HomeMy WebLinkAboutDERR-2025-000464
CONCRETE ACM INSPECTION WORK PLAN
AIRPORT WEST VCP
Prepared for:
Stantec
2890 East Cottonwood Parkway #300
Salt Lake City, Utah 84121
NT Development
1700 South 4650 West
Salt Lake City, Utah 84104
October 23, 2024
Revised December 4, 2024
Prepared by:
Audra Heinzel
Utah-Certified Project Designer (ASB-3952)
Wasatch Environmental, Inc. (ASBC-169)
2410 West California Avenue
Salt Lake City, Utah 84104
Concrete Inspection Work Plan Airport West VCP
Wasatch Environmental, Inc. Table of Contents
Page i
TABLE OF CONTENTS
Section Page No.
1. INTRODUCTION ............................................................................................................................................. 1
1.1 Site Location and Description ............................................................................................. 1
1.2 Background ......................................................................................................................... 1
2. CONCRETE CRUSHING OPERATIONS AND OVERSIGHT .......................................................................... 2
3. OVERSIGHT TIMELINE AND DURATION ...................................................................................................... 3
4. REPORT .......................................................................................................................................................... 3
Figures
Figure 1 – Property Map
Figure 2 – 2007 Aerial Photograph
Figure 3 – 2008/2009 Aerial Photograph
Figure 4 – 2010 Aerial Photograph
Figure 5 – Work Plan Map
Appendices
Appendix A – 2024 Asbestos Survey Report
Concrete Inspection Work Plan Airport West VCP
Wasatch Environmental, Inc. Page 1
1. INTRODUCTION
The Airport West Voluntary Cleanup Program (VCP) site (Property) is listed as VCP Site #C092 and
includes the former North Temple Landfill (NTL). The NTL is a closed municipal landfill that was operated
by Salt Lake City Corporation from 1959 until 1979. This work plan (Work Plan) is for the inspection of
concrete product for suspect asbestos-containing materials (ACM) during preparation of the concrete for
crushing. The concrete is situated in a pile located on the western portion of the Property at the northwest
corner of 7200 West and Interstate 80 (I-80).
1.1 Site Location and Description
The North Temple Landfill site is located between downtown Salt Lake City and the Great Salt Lake,
along I‐80 on the North Temple Frontage Road approximately 6100 West and 7500 West, within the
northwest portion of Salt Lake County, Utah. The portion of the landfill where the concrete pile is located
is the western portion. The concrete pile occupies approximately 14 acres.
1.2 Background
The NTL is a closed municipal landfill that was operated by Salt Lake City Corporation between 1959 and
1979. During its operation, waste was deposited in shallow trenches and when filled, covered with native
soil. The landfill operation began in the eastern portion of the landfill and moved west as the landfilling
operation extended across the site. During the life of the landfill, the site received the majority of Salt Lake
City’s municipal waste stream. After Salt Lake City closed the landfill in 1979, the Property lay fallow. The
Property was previously owned by Suburban Land Reserve (SLR), an entity of the LDS Church. In 2017,
Utah’s School and Institutional Trust Land Administration (SITLA) obtained title from SLR to a 770-acre
parcel that encompasses the footprint of old landfill. SITLA’s plan has been to redevelop the Property and
enhance the Trust Fund for its stated beneficiaries (Permanent School Fund).
The concrete product pile consists of approximately 250,000 cubic yards of recycled concrete spread
over approximately 14 acres. The concrete pile lies atop a portion of the former NTL with known soil and
groundwater impacts. As part of the VCP investigation and remedial activities, the concrete pile must
be moved to provide access for additional soil and groundwater investigation, installation of
groundwater monitoring wells, and planned remediation activities. NT Development (SITLA’s
remediation contractor) plans to have the concrete crushed onsite. A portion of the crushed concrete
will be used as backfill and for roads during Airport West remedial activities. Furthermore, a portion of
the crushed concrete will be sold to the general public for commercial development, roadways, etc.
The concrete was placed on the Property around 2007 and originates from building foundations and
parking structures demolished in anticipation of the development of the City Creek Shopping Center in
Salt Lake City. IHI Environmental conducted pre-demolition asbestos surveys for all of the demolished
structures and SLR, the developer of City Creek and the former Property owner, agreed to stage the
concrete from the demolition on the Property. Each truck load of concrete demolition product was
reported as certified by IHI Environmental as asbestos free prior to being dumped on the Property.
However, SLR has not been able to locate the pre-demolition ACM surveys, asbestos-abatement
documentation, nor the IHI Environmental certifications. This Work Plan identifies concrete crushing
oversight activities intended to confirm the previous pre-demolition surveys and identify any suspect
ACM.
During a site visit with the Utah Division of Air Quality Air Toxics Lead and Asbestos group (UDAQ
ATLAS), suspect ACMs were observed on the surface of the concrete pile. Given the unavailability of
prior asbestos survey documentation, Stantec and Wasatch Environmental, Inc., (Wasatch) Utah-certified
asbestos inspectors performed, and asbestos survey of the suspect materials observed on the top of the
concrete pile in September 2024. A copy of the survey is presented as Appendix A. For the purposes of
the survey, the pile was divided into 8 Sectors (see Figure 1) and a total of 89 bulk material samples were
collected from 33 homogeneous materials observed which included epoxy coatings, conduit wrap, roofing
materials, resinous materials, stair tread and other flooring, carpet, tar, fabrics, insulation materials,
Concrete Inspection Work Plan Airport West VCP
Wasatch Environmental, Inc. Page 2
wrapped wiring, leveling compounds, plaster, and other miscellaneous materials. The suspect materials
represent approximately 1% of the concrete product on the Property.
No asbestos content was identified in the samples collected with the exception of three samples of a
malleable royal blue/grey coating. Laboratory analysis identified between 2% and 5% Chrysotile asbestos
in this coating material. The three pieces of this material were observed in Sector 2 of the overall concrete
pile. There was approximately 1-square-foot of this material present. This material is a Category II non-
friable material that would potentially become friable if run through the concrete crushing unit.
Placement of the concrete on the Property began in 2007 as evidenced in the 2007 aerial photograph
presented as Figure 2. By 2008/2009 the majority of the current material was present. The 2007,
2008/2009, and 2010 aerial photographs (Figures 2, 3, and 4) provide a general idea of how the concrete
product was placed as it was brought onto the Property with placement beginning on the southeastern
portion and moving to the west and north. Segregated wind rows and piles can be seen in Sectors 1
through 5 on the 2010 aerial photograph. Based on the aerial photographs, information provided to us by
NT Development, and our observations during the September 2024 asbestos survey, the truck loads from
each building were placed in the same piles as they were received as opposed to being randomly spread
across the Property. Therefore, we have concluded that the asbestos-containing coating is isolated to
Sector 2.
2. CONCRETE PREPARATION AND INSPECTION ACTIVITIES
Prior to preparation of the concrete product for crushing, a concrete crusher will be assembled in the
east-central area of the concrete pile (see Figure 5). During construction of the crusher, a bulldozer(s) will
be used to create access roads through the pile by pushing the concrete product into place. Water will be
used for dust suppression during these initial operations. Concrete product preparation activities will then
move to the southwest corner of the Property and consist of pushing the concrete product into 3 to 4-foot-
tall windrows. Water will be used for dust suppression on the Property during preparation and crushing
operations in accordance with all applicable UDAQ regulations. The dust suppression will be performed
by spraying water using a water truck or other means over the concrete as it is being moved to knock
down visible dust. During concrete product preparation activities, a Wasatch and/or Stantec Utah-certified
asbestos inspector(s) will be onsite observing the concrete product being turned over, providing visual
inspection of the underlying concrete product. A risk management check list with emergency plans as
needed will be prepared for inspection personnel and will be reviewed at daily site meetings.
The certified inspector(s) will be staged at a safe distance from the bulldozer(s), but in a location that the
inspector can observe the concrete product being turned over. Binoculars may be used for this purpose.
In addition to certified asbestos inspectors observing these operations, equipment operators will have
completed two-hour Occupational Safety and Health Administration (OSHA) asbestos awareness training
to be able to identify suspect ACMs. Once several windrows have been created, and the inspector can
safely inspect the windrows up close, the inspector will observe the concrete for the presence of suspect
ACM not sampled or identified during the September asbestos survey. A photographic log of all materials
sampled during the asbestos survey is presented in the survey report for reference and will be kept
onsite. Once the inspector(s) has cleared a windrow, the bulldozer will push the windrow concrete product
into a crusher feed stockpile (up to 20 feet tall). Periodically (no less than twice a day), during the
concrete product preparation work shift, the crusher feed stockpile will be inspected for the presence of
suspect ACM not previously sampled or identified. A front-end loader will then transfer the concrete
product from the crusher feed stockpile to the concrete crusher. Sector 2 will be the last area inspected
for clearance during the overall concrete crushing operation.
In the event that suspect ACM not previously observed is encountered during windrow preparation or
crusher feed stockpile inspection, the inspector will communicate with the bulldozer or front end loader
operator that the windrow or stockpile is not clear of suspect ACM. The windrow or portion of the
stockpile will be marked with signage typical of traffic controls to clearly communicate visually the
windrow/portion of the stockpile has not been cleared for crushing. The inspector will then enter the work
area to investigate the material. If it is determined by the inspector that the material is indeed a new
Concrete Inspection Work Plan Airport West VCP
Wasatch Environmental, Inc. Page 3
homogeneous material, the inspector will direct the bulldozer or front end loader to cease working in that
area and move to another location to continue operations.
The inspector will take a clear representative photograph of the material, log the samples in their daily
field notes, then collect a minimum of two samples per homogeneous material unless it’s a surfacing
material which will be sampled in accordance with the Utah Asbestos Rule, 3-5-7 sampling protocol. The
samples will be delivered under chain of custody to Dixon Information, a NVLAP-certified laboratory, for
analysis using visual estimation with the use of polarized light microscopy (PLM) according to EPA 600/R-
93-116 on an afterhours laboratory turnaround.
The photograph of the material and analytical results will be added to the log of materials previously
sampled. If sample results indicate that the material is asbestos containing (>1% asbestos), and is non-
friable, a backhoe will be utilized to determine extent and quantity of the ACM in the work area concrete
product. The concrete product with the ACM will then be transported to a designated staging area (see
Figure 5). The staging area will then be delineated with red tape or signage stating that the concrete
product in that area is asbestos containing.
If friable ACM is encountered, the concrete product/crusher feed pile in that area will be thoroughly
wetted, covered with polyethylene sheeting, and delineated with caution tape and the UDAQ will be
notified. A licensed asbestos abatement contractor will be retained for abatement operations. All
abatement activities will be performed in accordance with Utah Asbestos Rule (R307-801) and 40 CFR
Part 61 NESHAP Subpart M National Emission Standard for Asbestos. Abatement activities are beyond
the scope of this work plan and are not discussed further.
In Sector 2, where the known ACM royal blue/grey coating has been observed, a backhoe will be used to
segregate pieces of concrete and any other product that might be present from the pile. A certified
inspector will observe these operations for pieces of the ACM coating, or any other suspect materials not
previously observed and/or sampled. Given the bright royal blue color of the material, it is easily
identifiable. The pieces of concrete will be stockpiled for transfer to the crusher. If at any time the ACM
coating is observed, the backhoe will collect the material and surrounding concrete product into the
bucket and transport it to an established ACM staging area or create a new ACM staging area.
Segregation may then continue until all concrete product free of the ACM coating has been stockpiled.
Given the background and nature of the Property, all staged concrete product with ACM will remain
onsite. The concrete product will eventually be moved to the Airport West debris repository, which is
described in detail in the November 8, 2022, Project Design Contingency Plan for the Airport West VCP
and the August 2022 Phase I Area Remedial Action Plan (RAP). The repository will be located
approximately 0.6 miles east of the Property within the boundaries of the NTL. No asbestos-containing
material will be disposed outside the NTL boundaries.
3. OVERSIGHT TIMELINE AND DURATION
The concrete crushing operation is expected to take four months to complete. During the first four weeks
of operation, a Utah-certified asbestos inspector(s) will be onsite during the preparation of the concrete
for delivery to the crusher. If after four weeks no additional suspect ACM has been identified in the
windrows, oversight will be reduced to morning site visits to inspect windrows created the day before.
Daily inspection logs will be completed that will document the date and time of inspection, inspector, a
photographic log, and a hand drawn map of the windrows approved/not approved for crushing. As work
involves Sector 2, a certified asbestos inspector(s) will again be staged onsite during concrete product
preparation for crushing. Once preparation of the concrete product has been completed and the concrete
product has been cleared for crushing, ACM inspection activities will be concluded. . If equipment
operators encounter suspect ACM, work will stop in that area and a certified asbestos inspector will be
contacted to inspect the material.
4. REPORT
Concrete Inspection Work Plan Airport West VCP
Wasatch Environmental, Inc. Page 4
After the ACM inspection activities are concluded, a report will be produced that will include a narrative of
the crushing operations and oversight, a description of additional suspect homogenous materials sampled
(if any) including the estimated quantity and material condition, sampling protocol, location of any
concrete product with asbestos-containing materials remaining on the Property, quantity of remaining
product, final disposition of the remaining product, and final disposition and quantity of crushed concrete
product; sample location figure(s); daily inspection/field logs; photographs; analytical reports and chain-of-
custody documentation (if any); asbestos inspector certifications; and equipment operator training
certificates. A copy of the final report will be submitted to the UDAQ project manager within 30 days of
crushing operations ceasing.