HomeMy WebLinkAboutDERR-2024-005069
Cathodic Protection of POL Systems
2022 Annual Survey & Repairs
Dugway Proving Ground
Dugway, Utah
DLA-Energy Identifier DUG 22-CP
Contract No. W912HP-21-D-5000
Task Order No. W912HP22F5004
Submitted to:
U.S. Army Corps of Engineers
Charleston District
69A HAGOOD AVENUE
CHARLESTON, SC, 29403
Prepared By:
6445 Marindustry Drive
San Diego, California 92121
Survey October 24th – 25th, 2022
Draft Report November 21st, 2022
Final Report December 12th, 2022
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 i DUG 22-CP
Table of Contents
Page
1.0 Introduction ........................................................................................................... 1
1.1 Reference Standards and Documents ............................................................... 1
1.2 Acronyms and Abbreviations.............................................................................. 2
2.0 Executive Summary .............................................................................................. 3
3.0 Points of Contact .................................................................................................. 4
3.1 Corrpro Project Team ......................................................................................... 4
3.2 Activity Personnel ............................................................................................... 4
4.0 DLA-Energy Fuel Facility Descriptions ................................................................. 6
4.1 Bulk Fuels Storage ............................................................................................. 6
4.2 Motor Pool Facilities ......................................................................................... 12
5.0 Test Procedures ................................................................................................. 15
6.0 Findings .............................................................................................................. 17
6.1 Bulk Fuels Storage ........................................................................................... 17
6.2 Motor Pool ........................................................................................................ 17
7.0 Recommendations .............................................................................................. 19
7.1 Site Wide .......................................................................................................... 19
8.0 Points of Contact ................................................................................................ 20
Appendices
A. Survey Data Sheets
B. CP Drawings
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 1 DUG 22-CP
1.0 Introduction
The Defense Logistics Agency - Energy (DLA-Energy) through the U.S. Army Corps of
Engineers, Charleston District, contracted Corrpro to conduct cathodic protection (CP)
surveys. This CP survey includes all DLA-Energy capitalized assets for petroleum, oil,
and lubricant (POL) storage and distribution at Dugway Proving Ground, Tooele County,
UT. The intent of this survey is to determine: the condition of existing CP systems; if DLA-
Energy fuel transfer and storage assets meet NACE International criteria for CP; and if
any structures require a new system or upgrade to an existing CP system.
Mr. Brooks Bucher is Corrpro’s project manager. The survey was conducted during
October 24 and 25, 2022, by NACE certified Senior Corrosion Technologist Mahsa
Bakherad and NACE Certified Cathodic Protection Technician Alex Rosen. This report
has been prepared by Mahsa Bakherad and reviewed by Yash Mir, NACE certified CP
Specialist.
Lead Project Engineer: Mahsa Bakherad - Corrpro – Senior Corrosion Engineer
6445 Marindustry Drive, San Diego, CA 92121
Office: (858) 824-1992
1.1 Reference Standards and Documents
Unified Facilities Criteria UFC 3-570-06 – “Operation and Maintenance:
Cathodic Protection Systems”
Unified Facilities Criteria UFC 3-570-01 – “Cathodic Protection”
NACE International Standard Practice SP0193-2016 – “External Cathodic
Protection of On-Grade Carbon Steel Storage Tank Bottoms”
NACE International Standard Practice SP0285-2021 – “External Corrosion
Control of Underground Storage Tank Systems by Cathodic Protection”
NACE International Standard Practice SP0286-2007 – “Electrical Isolation of
Cathodically Protected Pipelines”
NACE International Standard Test Method TM0101-2012 – “Measurement
Techniques Related to Criteria for Cathodic Protection on Underground or
Submerged Metallic Tank Systems”
Steel Tank Institute Standard STI-P3 – “sti-P3 Specification and Manual for
Steel Tank Institute R051 – “Cathodic Protection Testing Procedures for sti-
P3 USTs”
Steel Tank Institute Standard STI-F894 – "ACT-100 Specification for External
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 2 DUG 22-CP
Corrosion Protection of FRP Composite Steel Underground Storage Tanks"
Steel Tank Institute Standard STI-F961 – "ACT-100U Specification for
External Corrosion Protection of Composite Steel Underground Storage
Tanks"
American Petroleum Institute API 653 – “Tank Inspection, Repair, Alteration,
and Reconstruction”
49 CFR 192.467 - External Corrosion Control: Electrical isolation
Army Corp of Engineers – EM 385-1-1 – “Safety and Health Requirements
Manual”
1.2 Acronyms and Abbreviations
AST Aboveground Storage Tank
CP Cathodic Protection
CSE Copper-Copper Sulfate (Reference Electrode)
DLA-Energy Defense Logistics Agency-Energy
HSCI High Silicon Cast Iron
ICCP Impressed Current Cathodic Protection
MOGAS Motor Gasoline
MMO Mixed Metal Oxide
NACE NACE International (Formerly the National Association of Corrosion Engineers)
POL Petroleum, Oil, and Lubricant
RMU Remote Monitoring Unit
S/E Structure-to-Electrolyte
USACE US Army Corps of Engineers
UST Underground Storage Tank
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 3 DUG 22-CP
2.0 Executive Summary
The scope of work consisted of the annual cathodic protection survey and repairs for the
DLA-Energy capitalized fuel facilities.
Table 1 – List of Accomplished Repairs
Item
No. Structure(s) Repair Item Status of Repair
1 Site Wide Conduct 2022 Annual CP Survey
Completed
(October 2022)
Table 2 – List of Recommended Repairs from 2022Survey
Item
No. Structure(s) Recommendation Refer to
Page(s)
Estimated
Cost
1 Site Wide Conduct Annual CP Survey in 2023 19 N/A
TOTAL: $ 0
.
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 4 DUG 22-CP
3.0 Points of Contact
3.1 Corrpro Project Team
Table 3 – Corrpro Project Team
Name Role Email Telephone
Jeremy
Bouknight
Operations/
Program Manager jbouknight@aegion.com 858-824-1992
Brooks Bucher Engineering Manager bbucher@aegion.com 858-824-1992
Alex Rosen Corrosion Technician
II arosen@aegion.com 858-824-1992
Mahsa
Bakherad
Senior Corrosion
Engineer mbakherad@aegion.com 858-824-1992
Yash Mir QC Reviewer yashmir@aegion.com 858-824-1992
3.2 Activity Personnel
Table 4 – Dugway Proving Ground, USACE, and DLA Energy Personnel
Name Contact Information
Mr. Gary Morgan
Fuels Department
English Village Fuels
Office: (435) 831-2968
Email: gary.a.morgan14.civ@mail.mil
Ms. Carolann Uttech
Plans and Operations Chief
Logistics Readiness Center
407th AFSB, Army Sustainment Command
Office: (435) 831-2679
Email: carolann.j.uttech.civ@mail.mil
Mr. Troy Christensen
Airfield Area Operation
Manager
Ditto Area Fuels
Office: (435) 831-7067
Email: troy.m.christiansen3.ctr@army.mil
Mr. Charles Nelson
Program Manager
DLA Energy SRM Division
Email: Charles.D2.Nelson@DLA.mil
Mr. Randy Adams
Facilities Team Lead
U.S. Army Petroleum Center
Office: 571-767-1779
Email: randy.l.adams4.civ@army.mil
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 5 DUG 22-CP
Name Contact Information
Mr. Ok Kim
General Engineer
U.S. Army Petroleum Center
Office: 571-767-0173
Email: ok.k.kim.civ@army.mil
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 6 DUG 22-CP
4.0 DLA-Energy Fuel Facility Descriptions
The DLA-Energy capitalized fuel facilities at Dugway Proving Ground are in four
geographical locations: Bulk Fuels Storage English Village, Bulk Fuels Storage Ditto,
Motor Pool Facility 5469, and Motor Pool Facility 4315.
Bulk Fuels Storage - English Village
o Two 125,000-gallon diesel fuel On-grade ASTs: Facility 5660 and 5661
Bulk Fuels Storage - Ditto
o Two 25,000-gallon Jet A fuel On-grade ASTs: Facility 4056 and 4057
Motor Pool - Facility 5469 (Close to English Village Area)
o UST Diesel
o UST MOGAS
o Diesel and MOGAS fuel dispensers
Motor Pool - Facility 4315 (Close to Ditto Area)
o UST diesel
o UST MOGAS
o Diesel and MOGAS fuel dispensers
4.1 Bulk Fuels Storage
English Village Area
Above Ground Storage Tanks (ASTs) 5660 and 5661 are each 25-foot diameter on-grade
ASTs with a nominal capacity of 125,000 gallons containing diesel fuel. The facility
drawings, as shown in Appendix B, indicate the tanks are constructed with a concrete
ring wall foundation. The tanks have individual earthen berms covered by a flexible
containment liner as seen in Figure 1.
Figure 1 – AST 5660 & AST 5661 and Aboveground Fuel Pipes
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 7 DUG 22-CP
The exterior surfaces of the steel plates under ASTs 5660 and 5661 receive corrosion
control from a single ICCP system installed in 2009, see Figure 2. This ICCP system for
both tank bottoms is powered by one 50-volt / 5-amp air-cooled; voltage tap-adjust
rectifier. Adjacent to the rectifier is an Elecsys Watchdog Scout RMU which can
additionally be used to interrupt the system. A three-circuit MMO anode ground bed
installed between the tank floor and the dielectric liner is 0.118-inch diameter MMO anode
wire installed in a loop pattern. Three stationary copper-copper sulfate reference
electrodes (CSEs) were installed under each tank bottom. Lead wires from the MMO
anodes and CSEs terminate in an anode/testing junction box located adjacent to the
RMU, see Figure 3. The drawings in Appendix B illustrate the layout of the ICCP system.
Figure 2 – English Village Rectifier (left) and RMU (right)
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 8 DUG 22-CP
Figure 3 – English Village AST 5660 & AST 5661 ICCP System Junction Box
Fuel is distributed to and from the tanks via truck racks located on the north and east
sides of the fuel farm facility. The issue and receipt piping connecting ASTs 5660 and
5661 to truck stands are 4 inches in diameter, stainless steel, and aboveground, except
for cased sections through the earthen containment berm, see Figure 4. The fuel-carrying
piping is not in contact with soil and therefore does not require CP.
Figure 4 – Aboveground 4-inch Pipe in Casing Through Earthen Berm
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 9 DUG 22-CP
Ditto Area
Tanks 4056 and 4057 in the Ditto Area are 14-foot diameter on-grade Jet A fuel ASTs,
each with a nominal capacity of 25,000 gallons, see Figure 5. Each tank rests on a
concrete ring wall foundation containing a sand pad surrounded by a vertical concrete
containment wall. There is no secondary containment liner beneath either tank.
Figure 5 – AST 4056 & 4057 and CPTS on White PVC Posts
Fuel piping connects a truck stand to filter pumphouse 4055 and the AST’s. This 4-inch
diameter fuel piping is aboveground and does not require CP.
An ICCP system, installed in 2008, provided corrosion control to the tank bottom of ASTs
4056 and 4057. The 10-volt/15-amp air-cooled rectifier installed in 2008 was replaced
with a 40-volt/42-amp air-cooled rectifier in 2018 (shown in Figure 6). The rectifier is
equipped with a Watchdog Scout RMU with interruption capabilities. This rectifier
powered by a distributed vertical anode groundbed with six tubular high silicon cast iron
canister anodes (HSCI). This anode groundbed was found non-operational in 2019 and
is no longer providing CP current.
In June 2022, a new distributed anode groundbed was installed around the outside of the
containment area. The new groundbed consists of eight, 12-ft deep holes each containing
one 70-lbs (84-inch long by 2.7-inch diameter) tubular HSCI anode with No.8 HMWPE
wire in an active column of 10-ft filled with SC-3 Loresco coke breeze. The anode holes
are located around the ASTs enclosure with two on the east side, two on the west side,
and four on the south side which can be seen in Figure 7. Lead wire from each of the
anodes are routed to a new anode junction box adjacent to the rectifier (see Figure 8).
The as-built drawings provided in Appendix B.
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 10 DUG 22-CP
Figure 6 – Ditto Rectifier
Four post-mounted CP test stations are located around each tank. Each test station
contains a structure lead wire and a stationary CSE lead wire. The stationary CSE’s are
situated 2 feet below grade, directly under the test station.
Figure 7 – Anode Groundbeds South of the Containment Area
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 11 DUG 22-CP
Figure 8 – Ditto Area Anode Junction Box
The AC disconnect switch for this ICCP system is not located next to the rectifier and can
instead be found in the front side of the pumphouse as shown in Figure 9 – Ditto Rectifier
AC Disconnect Location
.
Figure 9 – Ditto Rectifier AC Disconnect Location
ICCP System
AC Disconnect
ICCP System AC
Disconnect Switch
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 12 DUG 22-CP
4.2 Motor Pool Facilities
Facility 5469 at English Village
The Motor Pool Facility 5469 contains one diesel UST and one MOGAS UST, each with
dedicated fuel dispensers. This facility is located to the west of Building 5468, near the
English Village area and on Stark Road, see Figure 10.
Figure 10 – English Village Motor Pool Area
UST 1 (MOGAS) was manufactured in 1988, it is 23 feet and 8 inches in length, has a
12-foot diameter, and has a nominal capacity of 20,000 gallons. The tank is constructed
of double-walled steel and contains MOGAS fuel. UST 2 (diesel) was manufactured in
1988, is 26 feet 8 inches in length, has an 8-foot diameter, and has a nominal capacity of
10,000 gallons. The tank is constructed of double-walled steel and contains diesel fuel.
UST 1, containing MOGAS, was manufactured with direct connect galvanic anodes and
in 2018, a supplemental galvanic CP system was installed, which consisted of four 32-
lbs. prepackaged high-potential magnesium anodes, two new structure cables
exothermically welded to the exterior of the tank, and a new test station. A coupon suitable
for IR-free potential measurements is buried near the UST. Wires for the tank test leads,
anode lead, and coupon are terminated in a test station with a 0.1 ohm red Cott shunt for
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 13 DUG 22-CP
anode current measurements. The anodes were installed horizontally on the north and
east sides of the tank at a depth of approximately 8 feet.
UST 2, containing diesel, was manufactured with direct connect galvanic anodes and has
a supplemental galvanic CP system consisting of three magnesium anodes connected to
the tank through a 0.01-ohm RS wire shunt and a dedicated structure connection. The
size and date of installation for the supplemental CP system on UST 2 could not be
confirmed.
There are three soil access ports surrounding each tank for CP measurements.
The underground piping that connects UST 1 and 2 to the fuel dispensers is constructed
of double-walled fiberglass. These nonmetallic pipes do not require CP.
Facility 4135 at Ditto Area
The Motor Pool Facility 4135 consists of two USTs (one for MOGAS and one for diesel
storage). Each UST has a dedicated fuel dispenser located to the north of the tanks. The
facility is located near the Ditto Area off Stark Road on Third Street, as shown in Figure
11.
Figure 11 – Ditto Motor Pool Area
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 14 DUG 22-CP
UST 1 (MOGAS) was manufactured in 1999, is 23 feet 8 inches in length, has a 12-foot
diameter, and a nominal capacity of 20,000 gallons. The tank is constructed of double-
walled fiberglass and contains MOGAS fuel. UST 2 (diesel), manufactured in 1999, is 26
feet 8 inches in length, has an 8-foot diameter, and a nominal capacity of 10,000 gallons.
The tank is constructed of double-walled fiberglass and contains diesel fuel. The
underground piping that connects the USTs to the fuel dispensers is constructed of
double-walled nonmetallic material (EnviroFlex). An overview of this area can be seen in
Figure 12.
Figure 12 – Facility 4135
The USTs and fuel piping are non-metallic, and therefore do not require cathodic
protection. These structures will not be mentioned further in this report.
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 15 DUG 22-CP
5.0 Test Procedures
Testing was performed in accordance with Corrpro test procedures and NACE
International Standard Test Methods. A brief synopsis of the test methods employed
include the following:
Rectifier Inspection – The rectifiers at the facility were assessed for physical and
electrical damage, meter accuracy, and general operating condition. The electrical
disconnect and grounding were inspected to ensure they were in good condition.
Notes were also made about the seasonal condition of the soil (dry, wet, or frozen),
as these parameters can have a marked influence on groundbed operation. Where
rectifier-output monitoring data was available, this was also reviewed to determine
if any tendency for deteriorating performance was evident.
Structure-to-Soil Potential Measurement – Structure-to-electrolyte potential
testing was the primary method used to evaluate cathodic protection levels.
Testing was carried out using a high-impedance voltmeter and a calibrated
portable copper-copper sulfate electrode (CSE) and a stainless-steel contact
probe. To take measurement, the CSE was placed in contact with suitable soil
(electrolyte) overtop or near the structure being examined. A connection was made
to the structure being tested to complete the circuit through the voltmeter. For ICCP
systems, the current from the influencing rectifiers was simultaneously interrupted
to allow IR-free measurements.
Depolarized Potential Measurement – All sources of CP current that affected the
tested structure were left off for at least 24 hours. After that time, a structure-to-
electrolyte potential measurement was taken. This value was then used to calculate
the amount of polarization a structure was receiving.
Anode Current Output – Galvanic anode current output was calculated by
measuring the IR-drop across a permanent shunt of known resistance, installed in
series with the anode and applying Ohm’s Law. The same method was used for
impressed current anode circuits or an amp clamp instrument was used to
measure direct current.
Electrical Isolation – Many CP systems rely on effective electrical isolation for
correct operation. Flange electrical isolation was verified using potential
measurements on both sides of the isolation and using a Gas Electronics Flange
Isolation Checker to identify faulty hardware.
Impressed Current CP (ICCP) System Assessment – Five parameters were
evaluated to assess CP on assets protected by ICCP systems:
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 16 DUG 22-CP
o Rectifier performance
o Groundbed performance (resistance, anode output and soil condition)
o Structure-to-soil on or energized potential
o Structure-to-soil instant-off or polarized potential
o Structure-to-soil depolarized or native potential
Galvanic CP System Assessment – Six parameters were evaluated to assess
CP on assets protected by Sacrificial Anode Cathodic Protection Systems:
o Anode current output (collective and/ or individual)
o Open Circuit Potential (OCP) of the anode(s)
o Structure-to-soil On or energized potential
o Structure-to-soil Instant-off or polarized potential
o Structure-to-soil depolarized or native potential
o Effectiveness of installed electrical isolation kits and fittings.
Rectifier data, potential measurement data, and all other relevant survey data are
included in Appendix A. The cathodic protection systems’ effectiveness was determined
by evaluating these data with respect to NACE International criteria and the other
referenced standards.
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 17 DUG 22-CP
6.0 Findings
6.1 Bulk Fuels Storage
English Village
The rectifier was found in good condition and operating at 9.33 volts and 2.37 amps. Each
of the six anode circuits under the two ASTs was discharging a protective current. The
RMU unit was in good condition and operational.
The measured S/E potential data indicated both ASTs 5660 and 5661 were receiving an
adequate level of cathodic protection meeting the NACE International SP0193-2016,
“100 mV of cathodic polarization” criterion.
The calculated cathodic protection current densities for tank bottoms 5660 and 5661 are
2 and 2.5 mA/ft2 respectively. Cathodic protection current densities for AST bottoms are
typically in the range of 0.5 to 1.0 mA/ft2.
The testing data is tabulated in Appendix A.
Ditto Area
The rectifier was found in good condition and operating at 6.09 volts and 30.7 amps. The
newly installed anode groundbed in June 2022, was effective and each of the eight
anodes was discharging CP current, as designed. The RMU unit was in good condition
and operational.
Tank S/E potential measurements were measured at the test stations located at the
ASTs. Potential data indicates both AST 4056 and 4057 were receiving an adequate level
of CP, meeting the NACE International SP0193-2016, “100 mV of cathodic polarization”
criterion.
The testing data is tabulated in Appendix A.
6.2 Motor Pool
Facility 5469 at English Village
Both the diesel and Mogas USTs are electrically isolated from each other and have their
own respective galvanic CP system. Each UST has its respective test station which
houses lead wires for the anodes and the tank structure connection. The lead wires are
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 18 DUG 22-CP
connected through a 0.1-ohm wire shunt for MOGAS UST and a 0.01-ohm wire shunt for
Diesel UST. See Figure 13 and Figure 14.
Figure 13 – MOGAS UST Test Station
Figure 14 – Diesel UST Test Station
MOGAS UST
The S/E “Off” potentials were measured at north, south, and east through the soil access
ports for this UST. The measured data indicates the UST was receiving an adequate level
of CP meeting “a negative polarized potential of at least -850 mVCSE” per NACE SP0285-
2021. The measured current output of the CP system was about 3.6 mA. All four galvanic
anodes were still efficient and were providing CP current to the target structure. The
potential measurement on the electrical grounding indicates this tank was electrically
isolated from the electrical grounding. The testing data is tabulated in Appendix A.
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 19 DUG 22-CP
DIESEL UST
The S/E “Off” potentials were measured at north, south, and west through the soil access
ports for this UST. The measured S/E “Off” potentials around the diesel UST satisfied the
NACE SP0285-2021 CP criterion of -850 mVCSE or more negative polarized potential for
receiving adequate CP. The measured current output of the CP system was about 2.2
mA. Potential testing data indicates the UST was electrically isolated from the grounding
system. One of the four galvanic anodes was depleted and its lead wire was taped and
left disconnected from the terminal board. The rest of the anodes were effective. The
testing data is tabulated in Appendix A.
7.0 Recommendations
7.1 Site Wide
Perform annual CP survey in 2023.
Dugway Proving Ground
2022 Annual Survey
Corrpro Project 340532208 20 DUG 22-CP
8.0 Points of Contact
Any questions concerning this technical report should be addressed to:
Mahsa Bakherad
NACE CP Specialist #67428
6445 Marindustry Drive, San Diego, California 92121
Office: (858) 824-1992
Email: mbakherad@aegion.com
Questions concerning the contractual aspects of this work should be addressed to:
Corrpro Companies, Inc., San Diego:
Brooks Bucher
NACE CP Specialist #27931
Engineering Manager
6445 Marindustry Drive, San Diego, California 92121
Office: (858) 824-1992
Email: bbucher@aegion.com
U.S. Army Corps of Engineers, Charleston District:
Edwin D. Piedmont, P.E.
NACE CP Specialist #8639
CESAC Cathodic Protection Program Manager
69A Hagood Avenue, Charleston, South Carolina 29403-5107
Office: (843) 329-8127
Email: edwin.d.piedmont@usace.army.mil
U.S. Army Corps of Engineers, Charleston District:
Carole Works
COR and Chief of Engineering
69A Hagood Avenue, Charleston, SC 29403-5107
Office: (843) 329-8194
Email: carole.a.works@usace.army.mil
A-1
APPENDIX A
SURVEY DATA SHEETS
English Village - AST 5660 and AST 5661
Appendix A
Rectifier ID:Date Tested:
Target Structure:Tested By:
Rectifier Location:North Side of East Village Pumphouse Test Meter Info:
Weather Info:
Manufacturer:Universal Model:ASAI Date Installed:2009 Total Steps:
Input AC Volt:115/230 AC Current:3.1/1.5 Serial No:092945 C: 1-3 / F: 1-6
Output DC Volt:50 Volts Output DC Current:5 Amp Input AC Phase:Single AC Set On:
RMU model:Watchdog SCOUT RMU Serial No:56221-0017 RMU Location:Right Side of Rectifier 115 Volts
Type:Type:
Year Built:Anode Mtrl.:
Diameter:No. of Anodes
Tank Contents:Anode Shunts:50 mV 50 Amp
Panel Meter Measured Tap Setting
Circuit # Reading (mV) Current (Amp)
Voltage Output (V) 9 Volts 9.33 Volts C: 1 / F: 3 Tank 5660 A-1
2.08 0.21
Current Output (A) 2.6 Amps 2.37 Amps Tank 5660 A-2 4.06 0.41
Shunt Reading (mV) 23.7 mV Tank 5660 A-3 3.53 0.35
Total Tank 5660 n/a 0.97
Tank 5661 A-1 3.91 0.39
Tank 5661 A-2 5.22 0.52
50 mV / 5 Amps Tank 5661 A-3 3.14 0.31
Tap AC Voltage:Total Tank 5661 n/a 1.23
Panel Meter Measured Tap Setting
Circuit # Reading (mV) Current (Amp)
Voltage Output (V) 9 Volts 9.33 Volts C: 1 / F: 3 Tank 5660 A-1
2.08 0.21
Current Output (A) 2.6 Amps 2.37 Amps Tank 5660 A-2 4.06 0.41
Shunt Reading (mV) 23.7 mV Tank 5660 A-3 3.53 0.35
Total Tank 5660 (Tank 1) n/a 0.97
Tank 5661 A-1 3.91 0.39
Tank 5661 A-2 5.22 0.52
50 mV / 5 Amps Tank 5661 A-3 3.14 0.31
Tap AC Voltage:Total Tank 5661 (Tank 2) n/a 1.23
Stationary Cells1 ON (mV)iOFF (mV)Native/Depol2 (mV)Polarization (mV)
Tank 5660 (Tank1) C-1 -1523 -436 -237 199
C-2 -6366 -995 -543 452
C-3 -2150 -684 -439 245
Tank 5661 (Tank2) C-1 -1833 -589 -325 264
C-2 -3576 -872 -525 347
C-3 -2670 -750 -449 301
Date DC Volt DC Amp Tap Setting Tested By
22-Aug-12 9.00 Volts 2.00 Amps C: 1, F: 3 Corrpro
18-Jun-13 9.30 Volts 1.93 Amps C: 1, F: 3 Corrpro
17-Jun-14 9.30 Volts 1.80 Amps C: 1, F: 3 Corrpro
25-Feb-16 9.53 Volts 1.22 Amps C: 1, F: 3 Corrpro
20-Jul-17 8.94 Volts 3.79 Amps C: 1, F: 3 Corrpro
24-Jul-18 9.18 Volts 2.53 Amps C: 1, F: 3 Corrpro
20-Nov-19 9.34 Volts 1.94 Amps C: 1, F: 3 Corrpro
10-Nov-20 9.33 Volts 2.15 Amps C: 1, F: 3 Corrpro
3-Nov-21 9.27 Volts 2.40 Amps C: 1, F: 3 Corrpro
25-Oct-22 9.33 Volts 2.37 Amps C: 1, F: 3 Corrpro
As Found/As Left - Annual Survey 2018
11.8 VAC
AS LEFT CONDITIONS
RECTIFIER ACCURACY CHECK ANODE CURRENT OUTPUT
Main Shunt Rating
Labeled Tank No. 2 inside Junction Box
AS FOUND CONDITIONS
AST 36 ft tall MMO wire type arranged in loops under tank floor and above dieletric liner.
AC Input (set at 115 Volts)
TANK INFORMATION (AST 5660 and AST 5661 same construction information)ANODE GROUNDBED INFORMATION
AC Disconnect & Breaker Location:Left Side of Rectifier
10/24/2022 and 10/25/2022R-1 English Village
AST 5660 and AST 5661 MB/AR
AS LEFT - TANK-TO-SOIL POTENTIALS
RECTIFIER ACCURACY CHECK ANODE CURRENT OUTPUT (Holloway RS Shunt 0.01 Ohm)
Main Shunt Rating
25 ft Three anode circuits with loops arranged in 4 circles.
125,000 gal Diesel
Fluke 287 SN: 19510008
33 F, Cloudy
RECTIFIER RATINGS AND MANUFACTURER'S INFORMATION
3. RMU is functioning as designed. RMU software was upgarded to 4.10.2 which is the latest version.
Notes
As Found/As Left - Annual Survey 2012
As Found/As Left - Annual Survey 2013
As Found/As Left - Annual Survey 2014
As Found/As Left - Annual Survey 2016
As Found/As Left - Annual Survey 2019
1. "C" represents CuCu-SO4 stationary reference cells.
Notes
2. Rectifier was turned off at 10 AM on 10/24/2022. Depolarized potentials measured at 10:35 AM on 10/25/2022 after about 24 hours of depolarization.
As Found/As Left - Annual Survey 2021
As Found/As Left - Annual Survey 2020
As Found/As Left - Annual Survey 2017
As Found/As Left - Annual Survey 2022
1955 MMO 0.118" diameter on a AWG#10 wire loop
AC Input (set at 115 Volts)
11.8 VAC
HISTORICAL OUTPUT
Notes
Labeled Tank No. 1 inside Junction Box
A-2
Ditto - AST 4056 and AST 4057
Appendix A
Rectifier ID:Date Tested:
Target Structure:Tested By:
Rectifier Location:Center of Fenced Fuel Area Test Meter Info:
Weather Info:
Manufacturer:Corrpower Model:EHASE 40-42 Date Installed:2018 Total Steps:
Input AC Volt:115/230 AC Current:23.47/11.74 Serial No:18-678095 C: A-E / F: 1-5
Output DC Volt:40 Volts Output DC Current:42 Amp Input AC Phase:Single AC Set On:
RMU model:Watchdog SCOUT RMU Serial No:56221-0016 RMU Location:Left Side of Rectifier 115 Volts
Type:Type:
Year Built:Anode Mtrl.:
Diameter:No. of Anodes
Tank Contents:Anode Shunts:50 mV 50 Amp
Panel Meter Measured Tap Setting Circuit # Reading (mV)Current (Amp)
Voltage Output (V)7.0 Volts 6.09 Volts C: A / F: 4 A1 2.47 2.47
Current Output (A)30.0 Amps 30.7 Amps A2 3.37 3.37
Shunt Reading (mV)30.7 mV A3 3.41 3.41
A4 2.72 2.72
50 mV / 50 Amps A5 2.53 2.53
A6 4.78 4.78
A7 6.15 6.15
A8 4.92 4.92
Tap AC Voltage:0.001 Ohms Total n/a 30.35
Panel Meter Measured Tap Setting Circuit # Reading (mV)Current (Amp)
Voltage Output (V) 7.0 Volts 6.09 Volts C: A / F: 4 A1 2.47 2.47
Current Output (A) 30.0 Amps 30.7 Amps A2 3.37 3.37
Shunt Reading (mV) 30.7 mV A3 3.41 3.41
A4 2.72 2.72
50 mV / 50 Amps A5 2.53 2.53
A6 4.78 4.78
A7 6.15 6.15
A8 4.92 4.92
Tap AC Voltage:0.001 Ohms Total n/a 30.35
Stationary Cells2 ON (mV) iOFF (mV) Depol (mV) Polarization (mV)
Tank 4056 North -1814 -1059 -433 626
East -1641 -1015 -435 580
South -1405 -818 -356 462
West -1936 -1111 -422 689
Tank 4057 North -2095 -1093 -430 663
East -1675 -1076 -449 627
South -1649 -1053 -447 606
West -1698 -1094 -428 666
Date DC Volt DC Amp Tap Setting Tested By
22-Aug-12 6.00 Volts 12.00 Amps C: 2, F: 1 Corrpro
18-Jun-13 5.80 Volts 12.20 Amps C: 2, F: 1 Corrpro
17-Jun-14 5.80 Volts 12.00 Amps C: 2, F: 1 Corrpro
25-Feb-16 5.60 Volts 11.80 Amps C: 2, F: 1 Corrpro
19-Jul-17 5.60 Volts 10.78 Amps C: 2, F: 1 Corrpro
26-Jul-18 10.03 Volts 27.40 Amps C: B, F: 1 Corrpro
20-Nov-19 13.90 Volts 0.00 Amps C: B, F: 1 Corrpro
12-Nov-20 13.90 Volts 0.00 Amps C: B, F: 1 Corrpro
3-Nov-21 13.90 Volts 0.00 Amps C: B, F: 1 Corrpro
22-Jun-22 5.89 Volts 29.20 Amps C: A, F: 4 Corrpro
25-Oct-22 6.09 Volts 30.70 Amps C: A, F: 4 Corrpro As Found/As Left - Annual Survey 2022
AS LEFT - TANK-TO-SOIL POTENTIALS
Notes
HISTORICAL OUTPUT
Notes
As Found/As Left - Annual Survey 2012
As Found/As Left - Annual Survey 2013
As Found/As Left - Annual Survey 2014
As Found/As Left - Annual Survey 2016
As Found/As Left - Annual Survey 2017
As Left - New Rectifier Unit Installed in Annual Survey
2018
As Found/As Left - Annual Survey 2019
Notes
As Left - New Anode Groundbed Installed Jun 2022
3. RMU is functioning as designed. RMU software was upgarded to 4.10.2 which is the latest version.
As Found/As Left - Annual Survey 2020
As Found/As Left - Annual Survey 2021
2. Rectifier was turned off at 10:55 AM on 10/24/2022. Depolarized potentials measured at 11:10 AM on 10/25/2022 after about 24 hours of depolarization.
AS LEFT CONDITIONS
RECTIFIER ACCURACY CHECK ANODE CURRENT OUTPUT
13.3 VAC
AC Input (set at 115 Volts)
Main Shunt Rating
Anode Shunts
1. CuCu-SO4 stationary reference cells at CPTS inside the containment area.
AS FOUND CONDITIONS
RECTIFIER ACCURACY CHECK1 ANODE CURRENT OUTPUT
13.3 VAC
AC Input (set at 115 Volts)
Main Shunt Rating
Anode Shunts
AC Disconnect & Breaker Location:Left Side of Rectifier
TANK INFORMATION (AST 4056 and AST 4057 same construction)ANODE GROUNDBED INFORMATION
AST Distributed Vertical Anode Groundbed (Installed June 2022)
70Lb 2.7"*84" HSCI anode
14 ft Eight 12-ft deep holes, each contains one anode
25,000 gal JET A
R-2 DITTO 10/24/2022 and 10/25/2022
AST 4056 and AST 4057 MB/AR
Fluke 287 SN: 19510008
33 F, Cloudy
RECTIFIER RATINGS AND MANUFACTURER'S INFORMATION
A-3
English Village - MOGAS UST
Appendix A
Tank Name:Date Tested:Tested By: MB/AR
ID #:
Nominal Capacity:
Contents:
Manufacturer:
Year Installed:
Tank Type: UST
Portable Reference Cell Location ON (mV) Instant OFF (mV) Depol (mV) Polarization (mv)
North -1399 -1146 N/A N/A
South -1407 -1167 N/A N/A
East -1363 -1170 N/A N/A
CPTS -1407 -1167 N/A N/A
Remote @ 100' at the South East -1407 -1195 N/A N/A
Coupon4 -1398 -1186 N/A N/A
Anode OCP (mV) Current (mA)
-1732
-1757
-1731
-1706
3.60
5. The common cell testing indicated the tank was electrically isolated from the grounding and foreign structures.
3. The Coupon was depolarized for 15 minutes.
2. All measured data is in reference to a portable Copper/Copper Sulfate reference electrode.
4. The grounding potential was -480 mV.
1. Four (4) supplemental 32 lb. Magnesium anodes were installed on the MOGAS UST on 7/25/2018.
Notes
5469 Tank 1
20,000 Gallons
MOGAS
UST POTENTIAL SURVEY
Single Wall / Double Wall:
TANK CONSTRUCTION FEATURES
Unknown
1988
Double Walled Steel
NOTES
GALVANIC ANODE INFORMATION
Anode #3
Anode #4
Total
MOGAS UST 10/24/2022
Notes
Red Cott Shunt: 0.1Ω
Shunt reading = 0.360 mV; or 3.60 mA
Anode ID#
Anode #1
Anode #2
A-4
English Village - Diesel UST
Appendix A
Tank Name:Date Tested:Tested By: MB/AR
ID #:
Nominal Capacity:
Contents:
Manufacturer:
Year Installed:
Tank Type: UST
Portable Reference Cell Location ON (mV) Instant OFF (mV) Depol (mV) Polarization (mv)
North -1275 -1077 N/A N/A
South -1285 -1061 N/A N/A
West -1320 -1068 N/A N/A
CPTS -1304 -1051 N/A N/A
Remote @ 120' at the South East -1317 -1095 N/A N/A
Anode OCP (mV) Current (mA)
-1613
-1645
-1632
2.2Total
NOTES
1. The structure lead (White) was verified with common cell testing in 11-03-2021.
2. All measured data is in reference to a portable Copper/Copper Sulfate reference electrode.
3. One of the anode wire (Black) was found depleted and left disconnected.
4. The ground system potential was -480 mV and the Tank was isolated from the grounding system.
Anode #2 (Black)Shunt Reading = 0.022 mV; 2.2 mA
Anode #3 (White)
MOGAS UST 10/24/2022
Anode #1 (Black)RS Shunt, Shunt resistance = 0.01 Ω
1999
Single Wall / Double Wall: Double Walled Steel
UST POTENTIAL SURVEY
Notes
GALVANIC ANODE INFORMATION
Anode ID#Notes
Unknown
5469 Tank-2
10,000 Gallons
Diesel
TANK CONSTRUCTION FEATURES
A-5
B-1
APPENDIX B
CP DRAWINGS
B-2
B-3
N
B-4
CATHODIC PROTECTION SYSTEM AT DITTO BULK FUEL AREA
TANKS 4056 & 4057
DUGWAY PROVING GROUND
UTAH
DUG 21-CP
REV DRAWING NUMBER DESCRIPTION
U53-B222086-C-001 COVER PAGE
U53-B222086-C-002 SITE PLAN
U53-B222086-C-003 TYPICAL DETAILS
U53-B222086-C-004 ICCP WIRING DIAGRAM
G:
\
R
E
G
I
O
N
A
L
\
D
R
A
W
I
N
G
S
\
2
0
2
2
D
R
A
W
I
N
G
S
\
3
4
0
5
3
2
0
8
6
-
D
U
G
W
A
Y
\
A
S
-
B
U
I
L
T
\
U
5
3
-
B
2
2
2
0
8
6
-
C
-
0
0
1
_
0
0
5
.
D
W
G
CA
D
F
I
L
E
-
D
O
N
O
T
M
A
K
E
M
A
N
U
A
L
R
E
V
I
S
I
O
N
S
SHEET INDEX
APPROVED BY:
DATE:
SAFETY NOTES: CORRPRO COMPANIES, INC. DOES NOT ASSUME ANY LIABILITY FOR THE PROTECTION OR SAFETY OF ANY PERSON OR PROPERTY. CONTRACTOR SHALL BE
RESPONSIBLE FOR COMPLIANCE WITH ALL APPLICABLE LAWS (FEDERAL, STATE AND LOCAL), STATUTES, ORDINANCES, CODES, RULES AND REGULATIONS OF ALL AUTHORITIES
HAVING JURISDICTION AND ANY REQUIREMENTS IMPOSED BY THE PROPERTY OWNER(S). THE FOLLOWING SAFETY NOTES ARE FOR INFORMATIONAL PURPOSES ONLY.
1.PIPELINES AND APPURTENANCES CONSTRUCTED IN THE VICINITY OF OVERHEAD POWER LINES CAN EXPERIENCE UNSAFE ELECTRICAL VOLTAGES AND POTENTIALLY
LETHAL SHOCK HAZARDS WHILE THIS EQUIPMENT IS BEING HANDLED ABOVEGROUND AND UPON PLACEMENT IN THE PIPE TRENCH. CONTRACTOR IS RESPONSIBLE FOR ALL
PERSONNEL AND EQUIPMENT SAFETY DURING THE COURSE OF CONSTRUCTION INCLUDING BUT NOT LIMITED TO AWARENESS TRAINING, ALL SAFETY PRECAUTIONS AND
INTERIM ELECTRICAL GROUNDING.
2.CONTRACTOR SHALL ENSURE ALL INDIVIDUALS PERFORMING THE TASK OF THERMITE WELDING OR PIN BRAZING ARE PROPERLY TRAINED. THERMITE WELDING AND PIN
BRAZING ACTIVITIES REQUIRE FIRE EXTINGUISHERS ON-SITE, SAFETY GLASSES, GLOVES AND FIRE RESISTANT CLOTHING TO BE WORN AND LAYERED TO ELIMINATE SLAG
FROM ENTERING AN INDIVIDUAL'S SLEEVE AND GLOVE. HEARING PROTECTING REQUIRED.
3.FACE SHIELD AND GLOVE REQUIRED FOR GRINDING.
SAFETY ALERT: THIS DOCUMENT DOES NOT REFLECT ACTUAL SITE OR SUBSURFACE CONDITIONS AND SHALL NOT BE RELIED UPON FOR THE LOCATION OF ANY UTILITIES,
CURRENTS, HAZARDS OR OTHER CONDITIONS WHERE THE WORK IS TO BE PERFORMED. UNDERGROUND STRUCTURES AND UTILITIES MAY BE PRESENT WHICH ARE NOT
DOCUMENTED OR LOCATED. THIS DOCUMENT IS FURTHER SUBJECT TO ALL SAFETY NOTES SET FORTH HEREIN.
NOTICE: THIS DOCUMENT IS PRELIMINARY, PREPARED FOR A LIMITED PURPOSE, IN RELIANCE UPON INFORMATION PROVIDED BY OTHERS, AND INTENDED FOR SPECIFIC
APPLICATION UNDER CERTAIN CONDITIONS. THIS DOCUMENT, AND ANY DESIGNS OR DETAILS, ARE THE PROPERTY OF CORRPRO COMPANIES, INC. AND SHALL NOT BE COPIED,
REPRODUCED, TRANSMITTED, MODIFIED, RELIED UPON OR USED FOR ANY PURPOSE WITHOUT THE PRIOR EXPRESS WRITTEN PERMISSION OF CORRPRO. CORRPRO DOES NOT
WARRANT THE ACCURACY OF INFORMATION DEPICTED AND ASSUMES NO LIABILITY FOR ANY UNAUTHORIZED COPY, REPRODUCTION, TRANSMITTAL, MODIFICATION, RELIANCE
OR USE HEREOF. ANY USE REQUIRES AN INDEPENDENT DETERMINATION BY A QUALIFIED DESIGN PROFESSIONAL OF THE ACCURACY AND SUITABILITY OF ANY DATA, DESIGN,
DETAIL OR INFORMATION TO THE APPLICATION AND CONDITIONS. FAILURE TO COMPLY MAY RESULT IN PROPERTY DAMAGE OR PERSONAL INJURY FOR WHICH CORRPRO SHALL
HAVE NO LIABILITY. ELECTRONIC TRANSMISSION MAY RESULT IN ERRORS FOR WHICH CORRPRO ASSUMES NO LIABILITY.
DATE ISSUED:
REV.DRAWING NO.
CLIENT PROJECT NUMBER
CORRPRO PROJECT NUMBER
AS-BUILT
2022.07.22
340532086 0U53B222086C001
N
VICINITY MAP
SCALE: NTS
WORK PERFORMED:
1.INSTALLED NEW ANODE JUNCTION BOX.
2.INSTALLED NEW ANODE GROUND BED WITH EIGHT HIGH SILICON CAST IRON (HSCI)
ANODES. ROUTED ANODE LEAD WIRES IN A TRENCH TO ANODE JUNCTION BOX.
PROJECT
LOCATION
N
LOCATION MAP
SCALE: NTS
SALT LAKE CITY
UTAH
DUGWAY
2022.07.22
DEREK MAWHINNEY
B-5
PROJECT NO.SCALE
G:
\
R
E
G
I
O
N
A
L
\
D
R
A
W
I
N
G
S
\
2
0
2
2
D
R
A
W
I
N
G
S
\
3
4
0
5
3
2
0
8
6
-
D
U
G
W
A
Y
\
A
S
-
B
U
I
L
T
\
U
5
3
-
B
2
2
2
0
8
6
-
C
-
0
0
1
_
0
0
5
.
D
W
G
DESIGNED BY
APPROVED BY
CHECKED BY
DRAWN BY
CLIENT DRAWING NO.
REV.
SHEET NO.DRAWING NO.
TITLE
CLIENT
OF
CA
D
F
I
L
E
-
D
O
N
O
T
M
A
K
E
M
A
N
U
A
L
R
E
V
I
S
I
O
N
S
NOTICE: THIS DOCUMENT IS PRELIMINARY, PREPARED FOR A LIMITED PURPOSE, IN RELIANCE
UPON INFORMATION PROVIDED BY OTHERS, AND INTENDED FOR SPECIFIC APPLICATION
UNDER CERTAIN CONDITIONS. THIS DOCUMENT, AND ANY DESIGNS OR DETAILS, ARE THE
PROPERTY OF CORRPRO COMPANIES, INC. AND SHALL NOT BE COPIED, REPRODUCED,
TRANSMITTED, MODIFIED, RELIED UPON OR USED FOR ANY PURPOSE WITHOUT THE PRIOR
EXPRESS WRITTEN PERMISSION OF CORRPRO. CORRPRO DOES NOT WARRANT THE
ACCURACY OF INFORMATION DEPICTED AND ASSUMES NO LIABILITY FOR ANY UNAUTHORIZED
COPY, REPRODUCTION, TRANSMITTAL, MODIFICATION, RELIANCE OR USE HEREOF. ANY USE
REQUIRES AN INDEPENDENT DETERMINATION BY A QUALIFIED DESIGN PROFESSIONAL OF
THE ACCURACY AND SUITABILITY OF ANY DATA, DESIGN, DETAIL OR INFORMATION TO THE
APPLICATION AND CONDITIONS. FAILURE TO COMPLY MAY RESULT IN PROPERTY DAMAGE OR
PERSONAL INJURY FOR WHICH CORRPRO SHALL HAVE NO LIABILITY. ELECTRONIC
TRANSMISSION MAY RESULT IN ERRORS FOR WHICH CORRPRO ASSUMES NO LIABILITY.
SAFETY ALERT: THIS DOCUMENT DOES NOT REFLECT ACTUAL SITE OR SUBSURFACE
CONDITIONS AND SHALL NOT BE RELIED UPON FOR THE LOCATION OF ANY UTILITIES,
CURRENTS, HAZARDS OR OTHER CONDITIONS WHERE THE WORK IS TO BE
PERFORMED. UNDERGROUND STRUCTURES AND UTILITIES MAY BE PRESENT WHICH
ARE NOT DOCUMENTED OR LOCATED. THIS DOCUMENT IS FURTHER SUBJECT TO ALL
SAFETY NOTES SET FORTH HEREIN.
DRAFT DATE
(YYYY.MM.DD)
DUGWAY PROVING GROUND
DUGWAY, UTAH
DUG 21-CP
CATHODIC PROTECTION SYSTEM DESIGN
SITE PLAN
002 004 0U53B222086C002
CATHODIC PROTECTION SITE PLAN
SCALE: NTS
N
TANK 4056 TANK 4057
PUMPHOUSE
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XXXXXXXXXXXXXXX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X X X X X X X X X X X X X X X
NEGATIVE CABLE FROM
PIPE TO RECTIFIER
10'
30'
14'
15'
15'14'14'14'15'
15'
14'
A1A8
ANODE JUNCTION BOX
SEE PHOTOGRAPH
5/003
RECTIFIER
SEE PHOTOGRAPH
4/003
AC
AC BREAKER
EXISTING FINK
TEST STATION (TYP)
PHOTOGRAPH
TANK 4057
TANK 4056
5'
BONDING CABLE
BETWEEN PIPES
HSCI ANODE 70 lb.
(TYPICAL OF 8)SEE
DETAIL 1/003
2022.07.08 ROBIN M.
YASH M.MAHSA B.
DEREK M.
340532086 AS NOTED
B-6
PROJECT NO.SCALE
G:
\
R
E
G
I
O
N
A
L
\
D
R
A
W
I
N
G
S
\
2
0
2
2
D
R
A
W
I
N
G
S
\
3
4
0
5
3
2
0
8
6
-
D
U
G
W
A
Y
\
A
S
-
B
U
I
L
T
\
U
5
3
-
B
2
2
2
0
8
6
-
C
-
0
0
1
_
0
0
5
.
D
W
G
DESIGNED BY
APPROVED BY
CHECKED BY
DRAWN BY
CLIENT DRAWING NO.
REV.
SHEET NO.DRAWING NO.
TITLE
CLIENT
OF
CA
D
F
I
L
E
-
D
O
N
O
T
M
A
K
E
M
A
N
U
A
L
R
E
V
I
S
I
O
N
S
NOTICE: THIS DOCUMENT IS PRELIMINARY, PREPARED FOR A LIMITED PURPOSE, IN RELIANCE
UPON INFORMATION PROVIDED BY OTHERS, AND INTENDED FOR SPECIFIC APPLICATION
UNDER CERTAIN CONDITIONS. THIS DOCUMENT, AND ANY DESIGNS OR DETAILS, ARE THE
PROPERTY OF CORRPRO COMPANIES, INC. AND SHALL NOT BE COPIED, REPRODUCED,
TRANSMITTED, MODIFIED, RELIED UPON OR USED FOR ANY PURPOSE WITHOUT THE PRIOR
EXPRESS WRITTEN PERMISSION OF CORRPRO. CORRPRO DOES NOT WARRANT THE
ACCURACY OF INFORMATION DEPICTED AND ASSUMES NO LIABILITY FOR ANY UNAUTHORIZED
COPY, REPRODUCTION, TRANSMITTAL, MODIFICATION, RELIANCE OR USE HEREOF. ANY USE
REQUIRES AN INDEPENDENT DETERMINATION BY A QUALIFIED DESIGN PROFESSIONAL OF
THE ACCURACY AND SUITABILITY OF ANY DATA, DESIGN, DETAIL OR INFORMATION TO THE
APPLICATION AND CONDITIONS. FAILURE TO COMPLY MAY RESULT IN PROPERTY DAMAGE OR
PERSONAL INJURY FOR WHICH CORRPRO SHALL HAVE NO LIABILITY. ELECTRONIC
TRANSMISSION MAY RESULT IN ERRORS FOR WHICH CORRPRO ASSUMES NO LIABILITY.
SAFETY ALERT: THIS DOCUMENT DOES NOT REFLECT ACTUAL SITE OR SUBSURFACE
CONDITIONS AND SHALL NOT BE RELIED UPON FOR THE LOCATION OF ANY UTILITIES,
CURRENTS, HAZARDS OR OTHER CONDITIONS WHERE THE WORK IS TO BE
PERFORMED. UNDERGROUND STRUCTURES AND UTILITIES MAY BE PRESENT WHICH
ARE NOT DOCUMENTED OR LOCATED. THIS DOCUMENT IS FURTHER SUBJECT TO ALL
SAFETY NOTES SET FORTH HEREIN.
DRAFT DATE
(YYYY.MM.DD)
DUGWAY PROVING GROUND
DUGWAY, UTAH
DUG 21-CP
CATHODIC PROTECTION SYSTEM DESIGN
TYPICAL DETAILS
003 004 0U53B222086C003
1
003
HSCI ANODE GROUND BED INSTALLATION
SCALE: NTS
2
003 SCALE: NTS
18"
12"
12'
12"Ø HYDRO VAC
EXCAVATED HOLE
FINISHED GRADE
WARNING TAPE
FINE GRANULAR
BACKFILL
2.7"Ø x 7' HSCI TUBE ASSEMBLY
SEE DETAIL 2/003
#8 AWG STRD COPPER ANODE
LEAD WIRES WITH HMWPE
INSULATION RUN TO JUNCTION BOX
WITHOUT SPLICING
7'
SC-3 COKE BREEZE
4
003
AIR-COOLED RECTIFIER
SCALE: NTS
5
003
ANODE JUNCTION BOX
SCALE: NTS
D.C. RATED
40 VOLTS/42 AMPS
84"
2.7"Ø
ANODE LEAD WIRE #8
AWG HMWPE
CABLE GUIDE
CENTRIFUGALLY CAST TUBULAR
CAST IRON ANODE
EPOXY SEAL (4" THICK)
HIGH VOLTAGE INSULATING
COMPOUND MASTIC SEAL
(6" THICK)
END OF HMWPE INSULATION
TWO PIECE LEAD CONNECTOR
HIGH VOLTAGE INSULATING
COMPOUND MASTIC SEAL
(6" THICK)
EPOXY SEAL (4" THICK)
10'
ACTIVE
COLUMN
2'
GRANULAR
BACKFILL
3
003
CONCRETE TRAFFIC BOX
SCALE: NTS
12"
~14"
CAST IRON BOLT DOWN
TRAFFIC RATED, COVER
MARKED "ANODE"
CONCRETE BODY
TRAFFIC RATED
CONCRETE TRAFFIC BOX
SEE DETAIL 3/003
1'
70 LB. HIGH SILICON CAST IRON TUBE ASSEMBLY
2022.07.08 ROBIN M.
YASH M.MAHSA B.
DEREK M.
340532086 AS NOTED
B-7
PROJECT NO.SCALE
G:
\
R
E
G
I
O
N
A
L
\
D
R
A
W
I
N
G
S
\
2
0
2
2
D
R
A
W
I
N
G
S
\
3
4
0
5
3
2
0
8
6
-
D
U
G
W
A
Y
\
A
S
-
B
U
I
L
T
\
U
5
3
-
B
2
2
2
0
8
6
-
C
-
0
0
1
_
0
0
5
.
D
W
G
DESIGNED BY
APPROVED BY
CHECKED BY
DRAWN BY
CLIENT DRAWING NO.
REV.
SHEET NO.DRAWING NO.
TITLE
CLIENT
OF
CA
D
F
I
L
E
-
D
O
N
O
T
M
A
K
E
M
A
N
U
A
L
R
E
V
I
S
I
O
N
S
NOTICE: THIS DOCUMENT IS PRELIMINARY, PREPARED FOR A LIMITED PURPOSE, IN RELIANCE
UPON INFORMATION PROVIDED BY OTHERS, AND INTENDED FOR SPECIFIC APPLICATION
UNDER CERTAIN CONDITIONS. THIS DOCUMENT, AND ANY DESIGNS OR DETAILS, ARE THE
PROPERTY OF CORRPRO COMPANIES, INC. AND SHALL NOT BE COPIED, REPRODUCED,
TRANSMITTED, MODIFIED, RELIED UPON OR USED FOR ANY PURPOSE WITHOUT THE PRIOR
EXPRESS WRITTEN PERMISSION OF CORRPRO. CORRPRO DOES NOT WARRANT THE
ACCURACY OF INFORMATION DEPICTED AND ASSUMES NO LIABILITY FOR ANY UNAUTHORIZED
COPY, REPRODUCTION, TRANSMITTAL, MODIFICATION, RELIANCE OR USE HEREOF. ANY USE
REQUIRES AN INDEPENDENT DETERMINATION BY A QUALIFIED DESIGN PROFESSIONAL OF
THE ACCURACY AND SUITABILITY OF ANY DATA, DESIGN, DETAIL OR INFORMATION TO THE
APPLICATION AND CONDITIONS. FAILURE TO COMPLY MAY RESULT IN PROPERTY DAMAGE OR
PERSONAL INJURY FOR WHICH CORRPRO SHALL HAVE NO LIABILITY. ELECTRONIC
TRANSMISSION MAY RESULT IN ERRORS FOR WHICH CORRPRO ASSUMES NO LIABILITY.
SAFETY ALERT: THIS DOCUMENT DOES NOT REFLECT ACTUAL SITE OR SUBSURFACE
CONDITIONS AND SHALL NOT BE RELIED UPON FOR THE LOCATION OF ANY UTILITIES,
CURRENTS, HAZARDS OR OTHER CONDITIONS WHERE THE WORK IS TO BE
PERFORMED. UNDERGROUND STRUCTURES AND UTILITIES MAY BE PRESENT WHICH
ARE NOT DOCUMENTED OR LOCATED. THIS DOCUMENT IS FURTHER SUBJECT TO ALL
SAFETY NOTES SET FORTH HEREIN.
DRAFT DATE
(YYYY.MM.DD)
DUGWAY PROVING GROUND
DUGWAY, UTAH
DUG 21-CP
CATHODIC PROTECTION SYSTEM DESIGN
ICCP WIRING SCHEMATIC
004 004 0U53B222086C005
AC POWER
CIRCUIT BREAKER
120 VAC
SINGLE PHASE
RECTIFIER
AC INPUT
MAX. OUTPUT
RATING
40 VOLTS DC
42 AMP DC
S/N: 18-678095
DC (+)DC (-)
TO TANKS 4056 & 4057
AWG #8 (BLK)
A1 A2
ANODE GROUND BED
(1) AWG #8 (RED)(1) AWG #8 (BLACK)
ANODE JUNCTION BOX
BUS BAR (TYP)
A3 A4 A5 A6 A7 A8
A1 A2 A3 A4 A5 A6 A7 A8
ANODE LEAD # 8 HMWPE WIRES
2022.07.08 ROBIN M.
YASH M.MAHSA.B
DEREK M.
340532086 AS NOTED
B-8