Loading...
HomeMy WebLinkAboutDRC-2005-001281 - 0901a06880abe0a9INrnnNeuoNAL Unexturvr (use) ConponATroN Independence Plaza, Suite 950 . 1050 Seventeenth Street . Denver, CO 80265 . 303 628 7798 (main) . 303 389 I25 (fax) June 20, 2005 VIA OVERNIGHT DELIVERY Mr. Dane L. Finerfrock Executive Secretary Utah Radiation Control Board Department of Environmental Quality 168 North 1950 West PO Box 144850 Salt Lake City, Utah 84114-4850 Re: Ground Water Discharge Permit No. UGW370004, White Mesa Mill Dear Mr. Finerfrock: Pursuant to the request from Loren Morton, Roberts Pond As-Built Report. If you require any additional information on enclosed are three additional copies ofthe the Report, please feel free to contact me. Very truly yours, ,/z*'{YJ.{Harold R. Roberts Vice President - Corporate Development Ron F. Hochstein, IUSA, w/o enclosure David C. Frydenlund, IUSA, w/o enclosure T. Kenneth Miyoshi, ruSA, w/o enclosure As-Built Report MiII Area Retention Basin ("Roberts Pond") White Mesa MiIl International Uranium (USA) Corporation Independence plaza Suite 950 1050 Seventeenth Street Denver, Colorado 80265 T I I I I I I I I T I I 'l I I I I I t As-Euilt Report MilI Area Retention Basin ("Roberts Pond") White Mesa Mill International Uranium (USA) Corporation Independence Plaza Suite 950 1050 Seventeenth Street Denver, Colorado 80265 I t t I I I I T I t I I I I I I I I I Mill Area Retention Basin ("Roberts Pond',) As-Built Report Basis of Need and Project Description In May of 2002, the decision was made to clean out and re-line the White Mesa Mill ("Mill") area retention basin, commonly refeued to as Roberts Pond ("Pond"). The decision was based on concerns about the integrity of the existing Hypalon liner, and concerns that the build up of solids in the Pond from 22 years of operation had reduced the usable capacity and fi'eeboard to unacceptable levels. The Pond had been instailed and lined during the original Mill construction. The intended use of the Pond was as an emergency catchment basis to retain process solution or solids that may be unintentionally released from the Mill during normal operations. The initial plan was to clean the solids from the pond and then inspect the liner and make repairs as necessary. Once cleanout activities began it became obvions that the Hypalon liner would not be salvageable due to damage from the heavy equipment, and there were also concerns that previous damage to tire Hypalon liner had allowed contamination to spread to the sub surface soils. The decision was ultimately made to totally clean out the pond, verifu the area as radiologically clean and re-line the pond with 60 mil High Density Polyethylene ("HDPE"). Cleanup Activities and Radioloeical Verification The cleanout activities involved use of a long-boom track hoe and 10-ton haul trucks. The excavated material was transported to the ore pad because the residual uranium values were determirred to be sufficient to justify processing with the upcoming milling campaign. Excavation of the pond area continued until all the visible residues and liner material were removed from the area. A series of photographs, No. 1 through 8, in Appendix A show various phases of the cleanout activities. The next phase of the cleanup involved the use of a small "Bobcat" type loader to remove small areas of visible contamination while using radiological instruments to monitor the residual levels of contamination. Areas were detennined to be contaminated by use of a Eberline Model 3 with a 44-9 beta-gamma detector which also detects surface alpha contamination, an Eberline ESP-I with AC3-7 alpha probe, and a Ludlum Model 19 micro R meter. This was the initial radiological check to determine the success of the initial cleanup of the Pond area. The surface gamma readings over the pond area after initial cleanout and liner removal are shown in Appendix B. The Pond area is relatively small, less than 0.5 acre, so it was easy to physically check the entire Pond bottom and side slope areas. For comparison purposes, background readings were taken in locations outside of the Pond alea known to be uncontaminated. Photographs No. 9 through 16 in Appendix A illustrate the final phases of Pond cleanout and radiological measurement. Page 1 I I I I I I I t I t I I I I I I I I I Rernediation and cleanout efforts continued until all areas within the Pond were less than 100 microR per hour, or essentially background. After all the contaminated materials were determined to be removed from the Pond area, a 10 foot by 10 foot grid was established and soil samples were obtained and analyzed for uranium. Because the solutions historically present in the pond were from process spills and overflows, it was very unlikely that there would be thorium or radium values in the pond unless they were accompanied by significantly higher uranium values; therefore uranium was chosen as the indicator for final clean up of the pond area. After sample results were verified the pond area was designated as radiologically clean. The Pond is within the curent area covered by the Mill decomrnissioning plan. As such, the area will be included in the cleanup activities for final Mill decommission and will be subject to the radiological cleanup criteria in effect at that time. Synthetic Liner Installation The synthetic liner material specifications, installation procedures and quality assurance/quality control plan is detailed in the "Plans and Specifications for Re- Construction of the Mill Area Catchment Basin, May 2002". A copy of this document is included as Appendix C to this report. In preparation for linel installation, the bottom of the pond was cleaned of all large oversize rock and was rolled with a smooth drum roller to provide a suitable surface for the HDPE liner. The pond side slopes were also raked clean to ensure a suitable surface for the liner. Photographs No. 17 through 24 in Appendix A show typical surface preparation activities. As additional protection for the liner material, geo-textile material was installed over the entire pond bottom prior to liner placement. A series of photographs, No. 25 through 30 in Appendix A show various phases of the installation and cleaning of the geo-textile material. A single 60-mil HDPE liner, in ro11 widths of 22.5 feet, was installed in the pond. Quality Certificates for all the HDPE material supplies to the project are attached as Appendix D. Installation procedures followed the "Quality Assurance Manual for Installation of Flexible Membrane Lining Systems" (QA/QC Plan") that is attached as Appendix E to this report. Based on the approved QA/QC plan, and the total length of field seam in the installation, three (3) destructive tests (1 per 500 feet) were conducted on the liner field sealns. In addition, the entire lengths of all field seams were also tested by use ofair pressure and a vacuum box where necessary. Procedures for destructive and non-destructive testing are detailed in the QA/QC Plan. In addition to the destructive and non-destruction testing of the seams, all liner panels were visually inspected for signs of damage or stress caused by the installation process, with repairs completed and tested as necessary. Repairs were tested by use of a vacuum box. Photographs No. 31 through 52 show various liner installation activities as well as the destructive and non-destructive testing of the liner seams. Once the liner installation was complete approximately one foot of fresh water was placed in the pond to stabilize and secure the liner. Page 2 I t Appendix F, "Installation Reports", provides the following documentation on the I installation procedures and quality control testing: o inspection of the sub-grade prior to liner installation t : ffir*1il;*xf:onstartupseams I : [1frflT111","ffi',:l:i,,."_, . results of all destructive tests on liner seams I : 1x?:;:':i,lTl,ffiIrlip*uouni., I Appendix G, "Liner Installation Drawing" shows the location of each numbered liner I panel and each numbered seam for cross reference against the quality control test results. t .l I I I I I I I I I .T Page 3 I I I t t I I I I I t t I I I t t I I List of Appendices Appendix A Construction Photographs Appendix B Surface Gamma Readings Appendix C Plans and Specifications Appendix D Quality Certificates for Liner Material Appendix E Quality Assurance Manual for Installation of Flexible Membrane Lining Systems Appendix F Installation Reports Appendix G Liner Installation Drawing I I t I I I I I I I I t I I I I I I I Appendix A Construction Photographs Photo 1 - Initial Cleanout of Roberts Pond Figure 2 - Initial Cleanout of Roberts Pond Figure 3 -- Roberts Pond Cleanout in Final Stages Figure 4 - Roberts Pond Cleanout in Final Stages I I I I t I I I I I t I t T I t t I t f':-tS-"7 Figure 5 -- Roberts Pond Final Cleanout Before Verification Figure 6 -Roberts Pond Final Cleanout Before Verilication I I t I I I I I I T T I T I I I t l l'.,:i rl .-1.- r{ tp :-..u Figure 7 --Roberts Pond Final Cleanout Before Verification I I Fiu:*-- ":E# Figure 8 - Roberts Pond Final Cleanout Before Verification I I T I I I I I I I I I I I I I :-::4 a -.t.d -, Figure 9 -- Roberts Pond Final Radiological VerificationI I I Figure l0 - Roberts Pond Final Radiological Verification t I I t I I I .:\, i: ,1 :- :::::-,ia:t:::.::: ':-1::.i.+.=' I I I T I I I I t I t I Photo I I - Roberts Fond Final Radiological Verification - :=-:' l _'_ 'j -}'' . F'igune tr2 - Roberts Fomd F'inal R.adiotogical Verificatiosa t I I T I I I I T T T t T t I Figure l3 : R.oberts Pond Final ftadiological Verilication , 1:::j' .. :1.-d:,:..L1*,.;i*:. , .:1hffi* t II i t- -. G* RoEaer"ts Fomd Ff,mafl Radiological Ver"lfrcatflErfl amd Surf,aee Fneparation {l'i I I T T Figuin"e i4 - I I T I t t I I I T I t I I T I I I I i.-- --{t':'=f Figure 15 -Roberts Pond Final Radiological Verification Figure 16 - Roberts Pond Final Radiological Verification Figure 17 - Final Contouring and Bottom Preparation Figure 18 - Final Contouring and Bottom Preparation Figure 19 - Early Stage of Bottom Preparation Figure 20 - Bottom Leveling and Surface Preparation Figure 2l -- Bottom Leveling and Surface Preparation Figure 22 - Smooth Drum Roller, Bottom Preparation t I I I I t t t t t I I I I t t t I I Figure 23 -Smooth Drum Roller, Bottom Preparation and Anchor Trench Figure 24 - Smooth Drum Roller, Bottom Preparation Figure 25 ^ rnspection and cleanup of Geo-textile surface - -G -{F Figure 26 - Inspection and cleanup of Geo-textile surface t I I t I I t t I t I I I I I T T I I +. Figure 27 - Inspection and Cleanup of Geo-textile Surface u )- s =., Figure 28 - Inspection and Cleanup of Geo-textile Surface I I T I I I I I t I I I I I I I T I I .i,'""=={nr==-,.-. _-_. tT - * Figure 29 - Completed Geo-textile Surface Figure 30 : Beginning of HDPE Liner lnstallation t I I I I I I t t t I t I t I I I I I c ,+-"+- Figure 31 -- Beginning of HDPE Liner Installation Figure 32 - Beginning of HDPE Liner Installation Figure 33 -- Typical Hot Wedge Seaming Operation Figure 34 - Typical IIot Wedge Seaming Operation _T Figure 35 -- Typical Liner Installation Figure 36 - Typical Liner Installation Figure 37 -- Completion of Hot Wedge Weld Figure 38 - Side Slope Seaming Operation Figure 39 -- rnstallation of Last Portions of Liner Material r-rl 13 l -1= \-= T I t t I I t t I I I T I t I I I I I Figure 40 - Liner Panel Installation, Note panel Number Figure 41 -- Destructive Seam Test, Location DT-l ;*{fi Figure 42 - Destructive Seam Test, Location DT-z Figure 43 -- Destructive Seam Test, Location DT-3 Figure 44 - Repair of Destructive Test Location Figure 45 -- Typical Air Channel Testing Figure 46 - Typical Vacuum Box Testing Figure 47 -- Typical Vacuum Box Testing Figure 48 - Backfill and Compaction of Anchor Trench Figure 49 - Destructive Testing of Liner Seam Figure 50 - Completed Liner Installation Figure 51 -- Completed Liner Installation Figure 52 - Addition of Water for Stabilization of Liner T ,ffi1 11 I IIrl i:il f::'l I I I T I I T I I I Appendix B Surface Gamma Readings (after liner removal) t-r o Go U G FEo! o ).r o t<() F] () +i EIEIOInrl-l EI -alol 1rl H.-lEIciloltl 6nl EI cBlol O.,lcJl EIfrl =Ial ooo oooo oooo<) aa9oQ Q9OO e, O9Oe, I6 d6 6 6 5 6 6 ; 6 6 + 6 O to o r d) Loc.l F ol o to I r I Q = ; ; ; ; ; - N N Ol F r F r - r - F F F F F r N c!(\l N ooooooooooooo9QaqQoooooooooE====FRRERRP}R:::PS=PR}PPRR 888PeP88&R8RR8RR883PeR88Eqfiti = - i - - N N c{ N N - - F r r F F r r F F FF (\l OI oI oooooooooooooQQOOQOqOaA9a9A = 6 - N 6 6 F N F 6 6 6 tn (D N - r ro sf (o N @ co F- $ q! :tNrFFrr-CfINFFFFFFF-rr-F FNN oooooooooooooo9o9Qooooq9Q9o6 ; = + 6 6 6 6 6 6 rO N - N Al - ot N rf (o (o rr, st (o @ (o g2 i -r;;r;;(rl N r-F TFFTFFFF r FFFF C! oooooooooooQaoQQOQ9qAAaaAQ96 = d F 6 6 + 6 ; O O (I) cD F c! (f) r Gl c\.1 $ ro rO rO (O (O (O coFFF -TNGJNTFTFFFT F-FrFF oooooooooooooQQaaaoQQQa9aaa5 + ; 6 N 6 F F + + * (o to C') ro to @ @ - co $ :+ $ ro to (o @ 6lr-FTTFFFTFFFFT rFFFrFrrrF FF oo oooooo oo LoooqQaa a 9oo oo o o ootr N 6 6 6 F 6 F F 6 C\r'a + * to @ (o st (D c\l r $ to (o s to (o rF-FFTFFFFFFFTFTFFFFF oooooooooooooQQQagOQOOQ9AaAF d( ; 6 6 F = 6 = 6 + + + ro to to tc, Al $ o o o o (o (o.+ q? FFT,FFF FFTTFF--N oooooooooooooooooQQoqqaaaaQ6 6 ; 66 ; N (' ; ; tO + + |f, Q rt lo ro sf - t sf o @ to Lo q? FrF-rr-FFTFF-rAIrFr Fr(\ oooo ooo o oo roo lr) o o l{)aaooo oo ooQ Q6 + 6 < 6 6'b < < + N dt (\l tO to sf to (o to rr, Q @ (\l to ro sf @C\iNdlr-irir-rrFrr -TGIFFFTFF ooooooooooooooooooooooooooo6 ; C\l 6 tb tn + + (o (i ; - r O oj o (o !o e! S $ * N I <o r lrl ooooooooooooooQaaaQaa9o9aaa6 6 6 6 6 66 6 6 o o o Gl o N Q co ol cD o o o - Q q A IFFFrrF iirr(\lr$l -rrrrr-NNNN 888&888RP8838P898988888898Ra( ; = ; = ; N oj ot - F F r F F F F r - r oI ol ol N r r N ooooooooooooooooooooooooooo6 6 6 c| O O o (D O cD o $ co O O C! $ O O rr) @ rO rO cO O C\t t-dr tb O N i N N o,l c\l F N F F ol At Ol CD (D CD N N Ol r - N N OI I I I I I t I I I t t I I I I I I I I o - N cD $ ro (o r.- co o P = S P : I P : P 3 R e N R N R K Wes to East Goordinates o -0)o.!cAIEFEoo(,(?)-C 5oart:s Lo6Z (o F. @ o, o(\,t (\l N(\I (f,N tN r)N (oN I I I I t I rE ets?lg (E rE EIro IH T'ET*-+, L.tp I t I I I Appendix C Plans and Specifications t I I I :l I I I t t I I I I I I T I I PLANS AND SPECIFICATIONS FOR RE-CONSTRUCTION OF THE MILL AREA CATCHMENT POND WHITE MESA URANIUM MILL BLANDING, UTAH International Uranium (USA) Comoration Denver, Ccilorado t May 2002 1.0 Table of Contents INTENT OF SPECIFICATIONS 1.1 Definitions ENVIRONMTAL QUALITY PROTECTION 2.1 General2.2 Existing Facilities2.3 Water2.4 Air SITE PREPARATION 3.1 General3.2 Excavation 3.2.I General GEOTEXTILE 4.I General4.2 Performance4.3 Materials4.4 Installation Mill Area Catchment Pond - Plans and Specifications Revision 1.0 Page No. 1 1 International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah 2.0 3.0 4.0 I I T t I I I t t I I I t I I I I I T 5.0 Mill Area Catchment Pond - Plans and Specifications Revision 1.0 Table of Conte[tS (cont'd) Page No. 4 5.1 5.2 5.3 5.4 5.5 SYNTHETIC LINER General Performance Requirements Service Conditions Design Criteria Materials 5.5.1 HDPE Liner Items of Work Performed by Vendor Items of Work Preformed by Owner Quality Control 5.8.1 Field Seams 5.8.1.1 5.8.t.2 5.8.1.3 4 4 5 5 7 5.6 5.7 5.8 Destructive Tests Nondestructive Tests Repairs 9 10 10 s.9 Quality Control Reports 5.9.1 Material 5.9.2 Field Installation Reports 5.9.3 As-Built Drawing 5.9.4 Waranty 5.9.5 Acceptance 10 10 10 11 11 11 International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah I I T I I I I I I t T I I I T I t t I Mill Area Catchment Pond - Plans and Specifications Revision 1.0 1.0 INTENT OF SPECIFICATIONS, AND DEFINITATIONS The Specifications presented in this document cover the re-construction of the Mill Area Catchment Pond ("MACP"), including the embankments and synthetic liner, White Mesa Uranium Mill, Blanding, Utah. 1.1 Definitions 1.1.1 Owner - Owner as used in this document is: International Uranium (USA) Corporation Independence Plaza Suite 950 L050 Seventeenth Street Denver, Colorado 80265 Phone (303\ 628-7798Fax (303) 389-4125 1.I.2 Engineer - Designated representative of the Owner responsible for all aspects of the construction activities. 1.1.3 Ouality Control/Quality Assurance Officer - Designated representative of the Owner or Engineer responsible for management and implementation of the Quality Control/Quality Assurance Program. I.I.4 Vendor - Manufacturer, supplier, or contractor providing services or goods referenced in a specific section of this document. International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah Page 1 I t I I T I I I I I T I I I Mill Area Catchment Pond ENVIRONMENTAL QUALITY PROTECTION General - Plans and Specifications Revision 1.0 2.0 2.1 The Work shall be carried out in compliance with all applicable statutes, rules and regulations, licenses, and permits. 2.2 Existine Facilities During construction, care shall be exercised to preserve the existing facilities and prevent any unnecessary destruction, scarring or defacing of the natural surroundings constructed facilities in the vicinity of the Work. 2.3 Water Construction activities shall be performed by methods that will prevent entrance or accidental spillage of pollutants into nearby gullies, washes and underground water sources. Air Reasonable and practical efforts shall be made to operate construction equipment to minimize emissions of air contaminants. Fugitive dust from unpaved haul roads and other areas of heavy vehicle use shall be controlled by sprinkling, dust suppression agents, or by vehicle speed limits. If due to unusual circumstances, sprinkling and/or dust suppression agents are not fully effective in controlling excessive fugitive dust emission, vehicle speeds on unpaved haul roads shall be limited to 10 mph. Storage and handling of flammable and combustible liquids and provisions for fire prevention shall be in accordance with local and State regulations. lnternational Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah to or I 2.4 I I I Page 2 I I T I I I I T I I I I I I I t I I t 3.0 3.1 4.0 4.1 Mill Area Catchment Pond - Plans and Specifications Revision 1.0 SME PREPARATION General The required earthwork for re-construction of the MACP consists of removal of existing mill solution and sediment, and preparation of the MACP bottom and side slopes for synthetic liner installation. The earthwork shall conform to the lines and grade shown on Drawing No. WMM-02-L0T and in accordance with the Specifications. 3.2 Excavation 3.2.1 General Excavation and reconstruction of the MACP shall be made to the lines, grade and dimensions shown on Drawing No. WMM-02-101. The alignments and excavation lines on the drawing are subject to change as may be found necessary to adapt to the existing conditions present on the Mill site and as approved by the Engineer. The excavation shall conform as closely as practical to the established lines and grades. The finished contours cleaned of all loose, soft and disintegrated materials including removal of all such materials from pockets, and depressions in the MACP. All necessary precautions shall be taken to preserve the material below and beyond the lines of all excavations in the soundest possible condition. Where required to complete the Work, all excess excavation and over excavation shall be refilled with suitable materials acceptable to the Engineer. The excavated surface in areas to be covered by a synthetic lining shall be free from all loose earth and rock fragments over 0.5 inches in size, ,ootr, vegetation, or other foreign material. The excavated surface shall also be free from sharp breaks in slope and shall be fairly smooth with no pieces or fragments protruding more than 4 inches from the general plane of excavation, GEOTEXTILE General This specification covers the supply and installation of the Geotextile protective sheet for the MACP as shown on Drawing Nos. WMM-02-101. International Uranium (USA) Corporation White Mesa Uranium Mill BIanding, Utah 4.2 Performance Page 3 T I I I I I I I I I I I T I I I I I Mill Area Catchment Pond - Plans and Specifications Revision 1.0 The geotextile material is to be installed over the entire bottom and side slope area of the MACP. The material is intended for the puqpose of providing a smooth, cushioned surface for protection of the synthetic liner material 4.3 Materials The geotextile shall be a non-woven polypropylene material with a minimum weight of 4 ounces per square yard. 4.4 Installation 1. The geotextile material is to be installed over the prepared sub-base of the MACP and anchored in place by temporary means, approved by the Engineer, prior to installation of the synthetic liner. The surface of the bottom and side slopes of the MACP to be covered by the geotextile and synthetic lining shall be free from loose earth, ruts, sharp breaks in slope, roots, vegetation or other foreign material, and all cobbles or rock fragments protruding from the final smooth surface. 2. Care shall be taken to ensure that the installed geotextile contains no wrinkles or folds, which could potentially hide materials unsuitable for liner installation. Multiple layers of geotextile may be installed to aid in installation and reduce field fitting of odd sized sheets. Sheets shall be heat seamed with a minimum of 6 inches of overlap. SYNTHETIC LINER General This specification covers the design, supply, fabrication and installation of the synthetic Liner for the MACP as shown on Drawing Nos. WMM-02-101. The Liner is to be delivered and installed in the MACP. 5.2 1. 5.0 5.1 2. Performance Requirements The Liner shall resist both the chemical action of the liquids and the physical action of solutions or solids from the milling process as well as the effects of the environment, including but not limited to, extreme temperatures, ultraviolet radiation and variable wind conditions. The sources of constituents in the liquids are from the processing of uranium ore. The composition of the aqueous liquids, which could be stored in the MACP, are expected to have the typical concentrations given in Table 5.2-1. The MACP shall perform at any degree percent full. of fullness from near empty to 100 International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah I J. Page 4 T t t I t I I I I I I I 5.3 Mill Area Catchment Pond - PIans and Specifications Revision 1.0 Liner materials shall be suitable for a design ambient temperature range of minus 30 degrees F to plus 110 degrees F. Liner materials shall with stand the higher liner temperatures resulting from exposure to sunlight. The service life of the Liner shall be at least 25 years. Service Conditions The Liner shall be suitable for installation in an unprotected outdoor location. The Liner will be in service 24 hours per day, 365 days per year. The only time the MACP will be completely empty will be immediately after installation of the Liner. Desisn Criteria The Liner shall be installed in the MACP for which the subgrade has been prepared in accordance with Vendor and Owner Specifications. The dimensions of the MACP are given on Drawing No. WMM-02-101. Solutions may be introduced into the MACP by pumping and by gravity flow through HDPE piping laid over the adjacent ground and upon the interior pond slopes. Solution may also be introduced to the MACP from surface water runoff and from unexpected releases for the Mill process. The Liner shall be reinforced at inlet points to prevent wear, puncture, and/or other damage. Removal of liquids from the MACP will occur by pumping. Liquids may be recycled to the Mill or discharged to the Tailings Management System. The methods and standards of joining and sealing the Liner sections to form a watertight Liner shall be specified by the Vendor in the response to Owners request for quotation. International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah 5.4 1. t I t I I I t Page 5 TABLE 5.2-1 Mill Area Catchment Pond - Plans and Specifications Revision 1.0 TYPICAL LIQUIDS COMPOSITION Ion V U Na NH3 CI s04 Cu Ca Mg AI Mn Zn Mo pH As Se Grams/Liter 0.21 0.105 9.7 7.8 8.0 190.0 0.14 0.63 0.79 2.30 0.r4 t.20 0.70 0.70 0.44 N.D International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, UPh Page 6 2. 4. 5. 6. 7. 8. 9. I I I I I I I I I I I I I T I I I I I Mill Area Catchment Pond - Plans and Specifications Revision 1.0 5.5 Materials Vendor shall warrant the synthetic Liner material supplied, and that the thickness and physical properties meets the requirements of the Specifications as listed in Table 5.5-1. 5.5.1 HDPE Liner The Liner shall be of high density polyethylene (HDPE) with a minimum thickness of 60 mils, installed over the entire surface area of the MACP, including the bottom and side slopes. Liner thicknesses in the Specifications are nominal thickness. Actual thickness shall be within the manufacturer's tolerances. The Liner shall be placed on the prepared subgrade after acceptance by Vendor of the suitability of the surface preparation. The Liner shall meet the Performance Requirements, Service Conditions and Design Criteria in accordance with these Specifications. 5.6 Items of Work Performed by Vendor Work by Vendor shall include but not be limited to the following: 1. Fabrication and installation of an HDPE Liner system for the MACP, including all hardware and accessories for reinforcing of the liner for inlet and discharge of solutions. Delivery of the Liner material to the Owner's Plant Site near Blanding, Utah. Review and acceptance of Owner's earthwork and Liner installation drawings. Inspection and acceptance of Owner's earthwork prior to Liner installation. Furnishing of equipment, materials, supervision and labor for the Liner uncrating, handling and installation, including joining of the Liner material to form a continuous Liner covering the sides and bottoms of the MACP. Repair of any holes or blemishes detected in the liner before acceptance by Owner. All required Quality Control per Section 5.8 of these Specifications. The Liner installer shall provide Owner with layout drawings of the proposed Liner placement pattern and seams prior to project commencement. The drawings shall indicate the panel configuration and locations of seams. The Liner installer shall provide data on installation details for compensating for expansion and contraction due to temperature fluctuations (minus 30o F to plus looo D. International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah Page 7 I I I I T T I I t I I t I I I I I I Mill Area Catchment Pond - Plans and Specifications Revision 1.0 Material Properties for HDPE LinersTABLE 5.5-I Property Gauge (Nominal ) Thickness, Mils (Minimum) Specifi c Gravity (Minimum) Minimum Tensile Properties (Each Direction) 1. Tensile Strength at Break (Pounds/Inch Width) 2 . Tensile Strength at Yield (Pounds/Inch Width) 3 . Elongation at Break (Percent) 4 . Elongation at Yield (Percent) 5. Modulus of Elasticity (Pounds/Square Inch) Puncture Resistance, (lb.) Tear Resistance (Pounds Minimum) Stress Crack Resistance (hrs) Low Temperature, F Dimensional Stability (Each Direction, Percent Change Maximum) Resistance to Soil Burial (Percent Change Maximum in Relation to Original Value) I . Tensile Strength at Break and Yield 2. Elongation at Break and Yield 3 . Modulus of Elasticity Environmental Stress Crack (Minimum, Hours) Test Method ASTM D1593-99 ASTM D792-98 ASTM D638-99 ASTM D882-OO ASTM D4833-OO ASTM D1004-94a ASTM D5397-99 ASTM D746-98 ASTM DI2O4-94 (2l2Fo 15 Minutes) ASTM D3038-93 (1999) ASTM D1693-00 International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah Page 8 1. 2. J. I t I I I I I I I I I I I I I I I I t Mill Area Catchment Pond - Plans and Specifications Revision 1.0 5.1 Items of Work Preformed by Owner Owner shall perform the following: 1. Earthworkincludingexcavation. 2. Construction and repair of embankments as necessary. 3. Placement of the prepared sub-grade 4. Excavation of liner anchoring trenches. 5. Supply and installation of geotextile material. 6. Supply and installation of solution inlet structures and discharge pumps and piping. 5.8 Ouality Control The Vendor shall provide the Quality Control/Quality Assurance functions for installation of the Liner. 5.8.1 Field Seams 5.8.1. 1 Destructive Tests Field Fabricated Startup Seam - Vendor shall provide a representative seam fabricated from the same sheet material and using the same seaming methods as those recommended by the synthetic Liner manufacturer. The startup seam shall be no less than 10 feet (3 m) in length and shall be provided at the start of each day's or shift's seaming. Random samples for shear and peel testing shall be cut from the startup seam. The startup seam shall be allowed to cure or age properly before testing in accordance with manufacturer's directions. Field Cut Out - A minimum of one 3-foot (1.0 m) long section of the fabricated seam per 500 feet of seam shall be cut from the installed Liner. The cutout section shall be wide enough to accommodate peel and shear testing. Random specimens for peel and shear testing shall be cut from the sample. The resulting hole shall be patched with an oval-shaped piece of sheet material and shall be seamed in accordance with the manufacturer's instructions. The cutout seam shall be allowed to cure or age properly before testing in accordance with the manufacture's recommendations. The integrity of the field seams shall be determined in accordance with applicable methods in ASTM D4437-84 Standards. International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah Page 9 t t I I I I I I I I I I I I t I I I il 4. Mill Area Catchment Pond - Plans and Specifications Revision 1.0 The location of the seams, the machine used, the operator, weather conditions and any problems shall be logged on a shift basis. 5.8.1.2 Nondestructive Tests A Quality Control Technician employed by Vendor shall make a visual inspection of all field seams. In addition, the following test methods shall be employed by the Vendor. Air Pressure Testing - Air Pressure Testing shall be performed in accordance with ASTM D5820-95, Standard Practice for Pressurized Air Channel Evaluation of Dual Seamed Geomembranes. Vacuum Box Testing - All field seams shall be inspected for un-bonded areas by applying a vacuum to a soaped section of seam. This nondestructive test shall be performed in accordance with the method given in ASTM D 4437-84 Standards. 5.8.1.3 Repairs All defective field seams as detected by both destructive and nondestructive testsshall be marked and repaired in accordance with manufacturer's recommendations. Quality Control Reports5.9 5.9.1 Material The test reports, material properties sheets and Quality Control certificates required in Section 1.6 shall be supplied to Owner by the Vendor and reviewed by Owner prior to commencement of Liner installation. 5.9.2 Field lnstallation Reports The Vendor shall provide Owner with reports of the following: a) Changes in layout drawings b) Results of test seams. c ) Welding data. d) Nondestructive tests results. e) Destructive tests results. f ) Repair data. International Uranium (USA) Corporation White Mesa Uranium Mill Page 1o Blanding' Utah I I T I I I I I I I I I I I I I 5.9.3 As-Built Drawings Upon completion of the project, the Vendor shall provide Owner with a reproducible original of the drawings showing the panel location number and seam location number, patches and destructive test samples. 5.9.4 Warranty The Liner Vendor shall guarantee the Liner to be free of defects for a period of 10 years after installation. These warranties shall be provided to Owner upon completion of the project. 5.9.5 Acceptance The installed Liner shall be accepted by Owner when: The Liner installation is complete. All Quality Control documentation is submitted As-built drawings are received. Warranty documentation is received. Mill Area Catchment Pond - Plans and Specifications Revision 1.0 International Uranium (USA) Corporation White Mesa Uranium Mill Blanding, Utah a) b) c) d) Page I I I I I il I I :I II I il .l I I I r I I I Appendix D Quality Certificates for Liner Material 227..J5A__00 I I T T :::i:::*h ffiGilcilltr'lu/XmN'+" -ahcrlcq"{G t:ls qucr ll rrlFg cer.Tiir ifiecriie K011070 Liner Type:SMOOTH HDPE Thickness 1.Smm 60mil Length 128 m 420 feerWdth 6.86 m 2Z.S feet A/A'S DATA TEST ."-.-....._..-$.L*E8T........-.._._._..'..-.-*.R-E--S-LI-I-T.S*."._. -.glcc .940min .947 ROLL # Measurement ASTM D-751l5199 (Modified) METRICMIN: 1.557 mm MAX: 1.643 mm AVE: 1.597 mm ENGLISH 61 mil 65 mil 63 mil Lot # Specific Gravity ASTM D-792 DensityI I I T MFIASTM D-1238 COND. E GRADE: Mett Ftow tndex 190oC t2160 gchevron 9638 g /10 min .20-.30 .30 Carbon Black Content ASTM D-1603t4218 Range 2-3o/o 2.65 Carbon Black Dispersion ASTM D.5596 Category 1,2 I l3?i'l"i:TJ?ilo0,,,u0, ( 2 inches / minute ) Average Strength @ Yield psi 2,731 4,561 13 700o/o I I T t Elongation ASTMD-638(Modified) ( 2 inches / minute ) Lo = 1.3" Yield Lo = 2.0" Break Dimensional Stability ASTM D-1204 (Modified) Tear Resistance ASTM D-1004 (Modified) o/o t1 -0.20 nye1gg.e.ltrgnglh @ B-r-ggk psi 4000 Average Elongation @ Yield Average Elongation @ Break Average Dimensional Change 15.52 807.3 Average Tear Resistance 45 54.111 Puncture Resistance FTMS 101 Method 2065 (Modified)Load 104312 lbs I t I Puncture Resistance ASTM D-4833 (Modified)141.280 ESCR ASTM D - 1693 Minimum Hrs w / o Failures hrs 1500 ONGOING ONGCING Notched Constant Tensile Load Is-rll-D.:53e7 CUSTOMER: P.O.#: passifail@35%hrs I I t Colorado Lining 2000216 Date Signature..*d 7-6{0 Quality Control re. *trrcllcilltrluffiffi ==Tcmcttcoq&ii $iSs' qlucr ll rriigl ce niirr {fr ecriie ROLL # Measurement ASTM D-751/5199 (Modified) 145#z2 0:f MIN: MAX: AVE: K081314Lot #Liner Type:SMOOTH HDPE Thickness 1.Smm 60mil Length 128.00 m 420 feetWidth G.A6 m 22.6 feet A/A'S DATA TEST METRIC 1.48 rnm 1.679 mm 1.562 mm ENGLISH 58 mil 66 mil 61 mil *_sktHET** "..._._"..._.-_....-._R ES*-U_LTS**. .-._... . Specific Gravity ASTM D-792 Density g/cc .940min .945 MFIASTM D-1238 COND. E Melt Flow lndex 190oC 12160 g - g /10 min .20-.30chevron 9638 .28 Carbon Black Content ASTM D-1603/4218 Range o/o 2-3 2.01 Carbon Black Dispersion ASTM D.5596 Category 1,2 T I t I I I I I I I I t I I I I I I ,l Tensile Strength ASTM D€38 (Modified) ( 2 inches / minute ) Average Strength @ Yield Average Strength @ Break pst 2200 4000pst 2,639 4,779 ASTMD-638(Modified) ( 2 inches / minute ) Lo = 1.3" Yield Lo = 2.0" Break Average Elongation @ Yield Average Elongation @ Break o/o o/o 13 700 17.71 820.7 Dimensional Stability ASTM D-12A4 (Modified)Average Dimensional Change o/o x1 -0.89 Tear Resistance ASTM D-1004 (Modified)Average Tear Resistance 50.209 Puncture Resistance FTMS 101 Method 2065 (Modified)Load 1A 80lbs 98.058 Puncture Resistance ASTM D-4833 (Modified)140.100 ESCR ASTM D: l6e3 Notched Constant Tensile Load ASTM D -5397 Minimum Hrs w/ o Failures 1 500 ONGOING pass/'fail@35oh Quality Control ONGOING Colorado Lining 20014 Date:.......................Y ,,nn"rur"..# 02-0541 05/07 /oZ 13: 02 FAX AGRII-AUERICA+QC +++ C0L0MD0 LINING K081368 Liner Type:SMOOTH HDPE Thickneee 1.Smm 60mil Length 128 rn Wldth 6.86 m @ot Jt- 120 fset 2?.5 feet TEST _BESULTS___ .951 {*tr el9g1* tr*teceo?ncl&Pl' RoLL# 243228 01 Measurement ASTM D-751/51s9 (Modifiet,) cllucr lluiFg c@FiFrl{fii cctlre Lot # MIN; MAX: AVE: METRIC1.5 mm 1.fiIl mm 1.555 mm ENGLISH50 rnll e4 mil 61 mil Specific Gravlty ASTM D.792 DensiU glcc MFIASTM D-1238 COND. E GRADE: Mell Flow lndex 1900C 12160 g - g /10 mlns639 .19 Carbon Black Content ASTM D-l603/4218 Range Carbon Black Dispersion ASTM D-5596 Category Tensile Strength ASTM D{38 (Modified) ( 2 inches / mlnute ) Average Strength @ Yield Average Strength @ Break psi psi 3,4G3 4,320 15,20 417.3Yo I I I I t I I I T lr I I I I I t I I I I Elongation ASTMD-638(Modified) ( 2 inches / minute ) Lo = 1.3" Yield Lo = 2.0" Break Average ElongaUon @ Yleld Average Elongatlon @ Break Dimenrional Stability ASTM D-1204 (Modifieo)Average Dimensional Ghange -0.09 Tear Resistance ASTM D-1004 (Modified)Tear Resistance lbs lbs 60.039 115.060Puncture ResistancE FTMS 101 Method 2065 (Modified) Puncture Reslslance ASTM D4833 (Modlfled)Load 1ss.960 ESCR ASTM D - 1693 Minimum Hrs w / o Failuree 1500 hrs ONGOING Notched Constant Tensile Load ASTM D -6397 pass/fall@30%200 hrs PASS CUSTOMER: ColoradoLlnlng P.O.#: 2OOO244,-? I I I I t I I I t 05/07/02 13:02 FAx qu,cr ll niig eenihr {fi esrtle RoLL # 220160 Ol _. Lot # -. M031oo !- Llner Tvpe:sMoorH HDPE AGRII-AffERICA*QC +++ COLORADO LINING @oz Thicknese 1.5mm 60mil MeasurBment ASTM D-751/5199 (Modified) METRIC ENGLISH MIN: 1.527 mm 60 mil MAX: 1.641 mm 65 mil AVE; 1,591 rnm Gl mil Length 128width 6.86 m 42O bel m 22.5 feet TEST -.,, RESULTS. Specific GravitY ASTM D-792 Density glcc MFIASTM D-1238 COND. E GRADE: Melt Flow lndex 190oC 1216O g - g i10 mln 9638 Carbon Black Content ASTM D-1603/4216 Range Carbon Black Dlspersion ASTM 0.5596 Category Tensile Strength ASTM D-638 (Modified) ( 2 inches / minule ) Average Strength @ Yield ; Average Strength @ Break i Psi psi 2,619 4,819 I Elongation ASTMD-638(Modified) ( 2 inchee / minute ) Lo = 1.3'Veld Lo = 2.0" Break Average ElongaUon @ Veld Average Elongatlon @ Break % 1O.EE 882',3 Dimenslonal Stability ASTM D-12o4 (Modifled)Average Dimenelonal Change o/o -0.'16 Teer Resistance ASTM D'1004 (Modifiad)fiverage Tear ReslElanoe 40.834 Punciure Resistance FTMS 101 Method 2065 (Modified)Load 9E-665 Puncturo Resielance ASTM D-4833 (Mod'tfied) 147.040 I I I I I I I I T I ESCR ASTM D.1693 Minimum Hrs w / o Failures 1500 hrs Notched Constant Tensile Load ASTM D.5397 pass/fail@30%200 hrs PASS CUSTOMER; Colorado Llnlng ComPanY P.O.#: Quality Cont vo/vI/vA ad.va rlu ROLL #243226 o1 Lot # Aut\L'-,.!||,ll&l\tvai!qv aza vvuvtuu g vv qlrle lhiig E@e1iu {ftreeril-e Llner Typa:SMOOTH HDPE 1.5mm 60mllThickness Length 12A width K081308 m 6.86 mMeasurement ASTM D-751/s19e (Modified) METRIC MIN: 1.494 mm MAX: 1.605 mm AVE: 1.5tl.f mm ENGLISH 59 mil 63 mil 61 mil 120 leel 22.5 feel TEST RESULTS _ .951Speclflc GravitY ASTM D-792 Denslty glcc MFIASTM D-1238 COND. E GMDE: Melt Flow lndex 190oC /2160 g - g /10 mln .19 9839 Carbon Black Content Range ASTM D-160114218 2.69 Carbon Black Dispersion : ASTM D.5596 Category T I T t t I T I I I I I I I I I I t I Tensile Slrangth ASTM D-638 (Modified) ( 2 inches / minute ) ASTMD-638(Modified) ( 2 inches / minute ) Lo = 1.3'Veld Lo = 2.0" Break Avemge Strength @ Yield I psi Average Elongation @ Yield Average Elongation @ Break i 3,46a o/o 15.20 817.s Dirnensional Stability AsrM D-12A4 (Modlfted)Average Dimensional Change oh {r.0E Tear Reslstance ASTM D-1004 (Mortified)Avarage Tear Resistanoe Punclure Resistance FTMS 1o',! Method 2065 (Modified)115.660 Punciure Resistance ASTM D4833 (Modified)Load ESCR ASTM D - 1693 Minimum Hrs w / o Failures 1500 hrs ONGOING Notched Constant Tensile Load ASTM D -5397 pass /tuil@ 30%200 hrs CUSTOMER: GoloradoLining P.O.#: 20OOZ41.2 vo/vl/va Lo,vL lM r\u^rLt lurrtlvaq.qv I I I I T I I isil cilcllFll,I#t - dimc'=e lr*-i'-'---'cePr' Measurement ASTM D-751/5199 (Modified) RoLL#. _ _22933919 Elu,Gr ll niig €@niiu fiieefiie Specific GravitY ASTM D.792 Lot #J041357 Liner Type:SMOOTH HDPE Thickness 1.5mm 60mil Length 120 rn 42O feet Width 6.86 m 225 feet TEST METRIC MIN: 1.605 mm MAX: 't.678 mm AVE: 1,63 mm ENGLISH 63 mil 66 mil 64 mil Density g/cc ,, -.RESULTS- .945 MFIASTM D.1238 COND. E Melt Flow lndex 190oC 12160 g - g /10 min .27 GRADE:chevron 963E Carbon Blacl< Content ASTM D-1603/4218 Range Carbon Black DisPerslon ASTM D-5596 Category Tensile Strength ASTM D-638 (Modified) ( 2 lnches / minute ) Average Strength @ Yleld Average Strength @ Break ri',ir pst 2,418 4,603psi I I I T T I Elongation ASTMD-838(Modified) ( 2 inches / minute ) Lo = 1,3" Yield Lo = 2-0" Break Average Elongatlon @ Yield lil Average fJongation @ Break Yo 17.76 822.0 Dimensionpl $tabiliV ASTM D_1 ?:ii.! (Modified) Tear Resistattce ASTM g-1r)tt4 (Modified)Averagje Tear Resistance ,1 --- .-- A7.784 83-770Puncture Fl6filslance FTMS 101 lvletlrod 2065 (Modified)Load pUnoture [:.enislanCe ASTI/ r). 411,),1 (Modlfled)Load 121.920 ES(-;lr ASt I'i lr '11i93 Minimum Hre w/ o Failures 1500 hrs ONGOING Notri iorl t-.oirstant Tensile Load As-lt4 r'i ['1r;7 pass/fail@30%200 hrs ongolng rtucl.lai i {ri;1!:l:r colorado Lining I I l' t Ti T I. , SM€0AA.FRMpanmenl aryor !,1 8J01 T I I t ; t I I I ; I I I I I 3.4 Defects and Repairs .......,.............14 3.4.1 Identification ...............14 3.4.2 Evaluation ........,.. ........15 3.4.3 Repair Procedures .........15 3.4.3.1 Geomembrane Repair Procedures .....15 3.4.3.2 Geomembrane Verification of Repairs ....................................16 3.5 Backfilling of AnchorTrench ........16 3.7 Soils in Contact with the Geomembrane ............. .............16 SoiUEarth Cover on Top of Geomembrane ............. .................16 Typical Resin Properties............ .............L1 DETAILS OF HOT WEDGE SYSTEM ...............17 SEAM TESTING PROCEDURE ..........r.........;....... ................21 RELD SEAM FAILURE ............. ,.,.,,22 PEEL TEST FOR HOT WEDGE SEAM WELD .....22 DETAILS OF EXTRUSION WELDING SYSTEM ....................,23 DEFECT (LEAK) TEfiNG OF SYNTHmC UNERS .............24 A LEAK DETECTION SYSTEM USING SPARK TESIABLE GEOMEMBMNE ..................................25 CoNDUCTIVEUNER TYPICAL QUESIONS .....26 SPARKTESTING CONDUCNVE LINER ...............28 GEOSYNTHmC TERMINOLOGY ........ ..............30 HDPE REFERENCE UST.. ..................33 DIAGRAMS ANCHORTRENCH DETAILS ..........D1 MULTIPLE I.AYERED ANCHOR TRENCH .........D2 WEDGE WELD ............D3 EXTRUSION WELD ......................D4 GAS VENT ..........,.......D5 HDPE PIPE BOOT ......DG PIPE PENETMTION WITH COLI.AR ................D7 PiPE PENETMTION DOUBLE I.AYER SYSTEM WiTH COLI-AR .............. ................D8 BATTEN ATTACHMENT. SINGLE LAYER ........D9 BATTEN ATTACHMENT. DOUBLE UNER .....D10 I I I Introduction Terms Of Reference 1.1.1 Purpose This manual addresses the quality assurance and quality control of the installation of flexible membrane liners used by Colorado Lining International (CU) in hazardous waste disposal landfills, surface impoundments or other installations as specified by the owner and/or engineer. This manual therefore delineates the quality procedures and standards for production and installation. This material reflects the requirements of the Hazardous and Solid Waste Amendments of 1984 to the Resource conservation and Recovery Act (RCRA), and 'construction Quality Assurance for Hazardous Waste Land Disposal Facilities, Public Comment Draft", Document EPA/530-SW-86-031, Juln 1986. 1.L.2 Quality Assurance and Quality Control In the next context of this manual, quality assurance and quality control are defined as follows: Oualitv Assurance - A planned and systematic pattern of all means and actions designedto provide adequate confidence that items or services meet contractual and regulatory requirements. Ouality Control - Those actions which provide a means to measure and regulate the characteristics of an item or service to contractual and regulatory requirements. In the context of liner production and installation. In the context of liner production and installation: Quality Assurance refers to means and actions employed by CU to assure conformity of the lining system production and installation with the Quality Assurance Plan and Specifications. Quality control refers to those actions taken by the Manufacturer, Fabricator and Installer to ensure that the materials and the workmanship meet the requirements of the plans and specifications. 1.1.3 Lining Materials For purposes of this document, the term "geomembrane" is applied to flexible membrane liners. More specifically "geomembrane" refers to polyethylene geomembranes, with either smooth surface or textured surface for increased friction. These geomembranes include high density polyethylene (HDPE) membranes which are made from resins with a specific aravity greater than 0.935. The quality assurance of a geosynthetic liner system is addressed herein in its entirety, including all stages from manufacture to installation. I I I I t t t.1.4 Scope of Quality Assurance and euality Control The scope of this manual includes the quality assurance applicable to manufacturing, shipment, handling, and installation of all geosynthetics. In particular, full-time quality assurance of the installation of geomembranes is essential. This manual does not address design guidelines, installation specifications, or selection of geomembranes. This manual does not address the quality assurance of soils, except in cases where soil placement may have an influence on the geomembrane. 1.1.5 Units In this manual, all properties and dimensions are expressed in U.s. units, with "equivalent" Si units in parentheses. It should be noted that the conversion is typically only accurate within ten percent. In cases of conflict or clarifications, the U.S. units shall be deemed to govern. 1.1.6 References The manual includes references to test procedures of the American Society for Testing and Materials (ASTM), the Federal Test Method Standards (FTMS) and the "standards for Flexible Membrane Liners" of the National Sanitation Foundation (NSF). Recognizing the changing nature of the above standards and the geosynthetic industry are targe, this manual is subject to periodic revision. Geomembrane Manufacturing and Delivery Manufacturino 2.t.1 Geomembrane Raw Material The raw material shall be first quality polyethylene resin containing no more than 2olo clean recycled polymer by weight, and meeting the following specifications for HDPE: Specific Gravity (ASTM D792 Method A or ASTM D1505):?. 935 prior to the addition of carbon black. Melt Index (ASTM D1238 condition 190/2.t6):0.05 - 0.3 g/10 min. Quality control testing shall be carried out to demonstrate that the product meets this specification. Prior to project completion, CLI shall provide the Project Manager with the following information: The origin (resin supplier's name, resin production plant), identification (brand name and number) and production date of the resin; A copy of the quality control certificates issued by the resin supplier noting results of density and melt index; Reports on the tests conducted by the Manufacturer to verify the quality of the resin used to manufacture the geomembrane rolls assigned to the considered I I I I I I I I I I I I I 2,L t I I I I I I t I I t I I t I t I I I 2.2 facility. These tests should include speciflc gravity (ASTM D792 Method A or ASTM D1505) and melt index (ASTM D1238 Condition 190/2.16); and Repofts on the tests conducted by the Manufacturer to verify the quality of the sheet. 2,1.2 Geomembrane Manufacturing cLI shall provide the Project Manager/owner with a property sheet including, at a minimum, all specified properties, measured using test methods indicated in the specifications, or equivalent. The owner or Ownert Representative shall verify that: The propefi values ceftified by the Manufacturer meet all of the specifications; and The measurements of all properties by the Manufacturer are properly documented, and that the test methods used are acceptable. 2.1,.3 Rolls After receipt of material, CU shall provide the Project Manager with one quality control certificate for every two rolls of geomembrane provided. A responsible party shall sign the quality control certificate. The quality control certificate shall include: Roll numbers and identification; and Results of quality control tests. As a minimum, geomembrane results shall be given for thickness, tensile strength, and tear resistance, evaluated in accordance with ASTM test methods approved by the Designer. Deliverv 2,2.1 Transpoftation and Handling CU through and independent trucking firm or other party as agreed upon by the owner will peform transportation of the geomembrane. If the geomembrane arrives on site prior to CLI project personnel, the customer is responsible for off-loading rolls. Geomembrane, when off-loaded, should be placed on a smooth, welldrained surface, free of rocks or any other protrusions which may damage the material. No special covering is necessary for geomembrane. The following should be verified prior to off-loading geomembrane: Handling equipment used on the site is adequate and does not pose any risk or damage to the geomembrane; and personnel will handle the geomembrane with care. Any welding rod delivered to the site prior to CLI arrival should be kept covered and dry, or placed in a storage facility. Upon arrival at the site, CU shall conduct a surface observation of all rolls for defects and for damage. This inspection shall be conducted without unrolling rolls unless defects or damages are found or suspected. cLI shall indicate any damage to the t I I t I I I Project Manager. 2.2.2 Storage The Project Manager shall provide storage in location (or several locations) such that on- site transportation and handling are minimized. Storage space should be protected form theft, vandalism, passage of vehicles, and be adjacent to the area to be lined. 3.1 Installation Anchor Trench Svstems All Anchor Trench systems shall be excavated bythe Earthwork contractor (unless otherwise specified) to the lines and widths shown on the design drawings, prior to geomembrane placement. If the anchor trench is excavated in clay susceptible to desiccation, no more than the amount of trench required for the geomembrane to be anchored in one day shall be excavated (unless otherwise specified) to minimize desiccation potential of the anchor trench clay soils. slightly rounded corners shall be provided in the trench where the geomembmne adjoins the trench so as to avoid sharp bends in the geomembrane. No large rocks or clay lumps shall be allowed to underlie the geomembrane in the anchor trench. Backfrlling of the anchor trench shall be conducted in accordance with Section 3.5. See Diagrams D-1 and D-2 for a detailed drawing of anchor systems. For attaching liners to structures, see Diagrams D-A & D-10. Geosvnthetic Placement Immediately prior to installation of the designed geomembrane liner, cLI and the owner or the owne/s representative shall observe the surface. The decision to repair cracks, if any, should be made only by the project Manager. CLI and the Project Manager for joint approval shall walk the subgrade. CU will sign acceptance of the surface condition of the subgrade. The integrity of the underlying soil is the responsible of the owner/earthwork contractor. Subgrade Preparation Recommendations: No liner shall be placed on sufaces not previously found acceptable by the cLI superuisor or his agent. No sharp stones or other hard objects that could penetrate the liner shall be present in the top 1 inch of the surface to be covered. surfaces to be lined shall be smooth and free of al rocks, sharp stones, sticks, roots, sharp objects, or debris of any kind. The surface should provide a firm; unyielding foundation for the geosynthetic with no sudden, sharp or abrupt I I t I I t t I 3.2 I I I I I I t t t changes or breaks in grade. 3.2.1 Field Panel Identification A field panel is the unit of geomembrane, which is to be seamed in the field; i.e., a field panel is a roll or a portion of roll cut in the field. -,ALthe time of installation, the CLI Field Supervisor shall give each field panel an "identification code" (Number or letter-number). The project Manager shall agree upon this identification code. This field panel identification code shall be as simple and logicalas possible. 3.2.2 Field Panel Placement 3.2.2.L Location Field Panels are located by the CU Field Supervisor in a manner consistent with the Specification and best suited to existing site conditions. 3.2.2.2 Installation Schedule Field Panels are placed one at a time, and each field panel is seamed immediately after its placement (in order to minimize the number of unseamed field panels); and CLI shall record the identification code, location, and date of installation of each geomembrane field panel. Daily progress Report to be submitted to Project Manager for forwarding to Engineer (Owner), also on a daily basis. 3.2.2.3 Weather Conditions Welding placement shall not take place during any precipitation, in the presence of excessive moisture, blowing dust, or in the presence of excessive winds (unless wind barriers are provided). In addition, welding shall not take place in an area of ponded water. 3.2.2,4 Method of Placement CLI shall verify the following: Any equipment used does not damage the geomembrane by handling, trafficking, excessive heat, leakage of hydrocarbons, or other means; The prepared surface underlying the geomembrane has not deteriorated since previous acceptance and is still acceptable immediately prior to geosynthetic placement; Any geosynthetic elements immediately underlying the geomembrane are clean and free of debris; All personnel working on the geomembrane do not smoke, wear damaging shoes, or engage in other activities which could damage the geomembrane; t I I t t I I I I t 'l I T I I I I I I T I I I t I I I I I I The method used to unroll the panels does not cause scratches or crimps in the geomembrane and does not damage the supporting soil; The method used to place the panels minimizes wrinkles (especially differential wrinkles between adjacent panels; Adequate temporary loading and/or anchoring (e.9., sand bags, tires), not likely to. damage the geomembrane, has been placed to prevent uplift by wind (in case of high winds, continuous loading, e.g., by adjacent sand bags, or soil is recommended along edges of panels to minimize risk of wind flow under the panels); Direct contact with the geomembrane is minimizedl i.e., geotextiles, extra geomembrane, or other suitable materials in areas where excessive traffic may be expected protect the geosynthetic(s). CLI shall inform the Project Manager if the preceding conditions are not fulfilled. 3.2.2.5 Damage CU shall inspect the geomembrane after placement and prior to seaming for damage. CU shall advise the Project Manager if any of the geomembrane should be repaired or accepted. Damaged geosynthetic or portions of damaged geosynthetics, which have been rejected, shall be marked and their removal from the work area recorded by CLI. Repairs to geomembrane shall be made according to procedures described in section 3.4. Field Seaminq 3.3.1 Seam Layout . In general, seams should be oriented parallel to the line of maximum slope; i.e., oriented along, not across, the slope. In corners and odd-shaped geometric locations, the number of seams should be minimized. No horizontal seam should be less than 5 feet (1.5 m) from the toe of the slope or areas of potential stress concentrations unless otherwise authorized. When full roll lengths do not extend past the toe of the slope, panel ends may be seamed provided the panel end is cut at and angle greater than 45" to minimize seam stress. A seam numbering system compatible with a panel numbering system shall be agreed upon at the Pre-Constructing Meeting. 3.3.1.1 Field Joints Overlapping adjacent sheets shall make Field joints, approximately 3 inches for extrusion welding and 4 inches for hot wedge welding. 3.3.1.2 Pipe Penetrations Polyethylene pipe penetrations shall be used for pipes penetrating through the lined area. When pipe composition is polyethylene, the fittings should be extrusion welded directly to the pipe if space permits. For dissimilar materials, the fittings should be fastened by mechanical means and sealant applied between the pipe and fittings. I I See details for pipe penetrations in Diagrams D-6, D-7 & D-8. I 3.3.2 Seaming Equipment and Products The approved processes for field seaming are extrusion welding and fusion (hot wedge) I },."Ifllf ,.ul,.,.:H;i*,i,I.i]',f.',ffiffiX',sharr be documented and submitted to the owner The extrusion welding apparatus shall be equipped with gauges giving the temperature t of the apparatus at the nozzle and extruder barrel. The fusion welding apparatus shall be equipped with gauges giving the,applicableI ff,:i,*.., I Equipment used for seaming is not likely to damage geomembrane; The extrusion welder is purged prior to beginning a seam until all heatdegraded I extrudate has been removed from the barel; The electric Aenerator is placed on a smooth base such that no damage occurs to the | ffiffi:compteted no more than one (1) hour prior to extrusion wetdins (bufrins I ^ ;i;il[ ,""::;::::]:", beneath the hot we,dine apparatus after usage; and I The geomembrane is protected from damage in heavily trafficked areas. I .,;":::;;;"*'''" I Prior to seaming, the seam area is clean and free of moisture, dust, dirt, debris of any f kind, and foreign material, and | ,::T::::;:"::":T::'"':',;"berof wrink'|esand"nshmou'[hs" t The normally required weather conditions for seaming are as follows: The high temperature limit for welding is the temperature at which the well being of the I crew becomes unceftain. Unless authorized in writing by the Project Manager, no seaming shall be attempted at I +H:T:::Tl["f::fiil",11J;-'.?["Ji?tins,sqgeds possibre ror errective werdins Further detail for cold weather welding follows in this section. I I 1 t I I t I I I I I I I I I I I I I I t In all cases, the geomembrane shall be dry and protected from the wind. CLI shall verify that these weather conditions are fulfilled and will advise the Project Manager if they are not. The Project Manager shall then decide if the installation shall be stopped or postponed Cold Weather Seamino of Polyethylene Liners Cold weather welding restrictions exist because problems associated with hot air seaming techniques have been mistakenly applied to extrusion welds. The CU extrusion weld, however, has been successfully employed in cold weather on severaljob sites. With the assistance of preheating the sheet, the cLI weld had been applied as low as -5?F. Both the CU extrusion weld and hot wedge weld are able to overcome cold weather welding restrictions because of their unique designs. cLI's extrusion weld is not solely temperature dependent. It combines pressure, extrudate, and mixing action in addition to temperature, to bond the liner together. The mixing action means that convective heat transfer takes place in addition to conductive heat transfer. Overall heat transfer is thus improved, and sensitivity to ambient temperature is dramatically reduced. The CLI extrusion welder is capable of continuously monitoring and controlling the temperatures of the extrudate and the zone of contact for independence of environmental conditions. To control the molten bead temperature accurately and to ensure no fluctuation out of the predetermined range the machine has: a. An over capacity heater band on the extruder. b. An extra over capacity heater band on the nozzle. c. A separate proportional temperature controller for each heater band. d. The nozzle thermocouple positioned approximately 1/8 inch from the end of the nozzle which rides on the sheet. The CLI hot wedge welder lifts the sheet slightly to minimize the effects of suticooling from a frozen sub-base. Temperature controls can be adjusted to guarantee fully integrated welding as demonstrated by peel testing. To guarantee quality welding in cold weather, the following procedures are recommended for CLI welds: The sheet should be preheated before welding any time ice crystals are present in the weld path. When strong winds are present, a shield of some sort should be set in place to prevent large convection heat losses from the welding gun during seaming. Test welds should always be prepared and tested before seaming in order to gauge appropriate welding conditions. (Example: Welding machine temperatures should be set higher and welding rates slowed down.) 3.3.5 Trial Seams I I Trial seams shall be made on fragment pieces of geomembrane liner to verify that I seaming conditions are adequate. Such trial seams shall be made at the beginning of t each seaming period (start of day, midday, and anytime equipment is turned off and allowed to cool down) for each seaming apparatus used. Trial seams shall be made | ;::lJ,#:'- '".*"]ll]:rrreet(1.0m)ronsbylroot(0.3m)wide I ffiil::lTip}I,,X,ffisea.m centered lensthwise. seam overlap shallbe nominallv Two adjoining specimens each 1 inch (25 mm) wide, shall be cut from the trial seam I sample by the.installer. The specimens shall be tested respectively in shear and peel t using a field tensionmeter, and they should not fail in the seam. If the additional specimen fails, the entire operation shall be repeated) If the additional specimen fails,I i:;iq[,:i,1,$il1H:t*":r"J"?l*5:::ffi'i::*nH:1l,ri,T,tTffI;:, | 3.3.6 General Seaming Procedure Unless otherwise specified, the general seaming procedure used by CU shall be as I ;" ,,;, of geomembrane shall be overtapped by approximatety four inches (100 mm) t ;'#:::::.:::".1":".::-,-,,,-il:',:,. a,ons,he ridse of ,he wrink,e in order to achieve a flat overlap. The cut "fishmouths" or wrinkles shall be seamed and I any portion where the overlap is inadequate shall then be patched with an oval or round t Ei:i,::j* same seomembrane extendins a minimum of 6 inches beyond the cut in all t Seaming shall extend up the panels and well into the anchor trench. All cross seams are to be extrusion welded where they intersect. The top flap of I membrane is removed in the area to be extrusion welded and the wetd area is groundf parallel to the seam prior to welding. I For fusion welding on wet or muddy subgrade, a movable protective layer of plastic may t be required to be placed directly below the overlapped membranes being seamed. This | ::::3l"TH,TJ'T,.T;1:liil5'JJ;ff:lllff;$':: to be werded and/or to provide 3,3,7 Nondestructive Seam Continuity Testing I 3s.7.L concept I CLI shall nondestructively test all field seams over their full length using at :ffi:Il""i;:;il: il:31"i;:':,.::T'll,? ffi:ffi',d'"?':J;flrlT#;,1i"1H"",': I information on seam strength. Continuity testing shall be carried out as the I I I I I I I I I I I I I I I I I I seaming work progresses, not at the completion of all field seaming. 3.3,7.2 Vacuum Testing The equipment shall be comprised of the following: A vacuum box assembly consisting of a rigid housing , a transparent viewing window, a soft neoprene gasket attached to the bottom, porthole or valve assembly, and a gauge to indicate chamber vacuum; A steelvacuum tank and pump assembly equipped with a pressure controller and pipe connections; A rubber pressure/vacuum hose with fittings and connections; A bucket and wide brush, mop or spray assembly; A soapy solution. The following procedures shall be followed: Energize the vacuum pump and reduce the tank pressure to approximately 5 psi (10 inches of Hg.); Wet a strip of geomembrane approximately 12 inches by 48 inches (0.3 m by 1.2 m) with the soapy solution; Place the box over the wetted area; Close the bleed valve and open the vacuum valve; Ensure that a leak tight seal is created; For a period of approximately 5 to 10 seconds, examine the geomembrane through the viewing window for the presence of soap bubbles; If no bubble appears after 10 to 15 seconds, close the vacuum valve and open the bleed valve, move the box over the next adjoining area with a minimum 3 inches (75 mm) overlap, and repeat the process; All areas where soap bubbles appear shall be marked and repaired in accordance with Section 3.4; Vacuum tested seams are recorded on Daily Progress ReporB. l0 I t I 3.3.7.3 Pressure Test Specifications for Dual Track Hot Wedge Welds: Test Pressure (after 5 min) PSi Maximum Pressure Sheet Thickness Min. Max. Drop AllowedI t t I I I t I 30 mil 40 mil 60 mil B0 mil 24 30 3 PSI24 30 3 PSr27 30 3 PSr27 30 3 PSI T I T I 100 mil & thicker 30 32 3 pSI 3.3.7.4 Air Pressure Testing (for Double Fusion Seam only) The equipment shall be comprised of the following: An air pump (manual or motor driven) equipped with pressure gauge capable of generating and sustaining a pressure between 25 and 30 psi (160 and 200 kPa); A rubber hose with fittings and connections; and A sharp hollow needle, or other approved pressure feed device. The following procedures shall be followed: Seal both ends of the seam to be tested; Inseft needle or other approved pressure feed device into the tunnel created by the fusion weld; Energize the air pump to a pressure between 25 and 30 psi (160 and 200 kPa), close valve, and sustain pressure for approximately five (5) minutes; If loss of pressure exceeds above listed valves, or does not stabilize, locate faulty area and repair in accordance with Section 3.4; Remove needle or other approved pressure feed device and seal; and Pressure tested seams are recorded on Daily Progress Reports. 3.3.8 DestructiveTesting 3.3.8.1 ConceptI ff'J::r';;;:rT,::1'i,:il.'^:ffir"Jtri#:::?:rilfi[rff"fTffiE.nin* t ::iJffif|,?'ffi"#,::::X'"T;,iiXTiffi:?liJ:'J$fl,#i::J;ne as the T II T I I t I I I I I I t I I T I I 3.3.8.2 Location and Frequency The owner and/or owner's representative shall select locations where seam samples will be cut. These locations shall be established as follows: A frequency shall be agreed upon by CLI and the Project Manager at the Resolution and/or Pre-Construction Meeting. Unless otherwise specified, destructive samples should be pulled at intervals of 1 sample for every 500 linear feet of weld. The seaming technician shall not be informed in advance of the locations where the seam samples will be taken. 3.3.8.3 Sampling Procedure Samples shall be cut by CLI as the seaming progresses in order to have test results before the geomembrane is covered by another material. Cll shall: Cut samples; Assign a number to each sample, which is to be based upon seam and sample number and mark it accordingly; Record sample location on daily report; and All holes in the geomembrane resulting from destructive seam sampling shall be immediately repaired in accordance with repair procedures described in Section 3.4 The continuity of the new seams in the repaired area shall be tested according to Section 3.3.7. 3.3.8.4 Size of Samples At a given sampling location, two types of samples shall be taken by the Installer. First, two sample coupons for field testing should be taken. Each of these sample coupons shall be 1 inch (0.25 mm) wide by 12 inches (0.3 m) long with the seam centered perpendicular to the length. The distance between these two samples shall be 42 inches If both sample coupons pass the field test described in Section 3.3.8.5, a sample shall be cut between the two coupons. This sample shall be cut into three parts and distributed as follows: One portion for the Installer (CU) for testing, 18 inches X 12 inches; One portion for Geosynthetic Quality Assurance Laboratory testing if applicable, 12 inches X 12 inches(O.3 m X 0.3 m); and One portion to the Owner for archive storage, 12 inches X 12 inches (0.3 m X 0.3 m). Final determination of the sample sizes shall be made at the Pre-Construction I I t2 t t I t I I I I I Meeting. 3.3.8.5 Field Testing The two 1 inches (25 mm) wide strips, mentioned in Section 3.3.8.4, shall be tested in the field for peel and shear and shall not fail in the seam. If any field test sample fails to pass, then the procedures outlined in 3.3.8.7 shall be followed. Electric or hand tensiometer testing in the field is to be carried out. The following procedure is followed: If the initial sample coupon test passes a film tearing bond, the sample qualifies for further teting to'obtain quantitive results. If it fails, the seam should be repaired in accordance with Section 3.4. Destructive Testino of Seams: Destructive testing of seams is very important because it provides the only direct evaluation of seam strength and bonding efficiency which indicates seam durability. Destructive testing involves two techniques: 1) shear testing, and 2) peel testing. Shear testing applies a tensile stress from the top sheet through the weld and into the bottom sheet. Peel testing, on the other hand, peels the top sheet back against the overlapped edge of the bottom sheet in order to obserue how separation ccurs. The peel test indicates whether or not the sheets are continuously and homogeneously connected through the seam. Soecification for Seam Strenqth (Based on NSF 54 Standards) Type of Material No. of Couoons Minimum Values Reouired (Pounds per inch of Width) Peel Peel Shear Shear Standard testing procedure is as follows: If there is a failure in either peel or shear, then five totail coupons are tested. If more than one coupon fails, then the sample fails. This is a modified ASTM IJ 30 mil HDPE 2 t 35 49 63 63 40 mil HDPE 2 7 48 67 85 86 50 mil HDPE 2 L 70 98 126 726 B0 mil HDPE 2 I 92 115 166 166 100 mil HDPE 2 7 115 143 207 2O7 30 mil HDT 2 1 31 44 56 56 40 mil HDT 2 I 42 60 76 76 60 mil HDT 2 7 63 BB 113 113 B0 mil HDT 2 t 84 115 151 151 100 mil HDT 2 7 105 t43 189 189 I I I t I I t I t I I I I I t T I I I Appendix E Quality Assurance Manual for Installation of Flexible Membrane Lining Systems QUALITY ASSURANCE MANUAL FOR THE INSTALLATION OF FLEXIBLE MEMBRANE LINING SYSTEMS I I I t I t I t I I I I I I I I I I I #,6sF_&8"ffiffii ru,%ffi 6(ffi,m 1062 Singing Hills Road Parker, Colorado 80138 (303) 841-2022 (800) 524-8672 (303) 841-5780 FAx Colorado Lining International I I I I t t t I I I I I I I t T I I I T I I I ; I il I I T I I I I I I I t TABLE OF CONTENTS INTRODUCTION .....................1 1.1 Terms of Reference ............... .......1 1.1.1 Purpose............. ............1 1.1.2 Quality Assurance and Quality Control ................1 1.1.3 Lining Materials .............1 1.1.4 Scope of Quality Assurance and Quality Control ....................1 1.1.5 Units .,.........2 1.1.6 References .......... ....,,...2 GEOMEMBRANE MANUFACTURING AND DELIVERY......... .........2 2.1 Manufacturing ..........2 2.1.1 Geomembrane Raw Material ................ ............,,2 2.1.2 Geomembrane Manufacturing .............. ..............3 2.1.3 Rolls ...........3 2.2 Delivery ......,...............3 2.2.1 Transportation and Handling .............. ................3 2.2.2 Storage............... ...........4 INSTALLATION ........... ............4 3.1 Anchor Trench Systems ................4 . 3.2 Geosynthetic Placement ................4 3.2.1 Field Panelldentification ..................5 3.2.2Field Panel Placement............ ...........5 3.2.2.L Location .........53.2.Z.2lnstallation .......................5 3.2.2.3 Weather Conditions ............5 3.2.2.4 Method of Placement ............... ...........5 3.2.2.5 Damage ..........6 3.3 Field Seaming .............6 3.3.1 Seam Layout .................6 3.3.1.1 Field Joints .......................53.3.l.2PipePenetrations. ..................6 3.3.2 Seaming Equipment and Products ...........,..........7 3.3.3 Seam Preparation .,......,..7 3.3.4 Weather Conditions for Seaming .............. ...........7 Cold Weather Seaming of Polyethylene Liners ...............8 3.3.5 Trial Seams ...................9 Failed Test Seams ...................9 3.3.5 General Seaming Procedure ..............9 3.3.7 Non-destructive Seam Continuity Testing ............93.3.7.1Concept ...........9 3.3.7.2 Vacuum Testing ...............10 3.3.7.3 Pressure Test Specifications for Dual Hot Wedge Welds ..........11 3.3.7.4 Air Pressure Testing (for Double Fusion Seam only) ....,..........11 3.3.8 Destructive Testing ......11 3.3.8.1 Concept .........11 3.3.8.2 Location and Frequency............. ......12 3.3.8.3 Sampling Procedure .........t2 3.3.8.4 Size of Samples ...............12 3.3.8.5 Field Testing ...................13 Destructive Testing of Seams .........13 3.3.8.6 Procedures for Destructive Test Failure ...............14 T t I I I I I I I I I I I I I I I I I I 3.4 method. The ASTM methods that are used are D4437, D413 and D53B which allcan apply. Reason for oass/fail criteria: The FTB requirement is very important. With a fully integrated, continuous connection through the seam, no weld bead/sheet or sheeVsheet inteface exists. Such an intefface might be separated by absorbed chemicals, causing failure of the seam. In addition to the FTB criterion, a minimum stress level is specified. This is important in order to protect against legitimate tearing of a thin portion of polymer in the weld (as might occur if the weld is off center) The minimum stress levels are necessarily lower than tensile yield strengths of the parent sheet because of the different configuration of the test specimens during destructive testing. Bending moments come into play along with straight tensile stresses, especially as the sheets are bent back in peel. These bending moments depend on the shape of the welds, which vary even within the same welding technique. The minimum stress values are based on the average performance values of passed weld specimens tested in the laboratory. 3.3.8.6 Procedures for Destructive Test Faiture The following procedures shall apply whenever a sample fails a destructive test. CLI has two options:1) Reconstruct the seam between any two passed test locations; or2) Trace the welding path to an intermediate location (10 feet maximum from the point of the failed test in each direction) and take a small sample coupon for an additional field test at each location. If these additional samples pass the field test, then full samples are taken. If these samples pass the tests, then the seam is reconstructed between these locations. If either sample fails, then the process is repeated to establish the zone in which the seam should be reconstructed. All acceptable seams must be bounded by two locations from which samples passing destructive tests have been taken. CLI shall document all actions taken in conjunction with destructive test failuresi e.g,, capping of failed seam area. Defects and Reoairs 3.4.t Identification All seams and non-seam areas of the geomembrane shall be examined by CLI for identification of defects, holes, blisters, undispersed raw materials and any sign of contamination by foreign matter. 3.4.1.1 Defective/damaged materials shall be identified via a deficiency report, either separately or on the Daily Report. Actions taken to resolve or correct the problem will also be recorded on the l4 ! I I I I I I I I I I I I I I similar form, 3.4.1.2 Defects, holes, blisters, undispersed raw materials, signs of contamination by foreign matter, unacceptable welds in geomembranes and other unsatisfactory conditions will be identified on the Daily Report form. The repair/corrective action to ofix" the problem will also be recorded on a similar form. 3,4.2 Evaluation Each suspect location, both in seam and non-seam areas, shall be non-destructively tested using the methods described in Section 3.3.7 as appropriate. Each location which fails the non-destructive testing.shallbe marked by CLI and repaired. Wo* shallnot proceed with any materials which will cover locations which have been repaired until laboratory test results with passing values are avaihble. 3.4.3 RepairProcedures 3.4.3.1 Geomembrane Repair procedures Any pottion of the geomembrane failing a destructive or nondestructive test shall be repaired. Several procedures exist for the repair of these areas. The final decision as to the appropriate repair procedure shall be agreed upon between the Project Manager and CU. The procedures available include: Patching - used to repair large holes, tears, and contamination by foreign matter; Buffing and re-welding - used to repair small sections of extruded seams; Spot welding or seaming - used to repair pinholes or other minor localized flaws; Capping - used to repair large lengths of failed seams; Topping - used to repair areas of inadequate seams which have an exposed edge; In addition, the following provisions shall be satisfied: Surfaces of the geomembrane which are to be repaired shall be abraded no more than one hour prior to the repair; All surfaces must be clean and dry at the time of repair; All seaming equipment used in repairing procedures must be approved; The repair procedures, materials, and techniques shall be approved in advance of the specific repair by the Project Manager and CLI. Patches or caps shall extend at least 6 inches beyond the edge of the defect, and all corners of patches shall be rounded with a radius of at least 3 inches. 3.4.3.2 Geomembrane Verification of Repairs Each repair shall be non-destructively tested using the methods described in t5 I t I I I T t I I i:T"?r,';1'J:^tr:J;BxTi;,iirirfi#J,.8:n:',r,?,r"*,iir[J,g[,f:r;ff', I repair shall be redone and retested until a passing test result is obtained. f 3.5 Backfitlino of Anchor Trench The anchor trench, if any, shall be adequately drained by Owner/Earthwork Contractor. to prevent ponding or-otherwise softening the adjacent soils while the trench is open. The anchor trench shall be backfilled by the Eafthwork Contractor or as outlined in the specifications and bid documents. since backfilling the anchor trench can affect material bridging at toe of slope, consideration should be given to backfill the liner at its most contracted state; preferably during the cool of the morning or extended period of overcast skies. Care shall be taken when backfilling the trenches to prevent any damage to the geosynthetics. I 3.6 Linino Svstem Acceotance The geosynthetic lining system shall be accepted when: I The installation of all materials are deployed and welded; I X"TlEf::. of the adequacv of all seams and repairs includins associated testins is 3.7 Soils in Contact wlth the Geomembrane t in contact with the geomembranes include: A geotextile or other cushion approved by the designer may be installed between angular aggregate and the geomembrane. Equipment used for placing soil shall not be driven directly on the geomembrane. A minimum thickness of 1 foot (0.3 m) of soil is recommended between a light dozer (such as a cAT D-3 or wide track caterpillar D-6 or lighter) and the geomembrane. In heavily trafficked areas such as access ramps, soil thickness should be at least 2 to 3 feet (0.6 - 0.9 m). Soil/Earth Cover on Too of Geomembrane: Placement of soils, sand or other types of earth cover on top of the liner shall not be performed until all destructive and non-destructive testing has been performed and accepted. Placement should be peformed to minimize wrinkles. Equipment operators should be briefed on method of placement and affects to thermal expansion and contraction of the liner. Material placed on top of the liner should be back-dumped on liner and, in order to avoid the formation of wrinkles, efforts should be made to load the soil so that it I I t t I I I I I l6 I I ;ffi;1ir;xJT,,"i#:,1[iJ#i::'J,::"':jl,.ru:miil,:]rE;ffi::,Ji'il: t 3)ilffi:ifi,;l:Ilxlf,XiffiJt*l'H,'rgg,:oir, then pushins soir up and If a wrinkle forms, every effort should be made to walk the wrinkre out. 'l Minor folding over of wrinkles is acceptable providing an even transition occurs at I ilr:,.Hl:['::tT:'I: "fl]ff:x;;T"il,tff#,:.creared ar the tair of the wrinkre, the I TyprcAL RESrN PROPERTTES OF VTRGTN RESrN Property Test Method UNIT HDpE Value I Density ASTM D1s05 s/cc 0.93s-0.941 Condition A l Melt Index l,#.?}1T*, 9/10 min. 0.05 - 0.30 trffi TYPICAL RESIN PROPERTIES OF COMPOUNDED RESIN Test Method UNIT HDpE Value ASTM D1505 g/cc 0.940 min. Condition A ASTM D1238 9/10 min. 0.05 - 0.30 (190oC/2.16 kg) I Carbon Black Content ASTM D1503 o/o 2.0 - 3.0 t Environmentalstress Crack ASTM D1693 Hrs. 1500 Melt Index I t t I I DETAILS OF HOT WEDGE WELDING SYSTEM I. FML Preparation A. Note that this document assumes that the proper FML has been brought to its exact plan position for final installation and seaming. B. The two FMLs to be joined must be properly positioned such that approximately three inches of overlap exists. C. if the overlap is insufficient, lift the FML up to allow air beneath it and "float" it into proper position. Avoid dragging FML sheets, particularly when they are on rough soil subgrades since scratches in the material can create various stress t1 F. G. A. T I I I I I I I I I I t T I I I I I points of different depths and orientations. There can be no excessive undulations (waves) along the seams during the seaming operation due to problems in slack adjustment. when this occurs, with the upper sheet having more slack than the lower one, it often leads to the undesirable formation of "fishmouths" which must be trimmed, laid flat, and reseamed via a patch. There generally will be excessive slack in the FMLs depending on the ambient temperature, length of time the FML will be exposed, etc. The sheets which are overlapped for seaming must be clean. The sheets which are overlapped for seaming must be completely free of moisture in the area of the seam. Air blowers are usually preferred over rags because sufficient dry rags are usually not available to keep the FML dry enough to be suitable for seaming. No seaming is allowed during rain or snow, unless the seam is covered with an enclosure. The soil surface beneath the FMLs cannot be saturated because the heat of seaming will draw the water into the region to be joined, ponded water on the soil's surface beneath the FML is never allowed. The soil beneath the FMLs cannot be frozen, for the heat of seaming will thaw the frost allowing water to be drawn into the region to be joined. The seaming, however, can be accomplished with rub sheets of FML directly under seam edges. Ambient temperatures for seaming should be above freezing (i.e., thirty-two degrees' Fahrenheit). However, seam welding temperatures below thirty-two degrees Fahrenheit can be accomplished as stated in item L. For cold weather seaming, it may be advisable to preheat the sheets with a hot air blower, to use a shield of some soft to prevent heat losses during seaming, and to make numerous test welds in order to determine appropriate seaming conditions (e.9., equipment temperatures should be set higher and seaming rates slowed down during cold weather seaming). II.Eouioment Preoaration A working and properly functioning small electric aenerator must be available within close proximity of the seaming region and with adequate extension cords to complete the entire seam. The generator must be rubber tired, or placed on a smooth plate such that it is completely stable so that no damage can occur to the FML. Fuel (gasoline or diesel) for the generator must be stored off the FML. A hot wedge seaming device is a completely self-contained system known as a "hot shoe". As the hot wedge method is one of melting the opposing sufaces of the two I r8 I I I I I T I T I I I I I I I t I III. FMLs to be joined, no grinding of sheets is necessary or allowed. D. Tacking of the FML sheets as done in extrudate fillet seaming is not needed. E. The hot wedge itself, or "anvil", should be inspected to see that it is uniform and reasonably tapered. Various types are currently available. Some are smooth' ' suffaced while others have patterned ridges in the direction of the seam. The, taper dimensions vary according to different types of machines. The major point for inspection is that no sharp edges should exist where FML sheet surfaces must pass. F. Knurled rollers for applying pressure on the sheets and driving the device follow the wedge. They should be inspected for sharp surfaces. G. If a dual, or split, hot wedge seam is being made, the recessed space for the air track should be examined. H. As the FML sheet materials pass through the machine, they must come in contact with the wedge in order to heat the material properly. Hot wedge welding machines are equipped with pressure shoes which assure contact between the FML sheet and the wedge as the material passes through the machine. Once the welding machine has been set up for a pafticular FML thickness, fufther field adjustments are not required. The wedge has an adjustment that is actually a stopping device to keep the "hot shoe", or anvil from being pulled into the nip/drive rollers, especially when material is not going through the machine. The drive, or wedge units, must be disengaged before the material runs completely out of the machine. Serious damage will occur to the FML sheets if the wedge gets pulled through the nip/drive rollers. I. The front part of the seaming device should be inspected for sharp corners and irregular details which may damage the FMLs. J. Temperature controllers on the wedge device should be checked periodically. ActualSeamino Process A. The hot wedge system is properly positioned for the making of a dual (split seam). B. The principle of the hot wedge is that both surfaces to be fused come into intimate contact with the hot wedge, or anvil. The wedge lifu up both layers of FML off the subgrade and fusion is brought about by compressing the two melted surfaces together, causing an intermingling of the polymers at a pressure of approximately one hundred pounds per square inch. The hot anvil itself reduces the surface tension of the viscous polymer sheets and acts as a scraper/mixer, followed closely by the nip roller which squeezes the two FMLs together. C. Temperature setting will very according to the FML thickness being installed. In general, the sheet surface temperature as it passes through the nip/drive rollers is about thirty degrees Fahrenheit (fifteen degrees Celsius) lower than the wedge itself. t9 I I I t t I t I I I I I t I II I I ry. D. Ambient factors such as clouds, moisture, and hot sun will require the temperature setting of the wedge to vary. A test strip of at least five feet in length should be run before welding begins, which will enable the operator to find the proper settings for the particular conditions that day. See Article 3.3.5. Depending upon the records to be kept, one might record a number of different temperatures; for example, the temperature of the hot anvil, the temperature of the sheet after seaming, the temperature of the sheet away from the seaming area and the ambient temperature E. Power for the drive motor should be off when positioning the machine to make a seam. Manually place the machine into the overlapped sheet of material. The sheets should be guided between the idlers and the wedge; and into the drive/nip rollers. This procedure is only'possible when starting with two new sheets. When starting a weld in the middle of two sheets, the material must be loaded from the sides. The machine is to be picked up a few inches, loading the bottom sheet first and then the top sheet. As soon as the nip rollers are engaged and the wedge is in position, the power to the drive motor should be turned on. Once the sheets are between the nip rollers, they shall be engaged immediately; otherwise, a melt-through will occur within a few seconds. The hot wedge should be moved into position and locked. F. It is necessary that the operator keep constant visual contact with the temperature controls, as well as the completed seam coming out of the machine. occasional adjustmenb of temperature will be necessary to maintain a consistent weld. Visual inspection and constant hand testing by the peel method or another method as cited in Article 3.3:8.2 are also recommended. G. On some soils, the wedge tends to "bulldoze" into the ground as it travels. This causes soil to enter the weld making the seam weak and unacceptable. To overcome this, it is recommended that the operator take some of the weight off the front of the machine by lifting it slightly. Alternatively, some type of base for the machine to travel on could be provided. Strips of geotextile or geomembrane have proven effective to prevent this bulldozing effect. After Seamino A. A smooth insulating plate or heat insulating fabric is to be placed beneath the hot welding apparatus after usage. B. A slight amount of "squeeze-out" or')flashing" is a good indicator that the proper temperatures were achieved. It signifies a proper seam in that some of the melted polymer was laterally extruded out of the seam zone. The pressure should be decreased untilonly a minimal amount of hot melt is squeezing out. c. For FMLs of 40 mil thickness and less, a long, low wave-length pattern in one direction of the seam on its top sufface is indicative of a proper weld. If the wave peaks become too close together, the machine speed should be increased until a satisfactory pattern is present. The absence of this wavelength pattern indicates that the rnachine speed should be decreased. FMLs of 40 mil in thickness and less require considerable visual inspection. There will be no wavy pattern for FMLs greater than 40 mil in thickness due to the inherent stiffness of the thicker material. 20 I I I I I t I I D. Nip/drive roller marks will always show on the suface. Their depth, however, should be visually obseruable, but just barely evident to the touch.E. The hot wedge device has only a few adjustments that can be made, but it is very impoftant that they be checked daily. Cleaning of machine should be done at least daily. General: CLI's unique automatic seaming machine creates two distinct seams. These two seams are separated by a void or air space. This seam design is intentional for two primary reasons. First, it allows a very positive test for leak integrity, and second, the double weld seam offers both a primary and a secondary seal for the seam. Test Procedure: 1. Seal one end of the seam by applying heat to the end of the seam, via hand leister, until "flow temperature" is achieved. At all times before heat sealing the end of the seam, the operator should insure that the void or air channel is free of obstruction. This obtained by allowing air pressure to travel freely to the opposite end of the pressure gauge/needle assembly. 2. Clamp off end using hand vise gripper. 3. A pressure gauge/needle assembly is inserted into void or air chamber. 4. Air pressure is then applied into the air chamber with the use of an air pump per the following schedule: I I I I T T I I I I I Material 30 mil 40 mil 60 mil B0 mil 100 mil Initial Pressure Schedule Field Testing Minimum PSI Maximum pSI 24 3024 3027 3027 3030 32 Above 100 mil - Colorado Lining supplies a thicker mil HDPE membrane on special order. Seaming and field testing procedures are available upon request by the client. 5. After initial staft of air pressure, the air should be allowed to reach ambient liner temperature. 6. Pressure test FML seam according to the initial pressure test schedule. Hold test for five minutes. If no pressure drop is greater than the maximum allowable pressure drop, the seam is judged leak free. 2l I I t I t I I I I I I I I I Material 30 mil 40 mil 60 mil 80 mil 100 mil Maximum Allowable Pressure Drop Field Test (after five minutes) 3 PSI 3 PSi 3 PSI 3 PSI 3 PSI FIELD SEAM FAILURE Should failure occur through excessive leak down over the scheduled time period, check both ends of seam to insure proper seal and retest. Should failure reoccur, check the top fusion seam by applying a constant flow of air pressure to void or air channel. Mix a strong solution of liquid detergent and water and apply an ample amount to the top fusion weld. Any failure or leak will be indicated by continuous bubbles appearing. If no failure appears in the top fusion seam area, check systematically by isolating random sections of the seam. This should be accomplished in one hundred and fifty linear foot sections of seam. Then retest each section by pressure testing until the leak is located. Repair failed seam area by extrusion welding the outside edge of the top fusion weld between areas of failure. Then vacuum test repair seam area. All repairs in accordance with Quality Assurance/Quality Control Manual. PEEL TEST FOR HOT WEDGE SEAM WELD This test is the most severe test that a seam can be subjected to. The peel test is the greatest proof that a seam will have the strength to last the life of the flexible membrane liner (FML). The mechanical procedures of the peel test are as follows: Procedure: 1. Seam sample cut approximately one inch wide by approximately six inches long. 2. . Only the inner weld track is peeted apart in this destructive test. The outer track (directly at sheet edge) is for the purpose of air pressure testing capabilities. 3. Clamp bottom tabs into the testing machine (Field Tensiometer or l-ab Instron), turn on machine and pullthe seam. 4. All testing of destructive samples of fusion seam will be in accordance with ASTM D413 and ASTM D638.I I I I 22 t T I I DETAILS OF EXTRUSION WELDING SYSTEM I r. rntroduction The Hot Wedge Welding System is the primary seaming system for FML installation, and the Extrusion Welding System is utilized for repairs and detailwork. The Extrusion Welding System produces a seam quality equal to the hot wedge weld and has the advantage that all welds are applied on top of the FML which allows its use at "T" intersections and in irregular seam areas such as pipe boots. rI. 'EEt-EElatlsE I FML preparation is the same as described for the hot wedge weld. r III. Eouioment PreoarationIA. A working and properly functioning small electric generator must be available within close proximity of the seaming region and with adequate extension cords to complete the entire seam. The generator must be rubber tired, or placed on a smooth plate such that it is completely stable so that no damage can occur to the FML. Fuel (gasoline or diesel) for the generator must be stored off the FML. B. The extrusion welder is a completely self-contained system which requires no adjustments after it has been initially set up for a particular FML thickness. C. An initial inspection of the extrusion welder should be made before the first heat up to confirm that the electrical cords, insulation and covers are in good condition and that the welding nozzle is correct for the FML to be seamed. D. The welding machine should be connected to a proper power supply and heated to the correct welding temperature for the FML to be seamed. E. After the unit has reached correct operating temperature, clean, dry welding rod should be insefted and the unit operated for several minutes to confirm that temperature controllers are operating properly and that the welding rod feed system and rotating tips are operating properly. F. The flow of extrudate from the test run will force the rotating tips to the outermost position and these can now be checked for propei setting with deith calipers. G. The teflon shoes should be checked for excessive wear and replaced if necessary. The teflon shoes must be trimmed for proper control of the weld bead configuration. ry. ActualSeaminqProcess A. FML materialto be extrusion welded must have surface oxidation removed by lightly grinding the weld surface with a 60 or B0 girt disc. The grinding is performed parallel to the seam and controlled such that grinding marks do not extend more than 0.25 inches outside the area of the weld bead. Grinding should precede the actual welding as closely as possible but in no case should 'l 'l I I t t I I I I I t li t I I I I t I I T I T grinding precede welding by more than one hour. Sixty mil or thicker liners should have the edge of the top sheet beveled by grinding to approximately a 45.?angle. B' The FML to be extrusion welded must be temporarily bonded to hold the material in place until the extrusion weld bead cools and attains full strength. This is normally accomplished by performing an automatic or hand hot air tack weld. C' The extrusion welder should be purged of all degraded plastics prior to the start of seaming. D. The welding operation should be observed to assure that the weld bead is centered over the edge of the top FML sheet and that weld bead appearance is smooth and uniform. E. Allextrusion welds should be non-destructively tested by vacuum testing as described in the QC Manual. Areas which cannot be non-destructively tested should be visually inspected. F. . Destructive tests can be conducted when seam lengths are adequate. DEFECT (LEArO TESTTNG OF SYNTHETTC LTNERS Fol.ward: Environmentalists and activists have long used the phrase "ALL LINERS LEAK" as their battle cry and until now, the claim had some validity. The most carefully manufactured synthetic liners can be accidentally damaged. Desiccation, consolidation, and chemical attack will increase the permeability of clay or soil liners. Available insitu defect or leak testing systems are costly and have limitations. A brief overview of the various systems available and their limjtations follows: Smoke & Detectable Gas Smoke and detectable gas systems are similar in that a specific area is isolated by sandbagging or weighting the perimeter and the detection media (smoke or gas) is injected under the liner it a slight positive pressure. The area is then surveyed, either visually or with instrumentation, to find defects where the media is venting through the liner. These systems are costly, time consuming, and heavily dependent on the skill and diligence of the suruey personnel. The minimum hole size the detection media will pass through and whether the detection media has been able to reach the entire undersurface of the liner, particularly when the liner is in intimate contact with a subgrade such as compacted clay, are criticalfor a quality inspection. Electric Leak Survev Electric leak surveys have been the standard leak detection tool for some time. This test requires an electrically conductive layer below and above the liner. The lower conductive layer is typically the soil and the upper conductive layer is water. A cathode ground is established and an anode is placed in the water. As the water leaks through a defect, a current is established. A hand- held probe is then traversed through the water and the current traced to the defect. The typical procedure is to flood the test area to a depth of approximately 6', probe, then locate and mark the defects, drain the area and pefform repairs. t I I I I I I 24 I I I I I I I I I t t t I t t t I I I Depending on bottom configuration, water depth can be substantial in some areas requiring a search by boat rather than wading. The fill and drain process is both time consuming and expensive, pafticularly if adequate water supplies are not available in the construction area. The suruey itself is expensive and relative slow and requires skilled operators to find the smaller defects. Although the system can theoretically detect holes as small as 0.25 mm, the practical limit seems to be about 1"mm or larger. Small holes in the same vicinity as large holes can be masked by the larger hole. A second survey is often conducted to insure that all defects have been located and repaired. Should a wrinkle lift the liner off the subgrade, the electrical contact can be lost unless large quantities of fluid leak in and re-establish the circuit. Also, due to the low voltage (12 to 110 volts), fluid must penetrate the defect and establish electrical conductivity between the upper and lower conductive mediums. Leak detection systems in use today have been quite useful. However, the cost and time required to conduct the tests have limited their use to a few of the most critical liner projects. The CLI system, which is described below, overcomes these disadvantages and adds additional features which are simply not practicalwith existing systems. A LEAK DETECTION SYSTEM USING SPARK TESTABLE GEOMEMBRANE "Holiday" or "spark" testers were originally developed to detect defects on "Holidays" in pipe coatings. For a number of years, they have been used to detect pinholes in extrusion weld beads on liner seams. The procedure is simply a matter of imbedding a thin copper wire in an extrusion weld and applying a high potential (12,000 to 20,000 volts) between the wire and a brass brush. As the brush is passed over the weld, any pinholes cause a spark which can be seen visually, and an alarm is sounded. CLI now makes it possible to use this simple technology to test every square inch of an installed liner in a dry state. The co-extrusion technology which made possible textured liner and multi- colored layered liner is used to add a thin (approximately 5 mil) electrically conductive layer: to the standard liners, using electrically conductive carbon black. The liner is installed with the electrically conductive layer on the bottom and standard non-conducLive layers on the top. The spark test equipment may be connected directly to the conductive layer by the use of clamps or may reach the conductive layer through an earth ground. A wide (2-6') brass brush is passed over the liner surface and, as in a seam test, any pinhole will cause a spark which triggers an alarm. The test equipment includes a marking system to define the edge of each pass of the brush so that each pass of the brush should overlap the previous pass. The equipment provides output signals for an audible alarm. This signal is used to mark the location of the defect for repair, and provide a strip chart record of the test. The system is simple, yet it provides a multitude of advantages. Current flow is minuscule; therefore, the system is safe for personnel and no heat is generated when a spark occurs. The extremely high voltage eliminates the need for a conductive fluid to penetrate the defect and provide a current path. Even the most minute defects can be located. Most welds are automatically spark tested when the liner is tested. (This comes as a 1. 2-5 I I I I I T I t I I I I t I t I I I I bonus to the normal non-destructive and destructive weld testing. 4. Since the conductive layer is an integral part of the liner, there are no areas where the electrical potential does not exist. 5. Primary liners can be tested as easily as secondary or ground contact liners. 6. complex configurations such as pipe boots can be completely tested. . 7. Water puddles or dirt on the liner do not affect the test. In the case of a water puddle, the entire puddle will become charged and will spark. To locate the leak the water is removed and the area re-tested. B, No water pumping is required. 9. Repairs can be re-tested quickly and easily. 10. The test is fast. one walking operator can best 7/2 acre per hour and for large areas, a vehicular mounted test device could easily cover 1-1/2 to 2 acres per hour, 11. Operator skill requirements are minimal. L2. Chemical resistance is completely retained as are all other properties. In the case of exposed liners in ponds and similar applications, the linei can be re-tested at any time in the future. 13. One common cause of defects in double lined systems is damage to the secondary liner caused when destructive samples are cut from the primary liner. Now this area can be tested to assure that no inadvertent cuts have been made in the secondary liner, and the primary liner patch can be tested as well. The CLI system provides a fast, cost effective method of 100o/o inspection for synthetic liners, especially when combined with a co-extruded, white upper layer for improved visual inspection and reflection of radiant heat. A new state-of-the-art plateau has been reached in synthetic liners. Since the co-extruded layers do not affect basic sheet properties and provide enhanced value, re-permitting or variances are unlikely to be required for previously permitted pCIects. 1. Q: A: CONDUCTIVE LINER TYPICAL QUESTTONS Is the system safe? Yes. Although the test voltage is very high (12,000 to 35,000 volts), virtually no current (amps) is involved. This is similar to spark plugs on an automobile, and while one can receive an uncomfortable shock, there is no physical danger. Shock can be eliminated by the use of rubber boots and gloves. Does the spark damage the liner? No. Since virtually no current flows, no heat is generated. Does the conductive coating change sheet properties or weld strengths? 2. Q: A: 3. Q: 26 I I I A: No. Lab testing shows no change in liner propefties or weld strengths. Does dirt or water on the liner invalidate the test? No. However, if a hole is located in a water puddle, the entire puddle will become charged and will spark. It will be necessary to remove the water and retest to pinpoint the hole. Can the.test be conducted under water or over fill materials such as dirt, sand or concrete? No. As explained in (4) above, the entire water body will become charged and indicate that a hole exists but not locate it. The same may happen with wet fills of clay or sand. Dry sand or concrete would be unlikely to react. Can an exposed liner such as a pond be retested at future dates? Yes. when filled, a simple resistance test will indicate a hole, and the pond can then be drained and retested to locate the hole. The conductive layer is a permanent paft of the liner. could existing liners or new liners without the conductive layer be tested? If a liner without a conductive coating were in intimate contact with a conductive medium such as the earth, the test could be used. However, if a defect were present in a wrinkle or over geonet or any location where intimate contact did not exist, then no spark would occur and the test would be invalid. The key is intimate contact between the liner and the conductive media. If foils or water films are used as the conductive media, intimate contact could not be guaranteed, and the test would be invalid. How can electrical continuity between liner panels be assured? with the colorado Lining International system each panel is energized as it is tested. If necessary the panels can be connected by welding a ,)umper,, of conductive extrusion weld from panel to panel or by placing a scrap of conductive liner, with conductive side up, between panels. How long will it take to conduct this test? Test rates of 1 acre per hour or more seem reasonable. Is a high level of operator skill required? No. How can one be sure which is the conductive side of remnants and odd pieces? A simple resistance or continuity test will identiff the conductive side. Will induced ground currents in areas such as large power plants affect the test as they do with conventional electric leak surveys? No. Must defects exceed a minimum size, to be located by the test as is common with electric leak surveys? No. Common electric leak surveys depend on establishing current flow through a defect at low voltage. The very high voltages used in this system will penetrate the smallest defect. I 'l I I I I I I I I I I I T 4, Q: A: s. Q: A: 6. Q: A: 7. Q: A: B. Q: A: s. Q: A: 10. Q: A: 11. Q: A: 12. Q: A: 13. Q: A: 2'7 I I I I T I I t I 14. Q: Is this system designed to replace normal QC procedures such as non-destructive and destructive weld testing?A: No. This test is designed to serve as an additional procedure to further raise the confidence level in a liner system. 15. Q: What other benefits are available with the system?A: 1.) Areas such as pipe boots and complex configurations which are difficult, if not impossible, to test non{estructively, can be tested with this system.2.) When destructive samples are taken from a primary liner, it is not uncommon to find the secondary liner was damaged in the process. This system permits an immediate retest of the secondary liner. 3.) Patches and repairs can be immediately retested. 4.) The conductive layer can be used for Cathodic Protection under steel tanks. 16. Q: Competitive bidding is required on my project. If defect testing is specified, will this not eliminate competitive bids?A: No. The well-known electric leak survey is a valid test procedure and is available to all bidders as a defect test procedure. CU believes that our system is superior, but alternate methods are available. 17. Q: Will re-permitting or variances be required to use conductive liner on projects previously permitted? A: This will vary with the different permitting agencies and regulatory bodies. However, since the basic liner properties and specification do not change and the ability to test for defects prior to use represent enhanced value irt the liner, it is likely that regulators will look favorably on the use of this material, SPARK TESTING CONDUCTIVE LINER Spark (or Holiday) testing was originally developed to inspect coatings on steel pipe. In this application, a high electrical potential (voltage) of negative polarity (ground) is applied to the metal pipe. A wand or brush of opposite positive polarity is passed over the coating and any voids in the costing establish electric continuity and allow a spark to pass between the metal pipe and the wand. This same simple technology is used to test synthetic liners for defects. Synthetic liners made of plastic materials such as high density polyethylene are not normally electrically conductive just as in the coatings on metal pipes. In order to spark test a synthetic liner, an electrically conductive material must be in intimate contact with the liner. Intimate contact is critical for a valid test because air is also a good electrical insulator. Tvpically. 1,700 to 2,000 volts per millimeter are required to establish an electrical arc. Therefore, to bridge a 1-inch air gap, a 35,000 to 50,000 volt potential would be required. To bridge a 4-inch air gap, 140,000 to 200,000 volts would be required, which is clearly not a potential level to be handled by anyone who is not an electrical expert. The necessary conductive layer could be the earth itself; however, wrinkles, bridged areas or any condition separating the liner and the earth would invalidate the test. Metal foils could be glued I t I I I t I I I I 28 I I I I I t I I I I t t I I I I t I I to the liner; however, the cost would be prohibitive and fragile fails could easily be damaged during installation. Any stray ground currents in the soil as is common around high voltage transmission lines can cause galvanic corrosion in metal foils. CU has solved this problem by co-extruding a thin layer (approximately 5 mil) of liner material with a special electrically conductive carbon black on one side of the basic liner. The special carbon black makes this layer electrically conductive and at the same time retains the corrosion resistance and other desirable properties of the base liner. Since the conductive layer is co- extruded, it is an integral part of the base liner and cannot be torn or damaged suih that it failsto peform its basic duty. The high voltage potential (15,000 to 35,000 volts) source can be connected to the liner in one of three ways: 1. Direct connection to the conductive layer; 2. Through an Eath Ground: If any part of the conductive layer touches earth, the entire conductive layer is energized. Both methods above require an elecLrical lead from the power supply to the wand; therefore, in a large lined area, thousands of liner feet of cable would be required which would in itself be cumbersome. Foftunately, it is possible to take advantage of the electrical propefi of capacitance and eliminate the long electrical lines. A capacitor is an electrical'device in which two electrically conductive materials are separated by a dielectric (or non-conductive) material. A capacitor will store an electrical charge in each conductive material when attached to apower source. We can take advantage of the "Capacitance effect" by placing an electrically conductive rubber pad on top of the liner and inducing a potential in the conductive layer of the liner; and 3.) Through Electrical Capacitance Effect: The rubber pad can move with the test unit and energizes the conductive layer through the "Capacitance effect". Once the conductive liner layer has been energized by one of the methods above, the wand ispassed over the upper surface of the liner. Any defect or pinhole which penetrates the liner to the conductive layer will allow a spark to pass through the liner to the wand. This spark is clearly visible and triggers an zudible alarm and can trigger a strip chart for a record of the number of defecE located in a test. 29 T t I I I I I I I I ASTM Angle of Friction Bonded Seam Strength Breaking Strength Carbon Black Crystallization, Polymer Density Dimensional Change Direct Shear Test Dispersion Elongation at Break Elongation. Percent Elongation al Yield Environnrental Stress Crack Extrusion Welded Seams GEOSYNTHETICS TERMINOLOGY American Society for Testing & Materials. (215) 299-5400 Angle of friction between solid bodies. (Degree) Angle whose tangent is the ratio between the maximum value of,shear stress that resists slippage between two solid bodies at respect to each other, and the normal stress across the contact surfaces. strength of a seam of liner material measured either in shear or peel modes. Strength ofthe seam is reported either in absolute units: e.g., pounds per inch of width; or as a percent of the strength of the sheeting. Tensile force to break measured in lbs.(Newtons) on a supported/unsupported membrane. Additive for elastomeric and plastic sheeting or film for ultraviolet absorption and pigmentation. Typically 1%o to 2o/o of the base product in the case of thermoplastics and crystalline thermoplastics, and l0%o to 45oh in the case of elastomers and thermoplastic elastomers; imparts a black color to the compound which retards aging by ultaviolet light from the sun and increases the stiffrress of elastomeric compounds Arrangement of previously disordered polymer segments of repeating patterns into geometric symmetry. The mass per unit volume, (Ml-3)?kg/m3[4] A generic term for changes in length or width of a fabric specimen subjected toa specified condition. A shear test in which soil or rock under a n applied normal load is stressed to failure by moving one section of the sample/sample container (shear box) relative to the other section. l.) A distribution of finely divided particles in a medium; for example a coiloidal suspension of a substance.2.) A qualitative estimation of the separation and uniform distribution of fibers, typically in a water suspension for wet forming. The extension of a uniform section of a specimen at rupture expressed as percent of the original length. For geosynthetics, the increase in a length ofa specimen expressed as a percentage ofthe original guage length, i.e., engineering strain. The extension of a uniform section of specimen at yield expressed as percent of the original length. The developrttent ofcracks in a nraterial that is subjected to stress or strain in the presence of specific chemicals. A bond between the two flexible membrane sheets is achieved by heat extruding the hot parent material between or over the overlap areas (followed by applied 30 I I t I t I I t I I t I t t t I I I I Film Tear Bond (FTB) FTMS Federal Test Method Standard. High Density Polyethylene pressure if between the sheets.) Failure of one of the parts of a peel or ply adhesion test specimen by tearing, instead of separating from the other part of the specimen at the manufactured or formed interface. (HDPE) Melting Point Modulus of Elasticity Moisture Content Nets NSF Ozone Resistance Puncture Resistance Seam Peel Strength Seam Shear Strength (202)783-3238 A polymer prepared by low-pressure polymerization of ethylene as the principal . monomer. The temperature at which the solid and liquid states of a substance are in* -.*equilibrium; generally, the temperature at which a substance changes from a solid to a liquid. The ratio of stress to strain for a material under given loading conditions; numerically equal to the slope of the tangent or the secant of a stress-strain curve. The use of the term Modulus of Elasticity is recommended for materials that deform in accordance with Hooke's law; the therm Modulus of Deformation for materials that deform otherwise. The percentage by weight of water contained in the pore space of a rock or soil with respect to the weight of the solid material (ISRM). Coarse strand, typically I to 5 mm (3/64 to 3/16 in.) in diamerer, obtained by extrusion, are used to make nets. They consist of two sets of coarse parallel extruded strands intersecting with a constant angle (generally between 60o to 90'). National Sanitation Foundation Standard. (313) 769-8010 It is primarily a test for rubber deterioration and is based on a qualit4tive assessment of surface cracking of the material after exposure. Extent to which a material is able to withstand the action of a sharp object without perforation. Examples of a test of the properry are Federal rest Method Standard No. l0lB, methods 2031 or 2065. A representative specimen is taken across the seam and placed in a tensile testing machine. For the peel test, one end and the closest end ofthe adjacent piece are gripped, placing the seamed portion between them to be in a tensile mode. The resistance to peel is measured. A representative specimen i taken across the seam and placed in a tensile testing machine. For the shear test, the two separate pieces of -eeomembrane are pulled apart, placingthe joined orseamed portion in shear. The resistance to shear is measured. The maximum force required to tear a specified specimen. the force acting substantially parallel to the major axis of the tesr specinren. Measured in both initiated an uninitiated models. Obtained value is dependent on specimen geometry, rate of extension, and type of fabric reinforcement. Values are reported in sffess, e.g., pounds, or stress per unit of thickness, e.g., pounds per inch. 3I Tear Strength t I t I I I I I I I I I I I I t Ii I Tensile Strength Thermal Stability Thickness Transmissivity Water Absorption Water Vapor Transmission The.maximum tensile stress per unit of originar cross sectional area applied during stretching of a specimen to break; units: SI-Mega or kilopascal, customary: lb. per sq. in. The ability of fibers and yarns to resist degradation at extreme temperatures. The normal distance between two surfaces of a geosynthetic. Note: Thickness is usually determined as the distance between an anvil, or base, and a presser foot used to apply a specified compressive stress. For a geotextile, the volumetric flow rate per unit thickness under laminar flow conditions, in the in-plane direction of the fabric. The increase in weight of a test specimen after immersion in water under - specified conditions of time and temperature, expressed as a percentage of its dry weight. water vapor flow normal to two parallel surfaces of a material, through a unit area, under the conditions of a specified test such as ASTM E96. )z lt;W ,,.,iffi!,ri*", ll aM | 8oo-s24-8672 I rflrrnl IrI - coLoRADo LTNTNG TNTERNATToNALsIt | - HDPE REFERENCE LrST tlI I I LOCATION I SQUARE FOOT QUANTITY I MIL THICKNESS Ir- II - Action Linino HDPE I t 'i:y:I -3-i1':'--1- __llii__- | ,aircraft De-fcino Recvcte Stonoe Facilitv HDPE I I _i1e_?:_11_ __1_i.__ I Alec Beck HDPE I f Austin, TX 7,3L3 sf .10 mil I r ;;;;;;;;;i;;;;;;;;;;;---;;;;;;;;;il 6;-----I cor C-ourse Lakes I I ljlT-T:-T:i-T-::- - ----------::!:t--T--. -.-- ---------3:tl----------- I Atter Monofill Foth & Van Dyke HDPE I f Davenport, IA 210,000 sf 60 millrI - Ambrusia LIMTM M.K. Ferguson,Inc. HDPE I f ffitrJ":,3:fi- 155,ooo sr 4o mir III Ambrcsia Lakes UMTRA Proixl M.K. Ferguson,Inc. HDPE I f Ambrosia Lakes, NM 650,000 sf ,10 mil III - Amor Prcast HDPEI I Litueton, CO 339,523sf 30 mil I I 1!:'2?{ 1Tl1 I _ American fuda Yankee Gulch Kvaerner HDPE I r *'chute, co 133;i33:[ 33ilii I z83,5o0 sf 6o mit I f 146,650 sf 6o milI r ---- | - Ames Construction. fnc, HDPE | - Rurora, CO 223,830 sf 60 mil HDTlI ..-?l!:!l-1:l-. TTIII-?: Ilr I Corporate Office: LO62 Singing Hills Road Parker, CO 80138 800-524-8672 Amoo Casoer Former Refineru Barrier CasPer, \A/Y ThermoRetec Corporation 17,010 sf 13,500 sf HDPE 60 mil Geotextile Amoa Oil Comoration Oil Storage Tank Lining Systems Casper, \MY Pritcha rd C,orporation 34,860 sf 35,000 sf HDPE 60 mil 80 milHDPE Amoa fuuth Evaoontion Ponds Grainger, WY Amoco Production Company-OK 175,500 sf HDPE 40 mil I I I I I I I T I Aoadre Gold Casino Globe, AZ HDPE 40 mil Geote,xtile 138,937 sf 9,000 sf Arc Weldino Soecialists Steamboat Springs, CO 235,000 sf HDPE 60 mil Anowhead Countv Club Golf Couts Golf Course Lakes Rapid City, SD Wyss Associates,Inc. 19,800 sf HDPE 60 mil ASI RCC Tnc Boulder, CO 18,900 sf HDPE 60 mil Asohalt Pavino Denver, CO L32,975 *HDPE 30 mil Aastin Golf Cource Austin, TX HDPE 210 milSmooth 40 milTextured Geotextile Boz 208,2106 sf 10,750 sf 209,475 sf AWSRemediation Denver, CO 27,900 sf HDPE 30 mil BEI Landfill Commerce City, CO 11,090 sf HDPE 50 mil Balo Disoosl Facilitv Sydney, MT 43,875 sf HDPE 40 mil I I T I t t t I t I hr*dale Air Force Base Fire Training Facility Shreveport, l-A Dept. ofthe Navy 23,200 sf HDPE B0 mil Banett.Resoures Evapomtion Ponds Parachute, CO 424,790 sf 330,139 sf HDPE 40 mil 60 mil h*line Golf Cource Inigation Pond Belleview, FL Stan Norton Engineering 70,000 sf HDPE 40 mil Bel m on t Co n stru cti on Serui ces I 28,350 sf 50 mil Bio Islapd Countru Club Inigation Lakes Kailua Kona, HI In-House 965,250 sf HDPE u10 mil Boi* C,ascade Intemational Falls, MN BarUett & Associates 345,747 sf HDPE 40 mil Boi* Cascade LFCao Ray, MN 110,720 sf LLDPET ,10 mil Boodle Mill Site GntralCity, CO In-House 30,000 sf HDPE 60 mil I I I I I I I I I I Bodle Mill Site Denver, CO Re-Tec,Inc. 30,000 sf 30,000 sf 30,000 sf HDPE .10 mil Geotextile 40 mil Double BrcadAcre Landfill Pueblo, CO 160,650 sf HDPE 60 mil Brdericlc Wood Producb Suoerfund Site Denver, CO 30,000 sf HDPE 210 mil Bullfroo Unit Wyoming 89,233 sf FIDPE 40 mil Budinoton Nofthem Fueling Facility Guernsey, WY HDR Engineering, Inc. 483,950 sf HDPE 60 mil Gdus Dairu Ft. Morgan, CO 108,000 sf HDPE 40 mil Calamus Fish Hatclteru Phase II & III Improvements Burwell, NE KCM,Inc. 1,740,000 sF 1,032,000 sf VLDPE 30 mil 40 mi|VLDPE Canvon Snrinos Golf Coutse San Antoniq TX HDPE 40 mil 60 milHDPE 13,500 sf 151,200 sf @re Environmenbl Manaaement Englewood, CO 20,775 sf HDPE 40 mil I Camill filt New Pad Installation South Lansing, NY Gaynor & Associates L23,975 sf HDPE B0 mil I C.entennial Ao Suoolv Greeley, CO L2,l4L sf HDPE B0 mil I CET Envirunmenbl *ruices fnc. Englewood, CO HDPE 20 mil155,385 sf T t I Chiaoo Contractor's Su oolv Bellwood,IL 12,552 sf HDPE ztO mil Citvof Famo Landfill Fargo, ND 21,000 sf HDPE 60 mil Coastal Fuel *ruices Roosevelt, UT 7,700 sf HDPE 30 mil @neio Constructorc Kingsburg, CA 9,450 sf HDPE 60 mil Coooer Oueen EvenB Pond Bisbee, AZ 159,000 sf HDPE 80 mil Cnia WWTP Craig, CO Black & Veatch 64,000 sf 54,000 sf HDPE 60 mil 80 milHDPE Craio WWTP (Phas ffl Southwest Lagoon Craig, CO Black & Veatch 87,750 * 67,500 sf HDPE z$0 mil 40 mil HDT Cnio WWTP (Pha* ff *ction Ifr Southeast Lagoon Craig, CO Black & Veatch 117,000 sf 54,000 sf HDPE 40 mil 40 milHDT I I t I I I I I t I I t I I I I Crioole Crcek& WdorGold Mine Proess Building Lining/Secondary Containment Victor, CO Bateman Engineering, Inc. 21,600 sf 51,000 sf VLDPE 80 mil B0 mil HDPE Cutwnti National Park Wastewater Lagoon Lining Gunnison, CO National Park Service 222,O0O sf HDPE 4O mil D & D Farms Lagoon Lining Holyoke, CO 470,LL5 sf HDPE 40 mil DRM. fnc Gillette, \{Y HDPE 210 mil 60 mil HDPE 37,625 sf 18,900 sf Danw, fnc Houma, [A White/Black 29,250 sf HDPE 40 mil Delta Correctiona I Facilitu Delta, CO Martin & Martin 55,000 sf HDPE 40 mil Denver fn terna tiona I Airooft Glycol Recycle Facilities/Concourse B De-lcing Denver, CO Burns McDonnel 42,000 sf HDPE 40 mil t I 27,000 sf BO mi| HDPE DenverRadium Pruiect Robco Superfund Site UNC Geotech VLDPE 30 milDenver, CO Diamond Star Ranch Eagle, CO sf 132,610.5 sf HDPE 40 mil Dinoaur National Monument Quarry Sewage Lagoon Re-Line Vemal, UT NaUonal Park Service 50,000 sf HDPE 40 mil Dae Compound Wash Pond #7 Grand Junction, CO UNC Geotech 22,000 sf VLDPE 30 mil Dows WWW Dows,IA Wallace, Holland, lGsder & Smitz Co. 110,000 sf HDPE 60 mil Duranao UMTRA Retention Pond/Old Durango Mill Site Durango, CO MK Ferguson Company 270,000 sf HDPE 40 mil I I t t I I I t I I I t Eaole Mine Remediattbn Pruiect Cap Closureflffater Tank/Sludge Pond/ Temporary Run OfflDrainage Berm/Sludge CellExpansion Minturn, CO Dames & Moore, Inc. 65,000 sf u10,000 sf 75,000 sf 6,500 sf 237,000 sf 60 mil 100 mil HDPE 30 milVLDPE 40 mi|VLDPE 40 milHDPE EIJebeI WWTP Sewage Lagoons ElJebel, CO Enaftech 110,000 sf HDPE 40 mil El PalomarGolf Cout* Golf Course Ponds Guadalahara, Mexico In-House 465,000 sf HDPE 60 mil EllswordrAirFore Base East Nike Site - Repair Sewage Lagoon 2Bh Civil Engineering Squadron HDPE B0 mil Envhonmenbl Linerc, fnc Cortez, CO sf 29,250 sf HDPE 40 mil FaIIs Citv UMTM Falls City, TX MK Ferguson 680,000 sf HDPE 40 mil Famo Landfill Landfill Lining Fargo, ND City of Fargo Engineering Dept. 280,000 sf HDPE 60 mil Fa rn s wo rth Co n stru cti o n irrigation Ditch Lining Paonia, CO HDT 60 mil12,320 sf t t Fil-Estate Golf & Develooment Golf Course Lining Manila, Philippines HDPE 30 mil 40 mil HDPE 1,738,900 sf 2L9,375 sf Fish Crcek Reseruoir Reservoir Enlargement Steamboat Springs, CO Woodward{lyde Consultants 128,565 sf HDT B0 mil I T I t I I t I Flatiton -runtier-Kem oer Joint Venfiue Retention Pond Fort Lupton, CO In-House 47,880 sf HDPE 50 mil FMC Phosnhorus Chemical Fac. Pocatella,ID 5,584 sf HDPE 60 mil Fo ru ost Goltlo Ematis n a I Golf Course Lakes Manila, Philippines In-House 927,375 sf HDPE 40 mil Fott @tsn Armv Base Foft Carson, CO Black & Veatch 19,000 sf HDPE 210 mil Fo tt @ I I i n s- Lo ve la n d A i ro o rt Seoondary C.ontainment Lweland, CO Isbill Associates, Inc. 8,500 sf VLDPE 40 mil Fun Vallev Resort Southpark, CO Cap Allen Engineers, Inc. 210,000 sf HDPE 40 milI I Galamb Mobile Homes Watkins, CO 33,964 sf HDPE 40 mil Gold Hill Mill Gold Hill, CO McCulley, Frick & Gilman 53,000 sf 53,000 sf HDPE 50 mil GCL Bentofix Gould C;onstruction Glenwood Springs, CO 9,000 sf HDPE B0 mil Elden Goldsmith Templeton, CA 6,800 sf HDPE 30 mil I I t I I I Gould Construction South Gnyon Landfill Glenwood Springs, CO 51,000 sf HDPE 60 milTextured Glacier Construction Denver, CO 39,645 sf HDPE 60 mil Grain Prucessino Coro, Washington,IN 88,132 sf HDPE 60 mil I T Grand Junction UMTRA Phase f MillSite Grand Junction, CO MK Ferguson, Inc. 150,000 sf HDPE 40 mil I I I Grand Junction UMTRA Phase II Cheney Reservoir Disposal Site/Repository/ Disposal Cell Retention Pond Grand Junction, CO MK Ferguson, Inc. 275,000 sf 30,000 sf 'HDPE 40 mil 30 mi|VLDPE Gten River UMTRA Green River, UT MK Ferguson, Inc. 50,000 sf HDPE 40 mil Gunnison UMTRA Gunnison, CO MK furguson,Inc. 190,000 sf HDPE .10 mil Hardaoe Site Remedv Com. Undsay, OK IT Corporation 190,125 sf HDT 40 mil I t I I t Hastinos ' ' qe Countv landfill Hastings, NE Olsson & Associates 245,650 sf HDPE 60 mil HavSoinas UTWTP Inigation Storage PondAffWT Cells Hay Springs, NE Baker & Associates 151,200 sf HDPE 60 mil Hiohwav32Ash landfill Port Washington, \M 133,600 sf HDPE 210 milI I Hillto* WWTP Hillrce, CO KLH-NUH 410,000 sf HDPE zl0 mil Hinds Eneruv Facilitv Jackson, MS 57,060 sf HDPE 50 mil t Hunt Field Runwav Rehabilitabbn Lander, WY Morrison Maihrlg Inc. 220,000 sf VLDPE 30 mil I HfS-Geotans Westninster, CO 7,700 sf HDPE 30 mil Hvdto-Chem Proessino Methanol Processing Pla nt Commerce City, CO In-House 78,000 sf VLDPE 30 milT I t lEE Holcomb, KS 2168,000 sf 458,000 sf 468,000 sf 226,800 sf 775,000 sf 48,200 sf HDPE 40 mil 60 mil HDPE Geo-Net 60 mil 40 mil 60 mil fowa Countv Leachate Collection Facilitv Iowa County, IA Howard R. Green, Inc. 32,000 sf HDPE 60 mil Jeffiev Citv Reclamation Prciect Mine Site Lagoon/Water Pond Jeffrey Crty, WY Phelps- Dodge Mining 48,800 sf HDPE 60 mil Johansen Farms Underwood, MN 40,480 sf I-lDPE z[0 mil John Terrufiles Companv Denver,CO 59,920 sF WovenflrVh 20 mil Julsbum WWTP Meline & Ireland 120,000 sf I I I I I t I CO KellvAir Fote Base Fire Training Facility San Antonio, TX U.S. Army Corps of Engineers 44,625 st 45,24O sf 50,400 sf HDPE 210 mil Gundseal 80 mil PN-3000 Geonet 80 milHDPE Kuioer Water Trcatment Plant Aurom, CO 182,500 sf HDPE 40 mil lamelti & tuns- fnc Fridley, MN 64,233 sf HDPE 60 mil Lander Golf & Countv Cluh Expansion lander, WY Wyss Associates 73,725 sf 222,660 sf HDPE 40 mil Le Construction, fnc Sublette, KS HDPE 30 mil HDT Limon Tri-State Facilitv Umon, CO TiC 2fi,000 sf HDPE 60 mil lone Oak Dainr Phinview, MN HDPE 210 mil Geotextile 55,986 sf 55,986 sf Lonas Peak Water District Run ffi Pond Longmont, CO Rocky Mountain Consultants 13,500 sf HDPE 5O mil t I I I I I I I I I I Lost Cabin Gas Plant Water Storage Reseruoir !I'li:-Y LowruLandftll FTPA Waste Pit Denver, CO United Engineers & Constructors 242,000 sf HDPE B0 mil 2l2,L4O sf 212,L40 sf 77,000 sf 114,107 sf HDPE uCI mil Geotextile Geo-Net 40 mi| LLDPE Lowru Landfill Supeffund Site Aurora, CO Parsons Engineering Sciences, Inc. 9,000 sf HDPE 40 mil LuasAetospace Process Building Secondary Containment Park City, UT In-House 17,000 sf HDPE 40 mil Luke Air Force Base U.S. Army Corps of Engineers Crash Fire Rescue Training Facility Luke AFB, AZ 46,500 sf 24,000 sf B0 mil 40 mil HDPE Maoma Copoen fnc, San Manuel Mine Site San Manuel, AZ In-House 60,750 sf HDPE B0 mil Mallett Oil Secondary Containment Leadvillg CO In-House 11,985 sf HDPE 40 mil T I I t I I t I t Manila Southwoods Golf & Countru Club Carmona, Cauite, Philippines L,022,450 sf HDPE 30 mil Maralex Resources DeBeuque, CO 67,500 sf HDPE 40 mil Maftha's Vineuard Golf Cource Edgartown, MA HDPE 10 mil 108 153,900 sf 32,400 sf Ma rti n M a ri e tta Co ro o ra ti o n Acid Sump Closure/Fire Protection Facility Waterton Plant, CO IT Corporation 43,500 sF HDPE 40 mil Matfrell UMTRA RetenUon Basins/Wash Water Maybell, CO MK Ferguson, Inc. 219,375 sf HDPE 40 mil -7,A. McCullouoh WTP 5 MG Reservoir/Wash Water Supply/ PRV VaulVPlant Effiuent Manhole USAF Academy, CO Black & Veatch 70,875 st HDPE 40 mil Mid-Ameria Dairumen fnc Wastewater StabilizaUon Lagoon Ravenna, NE Miller & Associates C-onsulting Eng. 1z+0,000 sf HDPE 60 mil Midwav Landftll Colorado Springs, CO Industrial Compliance 6,000 sf HDPE 60 mil I t I T I I I I Millette Oil Leadville, CO 11,985 sf HDPE 40 mil Milliken Sanitation Distrid WWP Milliken, CO Donahue & Associates 270,000 sf 270,000 sf HDPE 40 mil Geotextile Molvcoro- fnc. Process Water Pond Louviers, CO Vail Engineers 130,000 sf 130,000 sf HDPE B0 mil 60 mil GeoNet Moncrief Oil Evaporation Pond Lysite, \,VY In-House 90,000 sf HDPE 40 mil Monfort Beef Plant Garden City, KS HDPE 40 mil 50 mil HDPE 142,000 sf 142,000 sf Monticello Mill Site (Phase III Retention Pond/Drainage Canal Monticello, CO Rust Geotech 67,275 sf 86,940 sf HDPE 40 mil 60 mil HDPE Mountain Redion Corporation Grand Junction, CO 25,365 sf HDPE 30 mil Municioal Eauipment Comoanv Ridgeway, IL 152,613 sf HDPE 60 mil Naturita UMTRA Mill Site Drainage Ditches/Retention Pond Naturita, CO MK Ferguson, Inc. 87,000 sf HDPE 40 mil Nevada Hvdmarbons Proiect Processing Facility Reno, NV In-House 60,000 sf HDPE 80 mil Newberru Farms Rensselaer, IN 25t,123 sf HDPE 50 mil Nilex Corooration Englewood, CO 37,800 sf HDPE 30 mil T I I I I I I I t T t I T I t I I I I Ilotthbank Golf Cource Golf Course Lakes San Angelo, TX In-House 482,625 sf HDPE 40 mil Noriltern States Power Minneapolis, MN HDPE 40 milHDT 40 mil HDT 108,240 sf 147,108 sf Norwood Raw Water Resenroir Norwood, CO Westwater Engineering 505,000 sf HDPE 40 mil OEA UI4WTP Facilities fmorovements Aurora, CO Gmp, Dresser & McKee 408,118 sf HDPE 40 mil Old Works Golf Cource Anaconda, MT HDPE 60 mil 60 milHDT 220,000 sf 375,000 sf Ovid WWTP Sewage Lagoon Ovid, CO Meline & Ireland 20,000 sf HDPE 40 mil PacificJunction Secondary Containment/Fertilizer Storage Pacific Junction, IA CSM, Inc. 58,750 sf HDPE 60 mil Paoillion Creek WWTP Yard Waste Compost Pad/Detention Basin Bellevue, NE City of Omaha, Plant Engineering 27,500 sf HDPE 40 mil I t Par* Construction Minneapolis, MN 34,700 sf HDT 50 mil Pewnee PowerStation Brush, CO In-House 133,000 sf HDPE 100 mil Peakview Acres Little Falls, MN L43,700 sf HDPE 60 mil Peavlefs Mountain Sbr fnc, Afton, \UY 29,250 sf HDPE 40 mil Perdue Farms Cromwell, KY 405,720 sf HDPE 60 mil I I I I I I I I t Perdue Farms WWTP Sludge Lagoons Cromwell, KY Chas. N. Clark Associates, Ltd. 434,000 sf HDPE 60 mil Perrv Creek Flood Protection Sioux City, IA U.S. Army Corp. 23,625 sf HDPE 40 mil PFFJ Animal Waste Laooon Wastewater Lagoon Snowflake, AZ Surface Contracting Co. 1,463,616 sf HDPE 40 mil PFFJ Exoansion Snowflake, AZ Axis Engineering 1,057,450 sf HDPE 40 mil PFFJ, Tnc Finisher/Nursery Snowflake, AZ 321,750 sf HDPE 40 mil PFFJ, Tnc Snowflake, AZ In-House 1,053,000 sf HDPE 40 mil Pooov Ridae Golf Cource Greiner Engineering 175,500 sf Inigation Pond Livermore, CA HDPE 40 mil Pueblo Fish Hatcherv Solar Heating Pond Pueblo, CO U.S. Bureau of Reclamation 270,000 sf HDPE 40 mil Power Resources Glenrock, WY 7,540 sf HDPE 80 mil I I T I I I I I Pvramid Excavation & Construction Kansas Dept. of Transportation Louisburg, KS 108,000 sf HDPE 40 mil Ouarru Hills Dainr Toward Rolling Stone, MN 66,176 sf HDPE 30 mil The Rapids New Castle, CO C.G. & G. Construction 78,750 sf HDPE 40 mil Reconstruction of WW Pond #3 Wastewater Disposal Pond Cheyenne, WY DM Hopkins & Associates 75,600 sf 66,150 sf HDPE 60 mil 60 mil HDC Redstone Develooment Denver, CO 34,272 sf HDPE 30 mil I I I I I I Reno Countv Landftll Hutchinson, KS CDM Engineering 88,000 sf 394,000 sf HDPE 40 mil 60 mil HDPE Ria Remediation Rico, CO 56,700 sf HDT 60 mil Rifle UMTM Estes Gulch Disposal Cell Rifle, CO MK Engineers, Inc. 55,620 sf HDPE 60 mil River Bend Subdivision Glenwood Springs, WY 34,750 sf HDPE 40 mil River Vallev Ranch Golf Cource Carbondale, CO 248,600 sf HDPE 40 mil Riverton UMTRA Proiect Riverton, \MY MK Ferguson, Inc. 150,000 sf HDPE 40 mil RM Cat Colorado Springs, CO 5,850 sf HDPE 80 mil I I T I I Robinson Brick Soil Pond Decon Pond Denver, CO Tuttle Applegate 25,600 sf HDPE 30 mil Rockv Flats Weapons Plant Secondary Containment Carbon Filter Tanks Aruada, CO E.G. & G. 8,800 sf VLDPE 30 mil Rockv Mountain Arcenal Pad Installation Commerce City, CO U.S. Army Corps of Engineers 14,400 sf HDPE 50 mil Rockv Vista Farms LLC Piez, MN 57,904 sf HDPE 60 mil Roe & Sons Golf Cource Construction Golf Course Lake Anaconda, MT In-House 220,000 sf 375,000 sf HDPE 60 mil Smooth 60 milTextured T I t I I t I Roval Westmoreland Golf & Countru Club In-House 58,500 sf HDPE 40 mil Golf Course Lake ll-l1Ti-l:-?11?--1-"-l Roval Westmoreland Golf (Phase lfr Golf Course Lake St. James, Barbados Associated Consulting Engineers 131,625 sf 135,000 sf HDPE 40 mil Geotextile I I I Seotic Seruices Union, MO 29,250 *HDPE 40 mil *verence WWTP Severence, CO 7,230 sf HDPE 60 mil S.F. Phosohates Gypsum Pond/Double Layer Containment Rock Springs, WY HDPE 27,000 sf 18,000 sf 60 mil Geotextile I I I I Shadduck Chemical Denver, CO 84,375 sf HDPE 30 mil Show Me Landfill Landfill Lining Warrensburg, MO Industrial Compliance 62L,140 sf HDPE 60 mil Sinclair Oil Corooration Sinclair Refinery Sinclair, \MY Resource Technologies Group, Inc. 190,000 sf 190,000 sf 190,000 sf HDPE 40 mil 50 mil HDPE Geo-Net I I T T Slick Rock UMTRA Proiect Slick Rock, CO MK Ferguson, Inc. 279,375 sf HDPE 40 mil SLV Earthmoverc Monte Vista, CO In-House 74,625 st HDPE 40 mil Snvder Oil Rifle, CO 95,L72 sf HDPE 40 mil fulvav Minerals Rock Springs, WY 7,000 sf HDPE 100 mil fuuthern Golf & Countrv Club St. Michael, Barbados, W.L 131,625 sf HDPE 40 mil Southwind Devel, Com, WWTP Wastewater Lagoons Garden City, KS Mid-Kansas Engineering 146,000 sf HDPE 40 mil t I I I I T I I Stanlev Canvon Proiect Tank Roof Lining Colorado Springs, CO Black & Veatch 36,000 sf HDPE 40 mil Star Ranch Hutto, TX 356,552sf HDPE 40 mil Stea m boa t 5p ri n os A i roort Containment Liner Steamboat Springs, CO Isbell Associates 12,000 sf HDPE 40 mil Ste.amboat Lake State Park Maphis International, Ltd. Water & Wastewater Facilities Steamboat Springs, CO 45,000 sf 60 mil Sterlino WWTP Nitrification Basins Sterling, CO The Engineering Company 131,625 sf HDPE 40 mil Sun set M etro oo I ita n D istrict Ellicott Springs, CO Scheaffer & Roland, Inc. 85,000 sf VLDPE 30 mil Suoerior Golf Cource Construction- fnc Las Vegas, NV 98,719 sf HDPE 40 mil Terminal Storaoe Reseruoir Irigation Canal Broomfield, CO Rocky Mountain Consulting 55,200 sf HDPE 30 mil Tera Enaineerina & Conrtruction Milwaukee, \M 10,260 sf HDPE 50 mil Tezak Heaw Eouioment Comoanv Penrose, CO 18,900 sf HDPE 30 mil Tota I Gol f Co n stru cti o n Bahama Reef Golf Course Freeport, Bahamas 94,500 sf HDPE 30 mil I I I I t t I I I t I I I t t I I I I Town of FrederickGolf Cource Golf Course Lakes Frederick, MD Town of Frederick 120,000 sf HDPE 40 mil Transenerov Grindino fnc, Houston, TX 73,L25 sf HDPE 40 mil UMETCO Minerals Corooration In-House 875,000 sf 875,000 sf HDPE 40 mil Geotextile Superfund Cleanup Uravan, CO Union Paciftc fie Treatment Plant Tank Containment Laramie, WY cH2M Hill 39,000 sf HDPE 40 mil United Airlines Fuel Restoration Pruiect Denver, CO Swanson Rin(Facilitech 50,000 sf HDPE 40 mil Univercitv of Nevada Fire Training Facility Reno, NV In-House 31,000 sf HDPE 60 mil Upoer Canal Catchment Reoairs Delta, CO Bureau of Land Management 12,000 sf VLDPE 40 mil Veit & Comoanv fnc. Rogers, MN HDPE Textured 40 mil HDPE Smooth 40 mil HDPE Textured 60 mil 72,284 sf 136,124 sf 72,824 sf 141,404 sf HDPE Smooth 60 mil Velan Filterc Process Building Secondary Containment Colorado Springs, CO Koepf & Lange 15,000 sf HDPE 60 mil HDPE 40mil t I I I I I T I I Veterans Memorial Park Boulder City, NV 200,000 sf Wa ds wo rth G o I f Co n stru cti o n Hutto, TX Plainfield, IL 22,500 sf 38,607 sf Woven Coated PE 12 mil HDPE 40 mil Warren AFB Fire Trainino Facilitv Cheyenne, \,VY USAF,Engineering 44,000 sf 214,000 sf 214,000 sf DN-3000 Drainage Net 80 mil HDPE Geotextile WBf, fnc, Buffalo, \MY In-House 12,000 sf HDPE 60 mil IUB Pumo & Suoolv Ft. Morgan, CO 7,200 st HDPE 12 mil West Elk Mine Facilitv Summerset, CO t3,L67 sf 13500 sf HDPE 60 mil Geotextile The White Grouo HDPE 40 milCushing, OK 7,700 sf Whiteman Air Fore Base Crash Fire Rescue Training Facility Whiteman AFB, MO U.S. Army Corps of Engineers 75,6001sf ' HDPE 60 mil Wildhorce Golf Cource Carbondale, CO 230,000 sf HDPE 40 mil Williston Basin Pioeline Wastewater Pond #1 Rehabilitation Worland, WY Western Water Consultants, Inc. 7,2OO sf L4,625 sf HDPE 80 mil 40 mil I I I I I I I I I I Woodman Hills/Paint Brush Hills Colorado Springs, CO Martin & Martin 121,616 sf HDPE 40 mil Wvomina Premium Farms Wheatland, WY 190,260 sf HDPE 60 mil Wvondotte Golf Club S.A. Golf 121,575 sf HDPE 40 mil Golf Course Lakes Lake Orion, MI I t-: :I' I I .;,'r: t I j f. 1t I a T I t I I t *' _rl itt :!i U Anchor Trench 1.5' deep x 1' wide Trench Backfill I I lr 3'Min -l Fluid Level V Anchor Trench 2' deeP x 4'wide rr"n"n Backfiil I l. 3'Min. -l Fluid Level Anchor trench dimensions for a specific project must be determined by the engineer to suit local soil conditions. Anchor Trench Details 6kK,,,m Diagram D-l Compacted Subgrade Wedge Weld with Void for Air Pressure Testing W Wedge Weld 6km,m Diagram D€ I I l- I I r:' 1,, I Ii T I I t t ]r T Ii 4'Diameter Hole Through Liner Only 6" x 6" Sealed on Three (3) Sides W Gas Vent Diagram D-56(,(K^,ffi T I,'. I I I !iit :., l1 I l' '1I : t I ; I t I s*fI' ,,1 tr to Liner (TYP) Batten Attachment w Pipe Penetration with Collar6((K,ffi Diagram D-7 1/4" Thick x 2" Closed Cell Nitrile/PVC Sponge with Adhesive Backing 1/4" Thick x 2" Batten Washer 3/8" x 3-3/4" @ G" O.C. Stud Anchor \Concrete Para-JT or Equal Sealant Batten Attachment - Single Layer I I I" I I ...:: I I "'' I I I t t 't.I I I tr,ft $ llilr, I ffil: ,if) I ',i:ac l $l ;:1gl *l ul I I I I I t t I I t I Appendix F I t I I I I I T 'l I t 'l ,l I I I I Installation Reports :W v*,m,#trF 'lorr tnside Line on containment I t Colorado Lining lnternational I lnstallation Reports I t for I International Uranium lat I Blanding, Utah T t I t t I I 1062 sinsins Hins Rood porker, corqrodo 80138 ,r:r?ii?!i" oJ6f?r'ro-uun Fox 303-B4t-5780 www,cororodorinins,com WI t Sincerely, A); C: Vinnie Davis Project Manager I 'l I I I t I I I I I I I I T I I 1062 Singing Hills Rood pn.aA Lru,tf, INTIRNAiIONAL- Your Inside Line On Containment lwrc 6,2002 Harold Roberts International Uranium Independen ce Plaza Suite 950 1050 17th Street Denver, CO 80265 i Re: Blanding, Utah Project Dear Harold: This letter shall serve as certification that the 60 Mil HDPE Colorado Lining Intemational (CLD provided to International Uranium, meets desigu specifications for this project. In addition, this HDPE was installed and tested in accordance with the provided design specifications. The installation and quality assurance testing also meeti or exceeded documented industry guidelines and standards. We are providing you with the associated field documentation to support this certification. In addition, you are also protected by a fivg-year material wa:ranty and a one-year installation warranty. On behalf of our dedicated installation team and management staff, we would like to thank you for giving us the opportunity to successfully complete this project for you. If you have any further requests, piease do not hesitate to contact me. Porker,cotorodo80138,*??lfili"%f%o-uuz Fox303-B4t-s780 www.cotorodotinins,com outu, -\''.14-02 I t t I t I l I I I I T It I I t l) I I fr/orads #tu{tu, rt$[[mflililfl8$*r o " Your Inslde Line On Containmenln Project: Owner: Engineer: Contractor: Installation Superuisor: Material: Colorado Lining Internationat (CLf) is not responsible for subsurface conditions, which may affect lining performance. Is surface is acceptable for of geomembranes?-'( Suberade Inspection Blanding, Utah International Uranium International Uranium 60mil HDPE Accepted By Representative of Owner (Signahrre) PrintName/Title Company Accepted By Representative of CLI (Signature) PrintName/Title 1062 Singing Hills Road Parkcr, Colorado 80138 CORPORATE OFFICE 800 5248672 30384t2022 Fa< 303 841 5780 www.ooloradolining.com 6/or,a,/s ,rt?x{hd, tl il [ $ tfl fli il { it 0 il $ rr 'n Your Inside Line On Containmentu Project: Owner: Engineer: Contractor: Installation Supervisor: Brian KendallMaterial: 60mil HDPE Nlaterial Inventory Log Page _ of_ Blanding, Utah International Uranium International Uranium No.RollNumber Width Length Material Condition Return (Factorv or CLI) 1 105422 22.s ,)Good Gartial Roll)None 2 227555 22.s ,)Good (Partial Roll None J 225360 22.5 ?Good Gartial Roll)None 4 229339 22.5 ?Good 0artial Roll)None 5 243226 22.5 2 Good Gartial Roll)None 6 243228 22.s ,l Good (Partial Roll)None 1062 Singing Hills Road CoRIoMTE oFFICE Parkor, Colomdo 80138 800 524 8672 303841 2O2Z Fax 303 841 5780 www,ooloradolining.com ,frfurffifihind, tt$[[flilililit0uflu' u Your Inside Line On Containment,, Date: Project: Owner: Engineer: Contractor: Installation Supervisor: Material: 5-29-02 Blanding, Utah International Uranium fnternational Uranium Brian Kendall 60mil HDPE Fusion Weld X ' Extrusion Weld Unit Type & No. H.S#0019AIL Daily Observations / Notes:Weather Conditions: Material arrived around noon and we completed the installation portion of the project CoR?oxATE oFFrcE1062 singing Hilrs Road parker, colorado 80138 800 sz4 aelz ioi ut zozz Fax 303 841 5780 www.coloradolining.com I I I I I I I I I I I I t I I I I I I 6/srado fu{:rw ttilril[$$tflfltt0ilr$rL' " Your Inside Line On Containment" Date: Project: Owner: Engineer: Contractor: Installation Supervisor: Material: Dailv Installation Report s-30-02 Blanding, Utah International Uranium International Uranium Brian Kendall 60mil HDPE Fusion Weld X ' Extrusion Weld X Unit Type & No. H.S#0019. X-2#0104 Daily Observations / Notes:Weather Conditions: Todaywe finished our toe seams, patching, and all the remaining testing.. We had the job completed around 6:00pm. 1062 Singing Hills Road Parker, colorado 80138 ro8?yo"#T offi"ior roL Fax 303 841 s780 www.coloradotining.com Date of Test Time of Test Ambient Air Temn untt lemp.Pre-Heat Temp. Unit Speed Peel Value Insidc/oBid. Sheer Value Welding Tech. Pass/Fail 5-29-02 7:30 70 775 10 122/125 155 M.L Pass t35n24 142 Pass 122/127 Pass 5-30-02 9:45 80 475 47s /92 160 M.L Pass 189 145 Pass l8s Pass ry ffibrads rt?,/i{-td. llil[[fliil$lrtttflil$rl' " Your Inside Line On Containment" I I I I I t I I I I I /I I I ,I I I iI t Project: Owner: Engineer: Contractor: Installation Supervisor: Material: Page_ of_ Blanding, Utah International Uranium fnternational Uranium Brian Kendall 60mil IIDPE 1062 Singing Hills Road Pdrker, Colorado 80i38 CoPeoRATE oFFICE 8005248672 30384t2022 Fax 303 841 5780 wwwcoloradolining.com Panel No. Roll' Number Date Material Type width Length Seam No. I t05429 s-29-02 60mil HDPE 22 t29)5-29-02 22 24 J 5-29-02 22 35 4 ((5-29-02 22 50 5 227555 5-29-02 22 42 6 aa 5-29-02 22 25 7 105422 5-29-02 22 8 22755s 5-29-02 22 92I225360s-29-02 22 52 10 s-29-02 22 t44 11 aa 5-29-02 22 151 12 229339 s-29-02 22 rs9 13 5-29-02 22 171 14 aa 5-29-02 22 69 15 243226 5-29-02 22 109 16 aa 5-29-02 22 176 t7 aa 5-29-02 22 111l8243228s-29-02 22 69 19 5-29-02 22 43 20 aa s-29-02 22 21 \a 5-29-02 22 38 22 5-29-02 22 38z)aa 5-29-02 22 35 24 aa 5-29-02 22 41 25 aa 5-29-42 22 32 i ,:: ri ,iii'. r,'.it r,,: 1.iili,:. ffifurado rth{tua. fl,il[[ilililltttrflil$rr' u Your Inside Line On Containmenttt I I I I T I I I t I I T I t i I t I I Project: Owner: Engineer: Contractor: Installation Supervisor: Material: Panel Placement Log Page_ of_ Blanding, Utah International Uranium fnternational Uranium Brian Kendall 60mil IIDPE CoRpoRATE oFFrcE Paiker,Colorado 80138 800 524 8672 303 g4t2022 Fax 303 841 5780 wwu,.coloradolining.com Panel No. Roll Number Date Material Type width Length Seam No. 26 243228 5-29-02 60mil HDPE 22 27 ilr:,;.ffota:r'l ili:i.n ,Sq tiarerFdbtaseffi i _s: Page. ::,,,,, 1062 Singing Hills Road =50Er9!gsEd =s.e 9+E'6 q,i.rai (! i:.:.!t =.h o " id -iJ.+Et.. a A .a a o{ 0 rt 3WF 5ErJ.+GEIH g E E. E F E. 5..E'E= 3 E'-HEs Eii -11 ari:rrr rl!rl, ,Hts'--r*ttsJ' o !e o rlo Ft Hoa trrq ED'oao F+) ilillHIi (! lt a Jt (D o il rlo !t (D H(D0 F .ilP -E o 4LtDl(a l-IJ l'iit<llotala lwlolxl-l6IU'l*lrn t?laIE'l!el- Il^l-l(Dlra Lrl tf.) N) Ft D,98 \o LA v? (,h oo ul co5oo 9P(,rl O cp Llr :? LA 5oo y? 5co \o 5@ \o \o \o 5\o \o (n \o (Jr N)o\t\)(,l o Nco N)o\A@ so\5o\Ao\5(J|5(Jl Nco a 8d N N)5 tlLr)NN NJ tJ \o co !(i 5 u.)N)H \o oo -l o\5 l+J tJ avs:-E tJ\o u)9)UJN u.)(]J UJA t9(^N){\)(rr -l o\(,o\u)(^\o (,I\o 5 5 Nt)UJ UJ5 (,5 (}Jt)r! N)_\o \o b.JN)!(,gora= 3a z4 z49EE X X X X X X X x X X X X X X X X X X X X X X X X X :)> F> EE< il Q EF)U)0 FU t0U)v) H (aa FOU1a tD(na FU A2U)a H TDU)o nd t0V)u) SDv)o U'v) FU eeU)t)) E EDrr)o u)v) ts()) @ H E,(,th n, O(,tD(Aa Eft)al)q sev)h FO tDU)o FU tDv,0 pe rDq FU F,av, F! t0U)(A t0v)a 3B =a ? Dg rr oor-to F'E r{ o(DIo 7 FOt rr ooFt F ts rr oon ? 0)Ftrrr ooI ? A)+rr o(DFto z !9+ri oo o z D' 7iti ()oo ED+ri o(D- p 7i' r4 ooFto ? !Dr-,(ri () (DFt ? FD+rr oo =-tr ooFto r>F) x-r{ oo ? $ ,fr. ooEt ? F)7i- oox FOt rr oo o ? ID t\. l-{ ooHo Di>t r{ () @ !D5ri ooFto ? F) =-ri oor-to ? DO|{ifr{ ooHo FD tr o(Dr-to ? !DFl7frr ()oo S)r-t rr o(D o 8{=o=6,A=' !9 0a a \o \o a \o \o \o o o \o o \o o \o a \o o \o \o O \0 \o \o o \o \o o \o \o o \o \o <> tr o \o Q<> \o 4o=(D z o o o o O -aaO rD'r!= EE -.1{(i !{(^ !{(Jl !{L't -t-.t(i -t{L'I ! -lL.,I --l-I(Jl \]-f,LA *_l!(Jr -J-IlJr -l{(Jt {{ Lar -J{ Lal -l-lLfi -l-I(j \t\tut *J!(Jl -l-JL,I -J\) Lrr {{LA \)-)(n -J{tar -I-I(..t {{(a ;!O6'BEoo I9'> T I I I t9 rE lE o lg @ I ;"EsF g. s! !- T 3EA ' (})S/dof H I E-E I}@ T? '{ lA IE II t I ?=oltloFE B a 3E ; €,i. f !r i! Et g.!r =.h o ":iEiJ.6E " A A ri a (D{ a i a!!ll1. v9 ir' ir. ta/HEI qgE*i iE'EE o oei-:sH = cr: f A L S.-c dErtrt!9 le,te' E' iH IJ E)0e(D +) ll il'HI o E iliit?a Jt (D o oI rt o B' o Fa tD(A -il Et F 19 ?)o H TDt, il pao Edox HGo oI trO lri Fi(!a LA U) t...) HAT Ur! s UA Noo H gd N.) -l No\avs:-E \o o\brEP 2. zF z4o' EE X X o> -> EE< ,1 0 Fd oU) H A)U)U) >rE!,, H =a 7All+F ooEo D)Fl,fr{ o(D o j8{ =t!E=E'=p0a \o o \o {o=o 2 o a7.O(D8Eaq \t-l(Jr -l-l(,t r{g& EID Fl9> !e o :l Ft H tD0 l$ q9. IE o.. ElF la @o t ;"E$F g- s:J !_I SEE (}):t -loJc,aJid T s-E l3aIi-t!<rtg-=' TE I I HEA!AHEi !g,\/-'EgEE ="9.qESE'E8 !.rqE(9t9=.ho";i - ij. t rrt" A A .a a GEt u) rl qEUS i,iEUY= FEi.E rt rt =--algEXE E.;'l-l iD H. E: OQ =E 0'vi-\.E a tjFrEg Eii-e d=|.t-lrDtl ts. tsr- tttl lEd t(D l-tu)(D D' - CDV)Fl.r.t (? -l. (} r-lo0 FU b@ o\Nu oq oq oNo i t I t I IF o lE B ,a! l;"8sE9at I I sEl aY i AJE | $-E TE I?II l$ TE I I I I I I I ffi/oradg hx{hd, liil[[mruf,ilit0$$l'u Yoar Inside Line On ContainmcntttI I I I I T Date: Project: Owner: Engineer: Contractor: Installation Supervisor: Material: Geomernbrane Installation Ad-broval Blanding, Utah International Uranium Corp. ,q B, P,lro/s International Uranium Corp. 60mil IIDPE t t The Geomembrane on this project has been installed, inspected and tested in accordance with Industry Standards and Manufacturer recommendations. Date Accepted By (Signahre) PrintName/Title Company AII warranties to begin on the date of completion. Warranties to be issued upon receipt of final payment CoRpoMTE oFFrcE1062SingingHillsRoad Parker, Cotorado 80138 8OO 5249672 303 g4l 2022 t lt I T lI lj I I Fa:< 303 841 5780 www.coloradolinin!.com t l, ll li li I t I I I , IF'IU' @EMEf"flGcil #t Grg LIMITED MATEzuAL WARRANTY CUSTOMERNAME: PROJECT: TYPE MATERIAL: Intemational Uranium International Uranium - Blanding, Utah 60 milHDPE smooth geomembrane . 800-321-1379 8aO-373-2478 z . Fax 843-546-0516 Fax 281 -358-5297 I. I The company, referred to herein as AGRU/AMERICA, Inc., warrants that AGRU/AMERICA, liners will conespond to the specifications as indicated in AGRU/AMERICA technical records, catalogs, guidelines and test certificates at the time when sold. AGRU AMERICA warrants that the material is faultless and resistant for a period of five (5) years, prorated from the point of time sold when properly installed, covered and used for: run offpond AGRU/AMEzuCA'S liability under this waranty is not applicable when damage is caused by: Natural phenomena as thunder storms, floods, earthquakes, acts of war or other acts of God Chemicals which are not suitable for HDPE liners according to chemical resistance guides or from experience. Further, AGRU/AMERICA is not liable for damages due to the misapplication, incorrect installation, and damages resulting from any kind of inadequate handling. In the event that any defects are noticed in the liner, AGRU/AMERICA must be notified in writing within thirry (30) days. AGRU/AMERICA shall be given an opportunity to ascertain the cause of damages. AGRU/AMERICA reserves the right to decide how damages will be settled. Under no circumstances will AGRU/AMERICA assume liability for consequential damages due to defective liner or incorrect installation. AGRU/AMERICA will not be responsible for failures arising from incorrect welding of seams in the installation. Further, AGRU/AMERICA's warranty will be void in the event that the buyer performs repairs or makes alterations without the express approval of AGRU/AMERICA in writing. AGRU/AMERICA's maximum liability under this warranty will not exceed the purcha'se price of liner and will only be in force when payment has bben made in full and further claims regardless of the legal suppositions are not applicable. This warranty is only valid on condition that the generally approved technical staridards and in particular theguidelines for the installation of the liner are followed. I t i I I I lecutive Offices: 500 Ganrison Hoad, GeorgeEown , S.C. 29440 " B4B-b46-0600 lales Office: 700 Rockmead, Suire 150, Kingwood, TX 77339. 281-gSB-4741."' email: salesmkodaonr ramenir:a nnm For AGRU/AMENCA,lnc. /l.rt.u Authorized Signature I li T] li ll t; li CONTMCTOR: ENGINEER: PROJECT: Colorado (800) 524-8672 Texas (888) 5464641 Ki#6((K^,k^Y California (877) 578-5000' South Dakota (800) 661-2201 INSTALLATION WARRANTY Colorado Lining lnternational lnternational Uranium- Blanding, UT I I DATE OF ACCEPTANCE: 5I3OIO2 MATERIAL:60 mil HDPE Colorado Lining lnternational warrants workmanship performed by Colorado Lining lhternational to be free of defects for one (1) yea(s) from the date of acceptance. This limited warranty does not include damages or defects in workmanship resulting from acts of God, including but not limited to earthquakes, floods, piercing hail, ice, tornadoes, wind, or force majeure. The term "normal use" as used herein does not include, among other things, the exposure of seams to harmful chemicals, abuse of seams by machinery, equipment, or people, excessive pressure from any source, or strain from any source. Any claim for any alleged breach of this warranty must be made in writing to the President of Colorado Lining lnternational, by certified mail, within thirty (30) days after the alleged defect is first noticed. Should the required notice not be given, the defect and all warranties shall be deemed to have been waived by the purchaser and purchaser shall have no right of recovery against Colorado Lining lnternational. ln the event said repairs are to be effected, said repairs shall not be due until the area subject to repair is in a clean, dry, unencumbered condition. This includes but is not limited to the area available for repair to be free from all water, dirt, sludge, residuals and liquids of any kind. I hereby state that I have read and understand the above and foregoing Limited Warranty and agree to such by signing hereunder Zati^ ACCEPTED COLOMDO LINING INTERNATIONAL: I I t I I i I I I I t I I I .I I I I I t I I T I Appendix G Liner Installation Drawing I T T T I