HomeMy WebLinkAboutDERR-2024-013260Site Visit Report- Redwood Road Dump VCP #121
Date(s): 2/1/2024
Project Manager: Chris Howell. Allison Stanley is also on site.
Purpose of Site Visit: RAP Oversight
Observations:
DERR arrived on-site and met the SL Excavating foreman. Terracon is not on site today.
Impacted soil is being shipped to the SL County landfill. The last of the piles is pushed up next
to the asphalt pad. Removal is almost complete no estimated completion date given. Clean fill
that is stockpiled next to the site is being placed on the south end and compacted in lifts. The
idea is to push pockets of water on the surface to the north. Terracon is working with DWQ on
permitting to manage the water.
Through communication with Catherine Terracon will be doing some work next week to assist
with the water permitting.
No issues were identified during the site visit.