
D10 >= 2 INCH
D 5 >= NO. 200 SIEVE
TYPE B RIP RAP
D 1 oo<= 4-1 /2 INCH
D50 >= 1-1/4 INCH
D 1D >= 3/4 INCH
D 5 >= NO. 200 SIEVE
TYPE A FILTER ZONE
D 100<= 6 INCH
D70 <= 3 INCH
D 50 <= 1.57 INCH {40 mm)
D 15 <= .85 INCH (22 mm)
D 10 >= NO. 10 SIEVE (2mm)
D 5 >= NO. 200 SIEVE
TYPE B FILTER 6: SACRIFICIAL SOIL &
TYPE B FILTER &c SACRIFICIAL SOIL MATERIAL
GRADATIONS ARE DETERMINED BY THE FOLLOWING
SPECIFICATION:
D15 FILTER
D85 SOIL MUST BE < 5
050 FILTER
050 SOIL MUST BE <= 25
D15 FILTER
015 SOIL MUST BE >= 4
TYPE B FILTER MIN PERMEABILITY = 3.5 cm/sec
SACRIFICIAL SOIL MIN MOISTURE O 15 otm = 3.5¾
C
~
t; "' :, <>
,_ ~ z I :=oou ~~g~ cnoo::z < ... t;; Q
:~8i '!I II) 0 x ~ "' ~ a.ixeo
~ ~ .,
S~ §~n
u a. .... < 0
~IN
~
...,a::.I ~ ~ ~ ~< u O < I-' u t;:; ::> ~~ ~ ~ :~ I-.... ~ ::::i
I
C.,l~~u
ffi < g z V) V)
..., s
u
24001
C04
~
E
C
iB
0:: w > 0 0
...J 1-...J -:::, ::r ... :::;
I
ai
z 0 l-o -< :! 0:: . ...J
4
ai
z 0 l-o -< :! 0:: . ...J
------~7' ------+---~4' ---+----~6' -----------~7.5' -------------------------~21' --------------------1
1--~3' ~17'---------
:1t:: ~1·~ 0:: a,
i
_,' •-1 I '--:--:-.!....!....!.m..!....!...!.rn..!..!..!m•' 'TTl~fTT..:...:..:ITT.!...!....!.fTi..:....!...!.111..:....!....!-.-----.-----.'. ,-·-, 11
~45'
LLD PE OR NON-WOVEN GEOTEXTILE STRIP ( 16' WIDE)
TO PROTECT LINER FOR FUTURE COVER TIE-IN
SANDBAG
(TYPICAL)
~15'
HAUL ROAD
-IN 1-IJH' '.°"t.lJH,l"IJIUNI ·••-111-.;~ .. IIIIIH'I-Kl'T-
COVER CONSTRUCTION COVER CONSTRUCTION
TIE-IN FOR FUTURE __ PHASE
REIAOVE LLDPE LINER c!c
SANDBAGS (SALVAGE
FOR REUSE)
ai
REPAIR AND/OR RECONDITION, AND
RE-TEST PREVIOUS PHASE IAATERIAL
(SEE NOTE 2)
REMOVE PREVIOUS PHASE
MATERIAL (SEE NOTE 1)
9" MAX
REPAIR AND/OR RECONDITION, AND
RE-TEST PREVIOUS PHASE MATERIAL
(SEE NOTE 2)
'I 1-1' ,_, I •-1' ,_,,, • '---:.-l..!...!.m!.Llml..!...!.;-;--;-1 I ,-1 I,_.. • • ,_,' '':'""';,!....!...!.m.t...L!:111..!....!...!.;-;-;.! 1 i~•, ,_ -·' ,_,' ·==m=rn.!..!...!.rn~TTT' ''ffi'' 'rn-, I,-,',_.'. TIE-IN PREPARATION
ai ai
,-.-----.-.!....!.....!.l!I.!..' 'i-jT..!...!..'TTT.:..:..:.m..:...:..:rn~TTT.! ... .!...!.TTT.:...:....!.11'..:....!....!--,-----.-----;'' ,-------,------.-!...!...!.m.:...:...:.m~,--.------.·' ,-, ,----,' ·--.-----.------.:...:....!.1 ·11.!.....!..:.111~,' ,.! ''•.
COMPLETED TIE-IN BETWEEN PHASES
EP SECTION TIE-IN BETWEEN PHASES
NTS DUPLICATE COPY
TYPICAL STEPPED KEY-IN
DETAIL FOR BOTH
LAYERS or RADON
BARRIER (SEE NOTE 1)
STEPPED
KEY-IN
NOTES:
1. CONSTRUCTED KEY-INS
BETWEEN PREVIOUSLY
COMPLETED RADON
BARRIER AND
SUBSEQUENT RADON
BARRIER (BETWEEN
CONSTRUCTION PHASES)
IN ACCORDANCE WITH
THE COA/OC MANUAL &
2. REPAIR AND/OR
RECONDITION RADON
BARRIER MATERIAL AND
AND TEST (PER LIFT
SPECIFICATIONS).
3. THE TYPICAL STEPPED
KEY SHOWN IS GENERIC.
FIELD CONDITIONS MAY
REQUIRE MULTIPLE
STEPS.
4. "RADON B. LIMITS"
DEPICTS THE FULL
EXTENT or RADON
BARRIER CONSTRUCTED
AND TESTED PER
CONSTRUCTION PHASE.
5. "RADON B. BUYOFF"
INDICATES THE LIMITS or COMPLETED RADON
BARRIER THAT HAVE
BEEN OFFICIALLY
APPROVED PER EACH
CONSTRUCTION PHASE.
6. THE GEOSYNTHETIC
COVER c!c SANDBAGS
ARE ONLY INSTALLED ON
THE NORTHERN EDGE or &
THE PHASES.
7. PHASE 1 USED 30 MIL
LLDPE ON THE TOP
SLOPE AND B OZ
GEOTEXTILE ON THE
SIDE SLOPE.
B. SEE SHEET G02 FOR
SPECIFICATIONS.
~ ~ CII s
__ z I
..JO u 5 ~ .... OlUO I ::, Ill 0:: Z < t;; 0
co ~ !\: u 0::
25 ~ ... 0
U)
Vl w ~ c..
z
WI w< ~ I-CD ::::l
Zw 2: ~ ;:: (.)
I
Vl < :! < Vl t;:; ~ 0
0
E
C
w 0 .... ,....
w (/) ........ ~ ~
~-=-
I
w 0 .... ,.... w (/) t; t:: ..::!
~-=-I
w ~ w<ii' ........
~j
~-=-I
LINER PROTECTIVE
COVER
1x10-6 CM/SEC
RADON BARRIER
(FIRST LIFT)
SACRIFICIAL
SOIL
2
TYPE B FILTER
CLAY LINER
(RETAIN & PROTECT)
OWNER TO REMOVE OR REWORK LINER PROTECTIVE
COVER FOR RADON BARRIER CONSTRUCTION,
FOLLOW LIFT BONDING SPECIFICATIONS FOR
INTERFACE BETWEEN EXISTING AND NEW LAYERS &
CLAY LINER
(RETAIN & PROTECT)
FIRST CUT
(BY OWNER)
EXISTING .
(PRE-CONSTRUCTION)
SURFACE, VARIES
OWNER TO REMOVE OR REWORK LINER PROTECTIVE
COVER FOR RADON BARRIER CONSTRUCTION,
FOLLOW LIFT BONDING SPECIFICATIONS FOR
INTERFACE BETWEEN EXISTING AND NEW LAYERS &
0::
:CW ~~~ _w_
or~
TYPE A RIRPAP
TYPE A FILTER
:::e.., "'z ~:J ..-..
... 0:: (/)
i.....w~ 01--0:: zz < ::,w > o::u~
I
4
EXISTING
(PRE-CONSTRUCTION)
SURFACE, VARIES
EXISTING RUN Off
MATERIAL ..... ri-----ITT...,ITT.,.TiTT""I. I CONTROL BERM & FILL ELEVATION VARIES
.,,.L.r1"1==111==111==111==11 I .,..-,--11 ---~1'f 111==1 11-1 I I-', G) ...-n-11=-7:"r/7,.77,-r/7-T/'7'7 ..,..,,-/2-7 == == I 1-COVER/DITCH
:::e .... "'z ~:J
i...o::: vi" ...... w O>--iii: ZZ..: ::,w> o::u~
I
/, /, ~ L r -111 -11 1_ , PREPARATION--FIRST
11 111 11 I 111-"NATIVE" SOIL
-1 I 1==111=-' •
SECOND CUT
(BY OWNER) EL~ATION VARIES
_____ ..,..(]-::ITT ITT.,.TiT,......
.... r1 ~11f -<"1 -11 1ffl-l I 1_111 I ll l LI' 111-11
~-II I 111 -11 i-(2) . _ .1==11 1 / 1,11• RADON BARRIER &
I l
nE ru 111 111 -, CUT /EXCAVATION
_ ==I I l==I I 1==1 , ,--==I I 1==1 1 1=--1' "NATIVE" SOIL
DRAINAGE DITCH BORROW (FILL) MATERIAL
COMPACTED TO 95% STANDARD PROCTOR
(9" MAX LOOSE LIFTS) ~ INSPECTION ROAD
1 u.~ A'~tl.-~~-
CUT
2ND
_111 Ill ~
I 1-·. • 1 I ,lll . 11 1==11
DITCH FILL. COMPLETE
1° COVER & INSPECTION
. . . Sl--'.. ROAD CONSTRUCT! -,11 Ii 1----------
I I 1-1 1 I "---"NATIVE" SOIL -,,,~,-_ .. _.-_-, ,-EXISTING 111-11 1-{PRE-CONSTRUCTION)
SURFACE, VARIES
DITCH CONSTRUCTION DETAIL
SCALE: 1 "=8' -o•
DUPLICATE COPY
C
~ ~ <O (/) ~ /!:: ~ ~ §-<ti ::;! J: C u a. < w "-I u
' ~ ...__' ~ [5 ::, I ~ ::J1)8~ ~Puv,:::,
~
Vl..JZ , z<ow
~~Et;~ ::, ::, ...J
t., ..J ,-. a::U 0 Vl 1--Ul w (/) >-~ z e ffi < 8
z (/) :r
~-H
DUTSON
BOOTH
C06
.E
ID
C
1 2 4
PROJECT BOUNDARY _______ -J
fENCE OR ROPE
I
(
I
I
----------L--+---'--~--+-----1 x,o-s RADON BARRIER PLACEMENT EXTENTS
-·~7
--i===:Jt:=;==r==i~~-~-sx,o-a RADON BARRIER PLACEMENT EXTENTS
I
I TYPE B FILTER
PLACEMENT EXTENTS
SAC SOIL PLACEMENT I :_1--+----EXTENTS
I I _ _;~----TYPE A f lLTER ZONE
BERM WAS REMOVED AS PLANNED fOR THE CONSTRUCTION Of PHASE 6 FINAL COVER
I
I
I
I
I
I
L . I . PLACEMENT EXTENTS
-4 -
EX ISTING RUNOff CONTROL
BERM REMAINED NORTH Of
PHASE 6 ISOLATION BERM
u
APPROXIMATE TOE Of A,1
RUNOff CONTROL BERM
RUNOFF BERM DE TAI L
SCALE: 1 "=20'-0"
APPROXIMATE TOE
1 Of ISOLATION BERM
I I I / /
\ PHASE 6 PROJECT BOUNDARY !
---jJ_ _QNJE OR /07 / I
&
RUNOfF CONTROL BERM
EDGE Of NEW
HAUL/INSPECTION
ROAD (SUBSEQUENT
CONSTRUCTION PHASE)
PHASE 6 ISOLATION BERM NORTHERN EDGE,
THE HAUL ROAD RAMP HAS All BEEN BUILT
I
----......._
----------
TYPE A RIP RAP
PLACEMENT EXTENTS
HAUL ROAD RAMP
(RADON BARRIER MATERIAL)
DITCH INVERT END POINT &
~ / I t DITCH "" MATERO>C ~2 , FIELD DETERMINED EXTENT
AND GRADING
;1---------OUTER EDGE Of DITCH
(RIPRAP & fllTER
MATERIAL)
EXISTING SURFACE
(PRE -CONSTRUCTION)
CONTOUR LIN ES (TYPICAL)
EDGE OF NEW
HAUL/INSPECTION
ROAD (INITIAL
CONSTRUCTION PHASE)
----o--------a-Q:= BERM. BERM ELEVATION ~4274.2 PRMCT 9-0u,om /
fENCE OR ROPE HAUL ROAD RAMP TYPICAL DETAIL
ROCK RUNOff AREA
{FIELD DETERMINED
AREA & THICKNESS)
PHASE 6 1X10-1
CM/SEC RADON / ~
BARRIER LIMITS ~ L'-V( .-d
N 13,276.6
E 10,348.0 >
EXISTING SURFACE
CONTOUR LINES
ISOLATION RUNOFF BERM DETAIL
EXISTING SURFAC
--,,--;-CONTOUR LINES &
&
SCALE: 1 "= 20'
NOTES: &
1. RUNOff CONTROL BERMS CONSTRUCTED AND MAINTAINED BY THE OWNER. FIELD ADJUSTED THE
BERMS, AS NEEDED WITH ENGINEERING APPROVAL. BERMS WILL DIVERT RUNOFF fROM ADJACENT
AREAS fROM FLOWING ONTO RADON BARRIER AND/OR INTO THE COVER DRAINAGE DITCH.
2. RUNOff CONTROL BERMS CONSTRUCTED TO THE COA/OC MANUAL SPEClflCATIONS AND ARE AT
LEAST 4 FT WIDE AT THE TOP. FIELD ADJUSTED THE CENTERLINE AND TOE AS NEEDED.
3. PROJECT BOUNDARY fENCE/ROPE INSTALLED AND t.4AINTAINED ARE ROPE, WITH APPROPRIATE
RADIATION POSTINGS.
4. REfER TO CONSTRUCTION NOTES ON SHEET G02 fOR HAUL ROAD RAt.4P CONSTRUCTION AND
MATERIAL SPECIFICATIONS.
DUPLICATE COPY
~ ~ .., ::, <) ~ I ~ ~ l5 0 =, u i= I.&. <II Uo I c,:::, v, 0 C< z
-( I.&. ti; Q
:~8i '!) II) u
:t ~ g; !!l 0.. a:: .... 0
6-
S~ ~~.,, :! I
(j a. "-tE. 0 I ' .,,
~
u,O:::
~
2:u,VlI _.>-'<t
(j O < I-• (.) t;:; ::,
~
v,_.a ~ § ~ ~~ ~ "-< :::i c,-'tijVl(.) ~ ~ ~ §
E5 < ~ z V, V) ~ ~~
24001
C07
b:.