Loading...
HomeMy WebLinkAboutDERR-2024-007880SOUTHWEST JORDAN VALLEY GROUNDWATER PROJECT TENTATIVE CALENDAR (as of October 12, 2005) October-December, 2005 - Zone A’s R.O. Plant Startup and Operational Testing begins. - Kennecott submits drinking water system permit request to DEQ in October '05. - Drinking water system permit approval anticipated by end of quarter, pending completion of public comment period and approval by Drinking Water Board. January-March, 2006 - Zone A R.O. Plant Startup and Operational Testing concludes at end of January. - Municipal quality drinking water (per Three-Party Agreement) begins to be provided. - Deep well drilling contract awarded by District. July-September, 2006 - District to award feed water pipelines contract. January-March, 2007 - District to award treatment plant contract. July-September, 2007 - District to make decision on integrated (discharge to open waters of the Great Salt Lake) vs. separate (continue discharge to Kennecott tailings impoundment) design by September. - District to award by-product disposal system contract. October-December, 2007 - District to award deep well equipping contract. January-March, 2009 - Zone B’s R.O. Treatment Plant begins start-up phase.