HomeMy WebLinkAboutDERR-2024-013263Site Visit Report- Redwood Road Dump VCP #121 Date(s): 10/19/2023 Project Manager: Chris Howell. Purpose of Site Visit: Impacted Soil Excavation Oversight Observations: DERR arrived on-site and met with Sarah from Terracon. Reynolds Excavating is the contractor on site. Terracon over excavating two locations TP-40 and TP-37 based on lab results. TP-37 sidewall also failed to the south heading under the asphalt pad. DERR agreed with Terracon that the asphalt pad needs to stay to facilitate other parts of the RAP and the remaining impacted material will be removed when the asphalt pad is removed and sampled. Samples will be submitted for a rush TAT to Pace.