HomeMy WebLinkAboutDDW-2025-002207
March 7, 2025
Darren Hess
Weber Basin WCD Central
2837 UT-193
Layton, Utah 84041
Subject:Operating Permit, 5600 South Culinary Pipeline Relocation (Phases 2 & 3);
Weber Basin WCD Central, System #29023, File #13565
Dear Darren Hess:The Division of Drinking Water (the Division) received a request for an Operating Permit for the5600 South Culinary Pipeline Relocation (Phases 2 & 3) project from your
consultant, Tanner Sweat, P.E. with Bowen Collins & Associates on February 19, 2025. The Division issued Plan Approval for this project on January 24, 2024.
Our understanding of the project was the relocation of two segments of existing culinary water
pipeline infrastructure due to impacts of the UDOT 5600 South Interchange project.
Approximately 2,300 feet of 24-inch diameter ductile iron pipe (DIP) and 2,600 feet of 30-inch
diameter Prestressed Concrete Cylinder Pipe (PCCP) were replaced by 4,900 feet of 30-inch
diameter DIP. Another 500 feet of 16-inch diameter DIP was replaced with 30-inch diameter
HDPE. Two air valves were replaced and another five were added along with the replacement
of four blowoff valves and three isolation valves.
We have received the following information for 5600 South Culinary Pipeline Relocation (Phases 2 & 3)
Certification of Rule Conformance with plan approval conditions by a professional engineer.
Statement of conformance to design plans.
Satisfactory bacteriological results as evidence of proper disinfection and flushing.
We have determined that all conditions for operating permit issuance have been met. On this
basis, an Operating Permit for 5600 South Culinary Pipeline Relocation (Phases 2 & 3) is hereby issued as constituted by this letter. You may now place 5600 South Culinary Pipeline
Relocation (Phases 2 & 3) in service in your water system.
Please maintain a copy of this letter with your permanent records for future reference.
If you have any questions regarding this Operating Permit, please contact Cameron Draney, P.E.,
of this office, at (385) 271-7039, or Michael Newberry, P.E., Permitting and Engineering Manager, at (385) 515-1464.
Sincerely,
Russell Seeley, P.E.
Assistant Director
CLD/mrn/mdbcc:Scott Braeden, Weber-Morgan Health Department, sbraeden@co.weber.ut.usTanner Sweat, Bowin Collins, tsweat@bowencollins.comJordan Oyler, Bowin Collins, joyler@bowencollins.comDarren
Hess, Weber Basin WCD Central, dhess@weberbasin.govMatthew Meier, Weber Basin WCD Central, mmeier@weberbasin.govJosh Hogge, Weber Basin WCD Central, jhogge@weberbasin.govCameron Draney,
P.E., Division of Drinking Water, cdraney@utah.govJennifer Yee, Division of Drinking Water, jyee@utah.gov
CDraney 29023 13565 OP Phase 2 & 3 5600 South Pipeline