HomeMy WebLinkAboutDAQ-2025-000215
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144820 • Salt Lake City, UT 84114-4820
Telephone (801) 536-4000 • Fax (801) 536-4099 • T.D.D. (801) 903-3978
www.deq.utah.gov
Printed on 100% recycled paper
State of Utah
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF AIR QUALITY
Bryce C. Bird
Director
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
DAQC-005-25
Site IDs: 100443, 6987, 8314, 101603, 101006, 4683, 100907, 101734,
101858, 101768, 101623, 101855, 101621, 101738, 8071,
14399, 101854, 102096 (B4)
Jennifer McQueen
Javelin Energy Partners Management, LLC
5221 North O'Conner Boulevard, Suite 1100
Irving, TX 75039
Dear Ms. McQueen:
Re: Javelin Energy Partners Management, LLC – 8-25-26-C5-3H MWF; Lake Fork Ranch 4-
26-25-B4-4H MWF; Lake Fork Ranch 4-35-36-B4-1H MWF; Presbytery 1-15-16-C4-1H
MWF; Remund 1-27-28-C4-1H MWF; 8-24-23-C5-2H MWF; Betts 1-34-33-C4-2H
MWF; IWM 8/7-17/18-C4-1H; NORTH MOON 1; Park City 5-6-5-C4-3H MWF;
Remund Ridge 16-22-21-C4-7H MWF; SOUTH MOON 05-31-32-C4-4H; Bluebell 16-
24-23-C5-9H MWF; Ferrarini 12-26-25-B4-6H MWF; Goergen 9-13-14-C5-3H MWF;
Hutchins-Chiodo 3-20C5; LFR SOUTH 27-28 B4; OLSEN 13-14-C5 MULTI-WELL
FACILITY – Protocol Review and Test Date Confirmation – Duchesne County, UT
The testing protocol for (4) Caterpillar G3508, (4) Caterpillar G3516, (4) Waukesha 3524GSI, (2)
Cummins KTA19GCE, (1) Caterpillar G3306B TA/LCR, (1) Waukesha 5794GSI, and (2)
Cummins KTA19 engines at 8-25-26-C5-3H MWF; Lake Fork Ranch 4-26-25-B4-4H MWF;
Lake Fork Ranch 4-35-36-B4-1H MWF; Presbytery 1-15-16-C4-1H MWF; Remund 1-27-28-C4-
1H MWF; 8-24-23-C5-2H MWF; Betts 1-34-33-C4-2H MWF; IWM 8/7-17/18-C4-1H; NORTH
MOON 1; Park City 5-6-5-C4-3H MWF; Remund Ridge 16-22-21-C4-7H MWF; SOUTH
MOON 05-31-32-C4-4H; Bluebell 16-24-23-C5-9H MWF; Ferrarini 12-26-25-B4-6H MWF;
Goergen 9-13-14-C5-3H MWF; Hutchins-Chiodo 3-20C5; LFR SOUTH 27-28 B4; OLSEN 13-
14-C5 MULTI-WELL FACILITY in Duchesne County, UT, dated December 22, 2024, has been
reviewed and found acceptable. The agreed upon test dates are the January 27-29, 2025, February
3-7, 2025, and February 17-21, 2025, test campaigns.
+ 2 / 6 à Û Ù Û Þ
DAQC-005-25
Page 2
Acceptance of a protocol does not relieve the owner/operator and the testing contractor from strict
adherence to all applicable EPA methods, Utah Division of Air Quality (DAQ) policies, Utah Air
Quality Rules (UAQR), and methods approved by the Director. Any deviation from EPA
methods, DAQ policies, UAQR, and methods approved by the Director must be addressed
separately and express written consent given prior to commencement of testing.
The DAQ requires that all test reports include a statement that:
A. Testing was conducted while the source was operating at the rate and/or conditions
specified in the applicable approval order, operating permit, or federal regulation.
B. During testing, the source combusted fuels, used raw materials, and maintained
process conditions representative of normal operations, and operated under such
other relevant conditions specified by the Director.
C. Based on information and belief formed after reasonable inquiry, the statements
and information contained in the report are true, accurate, and complete.
If you have any questions, call me at (385) 232-4132 or e-mail me at pgbushman@utah.gov.
Sincerely,
Paul Bushman, Environmental Scientist
Division of Air Quality
PB:jl
cc: TriCounty Health Department