HomeMy WebLinkAboutDAQ-2025-001201WES(O OPERATING, IN(. OIL A GAS OPERATIONS January 14,2025 Mr. Bryce Bird, Director Division of Air Quality Attn: Compliance Section 195 North 1950 West P.O. Box 144820 Salt Lake City, Utah 84116 Re: NSPS OOOO -Semi-Annual Report- Period 022024 Dear Mr. Bird: The Blue Hills Gas Plant owned by Wesco Operating, lnc. is subject to the equipment leak standards in 40 CFR Part 60, Subpart OOOO. Subpart OOOO requires sources subject to the provisions to submit semi-annual reports to the Administrator in accordance with 40 CFR Part 60, Subpart Wa. Endosed is the semi-annual report, forthe period July 2024 through December 2024, that indudesthe required information identified under Section 60.487a of Subpart VVa. Please call me at (218) 340-2195 or todd@insightenv.com if you have any questions regarding this report. Sincerely, REXTEwED tnirials: @ r^,,. z'lfu f\slat Compliance Srutrr, rF.e.\^e c/ rr,u t481{Todd Monison Compliance Specialist I nsi ght Environmental, I nc. Encl. cc: State of Utah, Division of Air Quality, Department of Environmental Quality UTAH DFPAFITMENT OF -._DIVISION OF AIR OUALITY WESCO OPERATITIG, IN(. OIL & GAS OPENATIONS Statement of Gertification Wesco Operating, lnc. Blue Hills Gas Plant 40 CFR 60 Subpart OOOO Semi-AnnualReport Period July 2024 through December 2024 This document and all attachments were prepared under my direction or supervision in accordance with a system desQned to assure that qualified personnel properly gather, evaluate, and compile the information submifted herein. I certify that based on information and belief formed after reasonable inquiry, the statements and information in this document are true, a@unate, and complete. The reasonable inquiry on which this certifcation is based consisted of my inquiry of the person or persons responsible for gathering, evaluating, and compiling the informatirn submitted herein. ,5/Jk Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report Reporting Period: I July,2O24 to December,2024 Process Unit:Gas Plant Process Unit: NGL Storage Dates of process ,niiltffiilffi Dates of process unit shutdown: N/A Number of valves subject to the requirements of $60,482-7a, excluding those valves designated for no detectable emissions under the provisions of $60.482-7a(f).708 Number of pumps subject to the requirements of $60.482-2a, excluding those pumps designated for no detectable emissions under the provisions of 550,482-2a(e) and those pumps complying with 560.482-2a(f).o Number of compressors subject to the requirements of 550.482-3a, excluding those compressors designated for no detectable emissions under the provisions of S60.482-3a(i) and those compressors complying with $60.a82-3a(h).o Number of connectors subiect to the requirements of 560.482-11a.1628 Number of pressure relief devices subject to the requirements of $60.5401(b) except for those pressure relief devices designated for no detectable emissions under the provisions of 560.482-4a(a) and those pressure relief devices complying with 50.482-4(c).19 Number of valves subject to the requirements of $60.t182-7a, excluding those valves designated for no detectable emissions under the provisions of $60.482-7a(f).202 Number of pumps subject to the requirements of 560.482-2a, excluding those pumps designated for no detectable emissions under the provisions of $60.482-2a(e) and those pumps complying with 560.482-Za(fl.0 Number of compressors subject to the requirements of $50.482-3a, excluding those compressors designated for no detectable emissions under the provisions of $60.482-3a(i) and those compressors complying with 460,482-3a(h).o Number of connectors subject to the requirements of S60.482-11a.761 Number of pressure relief devices subject to the requirements of $60.5401(b) except for those pressure relief devices designated for no detectable emissions under the provisions of 560.482-4a(a) and those pressure relief devices complvine with 60.482-4(c).8 Period: I July,2O24 to December,2024 Process Unit: Reporting Period: Gas Plant Julv,2024 NUmDer oT vatves ror wnlcn teaKs were oereceo a5 oescnoeo rn i60.482-7a(b) or 960.483-2a 0 ltutiluEt ut vdtvts> tut wItLI tgdtr> wErE ltut I EPdil requ ired in S60.482-7a(dX1)0 Number of pumps for which leaks were detected as described in 560.a82-2a(b), (dX4Xii)(A) or (B), or (d)(sXiii)0 Number of pumps for which leaks were not repaired as required in 96o.482-2a(c)(1) and (dX6)0 Number of connectors for which leaks were detected as described in 960.482-11a(b)0 Number of connectors for which leaks were not repaired as required in 560.482-11a(d)0 Number of pressure relief devices for which leaks were detected as required in 560.5401(b)(2)0 Number of pressure relief devices for which leaks were not repaired as required in 560.5401(bX3)0 Page 1 of4 Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report Process Unit: Gas Plant Reporting Period: TC@62- Process Unit: Reporting Period; Gas Plant September, 2024 Process Unit: Reporting Period: Gas Plant October,2024 Process Unit: Gas Plant Reporting Period: Nffi;5er, 2024 Process Unit: Reporting Period: Gas Plant December,2024 !umber of valves for which leaks were detected as described in i60.a82-7a(b) or 560.483-2a 0 tlumber of valves for which leaks were not repaired as 'equired in 560.a82-7a(dX1)0 \umber of pumps for which leaks were detected as described in i60.482-2a(b), (dX4)(ii)(A) or (B), or (d)(5Xiii)0 {umber of pumps for which leaks were not repaired as 'equired in 960.482-2a(c)(1) and (d)(6)0 !umber of connectors for which leaks were detected as lescribed in 560.482-11a(b)0 tlumber of connectors for which leaks were not 'epaired as required in 960.482-11a(d)0 \'lumber of pressure relief devices for which leaks were detected as required in 960.5a01(b)(2)o tlumber of pressure relief devices for which leaks were not repaired as required in 560.5401(b)(3)0 Number of valves for which leaks were detected as described in 560.482-7a(b) or 960.483-2a 1 !umber of valves for which leaks were not repaired as 'equired in $60.a82-7a(dX1)0 Number of pumps for which leaks were detected as described in 960.a82-2a(b), (dX4Xii)(A) or (B), or (dXsXiii)o \lumber of pumps for which leaks were not repaired as 'equired in 560.482-2a(cX1) and (d)(6)0 Number of connectors for which leaks were detected as described in 560.482-11a(b)3 \lumber of connectors for which leaks were not 'epaired as required in 960.482-11a(d)0 Number of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 tlumber of pressure relief devices for which leaks were not repaired as required in 960.5401(b)(3)0 Number of valves for which leaks were detected as described in 560.482-7a(b) or 960.483-2a 0 Number ot valves for which leaks were not repaired as required in 960.482-7a(dX1)0 Number of pumps forwhich leaks were detected as described in 960.482-2a(b), (d)(4XiiXA) or (B), or (d)(s)(iii)0 Nurnber of pumps forwhich leaks were not repaired as required in 560.482-2a(cX1) and (d)(6I o tlumber of connectors for which leaks were detected as lescribed in 960.482-11a(b)0 Number of connectors for which leaks were not repaired as required in 560.482-11a(d)0 \lumber of pressure relief devices for which leaks were detected as required in 560.5a01(bX2)0 Number of pressure relief devices for which leaks were not repaired as required in 960.5a01(b)(3)o \lumber oI valves tor wnrcn leaKs were oetecleo as oescnDeo rn i60.482-7a(b) or 56o.483-2a 0 NUmDer oT vatves Tor wntcn teaKs were nor reparreo as required in 560.482-7a(dXl)o !umber ot pumps lor wnrcn leaks were oetefieo as oescnoeo ln i6o.a82-2a(b), (d)(4)(iiXA) or (B), or (dXs)(iii)0 NUmDer oT pumps Tor wntcn reaKs were not reparreo as required in 960.482-2a(c)(1) and (d)(6)o tlumber of connectorsforwhich leaks were detected as lescribed in 960.482-11a(b)o Number of connectors for which leaks were not repaired as required in 560.482-1fa(d)0 !umDer ol pressure relrel oevtces Tor wnlcn leaKs were detected as required in 560.5401(b)(2)o Number ot pressure reliet devices tor which leaks were not repaired as required in $60.5401(bX3)U {umber of valves for which leaks were detected as described in i60.a82-7a(b) or 560.483-2a 0 Number of valves for which leaks were not repaired as requ ired in 950.482-7a(d)(1)o tlumber of pumps for which leaks were detected as described in i60.482-2a(b), (dX4)(ii)(A) or (B), or (d)(s)(iii)0 Number of pumps for which leaks were not repaired as required in 560.482-2a(c)(1) and (dX6)0 [umber of connectors for which leaks were detected as lescribed in 960.482-11a(b)0 Number of connectors for which leaks were not repaired as required in $60.482-11a(d)0 \,lumber of pressure relief devices for which leaks were detected as required in $60.5401(b)(2)0 Number of pressure relief devices for which leaks were not repaired as required in $60.5a01(b)(3)0 Page 2 of 4 Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report Period:July,2024 to December, 2024 Process Unit: NGL Storage Reporting Period: lu9,zA?r4 Process Unit: NGL Storage Reporting Period: August, 2024 Process Unit: Reporting Period: NGL Storage September, 2024 Process Unit:NGL Storage October. 2024 Process Unit: Reporting Period: NGL Storage Number of valves for which leaks were detected as described in 960.482-7a(b) or 960.483-2a 0 Number of valves for which leaks were not repaired as requ ired in 560.a82-7a(dX1)0 tlumber of pumps for which leaks were detected as described in i6o.a82-2a(b), (d)(4Xii}(A) or (B), or (dxs)(iii)0 Number of pumps for which leaks were not repaired as required in 960.482-2a(cXr) and (dX0)o Number of connectors for which leaks were detected as described in 560.482-11a(b)o Number of connectors for which leaks were nol repaired as required in 560.482-11a(d)0 tlumber of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 Number of pressure relief devices for which leaks were not repaired as required in $60.5401(b)(3)0 tlumber of valves for which leaks were detected as described in i50.a82-7a(b) or 960.483-2a o Number of valves for which leaks were not repaired as required in 560.482-7a(dX1)o tlumber of pumps for which leaks were detected as described in i6o.as2-2a(b), (dX4XiiXA) or (B), or (d)(s)(iii)0 Number of pumps for which leaks were not repaired as required in 560.482-2a(c)(1) and (dX6)0 !umber of connectors for which leaks were detected as lescribed in 960.482-1 la(b)o tlumber of connectors for which leaks were not 'epaired as required in 960,482-11a(d)o \umber of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 tlumber of pressure relief devices for which leaks were not repaired as required in E€O.5401(bX3)0 Number of valves for which leaks were detected as described in 560.a82-7a(b) or 960.483-2a 0 [umber of valves for which leala were not repaired as .equired in 560.482-7a(dX1)o Number of pumps for which leaks were detected as described ir 560.482-2a(b), (d)(4Xii)(A) or (B), or (dXs)(iii)U tlumber of pumps forwhich leaks were not repaired as 'equired in 560.482-2a(cXr) and (dX0)0 Number of connectors for which leaks were detected as described in 960.482-11a(b)0 \umber of connectors for which leaks were not 'epaired as required in $60.482-11a(d)0 Number of pressure relief devices for which leaks were detected as required in 560.5a01(b)(2)0 Vumber of pressure relief devices for which leaks were not repaired as required in S6o.54O1(bX3)0 Number of valves for which leaks were detected as described in 560.482-7a(b) or 960.483-2a of valves for which leaks were not repaired as required in 960.a82-7a(dX1) Number of pumps for which leaks were detected as described i $60.a82-2a(b), (dX4XiiXA) or (B), or (d}(sXiii) of pumps for which leaks were not repaired as ired in 960.482-2a(cX1) and ( Number of connectors for which leaks were detected as described in 560.482-1 1a(b) of connectors for which leaks were not epaired as required in 960.482-11a(d) Number of pressure relief devices for which leaks were detected as required in 960.5a01(b)(2) Number of pressure relief devices for wh ich leaks were not repaired as required in $60.5a01(b)(3) November,2O24 Page 3 of4 Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report Process Unit:NGL Storage ber N u mber of va lves for wh ich leaks were detected as described in 550.482-7a(b) or 560.483-2a o tlumber of valves for which leaks were not repaired as 'equired in 960.a82-7a(dX1)0 Number of pumps for which leaks were detected as described in i5o.a82-2a(b), (dX4Xii)(A) or (B), or (dXsXiii)0 tlumber of pumps forwhich leaks were not repaired as 'equired in 960.482-2a(cX1) and (dX6)0 ,lumber of connectors for which leaks were detected as lescribed in 560.a82-11a(b)0 Number of connectors for which leaks were not repaired as required in 960.482-11a(d)0 tlumber of pressure relief devices for which leaks were detected as required in 960.5401(b)(2)0 Number of pressure relief devices forwhich leal<s were not repaired as required in 560.5401(bX3)0 Period: Decem 2U24 {umber of valves for which leaks were detected as described in i60.a82-7a(b) or S60.483-2a 0 Numberof valvesforwhich leakswere not repaired as required in 56O.482-7a(dX1)0 rlumber of pumps for which leaks were detected as described in i60.482-2a(b), (d)(aXii)(A) or (B), or (d)(s)(iii)0 \,lumber of pumps f or which Ieaks were not repaired as 'equired in 560.a82-2a(c)(1) and (d)(6)0 tlumber of connectors for which leaks were detected as lescribed in 960.482-11a(b)o Number of connectors for which leaks were not repaired as required in 560.482-11a(d)o {umber of pressure relief devices for which leaks were detected as required in $00.5aO1(b)(2)0 Number of pressure relief devices for which leaks were not repaired as required in 96O.5a01(b)(3)0 Page 4 of 4 l:,e t'', r ll n r I I' I i fr:-rr i"l i:; Ir.(; { i:{ f. j ;* F} !"i i Report Parameters Regulation: EPA60-OOOO Comp. Group: All Compliance Groups Unit: GAS PLANT Connectors lncluded Pressure Relief Devices lncluded Report Date: th3n025 ReportingPeriod'.71112O24 - 12131/2024 5rvBfrrp?E I Month Active Count M21 Leaks Late Repairs Delayed Added Deleted COMPR CONECT PUMP RELIEF VALVE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JU tY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JU LY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER 0 0 0 0 0 0 1641 1640 1640 1 628 1628 1628 709 709 709 708 708 708 4 4 4 4 4 4 39 39 39 39 39 39 0 0 n 0 0 0 0 0 3 0 0 0 0 0 0 0 0 0 n 0 n 0 0 0 0 n 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 I 0 12 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 n 0 1 0 0 0 0 0 0 0 0 o 0 0 1 0 0 0 0 0 0 0 0 0 .l'his roport produced using Skvllridgc LDAIi Last nrodilied : I | /10/2020 Page I ol2 Senti-ArrrruaI for NSPS (Rt\jSPS) Report Parameters Regulation: E PA6O-OOOO Comp. Group: All Compliance Groups Unit: GAS PLANT Connectors lncluded Pressure Relief Devices lncluded .[*- SKYBRID6E Report Date: 111312025 Reporting Period: 71112024 - 1213112024 Unit: GAS PLANT Active M21 Late Month Count Leaks Repairs Delayed Added Deleted {00014 'I-his report produced using SkyBridge LI)AR Last nr<rdified : I l/ lO/2020 Page 2 ol 2 ii:) la', ..i Il It r i, i i i()t I i .'l P Sl i,:i f'j -q [1 ;r ] Report Parameters Regulation: EPA6O-OOOO Comp. Group: All Compliance Groups Unit: NGL STORAGE Connectors lncluded Pressure Relief Devices lncluded .q*- 5rcYBRID6E Report Date: 1113D025 Reporting Period. 71112024 - 1213112024 FTitl-hffiffincei vatt!. trvLL.---*- Month Active Count M21 Leaks Late Repairs Delayed Added Deleted COMPR JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER 0 0 0 0 0 n 761 761 761 761 761 761 3 3 3 3 3 ? 14 14 14 14 14 14 202 202 202 202 202 202 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 CONECT 0 0 0 0 0 0 0 0 n 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 PUMP 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 RELIEF 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 VALVE 0 0 0 0 0 0 0 0 0 0 n 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 This report produced using Sk-vBridge l.DAIt Last moditled I I /1012020 Page 1 of 2 Serrr r-Anrtt lit I fc,i' NSPS ( RIJ SP{ii Report Parameters Regulation: EPA60-OOOO Comp. Group: All Compliance Groups Unit: NGL STORAGE Connectors lncluded Pressure Relief Devices lncluded n-- 5TYBRID6E Report Date: 111312025 Reporting Period. 711/2024 - 12/3112024 Unit: NGL STORAGE Active M21 Late Month Count Leaks Repairs Delayed Added Deleted 00000 'l'his report produced using SkyBridge I,DAR I-ast nrodified : I ll 10/2020 Page 2 ol 2 q)b!drtroJoE"EoJoEDtr - '6 E :{EN=c l !-o,at EE$E ,g E .c G FJ e0)oE6oo6)aha)o6o:ooz !to oU , e- 0 1 o o5 ( J ; ., GfE ? i oo o .a E 1 : o- o. t i xo G UJ E c t otooo.CLsoool!cooauG't tr ci = O 9r o! o - o. = 9o . !o . co>Oa ! oooo ooocioc(Eocoo(,oJtnos(, F 'i i =E tC\ roN(r )c\lIt(\ toc\|Nijo(, (Lc,cEoCL0,E. rJ )O,loC! t0) (EoEooot$ oooo o .. &9 5 i'i it r g PE a-c{eO5-o o E e R fr YE ? 8 ? rO H o q HE i S E E. E ; . " q o( E Z oo . .: E F E g Ei , i 0) o i i 6 9 v. t 5 & d WESCO OPERATING, INC. OIL A GAS OPERATIONS U'Lrri' 1 DI- l']AR-I MFN f OF E NVi iloii r\4i: NTAL Q IJA.L I TY January 14,2025 Ms. Cynthia Reynolds Air and Toxics Technical Enforcement Program Office of Enforcement Compliance and Environmental Justice Mail Code SENF-AT 1595 V[nkoop Street Denver, CO 80202-1129 DIVISION OF AIR QUALITY Re: NSPS OOOO - Semi-Annual Report - Period 022024 Dear Ms. Reynolds. The Blue Hills Gas Plant owned by Wesco Operating, lnc. is subject to the equipment leak standards in 40 CFR Part 60, Subpart OOOO. Subpart OOOO requires sour@s subject to the provisions to submit semi-annual reports to the Administrator in accordance with 40 CFR Part 60, Subpart Wa. Enclosed is the semi-annual report, for the period July 2024 through December 2024, that indudes the required information identified under Section 60.487a of Subpart VVa. Please call me at (218) 340-2195 or todd@insightenv.com if you have any questions regarding this report. Sincerely, Todd Monison Compliance Specialist lnsight EnMronmental, lnc. End. cc: State of Utah, Division of Air Quality,Department of Environmental Quality WEs(O OPERATING, INC. OIL & GAS OPERATIONS Statement of Gertification Wesco Operating, lnc. Blue Hills Gas Plant 40 CFR 60 Subpart OOOO Semi-Annual Report Period July 2024 through December 2024 This document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather, evaluate, and compile the information submitted herein. I certify that based on information and belief formed after reasonable inquiry, the statements and information in this document are true, accurate, and complete. The reasonable inquiry on which this certification is based consisted of my inquiry of the person or persons responsible for gathering, evaluating, and compiling the information submitted herein. /.' , Jefi Mller, Pbri Manager Btp Hils @s Plant Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report Period:,2024 to December, 2024 Process Unit:Gas Plant NGL Storage Dates of process unit shutdown: N/A Dates of process unit shutdown: Number of valves subject to the requirements of $60.482-7a, excluding those valves designated for no emissions under the provisions of $60.482-7a(f). Number of pumps subject to the requirements of 960.482-2a, excluding those pumps designated for no emissions under the provisions of $60.482-2a(e) and those pumps complying with $50.482-2a(f). of compressors subject to the requirements of 560.482-3a, excluding those compressors designated no detectable emissions under the provisions of 560.482-3a(i) and those compressors complying with of connectors to the requirements of 560.482-11a. mber of pressure relief devices subject to the requirements of 550.5401(b) except for those pressure relief designated for no detectable emissions under the provisions of 560.482-4a(a) and those pressure ief devices complving with 50.482-4(c). Number of valves subject to the requirements of 560.482-7a, excluding those valves designated for no emissions under the provisions of $50.482-7a(f). Number of pumps subject to the requirements of $60.482-2a, excluding those pumps designated for no tectable emissions under the provisions of $60.482-2a(e) and those with 560.482-2a(fl. Number of compressors subject to the requirements of $50.482-3a, excluding those compressors designated no detectable emissions under the provisions of $60.482-3a(i) and those compressors complying with Number of connectors to the requirements of 560.482-1la. Number of pressure relief devices subject to the requirements of 560.5zt01(b) except for those pressure relief devices designated for no detectable emissions under the provisions of S60.482-4a(a) and those pressure relief devices complying with 60.482-4( Period: I Julv,2o24 to December.2024 Process Unit: Reporting Period: Gas Plant Julv,2024 {umber ot valves tor whrch leaks were deteded as descnbeo ln i50.482-7a(b) or 560.483-2a 0 IUmoer oT vatves Tor wnrcn teaKs were nor repatreo as 'equ ired in $60.a82-7a(d)(1)0 rlumber of pumps for which leaks were detected as described in i6o.482-2a(b), (dX4XiiXA) or (B), or (dXs)(iii)0 tlumber of pumps for which leaks were not repaired as 'equired in 96O.tB2-2a(cXr) and (dX6)0 tlumber of connectors for which leaks were detected as lescribed in 960.482-1la(b)0 {umber of connectors for which leaks were not 'epaired as required in 96O.482-11a{d)o tlumber of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 tlumber of pressure relief devices for which leaks were not repaired as required in 960.5a01(bX3)o Page 1 of4 tlumber of valves for which leaks were detected as described in i60.482-7a(b) or S60.483-2a 0 \,lumber of valves for which leaks were not repaired as 'equired in 560.a82-7a(d)(1)o tlumber of pumps for which leaks were detected as described in i5o.a82-2a(b), (d)(4xii)(A) or (B), or (dxs)(iii)0 Number of pumps for which leaks were not repaired as required in 960.482-2a(c)(r) and (dX0)0 Number of connectom for which leaks were detected as described in 560.482-11a(b)o Number of connectors for which leaks were not repaired as required in 960.482-11a(d)0 tlumber of pressure relief devices for which leaks were detected as required in 560.5a01(bX2)0 Number of pressure relief devices for which leaks were not repaired as required in 560.5401(b)(3)0 Process Unit: Reporting Period: Gas Plant Process Unit: Gas Plant Reporting Period: Tuguilb24- Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report September,2024 Process Unit: Reporting Period: Gas Plant Oclober,2024 Process Unit: Reporting Period: Gas Plant ffiCm56T6'14 Process Unit: Reporting Period: Gas Plant oicembe-r,2024- ,lumber of valves for which leaks were detected as described in i60.a82-7a (b) or 96O.483-2a 1 Number of valves for which leaks were not repaired as required in 560.a82-7a(dX1)0 Number of pumps forwhich leaks were detected as described in i60.482-2a(b), (dX4Xii)(A) or (B), or (d)(sxiii)o Number of pumps for which leak were not repaired as required in 96o.482-2a(c)(1) and (dX6)0 rlumber of con nectors for which leaks were detected as lescribed in 960.482-11a(b)3 Number of connectors for which leaks were nol repaired as required in 560.482-11a(d)0 rlumber of pressure relief devices for which leaks were detected as required in $60.5a01(bX2)o tlumber of pressure relief devices for which leaks were not repaired as required in $60.5a01(b)(3)0 tlumber of valves for which leaks were detected as described in i60.a82-7a(b) or 960.483-2a o tlumber of valves for which leaks were not repaired as 'equlred in 560.482-7a(dX1)0 tlumber of pumps for which leaks were detected as described in i6o.482-2a(b), (dX4Xii)(A) or (B), or (dXsXiii)o tlumber of pumps for which leaks were not repaired as 'equired in S6o.482-2a(cXr) and (dXo)0 tlumber of connectors for which leaks were detected as lescribed in 960.482-11a(b)o Vumber of connectors for which leaks were not 'epaired as required in $60.482-1la(d)0 !umber of pressure relief devices for which leaks were detected as required in 960.5a01(b)(2)0 [umber of pressure relief devices for which leaks were not repaired as required in 960.5a01(bX3)0 \umber ot valves ior whtch leal(s were oeteceo as oescnDeo ln i60.482-7a(b) or S60.483-2a 0 NUmDer oT vatves Tor wntcn teaKs were nor repatreo as required in 560.a82-7a(d)(1)0 {umber ot pumps tor wnlch leaKs were oelecleo as oescnDeo ln 160.482-2a(b), (dX4Xii)(A) or (B), or (dXsXiii)0 \umDer oT pumps ror wnrcn leaxs were not reparreo as required in $6O.482-2a(cX1) and (dXe)o \,lumber of con nectors for which leaks were detected as lescribed in 560.482-11a(b)0 Number of connectors for which leaks were not repaired as required in 960.a82-11a(d)o Vumber of pressure reliet devices for which leaks were detected as required in 560.5a01(bX2)o \umber ot pressure reliet devices tor whrch lealG were not repaired as required in 560.5a01(b)(3)o Number of valves for which leaks were detected as described in S60.a82-7a(b) or 560.483-2a o tlumber of valves for which leaks were not repaired as 'equired in 560.482-7a(dX1)o \,lumber of pumps for which leaks were detected as described in i60.482-2a(b), (d)(4XiiXA) or (B), or (dXsXiii)0 tlumber of pumps for which leaks were not repaired as 'equired in 960.482-2a(cX1) and (dX6)0 Number of connectors for which leaks were detected as described in 960.482-11a(b)o ilumber of connectors for which leaks were not 'epaired as required in 560.182-11a(d)o Number of pressure relief devices for which leaks were detected as required in $60.5401(b)(2)0 tlumber of pressure relief devices for which leaks ^rere not repaired as required in 960.5401(bX3)0 Page2 of 4 Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report Period:,2024 to December. 2024 Process Unit: NGL Stora8e Reporting Period: July,2024 Process Unit: NGL Storage Reporting Period: Autust, 2024 Process Unit: NGL Storage Reporting Period: September, 2O24 Process Unit: NGL Storage Reporting Period: October, 2024 Process Unit: NGL Storate Number of valvesforwhich leaks were detected as described in 160.482-7a(b) or S60.483-2a o Numberof valvesforwhich leakswere not repaired as required in $60.a82-7a(dX1)0 ,,lumber of pumps for which leaks were detected as described in i6o.482-2a(b), (d)(4XiiXA) or (B), or (dXs)(iii)0 Numberof pumpsforwhich leakswere not repaired as required in 960.t182-2a(cXr) and (d)(0)o rlumber of connectors for which lea ks were detected as lescribed in 560.482-11a(b)0 Number of connectors for which leaks were not repaired as required in 560.482-11a(d)0 rlumber of pressure relief devices for which leaks were detected as required in 160.5a01(bX2)0 tlumber of pressure relief devices for which leaks were not repaired as required in 96O.5tlO1(bX3)0 tlumber of valves for which leaks were detected as described in i60.482-7a(b) or 960.483-2a 0 tlu mber of valves for which lea ks were not repaired as 'equ ired in 56O.a82-7a(d)(1)0 rlumber of pumps forwhich leaks were detected as described in i60.482-2a(b), (dX4Xii)(A) or (B), or (dXsXiii)0 tlumber of pumps for which leaks were not repaired as 'equired in 960.482-2a(c)(1) and (dX6)0 tlumber of connectors for which leaks were detected as lescribed in 560.482-11a(b)o tlumber of connectors for which leaks were not 'epaired as required in 56O.482-11a(d)o Vumber of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 tlumber of pressure relief devices for which leaks were not repaired as required in 560.5401(bX3)o {umber of valves for which leaks were detected as described in i60.482-7a(b) or S60.483-2a o rlumber of valves for which leaks were not repaired as 'equired in 960.482-7a(dX1)o Number of pumps for which leaks were detected as described in 960.482-2a(b), (dX4Xii)(A) or (B), or (d)(s[iii)0 tlumber of pumps for which leaks were not repaired as 'equired in 960.482-2a(cXr) and (dX6)0 Number of connectors for which leaks were detected as described in 560.482-11a(b)o {umber of connectors for which leaks were not 'epaired as required in 56o.a82-11a(d)0 Number of pressure relief devices for which leaks were detected as required in 560.5a01(bX2)0 {umber of pressure relief devices for which leaks were not repaired as required in S6o.5401(b)(3)0 Number of valves for which leaks were detected as described in 960.482-7a(b) or 960.483-2a o tlumber of valves for which leaks were not repaired as 'equired in 960.482-7a(dX1)0 tlumber of pumps forwhich leaks were detected as described in i6o.a82-2a(b), (dX4XiiXA) or (B), or (dXsXiii)o tlumber of pumps for which leaks were not repaired as 'equired in 56o.482-2a(cXr) and (d)(6)0 rlumber of connectors for which leaks were detected as lescribed in 560.a82-11a(b)0 tlumber of connectors for which leaks were not 'epaired as required in 950.482-11a(d)0 tlumber of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 !umber of pressure relief devices for which leaks were not repaired as required in $60.5401(b)(3)0 Reporting Period: November, 2024 Page 3 of4 Wesco Operating lnc. Blue Hills Gas Plant Semiannual LDAR Report tlumber of valves for which leaks were detected as described in i60.482-7a(b) or 960.483-2a 0 \umber of valves for which leaks were not repaired as 'equired in 560.a82-7a(dX1)0 Number of pumps for which leaks were detected as described in 560.482-2a(b), (dX4Xii)(A) or (B), or (dXsXiii)0 Number of pumps for which leaks were not repaired as required in 960.482-2a(c)(r) and (dX6)0 Number of connectors for which leaks were detected as described in 560.482-11a(b)o Number of connectors for which leaks were not repaired as required in 560.482-11a(d)o Number of pressure relief devices for which leaks were detected as required in 960.5a01(b)(2)o Number of pressure relief devices for which leaks were not repaired as required in 560.5a01(b)(3)o Process Unit:NGL Storage December ztJ24Period: Number of valves for which leaks were detected as described in 960.482-7a(b) or 96o.483-2a 0 tlumber of valves for wh ich lea ks were not repaired as 'equired in 550.482-7a(dX1)0 Number of pumps for which leaks were detected as described in 960.482-2a(b), (dX4)(iiXA) or (B), or (d)(s)(iii)o {umber of pumps for which leaks were not repaired as equired in 960.a82-2a(c)(1) and (d){6)o Nu mber of connectors for which leaks were detected as described in 560.482-11a(b)0 tlumber of connectors for which leaks were not 'epaired as required in $60.482-11a(d)0 Number of pressure relief devices for which leaks were detected as required in 960.5401(bX2)0 tlumber of pressure relief devices for which leaks were not repaired as required in $60.5401(b)(3)0 Page 4 of 4 Serrri Artirua l lor NSPS iRlJi"iPS) Report Parameters Regulation: EPA6&OOOO Comp. Group: All Compliance Groups Unit: GAS PLANT Connectors lncluded Pressure Relief Devices lncluded -[--SKYBRID6E Report Dale: 111312025 Reporting Period: 7 11 12024 _ 12t31t2024 I unit: cAS PLANT I Month Active Count M21 LateLeaks Repairs Delayed Added Deleted COMPR CONECT PUMP RELIEF VALVE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JU LY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JU LY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER OECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER 0 0 0 0 0 0 1641 1640 1640 1628 1628 1628 4 4 4 4 4 4 39 39 39 39 39 39 709 709 709 708 708 708 0 0 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 n 0 0 0 0 0 o 0 o 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 't2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o This report produced using SkvBridge LDAR Last modified I I I lOl2O2O Page 1 of2 Sefi-.i Annuat for l.lsps {RNSPS} i ReportDate: 111312O25 ::::.T"?:IffiT ,h Comp. Group: All Compliance GrouPs Unit: GAS PLANT Connectors lncluded Pressure Refief Devices lncluded Reporting Period: 711t2O24 - 1213112024 Unit: GAS PLANT Active M21 Late Month Count Leaks Repairs Delayed Added tleleted 400014 This report produced using SkyBridge LDAR Last modified : lll10/2020 Page 2 ot 2 Se r."rr Annrifil tr:r NSFS (RNSPS) Report Parameters Regulation: EPA6&,OOOO Comp. Group: All Compliance Groups Unit: NGL STORAGE Connectors lncluded Pressure Relief Devices lncluded -[--5TYBRID6E Report Dale: 1113f2O25 Reporting Period: 71112024 - 12131/2024 Unit:NGL STORAGE Month Active Count M21 Leaks Late Repairs Delayed Added Deleted COMPR CONECT PUMP RELIEF VALVE JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JU LY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER JULY AUGUST SEPTEMBER OCTOBER NOVEMBER DECEMBER 0 0 0 0 0 0 761 761 761 761 761 761 3 3 3 3 3 3 14 '14 14 14 14 14 202 202 202 202 202 202 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 n 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 This report produced using SkyBridge LDAR Last rnodified . llll0l202} Page 1 ol2 Sr,nri "Anriua ! for i',lStlS (RNSPSi Report Parameters Regulation: E PA60-OOOO Comp. Group: All Compliance GrouPs Unit: NGL STORAGE Connectors lncluded Pressure Relief Devices lncluded J-- STYBRID6E Report Date: 111312025 Reporting Period'. 71112024 - 12/31nO24 Unit: NGL STORAGE Late Repairs Delayed Added DeletedMonth M21 Leaks Active Count This report produced using SkyBridge LDAR Last modified: 11/10/2020 Page 2 ol 2 Repair Delayed History (R323) Report Parameters Unil All PrGss Units Regulation EPA6GOOOO Chss: All Componont Clas*s Report Date: 111412025 Area: All Areas Tag#: All Tags Leak opton:Reporting Perad: 711t2o24 - 1213112024 UNIT: Tag#:Locatlon lnsp. Date lnsp. PPM Date on Delay DOR lnsp. PPM Reason For Oalay Exp. Date OateRepair Off WR Approvsd By Date: Delay: Closed No data tor these paEmeteE This report produced using SkyBridge LOAR Last Modified - 1OE22J2O21 Page I of I ffi,_ffisTfi[q, DlvlsloN OF AIR o'1t''"