HomeMy WebLinkAboutDERR-2024-012489VCP/Brownfields Section - Site Visit Report
SITE NAME: Mayflower Mine
SITE LOCATION: Wasatch County
DATE OF SITE VISIT: 13 November 2024
PURPOSE OF SITE VISIT: DERR (David Bird and Allison Stanley) oversight of Phase 1 remedial action.
FIELD OBSERVATIONS: The DERR visited the Mayflower VCP site at ~1:10 pm on 13 November to
observe conditions at the site. The DERR observed additional asphalt paving which had been laid on the
south end of the Repository, which appeared to complete the asphalt paving needed to meet the
requirements of the design. Concrete was in the process of being finished at the transit station adjacent
to the Mayflower Village Drive near the middle of the Repository cover.
The DERR then proceeded to the western end of the Repository where the asphalt cover was complete
and in good condition. It appeared that concrete had been recently placed at the relocated detention
pond for the spillway structure.
The DERR contacted Extell (Kent Fawcett) before leaving the site. He had not been available when we
arrived. The DERR left the site at ~11:55 am.
SPLIT SAMPLES COLLECTED: N/A
IS THE WORK BEING PERFORMED IN A MANNER CONSISTENT WITH THE ACCEPTED WORKPLAN?
Yes
New asphalt at south end of Repository looking west.
New concrete at transit station near middle of Repository, looking northwest.