HomeMy WebLinkAboutDERR-2024-013263Site Visit Report- Redwood Road Dump VCP #121
Date(s): 10/19/2023
Project Manager: Chris Howell.
Purpose of Site Visit: Impacted Soil Excavation Oversight
Observations:
DERR arrived on-site and met with Sarah from Terracon. Reynolds Excavating is the contractor
on site.
Terracon over excavating two locations TP-40 and TP-37 based on lab results. TP-37 sidewall
also failed to the south heading under the asphalt pad. DERR agreed with Terracon that the
asphalt pad needs to stay to facilitate other parts of the RAP and the remaining impacted
material will be removed when the asphalt pad is removed and sampled.
Samples will be submitted for a rush TAT to Pace.