HomeMy WebLinkAboutDERR-2024-013085VCP/Brownfields Section - Site Visit Report SITE NAME: Airport West / North Temple Landfill SITE LOCATION: Salt Lake City DATE OF SITE VISIT: 20 December 2024 PURPOSE OF SITE VISIT: DERR (David Bird) oversight of field activities at the Airport West VCP site. FIELD OBSERVATIONS: At ~ 9 am, the DERR met SITLA’s contractor, NT Development (Eric Rice), Wasatch Environmental’s Certified Asbestos Inspector (Paige Williams), and concrete crushing subcontractor, Staker Parsons (Clint) at the site, to discuss how the inspection for possible asbestos containing material (ACM), and processing of concrete into roadbase material is progressing. There was a pile of processed material already about 30 feet high on site. NT Development indicated that the permit with DAQ is now in place, but is undergoing some minor revisions to reflect agreed upon field changes. NT Development will forward a copy of it to me. We discussed with the certified ACM inspector how the concrete, placed in windrows approximately 18 to 24 inches in height are being inspected for potential ACM, with a final inspection of the resulting stockpile before it is loaded into the crusher. I was told the actual crushing of concrete started two days ago (18 DEC), and that no ACM had been identified in that time frame. We discussed the requirements for dust control at the site. The expected timeframe for the crushing of the concrete is 3 to 4 months. The DERR left the site at ~10:00 am. SPLIT SAMPLES COLLECTED: No IS THE WORK BEING PERFORMED IN A MANNER CONSISTENT WITH THE ACCEPTED WORKPLAN? Yes Looking toward the east at the pile of processed concrete to be used as roadbase material. Looking southeast at the stockpile of concrete material (foreground) being fed into the crusher (backround).