Fwd: Clarifications?
1 message
Matt Sullivan <msullivan@utah.gov>Wed, Aug 28, 2024 at 9:34 AM
To: Deq submit <dwmrcsubmit@utah.gov>
Summit County, Three Mile Canyon Landfill, SW205
Updated Permit Application
---------- Forwarded message ---------
From: Issa Hamud <issahamud@yahoo.com>
Date: Mon, Feb 26, 2024 at 11:06 AM
Subject: Re: Clarifications?
To: Matt Sullivan <msullivan@utah.gov>
Matt,
Attached is the updated document. Thank you for the prompt review. Issa
Issa A Hamud, P.E.
Five Star Engineers LLC
corrected-DSHW-2022-026312-Issa-pages 1-103.pdf
23643K
8/29/24, 6:56 PM State of Utah Mail - Fwd: Clarifications?
https://mail.google.com/mail/b/AEoRXRS0rrGK4Ed_VWQNFRIRPWI-b5C8UEPsqpP4j7WCnESyCxma/u/0/?ik=adf9d5e615&view=pt&search=all&per…1/1
DSHW-2024-008064
Part II – Three Mile Landfill Permit Application 18 November 2022
Since the application of select waste over the protective layer of soil on the side slopes
will take place incrementally as the level of MSW within the cell raises, specific
measures will be followed to minimize the potential of liner damage. The following
procedure will be followed to ensure protection of the liner over the side slopes:
All Spotters and Equipment Operators involved with the placement of select
MSW will have annual training delineating the screening and placement of the
select MSW. The annual training documentation will identify the person receiving
the training, date of training, and the name of the person providing the training.
All training documents will be included in the operation record.
General MSW will be placed in the new lined cells only after the placement of the
protective soil has been completed. As the waste is placed, landfill Equipment
Operators will spread the select MSW in a layer of approximately 1’-2’ thick. The
Equipment Operator will perform the initial screening of the MSW as he/she
spreads the MSW into the 1’-2’ thick layer.
A dedicated Spotter will perform the second screening of the MSW for objects
capable of causing damage to the liner by penetrating the protective soil layer. All
materials with the potential of damaging the liner through the two (2) foot thick
soil layer will be removed from the MSW.
Once the MSW has been screened by the Spotter and deemed adequate for use as
the select MSW layer, the Landfill Superintendent will be notified.
The Equipment Operator will screen the MSW another time as he/she places the
select MSW layer over the two (2) foot thick protective soil layer.
The Superintendent will periodically observe the placement of the select MSW layer on
the side slopes as a final screening of the select MSW.
3.2.2.2 Development of Cell 2
Construction
Cell 2 will be constructed on 2024/2025 and begin accepting waste in 2025. Soil
generated from the Cell 2 excavation will be used to construct site access roads and for
daily landfill operational cover. Any excess soil will be stockpiled for use as daily,
intermediate, or final landfill cover construction in the Phase A Closure area.