March 13, 2024
Kendra Davis
Sun Outdoors-Canyonland Gateway
27777 Franklin Road
Suite 200
Southfield, Michigan 48034
Subject:Plan Approval, Cistern Tank (ST003) and Pump House (PF002);
Sun Outdoors, System #10034, File #13602
Dear Kendra Davis:The Division of Drinking Water (the Division) received the plans and specifications for the proposed Cistern Tank and Pump House Project from your consultant, Bill
Anderson, P.E. on January 13, 2024. The Division received the revised plans and specifications on February 7, 2024, and February 26, 2024. This project has met the conditions for receiving
a plan approval.
Our understanding of the project is the construction of a new 25,000-gallon buried concrete water tank (ST003) with a new pump house (PF002) constructed on top of the tank that will
provide pressure to the distribution system. These facilities will replace the existing above-ground water tanks (ST001 and ST002) and the existing pump station (PF001).
We have completed our review of the plans and specifications, stamped, and signed byBill Anderson, P.E., dated February 26, 2024, and find they basically comply with the applicable portions
of Utah’s Administrative Rules for Public Drinking Water Systems in R309. On this basis, the plans for the Cistern Tank and Pump House Project are hereby approved.
This approval pertains to construction only. An Operating Permit must be obtained from the Director before the Cistern Tank and Pump House Project may be put into service. A checklist
outlining the items required for operating permit issuance is enclosed for your information.Approvals or permits from the local authority or the county may be necessary before beginning
construction of this project. As the project proceeds, notice of any changes in the approved design, as well as any change affecting the quantity or quality of the delivered water, must
be submitted to the Division. We may also conduct interim and final inspections of this project. Please notify us when actual construction begins so that these inspections can be scheduled.
This approval must be renewed if construction has not begun or if substantial equipment has not been ordered within one year of the date of this letter.
If you have any questions regarding this approval, please contact Russell Seeley, of this office, at (435) 650-8519, or me at (385) 515-1464.
Sincerely,
Michael Newberry, P.E.
Permitting and Engineering Support Manager
RLS/mrn/mdbEnclosures –Operating Permit Checklistcc:Orion Rogers,SEU Health Department, orogers@utah.govBill Anderson, Anderson Engineering, bill@andersonmontana.comKendra Davis, Sun
Outdoors, kdavis4@suncommunities.comRussell Seeley, Division of Drinking Water, rseeley@utah.govRseeley 10034 13602 PA Basic
Utah Division of Drinking Water ― Checklist for Issuing Operating PermitsWater System Name:System Number: Project Description:File Number:
Items 1 through 8 below must be submitted to the Division and found to be acceptable prior to operating permit issuance (unless a water line project meets the requirements of R309-500-7
and is not required to obtain an Operating Permit).
Distribution lines (not including in-line booster pump stations) requiring Plan Approval may be placed into service prior to submitting all of the following items and receipt of Operating
Permit if the water system has received items 1 and 4 below.☐1.Certification of Rule Conformance by a professional engineer (P.E.) that all conditions of Plan Approval were accomplished,
and if applicable, changes made during construction were in conformance with rules R309-500 through 550☐2.As-built or record drawings incorporating all changes to approved plans and
specifications (unless no changes were made to the previously approved plans during construction)☐3.Confirmation that as-built or record drawings have been received by the water system☐4.Satisfactory
bacteriological samples as evidence of proper disinfection and flushing in accordance with the appropriate ANSI/AWWA standards:
☐ANSI/AWWA C651-14 AWWA Standard for Disinfecting Water MainsTwo consecutive sample sets at least 16 hours apart, none positive (e.g., every 1,200 feet, end-of-line, each branch)☐ANSI/AWWA
C652-11 AWWA Standard for Disinfection of Water-Storage FacilitiesOne or more samples, none positive☐ANSI/AWWA C653-13 AWWA Standard for Disinfection of Water Treatment PlantsTwo consecutive
samples per unit, none positive, no less than 30 minutes apart☐ANSI/AWWA C654-13 AWWA Standard for Disinfection of WellsTwo consecutive samples, none positive, no less than 30 minutes
apart☐5.Water quality data, where appropriate [For example, include raw and finished water data that demonstrate satisfactory performance of the treatment facility; sample should be
taken from a storage tank for residual volatile organic compounds after tank interior re-coating; etc.]☐6.If applicable, all other documentation that may have been required during the
plan review process☐7.If applicable, confirmation that the water system owner has received the O&M manual for the new facility☐8.If applicable, location data of new storage tank, treatment
facility, or source