HomeMy WebLinkAboutDDW-2024-014668
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144830 • Salt Lake City, UT 84114-4830
Telephone (801) 536-4200 • Fax (801-536-4211 • T.D.D. (801) 903-3978
www.deq.utah.gov
Printed on 100% recycled paper
State of Utah
SPENCER J. COX
Governor
DEIDRE HENDERSON
Lieutenant Governor
Department of
Environmental Quality
Kimberly D. Shelley
Executive Director
DIVISION OF DRINKING WATER
Tim Davis
Director
March 1, 2023
Trevor Clegg
Kamas City Water System
170 North Main
Kamas, Utah 84036
Subject: Plan Approval, Left Hand Fork Spring Transmission Line and Kamas Fish Hatchery
Water Line Replacement Project; Kamas City Water System, System #22007, File
#13267
Dear Trevor Clegg:
The Division of Drinking Water (the Division) received the plans and specifications for the Left
Hand Fork Spring Transmission Line and Kamas Fish Hatchery Water Line Replacement project
from your consultant, Robert Worley, P.E. with Sunrise Engineering, Inc. on February 8, 2023.
Additional information was requested and received on February 22, 2023. This project has met the
conditions for receiving a plan approval.
Our understanding of the project is the replacement of the Left Hand Fork Spring transmission
line from the spring box to the splitter box and the water line from the splitter box that diverts the
water to the Kamas Fish Hatchery connection. In addition, new flow meters and air vents will be
added to the splitter box junction. The transmission line from the spring box to the splitter box
will be increased in size from a 10-inch to 16-inch diameter HDPE pipe and the line going to the
Kamas Fish Hatchery will be replaced with a 12-inch diameter HDPE DR17 pipe.
We have completed our review of the plans and specifications, stamped and signed by Robert
Worley, P.E., dated February 3, 2023, and find they basically comply with the applicable portions
of Utah’s Administrative Rules for Public Drinking Water Systems in R309. On this basis, the
plans for the Left Hand Fork Spring Transmission Line and Kamas Fish Hatchery Water
Line Replacement project are hereby approved.
Trevor Clegg
Page 2 of 2
March 1, 2023
This approval pertains to construction only. An Operating Permit must be obtained from the
Director before the water lines may be put in service. A checklist outlining the items required
for operating permit issuance is enclosed for your information.
Approvals or permits from the local authority or the county may be necessary before beginning
construction of this project. As the project proceeds, a notice of any changes in the approved
design, as well as any change affecting the quantity or quality of the delivered water, must be
submitted to the Division. We may also conduct interim and final inspections of this project.
Please notify us when actual construction begins so that these inspections can be scheduled.
This approval must be renewed if construction has not begun or if substantial equipment has not
been ordered within one year of the date of this letter.
If you have any questions regarding this approval, please contact Julie Cobleigh, of this office, at
(385) 214-9770, or me at (385) 515-1464.
Sincerely,
Michael Newberry, P.E.
Engineering Manager
JJC/mrn/mdb
Enclosures – Operating Permit Checklist
cc: Nathan Brooks, Summit County Health Department, nbrooks@summitcounty.org
John Keyser, Sunrise Engineering, jkeyser@sunrise-eng.com
Trevor Clegg, Kamas City, tclegg@kamascityut.gov
Julie Cobleigh, Division of Drinking Water, jjcobleigh@utah.gov
DDW-2023-002801
Utah Division of Drinking Water ― Checklist for Issuing Operating Permits
Water System Name: System Number:
Project Description: File Number:
Items 1 through 8 below must be submitted to the Division and found to be acceptable prior to
operating permit issuance (unless a water line project meets the requirements of R309-500-7 and
is not required to obtain an Operating Permit).
Distribution lines (not including in-line booster pump stations) requiring Plan Approval may be
placed into service prior to submitting all of the following items and receipt of Operating Permit
if the water system has received items 1 and 4 below.
☐ 1. Certification of Rule Conformance by a professional engineer (P.E.) that all conditions of
Plan Approval were accomplished, and if applicable, changes made during construction
were in conformance with rules R309-500 through 550
☐ 2. As-built or record drawings incorporating all changes to approved plans and
specifications (unless no changes were made to the previously approved plans during
construction)
☐ 3. Confirmation that as-built or record drawings have been received by the water system
☐ 4. Satisfactory bacteriological samples as evidence of proper disinfection and flushing in
accordance with the appropriate ANSI/AWWA standards:
☐ ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water Mains
Two consecutive sample sets at least 16 hours apart, none positive (e.g., every
1,200 feet, end-of-line, each branch)
☐ ANSI/AWWA C652-11 AWWA Standard for Disinfection of Water-Storage Facilities
One or more samples, none positive
☐ ANSI/AWWA C653-13 AWWA Standard for Disinfection of Water Treatment
Plants
Two consecutive samples per unit, none positive, no less than 30 minutes apart
☐ ANSI/AWWA C654-13 AWWA Standard for Disinfection of Wells
Two consecutive samples, none positive, no less than 30 minutes apart
☐ 5. Water quality data, where appropriate [For example, include raw and finished water data that
demonstrate satisfactory performance of the treatment facility; sample should be taken from a
storage tank for residual volatile organic compounds after tank interior re-coating; etc.]
☐ 6. If applicable, all other documentation that may have been required during the plan review
process
☐ 7. If applicable, confirmation that the water system owner has received the O&M manual
for the new facility
☐ 8. If applicable, location data of new storage tank, treatment facility, or source