HomeMy WebLinkAboutDRC-2011-001510 - 0901a068801fbcb5State of Utah
GARY R. HERBERT
Governor
GREG BELL
Lieutenant Govemor
January 27, 2011
Departmentof DRC- 2011- 00 1
Environmental Quality
Amanda Smith
Executive Director
DIVISION OF RADIATION CONTROL
Rusty Lundberg
Director
Certified Mail
(Retum Receipt Requested)
Mr. Harold R. Roberts
Vice President, US Operations
Denison Mines (USA) Corp (DUSA)
1050 17* Street, Suite 950
Denver, CO 80265
Dear Mr. Roberts:
SUBJECT: January 27, 2011, 4:39 p.m. Email from Geosyntec Consultants, regarding Denison Mines
Cell 4B - CQA Report Addendum; DUSA CeU 4B Construction Quality Assurance [CQA]
Report; Cell 4B CQA Report Approval
Please note the following references:
1. The subject January 27, 2011, 4:39 p.m. Email from Geosyntec Consultants, transmitting a
Geosyntec Consultants response letter of the same date, known to DRC as CQA Report addendum
No. 3 to the subject CQA Report. This letter contains construction work clarifications and is
certified by Mr. Greg T. Corcoran, a Registered Professional Engineer in the state of Utah.
2. January 27, 2011, 2:00 pm. telephone conversation between Messrs. Greg Corcoran of Geosyntec
Consultants and David Rupp of the DRC.
3. January 27, 2011, 12:39 p.m. DRC Email to DUSA conunenting on the subject CQA Report.
4. January 27, 2011, 10:04 a.m. Geosyntec Consultants Email to DRC conveying a Geosyntec
Consultants response LeUer of the same date, known to DRC as CQA Report addendum No. 2.
This information is also certified as reference no. 1 above. ^
5. January 25, 2011 DRC Letter, Request for Information on the subject CQA Report and addendum
No.l.
6. January 21, 2011 Geosyntec Consultants Letter, known to DRC as CQA Report addendum No. 1.
This information is also certified as reference 1 above.
7. January 20, 2011 DRC Letter, Request for Information on the subject CQA Report.
8. November 30, 2011 DUSA Cell 4B CQA Report, prepared by Geosyntec Consultants, Volumes I
through III.
We received and reviewed the subject information noted in references 1, 4, 6, and 8 above. DRC provided
comments and requests for information per items 2, 3, 5, and 7 above. After review ofthe subject Email as
described in reference 1, we have no further comments. Therefore we hereby approve the Cell 4B
Construction Quality Assurance [CQA] Report, including addendums 1 through 3 as described in
references 1, 4, and 6 above.
195 North 1950 West • Salt Lake City, UT
Mailing Address: P.O. Box 144850 • Salt Lake City, UT 84114-4850
Telephone (801) 536-4250 • Fax (801) 533-4097 • T.D.D. (801) 536-4414
www.deq.utah.gov
Printed on 100% recycled paper
Page 2
If you have questions on this approval, please contact Mr. Rupp of my staff
UTAH RADL\TION CONTROL BOARD
Rusty LundbergTExecutive Secretary
DAR:dr
Cc: Harold R. Roberts, V.P. US Operations
Greg Corcoran, GeoSyntec Consultants
F:\C4BConstr\CQA RptApproval 01-201 l.doc