HomeMy WebLinkAboutDDW-2025-001688Danielle Zebelean <dzebelean@utah.gov>
Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
10 messages
Marianne Booth <mbooth@utah.gov>Thu, Apr 20, 2023 at 6:40 AM
To: JSCLARK@co.davis.ut.us, BANDERSON@wbcity.org, knilsen@wbcity.org, Danielle Zebelean <dzebelean@utah.gov>
Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
The attached letter is being sent out via email only today, please use this version for your records. The hard copy will be
mailed out from our offices at a later date.
If you have questions regarding the contents of the letter, please call or email the contact listed at the end of the letter.
Thank you,
--
Marianne Booth
Project Management Specialist
Division of Drinking Water
Phone: (385) 515-5273
Fax: (801) 536-4211
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
DDW-2023-006656.pdf
218K
Kris Nilsen <knilsen@wbcity.org>Mon, Jun 5, 2023 at 11:12 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "JSCLARK@co.davis.ut.us" <JSCLARK@co.davis.ut.us>, Blake Anderson <BAnderson@wbcity.org>, Marianne Booth
<mbooth@utah.gov>, Steve Maughan <SMaughan@wbcity.org>, "mnewberry@utah.gov" <mnewberry@utah.gov>
Marianne good day,
As per the plan approval request to notify the DDW when construction begins so that inspections can be scheduled,
Construction is beginning Today, Monday June 5, 2023.
2/13/25, 9:35 AM State of Utah Mail - Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1763699003122544801&simpl=msg-f:176369900312254480…1/5
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
[Quoted text hidden]
Kris Nilsen <knilsen@wbcity.org>Fri, Jun 23, 2023 at 2:00 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: "JSCLARK@co.davis.ut.us" <JSCLARK@co.davis.ut.us>, Blake Anderson <BAnderson@wbcity.org>, Marianne Booth
<mbooth@utah.gov>, Steve Maughan <SMaughan@wbcity.org>, "mnewberry@utah.gov" <mnewberry@utah.gov>
Marianne good day,
We plan to use the following products that differ from the approved plan details (due to availability of product).
1. Approved FERNCO reducer as end caps on sleeves.
a. FERNCO reducers available are currently unavailable in the quantity needed for the entire project. We plan
to use Link Seal products as end caps if FERNCO reducers are not available.(see attached image and
website link below)
b. Link Seal product is an approved equivalent end cap by West Bountiful City Engineering and Public Works.
c. LINK-SEAL® | Garlock
2. Spacers in 2” Diameter sleeve pipe
a. Prefabricated Plastic type Spacers for the 2” Diameter sleeve are currently NOT available. We plan to use
the following types of spacers in the 2” diameter sleeves.
i. Link Seal Products (see above website and attached image)
ii. Typical Redwood shims.
iii. Both are approved equivalent by West Bountiful City Engineering
and Public Works.
If you have any question or need additional information, please contact me.
[Quoted text hidden]
2/13/25, 9:35 AM State of Utah Mail - Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1763699003122544801&simpl=msg-f:176369900312254480…2/5
link seal.JPG
94K
Danielle Zebelean <dzebelean@utah.gov>Mon, Jun 26, 2023 at 12:13 PM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>, Steve Maughan <SMaughan@wbcity.org>
Thank you for the updates Kris!
Dani Zebelean, P.E.
Environmental Engineer II | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Mon, Jun 3, 2024 at 7:37 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>, Steve Maughan <SMaughan@wbcity.org>
Hi Kris,
Checking in on the progress of this project. Are the water lines completed?
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Kris Nilsen <knilsen@wbcity.org>Mon, Jun 3, 2024 at 8:56 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: Blake Anderson <BAnderson@wbcity.org>, Steve Maughan <SMaughan@wbcity.org>
2/13/25, 9:35 AM State of Utah Mail - Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1763699003122544801&simpl=msg-f:176369900312254480…3/5
Danielle good day,
Yes, the Water lines are completed.
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Mon, Jun 3, 2024 at 8:59 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>, Steve Maughan <SMaughan@wbcity.org>
Excellent!
Can you submit the items on the checklist of the plan approval and submit for an operating permit? This is the last page of
the plan approval letter. Then we can close out the project on our end.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
Kris Nilsen <knilsen@wbcity.org>Mon, Jun 3, 2024 at 9:08 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Danielle,
Yes, I will get it completed and to you.
[Quoted text hidden]
Kris Nilsen <knilsen@wbcityut.gov>Wed, Nov 27, 2024 at 10:19 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Dani,
I have redlines from the inspector during installation,
I am updating my as-builts set and will get them to you soon, sorry for the delay.
2/13/25, 9:35 AM State of Utah Mail - Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1763699003122544801&simpl=msg-f:176369900312254480…4/5
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
[Quoted text hidden]
Danielle Zebelean <dzebelean@utah.gov>Wed, Nov 27, 2024 at 10:25 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
Excellent! Thank you for the update.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
2/13/25, 9:35 AM State of Utah Mail - Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1763699003122544801&simpl=msg-f:176369900312254480…5/5
Danielle Zebelean <dzebelean@utah.gov>
AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful
City Water System, System #06014, File #13314
2 messages
Kris Nilsen <knilsen@wbcityut.gov>Fri, Jan 17, 2025 at 11:56 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>, Blake Anderson <banderson@wbcityut.gov>
Dani good day,
Thank you for your patience.
Attached are as-built drawings for the subject project.
Please let me know if you have any questions or comments.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Wednesday, November 27, 2024 10:25 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…1/9
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System, System
#06014, File #13314
Excellent! Thank you for the update.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Wed, Nov 27, 2024 at 10:19 AM Kris Nilsen <knilsen@wbcityut.gov> wrote:
Dani,
I have redlines from the inspector during installation,
I am updating my as-builts set and will get them to you soon, sorry for the delay.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…2/9
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, June 3, 2024 9:00 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>; Steve Maughan <SMaughan@wbcity.org>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System, System
#06014, File #13314
Excellent!
Can you submit the items on the checklist of the plan approval and submit for an operating permit? This is the last page
of the plan approval letter. Then we can close out the project on our end.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…3/9
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Jun 3, 2024 at 8:56 AM Kris Nilsen <knilsen@wbcity.org> wrote:
Danielle good day,
Yes, the Water lines are completed.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, June 3, 2024 7:38 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>; Steve Maughan <SMaughan@wbcity.org>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System, System
#06014, File #13314
Hi Kris,
Checking in on the progress of this project. Are the water lines completed?
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…4/9
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Jun 26, 2023 at 12:13 PM Danielle Zebelean <dzebelean@utah.gov> wrote:
Thank you for the updates Kris!
Dani Zebelean, P.E.
Environmental Engineer II | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…5/9
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jun 23, 2023 at 2:00 PM Kris Nilsen <knilsen@wbcity.org> wrote:
Marianne good day,
We plan to use the following products that differ from the approved plan details (due to availability of product).
1. Approved FERNCO reducer as end caps on sleeves.
a. FERNCO reducers available are currently unavailable in the quantity needed for the entire
project. We plan to use Link Seal products as end caps if FERNCO reducers are not available.
(see attached image and website link below)
b. Link Seal product is an approved equivalent end cap by West Bountiful City Engineering and
Public Works.
c. LINK-SEAL® | Garlock
2. Spacers in 2” Diameter sleeve pipe
a. Prefabricated Plastic type Spacers for the 2” Diameter sleeve are currently NOT available. We
plan to use the following types of spacers in the 2” diameter sleeves.
i. Link Seal Products (see above website and attached
image)
ii. Typical Redwood shims.
iii. Both are approved equivalent by West Bountiful City
Engineering and Public Works.
If you have any question or need additional information, please contact me.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…6/9
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
From: Kris Nilsen
Sent: Monday, June 5, 2023 11:13 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: JSCLARK@co.davis.ut.us; Blake Anderson <banderson@wbcity.org>; Marianne Booth
<mbooth@utah.gov>; Blake Anderson <banderson@wbcity.org>; Steve Maughan <smaughan@wbcity.org>;
mnewberry@utah.gov
Subject: RE: Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314
Marianne good day,
As per the plan approval request to notify the DDW when construction begins so that inspections can be
scheduled,
Construction is beginning Today, Monday June 5, 2023.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…7/9
From: Marianne Booth <mbooth@utah.gov>
Sent: Thursday, April 20, 2023 6:40 AM
To: JSCLARK@co.davis.ut.us; Blake Anderson <BAnderson@wbcity.org>; Kris Nilsen <knilsen@wbcity.org>;
Danielle Zebelean <dzebelean@utah.gov>
Subject: Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System, System
#06014, File #13314
Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
The attached letter is being sent out via email only today, please use this version for your records. The hard
copy will be mailed out from our offices at a later date.
If you have questions regarding the contents of the letter, please call or email the contact listed at the end of
the letter.
Thank you,
--
Marianne Booth
Project Management Specialist
Division of Drinking Water
Phone: (385) 515-5273
Fax: (801) 536-4211
drinkingwater.utah.gov
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…8/9
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
AS-BUILT DWG - CWRP 2023 - DDW WATER SYSTEM NO. 06014 - FILE NO. 13314.pdf
10601K
Danielle Zebelean <dzebelean@utah.gov>Tue, Jan 21, 2025 at 10:49 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>, Blake Anderson <banderson@wbcityut.gov>
Thank you Kris,
Can you also submit the other items on the OP checklist? The certification of rule conformance and the bacteriological
samples should be all we need.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
DDW-2023-006656.pdf
218K
2/13/25, 9:36 AM State of Utah Mail - AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Bountiful City Water System, System …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821523551823074603&simpl=msg-f:182152355182307460…9/9
Danielle Zebelean <dzebelean@utah.gov>
RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional
engineer (P.E.) - Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
2 messages
Kris Nilsen <knilsen@wbcityut.gov>Tue, Jan 21, 2025 at 2:26 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>, Blake Anderson <banderson@wbcityut.gov>
Dani,
Thank you for the follow up instructions,
Attached is the Certification of Rule Conformance by a professional engineer (P.E.)
Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314
We are gathering the required documentation to send to you for item 4.
☐ 4. Satisfactory bacteriological samples as evidence of proper disinfection and flushing in
accordance with the appropriate ANSI/AWWA standards:
☐ ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water Mains
Two consecutive sample sets at least 16 hours apart, none positive (e.g., every
1,200 feet, end-of-line, each branch).
Please contact me with any questions or comments.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…1/11
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Tuesday, January 21, 2025 10:49 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>; Blake Anderson <banderson@wbcityut.gov>
Subject: Re: AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Boun ful City Water System,
System #06014, File #13314
Thank you Kris,
Can you also submit the other items on the OP checklist? The certification of rule conformance and the bacteriological
samples should be all we need.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…2/11
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jan 17, 2025 at 11:57 AM Kris Nilsen <knilsen@wbcityut.gov> wrote:
Dani good day,
Thank you for your patience.
Attached are as-built drawings for the subject project.
Please let me know if you have any questions or comments.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Wednesday, November 27, 2024 10:25 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System, System
#06014, File #13314
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…3/11
Excellent! Thank you for the update.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Wed, Nov 27, 2024 at 10:19 AM Kris Nilsen <knilsen@wbcityut.gov> wrote:
Dani,
I have redlines from the inspector during installation,
I am updating my as-builts set and will get them to you soon, sorry for the delay.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…4/11
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, June 3, 2024 9:00 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>; Steve Maughan <SMaughan@wbcity.org>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System, System
#06014, File #13314
Excellent!
Can you submit the items on the checklist of the plan approval and submit for an operating permit? This is the last
page of the plan approval letter. Then we can close out the project on our end.
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…5/11
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Jun 3, 2024 at 8:56 AM Kris Nilsen <knilsen@wbcity.org> wrote:
Danielle good day,
Yes, the Water lines are completed.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, June 3, 2024 7:38 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>; Steve Maughan <SMaughan@wbcity.org>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System,
System #06014, File #13314
Hi Kris,
Checking in on the progress of this project. Are the water lines completed?
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…6/11
Thanks!
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Jun 26, 2023 at 12:13 PM Danielle Zebelean <dzebelean@utah.gov> wrote:
Thank you for the updates Kris!
Dani Zebelean, P.E.
Environmental Engineer II | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…7/11
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jun 23, 2023 at 2:00 PM Kris Nilsen <knilsen@wbcity.org> wrote:
Marianne good day,
We plan to use the following products that differ from the approved plan details (due to availability of
product).
1. Approved FERNCO reducer as end caps on sleeves.
a. FERNCO reducers available are currently unavailable in the quantity needed for the entire
project. We plan to use Link Seal products as end caps if FERNCO reducers are not available.
(see attached image and website link below)
b. Link Seal product is an approved equivalent end cap by West Bountiful City Engineering and
Public Works.
c. LINK-SEAL® | Garlock
2. Spacers in 2” Diameter sleeve pipe
a. Prefabricated Plastic type Spacers for the 2” Diameter sleeve are currently NOT available. We
plan to use the following types of spacers in the 2” diameter sleeves.
i. Link Seal Products (see above website and attached
image)
ii. Typical Redwood shims.
iii. Both are approved equivalent by West Bountiful City
Engineering and Public Works.
If you have any question or need additional information, please contact me.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…8/11
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
From: Kris Nilsen
Sent: Monday, June 5, 2023 11:13 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: JSCLARK@co.davis.ut.us; Blake Anderson <banderson@wbcity.org>; Marianne Booth
<mbooth@utah.gov>; Blake Anderson <banderson@wbcity.org>; Steve Maughan <smaughan@wbcity.org>;
mnewberry@utah.gov
Subject: RE: Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314
Marianne good day,
As per the plan approval request to notify the DDW when construction begins so that inspections can be
scheduled,
Construction is beginning Today, Monday June 5, 2023.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:18218953155264099…9/11
From: Marianne Booth <mbooth@utah.gov>
Sent: Thursday, April 20, 2023 6:40 AM
To: JSCLARK@co.davis.ut.us; Blake Anderson <BAnderson@wbcity.org>; Kris Nilsen
<knilsen@wbcity.org>; Danielle Zebelean <dzebelean@utah.gov>
Subject: Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314
Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
The attached letter is being sent out via email only today, please use this version for your records. The
hard copy will be mailed out from our offices at a later date.
If you have questions regarding the contents of the letter, please call or email the contact listed at the end
of the letter.
Thank you,
--
Marianne Booth
Project Management Specialist
Division of Drinking Water
Phone: (385) 515-5273
Fax: (801) 536-4211
drinkingwater.utah.gov
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:1821895315526409…10/11
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
Certification of Rule Conformance by a Professional engineer - EXECUTED.pdf
68K
Danielle Zebelean <dzebelean@utah.gov>Tue, Jan 21, 2025 at 2:41 PM
To: Kris Nilsen <knilsen@wbcityut.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>, Blake Anderson <banderson@wbcityut.gov>
Great! Thank you Kris.
Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
[Quoted text hidden]
2/13/25, 9:38 AM State of Utah Mail - RE: AS-BUILT DRAWINGS - Certification of Rule Conformance by a professional engineer (P.E.) - Water Main …
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1821895315526409906&simpl=msg-f:1821895315526409…11/11
Danielle Zebelean <dzebelean@utah.gov>
Re: Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314 - Satisfactory bacteriological samples as evidence
1 message
Kris Nilsen <knilsen@wbcityut.gov>Wed, Feb 12, 2025 at 4:36 PM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>, Blake Anderson <banderson@wbcityut.gov>
Dani good day,
A ached are samples showing sa sfactory absent results in compliance with opera ng permit check list requirement,
4. Sa sfactory bacteriological samples as evidence of proper disinfec on and flushing in
accordance with the appropriate ANSI/AWWA standards:
☐ ANSI/AWWA C651-14 AWWA Standard for Disinfec ng Water Mains
Two consecu ve sample sets at least 16 hours apart, none posi ve (e.g., every
1,200 feet, end-of-line, each branch)
The project roads and associated new main waterlines are rela vely short lengths compared to 1200 linear feet, new
main pipe lengths installed are per plan and as follows:
1. 1810 N, main pipe length of approximately 415 linear feet.
2. 1890 N, main pipe length of approximately 411 linear feet.
3. Parking lot connecting 1810 N and 1890 N, main pipe length of approximately 300 linear feet.
4. These three connected segments have a combined main pipe length of approximately 1,126 linear
feet.
5. 560 W street and cul-de-sac, main pipe length of approximately 480 linear feet.
Please let me know if you have any ques ons or comments.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
C. 801.725.2804
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…1/12
From: Danielle Zebelean
Sent: Tuesday, January 21, 2025 2:41 PM
To: Kris Nilsen
Cc: Steve Maughan; Blake Anderson
Subject: Re: Water Main Replacement Project (DS001); West Boun ful City Water System, System #06014,
File #13314 -
Great! Thank you Kris.
Division Name Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Tue, Jan 21, 2025 at 2:26 PM Kris Nilsen <knilsen@wbcityut.gov> wrote:
Dani,
Thank you for the follow up instructions,
Attached is the Certification of Rule Conformance by a professional engineer (P.E.)
Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314
We are gathering the required documentation to send to you for item 4.
☐ 4. Satisfactory bacteriological samples as evidence of proper disinfection and flushing in
accordance with the appropriate ANSI/AWWA standards:
☐ ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water Mains
Two consecutive sample sets at least 16 hours apart, none positive (e.g., every
1,200 feet, end-of-line, each branch).
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…2/12
Please contact me with any questions or comments.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Tuesday, January 21, 2025 10:49 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
Cc: Steve Maughan <SMaughan@wbcityut.gov>; Blake Anderson <banderson@wbcityut.gov>
Subject: Re: AS-BUILT DRAWIGNS - Water Main Replacement Project (DS001); West Boun ful City Water System,
System #06014, File #13314
Thank you Kris,
Can you also submit the other items on the OP checklist? The certification of rule conformance and the bacteriological
samples should be all we need.
Thanks!
Division Name Dani Zebelean, P.E.
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…3/12
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jan 17, 2025 at 11:57 AM Kris Nilsen <knilsen@wbcityut.gov> wrote:
Dani good day,
Thank you for your patience.
Attached are as-built drawings for the subject project.
Please let me know if you have any questions or comments.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…4/12
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Wednesday, November 27, 2024 10:25 AM
To: Kris Nilsen <knilsen@wbcityut.gov>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System, System
#06014, File #13314
Excellent! Thank you for the update.
Division Name Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Wed, Nov 27, 2024 at 10:19 AM Kris Nilsen <knilsen@wbcityut.gov> wrote:
Dani,
I have redlines from the inspector during installation,
I am updating my as-builts set and will get them to you soon, sorry for the delay.
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…5/12
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcityut.gov
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, June 3, 2024 9:00 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>; Steve Maughan <SMaughan@wbcity.org>
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System,
System #06014, File #13314
Excellent!
Can you submit the items on the checklist of the plan approval and submit for an operating permit? This is the last
page of the plan approval letter. Then we can close out the project on our end.
Thanks!
Division Name Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…6/12
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Jun 3, 2024 at 8:56 AM Kris Nilsen <knilsen@wbcity.org> wrote:
Danielle good day,
Yes, the Water lines are completed.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
From: Danielle Zebelean <dzebelean@utah.gov>
Sent: Monday, June 3, 2024 7:38 AM
To: Kris Nilsen <knilsen@wbcity.org>
Cc: Blake Anderson <BAnderson@wbcity.org>; Steve Maughan <SMaughan@wbcity.org>
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…7/12
Subject: Re: Plan Approval, Water Main Replacement Project (DS001); West Boun ful City Water System,
System #06014, File #13314
Hi Kris,
Checking in on the progress of this project. Are the water lines completed?
Thanks!
Division Name Dani Zebelean, P.E.
Environmental Engineer III | Division of Drinking Water
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Mon, Jun 26, 2023 at 12:13 PM Danielle Zebelean <dzebelean@utah.gov> wrote:
Thank you for the updates Kris!
Division Name Dani Zebelean, P.E.
Environmental Engineer II | Division of Drinking Water
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…8/12
M: (385) 278-5110
Hours: M - Th 7 am to 5 pm
drinkingwater.utah.gov
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
On Fri, Jun 23, 2023 at 2:00 PM Kris Nilsen <knilsen@wbcity.org> wrote:
Marianne good day,
We plan to use the following products that differ from the approved plan details (due to availability of
product).
1. Approved FERNCO reducer as end caps on sleeves.
1. FERNCO reducers available are currently unavailable in the quantity needed for the entire
project. We plan to use Link Seal products as end caps if FERNCO reducers are not
available.(see attached image and website link below)
2. Link Seal product is an approved equivalent end cap by West Bountiful City Engineering and
Public Works.
3. LINK-SEAL® | Garlock
2. Spacers in 2” Diameter sleeve pipe
1. Prefabricated Plastic type Spacers for the 2” Diameter sleeve are currently NOT available.
We plan to use the following types of spacers in the 2” diameter sleeves.
i. Link Seal Products (see above website and
attached image)
ii. Typical Redwood shims.
iii. Both are approved equivalent by West Bountiful City
Engineering and Public Works.
If you have any question or need additional information, please contact me.
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:18238966713405913…9/12
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
From: Kris Nilsen
Sent: Monday, June 5, 2023 11:13 AM
To: Danielle Zebelean <dzebelean@utah.gov>
Cc: JSCLARK@co.davis.ut.us; Blake Anderson <banderson@wbcity.org>; Marianne Booth
<mbooth@utah.gov>; Blake Anderson <banderson@wbcity.org>; Steve Maughan
<smaughan@wbcity.org>; mnewberry@utah.gov
Subject: RE: Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
Marianne good day,
As per the plan approval request to notify the DDW when construction begins so that inspections can be
scheduled,
Construction is beginning Today, Monday June 5, 2023.
Thanks,
Kris Nilsen
City Engineer
West Bountiful
550 N. 800 W.
West Bountiful City, UT 84087
knilsen@wbcity.org
O. 801.292.4486 EXT 108
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:1823896671340591…10/12
From: Marianne Booth <mbooth@utah.gov>
Sent: Thursday, April 20, 2023 6:40 AM
To: JSCLARK@co.davis.ut.us; Blake Anderson <BAnderson@wbcity.org>; Kris Nilsen
<knilsen@wbcity.org>; Danielle Zebelean <dzebelean@utah.gov>
Subject: Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water System,
System #06014, File #13314
Plan Approval, Water Main Replacement Project (DS001); West Bountiful City Water
System, System #06014, File #13314
The attached letter is being sent out via email only today, please use this version for your records. The
hard copy will be mailed out from our offices at a later date.
If you have questions regarding the contents of the letter, please call or email the contact listed at the
end of the letter.
Thank you,
--
Division Name Marianne Booth
Project Management Specialist
Division of Drinking Water
Phone: (385) 515-5273
Fax: (801) 536-4211
drinkingwater.utah.gov
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:1823896671340591…11/12
Emails to and from this email address may be considered public records and thus subject to Utah GRAMA
requirements.
West Bountiful City Water System, System #06014, File #13314 - SAMPLE RESULTS - SATISFACTORY -
ABSENT - RESULTS.pdf
859K
2/13/25, 9:37 AM State of Utah Mail - Re: Water Main Replacement Project (DS001); West Bountiful City Water System, System #06014, File #13314…
https://mail.google.com/mail/u/0/?ik=82c167e5f1&view=pt&search=all&permthid=thread-f:1823896671340591371&simpl=msg-f:1823896671340591…12/12