HomeMy WebLinkAboutDERR-2024-013255Site Visit Report- Redwood Road Dump VCP #121
Date(s): 5/14/2024
Project Manager: Chris Howell
Purpose of Site Visit: RAP Oversight/ NOI Permit inspection
Observations:
DERR arrived on-site JD Bush contractor was on the site installing utilities and managing
dewatering. I was told they coordinate with Terracon almost daily on progress. EK Bailey is on-
site crushing and processing imported fill to meet site Geotech requirements. The backfill
contractor SL Excavating was not on site. The frac tank is set up on the south end of the site
next to the stormwater discharge point on Indiana Ave. Culinary water lines are run from the
west of the driveway to the tank to mix with the pumped water to meet permit requirements. No
odors or sheen were noted at the discharge point. The majority of the standing water has been
removed and discharge is intermittent as needed when the pumps turn on.
No issues were identified during the site visit.